3. CHAPLIN STATION UPDATE
3
Activity Location Approx. Date & Duration What to Expect
Dewatering System Tank
Delivery
Latimer Ave and Eglinton Ave
work zone and Shoppers
Drug Mart parking lot
Friday September 11, 2020 from
12:00 a.m. – 6:00 a.m.
• Noise from trucks, a crane and
lift
• Occupancy of the Shoppers
Drug Mart parking lot
Tertiary Entrance
Construction
Wall and staircase construction,
framing
South side of Eglinton Ave,
east of Chaplin Cres and
adjacent Toronto Fire Station
135
Underway into spring 2021 • Periodic early morning/late
night work
• Noise from construction
activity, including use of
cranes, trucks, and other heavy
equipment
Main Entrance Construction
Concrete and formwork
North side of Eglinton Ave
between Chaplin Cres and
Gilgorm Rd
Underway into spring 2021
Station Box Construction
Rebar, concrete and formwork
Beneath Eglinton Ave Underway into spring 2021
Secondary Entrance
Construction
Pile installation
Southwest corner of Chaplin
Cres and Eglinton Ave
Underway into mid-September
2020
• Noise from a drill and trucks
9. AVENUE STATION UPDATE
9INSERT FOOTER
Activity Location Approx. Date & Duration What to Expect
Final lining (waterproofing,
rebar installation, and
mechanical electrical works)
Throughout all station areas Underway through to late-2020
• Deliveries at the main and
secondary entrances
Concrete Pours
Between the Main and Secondary
Entrances
Three times per week for approx.
12 – 18 hours through to 2021
• Concrete truck activity
• Occupation of the westbound
curb lane during some pours
Eglinton Connects
Streetscape and Cycle Track
Eglinton Ave between Lascelles
Blvd and Duplex Ave
Underway through to early 2021
Works on the north side of Eglinton
Ave will be extended west to
Lascelles Blvd as early as Sept 14,
2020
• Eglinton reduced to one lane
in each direction between
Lascelles Blvd & Duplex Ave
• Use of excavator, hydro-vac
and concrete trucks
Dewatering Well
Maintenance
Eglinton Ave between Braemar Ave
and Lascelles Blvd
Periodically through 2021; 9:00
a.m. – 4:00 p.m.
• Road occupancy around well
• Use of hydro-vac truck
Monitoring Work
Eglinton Ave between Braemar Ave
and Lascelles Blvd
Periodically through 2021 • Short-term road occupancy
11. EGLINTON CONNECTS – SCOPE OF WORK
11
• CTS will implement Eglinton Connects within immediate station areas and continuously
between Avenue Road and Holly Street
• Implementation of Eglinton Connects began July 7, 2020 on the north side of Eglinton Ave,
between Edith Drive and Duplex Ave
• As early as September 14, 2020, Eglinton Connects construction will extend west to
Lascelles Blvd
INSERT FOOTER
The scope of work includes:
✓ Widened sidewalks
✓ Separated cycle tracks
✓ On-street parking
✓ Full restoration of the roadway, curbs and sidewalks along Eglinton Ave
✓ Increased greenery and street furnishings
✓ Reduced traffic lanes (to accommodate wider sidewalks and cycle tracks)
12. EGLINTON CONNECTS
CURRENT TRAFFIC CONFIGURATION: EDITH DRIVE TO DUPLEX AVE
12INSERT FOOTER
Expected to remain in place through September 14, 2020
16. EGLINTON CONNECTS CONSTRUCTION OVERVIEW
16
Construction of the new Eglinton Streetscape and Cycle Track between Lascelles Blvd and Duplex Ave will
continue into 2021.
The Eglinton Connects Streetscape and Cycle Track is being constructed in coordination with the City of
Toronto’s Streetscape and Cycle Track Design.
Construction Hours:
• Monday – Saturday, 7:00 a.m. – 7:00 p.m. with periodic overnight work
Construction Activities:
• Excavation
• Utility Reinstatement
• Concrete Work
• Compaction and Paving
• Landscaping – installation of street furnishings, light poles, trees etc.
To accommodate this work, all street furnishings, bus shelters, and trees between Lascelles Blvd and Duplex Ave will be
removed. Notice will be provided in advance of removals.
Upon completion of Eglinton Connects, additional street furnishings and trees will be installed/planted along Eglinton Ave.