CONTROLLING THE POWER
PLANT AND INFRASTRUCTURE
PROJECTS SUPPLY CHAIN
Key Issues to look for and how they can
be solved
https://www.statsengineering.com
PREFACE
In huge infrastructure facilities and projects, such as power plants, unfortunately it is not always possible to
prevent poor installation quality. Discovering poor quality at a late stage can add an exponential increase
to the costs, with dreadful consequences for the client and the development of the whole plant. To the the
contrary, by using the Supply Chain risk mitigation methods enabling good surveillance for quality, there is a
chance to discover poor quality early thus allowing for immediate solution.
https://www.statsengineering.com
CONTROLLING THE POWER PLANT AND INFRASTRUCTURE PROJECTS SUPPLY CHAIN
A project is a set of activities with a defined start point and a defined end state, which pursues a defined goal and uses a defined set of
resources with a common goal for which we try to control costs, resource usage, completion time, and quality of the output.
Supply Chain Management in power industry is a critical activity for the success of the project and the industry required supply chain
practitioners with diverse knowledge not only on the business side but on also on the technical side enable them to procure the right tools
and services at competitive price and quality with minimum risk exposure.
The understanding and practicing of supply chain management (SCM) has become an essential prerequisite for staying competitive in the
global race and for enhancing profitability.
Defining Project
https://www.statsengineering.com
Proportions of Projects that encounter Cost & Time Control
Proportion of Projects Time overrun Cost Overrun
> 90% 2.9% 4.4%
60 - 90% 1.5% 7.4%
40 - 60% 8.8% 11.8%
10 - 40% 48.5% 35.3%
< 10% 38.2% 41.2%
Reference; Cost & Time Control of Construction Projects by Yakubu Adisa Olawale
Construction management and Economics
Why the Need for Supply Chain Management
Survey conducted on 250 construction projects in UK
https://www.statsengineering.com
Controlling the Power Plant and infrastructure projects supply chain
CONTROLLING THE POWER PLANT AND INFRASTRUCTURE PROJECTS SUPPLY CHAIN
Supply chain is NOT a CHAIN of businesses
BUT A NETWORK of businesses & relationships
That offers the opportunity to capture the full potential of intra and inter-company integration and management to organize – people,
activities, information and resources involved in moving a product at the right quantities, right locations and at right time when linking them
from supplier to end-user satisfying the service level requirements. In other words it is management to efficiently integrate all resources.
https://www.statsengineering.com
CONTROLLING THE POWER PLANT AND INFRASTRUCTURE PROJECTS SUPPLY CHAIN
Power plants have:
1. Complex structures.
2. Involve large amounts of capital.
3. long-running construction period.
4. Multivendor supply chain.
5. Complex procedures and activities and equipment integration.
For example: A coal fired power plant of the 700 MW class consists of approximately 9000 activities
and 18000 logic links to determine the critical path and to identify schedule changes and subsequent
impacts.
(www.energy.siemens.com/hq/...power-plants/1_Successful_Complementation.)
https://www.statsengineering.com
POWER PLANT CONSTRUCTION SUPPLY CHAIN
A CRITICAL PHASE.
The construction phase is identified as a critical phase in power projects supply chain where
many unforeseen factors occur.( Article - Supply Chain Risk Management in power industry-
Vienna University of technology) Failure to manage project risks leads to significant
problems for the project and a project risk management in the supply chain in the
construction stage of power plant projects should be conducted to achieve and support:
 Shorter construction periods.
 Mitigate uncertainty factors and considerably high risks.
 Prevent time delays and cost overruns .
 Deliver quality.
https://www.statsengineering.com
BENEFITS OF SUPPLY CHAIN IN CONSTRUCTING A POWER PLANT
Supply chain has immense benefits to the adding value while minimizing total cost of project. Some of the benefits are listed below:
 Decrease in inventory cost by more accurate estimation and scheduling construction
execution to match it,
 Reduce the overall construction cost by streamlining the flow of supplies to the
execution process and by improving information flow between the agencies,
 Improve client’s satisfaction by offering better qualities, timely completion of projects and
minimizing the costs,
 Reduce the replenishment time of the supplies at the construction sites,
 Helps in accurate forecasting of change orders and making available actual estimation
information to all levels, Helps in standardizing of construction processes by
implementing quality assurance plan,
https://www.statsengineering.com
Sample of a System of Multiplier Supplier – Integrated Supply Chain Systems
CLIENT FEED & DESIGN ENGINEERING
PROCUREMENT
(VENDORS
LOGISTIC
OPERATION COMMISSIONING
PROJECT
COMPLETION
SITE
SUBCONTRACTORS
/SUPPLIERS
MAIN CONTRACTOR
Source: Supply Chain Improvement in Construction Industry- National technical University of Athens-Greece.
https://www.statsengineering.com
Supply Chain Risks
0
1
2
3
4
5
6
Rating of Concern on a scale of 1-10 (10 Indicating greatest Concern)
Reference: Managing Risk in the Global Supply Chain faculty - University of Tennessee
https://www.statsengineering.com
Supply Chain Risks Mitigation
0
1
2
3
4
5
6
7
8
Preference on a scale of 1-10 (10 Being Most Preferred )
Reference: Managing Risk in the Global Supply Chain faculty - University of Tennessee
https://www.statsengineering.com
Supply Chain Risks- Influencing factor when constructing a Power Plant
0
1
2
3
4
5
6
Right Contractors &
Subcontractors
Strong QA/QC
Strong Supplier Visibility & Due
Diligence
Expediting &
Inprocess
Inspection
Best Practice for
Shipping, Clearing &
Packaging - Pre
Shipment Inspection
PreShipment
Inspection
Purchase Insurance
Rating of Concern on a scale of 1-10)
Quality
RiskofSupplierFailure
Design
Consideration
MeetingClient
Expectation
Wrong
Specificationfor
Manufacturing
TransitLossduetoPoor
Packaging/Accidents
Customs
Political
Instability
R
I
S
K
S
https://www.statsengineering.com
TRADITIONAL COST AND HIDDEN COST OF POOR QUALITY( COPQ)
Hidden COPQ: The costs
incurred to deal with these
chronic problems
https://www.statsengineering.com
Traditional Cost
Hidden Cost
Quality and Supply Chain Management advantages
Source: Effectiveness of quality in Supply Chain management- Noida International University-India.
https://www.statsengineering.com
SUPPLY CHAIN RISK MITIGATION MEASURES- PROCUREMENT AND
CONSTRUCTION
1. Selection of Right Vendors and Suppliers.
2. Continuous Quality Surveillance System at site.
3. Listing Inhibitive and Mitigation Measures.
4. Understanding Critical Path for time Analysis and management.
5. Understanding importance of Criticality Index for reliability
https://www.statsengineering.com
Factory Evaluation – Vendor Assessment Procurement
VMT- Verification of Manufacturers testing Product Quality
In-process and Factory Acceptance Testing Product Conformance as per purchase specification.
Pre- Shipment Inspections Shipping of lesser quality material to the site.
Receipt Inspections by the means of enterprise part tracking system Receiving wrong or lesser quality material /substitute material
SQR pre-shipment and site QA/QC program guidelines and checklists Non Conventional and sub standard loading and unloading practices
SQR Guidelines for Marking and Packaging for shipping equipments Non Standard Packaging and Damage in transit
SQR Guideline for preservation and checklist for conformance of activity Non Standard preservation of critical equipments on site
SQR site QA/QC program and site material handling guidelines and checklists Defective or Non Standard methods of material handling on site.
SAT, after installation, Verification of performance as per PTC and relevant
standards after commissioning.
Commissioning of Power Plant/Infra Projects
Addressing Supply chain High Impact factors for quality-Solutions to the key
issues from SQR
https://www.statsengineering.com
Professional Services
To address following issues
Thank
you
CONTROLLING THE POWER PLANT
AND INFRASTRUCTURE PROJECTS
SUPPLY CHAIN
https://www.statsengineering.com

Mais conteúdo relacionado

Semelhante a Controlling quality supply chain issues for infrastructure projects

Nilesh More_Project Manager
Nilesh More_Project ManagerNilesh More_Project Manager
Nilesh More_Project Manager
Nilesh More
 
MUKUL PATEL 21042016
MUKUL PATEL 21042016MUKUL PATEL 21042016
MUKUL PATEL 21042016
Mukul Patel
 
Petrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj LloydPetrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj Lloyd
Nitin Sethi
 
Midstream Automation, Instrumentation & Control Congress 2015
Midstream Automation, Instrumentation & Control Congress 2015Midstream Automation, Instrumentation & Control Congress 2015
Midstream Automation, Instrumentation & Control Congress 2015
marketinglbcg
 
Offshore Wind Energy: Improving Project Development and Supply Chain Processe...
Offshore Wind Energy: Improving Project Development and Supply Chain Processe...Offshore Wind Energy: Improving Project Development and Supply Chain Processe...
Offshore Wind Energy: Improving Project Development and Supply Chain Processe...
Stavros Thomas
 
Aquaculture Facility Rehabilitation - Presentation 04-29-2013
Aquaculture Facility Rehabilitation - Presentation 04-29-2013Aquaculture Facility Rehabilitation - Presentation 04-29-2013
Aquaculture Facility Rehabilitation - Presentation 04-29-2013
David M. Athey, PE
 
EPC_Enterprise_Systems_Deck
EPC_Enterprise_Systems_DeckEPC_Enterprise_Systems_Deck
EPC_Enterprise_Systems_Deck
Jaswin Sood
 

Semelhante a Controlling quality supply chain issues for infrastructure projects (20)

IRJET- Review on Risk Assessment of Supply Chain Management in Constructi...
IRJET-  	  Review on Risk Assessment of Supply Chain Management in Constructi...IRJET-  	  Review on Risk Assessment of Supply Chain Management in Constructi...
IRJET- Review on Risk Assessment of Supply Chain Management in Constructi...
 
Nilesh More_Project Manager
Nilesh More_Project ManagerNilesh More_Project Manager
Nilesh More_Project Manager
 
MUKUL PATEL 21042016
MUKUL PATEL 21042016MUKUL PATEL 21042016
MUKUL PATEL 21042016
 
Investigation of Supply Chain Management in Construction Companies
Investigation of Supply Chain Management in Construction CompaniesInvestigation of Supply Chain Management in Construction Companies
Investigation of Supply Chain Management in Construction Companies
 
Quality management at construction projects: Case study of a stormwater netwo...
Quality management at construction projects: Case study of a stormwater netwo...Quality management at construction projects: Case study of a stormwater netwo...
Quality management at construction projects: Case study of a stormwater netwo...
 
Ch 2 develop an end-to-end process architecture
Ch 2   develop an end-to-end process architectureCh 2   develop an end-to-end process architecture
Ch 2 develop an end-to-end process architecture
 
Chapter 2 - Develop an End-to-end Process Architecture
Chapter 2 - Develop an End-to-end Process ArchitectureChapter 2 - Develop an End-to-end Process Architecture
Chapter 2 - Develop an End-to-end Process Architecture
 
Total Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project ControlsTotal Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project Controls
 
Quality Control in Infrastructure Development
Quality Control in Infrastructure DevelopmentQuality Control in Infrastructure Development
Quality Control in Infrastructure Development
 
JAYANT KUMAR
JAYANT KUMARJAYANT KUMAR
JAYANT KUMAR
 
Petrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj LloydPetrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj Lloyd
 
Midstream Automation, Instrumentation & Control Congress 2015
Midstream Automation, Instrumentation & Control Congress 2015Midstream Automation, Instrumentation & Control Congress 2015
Midstream Automation, Instrumentation & Control Congress 2015
 
IRJET- Construction Quality Management on Site
IRJET-  	  Construction Quality Management on SiteIRJET-  	  Construction Quality Management on Site
IRJET- Construction Quality Management on Site
 
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
 
Offshore Wind Energy: Improving Project Development and Supply Chain Processe...
Offshore Wind Energy: Improving Project Development and Supply Chain Processe...Offshore Wind Energy: Improving Project Development and Supply Chain Processe...
Offshore Wind Energy: Improving Project Development and Supply Chain Processe...
 
Operational Efficiency Based on Innovative Automation, Industry Expertise, En...
Operational Efficiency Based on Innovative Automation, Industry Expertise, En...Operational Efficiency Based on Innovative Automation, Industry Expertise, En...
Operational Efficiency Based on Innovative Automation, Industry Expertise, En...
 
Aquaculture Facility Rehabilitation - Presentation 04-29-2013
Aquaculture Facility Rehabilitation - Presentation 04-29-2013Aquaculture Facility Rehabilitation - Presentation 04-29-2013
Aquaculture Facility Rehabilitation - Presentation 04-29-2013
 
Choudhary Divyang Resume
Choudhary Divyang ResumeChoudhary Divyang Resume
Choudhary Divyang Resume
 
EPC_Enterprise_Systems_Deck
EPC_Enterprise_Systems_DeckEPC_Enterprise_Systems_Deck
EPC_Enterprise_Systems_Deck
 
Supply Chain Management Practices and Performance Effectiveness
Supply Chain Management Practices and Performance EffectivenessSupply Chain Management Practices and Performance Effectiveness
Supply Chain Management Practices and Performance Effectiveness
 

Mais de Aniruddha Kulkarni

Mais de Aniruddha Kulkarni (8)

Hazardous area module- Zones, Method of Determination of Hazardous area Radiu...
Hazardous area module- Zones, Method of Determination of Hazardous area Radiu...Hazardous area module- Zones, Method of Determination of Hazardous area Radiu...
Hazardous area module- Zones, Method of Determination of Hazardous area Radiu...
 
Make Profits - Evaluate your Construction Projects
Make Profits - Evaluate your Construction ProjectsMake Profits - Evaluate your Construction Projects
Make Profits - Evaluate your Construction Projects
 
Evaluation and Rating program for Construction Quality and Task Completion
Evaluation and Rating program for Construction Quality and Task CompletionEvaluation and Rating program for Construction Quality and Task Completion
Evaluation and Rating program for Construction Quality and Task Completion
 
Hazardous areas series( Module1 of 18) - What is hazardous area and explosio...
Hazardous areas series( Module1 of 18)  - What is hazardous area and explosio...Hazardous areas series( Module1 of 18)  - What is hazardous area and explosio...
Hazardous areas series( Module1 of 18) - What is hazardous area and explosio...
 
Critical path presentation for timely project completion
Critical path presentation for timely project completionCritical path presentation for timely project completion
Critical path presentation for timely project completion
 
Electrical safety training based on osha 1910 standards sw
Electrical safety training based on osha 1910 standards swElectrical safety training based on osha 1910 standards sw
Electrical safety training based on osha 1910 standards sw
 
Electrical testing equipment clamp meters- Usage, operations and Safety
Electrical testing equipment   clamp meters- Usage, operations and SafetyElectrical testing equipment   clamp meters- Usage, operations and Safety
Electrical testing equipment clamp meters- Usage, operations and Safety
 
Testing inspection and certification industry
Testing inspection and certification industryTesting inspection and certification industry
Testing inspection and certification industry
 

Último

DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
MayuraD1
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Último (20)

Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Bridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptxBridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptx
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 

Controlling quality supply chain issues for infrastructure projects

  • 1. CONTROLLING THE POWER PLANT AND INFRASTRUCTURE PROJECTS SUPPLY CHAIN Key Issues to look for and how they can be solved https://www.statsengineering.com
  • 2. PREFACE In huge infrastructure facilities and projects, such as power plants, unfortunately it is not always possible to prevent poor installation quality. Discovering poor quality at a late stage can add an exponential increase to the costs, with dreadful consequences for the client and the development of the whole plant. To the the contrary, by using the Supply Chain risk mitigation methods enabling good surveillance for quality, there is a chance to discover poor quality early thus allowing for immediate solution. https://www.statsengineering.com
  • 3. CONTROLLING THE POWER PLANT AND INFRASTRUCTURE PROJECTS SUPPLY CHAIN A project is a set of activities with a defined start point and a defined end state, which pursues a defined goal and uses a defined set of resources with a common goal for which we try to control costs, resource usage, completion time, and quality of the output. Supply Chain Management in power industry is a critical activity for the success of the project and the industry required supply chain practitioners with diverse knowledge not only on the business side but on also on the technical side enable them to procure the right tools and services at competitive price and quality with minimum risk exposure. The understanding and practicing of supply chain management (SCM) has become an essential prerequisite for staying competitive in the global race and for enhancing profitability. Defining Project https://www.statsengineering.com
  • 4. Proportions of Projects that encounter Cost & Time Control Proportion of Projects Time overrun Cost Overrun > 90% 2.9% 4.4% 60 - 90% 1.5% 7.4% 40 - 60% 8.8% 11.8% 10 - 40% 48.5% 35.3% < 10% 38.2% 41.2% Reference; Cost & Time Control of Construction Projects by Yakubu Adisa Olawale Construction management and Economics Why the Need for Supply Chain Management Survey conducted on 250 construction projects in UK https://www.statsengineering.com Controlling the Power Plant and infrastructure projects supply chain
  • 5. CONTROLLING THE POWER PLANT AND INFRASTRUCTURE PROJECTS SUPPLY CHAIN Supply chain is NOT a CHAIN of businesses BUT A NETWORK of businesses & relationships That offers the opportunity to capture the full potential of intra and inter-company integration and management to organize – people, activities, information and resources involved in moving a product at the right quantities, right locations and at right time when linking them from supplier to end-user satisfying the service level requirements. In other words it is management to efficiently integrate all resources. https://www.statsengineering.com
  • 6. CONTROLLING THE POWER PLANT AND INFRASTRUCTURE PROJECTS SUPPLY CHAIN Power plants have: 1. Complex structures. 2. Involve large amounts of capital. 3. long-running construction period. 4. Multivendor supply chain. 5. Complex procedures and activities and equipment integration. For example: A coal fired power plant of the 700 MW class consists of approximately 9000 activities and 18000 logic links to determine the critical path and to identify schedule changes and subsequent impacts. (www.energy.siemens.com/hq/...power-plants/1_Successful_Complementation.) https://www.statsengineering.com
  • 7. POWER PLANT CONSTRUCTION SUPPLY CHAIN A CRITICAL PHASE. The construction phase is identified as a critical phase in power projects supply chain where many unforeseen factors occur.( Article - Supply Chain Risk Management in power industry- Vienna University of technology) Failure to manage project risks leads to significant problems for the project and a project risk management in the supply chain in the construction stage of power plant projects should be conducted to achieve and support:  Shorter construction periods.  Mitigate uncertainty factors and considerably high risks.  Prevent time delays and cost overruns .  Deliver quality. https://www.statsengineering.com
  • 8. BENEFITS OF SUPPLY CHAIN IN CONSTRUCTING A POWER PLANT Supply chain has immense benefits to the adding value while minimizing total cost of project. Some of the benefits are listed below:  Decrease in inventory cost by more accurate estimation and scheduling construction execution to match it,  Reduce the overall construction cost by streamlining the flow of supplies to the execution process and by improving information flow between the agencies,  Improve client’s satisfaction by offering better qualities, timely completion of projects and minimizing the costs,  Reduce the replenishment time of the supplies at the construction sites,  Helps in accurate forecasting of change orders and making available actual estimation information to all levels, Helps in standardizing of construction processes by implementing quality assurance plan, https://www.statsengineering.com
  • 9. Sample of a System of Multiplier Supplier – Integrated Supply Chain Systems CLIENT FEED & DESIGN ENGINEERING PROCUREMENT (VENDORS LOGISTIC OPERATION COMMISSIONING PROJECT COMPLETION SITE SUBCONTRACTORS /SUPPLIERS MAIN CONTRACTOR Source: Supply Chain Improvement in Construction Industry- National technical University of Athens-Greece. https://www.statsengineering.com
  • 10. Supply Chain Risks 0 1 2 3 4 5 6 Rating of Concern on a scale of 1-10 (10 Indicating greatest Concern) Reference: Managing Risk in the Global Supply Chain faculty - University of Tennessee https://www.statsengineering.com
  • 11. Supply Chain Risks Mitigation 0 1 2 3 4 5 6 7 8 Preference on a scale of 1-10 (10 Being Most Preferred ) Reference: Managing Risk in the Global Supply Chain faculty - University of Tennessee https://www.statsengineering.com
  • 12. Supply Chain Risks- Influencing factor when constructing a Power Plant 0 1 2 3 4 5 6 Right Contractors & Subcontractors Strong QA/QC Strong Supplier Visibility & Due Diligence Expediting & Inprocess Inspection Best Practice for Shipping, Clearing & Packaging - Pre Shipment Inspection PreShipment Inspection Purchase Insurance Rating of Concern on a scale of 1-10) Quality RiskofSupplierFailure Design Consideration MeetingClient Expectation Wrong Specificationfor Manufacturing TransitLossduetoPoor Packaging/Accidents Customs Political Instability R I S K S https://www.statsengineering.com
  • 13. TRADITIONAL COST AND HIDDEN COST OF POOR QUALITY( COPQ) Hidden COPQ: The costs incurred to deal with these chronic problems https://www.statsengineering.com Traditional Cost Hidden Cost
  • 14. Quality and Supply Chain Management advantages Source: Effectiveness of quality in Supply Chain management- Noida International University-India. https://www.statsengineering.com
  • 15. SUPPLY CHAIN RISK MITIGATION MEASURES- PROCUREMENT AND CONSTRUCTION 1. Selection of Right Vendors and Suppliers. 2. Continuous Quality Surveillance System at site. 3. Listing Inhibitive and Mitigation Measures. 4. Understanding Critical Path for time Analysis and management. 5. Understanding importance of Criticality Index for reliability https://www.statsengineering.com
  • 16. Factory Evaluation – Vendor Assessment Procurement VMT- Verification of Manufacturers testing Product Quality In-process and Factory Acceptance Testing Product Conformance as per purchase specification. Pre- Shipment Inspections Shipping of lesser quality material to the site. Receipt Inspections by the means of enterprise part tracking system Receiving wrong or lesser quality material /substitute material SQR pre-shipment and site QA/QC program guidelines and checklists Non Conventional and sub standard loading and unloading practices SQR Guidelines for Marking and Packaging for shipping equipments Non Standard Packaging and Damage in transit SQR Guideline for preservation and checklist for conformance of activity Non Standard preservation of critical equipments on site SQR site QA/QC program and site material handling guidelines and checklists Defective or Non Standard methods of material handling on site. SAT, after installation, Verification of performance as per PTC and relevant standards after commissioning. Commissioning of Power Plant/Infra Projects Addressing Supply chain High Impact factors for quality-Solutions to the key issues from SQR https://www.statsengineering.com Professional Services To address following issues
  • 17. Thank you CONTROLLING THE POWER PLANT AND INFRASTRUCTURE PROJECTS SUPPLY CHAIN https://www.statsengineering.com