SlideShare uma empresa Scribd logo
1 de 32
Baixar para ler offline
Review and Analysis of
Delay Mitigation Schedules
Jorge Gonzales, PSP
Miami Dade Aviation Department
Scheduling Manager

Chris Carson, PMP, PSP, CCM
Alpha Corporation
Corporate Director Project Controls
Mitigation Schedule Analysis
• Triple constraints
   – Time
   – Cost
   – Scope/quality
   – Fourth constraint often added; risk
• Most programs are driven by one of the constraints
   – When one constraint must be fixed, others will vary
   – In this case, time was the fixed constraint
   – This requires a focus on mitigation of delays
• A structured effort is essential
Mitigation Schedule Analysis
• Miami International Airport
  – Individual projects comprise renovation and opening
    of gates
  – Cost impacts from failure to open gates on time result
    in millions of dollars of lost income
  – Failure would also severely impact passenger access
    to flights and create delays
  – Progress towards gate openings is dependent upon
    work in adjacent gate areas
  – Utilities run through other areas, some public
  – Phasing and coordination are much more complex
Mitigation Schedule Analysis
• Background
   – Program management staff recognized the need to
     actively manage the scheduling process
   – Developed detailed schedule specifications
      •   Required as-planned resource data
      •   Required monthly reports of as-built resource data
      •   Provided additional schedule review consultant (Alpha)
      •   Required weekly schedule-focused meetings
      •   Mandated detailed schedule updates
      •   Required submittal of formal mitigation plans from contractor
Mitigation Schedule Analysis
• Steps in the mitigation strategy process
   – Identification of the delay requiring mitigation
   – Formal request for a mitigation plan from contractor
   – Analysis of submitted mitigation plan
   – Analysis of mitigation plan alternates & options
   – Estimation of costs related to trade mitigation
   – Recommendations for specific mitigation efforts
   – Determine maximum risk
   – Choose preferred mitigation option
   – Choose mitigation strategy
   – Issue change order for mitigation effort
   – Re-baseline schedule to show mitigation
Mitigation Key Items
•Establish mitigation timeline for submittal, review, and
approval

•Ensure contract is set up for mitigation requirements; data,
schedule quality, direction

•Remove deal breakers from contractor qualifications

•Establish actual work in place at time of mitigation

•Monitor additional scope while mitigation is being prepared,
reviewed, and approved.
Mitigation Strategies
•Contractor best case versus owner best case schedule
   What if schedule comparisons.

•Contractor mitigation by logic changes (fast-track)

•Contractor mitigation by compression (crunching)

•Mitigation by scope modification.

•Validate contractor’s mitigation to ensure value from trade
contractor mitigation plan results
Mitigation Flow Chart

                                                                                      Owner reviews
                                Owner reviews
                                                                                       compressed
•Contractor identifies         mitigation proposal   •Owners provides                   schedule
 delay                                                feedback to contractor
                          •Contractor submits         and asks for missing     •Owner executes work
•Owner establishes         mitigation proposal
 merit to delay                                       documents                 order
                          •Owner asks contractor                               •Owner and contractor
                           for mitigation proposal                              reach agreement in
                                                                                negotiation meeting
      Owner chooses to                                      Contractor re-
      mitigate schedule                                    submits proposal
Mitigation Check List
•Pre-impact schedule
•Impacted schedule
•Narrative for impacted schedule
•Time impact analysis
•What if schedule options
•Mitigation cost calculations
•Owner’s maximum exposure calculation
•Subcontractor schedule & cost calculations
•Contractor’s proposal
•Work order or change order
•Re-baselined schedule
Mitigation Schedule Analysis
• Identification of the delay requiring mitigation
   – From contractor notification
   – From trending and completion prediction analysis
     done during schedule review
   – The sooner delay is identified, the greater
     opportunities for successful mitigation
Mitigation Schedule Analysis
• Formal request for a mitigation plan from contractor
   – Ensure that delay is not contractor responsibility
   – Provide specific request
   – Embark on parallel course
      • Evaluate scope reduction opportunities
      • Evaluate worst case effects without mitigation
   – Avoid overtime requests
      • Limits risk of consequential claims – inefficiency
   – Request includes breakdown of individual trade
     contractor costs for use in analysis
Mitigation Schedule Analysis
• Analysis of submitted mitigation plan
   – Ensure schedule represents current conditions
   – Provide analysis
        • Prospective for future impacts
        • Forensic analysis for embedded impacts
   –   Evaluate appropriateness of logic changes
   –   Review logic to identify re-sequencing
   –   Load crews to identify net change in crew count
   –   Segregate trade contractor mitigation time
        • Identifies best value for mitigation (lowest cost/day)
   – Recognize that mitigation schedules are often not well
     thought out
Mitigation Schedule Analysis
• Analysis of mitigation plan alternates & options
   – After basic analysis and review, look at options
   – Develop what-if scenarios for all options
       • Include cost calculations per trade
   – General options:
       •   Let the project slip
       •   Reduce, remove, or postpone scope
       •   Mitigation/re-sequencing
       •   Compression
       •   Evaluating interface milestone requirements for ability to relax
           requirements
   – Evaluate project time remaining
       • Requesting mitigation too early may waste money
       • May require future mitigation
   – Evaluate impact on other projects
   – Review to ensure all affected projects are included
Mitigation Schedule Analysis
• Estimation of costs related to trade mitigation
   – Sort schedule by trade
   – Identify time saved by each trade
   – Compare costs per trade to time saved
   – Ensure value in recommending mitigation on a per
     trade basis
   – Often the highest cost trade mitigations offer the least
     amount of time saved
Mitigation Schedule Analysis
• Recommendations for specific mitigation efforts
   – Contains relevant information related to final costs
     and time
   – Includes impact on other project milestones or
     operations
   – Identifies increased owner responsibilities
      •   More frequent inspections
      •   Off-hours inspections
      •   Limitations on access to certain areas
      •   Reduced submittal review time requirements
Mitigation Schedule Analysis
• Determine maximum risk
   – Goal is to shift performance risk to the contractor with
     issuance of change order
   – Negotiate this shift
   – Risk assessment
       • Review project risk register
       • Update risk response plan
       • May require new risk workshop
          – Duration achievement risks
          – Specific impact risks
          – Network risks
Mitigation Schedule Analysis
• Choose preferred mitigation option
   – Review with project team
   – Costs are generally of primary interest
   – PM team will assess their comfort level with the
     specific trade mitigations
   – Meeting generates additional suggestions and
     questions
   – May have to request additional work from contractor
     based on team meeting
Mitigation Schedule Analysis
• Choose mitigation strategy
   – Final review of contractor’s plan, including their
     response to any questions/suggestions
   – Make final decision for choice of strategy
   – Finalize negotiations with contractor
   – Ensure meeting of minds
Mitigation Schedule Analysis
• Issue change order for mitigation effort
   – Formalize agreement with change order
   – Include all pertinent facts to define mitigation needs
     and requirements
   – Ensure this is done quickly
   – Ensure it assigns performance and cost risks
   – Identify any conditions required of the owner to
     accommodate mitigation
North Terminal Case Studies
NTD PROGRAM FACT SHEET




     http://www.miami-airport.com
Case Study 1
A-B Infill Project
A-B Infill Project
•Contractor analysis
   •Identified 78 calendar days of delay due to 37+ changes
   •Option 1 base mitigation price of $1.2 Million.
   •Option 2 base mitigation plus most critical changes price
   of $1.7M
   •Option 3 base mitigation plus all pending changes lump
   sum price of $2.2M
Owner analysis
   •Developed what-if schedule to model changes: net impact
   of 17 calendar days (including all changes)
   •Identified maximum owner exposure of $1.3M
•Conclusion
   •Owner choose option 1 for $1.2 million
Case Study 2
B-C Infill Project
BC Infill Project
•Contractor analysis
   •129 days of delay due to MEP conflicts, late release of
   structural wall design, and $5.6M in changes
   •Owner max exposure to be $4.1M
   •D21, D22, and D23 gate openings delayed by 63 CD at a
   cost of $345,000
•Owner analysis
   •Developed what-if schedule
   •34 calendar days impact to gates
   •Cost of $335,000
•Conclusion
   •Owners decided only to mitigate gate opening
   •A best effort T&M work order was issued
Mitigation Schedule Analysis
• Lessons learned
   – Act quickly both in identifying and reviewing
   – Analyze fairly, contractor has a tough job with
     mitigation plan development
   – Analyze carefully
        • Schedule must be legitimate and appropriate
        • Analyze costs separately after time analysis
   –   Assess all options
   –   Evaluate impact on all other projects/milestones
   –   Ensure reasonableness of plan
   –   Goal is to mitigate once and rapidly
Conclusion
Keeping the North Terminal Program on schedule was a
constant effort that involved review of schedule and cost
performance, incorporation of change work, incorporation of
mitigation plans, and updating of interface milestones.
Questions?
Thank You
For Attending!

Mais conteúdo relacionado

Mais procurados

Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesChris Carson
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesChris Carson
 
DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.Chris Carson
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueChris Carson
 
Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop ConferenceChris Carson
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMIChris Carson
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingChris Carson
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - AirportChris Carson
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodChris Carson
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2Abdelhay Ghanem
 
Update Delay Analysis
Update Delay AnalysisUpdate Delay Analysis
Update Delay AnalysisChris Carson
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysisADITYA GHUMARE
 
Baseline Schedules 1
Baseline Schedules 1Baseline Schedules 1
Baseline Schedules 1Chris Carson
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2Chris Carson
 

Mais procurados (19)

Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual Schedules
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule Types
 
DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop Conference
 
Schedule Review
Schedule ReviewSchedule Review
Schedule Review
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - Airport
 
Claims Triage
Claims TriageClaims Triage
Claims Triage
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis Method
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2
 
Update Delay Analysis
Update Delay AnalysisUpdate Delay Analysis
Update Delay Analysis
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
 
Baseline Schedules 1
Baseline Schedules 1Baseline Schedules 1
Baseline Schedules 1
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2
 

Semelhante a Pmicos 2011 Review And Analysis Of Mitigation Schedules

Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesChris Carson
 
Contract administration iowa AGC
Contract administration iowa AGCContract administration iowa AGC
Contract administration iowa AGCCordell Parvin
 
Top 3 Challenges in Managing Triple Constraint
Top 3 Challenges in Managing Triple ConstraintTop 3 Challenges in Managing Triple Constraint
Top 3 Challenges in Managing Triple ConstraintSunil Guglani
 
Project management procurement
Project management  procurementProject management  procurement
Project management procurementMalcolm Peart
 
Brokerage Simplified
Brokerage SimplifiedBrokerage Simplified
Brokerage Simplifiedmcmahonkevin
 
Exploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryExploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryMECandPMV
 
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15Ian Carr SCMP, MCIPS
 
How to Choose a Project Delivery Method
How to Choose a Project Delivery MethodHow to Choose a Project Delivery Method
How to Choose a Project Delivery MethodPMA Consultants
 
20050314 tips on contract management
20050314 tips on contract management20050314 tips on contract management
20050314 tips on contract managementraymond_wan2005
 
Fleming.jon
Fleming.jonFleming.jon
Fleming.jonNASAPMC
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair IssuesTRIslides
 
Team Optimus_IIM K
Team Optimus_IIM KTeam Optimus_IIM K
Team Optimus_IIM KPravin Bokil
 

Semelhante a Pmicos 2011 Review And Analysis Of Mitigation Schedules (20)

Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel Schedules
 
Contract administration iowa AGC
Contract administration iowa AGCContract administration iowa AGC
Contract administration iowa AGC
 
Top 3 Challenges in Managing Triple Constraint
Top 3 Challenges in Managing Triple ConstraintTop 3 Challenges in Managing Triple Constraint
Top 3 Challenges in Managing Triple Constraint
 
Project management procurement
Project management  procurementProject management  procurement
Project management procurement
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Brokerage Simplified
Brokerage SimplifiedBrokerage Simplified
Brokerage Simplified
 
Intergrated baseline reviews as a tool in assurance
Intergrated baseline reviews as a tool in assurance Intergrated baseline reviews as a tool in assurance
Intergrated baseline reviews as a tool in assurance
 
Agile contracting
Agile contractingAgile contracting
Agile contracting
 
Claims
ClaimsClaims
Claims
 
Exploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryExploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project delivery
 
Design-Build Procurement Approaches
Design-Build Procurement ApproachesDesign-Build Procurement Approaches
Design-Build Procurement Approaches
 
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair Issues
 
How to Choose a Project Delivery Method
How to Choose a Project Delivery MethodHow to Choose a Project Delivery Method
How to Choose a Project Delivery Method
 
Rangkuman part 2
Rangkuman part 2Rangkuman part 2
Rangkuman part 2
 
20050314 tips on contract management
20050314 tips on contract management20050314 tips on contract management
20050314 tips on contract management
 
Pmp session 6
Pmp session 6Pmp session 6
Pmp session 6
 
Fleming.jon
Fleming.jonFleming.jon
Fleming.jon
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair Issues
 
Team Optimus_IIM K
Team Optimus_IIM KTeam Optimus_IIM K
Team Optimus_IIM K
 

Mais de Chris Carson

Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIChris Carson
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueChris Carson
 
Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpChris Carson
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry SchedulingChris Carson
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion SchedulesChris Carson
 
Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationChris Carson
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex ProjectChris Carson
 
Testimony Mistakes
Testimony MistakesTestimony Mistakes
Testimony MistakesChris Carson
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule DevelopmentChris Carson
 
Subcontractor Scheduling
Subcontractor SchedulingSubcontractor Scheduling
Subcontractor SchedulingChris Carson
 
Schedule Design PMI
Schedule Design PMISchedule Design PMI
Schedule Design PMIChris Carson
 

Mais de Chris Carson (11)

Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls Pp
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry Scheduling
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion Schedules
 
Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan Presentation
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex Project
 
Testimony Mistakes
Testimony MistakesTestimony Mistakes
Testimony Mistakes
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
Subcontractor Scheduling
Subcontractor SchedulingSubcontractor Scheduling
Subcontractor Scheduling
 
Schedule Design PMI
Schedule Design PMISchedule Design PMI
Schedule Design PMI
 

Pmicos 2011 Review And Analysis Of Mitigation Schedules

  • 1.
  • 2. Review and Analysis of Delay Mitigation Schedules Jorge Gonzales, PSP Miami Dade Aviation Department Scheduling Manager Chris Carson, PMP, PSP, CCM Alpha Corporation Corporate Director Project Controls
  • 3. Mitigation Schedule Analysis • Triple constraints – Time – Cost – Scope/quality – Fourth constraint often added; risk • Most programs are driven by one of the constraints – When one constraint must be fixed, others will vary – In this case, time was the fixed constraint – This requires a focus on mitigation of delays • A structured effort is essential
  • 4. Mitigation Schedule Analysis • Miami International Airport – Individual projects comprise renovation and opening of gates – Cost impacts from failure to open gates on time result in millions of dollars of lost income – Failure would also severely impact passenger access to flights and create delays – Progress towards gate openings is dependent upon work in adjacent gate areas – Utilities run through other areas, some public – Phasing and coordination are much more complex
  • 5. Mitigation Schedule Analysis • Background – Program management staff recognized the need to actively manage the scheduling process – Developed detailed schedule specifications • Required as-planned resource data • Required monthly reports of as-built resource data • Provided additional schedule review consultant (Alpha) • Required weekly schedule-focused meetings • Mandated detailed schedule updates • Required submittal of formal mitigation plans from contractor
  • 6. Mitigation Schedule Analysis • Steps in the mitigation strategy process – Identification of the delay requiring mitigation – Formal request for a mitigation plan from contractor – Analysis of submitted mitigation plan – Analysis of mitigation plan alternates & options – Estimation of costs related to trade mitigation – Recommendations for specific mitigation efforts – Determine maximum risk – Choose preferred mitigation option – Choose mitigation strategy – Issue change order for mitigation effort – Re-baseline schedule to show mitigation
  • 7. Mitigation Key Items •Establish mitigation timeline for submittal, review, and approval •Ensure contract is set up for mitigation requirements; data, schedule quality, direction •Remove deal breakers from contractor qualifications •Establish actual work in place at time of mitigation •Monitor additional scope while mitigation is being prepared, reviewed, and approved.
  • 8. Mitigation Strategies •Contractor best case versus owner best case schedule What if schedule comparisons. •Contractor mitigation by logic changes (fast-track) •Contractor mitigation by compression (crunching) •Mitigation by scope modification. •Validate contractor’s mitigation to ensure value from trade contractor mitigation plan results
  • 9. Mitigation Flow Chart Owner reviews Owner reviews compressed •Contractor identifies mitigation proposal •Owners provides schedule delay feedback to contractor •Contractor submits and asks for missing •Owner executes work •Owner establishes mitigation proposal merit to delay documents order •Owner asks contractor •Owner and contractor for mitigation proposal reach agreement in negotiation meeting Owner chooses to Contractor re- mitigate schedule submits proposal
  • 10. Mitigation Check List •Pre-impact schedule •Impacted schedule •Narrative for impacted schedule •Time impact analysis •What if schedule options •Mitigation cost calculations •Owner’s maximum exposure calculation •Subcontractor schedule & cost calculations •Contractor’s proposal •Work order or change order •Re-baselined schedule
  • 11. Mitigation Schedule Analysis • Identification of the delay requiring mitigation – From contractor notification – From trending and completion prediction analysis done during schedule review – The sooner delay is identified, the greater opportunities for successful mitigation
  • 12. Mitigation Schedule Analysis • Formal request for a mitigation plan from contractor – Ensure that delay is not contractor responsibility – Provide specific request – Embark on parallel course • Evaluate scope reduction opportunities • Evaluate worst case effects without mitigation – Avoid overtime requests • Limits risk of consequential claims – inefficiency – Request includes breakdown of individual trade contractor costs for use in analysis
  • 13. Mitigation Schedule Analysis • Analysis of submitted mitigation plan – Ensure schedule represents current conditions – Provide analysis • Prospective for future impacts • Forensic analysis for embedded impacts – Evaluate appropriateness of logic changes – Review logic to identify re-sequencing – Load crews to identify net change in crew count – Segregate trade contractor mitigation time • Identifies best value for mitigation (lowest cost/day) – Recognize that mitigation schedules are often not well thought out
  • 14. Mitigation Schedule Analysis • Analysis of mitigation plan alternates & options – After basic analysis and review, look at options – Develop what-if scenarios for all options • Include cost calculations per trade – General options: • Let the project slip • Reduce, remove, or postpone scope • Mitigation/re-sequencing • Compression • Evaluating interface milestone requirements for ability to relax requirements – Evaluate project time remaining • Requesting mitigation too early may waste money • May require future mitigation – Evaluate impact on other projects – Review to ensure all affected projects are included
  • 15. Mitigation Schedule Analysis • Estimation of costs related to trade mitigation – Sort schedule by trade – Identify time saved by each trade – Compare costs per trade to time saved – Ensure value in recommending mitigation on a per trade basis – Often the highest cost trade mitigations offer the least amount of time saved
  • 16. Mitigation Schedule Analysis • Recommendations for specific mitigation efforts – Contains relevant information related to final costs and time – Includes impact on other project milestones or operations – Identifies increased owner responsibilities • More frequent inspections • Off-hours inspections • Limitations on access to certain areas • Reduced submittal review time requirements
  • 17. Mitigation Schedule Analysis • Determine maximum risk – Goal is to shift performance risk to the contractor with issuance of change order – Negotiate this shift – Risk assessment • Review project risk register • Update risk response plan • May require new risk workshop – Duration achievement risks – Specific impact risks – Network risks
  • 18. Mitigation Schedule Analysis • Choose preferred mitigation option – Review with project team – Costs are generally of primary interest – PM team will assess their comfort level with the specific trade mitigations – Meeting generates additional suggestions and questions – May have to request additional work from contractor based on team meeting
  • 19. Mitigation Schedule Analysis • Choose mitigation strategy – Final review of contractor’s plan, including their response to any questions/suggestions – Make final decision for choice of strategy – Finalize negotiations with contractor – Ensure meeting of minds
  • 20. Mitigation Schedule Analysis • Issue change order for mitigation effort – Formalize agreement with change order – Include all pertinent facts to define mitigation needs and requirements – Ensure this is done quickly – Ensure it assigns performance and cost risks – Identify any conditions required of the owner to accommodate mitigation
  • 22. NTD PROGRAM FACT SHEET http://www.miami-airport.com
  • 25. A-B Infill Project •Contractor analysis •Identified 78 calendar days of delay due to 37+ changes •Option 1 base mitigation price of $1.2 Million. •Option 2 base mitigation plus most critical changes price of $1.7M •Option 3 base mitigation plus all pending changes lump sum price of $2.2M Owner analysis •Developed what-if schedule to model changes: net impact of 17 calendar days (including all changes) •Identified maximum owner exposure of $1.3M •Conclusion •Owner choose option 1 for $1.2 million
  • 28. BC Infill Project •Contractor analysis •129 days of delay due to MEP conflicts, late release of structural wall design, and $5.6M in changes •Owner max exposure to be $4.1M •D21, D22, and D23 gate openings delayed by 63 CD at a cost of $345,000 •Owner analysis •Developed what-if schedule •34 calendar days impact to gates •Cost of $335,000 •Conclusion •Owners decided only to mitigate gate opening •A best effort T&M work order was issued
  • 29. Mitigation Schedule Analysis • Lessons learned – Act quickly both in identifying and reviewing – Analyze fairly, contractor has a tough job with mitigation plan development – Analyze carefully • Schedule must be legitimate and appropriate • Analyze costs separately after time analysis – Assess all options – Evaluate impact on all other projects/milestones – Ensure reasonableness of plan – Goal is to mitigate once and rapidly
  • 30. Conclusion Keeping the North Terminal Program on schedule was a constant effort that involved review of schedule and cost performance, incorporation of change work, incorporation of mitigation plans, and updating of interface milestones.