Sparkle Entertainment's production schedule spans 4 weeks and includes 9 days of filming narrative scenes, performances, and symbols with their main cast and crew. Key roles include Daniel on camera, Farzin as director, Henali on continuity, and actors Evelina and James. The schedule also allocates 2 weeks for editing scenes, adding lipsyncing, and submitting a rough cut, with the final editing taking place in the fourth week of production.
1. Sparkle Entertainment’s Production
Schedule
Day Type of production RolesandStaff
Day 1 (16/Jan/2016)
9am to12pm
Filming(NarrativeScenes) Daniel – Camera
Farzin– Director
Henali – Continuity
Evelina(MainActress)
James(MainActor)
Day 2 (17/Jan/2016)
12pm to 3pm
Filming(Narrative)
Status- Completed
Daniel (C) Farzin(D),Henali (C)
Evelina– Actress
James- Actor
Day 3 (20/Jan/2016) Editing
Status- Completed
Daniel,Farzin,Henali
Day 4 (21/Jan/2016) Editingof currentscenes All mainstaff
Day 5 (23/Jan/2016)
9am to12pm
Filming(Performance) All staff
James- Actor
Day 6 (24/Jan)
12pm to 3pm
Filming(Performance) All staff
SupervisionfromEvelina
James- Performance
Week2 (25 – 29) Editing(Lipsyncing) All staff
Day 7 (3/Feb)
4pm to 6pm
Week3 (1-5)
Filming(Continued
Performance)
Editing(Roughcut
submitted)
Henali,Farzin
James– Performingactor
Daniel
Day 8 (6/Feb)
4pm to 6pm
Filming(Performance and
Symbolism)
Henali,Farzin
James
Day 9 (10/Feb)
4pm to 6pm
Week4 (8 - 12)
Final Filming(Performance)
Final Editing
Henali,Farzin
James
Farzin,Daniel