Highway drainage

Aglaia Connect
Aglaia ConnectEngineer em home
HIGHWAY DRAINAGE
Presented by
Aglaia
Highway drainage is a process of removing
and controlling excess surface and sub-soil
water within the right of way.
It includes interception and diversion of
water from the road surface and subgrade.
Excessmoisture in soil subgrade causesconsiderable
lowering of its stability.
Increasein moisture causereduction in strength of
many pavement materials like stabilized soil and
water bound macadam.
Sustained contact of water with bituminous pavements
causesfailure due to stripping of bitumen from
aggregates like loosening or detachment of some of the
bituminous pavement layers and formations of pot
holes
Excesswater on shoulders and pavement edges causes
considerable damage.
Highway drainage
In clayey soil variation in moisture content causes
considerable variation in volume of sub grade.
High moisture content causesincreases in weight and
thus increasein stress and simultaneous reduction in
strength of soil mass.
Erosion of soil from top of unsurfaced roads and slopes
of embankment,
cut and hill side is also due to surface water.
In cold regions presence of water in the subgrade and a
continuous supply of water from the ground water can
causeconsiderable damage to the pavement due to
frost action.
The surface water from the carriageway and shoulder
should effectively be drained off without allowing it
to percolate to sub grade.
Surface water from adjoining land should be
prevented form entering the roadway.
Side drain should have sufficient capacity and
longitudinal slope to carry away all surface water
collected.
Flow of surface water acrossthe road and shoulders
and along slopes should not causeformation of cross
ruts or erosion.
Highway drainage
Seepageand other sources of under ground water
should be drained off by the subsurfacedrainage
system.
Highest level of ground water table should be
kept well below the level of subgrade,
preferably by atleast 1.2m.
In waterlogged areasspecial precautions should
be taken
During rains,
• part of the rain water flows on surface
• part of it percolate through the soil mass as
gravitational water until it reaches the
ground water below the water table.
Removal and diversion of surface water from the
road way and adjoining land is termedassurface
drainage.
Diversion and removal of excess of soil water from
the subgrade is termed asSurfaceDrainage.
Methods of surface drainage
1.By Longitudinal sidedrains.
2.CatchbasinsandInlets in urbanareas
3.Providing damp proofcourse
4. Providing propercamber
5.Providing sufficient slope to the sides
6. Keepingthe level of carriage way at least 60 cm above the HFL.
A)Sidedrainsfor roadin embankment
-
It is necessaryto provide side drain on one side or
both sides, when road is constructed in
embankment.
Side drains should be at least 2.0 m away from
bottom edge of an embankment.
Depth of side drains is kept 1.0 to 1.5m to
prevent the entry of drain water intothe
embankment.
B)Sidedrainsfor roadin cutting
Highway drainage
A) Catch basins
Catchbasin is astructure like chamber
constructed on asewer line.
Water from pavement surface is collected in catch
basin and discharged to thesewer line.
The catch basin (catch pit) is provided with
grating to prevent the entry of rubbish into the
drainage system.
Highway drainage
Inlets is aconcrete box with grating either at the top or in the
side.
For aquick drainageit isnecessaryto ensure that shoulder
surface is properly slopedand free from irregularities and
depressions.
In impervious type, it is practiced to extend the subbasecourse
with drainageacrossthe shoulderupto side drain.
Alternatively we canprovide cont layer of 75-100mm thick laid
under the shoulder at the bottom layer of sub baseabout 150
mm thick extended upto theedge.
The pavedshouldershould be at least 0.5%steeper then
camber subjectedto min of 3%
The unpaved shoulder should be further 0.5%
steeper along the horizontal curve,Shoulder on
inner side of the curve should have slope steeper
than that of pavement.
On the outer side, the shoulder should be made
to drain away from the pavement, alow rate of
super elevation are provided.
On the other hand, where higher rate of super
elevation, the outside shoulder are kept level or
rounded.
Highway drainage
Highway drainage
Highway drainage
Except for amedian less than 5m wide, it is not
desirable to drain the median areatowards the
pavement surface.
 1.2 - 1.8 m wide median –Provided with kerbs
and always paved.
 1.8 - 5 m wide median – Usually turfed and
crowned so that surface water could run
towards the pavement maybe with or without
kerbs.
If carriage way slopes towards the median, central
drain maybe made to carry the runoff and slope
shouldnot be steeper than 6:1.
When the median hasonly earthen surface, it
should not be crowned because it can result in
soil particles being carried to the pavement
surface making itslippery.
Highway drainage
Removal or Diversion of excess soil-water from
sub-grade is termed as sub-surface drainage.
The changein moisture of sub-grade are causedby
the following
 Fluctuations in GroundWaterTable
 SeepageFlow
 Percolation Of RainWater
 Movement of CapillaryWater
In sub-surface drainage it is practiced to keep the
variation of moisture in sub-grade to a minimum.
Lowering of Water
Table
Controlling Seepage
Flow
Controlling Capillary
Water
In order to that the sub-grade and pavement are
not subjected to excessivemoisture the water
table shouldkept at least 1.0to 1.2m below the
sub-grade.
In places where water table is high to take the
road formation on embankment of height not
less than 1.0-1.2mis the best approach.
ButWhen the formation level is at or below the
general ground level it is necessaryto lower the water
table.
(a) If soil is relatively permeable, it may be possible
to lowerWTby constructing longitudinal drainage
trenches with drain pipe and filter sand and top of
trenches is covered with clay seal
The depth of trench depend on:
(i) The required lowering of water table
(ii) distanceb/w the drainagetrenches
(iii)Types of soil
Highway drainage
(b) If the soil is relatively
lesspermeable, the
lowering of ground WT
may not be adequate.
Hence in addition to the
longitudinal drains
traversedrainshaveto be
installed at suitable
intervals in effectively
drain off the water.
Highway drainage
When the general ground aswell asimpervious
strata below are sloping, seepageflow is likely to
exist.
If seepage zone is at depth less than 0.6-0.9 m
from sub-grade level, longitudinal pipe drain
in trench filled with filter material and clay seal
may be constructed to intercept the flow.
Highway drainage
Highway drainage
Highway drainage
If the water reaching the sub-grade due to capillary rise
is likely to be detrimental, it is possible to solve the
problem by arresting the capillary rise.
It canbe done by following methods:
(a)Alayer of granular materials of suitable thickness is
provided during the construction of embankment,
between the sub-grade and the highest level of sub
surface water table.
(b)Alternate method is providing the capillary cut off is
by inserting an impermeable or abituminous layer in
place of granular blanket.
Highway drainage
Thesizeandspacingof the sub-surface drainagesystem
depend on the
quantity of water to bedrained off, the type of soil and
type of drain.
The filter material usedin sub-surfacedrains should be
designedto have sufficient permeability offering
negligible resistance to the flow.
And alsoresist the flow of the fine foundation soil
resulting in soil piping.
TheSteps areas follows:
Draw grain sizedistribution curveon log scale%passingvs.
particles size for the foundation soil.
Find the valueof D15sizeof foundation soil.
 Thesizeof filter material should be 5times more than the
sizeof
foundation soil
 D15of filter/D15 of foundation >5
Tofulfill the condition to prevent piping.
 D15of filter/D85 of foundation <5
Henceplot apoint represent the upper limit of D15sizeof
filter given by 5D85of foundation.
Find the sizeof the perforation in the drain pipe or the gap
in the open jointed pipes andlet this be =Dp
Plot apoint representing D85sizeof filter given by the size
2Dp.
TheShadedarea thus obtained represents the region within
which the grain sizedistribution curveof satisfactoryfilter
material shouldlie.
Highway drainage
In caseof sub-grade subjected soil water to soakingcond.,
capillary rise, and in extreme cond. Even flooding for
prolonged periods is termed as water loggedareas.
In such areasconstruction and maintenanceof road is a
problem.
Methods adopted to Overcome
 Raisingthe road level by constructing embankment
 Providing acapillary cut off to arrest capillary water
 ProvidingCementConcrete Block
 Depressingthe sub surface water level by drainage
system
Thank you
Lintels
For more…. Mail to aglaiaconnect2018@gmail.com
1 de 44

Recomendados

Highway drainageHighway drainage
Highway drainageUMASOYA_KARTHIKEYAN
5.6K visualizações20 slides
Highway Drainage SystemHighway Drainage System
Highway Drainage SystemGOKULCIVER
5.9K visualizações21 slides
Introduction to highway engineeringIntroduction to highway engineering
Introduction to highway engineeringAavani Thampi
9.1K visualizações49 slides
Unit 2Unit 2
Unit 2MD MOZAFFAR MASUD
15.6K visualizações121 slides
GEOMETRIC DESIGN OF HIGHWAYGEOMETRIC DESIGN OF HIGHWAY
GEOMETRIC DESIGN OF HIGHWAYreemajadwani
26.5K visualizações32 slides

Mais conteúdo relacionado

Mais procurados

Diversion HeadworksDiversion Headworks
Diversion HeadworksGAURAV. H .TANDON
64.2K visualizações108 slides
Highway engineering PPTHighway engineering PPT
Highway engineering PPTKavin Raval
41.5K visualizações32 slides
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavementsGARRE RAVI KUMAR
31.5K visualizações51 slides
  Tunnel engineering  Tunnel engineering
Tunnel engineeringSaurabh Samant
90.7K visualizações26 slides
Highway Cross-sectional ElementsHighway Cross-sectional Elements
Highway Cross-sectional ElementsAkshathaBhandary
1.9K visualizações22 slides

Mais procurados(20)

Diversion HeadworksDiversion Headworks
Diversion Headworks
GAURAV. H .TANDON64.2K visualizações
Highway engineering PPTHighway engineering PPT
Highway engineering PPT
Kavin Raval41.5K visualizações
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavements
GARRE RAVI KUMAR31.5K visualizações
  Tunnel engineering  Tunnel engineering
Tunnel engineering
Saurabh Samant90.7K visualizações
Highway Cross-sectional ElementsHighway Cross-sectional Elements
Highway Cross-sectional Elements
AkshathaBhandary1.9K visualizações
Highway notes (planning, alignment, & geometric design )Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )
mohit kumar panchal136.6K visualizações
Burmister 2 layerBurmister 2 layer
Burmister 2 layer
SandeepUpadhyay4114.2K visualizações
Hill roadHill road
Hill road
Shree Swami atmanand saraswati inst. of technology, surat 7.2K visualizações
Determining equivalent single wheel load.(ESWL) Determining equivalent single wheel load.(ESWL)
Determining equivalent single wheel load.(ESWL)
Imran Nawaz3.3K visualizações
highway development in indiahighway development in india
highway development in india
Prathi Baa15.2K visualizações
Canal liningCanal lining
Canal lining
MANJUNATH BORAKANAVAR2.6K visualizações
Construction of flexible pavementsConstruction of flexible pavements
Construction of flexible pavements
pradip dangar26.5K visualizações
Spillways components and typesSpillways components and types
Spillways components and types
Rajkumar G24.7K visualizações
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
RAMPRASAD KUMAWAT22.5K visualizações
Airport drainageAirport drainage
Airport drainage
srinivas203629.3K visualizações
Railway Engineering-Curves and superelevationRailway Engineering-Curves and superelevation
Railway Engineering-Curves and superelevation
Mani Vel91.2K visualizações
Rigid pavementRigid pavement
Rigid pavement
pjainrahul99.4K visualizações
Khosla theoryKhosla theory
Khosla theory
AparnaRath1.8K visualizações
Railway Engineering - Geometric design of trackRailway Engineering - Geometric design of track
Railway Engineering - Geometric design of track
Mani Vel60.2K visualizações

Similar a Highway drainage

Highway drainageHighway drainage
Highway drainageZeeshanManzoor10
378 visualizações14 slides
To be presentedTo be presented
To be presentedManas Thapa
541 visualizações21 slides
Water logging.pptxWater logging.pptx
Water logging.pptxEmaan Sharma
38 visualizações36 slides

Similar a Highway drainage(20)

Chapter Four -4 Highway Drainage slide.pdfChapter Four -4 Highway Drainage slide.pdf
Chapter Four -4 Highway Drainage slide.pdf
rajundauliya83 visualizações
Chapter 4 Drainge and maintenance of roadChapter 4 Drainge and maintenance of road
Chapter 4 Drainge and maintenance of road
KHUSHBU SHAH476 visualizações
Highway drainageHighway drainage
Highway drainage
ZeeshanManzoor10378 visualizações
To be presentedTo be presented
To be presented
Manas Thapa541 visualizações
Water logging.pptxWater logging.pptx
Water logging.pptx
Emaan Sharma38 visualizações
F3 Subsoil drainage and installationF3 Subsoil drainage and installation
F3 Subsoil drainage and installation
toverwater17.2K visualizações
20160716_WATER SUPPLY.ppt20160716_WATER SUPPLY.ppt
20160716_WATER SUPPLY.ppt
Anbarasan Sivaraj4 visualizações
Drainage water management Drainage water management
Drainage water management
DHANUKA AGRI ACADEMY294 visualizações
Ground water recharge & water logging by Nikhil PakwanneGround water recharge & water logging by Nikhil Pakwanne
Ground water recharge & water logging by Nikhil Pakwanne
NIKHIL PAKWANNE2.3K visualizações
Ground water recharge & water loggingGround water recharge & water logging
Ground water recharge & water logging
NIKHIL PAKWANNE9.6K visualizações
Chapter 5 methods of irrigation Dr. Thomas Abraham_19-3-14Chapter 5 methods of irrigation Dr. Thomas Abraham_19-3-14
Chapter 5 methods of irrigation Dr. Thomas Abraham_19-3-14
Ambo University (Ethiopia)20K visualizações
NewNew
New
saibabu4840 visualizações
IMPORTANCE OF DRAINAGE IN IRRIGATED AREASIMPORTANCE OF DRAINAGE IN IRRIGATED AREAS
IMPORTANCE OF DRAINAGE IN IRRIGATED AREAS
Yallanagouda Madagoudra1.5K visualizações
Drainage systemDrainage system
Drainage system
Pawankumarm6521.3K visualizações
Earthen damEarthen dam
Earthen dam
amrutaware253 visualizações
Chapter 1Chapter 1
Chapter 1
saibabu4842 visualizações
Subsurface drainageSubsurface drainage
Subsurface drainage
Chethan B J2.9K visualizações

Mais de Aglaia Connect

Underground constructionUnderground construction
Underground constructionAglaia Connect
8K visualizações56 slides
Self curing-concrete-Self curing-concrete-
Self curing-concrete-Aglaia Connect
1.2K visualizações27 slides
Trenchless technologyTrenchless technology
Trenchless technologyAglaia Connect
1.2K visualizações33 slides
Reactive powder-concreteReactive powder-concrete
Reactive powder-concreteAglaia Connect
5.4K visualizações35 slides
Stress ribbon-bridgesStress ribbon-bridges
Stress ribbon-bridgesAglaia Connect
5.5K visualizações44 slides

Mais de Aglaia Connect(20)

Underground constructionUnderground construction
Underground construction
Aglaia Connect8K visualizações
Self curing-concrete-Self curing-concrete-
Self curing-concrete-
Aglaia Connect1.2K visualizações
Trenchless technologyTrenchless technology
Trenchless technology
Aglaia Connect1.2K visualizações
Reactive powder-concreteReactive powder-concrete
Reactive powder-concrete
Aglaia Connect5.4K visualizações
Stress ribbon-bridgesStress ribbon-bridges
Stress ribbon-bridges
Aglaia Connect5.5K visualizações
Self healing-material-bacterial-concreteSelf healing-material-bacterial-concrete
Self healing-material-bacterial-concrete
Aglaia Connect1.1K visualizações
Structural behavious-of-high-strength-concreteStructural behavious-of-high-strength-concrete
Structural behavious-of-high-strength-concrete
Aglaia Connect942 visualizações
Aerated autoclaved-concreteAerated autoclaved-concrete
Aerated autoclaved-concrete
Aglaia Connect318 visualizações
Transatlantic tunnel-floating-tunnelTransatlantic tunnel-floating-tunnel
Transatlantic tunnel-floating-tunnel
Aglaia Connect863 visualizações
Tube structuresTube structures
Tube structures
Aglaia Connect12.5K visualizações
Marble and-quarry-dust-as-additives-in-concrete Marble and-quarry-dust-as-additives-in-concrete
Marble and-quarry-dust-as-additives-in-concrete
Aglaia Connect849 visualizações
Computer ethics Computer ethics
Computer ethics
Aglaia Connect780 visualizações
Plastic waste into fuel using pyrolysis processPlastic waste into fuel using pyrolysis process
Plastic waste into fuel using pyrolysis process
Aglaia Connect1K visualizações
Geotextile for soil stabilizationGeotextile for soil stabilization
Geotextile for soil stabilization
Aglaia Connect1.3K visualizações
Corrosion control of underwater pilesCorrosion control of underwater piles
Corrosion control of underwater piles
Aglaia Connect399 visualizações
Constucted wetlands for waste water treatmentConstucted wetlands for waste water treatment
Constucted wetlands for waste water treatment
Aglaia Connect101 visualizações
Coconut shell as coarse aggregate in the concreteCoconut shell as coarse aggregate in the concrete
Coconut shell as coarse aggregate in the concrete
Aglaia Connect2.5K visualizações
Usage of geogrids in flexible pavementUsage of geogrids in flexible pavement
Usage of geogrids in flexible pavement
Aglaia Connect817 visualizações
Pervious concretePervious concrete
Pervious concrete
Aglaia Connect914 visualizações
Usage of geogrids in flexible pavementUsage of geogrids in flexible pavement
Usage of geogrids in flexible pavement
Aglaia Connect1.1K visualizações

Último(20)

Investor PresentationInvestor Presentation
Investor Presentation
eser sevinç15 visualizações
IEC 61850 Technical Overview.pdfIEC 61850 Technical Overview.pdf
IEC 61850 Technical Overview.pdf
ssusereeea975 visualizações
cloud computing-virtualization.pptxcloud computing-virtualization.pptx
cloud computing-virtualization.pptx
RajaulKarim2078 visualizações
Deutsch CrimpingDeutsch Crimping
Deutsch Crimping
Iwiss Tools Co.,Ltd15 visualizações
STUDY OF SMART MATERIALS USED IN CONSTRUCTION-1.pptxSTUDY OF SMART MATERIALS USED IN CONSTRUCTION-1.pptx
STUDY OF SMART MATERIALS USED IN CONSTRUCTION-1.pptx
AnnieRachelJohn18 visualizações
Paper 3.pdfPaper 3.pdf
Paper 3.pdf
Javad Kadkhodapour6 visualizações
SICTECH CORPORATE PRESENTATIONSICTECH CORPORATE PRESENTATION
SICTECH CORPORATE PRESENTATION
SiCtechInduction16 visualizações
Saikat Chakraborty Java Oracle Certificate.pdfSaikat Chakraborty Java Oracle Certificate.pdf
Saikat Chakraborty Java Oracle Certificate.pdf
SaikatChakraborty78714811 visualizações
Extensions of Time - Contract ManagementExtensions of Time - Contract Management
Extensions of Time - Contract Management
brainquisitive14 visualizações
SWM L1-L14_drhasan (Part 1).pdfSWM L1-L14_drhasan (Part 1).pdf
SWM L1-L14_drhasan (Part 1).pdf
MahmudHasan74787044 visualizações
String.pptxString.pptx
String.pptx
Ananthi Palanisamy47 visualizações
SEMI CONDUCTORSSEMI CONDUCTORS
SEMI CONDUCTORS
pavaniaalla200516 visualizações
Stone Masonry and Brick Masonry.pdfStone Masonry and Brick Masonry.pdf
Stone Masonry and Brick Masonry.pdf
Mohammed Abdullah Laskar19 visualizações
Solar PVSolar PV
Solar PV
Iwiss Tools Co.,Ltd11 visualizações
Codes and Conventions.pptxCodes and Conventions.pptx
Codes and Conventions.pptx
IsabellaGraceAnkers6 visualizações

Highway drainage

  • 2. Highway drainage is a process of removing and controlling excess surface and sub-soil water within the right of way. It includes interception and diversion of water from the road surface and subgrade.
  • 3. Excessmoisture in soil subgrade causesconsiderable lowering of its stability. Increasein moisture causereduction in strength of many pavement materials like stabilized soil and water bound macadam. Sustained contact of water with bituminous pavements causesfailure due to stripping of bitumen from aggregates like loosening or detachment of some of the bituminous pavement layers and formations of pot holes Excesswater on shoulders and pavement edges causes considerable damage.
  • 5. In clayey soil variation in moisture content causes considerable variation in volume of sub grade. High moisture content causesincreases in weight and thus increasein stress and simultaneous reduction in strength of soil mass. Erosion of soil from top of unsurfaced roads and slopes of embankment, cut and hill side is also due to surface water. In cold regions presence of water in the subgrade and a continuous supply of water from the ground water can causeconsiderable damage to the pavement due to frost action.
  • 6. The surface water from the carriageway and shoulder should effectively be drained off without allowing it to percolate to sub grade. Surface water from adjoining land should be prevented form entering the roadway. Side drain should have sufficient capacity and longitudinal slope to carry away all surface water collected. Flow of surface water acrossthe road and shoulders and along slopes should not causeformation of cross ruts or erosion.
  • 8. Seepageand other sources of under ground water should be drained off by the subsurfacedrainage system. Highest level of ground water table should be kept well below the level of subgrade, preferably by atleast 1.2m. In waterlogged areasspecial precautions should be taken
  • 9. During rains, • part of the rain water flows on surface • part of it percolate through the soil mass as gravitational water until it reaches the ground water below the water table. Removal and diversion of surface water from the road way and adjoining land is termedassurface drainage. Diversion and removal of excess of soil water from the subgrade is termed asSurfaceDrainage.
  • 10. Methods of surface drainage 1.By Longitudinal sidedrains. 2.CatchbasinsandInlets in urbanareas 3.Providing damp proofcourse 4. Providing propercamber 5.Providing sufficient slope to the sides 6. Keepingthe level of carriage way at least 60 cm above the HFL.
  • 12. It is necessaryto provide side drain on one side or both sides, when road is constructed in embankment. Side drains should be at least 2.0 m away from bottom edge of an embankment. Depth of side drains is kept 1.0 to 1.5m to prevent the entry of drain water intothe embankment.
  • 16. Catchbasin is astructure like chamber constructed on asewer line. Water from pavement surface is collected in catch basin and discharged to thesewer line. The catch basin (catch pit) is provided with grating to prevent the entry of rubbish into the drainage system.
  • 18. Inlets is aconcrete box with grating either at the top or in the side.
  • 19. For aquick drainageit isnecessaryto ensure that shoulder surface is properly slopedand free from irregularities and depressions. In impervious type, it is practiced to extend the subbasecourse with drainageacrossthe shoulderupto side drain. Alternatively we canprovide cont layer of 75-100mm thick laid under the shoulder at the bottom layer of sub baseabout 150 mm thick extended upto theedge. The pavedshouldershould be at least 0.5%steeper then camber subjectedto min of 3%
  • 20. The unpaved shoulder should be further 0.5% steeper along the horizontal curve,Shoulder on inner side of the curve should have slope steeper than that of pavement. On the outer side, the shoulder should be made to drain away from the pavement, alow rate of super elevation are provided. On the other hand, where higher rate of super elevation, the outside shoulder are kept level or rounded.
  • 24. Except for amedian less than 5m wide, it is not desirable to drain the median areatowards the pavement surface.  1.2 - 1.8 m wide median –Provided with kerbs and always paved.  1.8 - 5 m wide median – Usually turfed and crowned so that surface water could run towards the pavement maybe with or without kerbs.
  • 25. If carriage way slopes towards the median, central drain maybe made to carry the runoff and slope shouldnot be steeper than 6:1. When the median hasonly earthen surface, it should not be crowned because it can result in soil particles being carried to the pavement surface making itslippery.
  • 27. Removal or Diversion of excess soil-water from sub-grade is termed as sub-surface drainage. The changein moisture of sub-grade are causedby the following  Fluctuations in GroundWaterTable  SeepageFlow  Percolation Of RainWater  Movement of CapillaryWater In sub-surface drainage it is practiced to keep the variation of moisture in sub-grade to a minimum.
  • 28. Lowering of Water Table Controlling Seepage Flow Controlling Capillary Water
  • 29. In order to that the sub-grade and pavement are not subjected to excessivemoisture the water table shouldkept at least 1.0to 1.2m below the sub-grade. In places where water table is high to take the road formation on embankment of height not less than 1.0-1.2mis the best approach. ButWhen the formation level is at or below the general ground level it is necessaryto lower the water table.
  • 30. (a) If soil is relatively permeable, it may be possible to lowerWTby constructing longitudinal drainage trenches with drain pipe and filter sand and top of trenches is covered with clay seal The depth of trench depend on: (i) The required lowering of water table (ii) distanceb/w the drainagetrenches (iii)Types of soil
  • 32. (b) If the soil is relatively lesspermeable, the lowering of ground WT may not be adequate. Hence in addition to the longitudinal drains traversedrainshaveto be installed at suitable intervals in effectively drain off the water.
  • 34. When the general ground aswell asimpervious strata below are sloping, seepageflow is likely to exist. If seepage zone is at depth less than 0.6-0.9 m from sub-grade level, longitudinal pipe drain in trench filled with filter material and clay seal may be constructed to intercept the flow.
  • 38. If the water reaching the sub-grade due to capillary rise is likely to be detrimental, it is possible to solve the problem by arresting the capillary rise. It canbe done by following methods: (a)Alayer of granular materials of suitable thickness is provided during the construction of embankment, between the sub-grade and the highest level of sub surface water table. (b)Alternate method is providing the capillary cut off is by inserting an impermeable or abituminous layer in place of granular blanket.
  • 40. Thesizeandspacingof the sub-surface drainagesystem depend on the quantity of water to bedrained off, the type of soil and type of drain. The filter material usedin sub-surfacedrains should be designedto have sufficient permeability offering negligible resistance to the flow. And alsoresist the flow of the fine foundation soil resulting in soil piping. TheSteps areas follows: Draw grain sizedistribution curveon log scale%passingvs. particles size for the foundation soil. Find the valueof D15sizeof foundation soil.
  • 41.  Thesizeof filter material should be 5times more than the sizeof foundation soil  D15of filter/D15 of foundation >5 Tofulfill the condition to prevent piping.  D15of filter/D85 of foundation <5 Henceplot apoint represent the upper limit of D15sizeof filter given by 5D85of foundation. Find the sizeof the perforation in the drain pipe or the gap in the open jointed pipes andlet this be =Dp Plot apoint representing D85sizeof filter given by the size 2Dp. TheShadedarea thus obtained represents the region within which the grain sizedistribution curveof satisfactoryfilter material shouldlie.
  • 43. In caseof sub-grade subjected soil water to soakingcond., capillary rise, and in extreme cond. Even flooding for prolonged periods is termed as water loggedareas. In such areasconstruction and maintenanceof road is a problem. Methods adopted to Overcome  Raisingthe road level by constructing embankment  Providing acapillary cut off to arrest capillary water  ProvidingCementConcrete Block  Depressingthe sub surface water level by drainage system
  • 44. Thank you Lintels For more…. Mail to aglaiaconnect2018@gmail.com