SlideShare uma empresa Scribd logo
1 de 9
Upgrading Generator Protection
Using Multiple Relay Ups
INTRODUCTION
Contrary to popular belief, generators do experience short circuits and
abnormal electrical conditions. In many cases, equipment damage due to these
events can be reduced or prevented by proper generator protection. Generators,
unlike some other power system components, need to be protected not only
from short circuits, but from abnormal operating conditions. Examples of such
abnormal conditions are: overexcitation, overvoltage, loss-of-field, unbalanced
currents, reverse power, and abnormal frequency. When subjected to these
conditions, damage or complete failure can occur within seconds, thus requiring
automatic detection and tripping.
In a properly protected generator, automatic protection against harmful abnormal
conditions is required. The bulk of this paper deals with the need to provide such protection.
Objections to the addition of such protection is not that it will fail to operate when it should,
but that it might operate improperly to remove a generator from service unnecessarily. This
concern about upgrading protection can be greatly reduced by understanding the need for
such upgrades, and how to apply them to a given generator. An unnecessary generator
tripping is undesirable, but the consequences of not tripping and damaging the machine are
far worse. The cost to the utility for such an occurrence includes not only the cost of repair or
replacement of the damaged machine, but the substantial cost of replacement power during
the periods when the unit is out of service.
An alert and skillful operator, at manned locations, can sometimes avoid
removing a generator from service by correcting an abnormal operating
condition. In the vast majority of cases, however, the event will occur too rapidly
for the operator to react and automatic detection is required. Operators have
also been known to make mistakes, creating abnormal conditions where
generator tripping is required to avoid damage. Inadvertent energizing and over
excitation are examples of such events. For these reasons, operating procedures
are not a substitute for proper automatic protection.
IMPROVED SENSITIVITY PROTECTION AREAS
Negative Sequence (unbalanced current) Protection
There are a number of system conditions that can cause unbalanced
three-phase currents in a generator. These system conditions produce negative
sequence components of current which induce a double-frequency current in the
surface of the rotor. The skin effect of the double-frequency rotor current causes
it to be forced into the surface elements of the rotor. These rotor currents can
cause excessive temperatures in a very short time.
Currents in the Rotor Surface
Sequential Tripping
This method of shutting down a generator is used on steam
generators to prevent over speed when delayed tripping has no
detrimental effect on the generating unit. This method of generator
tripping was recommended by generator manufacturers of steam
turbines some years ago as a result of over speed generator failures and is
an upgrade item. It is used to trip the generator for prime mover
problems only where high speed tripping is
not a requirement. The first device tripped is the turbine valves. A reverse
power relay in series with the valves close position switches provides
security against possible over speed of the turbine by ensuring that steam
flows have been reduced, below the amount necessary to produce an
over speeding condition, before the generator breaker(s) are tripped. For
boiler/reactor or turbine mechanical problems, this is the preferred
tripping mode since it prevents the over speed of the machine. Figure 12
shows the block diagram for sequential tripping.
CONCLUSION
There are a number of functional protection areas on 20+ year old
generators which have significant shortcom- ings. This paper identifies
those protection areas and the risks of not addressing them. In addition, a
cost- effective strategy to upgrade protection to current industry
standards is outlined using multifunction digital relaying. Generation is
the single most expensive capital investment of a utility. Protecting this
investment to prevent failure should be a priority item with utilties as well
as non-utility generator owners.
Thank You

Mais conteúdo relacionado

Semelhante a Upgrading Generator Protection Using Multiple Relay Ups.pptx

An-Overview-of-Protection-System-Analysis-3.pdf
An-Overview-of-Protection-System-Analysis-3.pdfAn-Overview-of-Protection-System-Analysis-3.pdf
An-Overview-of-Protection-System-Analysis-3.pdfRamprasadSarkar1
 
induction motor protection system seminar report
induction motor protection system seminar reportinduction motor protection system seminar report
induction motor protection system seminar reportdipali karangale
 
Major faults in an alternator and their protection.
Major faults in an alternator and their protection.Major faults in an alternator and their protection.
Major faults in an alternator and their protection.javid iqbal sodagar
 
Starters of induction motor and protection equipment
Starters of induction motor and protection equipmentStarters of induction motor and protection equipment
Starters of induction motor and protection equipmentsateesh kumar
 
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...Emergency Power Supplies: Electrical Distribution Design, Installation and Co...
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...Living Online
 
442639191-Generator-Protection-ppt.ppt
442639191-Generator-Protection-ppt.ppt442639191-Generator-Protection-ppt.ppt
442639191-Generator-Protection-ppt.pptsanipriadi1
 
Experience feedback steam turbine
Experience feedback steam turbineExperience feedback steam turbine
Experience feedback steam turbineSouvik Dutta
 
IRJET- Adaptive Observer-Based Fault Estimation for DFIG based Wind Turbine S...
IRJET- Adaptive Observer-Based Fault Estimation for DFIG based Wind Turbine S...IRJET- Adaptive Observer-Based Fault Estimation for DFIG based Wind Turbine S...
IRJET- Adaptive Observer-Based Fault Estimation for DFIG based Wind Turbine S...IRJET Journal
 
Protection and monitoring of three phase induction motor from over voltage, u...
Protection and monitoring of three phase induction motor from over voltage, u...Protection and monitoring of three phase induction motor from over voltage, u...
Protection and monitoring of three phase induction motor from over voltage, u...IRJET Journal
 
Lecture_22_-_Generator_Protection by Dr. AHmad-al-Subhi
Lecture_22_-_Generator_Protection by Dr. AHmad-al-SubhiLecture_22_-_Generator_Protection by Dr. AHmad-al-Subhi
Lecture_22_-_Generator_Protection by Dr. AHmad-al-SubhiAniruddhaRay11
 
New Microsoft Word Document
New Microsoft Word DocumentNew Microsoft Word Document
New Microsoft Word DocumentBarunava Sikdar
 
Protection of induction motor using classical method
Protection of induction motor using classical methodProtection of induction motor using classical method
Protection of induction motor using classical methodIRJET Journal
 
Equipment protection
Equipment protectionEquipment protection
Equipment protectionSlides Hub
 
Protection of three phase synchronous generator
Protection of three phase synchronous generatorProtection of three phase synchronous generator
Protection of three phase synchronous generatorMohammad Abdullah
 
Three Phase Induction Motor Protection Scheme
Three Phase Induction Motor Protection SchemeThree Phase Induction Motor Protection Scheme
Three Phase Induction Motor Protection SchemeIRJET Journal
 
Installing, Programming & Commissioning of Power System Protection Relays and...
Installing, Programming & Commissioning of Power System Protection Relays and...Installing, Programming & Commissioning of Power System Protection Relays and...
Installing, Programming & Commissioning of Power System Protection Relays and...Living Online
 
Installing, Programming & Commissioning of Power System Protection Relays and...
Installing, Programming & Commissioning of Power System Protection Relays and...Installing, Programming & Commissioning of Power System Protection Relays and...
Installing, Programming & Commissioning of Power System Protection Relays and...Living Online
 
IRJET- GSM Based Transformer Fault Monitoring System
IRJET- GSM Based Transformer Fault Monitoring SystemIRJET- GSM Based Transformer Fault Monitoring System
IRJET- GSM Based Transformer Fault Monitoring SystemIRJET Journal
 

Semelhante a Upgrading Generator Protection Using Multiple Relay Ups.pptx (20)

An-Overview-of-Protection-System-Analysis-3.pdf
An-Overview-of-Protection-System-Analysis-3.pdfAn-Overview-of-Protection-System-Analysis-3.pdf
An-Overview-of-Protection-System-Analysis-3.pdf
 
induction motor protection system seminar report
induction motor protection system seminar reportinduction motor protection system seminar report
induction motor protection system seminar report
 
Major faults in an alternator and their protection.
Major faults in an alternator and their protection.Major faults in an alternator and their protection.
Major faults in an alternator and their protection.
 
Starters of induction motor and protection equipment
Starters of induction motor and protection equipmentStarters of induction motor and protection equipment
Starters of induction motor and protection equipment
 
Industrial control motor overload protection
Industrial control motor overload protectionIndustrial control motor overload protection
Industrial control motor overload protection
 
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...Emergency Power Supplies: Electrical Distribution Design, Installation and Co...
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...
 
442639191-Generator-Protection-ppt.ppt
442639191-Generator-Protection-ppt.ppt442639191-Generator-Protection-ppt.ppt
442639191-Generator-Protection-ppt.ppt
 
Experience feedback steam turbine
Experience feedback steam turbineExperience feedback steam turbine
Experience feedback steam turbine
 
IRJET- Adaptive Observer-Based Fault Estimation for DFIG based Wind Turbine S...
IRJET- Adaptive Observer-Based Fault Estimation for DFIG based Wind Turbine S...IRJET- Adaptive Observer-Based Fault Estimation for DFIG based Wind Turbine S...
IRJET- Adaptive Observer-Based Fault Estimation for DFIG based Wind Turbine S...
 
Protection and monitoring of three phase induction motor from over voltage, u...
Protection and monitoring of three phase induction motor from over voltage, u...Protection and monitoring of three phase induction motor from over voltage, u...
Protection and monitoring of three phase induction motor from over voltage, u...
 
Lecture_22_-_Generator_Protection by Dr. AHmad-al-Subhi
Lecture_22_-_Generator_Protection by Dr. AHmad-al-SubhiLecture_22_-_Generator_Protection by Dr. AHmad-al-Subhi
Lecture_22_-_Generator_Protection by Dr. AHmad-al-Subhi
 
New Microsoft Word Document
New Microsoft Word DocumentNew Microsoft Word Document
New Microsoft Word Document
 
Protection of alternator
Protection of alternatorProtection of alternator
Protection of alternator
 
Protection of induction motor using classical method
Protection of induction motor using classical methodProtection of induction motor using classical method
Protection of induction motor using classical method
 
Equipment protection
Equipment protectionEquipment protection
Equipment protection
 
Protection of three phase synchronous generator
Protection of three phase synchronous generatorProtection of three phase synchronous generator
Protection of three phase synchronous generator
 
Three Phase Induction Motor Protection Scheme
Three Phase Induction Motor Protection SchemeThree Phase Induction Motor Protection Scheme
Three Phase Induction Motor Protection Scheme
 
Installing, Programming & Commissioning of Power System Protection Relays and...
Installing, Programming & Commissioning of Power System Protection Relays and...Installing, Programming & Commissioning of Power System Protection Relays and...
Installing, Programming & Commissioning of Power System Protection Relays and...
 
Installing, Programming & Commissioning of Power System Protection Relays and...
Installing, Programming & Commissioning of Power System Protection Relays and...Installing, Programming & Commissioning of Power System Protection Relays and...
Installing, Programming & Commissioning of Power System Protection Relays and...
 
IRJET- GSM Based Transformer Fault Monitoring System
IRJET- GSM Based Transformer Fault Monitoring SystemIRJET- GSM Based Transformer Fault Monitoring System
IRJET- GSM Based Transformer Fault Monitoring System
 

Último

Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01KreezheaRecto
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...tanu pandey
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoordharasingh5698
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Intro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfIntro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfrs7054576148
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 

Último (20)

(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Intro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfIntro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdf
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 

Upgrading Generator Protection Using Multiple Relay Ups.pptx

  • 2. INTRODUCTION Contrary to popular belief, generators do experience short circuits and abnormal electrical conditions. In many cases, equipment damage due to these events can be reduced or prevented by proper generator protection. Generators, unlike some other power system components, need to be protected not only from short circuits, but from abnormal operating conditions. Examples of such abnormal conditions are: overexcitation, overvoltage, loss-of-field, unbalanced currents, reverse power, and abnormal frequency. When subjected to these conditions, damage or complete failure can occur within seconds, thus requiring automatic detection and tripping.
  • 3. In a properly protected generator, automatic protection against harmful abnormal conditions is required. The bulk of this paper deals with the need to provide such protection. Objections to the addition of such protection is not that it will fail to operate when it should, but that it might operate improperly to remove a generator from service unnecessarily. This concern about upgrading protection can be greatly reduced by understanding the need for such upgrades, and how to apply them to a given generator. An unnecessary generator tripping is undesirable, but the consequences of not tripping and damaging the machine are far worse. The cost to the utility for such an occurrence includes not only the cost of repair or replacement of the damaged machine, but the substantial cost of replacement power during the periods when the unit is out of service.
  • 4. An alert and skillful operator, at manned locations, can sometimes avoid removing a generator from service by correcting an abnormal operating condition. In the vast majority of cases, however, the event will occur too rapidly for the operator to react and automatic detection is required. Operators have also been known to make mistakes, creating abnormal conditions where generator tripping is required to avoid damage. Inadvertent energizing and over excitation are examples of such events. For these reasons, operating procedures are not a substitute for proper automatic protection.
  • 5. IMPROVED SENSITIVITY PROTECTION AREAS Negative Sequence (unbalanced current) Protection There are a number of system conditions that can cause unbalanced three-phase currents in a generator. These system conditions produce negative sequence components of current which induce a double-frequency current in the surface of the rotor. The skin effect of the double-frequency rotor current causes it to be forced into the surface elements of the rotor. These rotor currents can cause excessive temperatures in a very short time.
  • 6. Currents in the Rotor Surface
  • 7. Sequential Tripping This method of shutting down a generator is used on steam generators to prevent over speed when delayed tripping has no detrimental effect on the generating unit. This method of generator tripping was recommended by generator manufacturers of steam turbines some years ago as a result of over speed generator failures and is an upgrade item. It is used to trip the generator for prime mover problems only where high speed tripping is not a requirement. The first device tripped is the turbine valves. A reverse power relay in series with the valves close position switches provides security against possible over speed of the turbine by ensuring that steam flows have been reduced, below the amount necessary to produce an over speeding condition, before the generator breaker(s) are tripped. For boiler/reactor or turbine mechanical problems, this is the preferred tripping mode since it prevents the over speed of the machine. Figure 12 shows the block diagram for sequential tripping.
  • 8. CONCLUSION There are a number of functional protection areas on 20+ year old generators which have significant shortcom- ings. This paper identifies those protection areas and the risks of not addressing them. In addition, a cost- effective strategy to upgrade protection to current industry standards is outlined using multifunction digital relaying. Generation is the single most expensive capital investment of a utility. Protecting this investment to prevent failure should be a priority item with utilties as well as non-utility generator owners.