UP3B KALBAR
PROGRAM LANGIT BIRU
PONTIANAK BEBAS
LAYANGAN
www.pln.co.id |
Konfigurasi Silicon Rubber Eksisting Tower SUTT Siantan – Sei Raya
T. 041 T. 040 T. 039
Phasa R & T Phasa R & T
• Pekerjaan dimulai tanggal 14
Februari 2020 dan selesai
tanggal 18 Februari 2020
• Span T041 – 042 dipasang
silicon rubber (SR) Pada
Phasa R 150 meter dan T
sepanjang 150 meter
• Total penggunaan SR 600
Meter untuk Line 1 dan Line 2
Progress Penyelesaian (41 – 42)
• Pekerjaan dimulai tanggal 14
Februari 2020 dan selesai
tanggal 18 Februari 2020
• Span T040 – 041 dipasang
silicon rubber (SR) Pada
Phasa R 150 meter dan T
sepanjang 150 meter
• Total penggunaan SR 600
Meter untuk Line 1 dan Line 2
Progress Penyelesaian (40 – 41)
T. 001
5.73 kM 5.61 kM 5.49 kM
T. A T. B
75
meter
75
meter
150
meter
Detail Pemsangan Silicon Rubber Tower Transmisi
www.pln.co.id |
Pemasangan pada T.58 T.59 T.60 T.61 SeiRaya -
Siantan
T. 061 T. 060 T. 059
Phasa R & T Phasa R & S
• Pekerjaan dimulai tanggal 14
Februari 2020 dan selesai
tanggal 29 Februari 2020
• Span T040 – 041 dipasang
silicon rubber (SR) Pada
Phasa R 150 meter dan T
sepanjang 150 meter
• Total penggunaan SR 600
Meter untuk Line 1 dan Line 2
Progress Penyelesaian (60 – 61)
• Pekerjaan dimulai tanggal 14
Februari 2020 dan selesai
tanggal 29 Februari 2020
• Span T040 – 041 dipasang
silicon rubber (SR) Pada Phasa
R dan S Line 1 dan Line 2
Phasa R dan T sepanjang @150
Meter per phasa. (karena
andongan terlalu rendah )
• Total penggunaan SR 600 Meter
untuk Line 1 dan Line 2
Progress Penyelesaian (59 - 60)
T. 58
9.55 kM 9.25 kM 8.95 kM 8.64 kM
• Pekerjaan dimulai tanggal 14
Februari 2020 dan selesai
tanggal 29 Februari 2020
• Span T040 – 041 dipasang
silicon rubber (SR) Pada
Phasa R dan T sepanjang 300
Meter per phasa.
• Total penggunaan SR 600
Meter untuk Line 1 dan Line 2
Progress Penyelesaian (58 - 59)
Phasa R & T
Konfigurasi Silicon Rubber Eksisting Tower SUTT Siantan – Sei Raya
www.pln.co.id |
Gambar Rencana Pengaman Transmisi
Material Penghalang Kawat Layang Senar Nylon Polyamide
TOWER A
TOWER B
Keterangan
Besi Diagonal (Galvanis uk 4,4 cm)
Joint (Isolator)
Besi Horizontal (Galvanis uk 4,4 cm)
Rod Vertikal High Density
Polyetthylene (HDPE)/Isolator Polymer
Rencana
Shielding Tower
(Konduktor)
Terhadap Kawat Layang
Penghalang Kawat Layang
(Senar Nylon Polyamide (PA) uk 2 mm )
GSW
www.pln.co.id |
Gambar Rencana Pengaman Transmisi
Teknis Ukuran
www.pln.co.id |
Gambar Rencana Pengaman Transmisi
Material Penghalang Kawat Layang Kabel
Telfon
www.pln.co.id |
Gambar Rencana Pengaman Transmisi
Material Penghalang Kawat Layang Kabel
Telfon
www.pln.co.id |
Gambar Rencana Pengaman Transmisi
Teknis Ukuran
www.pln.co.id |
Kajian Operasional & Teknis
Melalui analisis jarak gangguan layangan pada tahun 2019-2020 di Line Siantan-Sei Raya maka rekomendasi titik
pemasangan akan difokuskan pada Span Tower 46-47, 52-53, 55-56, 57-58, 61-62* dan 62-63*
*note : rekomendasi juga berdasarkan titik tower yang sudah dilakukan perkuatan pondasi
0
1
2
3
4
5
6
7
8
GI
STN
T.001
T.002
T.003
T.004
T.005
T.006
T.007
T.008
T.009
T.010
T.011
T.012
T.013
T.014
T.015
T.016
T.017
T.018
T.019
T.020
T.021
T.022
T.023
T.024
T.025
T.026
T.027
T.028
T.029
T.030
T.031
T.032
T.033
T.034
T.035
T.036
T.037
T.038
T.039
T.040
T.041
T.042
T.043
T.044
T.045
T.046
T.047
T.048
T.049
T.050
T.051
T.052
T.053
T.054
T.055
T.056
T.057
T.058
T.059
T.060
T.061
T.062
T.063
T.064
T.065
Frekuensi Jarak Gangguan Layangan
Line Siantan - Sei Raya (2019-2020)
Rencana Pasang
www.pln.co.id |
Progress Rencana Pengaman Transmisi
No Uraian Kegiatan Progress & Keterangan PIC
1
Pengujian Mekanik dan Tegangan Tinggi Material ke
Lab UNTAN dan POLNEP
Sudah bersurat M-1 April
Rencana Pengujian M-3 April
PENYALURAN UP3B SIS KALBAR & ULTG
PONTIANAK
2 Pengajuan Kajian Teknis Pemasangan ke PUSLITBANG
Sudah bersurat M-1 April
Rencana Kajian dan Diskusi M-3 dan M-4
April
PENYALURAN UP3B SIS KALBAR & ULTG
PONTIANAK
3 Penentuan Rekomendasi Lokasi Pemasangan
Span Tower 46-47, 52-53, 55-56, 57-58,
61-62 dan 62-63 (Siantan-Sei Raya)
PENYALURAN UP3B SIS KALBAR & ULTG
PONTIANAK
4 Rencana Pemasangan
M-5 Mei (Setelah Periode Siaga), Butuh
Pemadaman Line
PENYALURAN UP3B SIS KALBAR & ULTG
PONTIANAK
Alat Uji Mekanis dan Tegangan Tinggi Material Nylon
www.pln.co.id |
Jaring Pengaman GI
Sekian dan
Terima Kasih

Mais conteúdo relacionado

Destaque

How Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental HealthHow Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental Health
ThinkNow
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
Kurio // The Social Media Age(ncy)
 

Destaque (20)

Product Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage EngineeringsProduct Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage Engineerings
 
How Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental HealthHow Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental Health
 
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdfAI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
 
Skeleton Culture Code
Skeleton Culture CodeSkeleton Culture Code
Skeleton Culture Code
 
PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024
 
Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)
 
How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
 
Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024
 
5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary
 
ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd
 
Getting into the tech field. what next
Getting into the tech field. what next Getting into the tech field. what next
Getting into the tech field. what next
 
Google's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search IntentGoogle's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search Intent
 
How to have difficult conversations
How to have difficult conversations How to have difficult conversations
How to have difficult conversations
 
Introduction to Data Science
Introduction to Data ScienceIntroduction to Data Science
Introduction to Data Science
 
Time Management & Productivity - Best Practices
Time Management & Productivity -  Best PracticesTime Management & Productivity -  Best Practices
Time Management & Productivity - Best Practices
 
The six step guide to practical project management
The six step guide to practical project managementThe six step guide to practical project management
The six step guide to practical project management
 
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
 
Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...
Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...
Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...
 
12 Ways to Increase Your Influence at Work
12 Ways to Increase Your Influence at Work12 Ways to Increase Your Influence at Work
12 Ways to Increase Your Influence at Work
 

pkashyutfysdbun ihsd vysdi csh

  • 1. UP3B KALBAR PROGRAM LANGIT BIRU PONTIANAK BEBAS LAYANGAN
  • 2. www.pln.co.id | Konfigurasi Silicon Rubber Eksisting Tower SUTT Siantan – Sei Raya T. 041 T. 040 T. 039 Phasa R & T Phasa R & T • Pekerjaan dimulai tanggal 14 Februari 2020 dan selesai tanggal 18 Februari 2020 • Span T041 – 042 dipasang silicon rubber (SR) Pada Phasa R 150 meter dan T sepanjang 150 meter • Total penggunaan SR 600 Meter untuk Line 1 dan Line 2 Progress Penyelesaian (41 – 42) • Pekerjaan dimulai tanggal 14 Februari 2020 dan selesai tanggal 18 Februari 2020 • Span T040 – 041 dipasang silicon rubber (SR) Pada Phasa R 150 meter dan T sepanjang 150 meter • Total penggunaan SR 600 Meter untuk Line 1 dan Line 2 Progress Penyelesaian (40 – 41) T. 001 5.73 kM 5.61 kM 5.49 kM T. A T. B 75 meter 75 meter 150 meter Detail Pemsangan Silicon Rubber Tower Transmisi
  • 3. www.pln.co.id | Pemasangan pada T.58 T.59 T.60 T.61 SeiRaya - Siantan T. 061 T. 060 T. 059 Phasa R & T Phasa R & S • Pekerjaan dimulai tanggal 14 Februari 2020 dan selesai tanggal 29 Februari 2020 • Span T040 – 041 dipasang silicon rubber (SR) Pada Phasa R 150 meter dan T sepanjang 150 meter • Total penggunaan SR 600 Meter untuk Line 1 dan Line 2 Progress Penyelesaian (60 – 61) • Pekerjaan dimulai tanggal 14 Februari 2020 dan selesai tanggal 29 Februari 2020 • Span T040 – 041 dipasang silicon rubber (SR) Pada Phasa R dan S Line 1 dan Line 2 Phasa R dan T sepanjang @150 Meter per phasa. (karena andongan terlalu rendah ) • Total penggunaan SR 600 Meter untuk Line 1 dan Line 2 Progress Penyelesaian (59 - 60) T. 58 9.55 kM 9.25 kM 8.95 kM 8.64 kM • Pekerjaan dimulai tanggal 14 Februari 2020 dan selesai tanggal 29 Februari 2020 • Span T040 – 041 dipasang silicon rubber (SR) Pada Phasa R dan T sepanjang 300 Meter per phasa. • Total penggunaan SR 600 Meter untuk Line 1 dan Line 2 Progress Penyelesaian (58 - 59) Phasa R & T Konfigurasi Silicon Rubber Eksisting Tower SUTT Siantan – Sei Raya
  • 4. www.pln.co.id | Gambar Rencana Pengaman Transmisi Material Penghalang Kawat Layang Senar Nylon Polyamide TOWER A TOWER B Keterangan Besi Diagonal (Galvanis uk 4,4 cm) Joint (Isolator) Besi Horizontal (Galvanis uk 4,4 cm) Rod Vertikal High Density Polyetthylene (HDPE)/Isolator Polymer Rencana Shielding Tower (Konduktor) Terhadap Kawat Layang Penghalang Kawat Layang (Senar Nylon Polyamide (PA) uk 2 mm ) GSW
  • 5. www.pln.co.id | Gambar Rencana Pengaman Transmisi Teknis Ukuran
  • 6. www.pln.co.id | Gambar Rencana Pengaman Transmisi Material Penghalang Kawat Layang Kabel Telfon
  • 7. www.pln.co.id | Gambar Rencana Pengaman Transmisi Material Penghalang Kawat Layang Kabel Telfon
  • 8. www.pln.co.id | Gambar Rencana Pengaman Transmisi Teknis Ukuran
  • 9. www.pln.co.id | Kajian Operasional & Teknis Melalui analisis jarak gangguan layangan pada tahun 2019-2020 di Line Siantan-Sei Raya maka rekomendasi titik pemasangan akan difokuskan pada Span Tower 46-47, 52-53, 55-56, 57-58, 61-62* dan 62-63* *note : rekomendasi juga berdasarkan titik tower yang sudah dilakukan perkuatan pondasi 0 1 2 3 4 5 6 7 8 GI STN T.001 T.002 T.003 T.004 T.005 T.006 T.007 T.008 T.009 T.010 T.011 T.012 T.013 T.014 T.015 T.016 T.017 T.018 T.019 T.020 T.021 T.022 T.023 T.024 T.025 T.026 T.027 T.028 T.029 T.030 T.031 T.032 T.033 T.034 T.035 T.036 T.037 T.038 T.039 T.040 T.041 T.042 T.043 T.044 T.045 T.046 T.047 T.048 T.049 T.050 T.051 T.052 T.053 T.054 T.055 T.056 T.057 T.058 T.059 T.060 T.061 T.062 T.063 T.064 T.065 Frekuensi Jarak Gangguan Layangan Line Siantan - Sei Raya (2019-2020) Rencana Pasang
  • 10. www.pln.co.id | Progress Rencana Pengaman Transmisi No Uraian Kegiatan Progress & Keterangan PIC 1 Pengujian Mekanik dan Tegangan Tinggi Material ke Lab UNTAN dan POLNEP Sudah bersurat M-1 April Rencana Pengujian M-3 April PENYALURAN UP3B SIS KALBAR & ULTG PONTIANAK 2 Pengajuan Kajian Teknis Pemasangan ke PUSLITBANG Sudah bersurat M-1 April Rencana Kajian dan Diskusi M-3 dan M-4 April PENYALURAN UP3B SIS KALBAR & ULTG PONTIANAK 3 Penentuan Rekomendasi Lokasi Pemasangan Span Tower 46-47, 52-53, 55-56, 57-58, 61-62 dan 62-63 (Siantan-Sei Raya) PENYALURAN UP3B SIS KALBAR & ULTG PONTIANAK 4 Rencana Pemasangan M-5 Mei (Setelah Periode Siaga), Butuh Pemadaman Line PENYALURAN UP3B SIS KALBAR & ULTG PONTIANAK Alat Uji Mekanis dan Tegangan Tinggi Material Nylon