SlideShare uma empresa Scribd logo
1 de 14
1
CROSSTOWN LRT
Construction Liaison Committee
November 2019
2
Leaside Station Update
3
Leaside Station: What to Expect
Year What to Expect
2019-2020
• Deep excavation, hauling, concrete and material deliveries will continue
on the surface through 2020
• Extended construction hours through mid-2020; 5:00 a.m. – 11:00 p.m.
• Deep excavation of the station box will continue into early 2020
• Main and secondary entrance sites will continue to be the main access
points for the deep excavation underneath Eglinton Avenue
• Periodic additional lane closures may be required to facilitate dewatering,
deck repair and concrete works
• Permanent works have commenced at the main entrance and will continue
into late 2020, including waterproofing, formwork, rebar installation and
concrete works
• Durations of each stage may vary due to work sequencing, weather and
unexpected circumstance delays and private agreements
4
Current Traffic Staging
4
No S/B Right
Turn on Red.
5
Dewatering Works
Howard Talbot Park
• November 11, 2019 for three (3) weeks
• Crews will conduct vertical drilling of wells and trenches to connect to the existing
dewatering system
• Restoration and reinstatement of landscaping will be done following the completion of the
work
• A fence will be installed around the work zone for public safety
6
Decking Repair
7:00 a.m. on Wednesday November 13 to 7:00 p.m. on Thursday November 14th,
2019 there will be new lane and turn restrictions at the Eglinton Avenue East and
Bayview Avenue intersection to accommodate urgent decking repairs.
*Paid duty officers and flag
persons will be onsite to assist with
directing traffic and pedestrians for
the duration of the work
7
Leaside Station Progress Photos
MAIN ENTRANCE EXCAVATION FOR
PLACEMENT OF CORNER BRACE
TUNNEL BREAKOUT
MAIN ENTRANCE PERMANENT
WORKS
WATERMAIN SUPPORTED DURING
EXCAVATION
8
Emergency Exit 3 Site
(Leaside High School)
9
Emergency Exit 3 Update
• Following this work, the work zone will shift to
the middle of the roadway and traffic will be
routed north and south of the work zone.
• This stage will be in place through to late 2019.
• Early 2020, the construction zone will be
removed and a small emergency exit building
will be permanently in place on the boulevard.
Early October, the construction zone shifted to the north side
of EglintonAvenue.The new construction zone will allow for
the completion of utility relocations, backfill and road
restoration.This configuration will remain in place through to
late November, 2019.
10
Laird Station Update
11
Laird Station: What to Expect
Year What to Expect
2019
• Long duration removals are now complete. Periodic removals may
for the remainder of 2019 as work transitions to permanent
works inside of the completed cavern
Permanent Works:
• Waterproofing, form and rebar and concrete works will occur
completed cavern
• During the concrete works, there will be continuous delivery of
to the surface sites
• The concrete will form parts of the permanent station structure
underground
2020
• Utility and road restoration
• Permanent works will continue
• Overnight works will continue through to summer 2020
12
Laird StationTraffic Configuration
Through 2020
13
Laird Station Concrete Pour
One (1) dayTBD (November 22 – 27, 2019) between 5:00am-11:00pm
14
Laird Station Progress Photos
EAST END OF TUNNEL CONCRETE
POUR
WEST END OF TUNNEL
COMPLETED WATERPROOFING
MAIN SHAFT WATERPROOFING OF
WALLS

Mais conteúdo relacionado

Mais procurados

Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018
Crosstown TO
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Nov 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Nov 2019Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Nov 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Nov 2019
Crosstown TO
 
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
Crosstown TO
 
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
Crosstown TO
 
Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018
Crosstown TO
 
Central open house - oct 2019
Central open house - oct 2019Central open house - oct 2019
Central open house - oct 2019
Crosstown TO
 

Mais procurados (20)

West works open house deck March 12 2020
West works open house deck   March 12 2020 West works open house deck   March 12 2020
West works open house deck March 12 2020
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020
 
Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
  Chaplin Avenue CLC Presentation Deck - Jan 8 2020  Chaplin Avenue CLC Presentation Deck - Jan 8 2020
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
 
Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting
 
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
 
Pharmacy to Kennedy CLC meeting
Pharmacy to Kennedy  CLC meetingPharmacy to Kennedy  CLC meeting
Pharmacy to Kennedy CLC meeting
 
Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021
 
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Nov 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Nov 2019Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Nov 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Nov 2019
 
Leaside and Laird CLC - January 11, 2021
Leaside and Laird CLC - January 11, 2021Leaside and Laird CLC - January 11, 2021
Leaside and Laird CLC - January 11, 2021
 
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
 
Pharmacy kennedy clc meeting - deck - march 26,2019
Pharmacy   kennedy clc meeting - deck - march 26,2019Pharmacy   kennedy clc meeting - deck - march 26,2019
Pharmacy kennedy clc meeting - deck - march 26,2019
 
Final central east open house oct282020
Final central east open house oct282020Final central east open house oct282020
Final central east open house oct282020
 
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
 
Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018
 
Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021 Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021
 
Central open house - oct 2019
Central open house - oct 2019Central open house - oct 2019
Central open house - oct 2019
 

Semelhante a Leaside Laird CLC November 2019 Presentation

CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
Crosstown TO
 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Crosstown TO
 
Technical Council Briefing - ION Construction ̶ Six Month Overview
Technical Council Briefing - ION Construction ̶ Six Month OverviewTechnical Council Briefing - ION Construction ̶ Six Month Overview
Technical Council Briefing - ION Construction ̶ Six Month Overview
Darren Shaw, SIOR
 
Wlrt com-grand linq-technical-briefing-2015-02-23
Wlrt com-grand linq-technical-briefing-2015-02-23Wlrt com-grand linq-technical-briefing-2015-02-23
Wlrt com-grand linq-technical-briefing-2015-02-23
Darren Shaw, SIOR
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Crosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
Crosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018
Crosstown TO
 
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Crosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Crosstown TO
 

Semelhante a Leaside Laird CLC November 2019 Presentation (20)

Leaside - Laird Construction Liaison Committee (CLC) Meeting Presentation
Leaside - Laird Construction Liaison Committee (CLC) Meeting PresentationLeaside - Laird Construction Liaison Committee (CLC) Meeting Presentation
Leaside - Laird Construction Liaison Committee (CLC) Meeting Presentation
 
Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Central West Fall Open House - Oct 28 2019
Central West Fall Open House - Oct 28 2019Central West Fall Open House - Oct 28 2019
Central West Fall Open House - Oct 28 2019
 
Central West Open House
Central West Open HouseCentral West Open House
Central West Open House
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020
 
Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019
 
Technical Council Briefing - ION Construction ̶ Six Month Overview
Technical Council Briefing - ION Construction ̶ Six Month OverviewTechnical Council Briefing - ION Construction ̶ Six Month Overview
Technical Council Briefing - ION Construction ̶ Six Month Overview
 
Wlrt com-grand linq-technical-briefing-2015-02-23
Wlrt com-grand linq-technical-briefing-2015-02-23Wlrt com-grand linq-technical-briefing-2015-02-23
Wlrt com-grand linq-technical-briefing-2015-02-23
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018
 
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
 
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdfChaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
 
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017
 
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
 
Alamo Heights CCM 01.14.19 Item #7 PPT Const Update 5500 Broadway
Alamo Heights CCM 01.14.19 Item #7  PPT Const Update 5500 BroadwayAlamo Heights CCM 01.14.19 Item #7  PPT Const Update 5500 Broadway
Alamo Heights CCM 01.14.19 Item #7 PPT Const Update 5500 Broadway
 

Mais de Crosstown TO

Mais de Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 

Último

Último (20)

celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hour
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hourcelebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hour
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hour
 
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
 
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
 
World Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterWorld Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - Poster
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
 
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
 
Financing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCFinancing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCC
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
 
Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptx
 
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORSPPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
 
Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)
 
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
 
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
 
TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...
TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...
TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...
 
CBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related Topics
 
Finance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCCFinance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCC
 
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
 
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
 

Leaside Laird CLC November 2019 Presentation

  • 1. 1 CROSSTOWN LRT Construction Liaison Committee November 2019
  • 3. 3 Leaside Station: What to Expect Year What to Expect 2019-2020 • Deep excavation, hauling, concrete and material deliveries will continue on the surface through 2020 • Extended construction hours through mid-2020; 5:00 a.m. – 11:00 p.m. • Deep excavation of the station box will continue into early 2020 • Main and secondary entrance sites will continue to be the main access points for the deep excavation underneath Eglinton Avenue • Periodic additional lane closures may be required to facilitate dewatering, deck repair and concrete works • Permanent works have commenced at the main entrance and will continue into late 2020, including waterproofing, formwork, rebar installation and concrete works • Durations of each stage may vary due to work sequencing, weather and unexpected circumstance delays and private agreements
  • 4. 4 Current Traffic Staging 4 No S/B Right Turn on Red.
  • 5. 5 Dewatering Works Howard Talbot Park • November 11, 2019 for three (3) weeks • Crews will conduct vertical drilling of wells and trenches to connect to the existing dewatering system • Restoration and reinstatement of landscaping will be done following the completion of the work • A fence will be installed around the work zone for public safety
  • 6. 6 Decking Repair 7:00 a.m. on Wednesday November 13 to 7:00 p.m. on Thursday November 14th, 2019 there will be new lane and turn restrictions at the Eglinton Avenue East and Bayview Avenue intersection to accommodate urgent decking repairs. *Paid duty officers and flag persons will be onsite to assist with directing traffic and pedestrians for the duration of the work
  • 7. 7 Leaside Station Progress Photos MAIN ENTRANCE EXCAVATION FOR PLACEMENT OF CORNER BRACE TUNNEL BREAKOUT MAIN ENTRANCE PERMANENT WORKS WATERMAIN SUPPORTED DURING EXCAVATION
  • 8. 8 Emergency Exit 3 Site (Leaside High School)
  • 9. 9 Emergency Exit 3 Update • Following this work, the work zone will shift to the middle of the roadway and traffic will be routed north and south of the work zone. • This stage will be in place through to late 2019. • Early 2020, the construction zone will be removed and a small emergency exit building will be permanently in place on the boulevard. Early October, the construction zone shifted to the north side of EglintonAvenue.The new construction zone will allow for the completion of utility relocations, backfill and road restoration.This configuration will remain in place through to late November, 2019.
  • 11. 11 Laird Station: What to Expect Year What to Expect 2019 • Long duration removals are now complete. Periodic removals may for the remainder of 2019 as work transitions to permanent works inside of the completed cavern Permanent Works: • Waterproofing, form and rebar and concrete works will occur completed cavern • During the concrete works, there will be continuous delivery of to the surface sites • The concrete will form parts of the permanent station structure underground 2020 • Utility and road restoration • Permanent works will continue • Overnight works will continue through to summer 2020
  • 13. 13 Laird Station Concrete Pour One (1) dayTBD (November 22 – 27, 2019) between 5:00am-11:00pm
  • 14. 14 Laird Station Progress Photos EAST END OF TUNNEL CONCRETE POUR WEST END OF TUNNEL COMPLETED WATERPROOFING MAIN SHAFT WATERPROOFING OF WALLS

Notas do Editor

  1. RON Here we have the plan to roll out the intersection works. Blue being the shorter duration weekend works and yellow representing the 6 weeks of no through north/south traffic.
  2. RON Here we have the plan to roll out the intersection works. Blue being the shorter duration weekend works and yellow representing the 6 weeks of no through north/south traffic.