Mitigation and Performance
Recovery Using Earned Value
Patrick M. Kelly, PSP
• Degree:
   – B.S. Ocean Engineering (1996)
• University:
   – US Naval Academy
• Years of Experience:
   – 11 (incl. Civil Engineer Corps)
• Professional Field:
   – Contracting, Project Manager, Project Controls Manager (Scheduling,
     Claims & Disputes Resolution). Managed aviation, industrial, commercial,
     infrastructure and critical structures assignments, and other projects nationwide, providing
     construction and contract management, schedule analysis, impact analysis, cost evaluation,
     entitlement analysis, and other claims and dispute resolution services.

• Something you do not know about me:
   – Patrick doesn’t like to reveal too much about himself
Chris Carson, PSP, PMP, CCM
• Corporate Director of Project Controls, Alpha Corporation
    –   Responsible for standards, processes, and procedures for a team of schedulers, analysts,
        and project managers in multiple office locations
    –   Provided seminars for hundreds of scheduling professionals in CPM scheduling
        methodologies, and manages the in-house training program at Alpha
• Certifications: PSP, CCM (Certified Construction Manager - CMAA), PMP (Project
   Management Professional - PMI)
• University: University of Virginia, Mechanical Engineering, 1972
• Professional Field: 37 years of experience in Construction Management, CM Services
   especially Scheduling, Estimating, Claims
• Active in AACEi
    –   Co-Author for “Identifying the Critical Path” RP, author for “Recovery Scheduling” RP
    –   Co-author for “Schedule Design” RP, currently underway, participating author for “Forensic
        Schedule Analysis” RP
• Active in PMI College of Scheduling
    –   Managing Director for Scheduling Excellence writing “Best Practices and Guidelines for
        Scheduling” and “Best Practices and Guidelines for Schedule Impact Analysis”
• Active in CMAA (Construction Management Association of America)
    –   Served on 9 person committee revising the Time Management Chapter of the CMAA’s CM
        Standards of Practice
• Something you do not know about me:
    –   I am a proud grandfather of two girls and a boy
    –   I was given an award for “Significant Contributions to the Scheduling Industry” at the 2009
        CoS national conference

                                                                                                      3
Overview
Overview
• This paper discusses the practical use of Earned Value
  metrics and calculations in monitoring and controlling
  schedule slippage, and, more importantly, in identifying
  appropriate mitigation plans to regain time.
• Earned Value Management can be used to:
   – Identify the specific trades or scopes of work that are contributing to
     poor performance.
   – Fashion an appropriate isolated and detailed mitigation strategy to
     provide steps for the improved performance necessary.
• This presentation provides an innovative look, from an
  Earned Value perspective, at the needs within the
  schedule database to support schedule compression.
• The program illustrated will provide a process and
  graphical displays to define and promote more practical
  steps to aid mitigation than just reporting on EV metrics.
Introduction
Brief Background on EVMS
• Earned Value Management began as a set of
  35 Cost/Schedule Control Systems Criteria
  (C/SCSC) imposed by the DoD on industrial
  firms wishing to do business in a cost-
  reimbursable or incentive contract.
• EVM subsequently has grown beyond the
  factory floor and become an important
  supplementary analysis tool to the use of
  Critical Path Method scheduling in
  construction applications.
Brief Background on EVMS
• The CPM schedule, as the primary project
  management tool on the construction project,
  will measure the contractor’s progress
  against his baseline plan.
  – CPM schedule is used to generate the baseline Budgeted Cost of
    Work Scheduled (BCWS) Curve, which will form the basis of EVM
    analysis throughout the project.
  – Use of EVM metrics provides additional understanding of the
    project’s health by adding texture to the analyst’s understanding
    of:
     • Critical Path delay
     • Non-Critical Path slippage and float erosion
     • Performance in particular areas of work or in particular
       trades.
Schedule Compression
• Projects sometimes slip behind schedule,
  and the late predicted completion date can be
  unacceptable or unsustainable to the parties
  to the contract.
  – This paper does not discuss cause or compensability of the
    slippages, delays, or mitigation actions.
  – Regardless of who is paying, the EVM metrics can aid the
    scheduler in determining a successful mitigation strategy.

• Common causes of slippage:
  –   Design Clarity
  –   Planning Efforts
  –   Project Management & Production
  –   Change Management
Key EVM Metrics
      Schedule Analysis and Forecasting                  Cost Analysis and Forecasting
Schedule Variance (Are we ahead or behind Cost Variance (Are we under or over budget?)
schedule?)
                 SV = EV - PV
                                                                 CV = EV - AC

Schedule Performance Index (How efficiently are Cost Performance Index (How efficiently are we
we using time?)                                 using our resources?)


                SPI = EV / PV                                    CPI = EV / AC


Time Performance Ratio (What are the effects of To-Complete Performance Index (How efficiently
slippage issues on activity duration?)          must we use our remaining resources?)


                TPR = AD / OD                           TCPI = (BAC – EV) / (BAC – AC)


              -From PMI’s Practice Standard for Earned Value Management
Key EVM Metrics
• Each of these metrics has the ability to guide
  a schedule analyst, during the schedule
  compression process, by highlighting
  specific areas of slippage, or by highlighting
  specific areas of success upon which the
  contractor should capitalize.
Prerequisites and Preparatory Steps
Prerequisites
• It is essential that the scheduling process, from
  baseline schedule generation through the schedule
  updating and monitoring processes, be geared at
  the outset to record information in such a way that
  will facilitate simple EVM analysis.
• By starting with this end in mind, the scheduler will
  have at his disposal quick and easy access to the
  EVM metrics which will supplement his
  understanding of the CPM schedule, and therefore
  also his ability to revise and compress the schedule
  when the need arises.
Preparatory Steps - Baseline
• Baseline schedule is fully designed and developed,
  and captures the complete scope of work.
• Baseline schedule is properly cost and resource
  loaded with accurate information.
  – Schedule-based EVM metrics are available and useful, but the full value
    of EVM only becomes apparent when one can use the metrics generated
    by cost and resource loading.
  – Schedule Analysis and Forecasting:
      • Schedule Variance
      • Schedule Performance Index
      • Time Performance Ratio
  – Cost Analysis and Forecasting:
      • Cost Variance
      • Cost Performance Index
      • To-Complete Performance Index
Preparatory Steps - Baseline
• Detailed use of Activity Codes
  – Codes will create a schedule database that can be exported and
    manipulated in a spreadsheet later on.
  – Detailed use of Activity Coding of the baseline schedule will allow the
    creation of a BCWS Curve not only for the overall project, but also for
    each of the trades represented by a Responsibility Activity Code.

• Creation of the BCWS Curve
  – Can be generated within the schedule software.
  – Can be generated within a spreadsheet.
  – Curves can be generated on a per-trade basis if Activity Coding is
    sufficient.
  – Curves form the basis of EVM analysis during the updating process.
• What happens when there is no resource loading?
  – Still possible to run EVM metrics
      • Analyst loads crews, manpower, duration days, uses other metrics
Preparatory Steps - Updates
• Typical update preparation and maintenance rules
  apply.
• Additionally, it is important to create additional
  Activity Codes which will allow for simple collation
  and analysis of activity-specific EV data, once the
  schedule database is exported to a spreadsheet.
• Continuous coding of activities to track which
  trades, types of work, areas of work, etc., are
  impacted by known issues will allow the schedule
  analyst to make more effective recommendations
  regarding schedule compression.
Preparatory Steps - Updates
• Design and Contract Drawing Clarity:
  – In updates, it is important to code activities with an “impact” code which
    relates specific RFI’s to this activity.
  – The code should be supplemented by specific information in the
    activity’s log notes or notebook entry; however, the Activity Code is
    essential for quick and effective EVM analysis within spreadsheets.
  – Log notes must record delays to the start of an activity due to Design
    Clarity issues, as represented by an RFI or other appropriate record
    documentation, and should also track the start and finish date of RFI
    review.
      • If an in-progress activity is affected by a Design Clarity issue, the scheduler should
        consider the use of the Suspend-Resume function to show the break in progress.
      • Use of this function will also ensure that the activity’s Actual Duration is only
        reflective of the contractor’s progress, so that progress-related delays are clearly
        separated from Design Clarity issues.
  – Should RFI’s or other Design Clarity issues result in changes to the
    design, the scheduler must appropriately account for the changes in the
    network, to include alterations to activities, durations, logic, cost
    loading, and the BCWS curve. This will ensure a fair comparison of the
    EV to the PV as the project progresses.
Preparatory Steps - Updates
• Project Management and Production:
  – Proper coding within the baseline schedule should allow for the
    generation of trade-specific EVM metrics.
  – PM staff should:
      • Continually create impact codes and log notes to represent
        occasions where particular subcontractors have fallen short of
        expectations in some way.
      • Code and note any occasion where project progress was delayed
        or disrupted by the action or inaction of the owner, or by third-party
        delays.
  – Assiduous attention to detail in this regard will allow the analyst to
    separate out those trends which are representative of poor contractor
    performance from those which were representative of impacts external
    to the contractor.
      • Document start delays and production delays in log notes
      • Use Suspend / Resume
Prerequisites and Preparatory Steps
• Goal is to create a detailed database of uniformly
  coded information which will yield quick and
  accurate trending information that can be filtered on
  a by-trade or other basis, in order to guide the
  scheduler in development of a compressed
  schedule.
EVM in Schedule Compression
EVM in Schedule Compression
• Crashing. A schedule compression technique in which cost and
  schedule tradeoffs are analyzed to determine how to obtain the
  greatest amount of compression for the least incremental cost.
  Examples of crashing could include approving overtime, bringing in
  additional resources, or paying to expedite delivery to activities on
  the critical path. Crashing only works for activities where additional
  resources will shorten the duration. Crashing does not always
  produce a viable alternative and may result in increased risk and/or
  cost.
• Fast tracking. A schedule compression technique in which
  phases or activities normally performed in sequence are performed
  in parallel. An example is constructing the foundation for a building
  before completing all of the architectural drawings. Fast tracking
  may result in rework and increased risk. Fast tracking only works if
  activities can be overlapped to shorten the duration.
                              -From PMI’s Body of Knowledge, Fourth Edition
EVM in Schedule Compression
• Whether the schedule is to be crashed or fast-
  tracked, it is essential that the scheduler understand
  the following:
  – Which trades are not performing up to expectations or contractual
    obligations, and will therefore require additional resources or project
    management attention in order to meet or exceed current production
    goals?
  – Which trades are exceeding expectations or contractual obligations, and
    will therefore likely exceed current production goals?
  – Delay and responsibility for delay will require CPM analysis, not only
    EVMS – this is a trending tool that can be used to point out specific
    trends among trade contractors that will likely affect progress
EVM in Schedule Compression
• By exporting the schedule database to a spreadsheet,
  the scheduler can examine the historical data to gain an
  understanding of the performance of each trade.
• At a minimum, the scheduler should export the following
  data fields from the schedule database into a
  spreadsheet:
            Activity ID                 Budgeted cost
        Activity description              Actual cost
         Original duration          Cost Percent Complete
          Actual duration                    Phase
         Percent complete                  Work Area
             Early start                  CSI Division
            Early finish                 Type of Work
            Actual start         Responsibility/Subcontractor
           Actual finish                  Issue Codes
                                           Resources
EVM in Schedule Compression
     Export or copy trending data into table in
     preparation for pivot tables or charts
                                                   2005                                                     2006
                       May     Jun     Jul     Aug     Sep     Oct    Nov      Dec     Jan     Feb     Mar   Apr       May     Jun     Jul
Percent Complete      23.00   27.30   32.50   37.40   40.80   44.50           50.20   53.00   59.00   63.00 73.00     79.00   85.00   89.00
Critical Activities    189     141     596     713     705     756                     12      170     454    11       200      36     82
LP Activities                          171     107     191     142            519       6               6     6        26       25     22
Logic Changes         3,151   209      153     286     695     134            771     3,505    57      194   526       69       78     78
Out of sequence                                                                                                                        69
Number of
                      2,287   2,289   2,285   2,313   2,317   2,326                   2,776   2,777   2,780   2,807   2,808   2,812   2,816
Activities
In Progress           54      44       54     47      46       49                     67        75      84      76     92      121     107
Complete              212     249     304     372     454     535                     855     1,044   1,280   1,601   1,850   2,007   2,208
Missed ES             32      35       25     23      18       25                     24        30      28      29     44       37      25
Missed EF             27      26       25     37      29       39                     59        47      60      38     78       82     101
Missed Both           33      38       45     65      76      102                     114      115     244     191     292     396     377
Early ES                                                                                                15      12      8        5      0
Early EF                                                                                                 7      13     13        4      3
Early Both                                                                                               0      31      8        2      1
Project TPR           2.18     3.09   1.77     1.64   1.57     3.01    2.12    3.42   3.30     1.97    2.19    2.95   1.96     2.53    2.52
BCW S ($M)            15.89   25.11   34.66   40.00   41.48   48.64   53.79   57.30           67.67           75.00   80.62   83.33   93.09
BCW P ($M)            8.90    22.10   30.50   36.40   36.50   42.80   46.80   51.00   56.40   60.90   60.70   72.00   78.20   82.50   82.37
ACW P ($M)             4.6    17.40   27.70   27.70   37.20   38.30   43.40   45.90   52.20   55.20   60.40   70.00   76.5    80.60   81.75
CPI                   1.90     1.37   1.22     1.11   0.98     1.12    1.08    1.11   1.08     1.10    1.00    1.03   1.02     1.02    1.01
SPI                   0.56     0.88   0.88     0.91   0.88     0.88    0.87    0.89   0.70     0.90            0.96   0.97     0.99    0.88




                                                                                                                                        24
EVM in Schedule Compression
• Generate Time Performance Ratio and collate data
  within a Pivot Table.                  Milestone   HB     HBRC    HRU     JCD    WCE    WM
                                                                                                 Grand
                                                                                                 Total
                                             1       0.78    3.00   30.00   1.00   2.30           4.49
                                             3       1.77           10.75                         8.51
             Type of Work        TPR         4       1.67           1.00    0.83                  1.03
      Backfill                    2.66       5       5.83                   0.50          1.00    2.33
      Concrete                    2.15      70       0.86   1.00                   1.00           0.99
      Dredging                    2.35      90                      1.00                          1.00
      Electrical                  1.52      7A       8.40   0.15    1.20    1.45                  1.87
                                            7B       3.96   0.05    1.40                          2.67
      Excavation/Backfill Work    3.25      7C       2.01   0.05    1.33                          1.48
      Signing/Marking             5.00      7D       4.27           0.78                          2.52
      Precast Concrete            3.60      7E       2.55                                         2.55
      Pile                        3.19      8A       5.60                                         5.60
      Sheet Pile                  2.66      8B       4.19                                         4.19
                                            9A                      2.70    1.71                  2.32
      Sewer Service               0.33      9B                              1.01                  1.01
      Water Line                  2.12    Grand
      Misc. Steel                 5.30    Total      3.55   0.97    2.84    1.23   1.26   1.00   1.84
      Crane Rail                  9.13
EVM in Schedule Compression
• Additional EVM metrics can be created by creating
  pivot graphs of cumulative EV data over time, as
  represented in the schedule database.
  – By filtering the EV data by each of the trade codes, and plotting the
    cumulative data by month, the EV data for each trade can be compared
    to the BCWS Curves generated from the baseline schedule.
  – From these curve comparisons, SV, CV, SPI, CPI, and TCPI can be
    generated for each trade.
• Causes of the slippage within a particular
  subcontractor’s work will have to be determined
  through examination of project documentation and
  interviews with the project staff.
EVM in Schedule Compression
  Separating Earned Value curves by trade or location
  will show very different results from project average
  Earned Value metrics



HVAC
                Improvements           Problems




ELEC                               Consistent Time Problems




                                                              27
EVM in Schedule Compression
• Recovery concepts
  – Determine slope of EV curve necessary to recover to end of project or milestone
  – Graphically
      • Produce trade specific EVMS curves
      • Identify increased production curve from current time period to end of
        project
      • Convert production curve to shortened durations
      • Verify ability of trade contractor to supply resources produce durations




                                                                                   28
EVM in Schedule Compression
• Determine production slope for recovery
• Use proportions to adjust remaining durations of trade
          Cost Or Quantity
                                                                 Time
             Compressed EAC          Increased Costs from        Overrun
                                             Compression
                      EAC
                                                                               Cost
                      BAC                                                      Overrun


                                              Time
 • Check history                              Variance      Production Slope
                                                            Required to Meet
 • Verify ability to                            AC          Deadline
   provide resources
                                    BCWS
                                    (PV)
                                             EV

                       0
                            Start                  DD       Completion
                                                                           Time
                                                                                         29
EVM in Schedule Compression
• In identifying underperforming trades, the scheduler
  must investigate further to determine why this
  particular trade was underperforming:
  – Did it provide sufficient resources?
  – Did the observed resources match planned resources?
  – Were Man-Days or Crew-Days spent inefficiently?
• However, the comparison of each trade’s PV to it’s
  EV will focus the scheduler’s attention on that trade,
  and will prevent the scheduler from creating a
  mitigation strategy that relies upon subcontractors
  that have demonstrated an inability to meet their
  commitments in the baseline schedule.
EVMS in Schedule Compression
                                       700

Run resource profile comparisons                  Sum of Planned Man Power   Sum of Actual Man Power
To show failure to meet planned        600

levels of manpower
                                       500

This frames the discussion for any
trade contractors that have not met    400

plan, but need to ramp up for
schedule mitigation                    300



This also allows the discussion of     200
whether the under-manning can be
overcome with the trade contractor
                                       100
for the purposes of mitigation or if
another contractor is needed
                                         0
                                             Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

                                                2001                                    2002




                                                                                                           31
Resource Analysis
Review individual trade or responsibility – check for
predicted overload in the trade work – by crew, by location




                                                              32
EVM in Schedule Compression
• As the mitigation strategy is implemented within the
  CPM schedule, the schedule analyst must run
  resource curves to determine if more resources are
  needed.
• When analyzing the new resource curves, the
  analyst should ask the following questions for each
  trade:
  – Does the new resource level exceed that which was previously agreed
    upon with the subcontractor?
  – Can the subcontractor provide the new level of resources, and who will
    bear the burden of the cost of the increased resources?
  – If not, can the prime contractor hire additional subcontractors for this
    trade in order to achieve the increased level of production necessary to
    compress the schedule?
EVM in Schedule Compression
• In order to analyze resources, run a Resource Table.
  – Load activities with Crews if the schedule is not resource loaded, and
    then create a resource table.
  – Such a table will visually demonstrate where there may be conflicts with
    the numbers of crews for each trade. This is a source for slippage
    which should be discussed with the contractors.
EVMS in Schedule Compression
• Excellent paper – Al Kuhn, PSP
   – use when no resource loading in schedule
   – Allows crew loading & analysis




                                                35
Resource Analysis with EV
Set up Crew Resources – Use them to check maximum
available limits




                                                    36
Conclusion
Conclusion
• Trends shown in the EVM metrics can be applied in selecting
  areas for compression, highlighting the need for additional
  resources, and checking the realism of a newly developed
  compressed schedule, prior to implementation.
• The scheduler will have the ability to provide accurate and
  useful recommendations to the project management staff in
  support of mitigation and recovery efforts.
• The use of a good, trade specific Earned Value Management
  System will provide useful data for use in mitigation efforts as
  long as there is a mitigation strategy in place and a
  monitoring system that will provide good, reliable metrics on
  a periodic basis.
• Those metrics must be maintained, analyzed, and used in the
  mitigation plan to guide the trade contractors as necessary to
  fulfill the needs for recovery.
Conclusion
• This process will also provide early warning of problem trade
  contractors in advance of the need to mitigate, and when the
  need arises, the process will lay out guidelines for mitigation,
  as well as provide the appropriate documentation to
  encourage and legally support the need for specific trade
  contractor mitigation.
• With proper use of this system, it is also possible to minimize
  loss of productivity claims by periodic monitoring of the
  slippage in work, assessing responsibility, and predicting the
  remaining required production rates, as well as resource
  requirements, that are necessary to complete on time.
Mitigation and Performance
  Recovery Using Earned Value

                           Questions?
    Chris Carson, PSP, PMP, CCM                Patrick M. Kelly, PSP
Corporate Director of Project Controls      Project Controls Manager

  Chris.Carson@alphacorporation.com      Patrick.Kelly@alphacorporation.com
  (O) 757-533-9368  (M) 757-342-5524     (O) 757-533-9368   (M) 757-217-6820
41

Mais conteúdo relacionado

Mais procurados

Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Charlie Jackson
 
Schedule levels-as-presented 02-may11
Schedule levels-as-presented  02-may11Schedule levels-as-presented  02-may11
Schedule levels-as-presented 02-may11
PMA Consultants
 

Mais procurados (20)

VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery Scheduling
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
 
Schedule levels-as-presented 02-may11
Schedule levels-as-presented  02-may11Schedule levels-as-presented  02-may11
Schedule levels-as-presented 02-may11
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
 
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
 

Destaque

Teeth&the slumber party massacre
Teeth&the slumber party massacreTeeth&the slumber party massacre
Teeth&the slumber party massacre
boogedy
 
Different types of glasses
Different types of glassesDifferent types of glasses
Different types of glasses
Krishna Sahit
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
Rahul Dubey
 

Destaque (20)

Baseline Schedules 1
Baseline Schedules 1Baseline Schedules 1
Baseline Schedules 1
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan Presentation
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual Schedules
 
Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop Conference
 
Teeth&the slumber party massacre
Teeth&the slumber party massacreTeeth&the slumber party massacre
Teeth&the slumber party massacre
 
Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls Pp
 
استحالة تحريف الكتاب المقدس
استحالة تحريف الكتاب المقدساستحالة تحريف الكتاب المقدس
استحالة تحريف الكتاب المقدس
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule Types
 
طقس خدمة القداس الإلهى
طقس خدمة القداس الإلهىطقس خدمة القداس الإلهى
طقس خدمة القداس الإلهى
 
ملابس الكهنوت (Final)
ملابس الكهنوت (Final)ملابس الكهنوت (Final)
ملابس الكهنوت (Final)
 
شرح القداس الألهى
شرح القداس الألهىشرح القداس الألهى
شرح القداس الألهى
 
Bdsm intro
Bdsm introBdsm intro
Bdsm intro
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
 
Different types of glasses
Different types of glassesDifferent types of glasses
Different types of glasses
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Stanford presentation - Intro to BDSM
Stanford presentation - Intro to BDSMStanford presentation - Intro to BDSM
Stanford presentation - Intro to BDSM
 
SEXUAL OFFENCES
SEXUAL OFFENCESSEXUAL OFFENCES
SEXUAL OFFENCES
 

Semelhante a Schedule Recovery Using Earned Value

Resume_McColgin_Quentin_Master_Scheduling
Resume_McColgin_Quentin_Master_SchedulingResume_McColgin_Quentin_Master_Scheduling
Resume_McColgin_Quentin_Master_Scheduling
Quentin McColgin
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptx
ssusercf695b
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.gary
NASAPMC
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.gary
NASAPMC
 
Bridging the cost schedule divide - integrating primavera and cost systems ppt
Bridging the cost schedule divide - integrating primavera and cost systems pptBridging the cost schedule divide - integrating primavera and cost systems ppt
Bridging the cost schedule divide - integrating primavera and cost systems ppt
p6academy
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
Glen Alleman
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
Shraddha PMP
 
Lecture 8 (software Metrics) Unit 3.pptx
Lecture 8 (software Metrics) Unit 3.pptxLecture 8 (software Metrics) Unit 3.pptx
Lecture 8 (software Metrics) Unit 3.pptx
ironman427662
 

Semelhante a Schedule Recovery Using Earned Value (20)

Using Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project PerformanceUsing Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project Performance
 
Intergrated baseline reviews as a tool in assurance
Intergrated baseline reviews as a tool in assurance Intergrated baseline reviews as a tool in assurance
Intergrated baseline reviews as a tool in assurance
 
MandC.pdf
MandC.pdfMandC.pdf
MandC.pdf
 
Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018
 
Resume_McColgin_Quentin_Master_Scheduling
Resume_McColgin_Quentin_Master_SchedulingResume_McColgin_Quentin_Master_Scheduling
Resume_McColgin_Quentin_Master_Scheduling
 
Notional cam interview questions (update)
Notional cam interview questions (update)Notional cam interview questions (update)
Notional cam interview questions (update)
 
Project control and process instrumentation
Project control and process instrumentationProject control and process instrumentation
Project control and process instrumentation
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptx
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.gary
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.gary
 
An introduction to an effective earned value management system (EVMS) webinar...
An introduction to an effective earned value management system (EVMS) webinar...An introduction to an effective earned value management system (EVMS) webinar...
An introduction to an effective earned value management system (EVMS) webinar...
 
Bridging the cost schedule divide - integrating primavera and cost systems ppt
Bridging the cost schedule divide - integrating primavera and cost systems pptBridging the cost schedule divide - integrating primavera and cost systems ppt
Bridging the cost schedule divide - integrating primavera and cost systems ppt
 
ERP II Overview.ppt
ERP II Overview.pptERP II Overview.ppt
ERP II Overview.ppt
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
 
Delivering nothing efficiently
Delivering nothing efficientlyDelivering nothing efficiently
Delivering nothing efficiently
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
Lecture 8 (software Metrics) Unit 3.pptx
Lecture 8 (software Metrics) Unit 3.pptxLecture 8 (software Metrics) Unit 3.pptx
Lecture 8 (software Metrics) Unit 3.pptx
 
LINE OF BALANACE
LINE OF BALANACELINE OF BALANACE
LINE OF BALANACE
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
T24 Temenos Earned Value Management & Project Planning Presentation
T24 Temenos Earned Value Management & Project Planning PresentationT24 Temenos Earned Value Management & Project Planning Presentation
T24 Temenos Earned Value Management & Project Planning Presentation
 

Mais de Chris Carson

Mais de Chris Carson (19)

Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation Schedules
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry Scheduling
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis Method
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion Schedules
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does Not
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract Admin
 
Claims Triage
Claims TriageClaims Triage
Claims Triage
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
 
Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel Schedules
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful Mediation
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex Project
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - Airport
 
Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse Weather
 
Testimony Mistakes
Testimony MistakesTestimony Mistakes
Testimony Mistakes
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
Subcontractor Scheduling
Subcontractor SchedulingSubcontractor Scheduling
Subcontractor Scheduling
 
Schedule Design PMI
Schedule Design PMISchedule Design PMI
Schedule Design PMI
 
DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.
 

Schedule Recovery Using Earned Value

  • 2. Patrick M. Kelly, PSP • Degree: – B.S. Ocean Engineering (1996) • University: – US Naval Academy • Years of Experience: – 11 (incl. Civil Engineer Corps) • Professional Field: – Contracting, Project Manager, Project Controls Manager (Scheduling, Claims & Disputes Resolution). Managed aviation, industrial, commercial, infrastructure and critical structures assignments, and other projects nationwide, providing construction and contract management, schedule analysis, impact analysis, cost evaluation, entitlement analysis, and other claims and dispute resolution services. • Something you do not know about me: – Patrick doesn’t like to reveal too much about himself
  • 3. Chris Carson, PSP, PMP, CCM • Corporate Director of Project Controls, Alpha Corporation – Responsible for standards, processes, and procedures for a team of schedulers, analysts, and project managers in multiple office locations – Provided seminars for hundreds of scheduling professionals in CPM scheduling methodologies, and manages the in-house training program at Alpha • Certifications: PSP, CCM (Certified Construction Manager - CMAA), PMP (Project Management Professional - PMI) • University: University of Virginia, Mechanical Engineering, 1972 • Professional Field: 37 years of experience in Construction Management, CM Services especially Scheduling, Estimating, Claims • Active in AACEi – Co-Author for “Identifying the Critical Path” RP, author for “Recovery Scheduling” RP – Co-author for “Schedule Design” RP, currently underway, participating author for “Forensic Schedule Analysis” RP • Active in PMI College of Scheduling – Managing Director for Scheduling Excellence writing “Best Practices and Guidelines for Scheduling” and “Best Practices and Guidelines for Schedule Impact Analysis” • Active in CMAA (Construction Management Association of America) – Served on 9 person committee revising the Time Management Chapter of the CMAA’s CM Standards of Practice • Something you do not know about me: – I am a proud grandfather of two girls and a boy – I was given an award for “Significant Contributions to the Scheduling Industry” at the 2009 CoS national conference 3
  • 5. Overview • This paper discusses the practical use of Earned Value metrics and calculations in monitoring and controlling schedule slippage, and, more importantly, in identifying appropriate mitigation plans to regain time. • Earned Value Management can be used to: – Identify the specific trades or scopes of work that are contributing to poor performance. – Fashion an appropriate isolated and detailed mitigation strategy to provide steps for the improved performance necessary. • This presentation provides an innovative look, from an Earned Value perspective, at the needs within the schedule database to support schedule compression. • The program illustrated will provide a process and graphical displays to define and promote more practical steps to aid mitigation than just reporting on EV metrics.
  • 7. Brief Background on EVMS • Earned Value Management began as a set of 35 Cost/Schedule Control Systems Criteria (C/SCSC) imposed by the DoD on industrial firms wishing to do business in a cost- reimbursable or incentive contract. • EVM subsequently has grown beyond the factory floor and become an important supplementary analysis tool to the use of Critical Path Method scheduling in construction applications.
  • 8. Brief Background on EVMS • The CPM schedule, as the primary project management tool on the construction project, will measure the contractor’s progress against his baseline plan. – CPM schedule is used to generate the baseline Budgeted Cost of Work Scheduled (BCWS) Curve, which will form the basis of EVM analysis throughout the project. – Use of EVM metrics provides additional understanding of the project’s health by adding texture to the analyst’s understanding of: • Critical Path delay • Non-Critical Path slippage and float erosion • Performance in particular areas of work or in particular trades.
  • 9. Schedule Compression • Projects sometimes slip behind schedule, and the late predicted completion date can be unacceptable or unsustainable to the parties to the contract. – This paper does not discuss cause or compensability of the slippages, delays, or mitigation actions. – Regardless of who is paying, the EVM metrics can aid the scheduler in determining a successful mitigation strategy. • Common causes of slippage: – Design Clarity – Planning Efforts – Project Management & Production – Change Management
  • 10. Key EVM Metrics Schedule Analysis and Forecasting Cost Analysis and Forecasting Schedule Variance (Are we ahead or behind Cost Variance (Are we under or over budget?) schedule?) SV = EV - PV CV = EV - AC Schedule Performance Index (How efficiently are Cost Performance Index (How efficiently are we we using time?) using our resources?) SPI = EV / PV CPI = EV / AC Time Performance Ratio (What are the effects of To-Complete Performance Index (How efficiently slippage issues on activity duration?) must we use our remaining resources?) TPR = AD / OD TCPI = (BAC – EV) / (BAC – AC) -From PMI’s Practice Standard for Earned Value Management
  • 11. Key EVM Metrics • Each of these metrics has the ability to guide a schedule analyst, during the schedule compression process, by highlighting specific areas of slippage, or by highlighting specific areas of success upon which the contractor should capitalize.
  • 13. Prerequisites • It is essential that the scheduling process, from baseline schedule generation through the schedule updating and monitoring processes, be geared at the outset to record information in such a way that will facilitate simple EVM analysis. • By starting with this end in mind, the scheduler will have at his disposal quick and easy access to the EVM metrics which will supplement his understanding of the CPM schedule, and therefore also his ability to revise and compress the schedule when the need arises.
  • 14. Preparatory Steps - Baseline • Baseline schedule is fully designed and developed, and captures the complete scope of work. • Baseline schedule is properly cost and resource loaded with accurate information. – Schedule-based EVM metrics are available and useful, but the full value of EVM only becomes apparent when one can use the metrics generated by cost and resource loading. – Schedule Analysis and Forecasting: • Schedule Variance • Schedule Performance Index • Time Performance Ratio – Cost Analysis and Forecasting: • Cost Variance • Cost Performance Index • To-Complete Performance Index
  • 15. Preparatory Steps - Baseline • Detailed use of Activity Codes – Codes will create a schedule database that can be exported and manipulated in a spreadsheet later on. – Detailed use of Activity Coding of the baseline schedule will allow the creation of a BCWS Curve not only for the overall project, but also for each of the trades represented by a Responsibility Activity Code. • Creation of the BCWS Curve – Can be generated within the schedule software. – Can be generated within a spreadsheet. – Curves can be generated on a per-trade basis if Activity Coding is sufficient. – Curves form the basis of EVM analysis during the updating process. • What happens when there is no resource loading? – Still possible to run EVM metrics • Analyst loads crews, manpower, duration days, uses other metrics
  • 16. Preparatory Steps - Updates • Typical update preparation and maintenance rules apply. • Additionally, it is important to create additional Activity Codes which will allow for simple collation and analysis of activity-specific EV data, once the schedule database is exported to a spreadsheet. • Continuous coding of activities to track which trades, types of work, areas of work, etc., are impacted by known issues will allow the schedule analyst to make more effective recommendations regarding schedule compression.
  • 17. Preparatory Steps - Updates • Design and Contract Drawing Clarity: – In updates, it is important to code activities with an “impact” code which relates specific RFI’s to this activity. – The code should be supplemented by specific information in the activity’s log notes or notebook entry; however, the Activity Code is essential for quick and effective EVM analysis within spreadsheets. – Log notes must record delays to the start of an activity due to Design Clarity issues, as represented by an RFI or other appropriate record documentation, and should also track the start and finish date of RFI review. • If an in-progress activity is affected by a Design Clarity issue, the scheduler should consider the use of the Suspend-Resume function to show the break in progress. • Use of this function will also ensure that the activity’s Actual Duration is only reflective of the contractor’s progress, so that progress-related delays are clearly separated from Design Clarity issues. – Should RFI’s or other Design Clarity issues result in changes to the design, the scheduler must appropriately account for the changes in the network, to include alterations to activities, durations, logic, cost loading, and the BCWS curve. This will ensure a fair comparison of the EV to the PV as the project progresses.
  • 18. Preparatory Steps - Updates • Project Management and Production: – Proper coding within the baseline schedule should allow for the generation of trade-specific EVM metrics. – PM staff should: • Continually create impact codes and log notes to represent occasions where particular subcontractors have fallen short of expectations in some way. • Code and note any occasion where project progress was delayed or disrupted by the action or inaction of the owner, or by third-party delays. – Assiduous attention to detail in this regard will allow the analyst to separate out those trends which are representative of poor contractor performance from those which were representative of impacts external to the contractor. • Document start delays and production delays in log notes • Use Suspend / Resume
  • 19. Prerequisites and Preparatory Steps • Goal is to create a detailed database of uniformly coded information which will yield quick and accurate trending information that can be filtered on a by-trade or other basis, in order to guide the scheduler in development of a compressed schedule.
  • 20. EVM in Schedule Compression
  • 21. EVM in Schedule Compression • Crashing. A schedule compression technique in which cost and schedule tradeoffs are analyzed to determine how to obtain the greatest amount of compression for the least incremental cost. Examples of crashing could include approving overtime, bringing in additional resources, or paying to expedite delivery to activities on the critical path. Crashing only works for activities where additional resources will shorten the duration. Crashing does not always produce a viable alternative and may result in increased risk and/or cost. • Fast tracking. A schedule compression technique in which phases or activities normally performed in sequence are performed in parallel. An example is constructing the foundation for a building before completing all of the architectural drawings. Fast tracking may result in rework and increased risk. Fast tracking only works if activities can be overlapped to shorten the duration. -From PMI’s Body of Knowledge, Fourth Edition
  • 22. EVM in Schedule Compression • Whether the schedule is to be crashed or fast- tracked, it is essential that the scheduler understand the following: – Which trades are not performing up to expectations or contractual obligations, and will therefore require additional resources or project management attention in order to meet or exceed current production goals? – Which trades are exceeding expectations or contractual obligations, and will therefore likely exceed current production goals? – Delay and responsibility for delay will require CPM analysis, not only EVMS – this is a trending tool that can be used to point out specific trends among trade contractors that will likely affect progress
  • 23. EVM in Schedule Compression • By exporting the schedule database to a spreadsheet, the scheduler can examine the historical data to gain an understanding of the performance of each trade. • At a minimum, the scheduler should export the following data fields from the schedule database into a spreadsheet: Activity ID Budgeted cost Activity description Actual cost Original duration Cost Percent Complete Actual duration Phase Percent complete Work Area Early start CSI Division Early finish Type of Work Actual start Responsibility/Subcontractor Actual finish Issue Codes Resources
  • 24. EVM in Schedule Compression Export or copy trending data into table in preparation for pivot tables or charts 2005 2006 May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Percent Complete 23.00 27.30 32.50 37.40 40.80 44.50 50.20 53.00 59.00 63.00 73.00 79.00 85.00 89.00 Critical Activities 189 141 596 713 705 756 12 170 454 11 200 36 82 LP Activities 171 107 191 142 519 6 6 6 26 25 22 Logic Changes 3,151 209 153 286 695 134 771 3,505 57 194 526 69 78 78 Out of sequence 69 Number of 2,287 2,289 2,285 2,313 2,317 2,326 2,776 2,777 2,780 2,807 2,808 2,812 2,816 Activities In Progress 54 44 54 47 46 49 67 75 84 76 92 121 107 Complete 212 249 304 372 454 535 855 1,044 1,280 1,601 1,850 2,007 2,208 Missed ES 32 35 25 23 18 25 24 30 28 29 44 37 25 Missed EF 27 26 25 37 29 39 59 47 60 38 78 82 101 Missed Both 33 38 45 65 76 102 114 115 244 191 292 396 377 Early ES 15 12 8 5 0 Early EF 7 13 13 4 3 Early Both 0 31 8 2 1 Project TPR 2.18 3.09 1.77 1.64 1.57 3.01 2.12 3.42 3.30 1.97 2.19 2.95 1.96 2.53 2.52 BCW S ($M) 15.89 25.11 34.66 40.00 41.48 48.64 53.79 57.30 67.67 75.00 80.62 83.33 93.09 BCW P ($M) 8.90 22.10 30.50 36.40 36.50 42.80 46.80 51.00 56.40 60.90 60.70 72.00 78.20 82.50 82.37 ACW P ($M) 4.6 17.40 27.70 27.70 37.20 38.30 43.40 45.90 52.20 55.20 60.40 70.00 76.5 80.60 81.75 CPI 1.90 1.37 1.22 1.11 0.98 1.12 1.08 1.11 1.08 1.10 1.00 1.03 1.02 1.02 1.01 SPI 0.56 0.88 0.88 0.91 0.88 0.88 0.87 0.89 0.70 0.90 0.96 0.97 0.99 0.88 24
  • 25. EVM in Schedule Compression • Generate Time Performance Ratio and collate data within a Pivot Table. Milestone HB HBRC HRU JCD WCE WM Grand Total 1 0.78 3.00 30.00 1.00 2.30 4.49 3 1.77 10.75 8.51 Type of Work TPR 4 1.67 1.00 0.83 1.03 Backfill 2.66 5 5.83 0.50 1.00 2.33 Concrete 2.15 70 0.86 1.00 1.00 0.99 Dredging 2.35 90 1.00 1.00 Electrical 1.52 7A 8.40 0.15 1.20 1.45 1.87 7B 3.96 0.05 1.40 2.67 Excavation/Backfill Work 3.25 7C 2.01 0.05 1.33 1.48 Signing/Marking 5.00 7D 4.27 0.78 2.52 Precast Concrete 3.60 7E 2.55 2.55 Pile 3.19 8A 5.60 5.60 Sheet Pile 2.66 8B 4.19 4.19 9A 2.70 1.71 2.32 Sewer Service 0.33 9B 1.01 1.01 Water Line 2.12 Grand Misc. Steel 5.30 Total 3.55 0.97 2.84 1.23 1.26 1.00 1.84 Crane Rail 9.13
  • 26. EVM in Schedule Compression • Additional EVM metrics can be created by creating pivot graphs of cumulative EV data over time, as represented in the schedule database. – By filtering the EV data by each of the trade codes, and plotting the cumulative data by month, the EV data for each trade can be compared to the BCWS Curves generated from the baseline schedule. – From these curve comparisons, SV, CV, SPI, CPI, and TCPI can be generated for each trade. • Causes of the slippage within a particular subcontractor’s work will have to be determined through examination of project documentation and interviews with the project staff.
  • 27. EVM in Schedule Compression Separating Earned Value curves by trade or location will show very different results from project average Earned Value metrics HVAC Improvements Problems ELEC Consistent Time Problems 27
  • 28. EVM in Schedule Compression • Recovery concepts – Determine slope of EV curve necessary to recover to end of project or milestone – Graphically • Produce trade specific EVMS curves • Identify increased production curve from current time period to end of project • Convert production curve to shortened durations • Verify ability of trade contractor to supply resources produce durations 28
  • 29. EVM in Schedule Compression • Determine production slope for recovery • Use proportions to adjust remaining durations of trade Cost Or Quantity Time Compressed EAC Increased Costs from Overrun Compression EAC Cost BAC Overrun Time • Check history Variance Production Slope Required to Meet • Verify ability to AC Deadline provide resources BCWS (PV) EV 0 Start DD Completion Time 29
  • 30. EVM in Schedule Compression • In identifying underperforming trades, the scheduler must investigate further to determine why this particular trade was underperforming: – Did it provide sufficient resources? – Did the observed resources match planned resources? – Were Man-Days or Crew-Days spent inefficiently? • However, the comparison of each trade’s PV to it’s EV will focus the scheduler’s attention on that trade, and will prevent the scheduler from creating a mitigation strategy that relies upon subcontractors that have demonstrated an inability to meet their commitments in the baseline schedule.
  • 31. EVMS in Schedule Compression 700 Run resource profile comparisons Sum of Planned Man Power Sum of Actual Man Power To show failure to meet planned 600 levels of manpower 500 This frames the discussion for any trade contractors that have not met 400 plan, but need to ramp up for schedule mitigation 300 This also allows the discussion of 200 whether the under-manning can be overcome with the trade contractor 100 for the purposes of mitigation or if another contractor is needed 0 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2001 2002 31
  • 32. Resource Analysis Review individual trade or responsibility – check for predicted overload in the trade work – by crew, by location 32
  • 33. EVM in Schedule Compression • As the mitigation strategy is implemented within the CPM schedule, the schedule analyst must run resource curves to determine if more resources are needed. • When analyzing the new resource curves, the analyst should ask the following questions for each trade: – Does the new resource level exceed that which was previously agreed upon with the subcontractor? – Can the subcontractor provide the new level of resources, and who will bear the burden of the cost of the increased resources? – If not, can the prime contractor hire additional subcontractors for this trade in order to achieve the increased level of production necessary to compress the schedule?
  • 34. EVM in Schedule Compression • In order to analyze resources, run a Resource Table. – Load activities with Crews if the schedule is not resource loaded, and then create a resource table. – Such a table will visually demonstrate where there may be conflicts with the numbers of crews for each trade. This is a source for slippage which should be discussed with the contractors.
  • 35. EVMS in Schedule Compression • Excellent paper – Al Kuhn, PSP – use when no resource loading in schedule – Allows crew loading & analysis 35
  • 36. Resource Analysis with EV Set up Crew Resources – Use them to check maximum available limits 36
  • 38. Conclusion • Trends shown in the EVM metrics can be applied in selecting areas for compression, highlighting the need for additional resources, and checking the realism of a newly developed compressed schedule, prior to implementation. • The scheduler will have the ability to provide accurate and useful recommendations to the project management staff in support of mitigation and recovery efforts. • The use of a good, trade specific Earned Value Management System will provide useful data for use in mitigation efforts as long as there is a mitigation strategy in place and a monitoring system that will provide good, reliable metrics on a periodic basis. • Those metrics must be maintained, analyzed, and used in the mitigation plan to guide the trade contractors as necessary to fulfill the needs for recovery.
  • 39. Conclusion • This process will also provide early warning of problem trade contractors in advance of the need to mitigate, and when the need arises, the process will lay out guidelines for mitigation, as well as provide the appropriate documentation to encourage and legally support the need for specific trade contractor mitigation. • With proper use of this system, it is also possible to minimize loss of productivity claims by periodic monitoring of the slippage in work, assessing responsibility, and predicting the remaining required production rates, as well as resource requirements, that are necessary to complete on time.
  • 40. Mitigation and Performance Recovery Using Earned Value Questions? Chris Carson, PSP, PMP, CCM Patrick M. Kelly, PSP Corporate Director of Project Controls Project Controls Manager Chris.Carson@alphacorporation.com Patrick.Kelly@alphacorporation.com (O) 757-533-9368 (M) 757-342-5524 (O) 757-533-9368 (M) 757-217-6820
  • 41. 41