Amir Assarpour has over 10 years of experience in construction project management, scheduling, estimating, and cost control. He has worked on large infrastructure projects for NYPA, MTA, and Amtrak/LIRR. As a senior estimator and scheduler, he developed schedules and budgets, analyzed bids, and ensured project success. He also has experience in design and value engineering. He holds an MS in Civil Engineering and is a licensed Professional Engineer in New York.
Amir Assarpour resume construction engineer scheduler estimator
1. Amir Assarpour, P. E. amir.assarpour@gmail.com
Objective: Obtain a position as Senior Scheduler, Senior Estimator, or Construction
Engineer with potential to become Construction Manager.
Experience
09/2009 – Present MCSS, Inc., Holmdel, NJ
Throgs Neck Bridge Security Project – Est. Const. Cost of $19,500,000
Senior Estimator & Scheduler (P6/P3)
• Produced the Engineers Estimate and analyze contractors bids
• Finalized project schedule, cost, and its implementation throughout the
Engineering, Procurement, Construction, and Commissioning phases using
P6
• Coordinated between various firms/trades on project scope to insure common
assumptions
• Developed procedures for preparation and maintenance of project plans,
master/detail schedules, and activity coding such as WBS
• Analyzed, commented, and approved the final schedule submitted by the
contractors to optimize cost/timing and identify discrepancies
• Executed cost and scope control management procedures for schedule, scope,
risk, quality, and issues
• Collected, consolidated, and monitored the project scope, cost, and schedule
control information to ensure overall project status was assessed and to
identify potential problems for corrective/preventive actions
NYPA Security Project – Est. Const. Cost of $2,800,000
Senior Estimator & Scheduler (P6)
• Produced the Engineers Estimate
• Developed and implemented project time schedule by P6, WBS and related
procedures based on contractual obligations
• Prepared and distributed the bi-weekly, monthly, and quarterly reports
including S-curve, histograms, tabular reports and schedules
• Identified potential risks/opportunities and generated mitigation strategies to
ensure project success
MTACC-ESA Project (LIRR Project) – Est. Const. Cost of $11,000,000,000
Value Engineer/Estimator/Budget & Constructability Analyst
• Responsible for estimates and TIAs of $3,000,000,000 worth of construction
• Reviewed Designers documentation for consistency in design for MTACC-
ESA Project
• Produced Estimates for changes up to $30,000,000 to contract scope of work,
and subsequently negotiated with the Contractor on behalf of MTACC-ESA
• Checked Budget vs. Scope of work changes to insure appropriate funding for
the MTACC-ESA Project
• Developed procedures for preparation and maintenance of project plans,
master/detail schedules, and activity coding such as WBS
• Responsible for analysis of contractors Bids for various scopes of work and
contracts
2. 07/2006 – 01/2009 Langan Engineering & Environmental Services, Inc., Manhattan, NY
Staff Engineer III
• Solely Responsible for the initial design and advancement to 100% DD phase
for the Queens Plaza Bicycle & Pedestrian Improvement Project from
conceptual design stages
• Highly experienced CAD designer
• 1,465 design hours across 51 projects as Geotechnical Engineer performing
Preconstruction Surveys, Pile Load Tests per NYSDOT standards,
Subsurface investigations, assisting in Foundation design, Seismic analysis
and numerical modeling, assisting in excavation support and underpinning
design, Controlled inspection, and instrumentation monitoring during
construction.
• 4,040 design hours across 58 projects as Site/Civil Engineer designing of
storm, sanitary, and combined sewer systems, catch basins and area drains,
Stormwater Detention Tanks, Site Connection Proposals (SCP), Drainage
Master Plan (DMP) Development, Builders Pavement Plans (BPP),
Streetscape and Tree planting Design, Traffic Studies, Roadway Alignment
Design, Traffic Stripping and Signage Design, Traffic Signal Plan
Development, Maintenance and Protection of Traffic Design, Erosion and
Sediment Control Design, Demolition Plan Development, Utilities Plans,
Surveying, recruiting newly graduated college students, and training interns
01/2002 – 06/2006 General Engineering Department, Polytechnic University, Brooklyn, NY
Teaching Assistant: Head of Inventory/Purchasing Committee
• Instructed students in performance of lab exercises
• Tutored student with use of AutoCAD, and LabVIEW programs
• Head of Purchasing Committee for the acquisition of necessary lab
equipment
05/2001 – 09/2001 Cima Group Architects & Engineers, Westchester, NY
Interned as an Architect
• Worked on the design of AT&T Buildings in Hawaii and New York
• Helped in the design of the rehabilitation of NY Presbyterian Hospital
Education
NYU Polytechnic School of Engineering, NY, 01/2007 – 06/2009
Masters of Science in Civil Engineering/Minor in Construction Management
Polytechnic University, Brooklyn, NY, 09/2002 – 06/2006
Bachelors of Science in Civil Engineering
CUNY: City College, NY, NY, 06/2002 – 09/2002
Advanced Engineering Learning Program
Skills
Microsoft Office Applications: Word, Power Point, Project, Excel, Access
Technical Programs: P3 & Primavera P6 Professional Project Management,
HeavyBid (HCSS), AutoDesk AutoCAD, Bently Microstation
Licenses/Certifications
• MNR, Amtrak, and LIRR track trained
• NYS Professional Engineer LIC# 093704-1