DISTINGUISH THE MINE PERFORMANCE BY CONVEYOR
BELT AND HAULAGE SYSTEM OF TRANSPORTATION
A mini project
Submitted in partial fulfilment of requirements for award of
Bachelor of Technology and in
Mining Engineering
By
Anurag Kumar Jha
Exam Roll no.-511214025
SESSION 2015-2016
DEPARTMENT OF MINING ENGINEEING
INDIAN INSTITUTE OF ENGINEERING SCIENCE AND TECHNOLOGY, SHIBPUR
HOWRAH-711103
Section 1.01 Department of Mining Engineering
INDIAN INSTITUTE OF ENGINEERING SCIENCE AND
TECHNOLOGY, SHIBPUR
(An Institute of National Importance)
ii
CERTIFICATE
This is to certify that the dissertation titled “DISTINGUISH THE MINE
PERFORMANCE BY CONVEYOR BELT AND HAULAGE SYSTEM OF
TRANSPORTATION ” being submitted by Anurag Kumar Jha (Roll No.-511214025) to the
Department of Mining Engineering, Indian Institute of Engineering and Science Technology,
Shibpur, in partial fulfilment of requirements for award of dual degree of Bachelor of
Technology and Master of Technology in Mining Engineering is a record of bona fide work
carried out by him under my supervision and guidance.
To the best of my knowledge, the matter embodied in this document has not been submitted
anywhere else for award of any other degree or diploma.
Date. ___________________________________
(<Dr. N. C. DEY>)
Associate/ Assistant/ Professor in Mining
Engineering
iii
Acknowledgements
We are thankful to Dr. N. C. DEY, Professor, Department of Mining Engineering IIEST,
SHIBPUR for his constant supervision, guidance, motivation and support at every stage of
this project work.
We would also like to convey our sincere gratitude and indebtness to the faculty and staff
members of Department of Mining Engineering, IIEST, Shibpur, for their help at different
times.
We would also like to extend our sincere thanks to Dr. Indarnath Sinha, Dr. Pratik Dutta, for
their help in providing the necessary information for the dissertation work.
Last but not the least, our sincere thanks to all our friends who have extended all sorts of help
for completion of this work.
(Anurag kumar jha)
IV Sem Dual (BTech-Mtech) Degree
Programme in Mining Engineering
Indian Institute of Engineering
Science and Technology, Shibpur
Howrah-- 711103
iv
Table of Contents
DISTINGUISH THE MINE PERFORMANCE BY CONVEYOR BELT AND HAULAGE
SYSTEM OF TRANSPORTATION.........................................................................................1
CERTIFICATE..........................................................................................................................ii
Acknowledgements.................................................................................................................. iii
Table of Contents......................................................................................................................iv
Abstract.....................................................................................................................................vi
List of Figures..........................................................................................................................vii
List of Tables ......................................................................................................................... viii
Abbreviations and Acronyms Used ..........................................................................................ix
Chapter-1 Introduction...............................................................................................................1
Chapter-2 Transport System In Underground Mines.................................................................3
2.1 Teansport System.................................................................................................................3
2.1.1 Rope Haulage................................................................................................................3
2.1.2 CONVEYOR SYSTEM OF HAULAGE ................................................................................3
2.2 Underground Transport Arrangement..................................................................................3
2.3 Direct Rope Haulage............................................................................................................3
2.3.1 Direct Rope Double Drum Balanced Haulage..............................................................4
3.4 End Less Haulage ................................................................................................................5
3.5 Main and Tail rope haulage .................................................................................................7
3.6 Tail rope haulage..................................................................................................................8
3.7 Gravity haulage or self acting incline ..................................................................................8
3.8 Safety Devices in Haulage...................................................................................................8
3.9 Belt conveyor.......................................................................................................................8
3.9.1 Selection of belt conveyor ............................................................................................9
v
3.9.2 Factors For Designing Of Belt Conveyor ...................................................................10
3.9.3 Loop Take Up Arrangement Of Tensioning Device For Belt Conveyor....................10
Chapter-4 Observations ...........................................................................................................12
Chapter-5 Conclusions.............................................................................................................14
References................................................................................................................................15
Appendices.................................................................................................................................1
vi
Abstract
Transportation system is a measure part of mining activity at any type of mining method.
Selection of proper type of transportation system in any coal mines gives better production
efficiency as well as better productivity. It may reduce the labour charge and requirement of
man. It can also increase the production per shift.
Selection of transportation system is mainly depends upon the requirement of coal, condition
of coal seam, condition of roof and floor of gallery, depth of seam, man power,
mechanization of mines and mining method also.
vii
List of Figures
Sl No. Name Page
1 Track layout of direct rope
haulage
14
2 Endless rope haulage 15
3 Main and tail rope haulage 16
4 Layout of face gate and trunk
conveyor in coal mine
18
viii
List of Tables
ix
Abbreviations and Acronyms Used
1
Chapter-1
Introduction
Transport development followed two distinct routes in each of the major functions namely
the movement of ore /coal, persons, material and equipment. Ore/coal transport has either
been by locomotive hauled mine cars belt conveyor or rubber tired trucks. The transport of
persons materials and equipment has either been by rail mounted tracks systems or trackless
systems/movable vechicles. Each system described above is still widely popular for those
various specific region.
The consideration of transport system for ore and coal, persons, materials, and equipment and
major factors in the decision to use drifts and or shafts for a mine
2
3
Chapter-2
Transport System In Underground Mines
2.1 Teansport System
2.1.1 Rope Haulage
i) Direct rope haulage
(1) Tail rope haulage
ii) Endless rope haulage
(1) Over-rope
(2) Under-rope
iii) Main and tail rope haulage
iv) Gravity haulage
2.1.2 CONVEYOR SYSTEM OF HAULAGE
i) Belt conveyor
ii) Cable belt conveyor
iii) Chain conveyor
(1) Scraper chain conveyor
(2) Armoured chain conveyor
(3) Gate end loader
(4) Mobile stage loader
(5) Pick-aback conveyor
iv) Plate conveyor
v) Disc conveyor
2.2 Underground Transport Arrangement
It is divided into following category
1) Main haulage
The main haulage arrangement is that which operates between winding shaft/incline
and the main underground loading points. At the main loading point, the loads are
collected from one, two or more districts.
2) Gathering haulages
The gathering haulage arrangement is that which operates between the working faces
and the main loading points
3) Secondry haulage
In a large mine, where the working faces are far from the main loading point, an
intermediate transport arrangement operates and it is known as secondary haulage
2.3 Direct Rope Haulage
It is a simplest system employing in the mine ,consists of one pulling rope and one
haulage drum for hauling minerals in tubs ir mine cars up a gradient which is generally
stipper than 1 in 10. The haulage engine is situated at the top of an incline roadway and
4
the train of tubsis attached to one end of the rope, the end being fixed to the haulage
drum.
The empty tubs attached to the end of the haulage rope travel on the down gradient by
their own weight and do not require power from the haulage engine. The drum shafts is
therefore provided with a jow clutch to disengage it from the engine. A slip ring motor
with drum controller is used.
Advantage
(1) The rope speed is generally 8-12 km/h and the system can operate
between any point of the haulage plane and the haulage engine
(2) It can, therefore, cope with the haulage requirements of an advancing
working face.
(3) Only one haulage track is required
(4) The system can also serve branch roads if the gradient is suitable for
down-the-gradient movement of empties by gravity. For this reason, the
branch road deviating at an angle of not more than 400
off the main road is
convenient
Disadvantage
(1) High peak power demand as load starts its journey up the gradient
(2) Severe braking duty on the downward run.
(3) High haulage speed demanding high standard of track maintenance
(4) Not suitable for mild inclination of roads.
(5) A derailment is associated with heavy damage because of high speed
2.3.1 Direct Rope Double Drum Balanced Haulage
It is a modification of direct rope haulage, two drums are provided so that when a train of full
tubs is being hauled out bye, a set of empty tubs is lowered inbye. Both the drums are fitted
with clutches and are mounted on the same shaft, weight of the rope and the tubs are balanced
and only the unbalanced load for the engine is mineral. This results in a reduced peak power
demand and easer breaking , the system gives higher output in each trip of the rope brings the
loads and there is regular delivery of the loaded tubs.
The system requires wider roads for the haulage.
5
2.1 Track Layout Of Direct Rope Haulage
(E-track of empties and F-track of loaded)
3.4 End Less Haulage
In this system there are two parallel tracks side by side. One for loaded tubs and the
another for empty tubs and the endless rope passing from driving drum locared at
outbye end of the haulage road to the inbye end and back again via a tension bogey.
The tubs loaded as well as empties are attached to the rope with regular interval with
the help of clips so that the entire rope length has tubs on it at intervals. Only one end
of the tub is attached to the rope at a time. But where lashing chain is used for
attachment the normal practice is to attach a set of tubs and the attachment or
detachment is performed by stopping the rope if however clips are used for single tubs
they can be attached or detached when the rope is in motion. The gradient of haulage
road is mild and rarely exceeds 1 in 6. The rope speed ranges between 3 km/h and 7
km/h and the haulage is slow moving. The rope moves in one direction only.
6
2.2 End Less Rope Haulage
There are two types of endless rope haulage.
1. Over rope type
In over rope type the haulage rope passes over the tub or set a tubs.
2. Under rope type
In under rope type it passes beneath the tub or set of tubs.
Advantage
i) Because of slow speed, less wear and tear.
ii) Accident from derailed tubs does not cause much damage due to slow speed.
iii) Motor of less power required.
iv) It does not place heavy demand on the power supply.
Disadvantage
i) It requires wide road for two tracks.
ii) It is not suitable for sleep gradient
iii) Load on the rope is larger and a rope of larger cross-section is required.
iv) Large no of tubs and clips are required as rolling stock.
v) If a break-down of any tub occurs the whole system comes to a standstill.
7
vi) It can not serve a main road and a branch road simultaneously unless elaborate
arrangements are made to course the rope to the branch line with the help of
deflection pulleys.
3.5 Main and Tail rope haulage
In main and tail rope haulage, the hauling engine is provided with two separate drums
one for the main rope, which haul the full train out and one for the tail which haul for
the empty train in. When one drum is in gear, the other revolves freely on the shaft
but controlled when necessary, by the brake to keep the rope taut. The main rope is
approximately equal to the length of the plane and the tail ropes twice this length. In
this type of haulage only one track is required and it is suitable for undulating
roadways where it is impossible and undesirable to maintain the double track required
for endless rope haulage. It can readily negotiate curves and it is convenient for
working branches. It operates at fairlyhigh speeds and with long trains and if a
derailment occurs,the resulting damage and delay likely to be considerable.
2.3 Main And Tail Rope Haulage
Advantage
i) This system of haulage is suitable for undulating roadways, where it is impossible
or undesirable to maintain the double track .
ii) Unlike endless rope haulage, this system requires one track.
iii) Less maintenance cost for one track compare to two tracks.
iv) Can readily negotiate curve.
8
v) It is convenient for working branches.
vi) It operates at fairly high speed.
Disadvantage
i) As it operates at fairly high speed, more wear and tear.
ii) Derailment can cause more harms to man and machine.
iii) Long length of rope is required causing more cost of maintenance.
iv) It became very difficult to manage the system properly.
3.6 Tail rope haulage
It is situated at the lower level and the empties are hauled up the sloping track. The
haulage rope passes to the train of empty tubs via a deflection pulley located at the top
of the roadway. The loads travel by gravity down the gradient but as the rope is
attached to them; their descent is controlled by the haulage driver.
3.7 Gravity haulage or self acting incline
It is located at the top of the inclined roadway and is employed to lower by gravity the
loads attached to one end of the rope which passes round the vertical jig pulley. Only
single track is required for the operation but at the mid way of the road where the
loads and empties meet, double track or a bye-pass is essential. This haulage operates
without any motor or external source of power and consists of a cast iron pulley of 1.3
m to 2 m diameter having a brake path on the side and a strap brake.
3.8 Safety Devices in Haulage
i) Stop blocks
ii) Buffers
iii) Back catches
iv) Pointer plates
v) Drop war wick
vi) Age croft device
vii)Back stays
viii) Runway switches
ix) Jazz rails
x) Retarders
xi) Approach warning device
3.9 Belt conveyor
The belt conveyor is basically an endless belt in a straight line stretched between two
drums, one driving the system and the other acting as a return drum. In coal mines and
other mines of stratified deposits, where the underground mineral if won by longwall
method, the transport media which often consists of conveyor.
9
2.4 Layout Of Face, Gate And Trunk Conveyors In A Coal Mine
The system of transport by belt conveyor consists of the following:-
i) A flat endless belt which moves continuously and carries at its top
surface the material to be conveyed.
ii) The idlers which support the belt.
iii) The structure of channel iron on which the idlers are mounted.
iv) The tensioning arrangement for keeping the belt in proper tension.
v) The drums at the discharge and tail end over which the belt passes.
vi) The drive head which comprises the electric motor, coupling, gearing
and snub pulleys.
3.5(b)-Arrangement of a belt conveyor
3.9.1 Selection of belt conveyor
10
There are following factors that decide the selection of belt conveyor
(a) Amount of material to be conveyed
(b) Continuity of operation needed
(c) Size of lumps
(d) Distance of transportation
(e) Environmental allowance
(f) Gradient
(g) Method of coal winning, i.e. Longwall or Bord and Pillar
(h) Capital Available
Advantages:-
(a) A continuous supply of material
(b) Low operating cost than road transportation system
(c) High rate and speed of supply
(d) Bunding can be done to get fair grade
(e) More efficiency and low cost
Limitations of belt conveyor:-
There are following limitation of belt conveyor-
(a) It cannot be used for long distances
(b) It requires high one time capital investment
(c) It cannot handle the Lumps of big size
(d) Place should be dry enough where it will installed and air velocity should
not be high
(e) It cannot be operates at high inclinations
3.9.2 Factors For Designing Of Belt Conveyor
i) The average tonnage (t/h), peak rate (t/min) and frequency of peak rates.
ii) Characteristics of the material i.e.
 Density
 Maximum lump size
 Nature of material- dry, wet, sticky, dusty
 Chemical action on belt
iii) Graphical layout of conveyor profile and motive power available (i.e.
electric motor).
iv) Operating conditions - hours of working, climatic conditions etc.
v) Suitability of a belt conveyor & width and speed of belt.
vi) Belt shape
vii)Power and layout required
3.9.3 Loop Take Up Arrangement Of Tensioning Device For Belt Conveyor
Tensioning of the belt is necessary to prevent excessive sagging of the belt or
belt in good contact with the driving drum. There are following arrangement
for the tensioning of the belt-
11
(i) Automatic take ups
(ii) Gravity take ups
(iii)Take up pulley with counter weight
(iv)Counter weighted loop take
(v) Counterweighted wheel mounted tail end pulley
(vi)Power take ups
(vii) Electric motorized winch and load cell loop take up
(viii) Electric motorized winch and load cell loop take up
(ix)Hydraulically loop takes up
(x) Rigid or manual take ups
(xi)Screw take up
(xii) Jack take up
(xiii) Winch take up
12
Chapter-4
Observations
The study of many overland conveyor (OLC) vs. truck haulage reveal some basic and new
facts:
1) Belt conveyor is more time and effort saving so it saves the costs. However , it is
inconvenient to move, which the advantage of trucks.
2) The problem with haulage no matter the tonnage class size is that they are only fifty
percent efficiency.
3) Conveyors have a very high cost per foot of installation in thousands of dollars per
foot and they requires replacement idlers belting, motor, pulleys, gear boxes, chain
drives, high or medium voltage electricity to power them, emergency stop systems
from end to end and labor to main tail them as well as labor to install conveyor
extensions.
A conveying system of any ype requires primary and secondary crossing system and
or conveyor belt feeder/breakers to load them as well. Adding more to the purchase
cost operational cost.
4) Penalizing the conveyor with ore size reduction is also a fallacy. The rock is going to
be crushed in any case in order to processed. One can argue about crusher
maintenance in remote areas. Still these facts are assessed during the feasibility
phase.
5) Breakeven point for OLC is a transport circuit that must convey 2 million tons per
annum over more than one kilo meter or the total multiplier of tons and kilo meters.
This is further dependent on local fuel costs and terrain difficulty. Some countries
subsidize their diesel fuel that artificially lowers the truck penalty that is now
changing.
6) Conveyors can often be routed in a more direct path than the road haulage thereby
reducing the kilo meter penalty. The path may include bridges over rivers, roads,
railroads, etc.
7) Conveyors can negotiate rough terrain to 18 degrees or more making for shorter
paths or that would require tunnel by trucks.
8) Conveyors are more efficient with fuel usage than trucks especially with the payload
of an empty truck return haul.
9) Conveyor designs have become more efficient with new rubber compounds and new
design methods that lower rolling energy by 50% or more than many suppliers of
rubbers from 5 years ago. Trucks have not seen such improvements in rolling losses.
A case in point is the Curragh 20km single flight overland that transports 2500 t/h. It
is light and fast (7.5 m/s). It is very light for the tons conveyed due to efficient use of
sheet metal components for is idler and belt support and wind shielding. IN 2007, it
was the fastest operating belt conveyor in Australia. Speed lowers the conveyor
system width which is the most capital intensive parameter. Some have disparaged the
13
design and been wrong in their assessment. It's 5 m carry side and 10 m return idler
spacing is proven to be appropriate when the plant has been properly operated.
10) New research into more efficient belt conveyor operations is proving that
further cost effective gains are possible compared to trucks and trains. More
difficult terrain, stronger belts, lower belt strength as measured by the necessary
Safety Factor, lower rolling resistance designs, and lower metal mass per km all
point to ongoing improvements over truck and trains.
11) New conveyor configurations can be found with better trough shapes, pipe, and
semi pipe designs are now a reality where high lifts and sharp curvatures are
required that add to belt conveyor transport efficiency.
12) studies of +100km conveyors does demonstrate the ability for long and efficient
transport compared with train haulage. Risk analysis then becomes an important
factor in the “what if “scenarios.
14
Chapter-5
Conclusions
There are various advantage and disadvantage of both of the method of transportation of
material. But we can chose any one by our requirement because where belt conveyor has lot
of maintenance and installing cost but it will give us lot of production who save our time and
labour cost where as if we can not interested in the huge production than truck haulage best
option but we should try belt conveyor with advanced technology who will give us
production in long distance. It will save the effort and other labour work. If we want to
supply the material in long path way than haulage is more efficient belt conveyor is not
sufficient. And if we want to handle big size lump conveyor is not adequate for it. Belt
conveyor can not operate at high inclination and the place should be enough clean and dry.
Land and weather are good grounds for eliminating either choice. The question should be
"Do you want the stuff or not?" If the answer is yes then the economics is out of the window.
You have to have it so be prepared to pay for it. Trucks need good dry ground to travel and
plenty of it. Conveyors also need an acceptable right of way and can only negotiate a route
within set limits. Truck CAPEX is not so small andthe OPEX is higher than for conveyors,
provided you don't slit a
belt into 2.
15
References
1
Appendices

Mais conteúdo relacionado

Mais procurados

Longwall Mining
Longwall MiningLongwall Mining
Longwall Mining
VR M
 
Mining machinary nit rourkela
Mining machinary nit rourkelaMining machinary nit rourkela
Mining machinary nit rourkela
rrosan1991
 

Mais procurados (20)

Transportation in underground mines
Transportation  in underground mines Transportation  in underground mines
Transportation in underground mines
 
Haulage system in Mines
Haulage system in MinesHaulage system in Mines
Haulage system in Mines
 
Longwall Mining
Longwall MiningLongwall Mining
Longwall Mining
 
Opencast mining machineries
Opencast mining machineriesOpencast mining machineries
Opencast mining machineries
 
Belt conveyor
Belt conveyorBelt conveyor
Belt conveyor
 
Wire ropes used in mining
Wire ropes used in miningWire ropes used in mining
Wire ropes used in mining
 
Kope winder or friction winder ppt
Kope winder or friction winder pptKope winder or friction winder ppt
Kope winder or friction winder ppt
 
Development and depillaring with continuous miner
Development and depillaring with continuous minerDevelopment and depillaring with continuous miner
Development and depillaring with continuous miner
 
LHD Load haul dump ppt
LHD Load haul dump pptLHD Load haul dump ppt
LHD Load haul dump ppt
 
Shuttle car
Shuttle carShuttle car
Shuttle car
 
Shaft sinking 1
Shaft sinking 1Shaft sinking 1
Shaft sinking 1
 
Method of working of continuous miner in underground coal
Method of working of     continuous miner in underground coalMethod of working of     continuous miner in underground coal
Method of working of continuous miner in underground coal
 
Bucket wheel excavator ppt
Bucket wheel excavator pptBucket wheel excavator ppt
Bucket wheel excavator ppt
 
Shaft sinking.
Shaft sinking.Shaft sinking.
Shaft sinking.
 
Introduction to Conveyors.ppt
Introduction to Conveyors.pptIntroduction to Conveyors.ppt
Introduction to Conveyors.ppt
 
Mining machinary nit rourkela
Mining machinary nit rourkelaMining machinary nit rourkela
Mining machinary nit rourkela
 
Highwall mining – a new approach in india
Highwall mining – a new approach in indiaHighwall mining – a new approach in india
Highwall mining – a new approach in india
 
longwall mining
longwall mininglongwall mining
longwall mining
 
Belt conveyor
Belt conveyorBelt conveyor
Belt conveyor
 
DIRECT ROPE HAULAGE SYSTEM IN MINING
DIRECT ROPE HAULAGE SYSTEM IN MININGDIRECT ROPE HAULAGE SYSTEM IN MINING
DIRECT ROPE HAULAGE SYSTEM IN MINING
 

Semelhante a Belt conveyor and Haulage system in the mine

Design and fabrication_automatic_conveyor_ppt
Design and fabrication_automatic_conveyor_pptDesign and fabrication_automatic_conveyor_ppt
Design and fabrication_automatic_conveyor_ppt
DuraimuruganM27
 
Mumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metroMumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metro
satish choudhari
 

Semelhante a Belt conveyor and Haulage system in the mine (20)

In pit crusher conveyour system
In pit crusher conveyour systemIn pit crusher conveyour system
In pit crusher conveyour system
 
DESIGN OF SUPPORT SYSTEM IN BORD AND PILLAR MINE
DESIGN OF SUPPORT SYSTEM IN BORD AND PILLAR MINEDESIGN OF SUPPORT SYSTEM IN BORD AND PILLAR MINE
DESIGN OF SUPPORT SYSTEM IN BORD AND PILLAR MINE
 
Metro Project
Metro ProjectMetro Project
Metro Project
 
Blastless track construction in tunnel and elavated metro station constructio...
Blastless track construction in tunnel and elavated metro station constructio...Blastless track construction in tunnel and elavated metro station constructio...
Blastless track construction in tunnel and elavated metro station constructio...
 
Design and fabrication_automatic_conveyor_ppt
Design and fabrication_automatic_conveyor_pptDesign and fabrication_automatic_conveyor_ppt
Design and fabrication_automatic_conveyor_ppt
 
Time Overrun in Transportation Project - A Case Study of Mumbai Monorail
Time Overrun in Transportation Project - A Case Study of Mumbai MonorailTime Overrun in Transportation Project - A Case Study of Mumbai Monorail
Time Overrun in Transportation Project - A Case Study of Mumbai Monorail
 
diesel locomotive works training report by somesh dwivedi
diesel locomotive works training report by somesh dwivedidiesel locomotive works training report by somesh dwivedi
diesel locomotive works training report by somesh dwivedi
 
Belt conveyor
Belt conveyorBelt conveyor
Belt conveyor
 
DESIGN OF MINE SHAFT ELEVATOR design guide
DESIGN OF MINE SHAFT ELEVATOR   design  guideDESIGN OF MINE SHAFT ELEVATOR   design  guide
DESIGN OF MINE SHAFT ELEVATOR design guide
 
Development Of Tipper Unloading Mechanism
Development Of Tipper Unloading MechanismDevelopment Of Tipper Unloading Mechanism
Development Of Tipper Unloading Mechanism
 
Design, Simulation & Optimization of Gravity Spiral Roller Conveyer with Auto...
Design, Simulation & Optimization of Gravity Spiral Roller Conveyer with Auto...Design, Simulation & Optimization of Gravity Spiral Roller Conveyer with Auto...
Design, Simulation & Optimization of Gravity Spiral Roller Conveyer with Auto...
 
Dlw locomotive workshop
Dlw locomotive workshopDlw locomotive workshop
Dlw locomotive workshop
 
Highway construction or Road work report
Highway construction or Road work reportHighway construction or Road work report
Highway construction or Road work report
 
Mumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metroMumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metro
 
Indian railway ajmer
Indian railway ajmerIndian railway ajmer
Indian railway ajmer
 
IRJET- Design and Manufacturing of Ladder Roof Lift for Material Lifting
IRJET-  	  Design and Manufacturing of Ladder Roof Lift for Material LiftingIRJET-  	  Design and Manufacturing of Ladder Roof Lift for Material Lifting
IRJET- Design and Manufacturing of Ladder Roof Lift for Material Lifting
 
Motorized Sccissor Lift
Motorized Sccissor Lift Motorized Sccissor Lift
Motorized Sccissor Lift
 
Optimization of productivity with surface miner using conveyor loading and tr...
Optimization of productivity with surface miner using conveyor loading and tr...Optimization of productivity with surface miner using conveyor loading and tr...
Optimization of productivity with surface miner using conveyor loading and tr...
 
Nce603 mod unit5
Nce603 mod unit5Nce603 mod unit5
Nce603 mod unit5
 
Optimization of productivity with surface miner using
Optimization of productivity with surface miner usingOptimization of productivity with surface miner using
Optimization of productivity with surface miner using
 

Mais de Anurag Jha (9)

Mine Opening and Development
Mine Opening and DevelopmentMine Opening and Development
Mine Opening and Development
 
Traning report on Khetri Copper Mine
Traning report on Khetri Copper MineTraning report on Khetri Copper Mine
Traning report on Khetri Copper Mine
 
Sontaneous Heating Characteristics of Coal
Sontaneous Heating Characteristics of CoalSontaneous Heating Characteristics of Coal
Sontaneous Heating Characteristics of Coal
 
Stope Optimization in Metal Mines
Stope Optimization in Metal MinesStope Optimization in Metal Mines
Stope Optimization in Metal Mines
 
Acid Mine drainage occurrence and its remediation
Acid Mine drainage occurrence and its remediationAcid Mine drainage occurrence and its remediation
Acid Mine drainage occurrence and its remediation
 
DESIGN OF SUPPORT SYSTEM IN BORD AND PILLAR MINE
DESIGN OF SUPPORT SYSTEM IN BORD AND PILLAR MINEDESIGN OF SUPPORT SYSTEM IN BORD AND PILLAR MINE
DESIGN OF SUPPORT SYSTEM IN BORD AND PILLAR MINE
 
Highwall Mining
Highwall MiningHighwall Mining
Highwall Mining
 
Excursion Report of Jhanjhra Coal Mines
Excursion Report of Jhanjhra Coal MinesExcursion Report of Jhanjhra Coal Mines
Excursion Report of Jhanjhra Coal Mines
 
Optimization of Blasting Parameters in open cast mines
Optimization of Blasting Parameters in open cast minesOptimization of Blasting Parameters in open cast mines
Optimization of Blasting Parameters in open cast mines
 

Último

Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Christo Ananth
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
Tonystark477637
 

Último (20)

Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 

Belt conveyor and Haulage system in the mine

  • 1. DISTINGUISH THE MINE PERFORMANCE BY CONVEYOR BELT AND HAULAGE SYSTEM OF TRANSPORTATION A mini project Submitted in partial fulfilment of requirements for award of Bachelor of Technology and in Mining Engineering By Anurag Kumar Jha Exam Roll no.-511214025 SESSION 2015-2016 DEPARTMENT OF MINING ENGINEEING INDIAN INSTITUTE OF ENGINEERING SCIENCE AND TECHNOLOGY, SHIBPUR HOWRAH-711103
  • 2. Section 1.01 Department of Mining Engineering INDIAN INSTITUTE OF ENGINEERING SCIENCE AND TECHNOLOGY, SHIBPUR (An Institute of National Importance) ii CERTIFICATE This is to certify that the dissertation titled “DISTINGUISH THE MINE PERFORMANCE BY CONVEYOR BELT AND HAULAGE SYSTEM OF TRANSPORTATION ” being submitted by Anurag Kumar Jha (Roll No.-511214025) to the Department of Mining Engineering, Indian Institute of Engineering and Science Technology, Shibpur, in partial fulfilment of requirements for award of dual degree of Bachelor of Technology and Master of Technology in Mining Engineering is a record of bona fide work carried out by him under my supervision and guidance. To the best of my knowledge, the matter embodied in this document has not been submitted anywhere else for award of any other degree or diploma. Date. ___________________________________ (<Dr. N. C. DEY>) Associate/ Assistant/ Professor in Mining Engineering
  • 3. iii Acknowledgements We are thankful to Dr. N. C. DEY, Professor, Department of Mining Engineering IIEST, SHIBPUR for his constant supervision, guidance, motivation and support at every stage of this project work. We would also like to convey our sincere gratitude and indebtness to the faculty and staff members of Department of Mining Engineering, IIEST, Shibpur, for their help at different times. We would also like to extend our sincere thanks to Dr. Indarnath Sinha, Dr. Pratik Dutta, for their help in providing the necessary information for the dissertation work. Last but not the least, our sincere thanks to all our friends who have extended all sorts of help for completion of this work. (Anurag kumar jha) IV Sem Dual (BTech-Mtech) Degree Programme in Mining Engineering Indian Institute of Engineering Science and Technology, Shibpur Howrah-- 711103
  • 4. iv Table of Contents DISTINGUISH THE MINE PERFORMANCE BY CONVEYOR BELT AND HAULAGE SYSTEM OF TRANSPORTATION.........................................................................................1 CERTIFICATE..........................................................................................................................ii Acknowledgements.................................................................................................................. iii Table of Contents......................................................................................................................iv Abstract.....................................................................................................................................vi List of Figures..........................................................................................................................vii List of Tables ......................................................................................................................... viii Abbreviations and Acronyms Used ..........................................................................................ix Chapter-1 Introduction...............................................................................................................1 Chapter-2 Transport System In Underground Mines.................................................................3 2.1 Teansport System.................................................................................................................3 2.1.1 Rope Haulage................................................................................................................3 2.1.2 CONVEYOR SYSTEM OF HAULAGE ................................................................................3 2.2 Underground Transport Arrangement..................................................................................3 2.3 Direct Rope Haulage............................................................................................................3 2.3.1 Direct Rope Double Drum Balanced Haulage..............................................................4 3.4 End Less Haulage ................................................................................................................5 3.5 Main and Tail rope haulage .................................................................................................7 3.6 Tail rope haulage..................................................................................................................8 3.7 Gravity haulage or self acting incline ..................................................................................8 3.8 Safety Devices in Haulage...................................................................................................8 3.9 Belt conveyor.......................................................................................................................8 3.9.1 Selection of belt conveyor ............................................................................................9
  • 5. v 3.9.2 Factors For Designing Of Belt Conveyor ...................................................................10 3.9.3 Loop Take Up Arrangement Of Tensioning Device For Belt Conveyor....................10 Chapter-4 Observations ...........................................................................................................12 Chapter-5 Conclusions.............................................................................................................14 References................................................................................................................................15 Appendices.................................................................................................................................1
  • 6. vi Abstract Transportation system is a measure part of mining activity at any type of mining method. Selection of proper type of transportation system in any coal mines gives better production efficiency as well as better productivity. It may reduce the labour charge and requirement of man. It can also increase the production per shift. Selection of transportation system is mainly depends upon the requirement of coal, condition of coal seam, condition of roof and floor of gallery, depth of seam, man power, mechanization of mines and mining method also.
  • 7. vii List of Figures Sl No. Name Page 1 Track layout of direct rope haulage 14 2 Endless rope haulage 15 3 Main and tail rope haulage 16 4 Layout of face gate and trunk conveyor in coal mine 18
  • 10. 1 Chapter-1 Introduction Transport development followed two distinct routes in each of the major functions namely the movement of ore /coal, persons, material and equipment. Ore/coal transport has either been by locomotive hauled mine cars belt conveyor or rubber tired trucks. The transport of persons materials and equipment has either been by rail mounted tracks systems or trackless systems/movable vechicles. Each system described above is still widely popular for those various specific region. The consideration of transport system for ore and coal, persons, materials, and equipment and major factors in the decision to use drifts and or shafts for a mine
  • 11. 2
  • 12. 3 Chapter-2 Transport System In Underground Mines 2.1 Teansport System 2.1.1 Rope Haulage i) Direct rope haulage (1) Tail rope haulage ii) Endless rope haulage (1) Over-rope (2) Under-rope iii) Main and tail rope haulage iv) Gravity haulage 2.1.2 CONVEYOR SYSTEM OF HAULAGE i) Belt conveyor ii) Cable belt conveyor iii) Chain conveyor (1) Scraper chain conveyor (2) Armoured chain conveyor (3) Gate end loader (4) Mobile stage loader (5) Pick-aback conveyor iv) Plate conveyor v) Disc conveyor 2.2 Underground Transport Arrangement It is divided into following category 1) Main haulage The main haulage arrangement is that which operates between winding shaft/incline and the main underground loading points. At the main loading point, the loads are collected from one, two or more districts. 2) Gathering haulages The gathering haulage arrangement is that which operates between the working faces and the main loading points 3) Secondry haulage In a large mine, where the working faces are far from the main loading point, an intermediate transport arrangement operates and it is known as secondary haulage 2.3 Direct Rope Haulage It is a simplest system employing in the mine ,consists of one pulling rope and one haulage drum for hauling minerals in tubs ir mine cars up a gradient which is generally stipper than 1 in 10. The haulage engine is situated at the top of an incline roadway and
  • 13. 4 the train of tubsis attached to one end of the rope, the end being fixed to the haulage drum. The empty tubs attached to the end of the haulage rope travel on the down gradient by their own weight and do not require power from the haulage engine. The drum shafts is therefore provided with a jow clutch to disengage it from the engine. A slip ring motor with drum controller is used. Advantage (1) The rope speed is generally 8-12 km/h and the system can operate between any point of the haulage plane and the haulage engine (2) It can, therefore, cope with the haulage requirements of an advancing working face. (3) Only one haulage track is required (4) The system can also serve branch roads if the gradient is suitable for down-the-gradient movement of empties by gravity. For this reason, the branch road deviating at an angle of not more than 400 off the main road is convenient Disadvantage (1) High peak power demand as load starts its journey up the gradient (2) Severe braking duty on the downward run. (3) High haulage speed demanding high standard of track maintenance (4) Not suitable for mild inclination of roads. (5) A derailment is associated with heavy damage because of high speed 2.3.1 Direct Rope Double Drum Balanced Haulage It is a modification of direct rope haulage, two drums are provided so that when a train of full tubs is being hauled out bye, a set of empty tubs is lowered inbye. Both the drums are fitted with clutches and are mounted on the same shaft, weight of the rope and the tubs are balanced and only the unbalanced load for the engine is mineral. This results in a reduced peak power demand and easer breaking , the system gives higher output in each trip of the rope brings the loads and there is regular delivery of the loaded tubs. The system requires wider roads for the haulage.
  • 14. 5 2.1 Track Layout Of Direct Rope Haulage (E-track of empties and F-track of loaded) 3.4 End Less Haulage In this system there are two parallel tracks side by side. One for loaded tubs and the another for empty tubs and the endless rope passing from driving drum locared at outbye end of the haulage road to the inbye end and back again via a tension bogey. The tubs loaded as well as empties are attached to the rope with regular interval with the help of clips so that the entire rope length has tubs on it at intervals. Only one end of the tub is attached to the rope at a time. But where lashing chain is used for attachment the normal practice is to attach a set of tubs and the attachment or detachment is performed by stopping the rope if however clips are used for single tubs they can be attached or detached when the rope is in motion. The gradient of haulage road is mild and rarely exceeds 1 in 6. The rope speed ranges between 3 km/h and 7 km/h and the haulage is slow moving. The rope moves in one direction only.
  • 15. 6 2.2 End Less Rope Haulage There are two types of endless rope haulage. 1. Over rope type In over rope type the haulage rope passes over the tub or set a tubs. 2. Under rope type In under rope type it passes beneath the tub or set of tubs. Advantage i) Because of slow speed, less wear and tear. ii) Accident from derailed tubs does not cause much damage due to slow speed. iii) Motor of less power required. iv) It does not place heavy demand on the power supply. Disadvantage i) It requires wide road for two tracks. ii) It is not suitable for sleep gradient iii) Load on the rope is larger and a rope of larger cross-section is required. iv) Large no of tubs and clips are required as rolling stock. v) If a break-down of any tub occurs the whole system comes to a standstill.
  • 16. 7 vi) It can not serve a main road and a branch road simultaneously unless elaborate arrangements are made to course the rope to the branch line with the help of deflection pulleys. 3.5 Main and Tail rope haulage In main and tail rope haulage, the hauling engine is provided with two separate drums one for the main rope, which haul the full train out and one for the tail which haul for the empty train in. When one drum is in gear, the other revolves freely on the shaft but controlled when necessary, by the brake to keep the rope taut. The main rope is approximately equal to the length of the plane and the tail ropes twice this length. In this type of haulage only one track is required and it is suitable for undulating roadways where it is impossible and undesirable to maintain the double track required for endless rope haulage. It can readily negotiate curves and it is convenient for working branches. It operates at fairlyhigh speeds and with long trains and if a derailment occurs,the resulting damage and delay likely to be considerable. 2.3 Main And Tail Rope Haulage Advantage i) This system of haulage is suitable for undulating roadways, where it is impossible or undesirable to maintain the double track . ii) Unlike endless rope haulage, this system requires one track. iii) Less maintenance cost for one track compare to two tracks. iv) Can readily negotiate curve.
  • 17. 8 v) It is convenient for working branches. vi) It operates at fairly high speed. Disadvantage i) As it operates at fairly high speed, more wear and tear. ii) Derailment can cause more harms to man and machine. iii) Long length of rope is required causing more cost of maintenance. iv) It became very difficult to manage the system properly. 3.6 Tail rope haulage It is situated at the lower level and the empties are hauled up the sloping track. The haulage rope passes to the train of empty tubs via a deflection pulley located at the top of the roadway. The loads travel by gravity down the gradient but as the rope is attached to them; their descent is controlled by the haulage driver. 3.7 Gravity haulage or self acting incline It is located at the top of the inclined roadway and is employed to lower by gravity the loads attached to one end of the rope which passes round the vertical jig pulley. Only single track is required for the operation but at the mid way of the road where the loads and empties meet, double track or a bye-pass is essential. This haulage operates without any motor or external source of power and consists of a cast iron pulley of 1.3 m to 2 m diameter having a brake path on the side and a strap brake. 3.8 Safety Devices in Haulage i) Stop blocks ii) Buffers iii) Back catches iv) Pointer plates v) Drop war wick vi) Age croft device vii)Back stays viii) Runway switches ix) Jazz rails x) Retarders xi) Approach warning device 3.9 Belt conveyor The belt conveyor is basically an endless belt in a straight line stretched between two drums, one driving the system and the other acting as a return drum. In coal mines and other mines of stratified deposits, where the underground mineral if won by longwall method, the transport media which often consists of conveyor.
  • 18. 9 2.4 Layout Of Face, Gate And Trunk Conveyors In A Coal Mine The system of transport by belt conveyor consists of the following:- i) A flat endless belt which moves continuously and carries at its top surface the material to be conveyed. ii) The idlers which support the belt. iii) The structure of channel iron on which the idlers are mounted. iv) The tensioning arrangement for keeping the belt in proper tension. v) The drums at the discharge and tail end over which the belt passes. vi) The drive head which comprises the electric motor, coupling, gearing and snub pulleys. 3.5(b)-Arrangement of a belt conveyor 3.9.1 Selection of belt conveyor
  • 19. 10 There are following factors that decide the selection of belt conveyor (a) Amount of material to be conveyed (b) Continuity of operation needed (c) Size of lumps (d) Distance of transportation (e) Environmental allowance (f) Gradient (g) Method of coal winning, i.e. Longwall or Bord and Pillar (h) Capital Available Advantages:- (a) A continuous supply of material (b) Low operating cost than road transportation system (c) High rate and speed of supply (d) Bunding can be done to get fair grade (e) More efficiency and low cost Limitations of belt conveyor:- There are following limitation of belt conveyor- (a) It cannot be used for long distances (b) It requires high one time capital investment (c) It cannot handle the Lumps of big size (d) Place should be dry enough where it will installed and air velocity should not be high (e) It cannot be operates at high inclinations 3.9.2 Factors For Designing Of Belt Conveyor i) The average tonnage (t/h), peak rate (t/min) and frequency of peak rates. ii) Characteristics of the material i.e.  Density  Maximum lump size  Nature of material- dry, wet, sticky, dusty  Chemical action on belt iii) Graphical layout of conveyor profile and motive power available (i.e. electric motor). iv) Operating conditions - hours of working, climatic conditions etc. v) Suitability of a belt conveyor & width and speed of belt. vi) Belt shape vii)Power and layout required 3.9.3 Loop Take Up Arrangement Of Tensioning Device For Belt Conveyor Tensioning of the belt is necessary to prevent excessive sagging of the belt or belt in good contact with the driving drum. There are following arrangement for the tensioning of the belt-
  • 20. 11 (i) Automatic take ups (ii) Gravity take ups (iii)Take up pulley with counter weight (iv)Counter weighted loop take (v) Counterweighted wheel mounted tail end pulley (vi)Power take ups (vii) Electric motorized winch and load cell loop take up (viii) Electric motorized winch and load cell loop take up (ix)Hydraulically loop takes up (x) Rigid or manual take ups (xi)Screw take up (xii) Jack take up (xiii) Winch take up
  • 21. 12 Chapter-4 Observations The study of many overland conveyor (OLC) vs. truck haulage reveal some basic and new facts: 1) Belt conveyor is more time and effort saving so it saves the costs. However , it is inconvenient to move, which the advantage of trucks. 2) The problem with haulage no matter the tonnage class size is that they are only fifty percent efficiency. 3) Conveyors have a very high cost per foot of installation in thousands of dollars per foot and they requires replacement idlers belting, motor, pulleys, gear boxes, chain drives, high or medium voltage electricity to power them, emergency stop systems from end to end and labor to main tail them as well as labor to install conveyor extensions. A conveying system of any ype requires primary and secondary crossing system and or conveyor belt feeder/breakers to load them as well. Adding more to the purchase cost operational cost. 4) Penalizing the conveyor with ore size reduction is also a fallacy. The rock is going to be crushed in any case in order to processed. One can argue about crusher maintenance in remote areas. Still these facts are assessed during the feasibility phase. 5) Breakeven point for OLC is a transport circuit that must convey 2 million tons per annum over more than one kilo meter or the total multiplier of tons and kilo meters. This is further dependent on local fuel costs and terrain difficulty. Some countries subsidize their diesel fuel that artificially lowers the truck penalty that is now changing. 6) Conveyors can often be routed in a more direct path than the road haulage thereby reducing the kilo meter penalty. The path may include bridges over rivers, roads, railroads, etc. 7) Conveyors can negotiate rough terrain to 18 degrees or more making for shorter paths or that would require tunnel by trucks. 8) Conveyors are more efficient with fuel usage than trucks especially with the payload of an empty truck return haul. 9) Conveyor designs have become more efficient with new rubber compounds and new design methods that lower rolling energy by 50% or more than many suppliers of rubbers from 5 years ago. Trucks have not seen such improvements in rolling losses. A case in point is the Curragh 20km single flight overland that transports 2500 t/h. It is light and fast (7.5 m/s). It is very light for the tons conveyed due to efficient use of sheet metal components for is idler and belt support and wind shielding. IN 2007, it was the fastest operating belt conveyor in Australia. Speed lowers the conveyor system width which is the most capital intensive parameter. Some have disparaged the
  • 22. 13 design and been wrong in their assessment. It's 5 m carry side and 10 m return idler spacing is proven to be appropriate when the plant has been properly operated. 10) New research into more efficient belt conveyor operations is proving that further cost effective gains are possible compared to trucks and trains. More difficult terrain, stronger belts, lower belt strength as measured by the necessary Safety Factor, lower rolling resistance designs, and lower metal mass per km all point to ongoing improvements over truck and trains. 11) New conveyor configurations can be found with better trough shapes, pipe, and semi pipe designs are now a reality where high lifts and sharp curvatures are required that add to belt conveyor transport efficiency. 12) studies of +100km conveyors does demonstrate the ability for long and efficient transport compared with train haulage. Risk analysis then becomes an important factor in the “what if “scenarios.
  • 23. 14 Chapter-5 Conclusions There are various advantage and disadvantage of both of the method of transportation of material. But we can chose any one by our requirement because where belt conveyor has lot of maintenance and installing cost but it will give us lot of production who save our time and labour cost where as if we can not interested in the huge production than truck haulage best option but we should try belt conveyor with advanced technology who will give us production in long distance. It will save the effort and other labour work. If we want to supply the material in long path way than haulage is more efficient belt conveyor is not sufficient. And if we want to handle big size lump conveyor is not adequate for it. Belt conveyor can not operate at high inclination and the place should be enough clean and dry. Land and weather are good grounds for eliminating either choice. The question should be "Do you want the stuff or not?" If the answer is yes then the economics is out of the window. You have to have it so be prepared to pay for it. Trucks need good dry ground to travel and plenty of it. Conveyors also need an acceptable right of way and can only negotiate a route within set limits. Truck CAPEX is not so small andthe OPEX is higher than for conveyors, provided you don't slit a belt into 2.