SlideShare uma empresa Scribd logo
1 de 28
Solved Example
Example
 Consider the following project to
manufacture a simple mobile stone crasher.
The list of each activities, their relationship,
and the time required to complete them are
given in the table. We are interested to find
the time it will take to complete this project.
What jobs are critical to the completion of
the project in time, etc?
List of Activities
Activity Symbol Duration
(weeks)
Restriction
Preliminary design A 3 A < B, Cl
Engineering analysis B 1 B < Dl, F, H
Prepare layout I Cl 2 Cl < C2, Dl
prepare layout II C2 2 C2 < E
Prepare material request Dl 1 Dl < D2
Receive requested material D2 1 D2 < E
Fabricate Parts E 4 E < J
Requisition Parts F 1 F < G
Receive Parts G 2 G < J
Place subcontracts H 1 H < I
Receive subcontracted parts I 5 I < J
Assemble J 2 I < K
Inspect and test K 1
Solution:
 First the network diagram is constructed
 Then, it is necessary to find out the earliest
and latest completion time of for each
activity in the net work.
 The earliest and the latest times are re-
calculated by using ‘forward pass’ and
‘backward pass’ computations, respectively.
 The solution now starts by the forward pass
computation.
Step1. Determination of Earliest Time )
( j
E
 Forward Pass Computation
 The purpose of the forward pass computation is to find out
earliest start times for all the activities.
 For this, it is necessary to assign some initial value to the
starting node 10.
 Usually this value is taken to be zero so that the subsequent
earliest time could be interpreted as the project duration up to
that point in question.
 Rules for the computation are as follows:
0
10 
E
j
E
]
.[ ij
i
j D
E
Max
E 

Rule 1. Initial event is supposed to occur at time equal to
zero, that is,
Rule 2. Any activity can start immediately when all preceding
activities are completed.
for node j is given by
0
10 
E
]
.[ 20
20 i
i D
E
Max
E 

10
i 
Rule 3. Repeat step2 for the next eligible activity until the end
node is reached.
and
For node 20, node 10 is the only predecessor and hence
contains only one element. Therefore,
]
.[ ij
i
j D
E
Max
E 

3
3
0
20
,
10
10
20 



 D
E
E
,
,
5
2
3
21
,
20
20
21 



 D
E
E
4
1
3
30
,
20
20
30 



 D
E
E
5
1
4
50
,
30
30
50 



 D
E
E
5
1
4
60
,
30
30
60 



 D
E
E
5
]
4
0
4
,
5
0
5
.[ 31
,
30
30
31
,
21
21
31 








 D
E
D
E
Max
E
32
E
6
1
5
32
,
31
31
32 



 D
E
E
The collection i consists of node 21 and 30 that are preceding node
31, Therefore,
and values of can be computed as:
Once again, for node 40 and 70;
]
.[ 31
,
31 i
i D
E
Max
E 

Consider node 31, where there are two emerging
activities, i.e.
7
]
7
1
6
,
7
2
5
.[ 40
,
32
32
40
,
21
21
40 








 D
E
D
E
Max
E
11
]
10
5
5
,
7
2
5
,
11
4
7
.[ 70
,
60
60
70
,
50
50
70
,
40
40
70 












 D
E
D
E
D
E
Max
E
80
E 90
E
13
2
11
80
,
70
70
80 



 D
E
E
14
1
13
90
,
80
80
90 



 D
E
E
and values of , and can be computed as:
 From this computation, it can be inferred that this job will take 14
days to finish as this the longest path of the network.
 Activities along this longest path are:– 10 – 20 – 21 – 40 70 – 80 –
90. This longest path is called the critical path. In any network, it
is not possible that there can be only one critical path.
Step2. Determination of Latest Time )
( i
L
Backward Pass Computation
 In forward pass computation, the earliest time when a
particular activity will be completed is known.
 It is also seen that some activities are not critical to
the completion of the job.
 The question a manager would like to ask is: Can their
starting time be delayed so that the total completion
time is still the same?
 Such a question may arise while scheduling the resources
such as manpower, equipment, finance and so on.
 If delay is allowable, then what can be the maximum
delay? For this, the latest time for various activities
desired.
 The backward pass computation procedure is used to
calculate the latest time for various activities.
S
i
i T
or
E
L 
S
T
i
E
]
[
. ij
j
j
i D
-
L
Min
L 
Rule 1. Set
Where is the scheduled date for completion and
is the earliest terminal time.
i.e. the latest time for activities is the minimum of the
latest time of all succeeding activities reducing their
activity time.
Rule 3.Repeat rule 2 until starting activity reached.
Rule 2.
14
L90 
80
L
70
L
60
L
50
L
40
L
32
L
31
L
Latest times for activities of the network are calculated below:
By rule 1, set
.Applying rule 2, it is to determine
90
j
for
13
1
14
}
D
-
{L
Min.
L j
80,
j
j
80 




11
2
3
1
D
-
}
D
-
{L
Min.
L 70,80
80
j
70,
j
j
70 



 L
6
5
11
D
-
L
}
D
-
{L
Min.
L 60,70
70
j
60,
j
j
60 




9
2
11
D
-
L
}
D
-
{L
Min.
L 50,70
50
j
50,
j
j
50 




(j contains only one node 80)
(j contains node 70)
(j contains node 70)
7
4
11
D
-
L
}
D
-
{L
Min.
L 40,70
40
j
40,
j
j
40 




6
1
7
D
-
L
}
D
-
{L
Min.
L 32,40
32
j
32,
j
j
32 




5
1
6
D
-
L
}
D
-
{L
Min.
L 32,32
31
j
31,
j
j
31 




(j contains node 70)
(j contains node 40)
(j contains node 32)
Now consider node21, for this node, there are two succeeding
activities, namely 21 – 40, and 21 – 31. Hence,
5
5
0
5
5
2
7
.
.
31
,
21
31
40
,
21
40





















  Min
D
L
D
L
Min
}
D
-
{L
Min.
L j
21,
j
40)
(31,
j
21
3
3
1
4
3
2
5
.
.
30
,
20
30
21
,
20
21





















  Min
D
L
D
L
Min
}
D
-
{L
Min.
L j
21,
j
30)
(21,
j
20
4
4
1
5
4
1
5
5
0
5
.
.
31
,
60
31
31
,
50
31
31
,
30
31
































  Min
D
L
D
L
D
L
Min
}
D
-
{L
Min.
L j
30,
j
60)
50,
(31,
j
30
Similarly, for node 20, and 30,
0
3
D
-
L
}
D
-
{L
Min.
L 10,20
j
10,
j
j
10 



 3
20
0
L10 
E
L i
i 
0
L10 
and like the other one, for node 10,
The minimum value of
is no surprising result. Since, started with
, it is always possible to have
If this is not so, it means that some error is made in calculations of
forward pass or backward pass values.
Network diagram with critical path
Recall that path 10 – 20 – 21 – 40 – 70 – 80 – 90
was defined as the critical path of this network.
Along this path, it is observed that the latest
and earliest times are the same implying that any
activity along this path cannot be delayed
without affecting the duration of the project.
Step 3. Computation of Float )
( f
L
By definition, for activity 60 – 70, the float is one day
1
5
6
60
60 


 E
L
This float represents the amount by which this particular activity
can be delayed without affecting the total time of the project.
 Also, by definition, free float, if any will exist only on
the activities merge points.
 To illustrate the concept of free float, consider path
10 – 20 – 30 – 50 – 70, total float on activity 50 - 70 is
four days and since this is the last activity prior to
merging two activities, this float is free float also.
 Similarly, consider the activity 30-50 which has a total
float of 4 days but has zero free float because 4 day
of free float is due to the activity 50-70.
 If activity 30-50 is delayed up to four days,
the early start time of no activity in the
network will be affected.
 Therefore, the concept of free float clearly
states that the use of free float time will
not influence any succeeding activity float
time.
Step 4. To Identify Critical Path
 Identifying the critical path is a byproduct
of boundary time calculations. A critical
activity has no leeway in scheduling and
consequently zero total float. It is important
to note that the value of slack, associated
with an event, determines how critical that
event is. The less the slack, the more critical
an event is.
 The earlier calculation shows that the path or paths
which have zero float are called the critical ones or in
other words, a critical path is the one which connects
the events having zero total float or a minimum slack
time.
 If this logic is extended further more, it would
provide a guide rule to determine the next most
critical path, and so on.
 Such information will be useful for managers in the
control of project. In this example, path 10 – 20 – 30 –
60 – 70 – 80 - 90 happens to be next to critical path
because it has float of one day on many of its
activities.
Activity Duration
Start Finish
Total Float
Earliest Latest Earliest Latest
(1) (2) (3) (6)
A 3 0 0 3 3 0
B 1 3 4 4 5 1
C1 2 3 3 5 5 0
C2 2 5 5 7 7 0
D1 1 5 5 6 6 0
D2 1 6 6 7 7 0
E 4 7 7 11 11 0
F 1 4 8 5 9 4
G 2 5 9 7 11 4
H 1 4 5 5 6 1
I 5 5 6 10 11 1
J 2 11 11 13 13 0
K 1 13 13 14 14 0
i
E (2)
-
(6)
(4)  (2)
(3)
(5) 
 (3)
-
(4)
(7) 
ij
D
j)
-
(i
Boundary Times Duration for the Start and Finish of Activities

Mais conteúdo relacionado

Mais procurados

Basic structures in vhdl
Basic structures in vhdlBasic structures in vhdl
Basic structures in vhdl
Raj Mohan
 

Mais procurados (20)

Programmable Logic Array(PLA) & Programmable Array Logic(PAL)
Programmable Logic Array(PLA) & Programmable Array Logic(PAL)Programmable Logic Array(PLA) & Programmable Array Logic(PAL)
Programmable Logic Array(PLA) & Programmable Array Logic(PAL)
 
Network analysis and synthesis pdddfff
Network  analysis and synthesis pdddfffNetwork  analysis and synthesis pdddfff
Network analysis and synthesis pdddfff
 
Lec1 - Analog and Digital systems
Lec1 - Analog and Digital systemsLec1 - Analog and Digital systems
Lec1 - Analog and Digital systems
 
Basic structures in vhdl
Basic structures in vhdlBasic structures in vhdl
Basic structures in vhdl
 
Basics of plc_programming1
Basics of plc_programming1Basics of plc_programming1
Basics of plc_programming1
 
Ripple Carry Adder
Ripple Carry AdderRipple Carry Adder
Ripple Carry Adder
 
Tellegen’s-Substitution-Reciprocity-Theorem.ppt
Tellegen’s-Substitution-Reciprocity-Theorem.pptTellegen’s-Substitution-Reciprocity-Theorem.ppt
Tellegen’s-Substitution-Reciprocity-Theorem.ppt
 
Plc networking basics - controllogix
Plc networking basics - controllogixPlc networking basics - controllogix
Plc networking basics - controllogix
 
Network Analysis and Synthesis
Network Analysis and SynthesisNetwork Analysis and Synthesis
Network Analysis and Synthesis
 
Clippers and clampers
Clippers and clampersClippers and clampers
Clippers and clampers
 
Latches &amp; flip flop
Latches &amp; flip flopLatches &amp; flip flop
Latches &amp; flip flop
 
Verilog operators
Verilog operatorsVerilog operators
Verilog operators
 
adder and subtractor
 adder and subtractor adder and subtractor
adder and subtractor
 
Unidad aritmetica logica
Unidad aritmetica logicaUnidad aritmetica logica
Unidad aritmetica logica
 
Chapter 01 Basic Principles of Digital Systems
Chapter 01 Basic Principles of Digital SystemsChapter 01 Basic Principles of Digital Systems
Chapter 01 Basic Principles of Digital Systems
 
Project report latest
Project report latestProject report latest
Project report latest
 
Allenbradley Control Logix PLC Network Architecture
Allenbradley Control Logix PLC Network  ArchitectureAllenbradley Control Logix PLC Network  Architecture
Allenbradley Control Logix PLC Network Architecture
 
555 timer
555 timer555 timer
555 timer
 
Vlsi design flow
Vlsi design flowVlsi design flow
Vlsi design flow
 
Polar plot
Polar plotPolar plot
Polar plot
 

Semelhante a Chapter-2 Solved examples.ppt

470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
Nitin137794
 
MP assignment for printing
MP assignment for printingMP assignment for printing
MP assignment for printing
Hieu Pham
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
Debanjan15
 
Lec 9 &amp; 10 chapter 5 project scheduling
Lec 9 &amp; 10 chapter 5 project schedulingLec 9 &amp; 10 chapter 5 project scheduling
Lec 9 &amp; 10 chapter 5 project scheduling
Syed Hamza
 

Semelhante a Chapter-2 Solved examples.ppt (20)

criticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfcriticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdf
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
MP assignment for printing
MP assignment for printingMP assignment for printing
MP assignment for printing
 
Networktechniques
NetworktechniquesNetworktechniques
Networktechniques
 
Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel Template
 
Ii. pert cpm
Ii. pert cpmIi. pert cpm
Ii. pert cpm
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniques
 
Network Techniques for Project Management
Network Techniques for Project ManagementNetwork Techniques for Project Management
Network Techniques for Project Management
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
Operation research's CPM techniques
Operation research's CPM techniques Operation research's CPM techniques
Operation research's CPM techniques
 
Lec 9 &amp; 10 chapter 5 project scheduling
Lec 9 &amp; 10 chapter 5 project schedulingLec 9 &amp; 10 chapter 5 project scheduling
Lec 9 &amp; 10 chapter 5 project scheduling
 
PERT-CPM PPT.pptx
PERT-CPM PPT.pptxPERT-CPM PPT.pptx
PERT-CPM PPT.pptx
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 
Cpmprt
CpmprtCpmprt
Cpmprt
 
Unit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chainUnit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chain
 
CPM.pptx
CPM.pptxCPM.pptx
CPM.pptx
 
Critical path method (CPM).pptx
Critical path method (CPM).pptxCritical path method (CPM).pptx
Critical path method (CPM).pptx
 

Mais de BetshaTizazu2

Proposal power point draft.pptx
Proposal power point draft.pptxProposal power point draft.pptx
Proposal power point draft.pptx
BetshaTizazu2
 
Presentation Proposal.pptx
Presentation Proposal.pptxPresentation Proposal.pptx
Presentation Proposal.pptx
BetshaTizazu2
 
EYAYA PROJECT PROGRES APRIL 30.pptx
EYAYA PROJECT PROGRES APRIL 30.pptxEYAYA PROJECT PROGRES APRIL 30.pptx
EYAYA PROJECT PROGRES APRIL 30.pptx
BetshaTizazu2
 
Project Implementation, SM 2015 1.pptx
Project Implementation, SM 2015 1.pptxProject Implementation, SM 2015 1.pptx
Project Implementation, SM 2015 1.pptx
BetshaTizazu2
 
Book Chapter Review of the Title 01.pptx
Book Chapter Review  of the Title 01.pptxBook Chapter Review  of the Title 01.pptx
Book Chapter Review of the Title 01.pptx
BetshaTizazu2
 
The Prospects Of Economic Growthhhh...pptx
The Prospects Of Economic Growthhhh...pptxThe Prospects Of Economic Growthhhh...pptx
The Prospects Of Economic Growthhhh...pptx
BetshaTizazu2
 
Presentation for research team.ppt
Presentation for research team.pptPresentation for research team.ppt
Presentation for research team.ppt
BetshaTizazu2
 
Soft Skills 2011 Secretariat of the House of Federation .ppt
Soft Skills 2011 Secretariat of the House of Federation .pptSoft Skills 2011 Secretariat of the House of Federation .ppt
Soft Skills 2011 Secretariat of the House of Federation .ppt
BetshaTizazu2
 
project_risk_mgmt_final 1.ppt
project_risk_mgmt_final 1.pptproject_risk_mgmt_final 1.ppt
project_risk_mgmt_final 1.ppt
BetshaTizazu2
 
Feasibility Analysis.ppt
Feasibility Analysis.pptFeasibility Analysis.ppt
Feasibility Analysis.ppt
BetshaTizazu2
 
Wal-mart’s and Hard Rock.pptx
Wal-mart’s and Hard Rock.pptxWal-mart’s and Hard Rock.pptx
Wal-mart’s and Hard Rock.pptx
BetshaTizazu2
 

Mais de BetshaTizazu2 (20)

Proposal power point draft.pptx
Proposal power point draft.pptxProposal power point draft.pptx
Proposal power point draft.pptx
 
Presentation Proposal.pptx
Presentation Proposal.pptxPresentation Proposal.pptx
Presentation Proposal.pptx
 
EYAYA PROJECT PROGRES APRIL 30.pptx
EYAYA PROJECT PROGRES APRIL 30.pptxEYAYA PROJECT PROGRES APRIL 30.pptx
EYAYA PROJECT PROGRES APRIL 30.pptx
 
Project Implementation, SM 2015 1.pptx
Project Implementation, SM 2015 1.pptxProject Implementation, SM 2015 1.pptx
Project Implementation, SM 2015 1.pptx
 
ch01.ppt
ch01.pptch01.ppt
ch01.ppt
 
Book Chapter Review of the Title 01.pptx
Book Chapter Review  of the Title 01.pptxBook Chapter Review  of the Title 01.pptx
Book Chapter Review of the Title 01.pptx
 
The Prospects Of Economic Growthhhh...pptx
The Prospects Of Economic Growthhhh...pptxThe Prospects Of Economic Growthhhh...pptx
The Prospects Of Economic Growthhhh...pptx
 
Presentation for research team.ppt
Presentation for research team.pptPresentation for research team.ppt
Presentation for research team.ppt
 
Soft Skills 2011 Secretariat of the House of Federation .ppt
Soft Skills 2011 Secretariat of the House of Federation .pptSoft Skills 2011 Secretariat of the House of Federation .ppt
Soft Skills 2011 Secretariat of the House of Federation .ppt
 
Positive Atitude.ppt
Positive Atitude.pptPositive Atitude.ppt
Positive Atitude.ppt
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
Crashing and Updating.ppt
Crashing and Updating.pptCrashing and Updating.ppt
Crashing and Updating.ppt
 
ch05_crashing.ppt
ch05_crashing.pptch05_crashing.ppt
ch05_crashing.ppt
 
project_risk_mgmt_final 1.ppt
project_risk_mgmt_final 1.pptproject_risk_mgmt_final 1.ppt
project_risk_mgmt_final 1.ppt
 
Feasibility Analysis.ppt
Feasibility Analysis.pptFeasibility Analysis.ppt
Feasibility Analysis.ppt
 
PCCC Ch-1.ppt
PCCC Ch-1.pptPCCC Ch-1.ppt
PCCC Ch-1.ppt
 
Wal-mart’s and Hard Rock.pptx
Wal-mart’s and Hard Rock.pptxWal-mart’s and Hard Rock.pptx
Wal-mart’s and Hard Rock.pptx
 
Biruk POM.pptx
Biruk POM.pptxBiruk POM.pptx
Biruk POM.pptx
 
Weaver_Concept_Selection_20080729.ppt
Weaver_Concept_Selection_20080729.pptWeaver_Concept_Selection_20080729.ppt
Weaver_Concept_Selection_20080729.ppt
 
hiwot FSCM1.pptx
hiwot FSCM1.pptxhiwot FSCM1.pptx
hiwot FSCM1.pptx
 

Último

Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
ciinovamais
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
ZurliaSoop
 

Último (20)

Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Dyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptxDyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptx
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 

Chapter-2 Solved examples.ppt

  • 2. Example  Consider the following project to manufacture a simple mobile stone crasher. The list of each activities, their relationship, and the time required to complete them are given in the table. We are interested to find the time it will take to complete this project. What jobs are critical to the completion of the project in time, etc?
  • 3. List of Activities Activity Symbol Duration (weeks) Restriction Preliminary design A 3 A < B, Cl Engineering analysis B 1 B < Dl, F, H Prepare layout I Cl 2 Cl < C2, Dl prepare layout II C2 2 C2 < E Prepare material request Dl 1 Dl < D2 Receive requested material D2 1 D2 < E Fabricate Parts E 4 E < J Requisition Parts F 1 F < G Receive Parts G 2 G < J Place subcontracts H 1 H < I Receive subcontracted parts I 5 I < J Assemble J 2 I < K Inspect and test K 1
  • 4. Solution:  First the network diagram is constructed
  • 5.  Then, it is necessary to find out the earliest and latest completion time of for each activity in the net work.  The earliest and the latest times are re- calculated by using ‘forward pass’ and ‘backward pass’ computations, respectively.  The solution now starts by the forward pass computation.
  • 6. Step1. Determination of Earliest Time ) ( j E  Forward Pass Computation  The purpose of the forward pass computation is to find out earliest start times for all the activities.  For this, it is necessary to assign some initial value to the starting node 10.  Usually this value is taken to be zero so that the subsequent earliest time could be interpreted as the project duration up to that point in question.  Rules for the computation are as follows:
  • 7. 0 10  E j E ] .[ ij i j D E Max E   Rule 1. Initial event is supposed to occur at time equal to zero, that is, Rule 2. Any activity can start immediately when all preceding activities are completed. for node j is given by
  • 8. 0 10  E ] .[ 20 20 i i D E Max E   10 i  Rule 3. Repeat step2 for the next eligible activity until the end node is reached. and For node 20, node 10 is the only predecessor and hence contains only one element. Therefore,
  • 9. ] .[ ij i j D E Max E   3 3 0 20 , 10 10 20      D E E , , 5 2 3 21 , 20 20 21      D E E 4 1 3 30 , 20 20 30      D E E 5 1 4 50 , 30 30 50      D E E 5 1 4 60 , 30 30 60      D E E
  • 10. 5 ] 4 0 4 , 5 0 5 .[ 31 , 30 30 31 , 21 21 31           D E D E Max E 32 E 6 1 5 32 , 31 31 32      D E E The collection i consists of node 21 and 30 that are preceding node 31, Therefore, and values of can be computed as: Once again, for node 40 and 70; ] .[ 31 , 31 i i D E Max E   Consider node 31, where there are two emerging activities, i.e.
  • 11. 7 ] 7 1 6 , 7 2 5 .[ 40 , 32 32 40 , 21 21 40           D E D E Max E 11 ] 10 5 5 , 7 2 5 , 11 4 7 .[ 70 , 60 60 70 , 50 50 70 , 40 40 70               D E D E D E Max E 80 E 90 E 13 2 11 80 , 70 70 80      D E E 14 1 13 90 , 80 80 90      D E E and values of , and can be computed as:
  • 12.  From this computation, it can be inferred that this job will take 14 days to finish as this the longest path of the network.  Activities along this longest path are:– 10 – 20 – 21 – 40 70 – 80 – 90. This longest path is called the critical path. In any network, it is not possible that there can be only one critical path.
  • 13. Step2. Determination of Latest Time ) ( i L Backward Pass Computation  In forward pass computation, the earliest time when a particular activity will be completed is known.  It is also seen that some activities are not critical to the completion of the job.  The question a manager would like to ask is: Can their starting time be delayed so that the total completion time is still the same?  Such a question may arise while scheduling the resources such as manpower, equipment, finance and so on.
  • 14.  If delay is allowable, then what can be the maximum delay? For this, the latest time for various activities desired.  The backward pass computation procedure is used to calculate the latest time for various activities.
  • 15. S i i T or E L  S T i E ] [ . ij j j i D - L Min L  Rule 1. Set Where is the scheduled date for completion and is the earliest terminal time. i.e. the latest time for activities is the minimum of the latest time of all succeeding activities reducing their activity time. Rule 3.Repeat rule 2 until starting activity reached. Rule 2.
  • 16. 14 L90  80 L 70 L 60 L 50 L 40 L 32 L 31 L Latest times for activities of the network are calculated below: By rule 1, set .Applying rule 2, it is to determine
  • 17. 90 j for 13 1 14 } D - {L Min. L j 80, j j 80      11 2 3 1 D - } D - {L Min. L 70,80 80 j 70, j j 70      L 6 5 11 D - L } D - {L Min. L 60,70 70 j 60, j j 60      9 2 11 D - L } D - {L Min. L 50,70 50 j 50, j j 50      (j contains only one node 80) (j contains node 70) (j contains node 70)
  • 18. 7 4 11 D - L } D - {L Min. L 40,70 40 j 40, j j 40      6 1 7 D - L } D - {L Min. L 32,40 32 j 32, j j 32      5 1 6 D - L } D - {L Min. L 32,32 31 j 31, j j 31      (j contains node 70) (j contains node 40) (j contains node 32) Now consider node21, for this node, there are two succeeding activities, namely 21 – 40, and 21 – 31. Hence,
  • 19. 5 5 0 5 5 2 7 . . 31 , 21 31 40 , 21 40                        Min D L D L Min } D - {L Min. L j 21, j 40) (31, j 21 3 3 1 4 3 2 5 . . 30 , 20 30 21 , 20 21                        Min D L D L Min } D - {L Min. L j 21, j 30) (21, j 20 4 4 1 5 4 1 5 5 0 5 . . 31 , 60 31 31 , 50 31 31 , 30 31                                   Min D L D L D L Min } D - {L Min. L j 30, j 60) 50, (31, j 30 Similarly, for node 20, and 30,
  • 20. 0 3 D - L } D - {L Min. L 10,20 j 10, j j 10      3 20 0 L10  E L i i  0 L10  and like the other one, for node 10, The minimum value of is no surprising result. Since, started with , it is always possible to have If this is not so, it means that some error is made in calculations of forward pass or backward pass values.
  • 21. Network diagram with critical path
  • 22. Recall that path 10 – 20 – 21 – 40 – 70 – 80 – 90 was defined as the critical path of this network. Along this path, it is observed that the latest and earliest times are the same implying that any activity along this path cannot be delayed without affecting the duration of the project.
  • 23. Step 3. Computation of Float ) ( f L By definition, for activity 60 – 70, the float is one day 1 5 6 60 60     E L This float represents the amount by which this particular activity can be delayed without affecting the total time of the project.
  • 24.  Also, by definition, free float, if any will exist only on the activities merge points.  To illustrate the concept of free float, consider path 10 – 20 – 30 – 50 – 70, total float on activity 50 - 70 is four days and since this is the last activity prior to merging two activities, this float is free float also.  Similarly, consider the activity 30-50 which has a total float of 4 days but has zero free float because 4 day of free float is due to the activity 50-70.
  • 25.  If activity 30-50 is delayed up to four days, the early start time of no activity in the network will be affected.  Therefore, the concept of free float clearly states that the use of free float time will not influence any succeeding activity float time.
  • 26. Step 4. To Identify Critical Path  Identifying the critical path is a byproduct of boundary time calculations. A critical activity has no leeway in scheduling and consequently zero total float. It is important to note that the value of slack, associated with an event, determines how critical that event is. The less the slack, the more critical an event is.
  • 27.  The earlier calculation shows that the path or paths which have zero float are called the critical ones or in other words, a critical path is the one which connects the events having zero total float or a minimum slack time.  If this logic is extended further more, it would provide a guide rule to determine the next most critical path, and so on.  Such information will be useful for managers in the control of project. In this example, path 10 – 20 – 30 – 60 – 70 – 80 - 90 happens to be next to critical path because it has float of one day on many of its activities.
  • 28. Activity Duration Start Finish Total Float Earliest Latest Earliest Latest (1) (2) (3) (6) A 3 0 0 3 3 0 B 1 3 4 4 5 1 C1 2 3 3 5 5 0 C2 2 5 5 7 7 0 D1 1 5 5 6 6 0 D2 1 6 6 7 7 0 E 4 7 7 11 11 0 F 1 4 8 5 9 4 G 2 5 9 7 11 4 H 1 4 5 5 6 1 I 5 5 6 10 11 1 J 2 11 11 13 13 0 K 1 13 13 14 14 0 i E (2) - (6) (4)  (2) (3) (5)   (3) - (4) (7)  ij D j) - (i Boundary Times Duration for the Start and Finish of Activities