Welding Inspection
Welding Inspection Practical
Course Reference WIS 5
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
The purpose of this session is to practice the reporting
format required by CSWIP in the practical plate
examination part of the CSWIP 3.1 Welding Inspectors
exam
Remember the responsibilities of a Welding Inspector are:
 Observe
 Report
 Compare
PlateInspectionPracticePlateInspectionPractice
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
To observe welding imperfections you are required to have
good close vision acuity
A close vision acuity test will be given to you before your
exam to establish if your vision meets the minimum standard
required
Its not just the project that must meet the
standard!!
You will also require a thorough knowledge of welding
imperfections and their likely location, causes and
implications
ObserveObserve
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
 TWI Multi-function weld gauge for measuring many
different weld measurements.
 Fillet weld gauges for measuring leg lengths and throat
thickness.
 Hi-Lo gauge for measuring misalignment and root gaps
 Angle gauges for measuring weld preparation angles
A number of specialist welding gauges are available to
measure the various elements that need to be measured
in a welded fabrication including
SpecialistWeldingGaugesSpecialistWeldingGauges
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
TWIMultipurposeWeldingTWIMultipurposeWelding
GaugeGauge
60
50
40
0
1/4 1/2 3/4
1
0
5
10
15
20
IN
MM
15
1/2
IN
MM
Angle of preparation
The scale reads from 0o to 60o in steps of 5o.
The angle is read against the chamfered
edge of the segment
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
Misalignment
The scale is used to measure misalignment of
components by placing the edge of the gauge on
the lower one and rotating the segment until the
pointer contacts the higher piece
60
50
40
0
1/4 1/2 3/4
1
0
5
10
15
20
IN
MM
MM
15
1/2
MMIN
TWIMultipurposeWeldingTWIMultipurposeWelding
GaugeGauge
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
Undercut
The scale reads from 0 in the negative up
to 5m. The segment is rotated until the
pointer reaches the full depth of the
undercut.
60
50
40
0
1/4 1/2 3/4
1
0
5
10
15
20
IN
MM
MM
15
1/2
MMIN
TWIMultipurposeWeldingTWIMultipurposeWelding
GaugeGauge
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
60
50
40
0
1/4 1/2 3/4
1
0
5
10
15
20
IN
MM
MM
15
1/2
MMIN
Excess weld metal
The scale is used to read off these
dimensions up to a maximum of 25mm
and 1 inch
TWIMultipurposeWeldingTWIMultipurposeWelding
GaugeGauge
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
Fillet weld leg length
The scale is used to read off these
dimensions up to a maximum of
25mm and 1 inch.
60
50
40
0
1/4 1/2 3/4
1
0
5
10
15
20
IN
MM
MM
15
1/2
MM
IN
TWIMultipurposeWeldingTWIMultipurposeWelding
GaugeGauge
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
Fillet throat thickness
The sliding pointer reads up to 20mm and 3/4
inch. In measuring throat thickness it is
assumed that the fillet weld has normal root
penetration
60
50
40
0
1/41/23/4
1
0
5
10
15
20
IN
MM
MM
15
1/2
MM
IN
TWIMultipurposeWeldingTWIMultipurposeWelding
GaugeGauge
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
Leg Length Gauge
G.A.L.
S.T.D.
10mm
12m
m
16mm
3mm
6mm
9m
m5m
m
4mm
L
Throat Thickness Gauge
G.A.L.
S.T.D.
10mm
12m
m
16mm
3mm
6m
m
9m
m5m
m
4mm
T
FilletWeldGaugesFilletWeldGauges
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
HILOWeldingGaugeHILOWeldingGauge
HI-LOSinglePurposeWeldingGauge
1
2
3
4
5
6
Root gap
dimension
Internal
alignment
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
M.S.Rogers
PlatePipeInspectionPlatePipeInspection
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
PlateInspectionPracticePlateInspectionPractice
Remember in the CSWIP 3.1 Welding Inspectors
examination your are required to conduct a practical
examination of a plate test weld, complete a thumb print
sketch and a final report on your findings
 Time allowed 1 hour and 15 minutes
 The code is provided
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
1) Use a pencil for the arrow lines, but make all
written comments and measurements in ink only
3) Do not forget to compare and sentence your report
2) Report everything that you can observe
4) Do not forget to date & sign your report
5) Make any observations, such as recommendations
for further investigation for crack-like imperfections.
PlateInspectionPointsPlateInspectionPoints
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
After you have observed an imperfection and determined
its type, you must be able to take measurements and
complete the thumb print report sketch
The first thumb print report sketch should be in the form
of a repair map of the weld. (i.e. All observations are
Identified Sized and Located)
ThumbPrintReportSketchThumbPrintReportSketch
The thumb print report sketch used in CSWIP exam will
look like the following example.
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1PlateThumbPrintReportPlateThumbPrintReport
ExampleExampleName (Block capitals) Joe BLOGGS Signature Joe Bloggs Test piece identification Example
Code used PH6/WI/00 Welding process MMA (SMAW) Joint type Single V Butt
Welding position Flat 1G/PA Length & thickness L=300mm D = 12.5mm Date 16/07/02
10
30
Cap undercut D = 1.0
53
5
Poor stop/start
24
63
Porosity
Incomplete filled groove +
Lack of side wall fusion
42
130
Mechanical
damage
D = 2
32
140
23
Note: all dimensions in mm
# Excessive cap height full weld length H = 5mm max
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
After you have completed your thumb print report sketch of
your test plate the next step is to complete your final report
again the report must be completed in ink (no pencil).
The report must be completed to your thumb print sketch,
do not leave any boxes empty, every box must be
completed or dashed out. You must also make any
comments you feel are necessary regarding any defects
observed.
The report form used in CSWIP will look like the following
example.
FinalReportFinalReport
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
PlateFinalReportExamplePlateFinalReportExample
Defect Type
Reinforcement (Height)
Reinforcement (Appear)
Incomplete filling
Inadequate weld width
Slag Inclusions
Undercut
Surface Porosity
Cracks/Cracklike Defect
Lack of fusion
Arc Strike
Mechanical Damage
Laminations
Misalignment
Longitudinal Seams
Plate/Pipe
Section
Accumulative
Total
Maximum
Allowable
Section
No
Accept
Reject
Defects Noted Code or Specification Reference
EXTERNAL DEFECTS
A - C L = 300 H=2.5 max 2.0 mm 14 Reject
A - C L=300 Not smooth Smooth 14 Reject
A - B L=24 None 13 Reject
A - C AcceptNone
Accept
Reject
A - C
A - C
A - C
A - B
A - B
None
2L=24 D=1.5 sharp 10% t
AcceptNone
Reject6L=8mm None
AcceptNone
RejectA - B 42 Areas None
ReferA - B 152 Areas smooth Seek Advice
A - C
A - C
AcceptNone
A - C AcceptNone
AcceptNone Pipe only
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
This Pipe/plate has been examined to the requirements of [code/specification] ……………………
And is accepted/rejected accordingly.
ROOT DEFECTS
Misalignment
Excessive Penetration
Lack of Penetration
Lack of Root Fusion
Root Concavity
Root Undercut
Crack/Cracklike Defect
Slag Inclusions
Porosity
A - C AcceptNone
B - C L=24 D=2.5mm 2.0 mm 1 Reject
B - C L=10 25 mm 11 Accept
A - C AcceptNone
A - C AcceptNone
A - B AcceptL= 27 D=0.5 sharp
A - C AcceptNone
A - C AcceptNone
A - C AcceptNone
10% t 2
BW/VI/00
Signature …………………………………. Date ………………………..
MSRogers 14/9/02
Use the other side for comments
PlateFinalReportExamplePlateFinalReportExample
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
PipeInspectionPracticePipeInspectionPractice
Remember in the CSWIP 3.1 Welding Inspectors
examination your are required to conduct a practical
examination of a pipe test weld, complete a thumb print
sketch and a final report on your findings
 Time allowed 1 hour and 45 minutes
 The code is nominated e.g API 1104
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
Page 1 of 3 CSWIP VISUAL INSPECTION PIPE REPORT
Name [Block capitals]____________ Signature_________Pipe Ident#________
Code/Specification used_________W elding Process_______ Joint type______
W elding position__________ Outside  & Thickness_____ Date ________
A B C
C D A
Complete as per plate report form
PipeThumbPrintReportPipeThumbPrintReport
ExampleExample
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
PipeCode:API114PipeCode:API114
Reinforcement Height: 7.8.2 page 20
Reinforcement Appear: 7.8.2 page 20
Incomplete groove: 7.8.2 page 20
Inadequate weld width: 7.8.2 page 20
Slag inclusions: 9.3.8 page 22
Undercut: 9.3.11 page 22
Porosity: 9.3.9 page 24
Cracks: 9.3.10 page 24
Lack of fusion: 9.3.4 page 22
Arc strikes/arc burns: A.5.3 page 55
Mechanical damage: Not referenced
Lamination: Not referenced
Misalignment: Not referenced
Longitudinal seams:Not referenced
Excess penetration: Not referenced
Lack of penetration: 9.3.1/9.3.2 page 21
Lack of root fusion: 9.3.5 page 21
Concave root: 9.3.6 page 22
Burn through: 9.3.7 page 22
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
MacroInspectionMacroInspection
M.S.RogersSectionRef23Copyright © 2003 TWI Ltd
WI 3.1
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
Remember in the CSWIP 3.1 Welding Inspectors
examination your are required to conduct a visual
examination of two macro samples
 Time allowed 45 minutes
 Code ISO 5817 Level stringent B
MacroInspectionPracticeMacroInspectionPractice
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
PLEASE READ CAREFULLY
You have been provided with one or two macro samples and the report sheets you
are required to complete the following
1. Ensure that you record your name and the date on the report sheet
2. Ensure that you sign the report sheet
3. Visually inspect the specimens and report:
The defects type
The defects size, length, depth and height if applicable
4. Comment on each defect e.g accept, reject or refer in accordance with
ISO 5817 stringent B
ALL LINE DRAWING & WRITING MUST BE COMPLETED IN INK
ALL MEASUREMENT IN MM / PHOTOGRAPH AT 10X MAGNIFICATION.
DIVDE ALL MEASUREMENTS BY 10 AND RECORD ON REPORT PROVIDED
NO LIQUID PAPER OR CORRECTION FLUID PERMITTED. CORRECTIONS MUST BE CROSSED
OUT AND THE CORRECTION MADE
TIME ALLOWED FOR TWO MARCS 45 MINUTES
MarcoInspectionMarcoInspection
InstructionsInstructions
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1Page 6
ISO 5817 : 1992
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
Acceptance levels B,C,D
For the CSWIP 3.1 exam
stringent B
Maximum pore diameter 3mm or
pore diameter shall be less than or
equal to 0.3 X plate thickness
Page 7
ISO 5817 : 1992
M.S.RogersCopyright © 2003 TWI Ltd SectionRef23
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
Specimen Thickness(mm)
8 15 30 60Defect
Overlap
Incomplete penetration
Lack of sidewall fusion
Gas pore
Slag inclusion
Elongated cavity
Linear misalignment
Cap undercut
Crack
Spatter
Dimensions
H = 1.5
L = 2.0
L = 2.0
D = 2.5
1.0 x 2.0
0.5 x 1.5
H = 1.8
D = 0.4
L = 1.5
D = 1.8
R R R R
R R R R
R R R R
R A A A
A A A A
A A A A
R R A A
A A A A
R R R R
X X X X
 Using ISO 5817 determine the acceptability of the defects listed. Under the column
headed specimen thickness, insert A,R and X
A = Accept
R = Reject
X = Refer
 Use the acceptance category stringent B when making your assessment assume
specimens to be plate butt welds
ISO5817ExerciseISO5817Exercise
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
1
2
3
4
5
DEFECT SIZE ACCEPT/REJECT
1 Lack of sidewall fusion + Slag 3 x 4 mm Reject
Reject
Accept
Accept
2
3
4
5
6
7
8
10
11
12
Lack of sidewall fusion
Slag inclusion
Cap undercut
3 mm
1.5 mm
0.5 mm
Plate lamination 5.2 mm Refer*
Excess weld metal
Excess root penetration
4 mm
None Accept
Reject
CHECK PHOTOGRAPH IDENT MATCHES FORM SUPPLIED. ALL LINE
DRAWING & WRITTING MUST BE IN INK. ALL MEASUREMENTS IN MM /
PHOTOGRAPH AT X10 MAGNIFICATION
RECORD DEFECTS AS YOU SEE THEM
THESES MACROS HAVE BEEN MASTERED FROM
THE PHOTOGRAPHS
INTERPRETATION DIFFICULTIES HAVE BEEN
RECORDED.
COMMENT ONLY IF A DEFINITE UNCERTAINTY
EXISTS: i.e SLAG/GAS IN SOME CASES
COMMENTS: *Materials
defect acceptance
dependent on application.
Seek advice.
Name: Mark Rogers
Signature: M S Rogers
Date: 20/03/03
MarcoReportExampleMarcoReportExample
M.S.Rogers
TECHNOLOGY
SectionRef23Copyright © 2003 TWI Ltd
WI 3.1
AnyQuestionsAnyQuestions
M.S.RogersCopyright © 2003 TWI Ltd SectionRef23

Mais conteúdo relacionado

Mais procurados

American Welding Society (AWS) Certifications for WELDING INSPECTOR WELD...
American Welding Society (AWS) Certifications for WELDING INSPECTOR WELD...American Welding Society (AWS) Certifications for WELDING INSPECTOR WELD...
American Welding Society (AWS) Certifications for WELDING INSPECTOR WELD...thiru1mech
 
Asme sec ix overview
Asme sec ix overviewAsme sec ix overview
Asme sec ix overviewAshifuddinAli
 
Welding Inspection Cswip
Welding Inspection CswipWelding Inspection Cswip
Welding Inspection Cswipguest831c1e
 
How to write a Welding Procedure Specification (ISO 15614-1
How to write a Welding Procedure Specification (ISO 15614-1How to write a Welding Procedure Specification (ISO 15614-1
How to write a Welding Procedure Specification (ISO 15614-1Tiago Pereira
 
Wis5 welding symbols 05
Wis5 welding symbols 05Wis5 welding symbols 05
Wis5 welding symbols 05Thang Do Minh
 
Procedure qualification
Procedure qualificationProcedure qualification
Procedure qualificationvaasuBandaru
 
Presentation on wpqr wps asme_ix
Presentation on wpqr wps asme_ixPresentation on wpqr wps asme_ix
Presentation on wpqr wps asme_ixmayank0738
 
CSWIP_3_2_Senior_Welding_Inspector_WIS10.pdf
CSWIP_3_2_Senior_Welding_Inspector_WIS10.pdfCSWIP_3_2_Senior_Welding_Inspector_WIS10.pdf
CSWIP_3_2_Senior_Welding_Inspector_WIS10.pdfAhmadRizki84
 
04 wis5 symbol
04 wis5 symbol04 wis5 symbol
04 wis5 symbolTori Tom
 
Weld Defects
Weld DefectsWeld Defects
Weld Defectsadminn2
 
Welding visual inspection
Welding visual inspectionWelding visual inspection
Welding visual inspectionbusinespartner
 
TWI CSWIP 3.1 00 Introduction (1).ppt
TWI CSWIP 3.1 00 Introduction (1).pptTWI CSWIP 3.1 00 Introduction (1).ppt
TWI CSWIP 3.1 00 Introduction (1).pptAhmedAlgamodi
 
16 wis5 consumable
16 wis5 consumable16 wis5 consumable
16 wis5 consumableTori Tom
 
CSWIP 3.2 New BOOK.pdf
CSWIP 3.2  New BOOK.pdfCSWIP 3.2  New BOOK.pdf
CSWIP 3.2 New BOOK.pdfVENKATESAN S
 

Mais procurados (20)

American Welding Society (AWS) Certifications for WELDING INSPECTOR WELD...
American Welding Society (AWS) Certifications for WELDING INSPECTOR WELD...American Welding Society (AWS) Certifications for WELDING INSPECTOR WELD...
American Welding Society (AWS) Certifications for WELDING INSPECTOR WELD...
 
Asme sec ix overview
Asme sec ix overviewAsme sec ix overview
Asme sec ix overview
 
Welding Inspection
Welding InspectionWelding Inspection
Welding Inspection
 
Welding Inspection Cswip
Welding Inspection CswipWelding Inspection Cswip
Welding Inspection Cswip
 
How to write a Welding Procedure Specification (ISO 15614-1
How to write a Welding Procedure Specification (ISO 15614-1How to write a Welding Procedure Specification (ISO 15614-1
How to write a Welding Procedure Specification (ISO 15614-1
 
WPS & WPQ
WPS & WPQWPS & WPQ
WPS & WPQ
 
Wis5 welding symbols 05
Wis5 welding symbols 05Wis5 welding symbols 05
Wis5 welding symbols 05
 
How to Qualify a Welding Procedure
How to Qualify a Welding ProcedureHow to Qualify a Welding Procedure
How to Qualify a Welding Procedure
 
Procedure qualification
Procedure qualificationProcedure qualification
Procedure qualification
 
How to produce PQR
How to produce PQRHow to produce PQR
How to produce PQR
 
Presentation on wpqr wps asme_ix
Presentation on wpqr wps asme_ixPresentation on wpqr wps asme_ix
Presentation on wpqr wps asme_ix
 
CSWIP_3_2_Senior_Welding_Inspector_WIS10.pdf
CSWIP_3_2_Senior_Welding_Inspector_WIS10.pdfCSWIP_3_2_Senior_Welding_Inspector_WIS10.pdf
CSWIP_3_2_Senior_Welding_Inspector_WIS10.pdf
 
04 wis5 symbol
04 wis5 symbol04 wis5 symbol
04 wis5 symbol
 
Weld Defects
Weld DefectsWeld Defects
Weld Defects
 
Welding visual inspection
Welding visual inspectionWelding visual inspection
Welding visual inspection
 
TWI CSWIP 3.1 00 Introduction (1).ppt
TWI CSWIP 3.1 00 Introduction (1).pptTWI CSWIP 3.1 00 Introduction (1).ppt
TWI CSWIP 3.1 00 Introduction (1).ppt
 
16 wis5 consumable
16 wis5 consumable16 wis5 consumable
16 wis5 consumable
 
cswip-3-1-new-book
 cswip-3-1-new-book cswip-3-1-new-book
cswip-3-1-new-book
 
CSWIP 3.2 New BOOK.pdf
CSWIP 3.2  New BOOK.pdfCSWIP 3.2  New BOOK.pdf
CSWIP 3.2 New BOOK.pdf
 
Qc piping guide
Qc piping guideQc piping guide
Qc piping guide
 

Destaque

Using pro weld in creo 2.0
Using pro weld in creo 2.0Using pro weld in creo 2.0
Using pro weld in creo 2.0Evan Winter
 
Arc Welding Processes 2 1
Arc Welding Processes 2 1Arc Welding Processes 2 1
Arc Welding Processes 2 1guest5be29
 
API COURSES 510 570-653
API COURSES 510 570-653 API COURSES 510 570-653
API COURSES 510 570-653 Sujin J
 
Api653 qualificationfor certification-2_2012
Api653 qualificationfor certification-2_2012Api653 qualificationfor certification-2_2012
Api653 qualificationfor certification-2_2012Tariq Mahmood
 
2016 : American Petroleum Institute (API) 653 Aboveground Storage Tanks Inspe...
2016 : American Petroleum Institute (API) 653 Aboveground Storage Tanks Inspe...2016 : American Petroleum Institute (API) 653 Aboveground Storage Tanks Inspe...
2016 : American Petroleum Institute (API) 653 Aboveground Storage Tanks Inspe...Ir. Syed Fadzil Syed Mohamed, P.Eng, CEng
 
Implementing TWI into Daily Work
Implementing TWI into Daily WorkImplementing TWI into Daily Work
Implementing TWI into Daily WorkBusiness901
 
Tasha ramisetti new resume 2015
Tasha ramisetti new resume 2015Tasha ramisetti new resume 2015
Tasha ramisetti new resume 2015Tasha Ramisetti
 
39. api 653 section 1 - 4 terms
39. api 653   section 1 - 4 terms39. api 653   section 1 - 4 terms
39. api 653 section 1 - 4 termsShahid Karim
 
Wis5 weldability n.ppt 1 11
Wis5 weldability n.ppt 1 11Wis5 weldability n.ppt 1 11
Wis5 weldability n.ppt 1 11Thang Do Minh
 
Overview of Training Within Industry (TWI) by Operational Excellence Consulting
Overview of Training Within Industry (TWI) by Operational Excellence ConsultingOverview of Training Within Industry (TWI) by Operational Excellence Consulting
Overview of Training Within Industry (TWI) by Operational Excellence ConsultingOperational Excellence Consulting
 
Cv of qaqc, inspection engineer, welding, painting & coating inspector. s.san...
Cv of qaqc, inspection engineer, welding, painting & coating inspector. s.san...Cv of qaqc, inspection engineer, welding, painting & coating inspector. s.san...
Cv of qaqc, inspection engineer, welding, painting & coating inspector. s.san...Sangilimuthu Samiayyah
 
PPT ON TYPES OF WELDING JOINTS
PPT ON TYPES OF WELDING JOINTSPPT ON TYPES OF WELDING JOINTS
PPT ON TYPES OF WELDING JOINTSHimanshu Yadav
 
Api 650 & 653 questions closed book with answers
Api 650 & 653 questions closed book with answersApi 650 & 653 questions closed book with answers
Api 650 & 653 questions closed book with answersJasminder singh
 
Cswip 3.1 question & Answers
Cswip 3.1 question & AnswersCswip 3.1 question & Answers
Cswip 3.1 question & AnswersRavi Shankar
 
Cswip welding inspection notes and questions
Cswip welding inspection notes and questionsCswip welding inspection notes and questions
Cswip welding inspection notes and questionsKarthik Banari
 

Destaque (20)

Welding symbols
Welding symbolsWelding symbols
Welding symbols
 
Using pro weld in creo 2.0
Using pro weld in creo 2.0Using pro weld in creo 2.0
Using pro weld in creo 2.0
 
Arc Welding Processes 2 1
Arc Welding Processes 2 1Arc Welding Processes 2 1
Arc Welding Processes 2 1
 
Welding basics1
Welding basics1Welding basics1
Welding basics1
 
API COURSES 510 570-653
API COURSES 510 570-653 API COURSES 510 570-653
API COURSES 510 570-653
 
Api653 qualificationfor certification-2_2012
Api653 qualificationfor certification-2_2012Api653 qualificationfor certification-2_2012
Api653 qualificationfor certification-2_2012
 
2016 : American Petroleum Institute (API) 653 Aboveground Storage Tanks Inspe...
2016 : American Petroleum Institute (API) 653 Aboveground Storage Tanks Inspe...2016 : American Petroleum Institute (API) 653 Aboveground Storage Tanks Inspe...
2016 : American Petroleum Institute (API) 653 Aboveground Storage Tanks Inspe...
 
CV_Thangaraj Raja
CV_Thangaraj RajaCV_Thangaraj Raja
CV_Thangaraj Raja
 
Implementing TWI into Daily Work
Implementing TWI into Daily WorkImplementing TWI into Daily Work
Implementing TWI into Daily Work
 
Tasha ramisetti new resume 2015
Tasha ramisetti new resume 2015Tasha ramisetti new resume 2015
Tasha ramisetti new resume 2015
 
39. api 653 section 1 - 4 terms
39. api 653   section 1 - 4 terms39. api 653   section 1 - 4 terms
39. api 653 section 1 - 4 terms
 
Api 653-curso
Api 653-cursoApi 653-curso
Api 653-curso
 
Wis5 weldability n.ppt 1 11
Wis5 weldability n.ppt 1 11Wis5 weldability n.ppt 1 11
Wis5 weldability n.ppt 1 11
 
Overview of Training Within Industry (TWI) by Operational Excellence Consulting
Overview of Training Within Industry (TWI) by Operational Excellence ConsultingOverview of Training Within Industry (TWI) by Operational Excellence Consulting
Overview of Training Within Industry (TWI) by Operational Excellence Consulting
 
Cv of qaqc, inspection engineer, welding, painting & coating inspector. s.san...
Cv of qaqc, inspection engineer, welding, painting & coating inspector. s.san...Cv of qaqc, inspection engineer, welding, painting & coating inspector. s.san...
Cv of qaqc, inspection engineer, welding, painting & coating inspector. s.san...
 
Welding Symbols
Welding SymbolsWelding Symbols
Welding Symbols
 
PPT ON TYPES OF WELDING JOINTS
PPT ON TYPES OF WELDING JOINTSPPT ON TYPES OF WELDING JOINTS
PPT ON TYPES OF WELDING JOINTS
 
Api 650 & 653 questions closed book with answers
Api 650 & 653 questions closed book with answersApi 650 & 653 questions closed book with answers
Api 650 & 653 questions closed book with answers
 
Cswip 3.1 question & Answers
Cswip 3.1 question & AnswersCswip 3.1 question & Answers
Cswip 3.1 question & Answers
 
Cswip welding inspection notes and questions
Cswip welding inspection notes and questionsCswip welding inspection notes and questions
Cswip welding inspection notes and questions
 

Semelhante a Twi welding training_6

23-WIS5 Visual Inspections 2006 Addition
23-WIS5 Visual Inspections 2006 Addition23-WIS5 Visual Inspections 2006 Addition
23-WIS5 Visual Inspections 2006 AdditionKamal Ahmed
 
Weld Improvement Example in Offshore Oil & Gas
Weld Improvement Example in Offshore Oil & GasWeld Improvement Example in Offshore Oil & Gas
Weld Improvement Example in Offshore Oil & GasImran Choudury
 
Road safety-barrier-systems-appendix-a
Road safety-barrier-systems-appendix-aRoad safety-barrier-systems-appendix-a
Road safety-barrier-systems-appendix-aIsti Kharoh
 
IRJET - Mathematical Modelling to Predict Bead Geometry and Shape Relationshi...
IRJET - Mathematical Modelling to Predict Bead Geometry and Shape Relationshi...IRJET - Mathematical Modelling to Predict Bead Geometry and Shape Relationshi...
IRJET - Mathematical Modelling to Predict Bead Geometry and Shape Relationshi...IRJET Journal
 
criteria of weld defects
criteria of weld defects criteria of weld defects
criteria of weld defects Saqib Rasool
 
DESIGN AND ANALYSIS OF MULTIFACE HYDRAULIC BENDING MACHINE DIE
DESIGN AND ANALYSIS OF MULTIFACE HYDRAULIC BENDING MACHINE DIEDESIGN AND ANALYSIS OF MULTIFACE HYDRAULIC BENDING MACHINE DIE
DESIGN AND ANALYSIS OF MULTIFACE HYDRAULIC BENDING MACHINE DIEIRJET Journal
 
IRJET- A Review Paper on the Production Line of an Aluminum Alloy Wheel Manuf...
IRJET- A Review Paper on the Production Line of an Aluminum Alloy Wheel Manuf...IRJET- A Review Paper on the Production Line of an Aluminum Alloy Wheel Manuf...
IRJET- A Review Paper on the Production Line of an Aluminum Alloy Wheel Manuf...IRJET Journal
 
Optimization of tube-flange welded joints under Torsional loading
Optimization of tube-flange welded joints under Torsional loadingOptimization of tube-flange welded joints under Torsional loading
Optimization of tube-flange welded joints under Torsional loadingIRJET Journal
 
THESIS - Spot Weld Tip Dressing, Presentation
THESIS - Spot Weld Tip Dressing, PresentationTHESIS - Spot Weld Tip Dressing, Presentation
THESIS - Spot Weld Tip Dressing, PresentationDavid Palmer, EIT
 
IRJET- Analysis of Hard Chrome Plating Process to Reduce Rejections using PDC...
IRJET- Analysis of Hard Chrome Plating Process to Reduce Rejections using PDC...IRJET- Analysis of Hard Chrome Plating Process to Reduce Rejections using PDC...
IRJET- Analysis of Hard Chrome Plating Process to Reduce Rejections using PDC...IRJET Journal
 
Various approaches to Eliminate MIG Welding and Defects occurring in DT cap F...
Various approaches to Eliminate MIG Welding and Defects occurring in DT cap F...Various approaches to Eliminate MIG Welding and Defects occurring in DT cap F...
Various approaches to Eliminate MIG Welding and Defects occurring in DT cap F...IRJET Journal
 
Manufacturing of welded joints with realistic defects
Manufacturing of welded joints with realistic defectsManufacturing of welded joints with realistic defects
Manufacturing of welded joints with realistic defectsITMA Materials Technology
 
IRJET- Development of Mathematical Models to Predict Weld Bead Geometry of Bu...
IRJET- Development of Mathematical Models to Predict Weld Bead Geometry of Bu...IRJET- Development of Mathematical Models to Predict Weld Bead Geometry of Bu...
IRJET- Development of Mathematical Models to Predict Weld Bead Geometry of Bu...IRJET Journal
 
181015 muna-fichas nebulizada-email
181015 muna-fichas nebulizada-email181015 muna-fichas nebulizada-email
181015 muna-fichas nebulizada-emaildaniel sandoval
 
Piping inspector questions 1
Piping inspector questions  1 Piping inspector questions  1
Piping inspector questions 1 MOHAMMAD ATIF ALI
 
Kammer Severe Service Valves For Industry
Kammer Severe Service Valves For IndustryKammer Severe Service Valves For Industry
Kammer Severe Service Valves For IndustryCTi Controltech
 
Review on Effect of Process Parameters - Friction Stir Welding Process
Review on Effect of Process Parameters - Friction Stir Welding ProcessReview on Effect of Process Parameters - Friction Stir Welding Process
Review on Effect of Process Parameters - Friction Stir Welding ProcessIRJET Journal
 
THE EFFECT OF OPENINGS IN THE SLAB STIFFENED WITH SHALLOW BEAMS
THE EFFECT OF OPENINGS IN THE SLAB STIFFENED WITH SHALLOW BEAMSTHE EFFECT OF OPENINGS IN THE SLAB STIFFENED WITH SHALLOW BEAMS
THE EFFECT OF OPENINGS IN THE SLAB STIFFENED WITH SHALLOW BEAMSIRJET Journal
 

Semelhante a Twi welding training_6 (20)

23-WIS5 Visual Inspections 2006 Addition
23-WIS5 Visual Inspections 2006 Addition23-WIS5 Visual Inspections 2006 Addition
23-WIS5 Visual Inspections 2006 Addition
 
Weld Improvement Example in Offshore Oil & Gas
Weld Improvement Example in Offshore Oil & GasWeld Improvement Example in Offshore Oil & Gas
Weld Improvement Example in Offshore Oil & Gas
 
Road safety-barrier-systems-appendix-a
Road safety-barrier-systems-appendix-aRoad safety-barrier-systems-appendix-a
Road safety-barrier-systems-appendix-a
 
IRJET - Mathematical Modelling to Predict Bead Geometry and Shape Relationshi...
IRJET - Mathematical Modelling to Predict Bead Geometry and Shape Relationshi...IRJET - Mathematical Modelling to Predict Bead Geometry and Shape Relationshi...
IRJET - Mathematical Modelling to Predict Bead Geometry and Shape Relationshi...
 
criteria of weld defects
criteria of weld defects criteria of weld defects
criteria of weld defects
 
DESIGN AND ANALYSIS OF MULTIFACE HYDRAULIC BENDING MACHINE DIE
DESIGN AND ANALYSIS OF MULTIFACE HYDRAULIC BENDING MACHINE DIEDESIGN AND ANALYSIS OF MULTIFACE HYDRAULIC BENDING MACHINE DIE
DESIGN AND ANALYSIS OF MULTIFACE HYDRAULIC BENDING MACHINE DIE
 
IRJET- A Review Paper on the Production Line of an Aluminum Alloy Wheel Manuf...
IRJET- A Review Paper on the Production Line of an Aluminum Alloy Wheel Manuf...IRJET- A Review Paper on the Production Line of an Aluminum Alloy Wheel Manuf...
IRJET- A Review Paper on the Production Line of an Aluminum Alloy Wheel Manuf...
 
Optimization of tube-flange welded joints under Torsional loading
Optimization of tube-flange welded joints under Torsional loadingOptimization of tube-flange welded joints under Torsional loading
Optimization of tube-flange welded joints under Torsional loading
 
THESIS - Spot Weld Tip Dressing, Presentation
THESIS - Spot Weld Tip Dressing, PresentationTHESIS - Spot Weld Tip Dressing, Presentation
THESIS - Spot Weld Tip Dressing, Presentation
 
IRJET- Analysis of Hard Chrome Plating Process to Reduce Rejections using PDC...
IRJET- Analysis of Hard Chrome Plating Process to Reduce Rejections using PDC...IRJET- Analysis of Hard Chrome Plating Process to Reduce Rejections using PDC...
IRJET- Analysis of Hard Chrome Plating Process to Reduce Rejections using PDC...
 
Various approaches to Eliminate MIG Welding and Defects occurring in DT cap F...
Various approaches to Eliminate MIG Welding and Defects occurring in DT cap F...Various approaches to Eliminate MIG Welding and Defects occurring in DT cap F...
Various approaches to Eliminate MIG Welding and Defects occurring in DT cap F...
 
Manufacturing of welded joints with realistic defects
Manufacturing of welded joints with realistic defectsManufacturing of welded joints with realistic defects
Manufacturing of welded joints with realistic defects
 
IRJET- Development of Mathematical Models to Predict Weld Bead Geometry of Bu...
IRJET- Development of Mathematical Models to Predict Weld Bead Geometry of Bu...IRJET- Development of Mathematical Models to Predict Weld Bead Geometry of Bu...
IRJET- Development of Mathematical Models to Predict Weld Bead Geometry of Bu...
 
181015 muna-fichas nebulizada-email
181015 muna-fichas nebulizada-email181015 muna-fichas nebulizada-email
181015 muna-fichas nebulizada-email
 
Piping inspector questions 1
Piping inspector questions  1 Piping inspector questions  1
Piping inspector questions 1
 
Chap-23-2.pdf
Chap-23-2.pdfChap-23-2.pdf
Chap-23-2.pdf
 
Kammer Severe Service Valves For Industry
Kammer Severe Service Valves For IndustryKammer Severe Service Valves For Industry
Kammer Severe Service Valves For Industry
 
Review on Effect of Process Parameters - Friction Stir Welding Process
Review on Effect of Process Parameters - Friction Stir Welding ProcessReview on Effect of Process Parameters - Friction Stir Welding Process
Review on Effect of Process Parameters - Friction Stir Welding Process
 
Production Engg. Theory
Production Engg. TheoryProduction Engg. Theory
Production Engg. Theory
 
THE EFFECT OF OPENINGS IN THE SLAB STIFFENED WITH SHALLOW BEAMS
THE EFFECT OF OPENINGS IN THE SLAB STIFFENED WITH SHALLOW BEAMSTHE EFFECT OF OPENINGS IN THE SLAB STIFFENED WITH SHALLOW BEAMS
THE EFFECT OF OPENINGS IN THE SLAB STIFFENED WITH SHALLOW BEAMS
 

Último

Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01KreezheaRecto
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Christo Ananth
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 

Último (20)

Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 

Twi welding training_6

  • 1. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 Welding Inspection Welding Inspection Practical Course Reference WIS 5
  • 2. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 The purpose of this session is to practice the reporting format required by CSWIP in the practical plate examination part of the CSWIP 3.1 Welding Inspectors exam Remember the responsibilities of a Welding Inspector are:  Observe  Report  Compare PlateInspectionPracticePlateInspectionPractice
  • 3. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 To observe welding imperfections you are required to have good close vision acuity A close vision acuity test will be given to you before your exam to establish if your vision meets the minimum standard required Its not just the project that must meet the standard!! You will also require a thorough knowledge of welding imperfections and their likely location, causes and implications ObserveObserve
  • 4. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1  TWI Multi-function weld gauge for measuring many different weld measurements.  Fillet weld gauges for measuring leg lengths and throat thickness.  Hi-Lo gauge for measuring misalignment and root gaps  Angle gauges for measuring weld preparation angles A number of specialist welding gauges are available to measure the various elements that need to be measured in a welded fabrication including SpecialistWeldingGaugesSpecialistWeldingGauges
  • 5. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 TWIMultipurposeWeldingTWIMultipurposeWelding GaugeGauge 60 50 40 0 1/4 1/2 3/4 1 0 5 10 15 20 IN MM 15 1/2 IN MM Angle of preparation The scale reads from 0o to 60o in steps of 5o. The angle is read against the chamfered edge of the segment
  • 6. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 Misalignment The scale is used to measure misalignment of components by placing the edge of the gauge on the lower one and rotating the segment until the pointer contacts the higher piece 60 50 40 0 1/4 1/2 3/4 1 0 5 10 15 20 IN MM MM 15 1/2 MMIN TWIMultipurposeWeldingTWIMultipurposeWelding GaugeGauge
  • 7. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 Undercut The scale reads from 0 in the negative up to 5m. The segment is rotated until the pointer reaches the full depth of the undercut. 60 50 40 0 1/4 1/2 3/4 1 0 5 10 15 20 IN MM MM 15 1/2 MMIN TWIMultipurposeWeldingTWIMultipurposeWelding GaugeGauge
  • 8. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 60 50 40 0 1/4 1/2 3/4 1 0 5 10 15 20 IN MM MM 15 1/2 MMIN Excess weld metal The scale is used to read off these dimensions up to a maximum of 25mm and 1 inch TWIMultipurposeWeldingTWIMultipurposeWelding GaugeGauge
  • 9. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 Fillet weld leg length The scale is used to read off these dimensions up to a maximum of 25mm and 1 inch. 60 50 40 0 1/4 1/2 3/4 1 0 5 10 15 20 IN MM MM 15 1/2 MM IN TWIMultipurposeWeldingTWIMultipurposeWelding GaugeGauge
  • 10. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 Fillet throat thickness The sliding pointer reads up to 20mm and 3/4 inch. In measuring throat thickness it is assumed that the fillet weld has normal root penetration 60 50 40 0 1/41/23/4 1 0 5 10 15 20 IN MM MM 15 1/2 MM IN TWIMultipurposeWeldingTWIMultipurposeWelding GaugeGauge
  • 11. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 Leg Length Gauge G.A.L. S.T.D. 10mm 12m m 16mm 3mm 6mm 9m m5m m 4mm L Throat Thickness Gauge G.A.L. S.T.D. 10mm 12m m 16mm 3mm 6m m 9m m5m m 4mm T FilletWeldGaugesFilletWeldGauges
  • 12. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 HILOWeldingGaugeHILOWeldingGauge HI-LOSinglePurposeWeldingGauge 1 2 3 4 5 6 Root gap dimension Internal alignment
  • 13. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 M.S.Rogers PlatePipeInspectionPlatePipeInspection SectionRef23Copyright © 2003 TWI Ltd WI 3.1
  • 14. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 PlateInspectionPracticePlateInspectionPractice Remember in the CSWIP 3.1 Welding Inspectors examination your are required to conduct a practical examination of a plate test weld, complete a thumb print sketch and a final report on your findings  Time allowed 1 hour and 15 minutes  The code is provided
  • 15. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 1) Use a pencil for the arrow lines, but make all written comments and measurements in ink only 3) Do not forget to compare and sentence your report 2) Report everything that you can observe 4) Do not forget to date & sign your report 5) Make any observations, such as recommendations for further investigation for crack-like imperfections. PlateInspectionPointsPlateInspectionPoints
  • 16. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 After you have observed an imperfection and determined its type, you must be able to take measurements and complete the thumb print report sketch The first thumb print report sketch should be in the form of a repair map of the weld. (i.e. All observations are Identified Sized and Located) ThumbPrintReportSketchThumbPrintReportSketch The thumb print report sketch used in CSWIP exam will look like the following example.
  • 17. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1PlateThumbPrintReportPlateThumbPrintReport ExampleExampleName (Block capitals) Joe BLOGGS Signature Joe Bloggs Test piece identification Example Code used PH6/WI/00 Welding process MMA (SMAW) Joint type Single V Butt Welding position Flat 1G/PA Length & thickness L=300mm D = 12.5mm Date 16/07/02 10 30 Cap undercut D = 1.0 53 5 Poor stop/start 24 63 Porosity Incomplete filled groove + Lack of side wall fusion 42 130 Mechanical damage D = 2 32 140 23 Note: all dimensions in mm # Excessive cap height full weld length H = 5mm max
  • 18. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 After you have completed your thumb print report sketch of your test plate the next step is to complete your final report again the report must be completed in ink (no pencil). The report must be completed to your thumb print sketch, do not leave any boxes empty, every box must be completed or dashed out. You must also make any comments you feel are necessary regarding any defects observed. The report form used in CSWIP will look like the following example. FinalReportFinalReport
  • 19. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 PlateFinalReportExamplePlateFinalReportExample Defect Type Reinforcement (Height) Reinforcement (Appear) Incomplete filling Inadequate weld width Slag Inclusions Undercut Surface Porosity Cracks/Cracklike Defect Lack of fusion Arc Strike Mechanical Damage Laminations Misalignment Longitudinal Seams Plate/Pipe Section Accumulative Total Maximum Allowable Section No Accept Reject Defects Noted Code or Specification Reference EXTERNAL DEFECTS A - C L = 300 H=2.5 max 2.0 mm 14 Reject A - C L=300 Not smooth Smooth 14 Reject A - B L=24 None 13 Reject A - C AcceptNone Accept Reject A - C A - C A - C A - B A - B None 2L=24 D=1.5 sharp 10% t AcceptNone Reject6L=8mm None AcceptNone RejectA - B 42 Areas None ReferA - B 152 Areas smooth Seek Advice A - C A - C AcceptNone A - C AcceptNone AcceptNone Pipe only
  • 20. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 This Pipe/plate has been examined to the requirements of [code/specification] …………………… And is accepted/rejected accordingly. ROOT DEFECTS Misalignment Excessive Penetration Lack of Penetration Lack of Root Fusion Root Concavity Root Undercut Crack/Cracklike Defect Slag Inclusions Porosity A - C AcceptNone B - C L=24 D=2.5mm 2.0 mm 1 Reject B - C L=10 25 mm 11 Accept A - C AcceptNone A - C AcceptNone A - B AcceptL= 27 D=0.5 sharp A - C AcceptNone A - C AcceptNone A - C AcceptNone 10% t 2 BW/VI/00 Signature …………………………………. Date ……………………….. MSRogers 14/9/02 Use the other side for comments PlateFinalReportExamplePlateFinalReportExample
  • 21. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 PipeInspectionPracticePipeInspectionPractice Remember in the CSWIP 3.1 Welding Inspectors examination your are required to conduct a practical examination of a pipe test weld, complete a thumb print sketch and a final report on your findings  Time allowed 1 hour and 45 minutes  The code is nominated e.g API 1104
  • 22. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 Page 1 of 3 CSWIP VISUAL INSPECTION PIPE REPORT Name [Block capitals]____________ Signature_________Pipe Ident#________ Code/Specification used_________W elding Process_______ Joint type______ W elding position__________ Outside  & Thickness_____ Date ________ A B C C D A Complete as per plate report form PipeThumbPrintReportPipeThumbPrintReport ExampleExample
  • 23. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 PipeCode:API114PipeCode:API114 Reinforcement Height: 7.8.2 page 20 Reinforcement Appear: 7.8.2 page 20 Incomplete groove: 7.8.2 page 20 Inadequate weld width: 7.8.2 page 20 Slag inclusions: 9.3.8 page 22 Undercut: 9.3.11 page 22 Porosity: 9.3.9 page 24 Cracks: 9.3.10 page 24 Lack of fusion: 9.3.4 page 22 Arc strikes/arc burns: A.5.3 page 55 Mechanical damage: Not referenced Lamination: Not referenced Misalignment: Not referenced Longitudinal seams:Not referenced Excess penetration: Not referenced Lack of penetration: 9.3.1/9.3.2 page 21 Lack of root fusion: 9.3.5 page 21 Concave root: 9.3.6 page 22 Burn through: 9.3.7 page 22
  • 24. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 MacroInspectionMacroInspection M.S.RogersSectionRef23Copyright © 2003 TWI Ltd WI 3.1
  • 25. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 Remember in the CSWIP 3.1 Welding Inspectors examination your are required to conduct a visual examination of two macro samples  Time allowed 45 minutes  Code ISO 5817 Level stringent B MacroInspectionPracticeMacroInspectionPractice
  • 26. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 PLEASE READ CAREFULLY You have been provided with one or two macro samples and the report sheets you are required to complete the following 1. Ensure that you record your name and the date on the report sheet 2. Ensure that you sign the report sheet 3. Visually inspect the specimens and report: The defects type The defects size, length, depth and height if applicable 4. Comment on each defect e.g accept, reject or refer in accordance with ISO 5817 stringent B ALL LINE DRAWING & WRITING MUST BE COMPLETED IN INK ALL MEASUREMENT IN MM / PHOTOGRAPH AT 10X MAGNIFICATION. DIVDE ALL MEASUREMENTS BY 10 AND RECORD ON REPORT PROVIDED NO LIQUID PAPER OR CORRECTION FLUID PERMITTED. CORRECTIONS MUST BE CROSSED OUT AND THE CORRECTION MADE TIME ALLOWED FOR TWO MARCS 45 MINUTES MarcoInspectionMarcoInspection InstructionsInstructions
  • 27. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1Page 6 ISO 5817 : 1992
  • 28. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 Acceptance levels B,C,D For the CSWIP 3.1 exam stringent B Maximum pore diameter 3mm or pore diameter shall be less than or equal to 0.3 X plate thickness Page 7 ISO 5817 : 1992 M.S.RogersCopyright © 2003 TWI Ltd SectionRef23
  • 29. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 Specimen Thickness(mm) 8 15 30 60Defect Overlap Incomplete penetration Lack of sidewall fusion Gas pore Slag inclusion Elongated cavity Linear misalignment Cap undercut Crack Spatter Dimensions H = 1.5 L = 2.0 L = 2.0 D = 2.5 1.0 x 2.0 0.5 x 1.5 H = 1.8 D = 0.4 L = 1.5 D = 1.8 R R R R R R R R R R R R R A A A A A A A A A A A R R A A A A A A R R R R X X X X  Using ISO 5817 determine the acceptability of the defects listed. Under the column headed specimen thickness, insert A,R and X A = Accept R = Reject X = Refer  Use the acceptance category stringent B when making your assessment assume specimens to be plate butt welds ISO5817ExerciseISO5817Exercise
  • 30. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 1 2 3 4 5 DEFECT SIZE ACCEPT/REJECT 1 Lack of sidewall fusion + Slag 3 x 4 mm Reject Reject Accept Accept 2 3 4 5 6 7 8 10 11 12 Lack of sidewall fusion Slag inclusion Cap undercut 3 mm 1.5 mm 0.5 mm Plate lamination 5.2 mm Refer* Excess weld metal Excess root penetration 4 mm None Accept Reject CHECK PHOTOGRAPH IDENT MATCHES FORM SUPPLIED. ALL LINE DRAWING & WRITTING MUST BE IN INK. ALL MEASUREMENTS IN MM / PHOTOGRAPH AT X10 MAGNIFICATION RECORD DEFECTS AS YOU SEE THEM THESES MACROS HAVE BEEN MASTERED FROM THE PHOTOGRAPHS INTERPRETATION DIFFICULTIES HAVE BEEN RECORDED. COMMENT ONLY IF A DEFINITE UNCERTAINTY EXISTS: i.e SLAG/GAS IN SOME CASES COMMENTS: *Materials defect acceptance dependent on application. Seek advice. Name: Mark Rogers Signature: M S Rogers Date: 20/03/03 MarcoReportExampleMarcoReportExample
  • 31. M.S.Rogers TECHNOLOGY SectionRef23Copyright © 2003 TWI Ltd WI 3.1 AnyQuestionsAnyQuestions M.S.RogersCopyright © 2003 TWI Ltd SectionRef23