SlideShare uma empresa Scribd logo
1 de 20
Monitor Communications
Monitor Communications
Coincides with PMBOK 10.3
Process Group and Knowledge Area Mapping
Knowledge Areas Initiating Planning Process Group Executing Process Group Monitoring and Controlling Process Group Closing Process Group
4. Project Integration
Management
4.1 Develop Project Charter
4.2 Develop Project Management
Plan
4.3 Direct and Manage Project Work
4.4 Manage Project Knowledge
4.5 Monitor and Control Project Work
4.6 Perform Integrated Change Control
4.7 Close Project or Phase
5. Project Scope
Management
5.1 Plan Scope Management
5.2 Collect Requirements
5.3 Define Scope
5.4 Create WBS
5.5 Validate Scope
5.6 Control Scope
6. Project Schedule
Management
6.1 Plan Schedule Management
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Durations
6.5 Develop Schedule
6.6 Control Schedule
7. Project Cost Management
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
7.4 Control Costs
8. Project Quality
Management
8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality
9. Project Resource
Management
9.1 Plan Resource Management
9.2 Estimate Activity Resources
9.3 Acquire Resources
9.4 Develop Team
9.5 Manage Team
9.6 Control Resources
10. Project Communications
Management
10.1 Plan Communications
Management
10.2 Manage Communications 10.3 Monitor Communications
11. Project Risk
Management
11.1 Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk
Analysis
11.5 Plan Risk Responses
11.6 Implement Risk Responses 11.7 Monitor Risks
12. Project Procurement
Management
12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements
13. Project Stakeholder
Management
13.1 Identify Stakeholders 13.2 Plan Stakeholder Engagement
13.3 Manage Stakeholder
Engagement
13.4 Monitor Stakeholder Engagement
What is it?
Monitor Communications is the process of ensuring the information
needs of the project and its stakeholders are met.
Why?
The key benefit of this process is the optimal information flow as
defined in the communications management plan and the stakeholder
engagement plan.
Monitor Communications
Coincides with PMBOK 10.3
Overview
• Monitor Communications determines if the planned communications artefacts and
activities have had the desired effect of increasing or maintaining stakeholders’
support for the project’s deliverables and expected outcomes.
• Monitor Communications may require a variety of methods, such as customer
satisfaction surveys, collecting lessons learned, observations of the team, reviewing
data from the issue log, or evaluating changes in the stakeholder engagement
assessment matrix.
Coincides with PMBOK 10.3
Monitor Communications
Monitor Communications
Coincides with PMBOK 10.3
Inputs Tools & Techniques Outputs
1. Project management plan
• Resource management plan
• Communications management
plan
• Stakeholder engagement plan
2. Project documents
• Issue log
• Lessons learned register
• Project communications
3. Work performance reports
4. Enterprise environmental factors
5. Organizational process assets
1. Expert judgment
2. Project management
information system
3. Data analysis
• Stakeholder engagement
assessment matrix
4. Interpersonal and team skills
• Observation/conversation
5. Meetings
1. Work performance information
2. Change requests
3. Project management plan
updates
• Communications
management plan
• Stakeholder engagement plan
4. Project documents updates
• Issue log
• Lessons learned register
• Stakeholder register
Inputs, Tools & Techniques, Outputs
Monitor Communications
Coincides with PMBOK 10.3
10.3 Monitor
Communications
Project
Management
Plan
Enterprise/Orga
nization
4.3 Direct and
Manage Project
Work
• Work performance
information
• Issue log
• Lessons learned register
• Project communications
• Enterprise environmental factors
• Organizational process assets
• Resource management plan
• Communications
management plan
• Stakeholder engagement
plan
Project
Documents
• Work Performance Report
Project
Documents
Project
Management
Plan
• Change requests
• Communications
management plan
• Stakeholder
engagement plan
• Issue log
• Lessons learned register
• Project communications
4.6 Perform
Integrated
Change Control
4.5 Monitor
and Control
Project Work
Monitor Communications - Inputs
Coincides with PMBOK 10.3
Project Management Plan
Project Management Plan components include:
• Resource management plan
• Communication management plan
• Stakeholder engagement plan
Monitor Communications - Inputs
Coincides with PMBOK 10.3
Project Documents
Project Documents include:
• Issue log
• Lessons learned register
• Project communications
Monitor Communications - Inputs
Coincides with PMBOK 10.3
Work Performance Data
Work performance data contains data on the types and quantities of
communications that have actually been distributed.
Coincides with PMBOK 10.3
Enterprise Environmental Factors
The enterprise environmental factors that can influence the Monitor
Communications process include:
• Organizational culture, political climate, and governance framework
• Established communication channels, tools, and systems
• Global, regional, or local trends, practices, or habits
• Geographic distribution of facilities and resources
Monitor Communications - Inputs
Coincides with PMBOK 10.3
Organisational Process Assets
The organizational process assets that may influence the Monitor Communications
process include:
• Corporate policies and procedures for social media, ethics, and security
• Organizational communication requirements
• Standardized guidelines for development, exchange, storage, and retrieval of
information
• Historical information and lessons learned repository from previous projects
• Stakeholder and communications data and information from previous projects.
Monitor Communications - Inputs
Monitor Communications – Tools & Techniques
Coincides with PMBOK 10.3
Expert Judgement
Expertise should be considered from individuals or groups with specialized
knowledge or training in the following topics:
• Communications with the public, the community, and the media, and, in an
international environment, between virtual groups
• Communications and project management systems
Monitor Communications – Tools & Techniques
Coincides with PMBOK 10.3
Project Management Information System
Project management information systems provides a set of standard tools
for the project manager to capture, store, and distribute information to
internal and external stakeholders with the information they need
according the communications plan. The information contained in the
system is monitored to assess its validity and effectiveness.
Monitor Communications – Tools & Techniques
Coincides with PMBOK 10.3
Data Representation
A data representation technique that can be used includes but is not
limited to the stakeholder engagement assessment matrix, which can
provide information about the effectiveness of the communications
activities. This is achieved by reviewing changes between desired and
current engagement and adjusting communications as necessary.
Monitor Communications – Tools & Techniques
Coincides with PMBOK 10.3
Interpersonal and Team Skills
Interpersonal and team skills that can be used for this process include
but are not limited to observation/conversation. Discussion and dialogue
with the project team helps determine the most appropriate way to
update and communicate project performance, and to respond to
requests from stakeholders for information.
Monitor Communications – Tools & Techniques
Coincides with PMBOK 10.3
Meetings
Face-to-face or virtual meetings are used for:
• Decision making
• Responding to stakeholder requests
• Having discussions with suppliers, vendors, and other project
stakeholders.
Monitor Communications – Outputs
Coincides with PMBOK 10.3
Work Performance Information
Work performance information includes information on how project
communication is performing by comparing the communications that
were implemented compared to those that were planned. It also
considers feedback on communications, such as survey results on
communication effectiveness.
Monitor Communications – Outputs
Coincides with PMBOK 10.3
Change Requests
The Monitor Communications process often results in the need for adjustment,
action, and intervention on communications activities defined in the
communications management plan. Change requests are processed through the
Perform Integrated Change Control process. These change requests may result in:
• Revision of stakeholder communication requirements, including stakeholders’
information distribution, content or format, and distribution method
• New procedures to eliminate bottlenecks
Monitor Communications – Outputs
Coincides with PMBOK 10.3
Project Management Plan Updates
Any change to the project management plan goes through the organization’s change
control process via a change request. Components that may require a change
request for the project management plan include:
• Communications management plan
• Stakeholder engagement plan
Monitor Communications – Outputs
Coincides with PMBOK 10.3
Project Document Updates
Project documents that may be updated as a result of carrying out this process
include:
• Issue log
• Lessons learned register
• Stakeholder register

Mais conteúdo relacionado

Mais procurados

Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity ResourceAnand Bobade
 
Project management
Project managementProject management
Project managementJay Raval
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage CommunicationAnand Bobade
 
Project communications management
Project communications managementProject communications management
Project communications managementSanket Gandhi
 
Project Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaProject Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaEdureka!
 
Project communication management
Project communication managementProject communication management
Project communication managementDikshant Ghimire
 
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...Anand Bobade
 
Chap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseChap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseAnand Bobade
 
Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workAnand Bobade
 
chap 4.4 Manage knowledge
chap 4.4 Manage knowledgechap 4.4 Manage knowledge
chap 4.4 Manage knowledgeAnand Bobade
 
11. Project Communication Management
11. Project Communication Management11. Project Communication Management
11. Project Communication ManagementBhuWan Khadka
 
Instructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionInstructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionMnbianchi
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire ResourcesAnand Bobade
 
Chap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkChap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkAnand Bobade
 

Mais procurados (20)

Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity Resource
 
Project management
Project managementProject management
Project management
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage Communication
 
Project communications management
Project communications managementProject communications management
Project communications management
 
PMP ITTOs Quick Review
PMP ITTOs Quick Review PMP ITTOs Quick Review
PMP ITTOs Quick Review
 
Project Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaProject Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | Edureka
 
PMP_Project Stakeholder Management
PMP_Project Stakeholder ManagementPMP_Project Stakeholder Management
PMP_Project Stakeholder Management
 
1. project integration management
1. project integration management1. project integration management
1. project integration management
 
Project communication management
Project communication managementProject communication management
Project communication management
 
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
 
Chap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseChap 4.7 Project or Phase Close
Chap 4.7 Project or Phase Close
 
Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project work
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
PMP_Project Integration Management
PMP_Project Integration ManagementPMP_Project Integration Management
PMP_Project Integration Management
 
chap 4.4 Manage knowledge
chap 4.4 Manage knowledgechap 4.4 Manage knowledge
chap 4.4 Manage knowledge
 
11. Project Communication Management
11. Project Communication Management11. Project Communication Management
11. Project Communication Management
 
Instructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionInstructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th Edition
 
Pmp integration management
Pmp integration managementPmp integration management
Pmp integration management
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire Resources
 
Chap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkChap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project Work
 

Semelhante a 10.3 Monitor Communication

10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication ManagementDavidMcLachlan1
 
13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder Engagement13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder EngagementDavidMcLachlan1
 
13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder Engagement13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder EngagementDavidMcLachlan1
 
10.0 Project Communications Management Overview
10.0 Project Communications Management Overview10.0 Project Communications Management Overview
10.0 Project Communications Management OverviewDavidMcLachlan1
 
Project / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsProject / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsAhmed Alageed
 
10. Project Communications Management.pptx
10. Project Communications Management.pptx10. Project Communications Management.pptx
10. Project Communications Management.pptxKamranKhan353531
 
13.1 Identify Stakeholders
13.1 Identify Stakeholders13.1 Identify Stakeholders
13.1 Identify StakeholdersDavidMcLachlan1
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principlestltiede
 
5.1 Plan Scope Management
5.1 Plan Scope Management5.1 Plan Scope Management
5.1 Plan Scope ManagementDavidMcLachlan1
 
Topic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdfTopic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdfHuyNguyen657394
 
projectscopemanagement1-140220062122-phpapp01 (1).pdf
projectscopemanagement1-140220062122-phpapp01 (1).pdfprojectscopemanagement1-140220062122-phpapp01 (1).pdf
projectscopemanagement1-140220062122-phpapp01 (1).pdfAbdiqadirOsman
 

Semelhante a 10.3 Monitor Communication (20)

10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication Management
 
13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder Engagement13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder Engagement
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
 
9.3 Acquire Resources
9.3 Acquire Resources9.3 Acquire Resources
9.3 Acquire Resources
 
CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4
 
13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder Engagement13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder Engagement
 
PMP-Scope Management area
PMP-Scope Management areaPMP-Scope Management area
PMP-Scope Management area
 
10.0 Project Communications Management Overview
10.0 Project Communications Management Overview10.0 Project Communications Management Overview
10.0 Project Communications Management Overview
 
Project / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsProject / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes Groups
 
10. Project Communications Management.pptx
10. Project Communications Management.pptx10. Project Communications Management.pptx
10. Project Communications Management.pptx
 
04 project integration management
04 project integration management04 project integration management
04 project integration management
 
Project Scope Management
Project Scope ManagementProject Scope Management
Project Scope Management
 
9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
 
9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
 
13.1 Identify Stakeholders
13.1 Identify Stakeholders13.1 Identify Stakeholders
13.1 Identify Stakeholders
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
 
5.1 Plan Scope Management
5.1 Plan Scope Management5.1 Plan Scope Management
5.1 Plan Scope Management
 
Topic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdfTopic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdf
 
projectscopemanagement1-140220062122-phpapp01 (1).pdf
projectscopemanagement1-140220062122-phpapp01 (1).pdfprojectscopemanagement1-140220062122-phpapp01 (1).pdf
projectscopemanagement1-140220062122-phpapp01 (1).pdf
 

Mais de DavidMcLachlan1

12.1 Procurement Contracts
12.1 Procurement Contracts12.1 Procurement Contracts
12.1 Procurement ContractsDavidMcLachlan1
 
12.2 Conduct Procurements
12.2 Conduct Procurements12.2 Conduct Procurements
12.2 Conduct ProcurementsDavidMcLachlan1
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control ProcurementsDavidMcLachlan1
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project KnowledgeDavidMcLachlan1
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIDavidMcLachlan1
 
Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2DavidMcLachlan1
 
Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2DavidMcLachlan1
 
Scenario - The Project Management Environment
Scenario - The Project Management EnvironmentScenario - The Project Management Environment
Scenario - The Project Management EnvironmentDavidMcLachlan1
 
Agile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentAgile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentDavidMcLachlan1
 
Agile Scenarios - Core Practices
Agile Scenarios - Core PracticesAgile Scenarios - Core Practices
Agile Scenarios - Core PracticesDavidMcLachlan1
 
Agile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningAgile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningDavidMcLachlan1
 
6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean FrameworksDavidMcLachlan1
 
5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean FrameworksDavidMcLachlan1
 
7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile EnvironmentDavidMcLachlan1
 
4.0 The Agile Core Practices
4.0 The Agile Core Practices4.0 The Agile Core Practices
4.0 The Agile Core PracticesDavidMcLachlan1
 
3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principlesDavidMcLachlan1
 
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...DavidMcLachlan1
 

Mais de DavidMcLachlan1 (20)

12.1 Procurement Contracts
12.1 Procurement Contracts12.1 Procurement Contracts
12.1 Procurement Contracts
 
12.2 Conduct Procurements
12.2 Conduct Procurements12.2 Conduct Procurements
12.2 Conduct Procurements
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control Procurements
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project Knowledge
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
 
Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2
 
Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2
 
Scenario - The Project Management Environment
Scenario - The Project Management EnvironmentScenario - The Project Management Environment
Scenario - The Project Management Environment
 
Agile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentAgile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile Environment
 
Agile Scenarios - Core Practices
Agile Scenarios - Core PracticesAgile Scenarios - Core Practices
Agile Scenarios - Core Practices
 
Agile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningAgile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave Planning
 
6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks
 
5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks
 
7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment
 
4.0 The Agile Core Practices
4.0 The Agile Core Practices4.0 The Agile Core Practices
4.0 The Agile Core Practices
 
3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles
 
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
 
7.4 Control Costs
7.4 Control Costs7.4 Control Costs
7.4 Control Costs
 
7.3 Determine Budget
7.3 Determine Budget7.3 Determine Budget
7.3 Determine Budget
 

Último

Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxVishalSingh1417
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Shubhangi Sonawane
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxRamakrishna Reddy Bijjam
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docxPoojaSen20
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxAreebaZafar22
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxnegromaestrong
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxVishalSingh1417
 
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIFood Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIShubhangi Sonawane
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.pptRamjanShidvankar
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701bronxfugly43
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin ClassesCeline George
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfAyushMahapatra5
 

Último (20)

Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIFood Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 

10.3 Monitor Communication

  • 2. Monitor Communications Coincides with PMBOK 10.3 Process Group and Knowledge Area Mapping Knowledge Areas Initiating Planning Process Group Executing Process Group Monitoring and Controlling Process Group Closing Process Group 4. Project Integration Management 4.1 Develop Project Charter 4.2 Develop Project Management Plan 4.3 Direct and Manage Project Work 4.4 Manage Project Knowledge 4.5 Monitor and Control Project Work 4.6 Perform Integrated Change Control 4.7 Close Project or Phase 5. Project Scope Management 5.1 Plan Scope Management 5.2 Collect Requirements 5.3 Define Scope 5.4 Create WBS 5.5 Validate Scope 5.6 Control Scope 6. Project Schedule Management 6.1 Plan Schedule Management 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Durations 6.5 Develop Schedule 6.6 Control Schedule 7. Project Cost Management 7.1 Plan Cost Management 7.2 Estimate Costs 7.3 Determine Budget 7.4 Control Costs 8. Project Quality Management 8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality 9. Project Resource Management 9.1 Plan Resource Management 9.2 Estimate Activity Resources 9.3 Acquire Resources 9.4 Develop Team 9.5 Manage Team 9.6 Control Resources 10. Project Communications Management 10.1 Plan Communications Management 10.2 Manage Communications 10.3 Monitor Communications 11. Project Risk Management 11.1 Plan Risk Management 11.2 Identify Risks 11.3 Perform Qualitative Risk Analysis 11.4 Perform Quantitative Risk Analysis 11.5 Plan Risk Responses 11.6 Implement Risk Responses 11.7 Monitor Risks 12. Project Procurement Management 12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements 13. Project Stakeholder Management 13.1 Identify Stakeholders 13.2 Plan Stakeholder Engagement 13.3 Manage Stakeholder Engagement 13.4 Monitor Stakeholder Engagement
  • 3. What is it? Monitor Communications is the process of ensuring the information needs of the project and its stakeholders are met. Why? The key benefit of this process is the optimal information flow as defined in the communications management plan and the stakeholder engagement plan. Monitor Communications Coincides with PMBOK 10.3
  • 4. Overview • Monitor Communications determines if the planned communications artefacts and activities have had the desired effect of increasing or maintaining stakeholders’ support for the project’s deliverables and expected outcomes. • Monitor Communications may require a variety of methods, such as customer satisfaction surveys, collecting lessons learned, observations of the team, reviewing data from the issue log, or evaluating changes in the stakeholder engagement assessment matrix. Coincides with PMBOK 10.3 Monitor Communications
  • 5. Monitor Communications Coincides with PMBOK 10.3 Inputs Tools & Techniques Outputs 1. Project management plan • Resource management plan • Communications management plan • Stakeholder engagement plan 2. Project documents • Issue log • Lessons learned register • Project communications 3. Work performance reports 4. Enterprise environmental factors 5. Organizational process assets 1. Expert judgment 2. Project management information system 3. Data analysis • Stakeholder engagement assessment matrix 4. Interpersonal and team skills • Observation/conversation 5. Meetings 1. Work performance information 2. Change requests 3. Project management plan updates • Communications management plan • Stakeholder engagement plan 4. Project documents updates • Issue log • Lessons learned register • Stakeholder register Inputs, Tools & Techniques, Outputs
  • 6. Monitor Communications Coincides with PMBOK 10.3 10.3 Monitor Communications Project Management Plan Enterprise/Orga nization 4.3 Direct and Manage Project Work • Work performance information • Issue log • Lessons learned register • Project communications • Enterprise environmental factors • Organizational process assets • Resource management plan • Communications management plan • Stakeholder engagement plan Project Documents • Work Performance Report Project Documents Project Management Plan • Change requests • Communications management plan • Stakeholder engagement plan • Issue log • Lessons learned register • Project communications 4.6 Perform Integrated Change Control 4.5 Monitor and Control Project Work
  • 7. Monitor Communications - Inputs Coincides with PMBOK 10.3 Project Management Plan Project Management Plan components include: • Resource management plan • Communication management plan • Stakeholder engagement plan
  • 8. Monitor Communications - Inputs Coincides with PMBOK 10.3 Project Documents Project Documents include: • Issue log • Lessons learned register • Project communications
  • 9. Monitor Communications - Inputs Coincides with PMBOK 10.3 Work Performance Data Work performance data contains data on the types and quantities of communications that have actually been distributed.
  • 10. Coincides with PMBOK 10.3 Enterprise Environmental Factors The enterprise environmental factors that can influence the Monitor Communications process include: • Organizational culture, political climate, and governance framework • Established communication channels, tools, and systems • Global, regional, or local trends, practices, or habits • Geographic distribution of facilities and resources Monitor Communications - Inputs
  • 11. Coincides with PMBOK 10.3 Organisational Process Assets The organizational process assets that may influence the Monitor Communications process include: • Corporate policies and procedures for social media, ethics, and security • Organizational communication requirements • Standardized guidelines for development, exchange, storage, and retrieval of information • Historical information and lessons learned repository from previous projects • Stakeholder and communications data and information from previous projects. Monitor Communications - Inputs
  • 12. Monitor Communications – Tools & Techniques Coincides with PMBOK 10.3 Expert Judgement Expertise should be considered from individuals or groups with specialized knowledge or training in the following topics: • Communications with the public, the community, and the media, and, in an international environment, between virtual groups • Communications and project management systems
  • 13. Monitor Communications – Tools & Techniques Coincides with PMBOK 10.3 Project Management Information System Project management information systems provides a set of standard tools for the project manager to capture, store, and distribute information to internal and external stakeholders with the information they need according the communications plan. The information contained in the system is monitored to assess its validity and effectiveness.
  • 14. Monitor Communications – Tools & Techniques Coincides with PMBOK 10.3 Data Representation A data representation technique that can be used includes but is not limited to the stakeholder engagement assessment matrix, which can provide information about the effectiveness of the communications activities. This is achieved by reviewing changes between desired and current engagement and adjusting communications as necessary.
  • 15. Monitor Communications – Tools & Techniques Coincides with PMBOK 10.3 Interpersonal and Team Skills Interpersonal and team skills that can be used for this process include but are not limited to observation/conversation. Discussion and dialogue with the project team helps determine the most appropriate way to update and communicate project performance, and to respond to requests from stakeholders for information.
  • 16. Monitor Communications – Tools & Techniques Coincides with PMBOK 10.3 Meetings Face-to-face or virtual meetings are used for: • Decision making • Responding to stakeholder requests • Having discussions with suppliers, vendors, and other project stakeholders.
  • 17. Monitor Communications – Outputs Coincides with PMBOK 10.3 Work Performance Information Work performance information includes information on how project communication is performing by comparing the communications that were implemented compared to those that were planned. It also considers feedback on communications, such as survey results on communication effectiveness.
  • 18. Monitor Communications – Outputs Coincides with PMBOK 10.3 Change Requests The Monitor Communications process often results in the need for adjustment, action, and intervention on communications activities defined in the communications management plan. Change requests are processed through the Perform Integrated Change Control process. These change requests may result in: • Revision of stakeholder communication requirements, including stakeholders’ information distribution, content or format, and distribution method • New procedures to eliminate bottlenecks
  • 19. Monitor Communications – Outputs Coincides with PMBOK 10.3 Project Management Plan Updates Any change to the project management plan goes through the organization’s change control process via a change request. Components that may require a change request for the project management plan include: • Communications management plan • Stakeholder engagement plan
  • 20. Monitor Communications – Outputs Coincides with PMBOK 10.3 Project Document Updates Project documents that may be updated as a result of carrying out this process include: • Issue log • Lessons learned register • Stakeholder register

Notas do Editor

  1. This process is performed throughout the project.
  2. The impact and consequences of project communications should be carefully evaluated and monitored to ensure that the right message with the right content (the same meaning for sender and receiver) is delivered to the right audience, through the right channel, and at the right time. The Monitor Communications process can trigger an iteration of the Plan Communications Management and/or Manage Communications processes to improve effectiveness of communication through additional and possibly amended communications plans and activities.
  3. Resource management plan - The resource management plan can be used to understand the actual project organization and any changes through understanding of roles and responsibilities and the project organization charts. Communications management plan - The communications management plan contains the current plan for collecting, creating, and distributing information in a timely manner. It identifies the team members, stakeholders, and the work involved in the communication process. Stakeholder engagement plan - The stakeholder engagement plan identifies the communication strategies that are planned to engage stakeholders.
  4. Issue log - The issue log provides the project’s history, a record of stakeholder engagement issues, and how they were resolved. Lessons learned register - Lessons learned earlier in the project can be applied to later phases in the project to improve communication effectiveness. Project communications - Provides information about communications that have been distributed.
  5. Observation and conversation enables the project manager to identify issues within the team, conflicts between people, or individual performance issues.
  6. The communications management plan is updated with new information to make communication more effective. The stakeholder engagement plan is updated to reflect the actual situation of stakeholders, their communication needs, and their importance.
  7. Issue log - The issue log may be updated with new information on issues raised, their progress, and resolution. Lessons learned register - The lessons learned register may be updated with causes of issues, reasons behind the corrective actions chosen, and other communication lessons learned as appropriate. Stakeholder register - The stakeholder register may be updated with revised stakeholder communication requirements.