SlideShare uma empresa Scribd logo
1 de 26
Chaplin Grout Plant and
Headwall Construction
Spring 2014
Councillor Stintz Briefing
February 3, 2014
Jamie Robinson
Director, Communications and Community Relations
Toronto Expansion Projects, Metrolinx

1
Eglinton Crosstown LRT
 Project
 $4.9 B (2010$), funded by the Province of Ontario
 19 kilometres east-west LRT from Kennedy to
Jane/Black Creek, including 10 kilometers of tunnel
 Connections to Yonge-University-Spadina Subway,
Scarborough RT and GO Stouffville
 Up to 26 stations

2
Tunnelling Works 2014

3
Tunnelling Update
 TBM 1 is well underway with tunnelling; just recently bored
through our west headwall at Keele St.
 TBM 2, a twin machine, has been assembled and is
following closely behind

4
Tunnel Drive Sequence
1. Construct
Tunnel Launch
Shaft
2. Construct
Extraction Shaft

5
Tunnel Drive Sequence
Commence Mining
Twin Tunnels
Install Jet Grout
Block “Headwalls”
from Surface

6
Tunnel Drive Sequence

Mine-Through Jet
Grout Blocks

7
Tunnel Drive Sequence

After Tunnel Contract:
• Install Station
Sidewall and
Headwall Support of
Excavation
• Excavate Station and

Commence
Removing Concrete
Tunnel Liners

Finally:
• Station Box Fully
Excavated & Tunnel
Lining Removed (Not
shown)
8
Launch Shaft Tunnel Boring Machine

9
Tunnel Drive Works 2013

10
Tunnel Drive Works Current Status
 In 2013 the majority of tunnel works took place between
Black Creek Drive and the vicinity of Allen Road
 In 2014 work continues east of Allen Road
 Crews are starting the construction of headwalls and utility
relocation at future station sites along Eglinton Avenue
West

11
Tunnel Drive Works
 Headwalls: Temporary support walls for future excavation
of the LRT stations.
 Made of concrete and installed to the depth of the future
track level
 Two methods of installation used: Secant Pile Walls, Jet
Grout
 Machinery including drill rigs, grout tanks, diggers and other
equipment

12
Tunnel Drive Works

Secant pile wall : formed by
intersecting concrete piles
13

Jet grout wall : uses engineered
grout to form wall in situ
Jet Grout Headwalls

14
15
Grout Plant for Headwall Construction
Why a grout plant at Chaplin?
 Headwalls for Chaplin required
 Gilgorm adjacent to work site
 Gilgorm to remain open one lane northbound
 Allows efficient use of space
 Other options examined included Vesta Drive and Eglinton
 Gilgorm preferred because of:
reduced property impact
reduced footprint on Eglinton Ave.

16
Grout Plant at Chaplin

 The site will be situated on Metrolinxowned property and occupy City of
Toronto roadway
 A fence will enclose the site to
demarcate the site from the public
roadway throughout the entire works
 The plant will service headwall
construction for Chaplin Station and
cross-passages at Vesta Dr and
Castle Knock Road
 The site is expected to be in place
for approximately 8-10 months

17
Grout Plant at Chaplin
Advantages of jet grout
technique for headwall
installation:
Reduce requirement for
extensive utility relocation
Overall construction time
savings

18
Timeline

With appropriate permissions in place Metrolinx’ contractor will:
 Begin to set up the grout plant
 Install fencing and secure the perimeter
 Install grout lines in the roadway
 Test works
 Begin Chaplin headwall construction works
 Chaplin headwall construction is currently scheduled to
commence in March 2014
 8-10 months anticipated
 Headwall works at Avenue Road and Bathurst are currently
being reviewed
19
Chaplin Work Staging- South Setup
 Work is set up on the south side of Eglinton
 The work zone is separated from the ROW with concrete
barriers and fencing
 Unoccupied traffic lanes remain open on the north side of
Eglinton with one lane in each direction
 Through-traffic southbound on Chaplin at Eglinton will not
be permitted
 Southbound traffic must exit at Eglinton or choose an
alternate route
 Expected duration: Approximately 4 months
20
Chaplin Work Staging- North Setup

 A work site is set up on the north side of Eglinton
 The work zone is separated from the ROW with concrete
barriers and fencing
 Unoccupied traffic lanes remain open on the south side of
Eglinton with one lane in each direction
 Through-traffic northbound on Chaplin at Eglinton will not
be permitted
 Northbound traffic must exit at Eglinton or choose an
alternate route
 Expected duration: Approximately 4 months
 Latimer Avenue is closed to/from Eglinton during this phase
21
Chaplin Station
Plan View

22
Chaplin Station
Preliminary Station Concept

Looking West

23
Chaplin Station
Entrance Locations
Primary Entrance

Secondary Entrance

Secondary Entrance

24
Next Steps
 Community Relations will outreach to specific condos and
apartment buildings to raise awareness of the site and
planned works
 Co-ordination with TTC will continue to ensure continued
bus service
 Co-ordination with local Fire Station also continues to
ensure service levels

25
www.metrolinx.com

Thank you
26

Mais conteúdo relacionado

Mais procurados

Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Crosstown TO
 
Mount Pleasant Junior School Meeting May 5
Mount Pleasant Junior School Meeting May 5Mount Pleasant Junior School Meeting May 5
Mount Pleasant Junior School Meeting May 5Crosstown TO
 
Forest hill station open house
Forest hill station open house Forest hill station open house
Forest hill station open house Crosstown TO
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2Crosstown TO
 
Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Crosstown TO
 
Caledonia station open house
Caledonia station open houseCaledonia station open house
Caledonia station open houseCrosstown TO
 
Science Centre Station and West At-Grade Surface Stops Open House - November ...
Science Centre Station and West At-Grade Surface Stops Open House - November ...Science Centre Station and West At-Grade Surface Stops Open House - November ...
Science Centre Station and West At-Grade Surface Stops Open House - November ...Crosstown TO
 
Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015Crosstown TO
 
Mount Dennis Mobility Hub Update and Station Design Review
Mount Dennis Mobility Hub Update and Station Design ReviewMount Dennis Mobility Hub Update and Station Design Review
Mount Dennis Mobility Hub Update and Station Design ReviewCrosstown TO
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Crosstown TO
 
Laird Station Open House - April 2017
Laird Station Open House - April 2017Laird Station Open House - April 2017
Laird Station Open House - April 2017Crosstown TO
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Crosstown TO
 
Avenue station open house
Avenue station open house Avenue station open house
Avenue station open house Crosstown TO
 
Eglinton Station Open House
Eglinton Station Open HouseEglinton Station Open House
Eglinton Station Open HouseCrosstown TO
 
Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017Crosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Crosstown TO
 
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017Crosstown TO
 
404 presentation
404 presentation404 presentation
404 presentationaricsma
 
Stations Presentation - Corridor Wide
Stations Presentation - Corridor WideStations Presentation - Corridor Wide
Stations Presentation - Corridor WideCrosstown TO
 

Mais procurados (20)

Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017
 
Mount Pleasant Junior School Meeting May 5
Mount Pleasant Junior School Meeting May 5Mount Pleasant Junior School Meeting May 5
Mount Pleasant Junior School Meeting May 5
 
Forest hill station open house
Forest hill station open house Forest hill station open house
Forest hill station open house
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2
 
Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Leaside Station Open House - March 2017
Leaside Station Open House - March 2017
 
Caledonia station open house
Caledonia station open houseCaledonia station open house
Caledonia station open house
 
Science Centre Station and West At-Grade Surface Stops Open House - November ...
Science Centre Station and West At-Grade Surface Stops Open House - November ...Science Centre Station and West At-Grade Surface Stops Open House - November ...
Science Centre Station and West At-Grade Surface Stops Open House - November ...
 
Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015
 
Mount Dennis Mobility Hub Update and Station Design Review
Mount Dennis Mobility Hub Update and Station Design ReviewMount Dennis Mobility Hub Update and Station Design Review
Mount Dennis Mobility Hub Update and Station Design Review
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017
 
Laird Station Open House - April 2017
Laird Station Open House - April 2017Laird Station Open House - April 2017
Laird Station Open House - April 2017
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
 
Avenue station open house
Avenue station open house Avenue station open house
Avenue station open house
 
Eglinton Station Open House
Eglinton Station Open HouseEglinton Station Open House
Eglinton Station Open House
 
Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017
 
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
 
404 presentation
404 presentation404 presentation
404 presentation
 
Stations Presentation - Corridor Wide
Stations Presentation - Corridor WideStations Presentation - Corridor Wide
Stations Presentation - Corridor Wide
 

Semelhante a Chaplin Grout Plant and Headwall Construction Spring 2014

Eglinton Crosstown Leaside Open House Presentation
Eglinton Crosstown Leaside Open House PresentationEglinton Crosstown Leaside Open House Presentation
Eglinton Crosstown Leaside Open House PresentationCrosstown TO
 
Eglinton Crosstown Update
Eglinton Crosstown UpdateEglinton Crosstown Update
Eglinton Crosstown UpdateCrosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018Crosstown TO
 
West Open House - Progress Update Sept 2014
West Open House - Progress Update Sept 2014West Open House - Progress Update Sept 2014
West Open House - Progress Update Sept 2014Crosstown TO
 
Leaside open house sep 2014 Slides
Leaside open house sep 2014 SlidesLeaside open house sep 2014 Slides
Leaside open house sep 2014 SlidesCrosstown TO
 
Leaside open house sep 2014 slides
Leaside open house sep 2014   slidesLeaside open house sep 2014   slides
Leaside open house sep 2014 slidesCrosstown TO
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Crosstown TO
 
Proposed Leslie Street Closure Town Hall Meeting - April 2019
Proposed Leslie Street Closure Town Hall Meeting - April 2019Proposed Leslie Street Closure Town Hall Meeting - April 2019
Proposed Leslie Street Closure Town Hall Meeting - April 2019Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingCrosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingCrosstown TO
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...Crosstown TO
 
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018 Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018 Crosstown TO
 

Semelhante a Chaplin Grout Plant and Headwall Construction Spring 2014 (20)

Eglinton Crosstown Leaside Open House Presentation
Eglinton Crosstown Leaside Open House PresentationEglinton Crosstown Leaside Open House Presentation
Eglinton Crosstown Leaside Open House Presentation
 
Eglinton Crosstown Update
Eglinton Crosstown UpdateEglinton Crosstown Update
Eglinton Crosstown Update
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
 
West Open House - Progress Update Sept 2014
West Open House - Progress Update Sept 2014West Open House - Progress Update Sept 2014
West Open House - Progress Update Sept 2014
 
Leaside open house sep 2014 Slides
Leaside open house sep 2014 SlidesLeaside open house sep 2014 Slides
Leaside open house sep 2014 Slides
 
Leaside open house sep 2014 slides
Leaside open house sep 2014   slidesLeaside open house sep 2014   slides
Leaside open house sep 2014 slides
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
 
Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
 
Proposed Leslie Street Closure Town Hall Meeting - April 2019
Proposed Leslie Street Closure Town Hall Meeting - April 2019Proposed Leslie Street Closure Town Hall Meeting - April 2019
Proposed Leslie Street Closure Town Hall Meeting - April 2019
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
 
Eglinton Park
Eglinton ParkEglinton Park
Eglinton Park
 
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018 Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
 

Mais de Crosstown TO

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfCrosstown TO
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023Crosstown TO
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Crosstown TO
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfCrosstown TO
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCrosstown TO
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxCrosstown TO
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxCrosstown TO
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfCrosstown TO
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
 

Mais de Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 

Último

mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 

Último (20)

mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 

Chaplin Grout Plant and Headwall Construction Spring 2014

  • 1. Chaplin Grout Plant and Headwall Construction Spring 2014 Councillor Stintz Briefing February 3, 2014 Jamie Robinson Director, Communications and Community Relations Toronto Expansion Projects, Metrolinx 1
  • 2. Eglinton Crosstown LRT  Project  $4.9 B (2010$), funded by the Province of Ontario  19 kilometres east-west LRT from Kennedy to Jane/Black Creek, including 10 kilometers of tunnel  Connections to Yonge-University-Spadina Subway, Scarborough RT and GO Stouffville  Up to 26 stations 2
  • 4. Tunnelling Update  TBM 1 is well underway with tunnelling; just recently bored through our west headwall at Keele St.  TBM 2, a twin machine, has been assembled and is following closely behind 4
  • 5. Tunnel Drive Sequence 1. Construct Tunnel Launch Shaft 2. Construct Extraction Shaft 5
  • 6. Tunnel Drive Sequence Commence Mining Twin Tunnels Install Jet Grout Block “Headwalls” from Surface 6
  • 8. Tunnel Drive Sequence After Tunnel Contract: • Install Station Sidewall and Headwall Support of Excavation • Excavate Station and Commence Removing Concrete Tunnel Liners Finally: • Station Box Fully Excavated & Tunnel Lining Removed (Not shown) 8
  • 9. Launch Shaft Tunnel Boring Machine 9
  • 11. Tunnel Drive Works Current Status  In 2013 the majority of tunnel works took place between Black Creek Drive and the vicinity of Allen Road  In 2014 work continues east of Allen Road  Crews are starting the construction of headwalls and utility relocation at future station sites along Eglinton Avenue West 11
  • 12. Tunnel Drive Works  Headwalls: Temporary support walls for future excavation of the LRT stations.  Made of concrete and installed to the depth of the future track level  Two methods of installation used: Secant Pile Walls, Jet Grout  Machinery including drill rigs, grout tanks, diggers and other equipment 12
  • 13. Tunnel Drive Works Secant pile wall : formed by intersecting concrete piles 13 Jet grout wall : uses engineered grout to form wall in situ
  • 15. 15
  • 16. Grout Plant for Headwall Construction Why a grout plant at Chaplin?  Headwalls for Chaplin required  Gilgorm adjacent to work site  Gilgorm to remain open one lane northbound  Allows efficient use of space  Other options examined included Vesta Drive and Eglinton  Gilgorm preferred because of: reduced property impact reduced footprint on Eglinton Ave. 16
  • 17. Grout Plant at Chaplin  The site will be situated on Metrolinxowned property and occupy City of Toronto roadway  A fence will enclose the site to demarcate the site from the public roadway throughout the entire works  The plant will service headwall construction for Chaplin Station and cross-passages at Vesta Dr and Castle Knock Road  The site is expected to be in place for approximately 8-10 months 17
  • 18. Grout Plant at Chaplin Advantages of jet grout technique for headwall installation: Reduce requirement for extensive utility relocation Overall construction time savings 18
  • 19. Timeline With appropriate permissions in place Metrolinx’ contractor will:  Begin to set up the grout plant  Install fencing and secure the perimeter  Install grout lines in the roadway  Test works  Begin Chaplin headwall construction works  Chaplin headwall construction is currently scheduled to commence in March 2014  8-10 months anticipated  Headwall works at Avenue Road and Bathurst are currently being reviewed 19
  • 20. Chaplin Work Staging- South Setup  Work is set up on the south side of Eglinton  The work zone is separated from the ROW with concrete barriers and fencing  Unoccupied traffic lanes remain open on the north side of Eglinton with one lane in each direction  Through-traffic southbound on Chaplin at Eglinton will not be permitted  Southbound traffic must exit at Eglinton or choose an alternate route  Expected duration: Approximately 4 months 20
  • 21. Chaplin Work Staging- North Setup  A work site is set up on the north side of Eglinton  The work zone is separated from the ROW with concrete barriers and fencing  Unoccupied traffic lanes remain open on the south side of Eglinton with one lane in each direction  Through-traffic northbound on Chaplin at Eglinton will not be permitted  Northbound traffic must exit at Eglinton or choose an alternate route  Expected duration: Approximately 4 months  Latimer Avenue is closed to/from Eglinton during this phase 21
  • 23. Chaplin Station Preliminary Station Concept Looking West 23
  • 24. Chaplin Station Entrance Locations Primary Entrance Secondary Entrance Secondary Entrance 24
  • 25. Next Steps  Community Relations will outreach to specific condos and apartment buildings to raise awareness of the site and planned works  Co-ordination with TTC will continue to ensure continued bus service  Co-ordination with local Fire Station also continues to ensure service levels 25