SlideShare uma empresa Scribd logo
1 de 42
Baixar para ler offline
Favorite Delay Analysis Methodologies
  Best Practices and Guidelines for Schedule Impact Analysis
                          Volume 1

                                   Chris Carson, PSP, CCM, PMP
           Corporate Director of Project Controls, Alpha Corporation
                Managing Director, Scheduling Excellence Initiative



AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
Based on AACE International Recommended Practice
        No. 29R-03, Forensic Schedule Analysis”




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
Observational
                3.1 Static – Gross
                        (As-Planned v. As-Built, Single Base)
                3.2 Static - Periodic
                        (As-Planned v. As-Built, Multiple Base)
                3.3 Dynamic – Contemporaneous “as-is”
                        (Contemporaneous Period Analysis)
                3.4 Dynamic – Contemporaneous “Split”
                        (Bifurcated Contemporaneous Period Analysis)
                3.5 Dynamic – Contemporaneous “Recreated”
                        (Contemporaneous Period Analysis, Recreated)


AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.1 Static – Gross (As-Planned v. As-Built, Single Base)
          • Applicable only to simple projects, short in duration, with a CP
            that’s unlikely to shift
          • Easy to understand, inexpensive to create
          • Not suitable to long or complicated projects because the
            projects change and the measuring point does not.
          • Use when no update schedules available
          • Need as-planned schedule and as-built data


AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.1 Static – Gross (As-Planned v. As-Built, Single Base)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.1 Static – Gross (As-Planned v. As-Built, Single Base)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.2. Static - Periodic                        (As-Planned v. As-Built, Multiple
        Base)
          • Similar to Single Base version
          • Measuring it in periods adds little since no new data?
          • May find updates useful – but if validated updates available, may
            use other methods that assess CP changes
          • Need as-planned schedule and as-built data
          • May provide for better presentation


AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.2. Static - Periodic               (As-Planned v. As-Built, Multiple Base)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.2. Static - Periodic               (As-Planned v. As-Built, Multiple Base)




        Continued next slide



AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.2. Static - Periodic               (As-Planned v. As-Built, Multiple Base)

  Continued from previous slide




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.3. Dynamic – Contemporaneous “as-is”
                  (Contemporaneous Period Analysis)
          • Applicable on complicated projects
          • Uses contemporaneous updates as new baselines
          • If done monthly, then it could be called a “Windows” analysis
          • Handles many problems like concurrency well




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.3. Dynamic – Contemporaneous “as-is” (CPA)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.3. Dynamic – Contemporaneous “as-is” (CPA)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.4. Dynamic – Contemporaneous “Split”
                  (Bifurcated Contemporaneous Period)
          • Applicable on complicated projects
          • Uses contemporaneous updates as new baselines
          • If done monthly, then it could be called a “Windows” analysis
          • Handles many problems like concurrency well
          • The “split” separates Logic-type changes from Actual Progress



AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.4. Dynamic – Contemporaneous “Split”        (Bifurcated CPA)




        Continued next slide



AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.4. Dynamic – Contemporaneous “Split”        (Bifurcated CPA)
                                                               Continued from
                                                                previous slide




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.4. Dynamic – Contemporaneous “Split”        (Bifurcated CPA)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.5. Dynamic – Contemporaneous “Recreated”
                   (Contemporaneous Period Analysis)
          • Applicable on complicated projects
          • Uses RECREATED updates as new baselines
          • If done monthly, then it might be called a “Windows” analysis
          • Handles many problems like concurrency well
          • However – virtually all of the baselines are created by the
            analyst



AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.5. Dynamic – Contemporaneous “Recreated”     (Recreated CPA)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.5. Dynamic – Contemporaneous “Recreated”                            (Recreated CPA)




                                                     Continued next slide
AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.5. Dynamic – Contemporaneous “Recreated”     (Recreated CPA)

                                                           Continued from
                                                            previous slide




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• Modeled
          • 3.6 Additive – Single Base          (Impacted as-planned)
          • 3.7 Additive – Multiple Base        (Retrospective TIA)
          • 3.8 Subtractive – Single Simulation (Collapsed as-built)
          • 3.9 Subtractive – Multiple Simulation




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.6 Additive – Single Base (Impacted As-Planned)
          • Accuracy very dependent on inclusiveness of fragnets and
            accuracy of as-planned schedule.
          • Also dependent on changes in Critical Path from As-Planned
          • Easy to understand
          • Can be purely hypothetical, generally does not prevail in
            litigation
          • Concurrency not addressed


AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.6 Additive – Single Base (Impacted As-Planned)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.6 Additive – Single Base (Impacted As-Planned)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.7 Additive – Multiple Base (Retrospective TIA)
          • Accuracy dependent on inclusiveness of fragnets and accuracy of
            updates – however more likely to include both owner and
            contractor issues
          • Easy to understand
          • No as-built required (although still useful)
          • Updates useful if used (failure to correlate creates problem)
          • Associated with actual events
          • Concurrency easily addressed by a two step process

AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.7 Additive – Multiple Base (Retrospective TIA)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.7 Additive – Multiple Base (Retrospective TIA)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.8 Subtractive – Single Simulation (Collapsed As-
        Built)
          • Accuracy dependent on creation of after the fact logic
          • Easy to understand
          • Uses actual events
          • Can be viewed as hypothetical
          • Critical path can be difficult to identify



AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.8 Subtractive – Single Simulation (Collapsed As-Built)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.8 Subtractive – Single Simulation (Collapsed As-Built)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.9 Subtractive – Multiple Simulation
          • Only known practitioner – Long International?
          • Accuracy still dependent on creation of after the fact logic
          • Uses actual Events
          • Can be viewed as hypothetical
          • Critical path can be difficult to identify




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.1 Static – Gross (As-Planned v. As-Built, Single Base)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.1 Static – Gross (As-Planned v. As-Built, Single Base)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
Forensic Use of                            METHOD
       Analysis            3.1   3.2   3.3     3.4   3.5   3.6   3.7   3.8

    Non-Compensable
                           OK    OK    OK      OK    OK    OK    OK    OK
     Time Extension


   Compensable Delay       OK    OK    OK      OK    OK                OK


   Right to Finish Early
                                                                       OK
   Compensable Delay

   Entitlement to Early
                           OK    OK    OK      OK    OK    OK    OK    OK
   Completion Bonus

    Disruption Without
                           OK    OK    OK      OK    OK    OK    OK
      Project Delay

       Constructive
                                               OK          OK    OK
       Acceleration



AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
•




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
•
            •   Must allow the source data to bear on the selection process
            •   Cannot predetermine a technique based on personal preference
            •   Balance client needs, budget, and time with sound analysis
                philosophy




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• Observational?
         • Count
      • Modeled?
         • Count



AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• Observational                                     • Observational
      • 3.1 Static – Gross                             • Count
      • 3.2 Static - Periodic                          • Count
      • 3.3 Dynamic – Contemporaneous “as-is”          • Count
      • 3.4 Dynamic – Contemporaneous “Split”          • Count
      • 3.5 Dynamic – Contemporaneous                  • Count
        “Recreated”



AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• Modeled                                        • Modeled
         • 3.6 Additive – Single Base                  • Count
         • 3.7 Additive – Multiple Base                • Count
         • 3.8 Subtractive – Single Simulation         • Count
         • 3.9 Subtractive – Multiple Simulation       • Count



AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis

Mais conteúdo relacionado

Mais procurados

Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMIChris Carson
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysisADITYA GHUMARE
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedMichael Pink
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4Moustafa Ismail Abu Dief
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanAdrias TAN
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingChris Carson
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractProject Controls Expo
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationVimal Daluwatta
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5Moustafa Ismail Abu Dief
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact AnalysisChris Carson
 

Mais procurados (20)

Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Prolongation and HOOH Costs
Prolongation and HOOH CostsProlongation and HOOH Costs
Prolongation and HOOH Costs
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
 
Fidic law1
Fidic law1Fidic law1
Fidic law1
 
Claims
ClaimsClaims
Claims
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 

Destaque

Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysiskatrin enders
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time AnalysisFarhan Moosa
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueChris Carson
 
The Vertex Companies, Inc. - Time Impact Analysis
The Vertex Companies, Inc. - Time Impact AnalysisThe Vertex Companies, Inc. - Time Impact Analysis
The Vertex Companies, Inc. - Time Impact AnalysisLisa Dehner
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueChris Carson
 
Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationChris Carson
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesChris Carson
 
Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop ConferenceChris Carson
 
Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpChris Carson
 
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...Project Controls Expo
 
Baseline Schedules 1
Baseline Schedules 1Baseline Schedules 1
Baseline Schedules 1Chris Carson
 
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...Project Controls Expo
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesChris Carson
 
Bdsm intro PART II/2/B
Bdsm intro PART II/2/BBdsm intro PART II/2/B
Bdsm intro PART II/2/BCree Stetler
 
Piezo roads new
Piezo roads newPiezo roads new
Piezo roads newSoma Giri
 

Destaque (19)

Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
SanDiegoPresentation
SanDiegoPresentationSanDiegoPresentation
SanDiegoPresentation
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
The Vertex Companies, Inc. - Time Impact Analysis
The Vertex Companies, Inc. - Time Impact AnalysisThe Vertex Companies, Inc. - Time Impact Analysis
The Vertex Companies, Inc. - Time Impact Analysis
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan Presentation
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual Schedules
 
Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop Conference
 
Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls Pp
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
 
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
 
Baseline Schedules 1
Baseline Schedules 1Baseline Schedules 1
Baseline Schedules 1
 
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule Types
 
Bdsm intro PART II/2/B
Bdsm intro PART II/2/BBdsm intro PART II/2/B
Bdsm intro PART II/2/B
 
Piezo roads new
Piezo roads newPiezo roads new
Piezo roads new
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
REPORT PPT
REPORT PPTREPORT PPT
REPORT PPT
 

Semelhante a Favorite Delay Analysis Methodologies Town Hall SEI

Scalable Software Testing and Verification of Non-Functional Properties throu...
Scalable Software Testing and Verification of Non-Functional Properties throu...Scalable Software Testing and Verification of Non-Functional Properties throu...
Scalable Software Testing and Verification of Non-Functional Properties throu...Lionel Briand
 
Database performance improvement, a six sigma project (mesure) by nirav shah
Database performance improvement, a six sigma project (mesure) by nirav shah Database performance improvement, a six sigma project (mesure) by nirav shah
Database performance improvement, a six sigma project (mesure) by nirav shah Nirav Shah
 
MCA Daemon: Hybrid Throughput Analysis Beyond Basic Blocks
MCA Daemon: Hybrid Throughput Analysis Beyond Basic BlocksMCA Daemon: Hybrid Throughput Analysis Beyond Basic Blocks
MCA Daemon: Hybrid Throughput Analysis Beyond Basic BlocksMin-Yih Hsu
 
Automating Speed: A Proven Approach to Preventing Performance Regressions in ...
Automating Speed: A Proven Approach to Preventing Performance Regressions in ...Automating Speed: A Proven Approach to Preventing Performance Regressions in ...
Automating Speed: A Proven Approach to Preventing Performance Regressions in ...HostedbyConfluent
 
Test Estimation
Test Estimation Test Estimation
Test Estimation SQALab
 
Schedule Analysis Methods - AACE 29R-03 Recommended.pdf
Schedule Analysis Methods - AACE 29R-03 Recommended.pdfSchedule Analysis Methods - AACE 29R-03 Recommended.pdf
Schedule Analysis Methods - AACE 29R-03 Recommended.pdfAnwar379976
 
Schedulability of Rate Monotonic Algorithm using Improved Time Demand Analysi...
Schedulability of Rate Monotonic Algorithm using Improved Time Demand Analysi...Schedulability of Rate Monotonic Algorithm using Improved Time Demand Analysi...
Schedulability of Rate Monotonic Algorithm using Improved Time Demand Analysi...IJECEIAES
 
Big Data Day LA 2016/ Use Case Driven track - Shaping the Role of Data Scienc...
Big Data Day LA 2016/ Use Case Driven track - Shaping the Role of Data Scienc...Big Data Day LA 2016/ Use Case Driven track - Shaping the Role of Data Scienc...
Big Data Day LA 2016/ Use Case Driven track - Shaping the Role of Data Scienc...Data Con LA
 
Scalable and Cost-Effective Model-Based Software Verification and Testing
Scalable and Cost-Effective Model-Based Software Verification and TestingScalable and Cost-Effective Model-Based Software Verification and Testing
Scalable and Cost-Effective Model-Based Software Verification and TestingLionel Briand
 
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...Egyptian Engineers Association
 
How to conduct abstract screening for systematic review – Pubrica
How to conduct abstract screening for systematic review – PubricaHow to conduct abstract screening for systematic review – Pubrica
How to conduct abstract screening for systematic review – PubricaPubrica
 
Software Testing- Principles of testing- Mazenet Solution
Software Testing- Principles of testing- Mazenet SolutionSoftware Testing- Principles of testing- Mazenet Solution
Software Testing- Principles of testing- Mazenet SolutionMazenetsolution
 
Chapter 3 - Analytical Techniques
Chapter 3 - Analytical TechniquesChapter 3 - Analytical Techniques
Chapter 3 - Analytical TechniquesNeeraj Kumar Singh
 
STUDY ON PROJECT MANAGEMENT THROUGH GENETIC ALGORITHM
STUDY ON PROJECT MANAGEMENT THROUGH GENETIC ALGORITHMSTUDY ON PROJECT MANAGEMENT THROUGH GENETIC ALGORITHM
STUDY ON PROJECT MANAGEMENT THROUGH GENETIC ALGORITHMAvay Minni
 
Real time Scheduling in Operating System for Msc CS
Real time Scheduling in Operating System for Msc CSReal time Scheduling in Operating System for Msc CS
Real time Scheduling in Operating System for Msc CSThanveen
 

Semelhante a Favorite Delay Analysis Methodologies Town Hall SEI (20)

Scalable Software Testing and Verification of Non-Functional Properties throu...
Scalable Software Testing and Verification of Non-Functional Properties throu...Scalable Software Testing and Verification of Non-Functional Properties throu...
Scalable Software Testing and Verification of Non-Functional Properties throu...
 
Database performance improvement, a six sigma project (mesure) by nirav shah
Database performance improvement, a six sigma project (mesure) by nirav shah Database performance improvement, a six sigma project (mesure) by nirav shah
Database performance improvement, a six sigma project (mesure) by nirav shah
 
MCA Daemon: Hybrid Throughput Analysis Beyond Basic Blocks
MCA Daemon: Hybrid Throughput Analysis Beyond Basic BlocksMCA Daemon: Hybrid Throughput Analysis Beyond Basic Blocks
MCA Daemon: Hybrid Throughput Analysis Beyond Basic Blocks
 
Automating Speed: A Proven Approach to Preventing Performance Regressions in ...
Automating Speed: A Proven Approach to Preventing Performance Regressions in ...Automating Speed: A Proven Approach to Preventing Performance Regressions in ...
Automating Speed: A Proven Approach to Preventing Performance Regressions in ...
 
Test Estimation
Test Estimation Test Estimation
Test Estimation
 
Mit16 30 f10_lec01
Mit16 30 f10_lec01Mit16 30 f10_lec01
Mit16 30 f10_lec01
 
SOFTWARE TESTING.pptx
SOFTWARE TESTING.pptxSOFTWARE TESTING.pptx
SOFTWARE TESTING.pptx
 
Time series
Time seriesTime series
Time series
 
11 generalsisation of fluent
11 generalsisation of fluent11 generalsisation of fluent
11 generalsisation of fluent
 
Schedule Analysis Methods - AACE 29R-03 Recommended.pdf
Schedule Analysis Methods - AACE 29R-03 Recommended.pdfSchedule Analysis Methods - AACE 29R-03 Recommended.pdf
Schedule Analysis Methods - AACE 29R-03 Recommended.pdf
 
Cs 331 Data Structures
Cs 331 Data StructuresCs 331 Data Structures
Cs 331 Data Structures
 
Schedulability of Rate Monotonic Algorithm using Improved Time Demand Analysi...
Schedulability of Rate Monotonic Algorithm using Improved Time Demand Analysi...Schedulability of Rate Monotonic Algorithm using Improved Time Demand Analysi...
Schedulability of Rate Monotonic Algorithm using Improved Time Demand Analysi...
 
Big Data Day LA 2016/ Use Case Driven track - Shaping the Role of Data Scienc...
Big Data Day LA 2016/ Use Case Driven track - Shaping the Role of Data Scienc...Big Data Day LA 2016/ Use Case Driven track - Shaping the Role of Data Scienc...
Big Data Day LA 2016/ Use Case Driven track - Shaping the Role of Data Scienc...
 
Scalable and Cost-Effective Model-Based Software Verification and Testing
Scalable and Cost-Effective Model-Based Software Verification and TestingScalable and Cost-Effective Model-Based Software Verification and Testing
Scalable and Cost-Effective Model-Based Software Verification and Testing
 
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
 
How to conduct abstract screening for systematic review – Pubrica
How to conduct abstract screening for systematic review – PubricaHow to conduct abstract screening for systematic review – Pubrica
How to conduct abstract screening for systematic review – Pubrica
 
Software Testing- Principles of testing- Mazenet Solution
Software Testing- Principles of testing- Mazenet SolutionSoftware Testing- Principles of testing- Mazenet Solution
Software Testing- Principles of testing- Mazenet Solution
 
Chapter 3 - Analytical Techniques
Chapter 3 - Analytical TechniquesChapter 3 - Analytical Techniques
Chapter 3 - Analytical Techniques
 
STUDY ON PROJECT MANAGEMENT THROUGH GENETIC ALGORITHM
STUDY ON PROJECT MANAGEMENT THROUGH GENETIC ALGORITHMSTUDY ON PROJECT MANAGEMENT THROUGH GENETIC ALGORITHM
STUDY ON PROJECT MANAGEMENT THROUGH GENETIC ALGORITHM
 
Real time Scheduling in Operating System for Msc CS
Real time Scheduling in Operating System for Msc CSReal time Scheduling in Operating System for Msc CS
Real time Scheduling in Operating System for Msc CS
 

Mais de Chris Carson

Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesChris Carson
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry SchedulingChris Carson
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodChris Carson
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion SchedulesChris Carson
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotChris Carson
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminChris Carson
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...Chris Carson
 
Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesChris Carson
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful MediationChris Carson
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule RevisionsChris Carson
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex ProjectChris Carson
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - AirportChris Carson
 
Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse WeatherChris Carson
 
Testimony Mistakes
Testimony MistakesTestimony Mistakes
Testimony MistakesChris Carson
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule DevelopmentChris Carson
 
Subcontractor Scheduling
Subcontractor SchedulingSubcontractor Scheduling
Subcontractor SchedulingChris Carson
 
Schedule Design PMI
Schedule Design PMISchedule Design PMI
Schedule Design PMIChris Carson
 
DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.Chris Carson
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2Chris Carson
 

Mais de Chris Carson (20)

Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation Schedules
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry Scheduling
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis Method
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion Schedules
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does Not
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract Admin
 
Claims Triage
Claims TriageClaims Triage
Claims Triage
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
 
Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel Schedules
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful Mediation
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex Project
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - Airport
 
Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse Weather
 
Testimony Mistakes
Testimony MistakesTestimony Mistakes
Testimony Mistakes
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
Subcontractor Scheduling
Subcontractor SchedulingSubcontractor Scheduling
Subcontractor Scheduling
 
Schedule Design PMI
Schedule Design PMISchedule Design PMI
Schedule Design PMI
 
DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2
 

Favorite Delay Analysis Methodologies Town Hall SEI

  • 1. Favorite Delay Analysis Methodologies Best Practices and Guidelines for Schedule Impact Analysis Volume 1 Chris Carson, PSP, CCM, PMP Corporate Director of Project Controls, Alpha Corporation Managing Director, Scheduling Excellence Initiative AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 2. Based on AACE International Recommended Practice No. 29R-03, Forensic Schedule Analysis” AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 3. Observational 3.1 Static – Gross (As-Planned v. As-Built, Single Base) 3.2 Static - Periodic (As-Planned v. As-Built, Multiple Base) 3.3 Dynamic – Contemporaneous “as-is” (Contemporaneous Period Analysis) 3.4 Dynamic – Contemporaneous “Split” (Bifurcated Contemporaneous Period Analysis) 3.5 Dynamic – Contemporaneous “Recreated” (Contemporaneous Period Analysis, Recreated) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 4. • 3.1 Static – Gross (As-Planned v. As-Built, Single Base) • Applicable only to simple projects, short in duration, with a CP that’s unlikely to shift • Easy to understand, inexpensive to create • Not suitable to long or complicated projects because the projects change and the measuring point does not. • Use when no update schedules available • Need as-planned schedule and as-built data AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 5. • 3.1 Static – Gross (As-Planned v. As-Built, Single Base) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 6. • 3.1 Static – Gross (As-Planned v. As-Built, Single Base) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 7. • 3.2. Static - Periodic (As-Planned v. As-Built, Multiple Base) • Similar to Single Base version • Measuring it in periods adds little since no new data? • May find updates useful – but if validated updates available, may use other methods that assess CP changes • Need as-planned schedule and as-built data • May provide for better presentation AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 8. • 3.2. Static - Periodic (As-Planned v. As-Built, Multiple Base) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 9. • 3.2. Static - Periodic (As-Planned v. As-Built, Multiple Base) Continued next slide AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 10. • 3.2. Static - Periodic (As-Planned v. As-Built, Multiple Base) Continued from previous slide AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 11. • 3.3. Dynamic – Contemporaneous “as-is” (Contemporaneous Period Analysis) • Applicable on complicated projects • Uses contemporaneous updates as new baselines • If done monthly, then it could be called a “Windows” analysis • Handles many problems like concurrency well AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 12. • 3.3. Dynamic – Contemporaneous “as-is” (CPA) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 13. • 3.3. Dynamic – Contemporaneous “as-is” (CPA) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 14. • 3.4. Dynamic – Contemporaneous “Split” (Bifurcated Contemporaneous Period) • Applicable on complicated projects • Uses contemporaneous updates as new baselines • If done monthly, then it could be called a “Windows” analysis • Handles many problems like concurrency well • The “split” separates Logic-type changes from Actual Progress AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 15. • 3.4. Dynamic – Contemporaneous “Split” (Bifurcated CPA) Continued next slide AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 16. • 3.4. Dynamic – Contemporaneous “Split” (Bifurcated CPA) Continued from previous slide AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 17. • 3.4. Dynamic – Contemporaneous “Split” (Bifurcated CPA) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 18. • 3.5. Dynamic – Contemporaneous “Recreated” (Contemporaneous Period Analysis) • Applicable on complicated projects • Uses RECREATED updates as new baselines • If done monthly, then it might be called a “Windows” analysis • Handles many problems like concurrency well • However – virtually all of the baselines are created by the analyst AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 19. • 3.5. Dynamic – Contemporaneous “Recreated” (Recreated CPA) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 20. • 3.5. Dynamic – Contemporaneous “Recreated” (Recreated CPA) Continued next slide AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 21. • 3.5. Dynamic – Contemporaneous “Recreated” (Recreated CPA) Continued from previous slide AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 22. • Modeled • 3.6 Additive – Single Base (Impacted as-planned) • 3.7 Additive – Multiple Base (Retrospective TIA) • 3.8 Subtractive – Single Simulation (Collapsed as-built) • 3.9 Subtractive – Multiple Simulation AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 23. • 3.6 Additive – Single Base (Impacted As-Planned) • Accuracy very dependent on inclusiveness of fragnets and accuracy of as-planned schedule. • Also dependent on changes in Critical Path from As-Planned • Easy to understand • Can be purely hypothetical, generally does not prevail in litigation • Concurrency not addressed AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 24. • 3.6 Additive – Single Base (Impacted As-Planned) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 25. • 3.6 Additive – Single Base (Impacted As-Planned) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 26. • 3.7 Additive – Multiple Base (Retrospective TIA) • Accuracy dependent on inclusiveness of fragnets and accuracy of updates – however more likely to include both owner and contractor issues • Easy to understand • No as-built required (although still useful) • Updates useful if used (failure to correlate creates problem) • Associated with actual events • Concurrency easily addressed by a two step process AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 27. • 3.7 Additive – Multiple Base (Retrospective TIA) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 28. • 3.7 Additive – Multiple Base (Retrospective TIA) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 29. • 3.8 Subtractive – Single Simulation (Collapsed As- Built) • Accuracy dependent on creation of after the fact logic • Easy to understand • Uses actual events • Can be viewed as hypothetical • Critical path can be difficult to identify AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 30. • 3.8 Subtractive – Single Simulation (Collapsed As-Built) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 31. • 3.8 Subtractive – Single Simulation (Collapsed As-Built) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 32. • 3.9 Subtractive – Multiple Simulation • Only known practitioner – Long International? • Accuracy still dependent on creation of after the fact logic • Uses actual Events • Can be viewed as hypothetical • Critical path can be difficult to identify AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 33. • 3.1 Static – Gross (As-Planned v. As-Built, Single Base) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 34. • 3.1 Static – Gross (As-Planned v. As-Built, Single Base) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 35. Forensic Use of METHOD Analysis 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 Non-Compensable OK OK OK OK OK OK OK OK Time Extension Compensable Delay OK OK OK OK OK OK Right to Finish Early OK Compensable Delay Entitlement to Early OK OK OK OK OK OK OK OK Completion Bonus Disruption Without OK OK OK OK OK OK OK Project Delay Constructive OK OK OK Acceleration AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 36. AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 37. AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 38. • AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 39. • Must allow the source data to bear on the selection process • Cannot predetermine a technique based on personal preference • Balance client needs, budget, and time with sound analysis philosophy AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 40. • Observational? • Count • Modeled? • Count AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 41. • Observational • Observational • 3.1 Static – Gross • Count • 3.2 Static - Periodic • Count • 3.3 Dynamic – Contemporaneous “as-is” • Count • 3.4 Dynamic – Contemporaneous “Split” • Count • 3.5 Dynamic – Contemporaneous • Count “Recreated” AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 42. • Modeled • Modeled • 3.6 Additive – Single Base • Count • 3.7 Additive – Multiple Base • Count • 3.8 Subtractive – Single Simulation • Count • 3.9 Subtractive – Multiple Simulation • Count AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis