1. Dattatraya R. Phadatare(B.E,PMP)
Mobile: +971 526561176 (UAE-Dubai )
E-Mail: d_phadatare@rediffmail.com
Resume Summary:
• More than 10 years of Gulf experience in Project planning and control.
• Having core expertise in the field of Planning, Monitoring & Controlling.
• Proficient in making reports .
• Skilled in preparation of Project Management Plan (detailed time & cost baseline, resource planning, impact
& recovery EPC schedules).
• Proficient in project reporting, site coordination, client meeting-presentation and team supervision.
Specialties: Planning, Monitoring, Controlling & Co-ordination
Professional Profile:
To utilize my inherent abilities and talent to work in a challenging environment that would facilitate continuous
learning and wide exposure to ideas that stimulate and achieve personal, professional and organizational growth.
Technical/Computer Skills:
Primavera project planner ver 6
Microsoft project ver. 2003
Microsoft project ver. 2007
MS Office 2007
Project Management Programming ( PMP – Cambridge )
Projects:
Current project
Company : China state construction & Engineering , Middle east LLC Dubai.
Designation: Sr.Planning Engineer
Project:: Viceroy Hotel & Resorts Project (B2+G+17), Dubai
Location:: UAE ,Dubai
Type Of project: : 5 Star Hotel & Resorts & Residence
Project value : 1.20 Billion AED
Duration : April 2014 to Till Date
Roles & responsibility
To Monitor , control & update daily site progress of main contractor & sub-contractor
To monitor, update daily tracking sheet & submit to client
To prepare ,update & monitor schedules for structural work , block work ,steel , EIFS ,Lift ,BMU, Glass, Public area,
Villas updates , Hard scape , Boundary wall updates etc.
To review , check , submit daily weekly , monthly report & management report
To submit weekly final percentage progress report & KPI report to client & management.
To prepare daily, weekly , monthly manpower site report for main contractor & sub-contractor & prepare the
manpower histogram.
Preparation of Weekly and Monthly Look Ahead microprogram and monitoring the same
To prepare & submit the Dash Board , KPI report to management & client ( updates about manpower histogram,
overall % progress, S curve updates, variance
To highlight the area of concerns, delays & action plan for completion.
To coordinate & attend the meeting with main contractor , subcontractor ,client & send the letters to concerns
To review & analyses of subcontractors daily & weekly reports
Previous Companies:
1) Company : Simplex Infrastructures Ltd, Bangalore, India
Designation: Senior Planning Engineer
Duration : April 2010 to July 2014
2. Job Responsibilities:
Pre tender planning related works – preparation of tender schedules, manpower and material, plant and machinery,
logistics planning and presentations to prospective clients along with the tender department.
Pre & Post tender planning related works – finalization of baseline schedules, manpower histogram, cash flow,
procurement plans, sales projections, monitoring the project at various levels, recovery planning, attending site
meetings and reporting to clients and management.
Currently involved in daily coordination works related to planning, monitoring and coordination with the site teams
for some of the prestigious projects as mentioned below
o Commercial project for M/s Tanglin Developments Ltd, at Bangalore – 3 towers – 2B+G+12 floors.
o Residential project for M/s KG Foundations P Ltd, at Chennai consisting of 2 towers of 2B+G+14 floors.
o Mixed development for M/s ITC, at Guntur consisting of 2 towers – G+9 floors, Club house, Office and a
Transit.
o Residential project for M/s Prestige at Bangalore consisting of 4 towers – 2B+G+18 floors.
2) Company : Emirates Trading Agency ( ETA )
Designation: Planning Engineer
Project: Al Mas Tower Project (B5+G+64+4S), Dubai
Location: Dubai
Type Of project: High rise
Project value : 500 Million AED
Duration : 03-Dec-07 to 12-Mar-10
Roles & responsibility
Preparing & tracking of contractual Program (Primavera 3),
Updating the status of work with respect to Baseline program on weekly basis
Preparation of Weekly and Monthly Look Ahead Schedule and monitoring the same
Calculating Actual Man hours Spent at site
Identifying factors leading to project extension & timely notification of the same to the consultants / client
3) Company : Synergy Properties Development Services Pvt. Ltd., Bangalore.
Designation: Planning & coordinate Engineer
Project: SEZ complex for Manhattan Embassy Business Park
Location: Bangalore
Project value : 300 Million AED
Duration : May 2004 to Oct.2007
Roles & responsibility
Monitor the progress of work, status of Actual v/s planned progress of work.
Analyze the gap between Actual progress v/s Planned at Planned intervals.
Maintain all the project performance /progress related documents (project schedules and bar charts etc)
Have to regularly update progress report, abstracts, MOM of review meeting and other MIS report.
Resource planning in consultation with the project management and the contractors
4) Company : Gammon India Ltd.
Designation: Assistant Engineer
Location: Bangalore
Project value : 500 Million AED
Duration : July 2001 to April 2004
Roles & responsibility
Planning Engineer for 5 star hotel complex project at Bangalore
Execution and Planning of ID Cooling Tower works both Civil & Mechanical Works at NTPC Vindhyachal from
Oct 04-May 06.
5) Company : POONA SHIMS ( POSH ) PVT. LTD. PUNE
Designation: Site Engineer
Location: Pune
Project value : 150 Million AED
Duration : Oct 1996 to April 2001
3. Roles & responsibility
Assisted in preparation of the project cost estimate and in the execution works
Assisted in preparation of rate analysis for client
Prepared daily, monthly and weekly progress report.
Education:
1
.
IQ Auditor for EMS :- ISO 14001 1996 Qualicon Services
2
.
Training for QS 9000 Internal Auditor 1998 Qualicon Services
3
.
IQ Auditor forQMS :- QS 9000:1998 ISO /
TS 16949
2002 Qualicon Services
4
.
MSA & Calibration – III 2003 Accurate Engineering
5
.
Computer fundamental & Basics MS Office 2000 Suyash Computer
6. AutoCAD R-2000 2001 Shree Siddhi Computers
7 VDA 6.3 certified Auditor 2013 TUV Sud Certificate
8 Project Management Programming ( PMP ) 2016 Cambridge Institute
Academic Achievements/Projects/Internships Undertaken:
Undertook a project on “ up gradation of village road ”
Attended seminar on “ energy conservation”
Extracurricular activities and achievements:
2nd runner up in Inter school Short put championship
Winner of various sports events from class 1st to class 10th
Personal Details:
Date of Birth : 11-March-1976
Marital status : Married
Language Known : English, Hindi and Marathi
Nationality : Indian ( Pune )
Passport no. : G3573903 & Emirates ID no.: 784-1976-4358609-8
Driving license : 199980004682
Address for contact : C/o- Mr. Jai Surve , Emrald building , Flat no.206, Burjuman Dubai.
Mobile +971 526561176 (UAE-Dubai ) , +971 569921282, +00919823154308 ( India )
QUALIFICATION BOARD YEAR OF PASSING
PGDBM (MBA) Pune University 2013
B.E.(Mech.) MIT PUNE 2006