Indian Construction
Contracts & Covid19 : Way
Forward
SR. MANAGER (LEGAL), DIRECTORATE GENERAL OF HYDROCARBONS/ BHARAT
PETROLEUM CORPORATION LIMITED
WWW.PRACTICALACADEMIC.BLOGSPOT.IN
WWW.SSRN.COM/AUTHOR=665603
WWW.LINKEDIN.COM/PUB/BADRINATH-SRINIVASAN/13/604/916
LAWBADRI@GMAIL.COM
Views are personal
PROBLEMS & ISSUES
Impact of Covid19 on Construction
Industry
 Cash flow
 Supply chain disruptions
 Time overrun: need for extension of time
 Cost overrun: need for increase in contract price
 Contractors: Substantial Increase in Cost of Performance
 Owners: Substantial decrease in Cost of Performance
 Manpower Issues
 Work resumption and other HSE issues
Views are personal
Time Overrun: Some Issues
 Time lost due to Covid-19 lockdown
 Time lost due to Covid19 affecting/ impacting supplies/ services
even prior to lockdown
 Time lost due to demobilisation and remobilisation
 Extra time that would be required for carrying out works in a
restricted regime.
Views are personal
Cost Overrun: Some Issues
 Idling charges
 Care of Facilities during Lockdown
 Demobilisation/ Remobilisation Costs
 Costs of paying labour wages during lockdown
 Price increase in raw materials & goods post-lockdown
 Mitigation plans in Project
 Suppliers/ Contractors claims including demurrage
 Other costs
Views are personal
Government’s Role
 Perusal of various Circulars
 Proactive response from a policy angle.
 Pandemic is considered as force majeure
 But how force majeure will impact contract performance may depend
on case-to-case basis
Views are personal
List of Government Notifications on
Covid19 as FM
 Impact of COVID-19 on foreign supply chains recognized as force majeure in government supply
contracts: Department of Expenditure, Ministry of Finance's OM dt. 19.02.2020
 DOE Notification dt. 13.05.2020 (time extensions)
 Time extension in scheduled commissioning of Renewable Energy projects considering foreign supply
chain disruptions: Ministry of New & Renewable Energy, OM dt. 20.03.2020
 MORTH Letter no. H-25016/01/2018-Toll dated 25th March 2020
 Ministry of Shipping, Guidelines to Major Ports dt. 31.03.2020
 Indian Railways (https://pib.gov.in/PressReleseDetail.aspx?PRID=1608603)
 DGS Order No. 08 of 2020 dt. 31.03.2020
 Ministry of Shipping order no. PD-13/33/2020-PPP/e-339106 dt. 20.03.2020
 Other Circulars
Views are personal
Some Questions
 Whether force majeure or not?
 Obligations affected by force majeure and manner?
 Whether notice has been given in time?
 Whether change in Law?
 How should be the contract, especially terms relating to price and time, be re-
negotiated?
 Time and Cost Overrun and escalation?
 Non-applicability of LD/ claim for damages for delay.
 Genuine dispute: How to resolve?
 Prolonged force majeure and consequences
Views are personal
Legal Issues & Problems
 Inability of parties
 to agree upon cost/ time overruns
 Inability of a general Contractor to perform
 The bleak prospect of disputes & the ability of the legal system to handle
it
 Inability to get proper advice on financial and legal aspects
 Government benefits: Awareness: Important role to be played by
construction associations, bodies like SCL and others.
 How to Proceed?
Views are personal
Views are personal
WAY FORWARD
“Breathing Space”
 How to deal with Construction Contracts Post-Covid19?
 Amicably Sort out Issues with the objective of completing projects
ASAP
 Provide for Amicable Dispute Resolution Solutions to make
construction contracts viable
 To bring to an end contracts made unviable post-Covid19
Views are personal
Ways Forward
 Standard Operating Procedure for Construction Projects affected by Covid 19
 Enablers
 Way Forward: Formats & Checklists
 Awareness of Government Measures
 Dispute Resolution
SCL and other construction associations may take the lead
Views are personal
SOP for Construction Projects affected by
Covid 19
 SOP on the Way Forward
 Invocation of Force Majeure/ Change in Law
 Cost Overruns
 Time Overruns
 Other Issues
 Discussions: in good faith & in interest of project completion
 Cash Flow
 Advance payments/ modification of contractual milestones
 Escrow accounts
Views are personal
SOP for Construction Projects affected by
Covid 19 (contd.)
 Inability of the general Contractor to perform/ make payment-
direct payment between Client and Sub-Contractors & modalities
 Preliminary/ Interim Orders aimed at completion of project & at
the same time maintaining Contractor cash flows
 Dispute Resolution
 Conciliation/ Mediation
 Arbitration
 Stress on inexpensive, swift, virtual and decisive resolution of disputes.
Views are personal
Enablers
 Templates/ Checklists/ Formats:
 Force majeure & change in law invocation & response templates
 Checklists on Impact
 Checklists on negotiations on Cost/ Time overruns
 Novation Agreement Formats
 Arbitration, Conciliation & Mediation Agreements Formats
 Settlement agreements Formats
 Compilation of Government schemes and judicial decisions in
construction sector for general awareness
Views are personal
Accelerated Dispute Resolution
Drastic Times call for Drastic Measures
 Speed, Inexpensive and Effective dispute resolution
 Fixed time ~ 3 months & Fixed costs ~5- 6 lakhs
 Completely Virtual
 Construction Dispute Specific
 Neutral
 Interim Measures: Extension of BGs & Preservation- Completion of
Project should be the objective
 Three modes: Accelerated Conciliation, Mediation & Arbitration
 Checklists/ Formats for use in Dispute resolution to be fixed
Views are personal
Accelerated Construction Conciliation
 Inability of the general contractor to perform/ make payment- direct payment between
Client and Sub-Contractors
 A finance, technical and a legal expert in each Panel
 Virtual & Time limit of three months
 No external counsels
 Specific disputes to be agreed between the parties and referred
 Common statement of facts and points of disagreement
 Proceedings to be confidential except as to costs
 In case of rejection of Settlement Proposal, costs of conciliation & subsequent legal
proceedings to be on Indemnity basis, if unsuccessful.
Views are personal
Accelerated Construction Mediation
 Professional Mediator well-versed in Construction Disputes
 Virtual & Time limit of three months
 No external counsels
 Specific disputes to be agreed between the parties and referred
 Common statement of facts and points of disagreement
 Proceedings to be confidential except as to costs
 For party rejecting the last settlement offer, costs of mediation & subsequent legal
proceedings to be on Indemnity basis, if unsuccessful.
Views are personal
Accelerated Construction Arbitration
 Fixed Costs: Not more than Rs. 5- 6 lakhs net
 A finance, technical and a legal expert in each Tribunal
 Time limit of three months
 Documents only/ Expedited (S. 29B ACA 1996)
 Specific disputes to be agreed between the parties and referred
 Common statement of facts and points of disagreement reg. facts/ law
 Power to decide on the basis of commercial sense, equity, etc.
 Strict implementation of Loser Pays principle for Costs
Views are personal
Parting Thoughts
 Construction bodies may discuss with
stakeholders about measures suggested
 Multi-tier Dispute Resolution
 May enter into deals with Arbitral
institutions
 Need to Proceed quickly
 Statute on construction contracts
THANK YOU
Views are personal

Mais conteúdo relacionado

Mais procurados

Arbitration processpt1
Arbitration processpt1Arbitration processpt1
Arbitration processpt1
Jim Walker
 
The Anatomy of a Commercial Arbitration - An Arbitration from Start to Finish
The Anatomy of a Commercial Arbitration - An Arbitration from Start to FinishThe Anatomy of a Commercial Arbitration - An Arbitration from Start to Finish
The Anatomy of a Commercial Arbitration - An Arbitration from Start to Finish
Now Dentons
 

Mais procurados (20)

Legal Considerations For Doing Bussiness In India
Legal Considerations For Doing Bussiness In IndiaLegal Considerations For Doing Bussiness In India
Legal Considerations For Doing Bussiness In India
 
Arbitration processpt1
Arbitration processpt1Arbitration processpt1
Arbitration processpt1
 
THE JUSTICE PROCESS IN RERA SECTION 31, 43(5), 58 AND ARTICLE 32,136 226 OF T...
THE JUSTICE PROCESS IN RERA SECTION 31, 43(5), 58 AND ARTICLE 32,136 226 OF T...THE JUSTICE PROCESS IN RERA SECTION 31, 43(5), 58 AND ARTICLE 32,136 226 OF T...
THE JUSTICE PROCESS IN RERA SECTION 31, 43(5), 58 AND ARTICLE 32,136 226 OF T...
 
Dr Mohan R Bolla on Institutional arbitration
Dr Mohan R Bolla on Institutional arbitration Dr Mohan R Bolla on Institutional arbitration
Dr Mohan R Bolla on Institutional arbitration
 
Appointment of arbitrator as per The Arbitration and Conciliation (Amendment)...
Appointment of arbitrator as per The Arbitration and Conciliation (Amendment)...Appointment of arbitrator as per The Arbitration and Conciliation (Amendment)...
Appointment of arbitrator as per The Arbitration and Conciliation (Amendment)...
 
Arbitration
ArbitrationArbitration
Arbitration
 
International commercial arbitration under the icc rules a critical view
International commercial arbitration under the icc rules  a critical viewInternational commercial arbitration under the icc rules  a critical view
International commercial arbitration under the icc rules a critical view
 
Arbitration
ArbitrationArbitration
Arbitration
 
064 po in adr
064 po in adr064 po in adr
064 po in adr
 
SIAC's proposal on cross institutional consolidation of arbitration proceedings
SIAC's proposal on cross institutional consolidation of arbitration proceedingsSIAC's proposal on cross institutional consolidation of arbitration proceedings
SIAC's proposal on cross institutional consolidation of arbitration proceedings
 
Arbitration Act in Bangladesh
Arbitration Act in BangladeshArbitration Act in Bangladesh
Arbitration Act in Bangladesh
 
Chapter 41: Securities Regulation
Chapter 41: Securities RegulationChapter 41: Securities Regulation
Chapter 41: Securities Regulation
 
The Anatomy of a Commercial Arbitration - An Arbitration from Start to Finish
The Anatomy of a Commercial Arbitration - An Arbitration from Start to FinishThe Anatomy of a Commercial Arbitration - An Arbitration from Start to Finish
The Anatomy of a Commercial Arbitration - An Arbitration from Start to Finish
 
SOLUTION FOR STALLED REAL ESTATE PROJECT
SOLUTION FOR STALLED REAL ESTATE PROJECTSOLUTION FOR STALLED REAL ESTATE PROJECT
SOLUTION FOR STALLED REAL ESTATE PROJECT
 
Leonine clause and put option
Leonine clause and put optionLeonine clause and put option
Leonine clause and put option
 
Project dispute avoidance and mitigation through conciliation and arbitration
Project dispute avoidance and mitigation through conciliation and arbitrationProject dispute avoidance and mitigation through conciliation and arbitration
Project dispute avoidance and mitigation through conciliation and arbitration
 
Bankruptcy Claims Trading (Series: Bankruptcy Transactions 301: Advice for th...
Bankruptcy Claims Trading (Series: Bankruptcy Transactions 301: Advice for th...Bankruptcy Claims Trading (Series: Bankruptcy Transactions 301: Advice for th...
Bankruptcy Claims Trading (Series: Bankruptcy Transactions 301: Advice for th...
 
50 tips for safe real estate transactions
50 tips for safe real estate transactions50 tips for safe real estate transactions
50 tips for safe real estate transactions
 
The Law on Trade Dispute resolution (Labour Law) (Kenya)
The Law on Trade Dispute resolution (Labour Law) (Kenya)The Law on Trade Dispute resolution (Labour Law) (Kenya)
The Law on Trade Dispute resolution (Labour Law) (Kenya)
 
Dissertation
DissertationDissertation
Dissertation
 

Semelhante a Indian Construction Contracts & Covid19 : Way Forward

ptac -_you_won_a_contract...now_what
ptac -_you_won_a_contract...now_whatptac -_you_won_a_contract...now_what
ptac -_you_won_a_contract...now_what
Colorado PTAC
 
2008 NCMA World Congress Presentation - Contract Closeout
2008 NCMA World Congress Presentation - Contract Closeout2008 NCMA World Congress Presentation - Contract Closeout
2008 NCMA World Congress Presentation - Contract Closeout
Katherine Woodall
 
2008 World Congress Presentation - Closeout
2008 World Congress Presentation - Closeout2008 World Congress Presentation - Closeout
2008 World Congress Presentation - Closeout
guest82281a
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
JB Nartey
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
JB Nartey
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
Adrias TAN
 

Semelhante a Indian Construction Contracts & Covid19 : Way Forward (20)

Making Changes on the Construction Project
 Making Changes on the Construction Project Making Changes on the Construction Project
Making Changes on the Construction Project
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
ptac -_you_won_a_contract...now_what
ptac -_you_won_a_contract...now_whatptac -_you_won_a_contract...now_what
ptac -_you_won_a_contract...now_what
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
 
Assessing Loss And Expenses Claim By Prolongation Cost
Assessing Loss And Expenses Claim By Prolongation CostAssessing Loss And Expenses Claim By Prolongation Cost
Assessing Loss And Expenses Claim By Prolongation Cost
 
2008 NCMA World Congress Presentation - Contract Closeout
2008 NCMA World Congress Presentation - Contract Closeout2008 NCMA World Congress Presentation - Contract Closeout
2008 NCMA World Congress Presentation - Contract Closeout
 
2008 World Congress Presentation - Closeout
2008 World Congress Presentation - Closeout2008 World Congress Presentation - Closeout
2008 World Congress Presentation - Closeout
 
Alternative Dispute Resolution methods Level III - B.Sc QS (Salford) March ...
Alternative  Dispute Resolution methods  Level III - B.Sc QS (Salford) March ...Alternative  Dispute Resolution methods  Level III - B.Sc QS (Salford) March ...
Alternative Dispute Resolution methods Level III - B.Sc QS (Salford) March ...
 
FED GOV CON - OTA - The Fine Print
FED GOV CON - OTA - The Fine PrintFED GOV CON - OTA - The Fine Print
FED GOV CON - OTA - The Fine Print
 
April 2018 newsletter
April 2018 newsletterApril 2018 newsletter
April 2018 newsletter
 
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
 
Contract - Construction Contracts and Specification
Contract - Construction Contracts and SpecificationContract - Construction Contracts and Specification
Contract - Construction Contracts and Specification
 
How To Protect Your Construction Business and Legal Interests
How To Protect Your Construction Business and Legal InterestsHow To Protect Your Construction Business and Legal Interests
How To Protect Your Construction Business and Legal Interests
 
Government Contracting - OTA's - Who Needs The FAR? - Win Federal Contracts
Government Contracting - OTA's - Who Needs The FAR? - Win Federal ContractsGovernment Contracting - OTA's - Who Needs The FAR? - Win Federal Contracts
Government Contracting - OTA's - Who Needs The FAR? - Win Federal Contracts
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
Risk in FIDIC contracts
Risk in FIDIC contracts Risk in FIDIC contracts
Risk in FIDIC contracts
 
Resolving Complex Delay Claims
Resolving Complex Delay ClaimsResolving Complex Delay Claims
Resolving Complex Delay Claims
 

Mais de Badrinath Srinivasan

Incorporation of Arbitration Clause by Reference: Inox Wind v Thermocables (S...
Incorporation of Arbitration Clause by Reference: Inox Wind v Thermocables (S...Incorporation of Arbitration Clause by Reference: Inox Wind v Thermocables (S...
Incorporation of Arbitration Clause by Reference: Inox Wind v Thermocables (S...
Badrinath Srinivasan
 

Mais de Badrinath Srinivasan (14)

Former Employee as Arbitrator after GF Toll
Former Employee as Arbitrator after GF TollFormer Employee as Arbitrator after GF Toll
Former Employee as Arbitrator after GF Toll
 
Consortium & Determination of "International"​ Character of Arbitration in India
Consortium & Determination of "International"​ Character of Arbitration in IndiaConsortium & Determination of "International"​ Character of Arbitration in India
Consortium & Determination of "International"​ Character of Arbitration in India
 
Substituted Performance in Indian Contract Law: An Analysis
Substituted Performance in Indian Contract Law: An AnalysisSubstituted Performance in Indian Contract Law: An Analysis
Substituted Performance in Indian Contract Law: An Analysis
 
Lecture 5: Relevancy of Certain Statements under Certain Circumstances
Lecture 5: Relevancy of Certain Statements under Certain CircumstancesLecture 5: Relevancy of Certain Statements under Certain Circumstances
Lecture 5: Relevancy of Certain Statements under Certain Circumstances
 
Lecture 4: Relevancy of Admissions & Confessions
Lecture 4: Relevancy of Admissions & ConfessionsLecture 4: Relevancy of Admissions & Confessions
Lecture 4: Relevancy of Admissions & Confessions
 
Lecture 2: Preliminary Aspects of the Indian Evidence Act, 1872
Lecture 2: Preliminary Aspects of the Indian Evidence Act, 1872Lecture 2: Preliminary Aspects of the Indian Evidence Act, 1872
Lecture 2: Preliminary Aspects of the Indian Evidence Act, 1872
 
Lecture 1: The Structure of Evidence Act, 1872
Lecture 1: The Structure of Evidence Act, 1872 Lecture 1: The Structure of Evidence Act, 1872
Lecture 1: The Structure of Evidence Act, 1872
 
Retrospective Applicability of the 2015 Amendments to Indian Arbitration Law
Retrospective Applicability of the 2015 Amendments to Indian Arbitration Law Retrospective Applicability of the 2015 Amendments to Indian Arbitration Law
Retrospective Applicability of the 2015 Amendments to Indian Arbitration Law
 
Arbitrability of Tenancy Matters in India: Recent Developments
Arbitrability of Tenancy Matters in India: Recent DevelopmentsArbitrability of Tenancy Matters in India: Recent Developments
Arbitrability of Tenancy Matters in India: Recent Developments
 
Incorporation of Arbitration Clause by Reference: Inox Wind v Thermocables (S...
Incorporation of Arbitration Clause by Reference: Inox Wind v Thermocables (S...Incorporation of Arbitration Clause by Reference: Inox Wind v Thermocables (S...
Incorporation of Arbitration Clause by Reference: Inox Wind v Thermocables (S...
 
New Delhi International Arbitration Centre Bill, 2018
New Delhi International Arbitration Centre Bill, 2018New Delhi International Arbitration Centre Bill, 2018
New Delhi International Arbitration Centre Bill, 2018
 
Arbitration between Nissan & Government of India
Arbitration between Nissan & Government of IndiaArbitration between Nissan & Government of India
Arbitration between Nissan & Government of India
 
Cost Allocation under the Amended Indian Arbitration Law: A Critique
Cost Allocation under the Amended Indian Arbitration Law: A CritiqueCost Allocation under the Amended Indian Arbitration Law: A Critique
Cost Allocation under the Amended Indian Arbitration Law: A Critique
 
LL.M. in India: A Critical Review
LL.M. in India:  A Critical ReviewLL.M. in India:  A Critical Review
LL.M. in India: A Critical Review
 

Último

一比一原版悉尼大学毕业证如何办理
一比一原版悉尼大学毕业证如何办理一比一原版悉尼大学毕业证如何办理
一比一原版悉尼大学毕业证如何办理
Airst S
 
一比一原版(UM毕业证书)美国密歇根大学安娜堡分校毕业证如何办理
一比一原版(UM毕业证书)美国密歇根大学安娜堡分校毕业证如何办理一比一原版(UM毕业证书)美国密歇根大学安娜堡分校毕业证如何办理
一比一原版(UM毕业证书)美国密歇根大学安娜堡分校毕业证如何办理
A AA
 
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
Airst S
 
一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理
Airst S
 
Code_Ethics of_Mechanical_Engineering.ppt
Code_Ethics of_Mechanical_Engineering.pptCode_Ethics of_Mechanical_Engineering.ppt
Code_Ethics of_Mechanical_Engineering.ppt
JosephCanama
 
Interpretation of statute topics for project
Interpretation of statute topics for projectInterpretation of statute topics for project
Interpretation of statute topics for project
VarshRR
 
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
e9733fc35af6
 
一比一原版伦敦南岸大学毕业证如何办理
一比一原版伦敦南岸大学毕业证如何办理一比一原版伦敦南岸大学毕业证如何办理
一比一原版伦敦南岸大学毕业证如何办理
Airst S
 

Último (20)

Shubh_Burden of proof_Indian Evidence Act.pptx
Shubh_Burden of proof_Indian Evidence Act.pptxShubh_Burden of proof_Indian Evidence Act.pptx
Shubh_Burden of proof_Indian Evidence Act.pptx
 
一比一原版悉尼大学毕业证如何办理
一比一原版悉尼大学毕业证如何办理一比一原版悉尼大学毕业证如何办理
一比一原版悉尼大学毕业证如何办理
 
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
 
The Main Steps on Starting a Business in Spain
The Main Steps on Starting a Business in SpainThe Main Steps on Starting a Business in Spain
The Main Steps on Starting a Business in Spain
 
Navigating Employment Law - Term Project.pptx
Navigating Employment Law - Term Project.pptxNavigating Employment Law - Term Project.pptx
Navigating Employment Law - Term Project.pptx
 
WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)
 
Police Misconduct Lawyers - Law Office of Jerry L. Steering
Police Misconduct Lawyers - Law Office of Jerry L. SteeringPolice Misconduct Lawyers - Law Office of Jerry L. Steering
Police Misconduct Lawyers - Law Office of Jerry L. Steering
 
Performance of contract-1 law presentation
Performance of contract-1 law presentationPerformance of contract-1 law presentation
Performance of contract-1 law presentation
 
一比一原版(UM毕业证书)美国密歇根大学安娜堡分校毕业证如何办理
一比一原版(UM毕业证书)美国密歇根大学安娜堡分校毕业证如何办理一比一原版(UM毕业证书)美国密歇根大学安娜堡分校毕业证如何办理
一比一原版(UM毕业证书)美国密歇根大学安娜堡分校毕业证如何办理
 
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
 
The doctrine of harmonious construction under Interpretation of statute
The doctrine of harmonious construction under Interpretation of statuteThe doctrine of harmonious construction under Interpretation of statute
The doctrine of harmonious construction under Interpretation of statute
 
一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理
 
Code_Ethics of_Mechanical_Engineering.ppt
Code_Ethics of_Mechanical_Engineering.pptCode_Ethics of_Mechanical_Engineering.ppt
Code_Ethics of_Mechanical_Engineering.ppt
 
Cyber Laws : National and International Perspective.
Cyber Laws : National and International Perspective.Cyber Laws : National and International Perspective.
Cyber Laws : National and International Perspective.
 
Interpretation of statute topics for project
Interpretation of statute topics for projectInterpretation of statute topics for project
Interpretation of statute topics for project
 
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURYA SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
 
Understanding the Role of Labor Unions and Collective Bargaining
Understanding the Role of Labor Unions and Collective BargainingUnderstanding the Role of Labor Unions and Collective Bargaining
Understanding the Role of Labor Unions and Collective Bargaining
 
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
 
Analysis of R V Kelkar's Criminal Procedure Code ppt- chapter 1 .pptx
Analysis of R V Kelkar's Criminal Procedure Code ppt- chapter 1 .pptxAnalysis of R V Kelkar's Criminal Procedure Code ppt- chapter 1 .pptx
Analysis of R V Kelkar's Criminal Procedure Code ppt- chapter 1 .pptx
 
一比一原版伦敦南岸大学毕业证如何办理
一比一原版伦敦南岸大学毕业证如何办理一比一原版伦敦南岸大学毕业证如何办理
一比一原版伦敦南岸大学毕业证如何办理
 

Indian Construction Contracts & Covid19 : Way Forward

  • 1. Indian Construction Contracts & Covid19 : Way Forward SR. MANAGER (LEGAL), DIRECTORATE GENERAL OF HYDROCARBONS/ BHARAT PETROLEUM CORPORATION LIMITED WWW.PRACTICALACADEMIC.BLOGSPOT.IN WWW.SSRN.COM/AUTHOR=665603 WWW.LINKEDIN.COM/PUB/BADRINATH-SRINIVASAN/13/604/916 LAWBADRI@GMAIL.COM
  • 3. Impact of Covid19 on Construction Industry  Cash flow  Supply chain disruptions  Time overrun: need for extension of time  Cost overrun: need for increase in contract price  Contractors: Substantial Increase in Cost of Performance  Owners: Substantial decrease in Cost of Performance  Manpower Issues  Work resumption and other HSE issues Views are personal
  • 4. Time Overrun: Some Issues  Time lost due to Covid-19 lockdown  Time lost due to Covid19 affecting/ impacting supplies/ services even prior to lockdown  Time lost due to demobilisation and remobilisation  Extra time that would be required for carrying out works in a restricted regime. Views are personal
  • 5. Cost Overrun: Some Issues  Idling charges  Care of Facilities during Lockdown  Demobilisation/ Remobilisation Costs  Costs of paying labour wages during lockdown  Price increase in raw materials & goods post-lockdown  Mitigation plans in Project  Suppliers/ Contractors claims including demurrage  Other costs Views are personal
  • 6. Government’s Role  Perusal of various Circulars  Proactive response from a policy angle.  Pandemic is considered as force majeure  But how force majeure will impact contract performance may depend on case-to-case basis Views are personal
  • 7. List of Government Notifications on Covid19 as FM  Impact of COVID-19 on foreign supply chains recognized as force majeure in government supply contracts: Department of Expenditure, Ministry of Finance's OM dt. 19.02.2020  DOE Notification dt. 13.05.2020 (time extensions)  Time extension in scheduled commissioning of Renewable Energy projects considering foreign supply chain disruptions: Ministry of New & Renewable Energy, OM dt. 20.03.2020  MORTH Letter no. H-25016/01/2018-Toll dated 25th March 2020  Ministry of Shipping, Guidelines to Major Ports dt. 31.03.2020  Indian Railways (https://pib.gov.in/PressReleseDetail.aspx?PRID=1608603)  DGS Order No. 08 of 2020 dt. 31.03.2020  Ministry of Shipping order no. PD-13/33/2020-PPP/e-339106 dt. 20.03.2020  Other Circulars Views are personal
  • 8. Some Questions  Whether force majeure or not?  Obligations affected by force majeure and manner?  Whether notice has been given in time?  Whether change in Law?  How should be the contract, especially terms relating to price and time, be re- negotiated?  Time and Cost Overrun and escalation?  Non-applicability of LD/ claim for damages for delay.  Genuine dispute: How to resolve?  Prolonged force majeure and consequences Views are personal
  • 9. Legal Issues & Problems  Inability of parties  to agree upon cost/ time overruns  Inability of a general Contractor to perform  The bleak prospect of disputes & the ability of the legal system to handle it  Inability to get proper advice on financial and legal aspects  Government benefits: Awareness: Important role to be played by construction associations, bodies like SCL and others.  How to Proceed? Views are personal
  • 11. “Breathing Space”  How to deal with Construction Contracts Post-Covid19?  Amicably Sort out Issues with the objective of completing projects ASAP  Provide for Amicable Dispute Resolution Solutions to make construction contracts viable  To bring to an end contracts made unviable post-Covid19 Views are personal
  • 12. Ways Forward  Standard Operating Procedure for Construction Projects affected by Covid 19  Enablers  Way Forward: Formats & Checklists  Awareness of Government Measures  Dispute Resolution SCL and other construction associations may take the lead Views are personal
  • 13. SOP for Construction Projects affected by Covid 19  SOP on the Way Forward  Invocation of Force Majeure/ Change in Law  Cost Overruns  Time Overruns  Other Issues  Discussions: in good faith & in interest of project completion  Cash Flow  Advance payments/ modification of contractual milestones  Escrow accounts Views are personal
  • 14. SOP for Construction Projects affected by Covid 19 (contd.)  Inability of the general Contractor to perform/ make payment- direct payment between Client and Sub-Contractors & modalities  Preliminary/ Interim Orders aimed at completion of project & at the same time maintaining Contractor cash flows  Dispute Resolution  Conciliation/ Mediation  Arbitration  Stress on inexpensive, swift, virtual and decisive resolution of disputes. Views are personal
  • 15. Enablers  Templates/ Checklists/ Formats:  Force majeure & change in law invocation & response templates  Checklists on Impact  Checklists on negotiations on Cost/ Time overruns  Novation Agreement Formats  Arbitration, Conciliation & Mediation Agreements Formats  Settlement agreements Formats  Compilation of Government schemes and judicial decisions in construction sector for general awareness Views are personal
  • 16. Accelerated Dispute Resolution Drastic Times call for Drastic Measures  Speed, Inexpensive and Effective dispute resolution  Fixed time ~ 3 months & Fixed costs ~5- 6 lakhs  Completely Virtual  Construction Dispute Specific  Neutral  Interim Measures: Extension of BGs & Preservation- Completion of Project should be the objective  Three modes: Accelerated Conciliation, Mediation & Arbitration  Checklists/ Formats for use in Dispute resolution to be fixed Views are personal
  • 17. Accelerated Construction Conciliation  Inability of the general contractor to perform/ make payment- direct payment between Client and Sub-Contractors  A finance, technical and a legal expert in each Panel  Virtual & Time limit of three months  No external counsels  Specific disputes to be agreed between the parties and referred  Common statement of facts and points of disagreement  Proceedings to be confidential except as to costs  In case of rejection of Settlement Proposal, costs of conciliation & subsequent legal proceedings to be on Indemnity basis, if unsuccessful. Views are personal
  • 18. Accelerated Construction Mediation  Professional Mediator well-versed in Construction Disputes  Virtual & Time limit of three months  No external counsels  Specific disputes to be agreed between the parties and referred  Common statement of facts and points of disagreement  Proceedings to be confidential except as to costs  For party rejecting the last settlement offer, costs of mediation & subsequent legal proceedings to be on Indemnity basis, if unsuccessful. Views are personal
  • 19. Accelerated Construction Arbitration  Fixed Costs: Not more than Rs. 5- 6 lakhs net  A finance, technical and a legal expert in each Tribunal  Time limit of three months  Documents only/ Expedited (S. 29B ACA 1996)  Specific disputes to be agreed between the parties and referred  Common statement of facts and points of disagreement reg. facts/ law  Power to decide on the basis of commercial sense, equity, etc.  Strict implementation of Loser Pays principle for Costs Views are personal
  • 20. Parting Thoughts  Construction bodies may discuss with stakeholders about measures suggested  Multi-tier Dispute Resolution  May enter into deals with Arbitral institutions  Need to Proceed quickly  Statute on construction contracts THANK YOU Views are personal