SlideShare uma empresa Scribd logo
1 de 41
Baixar para ler offline
Implementation of the
Single Window System in Kenya
Presentation to:
African Alliance for Electronic Commerce Meeting- Dakar, Senegal.
Venue: Hotel Decameron
Date: Monday, February 2nd , 2015
Presentation Outline
1. Background
2. SWS Project in Kenya
3. Project Stakeholders
4. Project Status
Tuesday, February 10, 2015 2
4. Project Status
5. Key Achievements
6. Challenges, Success factors & Lessons learnt
7. Recognition
8. Single Window Systems in EAC
9. Areas of cooperation
Background
2005 : Preliminary assessment of a Port Community Based System
(PCBS) Project – Conceptualization of the PCBS
2006 : Started Port Based Community System Project
Spearheaded by KPA and KRA
Steering Committee -MD -KPA & KRA- CG
2007 : Why Kenya National Electronic Single Window System
Cross cutting national Project –conceptual approach
Include all Government regulatory agencies
Give initiative GoK authority
Trade facilitation a GoK function
Steering Committee elevated to Government /Ministerial level
PS Treasury-Chair, PS Transport, PS Trade, KPA.KRA.KEBS
2011 : Kenya Trade Network Agency - KENTRADE
Background – Cont’d
A State Corporation established in January 2010 vide Legal
Notice No 6 of 2011.
Principal Objectives:
To Facilitate International TradeTo Facilitate International Trade
To implement, operationalize and manage the Kenya
Electronic Single Window System (Kenya Tradenet).
Parent Ministry:
National Treasury
Background: Why Single Window?
Trade procedures in Kenya have been inefficient, lengthy and slow
resulting in high cost of trade transactions/doing business. The
main reasons are as follows:
Many stakeholders involved in cargo clearance process.
Stakeholders exchange many documents among themselves.
Stakeholder ends up sending the same document to eachStakeholder ends up sending the same document to each
other many times.
Exchanges are in hard copy form and in most cases,
processing of information is carried out manually.
Perennial congestion at the port, long truck queues at the border
posts, corruption,
Underutilization of port facilities, and ultimately, loss of
competitiveness for the country.
Kenya’s Ease of Doing Business Ranking
Ease of Doing Business in
Population 44,353,691
GNI Per Capita (US$) 930
Doing Business 2015 Rank Doing Business 2014 Rank*** Change in
Rank
136 137 1
Topics DB 2015 Rank DB 2014
Rank
Change in
Rank
Starting a Business 143 134 -9
Tuesday, February 10, 2015 6
Starting a Business 143 134 -9
Dealing with Construction Permits 95 35 -60
Getting Electricity 151 151 No change
Getting Credit 116 111 -5
Protecting Minority Investors 122 118 -4
Paying Taxes 102 146 44
Trading Across Borders 153 152 -1
Enforcing Contracts 137 137 No change
Inefficient processes addressed by the Kenya
Electronic Single Window System
KRA
PCPB KPA PPB
Other related
government agencies
NBA
KEBS
Many government regulatory agencies
Chamber of Commerce
TBK
Carriers
Importer/Buyer
Exporter/Seller
Freight Forwarder
/Shipping
Insurance
Company
Numerous lodgments
Many Duplicated data elements
ACA
Results of Inefficiencies
Tons of trade documentsCongestion at Borders & Port
Impossible d'afficher l'image. Votre ordinateur manque peut-être de mémoire pour ouvrir l'image ou l'image est endommagée. Redémarrez l'ordinateur, puis ouvrez à nouveau le fichier. Si le x rouge est toujours affiché, vous devrez peut-être supprimer l'image avant de la réinsérer.
Impossible d'afficher l'image. Votre ordinateur manque peut-être de mémoire pour ouvrir l'image ou l'image est endommagée. Redémarrez l'ordinateur, puis ouvrez à nouveau le fichier. Si le x rouge est toujours affiché, vous devrez peut-être supprimer l'image avant de la réinsérer.
Human Intervention leading to
corruption
The Solution -Single Window System
UN CEFACT RECOMMENDATION 33;
A facility that allows parties involved in trade and transport to
lodge standardized information and documents with a single
entry point to fulfill all import, export, and transit-related
regulatory requirements.
Trader or Agent submits allTrader or Agent submits all
information required for
clearance once to the Single
Window System
Responses from various
Authorities and Financial
Institutions are returned to
Trader or Agent
Kenya Revenue
Authority
Kenya Ports
Authority
Other Control
Agencies
Banks
Bali Package & Single Window Systems
The Bali Package - a trade agreement resulting from the 9th
Ministerial Conference of the World Trade Organization held
in Bali, Indonesia from 3rd to 7th December 2013.
Single Window Systems relevant to implementation of 8 of the
13 articles of the Trade Facilitation Agreement.13 articles of the Trade Facilitation Agreement.
Article 7: Release and Clearance of Goods
Article 10: Formalities connected with Importation and
Exportation and Transit most significant.
Article 10 specifically encourages member states to establish
and maintain Single Window Systems.
Benefits to Government
1. Enhanced Revenue yields 7. Enforcement of controls laid down by
domestic policies and International
agreements
2. Improved trader Compliance 8. Improved international
competitiveness of Kenya
Tuesday, February 10, 2015 11
3. Enable use of sophisticated “Risk
Management” techniques for control
and enforcement purposes
9. Facilitate economic growth – Vision
2030
4. More effective and efficient
deployment of resources
10. Improved Infrastructure utilization at
ports
5. Availability of Trade Statistics 11. Enhance Transparency
6. Enhance e-Government G2B, G2G
Benefits to Business
1. Simplified trade information exchange
2. Faster trade documentation processing - electronic
3. Reduced errors with minimized data re-entry
Tuesday, February 10, 2015 12
3. Reduced errors with minimized data re-entry
4. Improved efficiency & transparency – eliminates manual processes
5. Lower business costs e.g. port storage charges
6. Security in supply chain process -traceability
Benefits to the Kenyan Economy
1. Based on the volume of goods imported/exported:-
•First 3 years – US$ 150m and US$ 250m per annum
•Thereafter - US$ 300m to US$ 450m per annum
2. Arising from improved services e.g.
•Reduced trade transaction costs
Tuesday, February 10, 2015 13
•Reduced trade transaction costs
•Reduced delays
•Reduced Inefficiencies
•Reduced corruption
•Reduced manual documents/paperwork
•Reduced cost of capital ( JIT Concept)
•Reduced demurrage
•Improved space utilization at ports/Airports-Increased capacity
utilization
Average Cargo Dwell Time
GovernmentEnterprises
Current Single Window Objective
7 days maximum - 3 days7 days maximum - 3 days
5 days
2 days
maximum - 1 day
maximum - 1 hr.
Project Stakeholders
Project Stakeholders (27)Project Stakeholders
1. Kenya Revenue Authority 7. Horticultural Crop Development
Authority
2. Kenya Ports Authority 8. Directorate of Veterinary Services
3. Kenya Bureau of Standards 9. Kenya Sugar Board
4. Kenya Plant Inspectorate Service 10. Kenya Dairy Board
5. Pharmacy & Poisons Board 11. Radiation Protection Board
6. Port Health 12. Pest Control Produce Board
Project Stakeholders (27)Project Stakeholders – Cont’d
13. Directorate of Mining 19. Anti-Counterfeit Agency
14. Kenya Wildlife Services 20. Kenya National Police Service
15. Central Bank of Kenya 21. Kenya National Chamber of
Commerce & IndustryCommerce & Industry
16. National Biosafety Authority 22. Ethics and Anti-Corruption
Authority
17. Agriculture, Fisheries and Food
Authority - Tea Directorate
23. National Environment
Management Authority
18. Nursing Council of Kenya 24. Kenya Maritime Authority
Project Stakeholders (27)Project Stakeholders – Cont’d
25. Office of Intermodal Freight
Management) of the DR Congo
(OGEFREM)
31. Kenya Bankers Association
26. Kenya Medical Laboratory
Technicians and Technologists Board
32. Association of Kenya Insurers
27. The National Treasury 33. Kenya Ship Agents Association
28. Kenya Association of Manufacturers 34. Container Freight Stations
Association of Kenya
29. Kenya International Freight &
Warehousing Association
35. Kenya Groupage Cargo Handling
Association
30. East African Shippers Council
Project Status
Project Status
• October 31, 2013 – Kenya TradeNet System go live
• May 2, 2014 – Official launch of the System.
• 3 Project Phases
Phases 1A – Pre-clearance Documentation Modules
Phase 1B – Declaration Submission Module
Phase 2 – Permits Module
Phase 3 – Permits Module
Implementation of 16 Modules & functionalities completed.
Implementation of 4 Modules & functionalities ongoing.
Launch of the Kenya TradeNet System - May 2, 2014
Implementation Status: Completed Modules
Module/ Functionality Date Gone Live
1. Unique Consignment Reference (UCR) Oct 31, 2013
2 Impending Arrival Report (IAR) Dec 02, 2013
3 Bay Plan (BAPLIE) submission Mar 28, 20143 Bay Plan (BAPLIE) submission Mar 28, 2014
4 Manifest Sea Mar 28, 2014
5 Manifest Air Apr 15, 2014
6 Permits Mar 28, 2014
7 Import Declaration Form (IDF) Mar 28, 2014
Implementation Status: Completed Modules
8. Payments Oct 31, 2013
9. Availability of attachments Oct 31, 2013
10. Cargo Release Nov 21, 2013
11. Reports Nov 15, 2013
12 User Admin Oct 31, 2013
13 Integration with Kenya Revenue Authority
systems
Oct 31, 2013
14 Integration with Kenya Ports Authority
Systems
Oct 31, 2013
15 Integration with KEPHIS System Oct 31, 2013
16 Dynamic Risk Management Sept 31, 2014
Implementation Status: Ongoing Modules
A. Pending Modules/ Functionalities Completion Date
1. Security Bonds February 28, 2015
2. Declaration Submission February 28, 2015
3. Exemptions Module February 28, 2015
4. Outbound Processes February 28, 2015
B. Other Ongoing Activities Completion Date
1. Permits - Phase 3 Training of End Users ( C & F
Agents, PGAs)
January 31, 2015
2. Declaration Module Training of End Users ( C & F
Agents
February 28, 2015
3. Piloting of Declaration Module February 28, 2015
4. Outbound Processes February 28, 2015
Key Achievements
Key Achievements
Unique Consignment Reference (UCR) Module - new concept in Kenya.
Electronic application of permits by the traders on 24 hours basis.
Electronic processing and approval of permits by the PGAs.
Electronic confirmation of Payments and provision of multiple payments
instruments. Ksh 124,875,700.00 (USD 1,387,508) has been collected byinstruments. Ksh 124,875,700.00 (USD 1,387,508) has been collected by
government agencies through the SWS Payment Gateway.
Integrated Risk Management System accessible by a number of the Partner
Government Agencies.
Full Integration with 3 major stakeholder systems (KRA, KPA, KEPHIS). Ongoing
integration work with other Agencies.
Real-time generation of reports
Compliance levels have gone up e.g. traders have to provide permits
Implementation Challenges, Success
Factors & Lessons learnedFactors & Lessons learned
Implementation challenges
1. Resistance to change 7. Inadequate legislation
2. Scope Creep 8. Inadequate funding
3. Payments System Challenges 9. Data Harmonisation challenges
Tuesday, February 10, 2015 28
4. Low ICT maturity of some PGAs 10. National Telecommunication
Infrastructure limitations
5. Slow roll out due to lethargy by
some PGAs
11. Uncoordinated system
developments among PGAs.
6. Large number of PGAs involved
(24)
12. Slow resolution of issues by PGAs
during piloting.
Key Success Factors
1. Strong political goodwill and
Government support
5. A strong business case
2. Development partners’ support 6. Sustained stakeholder
Tuesday, February 10, 2015 29
2. Development partners’ support 6. Sustained stakeholder
engagement
3. Clear requirements specification 7. Diverse & Competent Project
Implementation Team
4. Competent Project
Implementation Partner
8. A Practical Project Plan.
Lessons learnt
1. Need for formalization of inter -
organizational collaboration.
5. Continuous BPR to ensure optimal
performance and improvement of
processes.
2. Need for continuous engagement 6. Continuous knowledge transfer
Tuesday, February 10, 2015 30
2. Need for continuous engagement
with stakeholders (Internal &
External ) e.g sensitization forums &
trainings.
6. Continuous knowledge transfer
through trainings , workshops ,
conferences.
3. Increased collaboration with
relevant international bodies.
7. Competent project team.
4. Development of trade policy and
legislation that governs
implementation of SW concept.
RecognitionRecognition
Tuesday, February 10, 2015 31
CIO100 Awards 2014: Best Public Sector ICT Project
Single Window Systems in the EAC RegionSingle Window Systems in the EAC Region
33
NSW
GW
NSW
Centralized Gateway ModelDistributed Gateway Model => ASW
Regional Single Window Models
NSW
NS
W
Regional Service
GW
GW GW
GW
GW
NSW
Central
GW
NS
W
NSWNSW
RSW
EAC National Single Window Systems Implementation
Status
Country Single Window
Implementation
status
Remarks
Kenya Yes Implementation to be completed in April 2015.
Uganda No Funding obtained through TMEA & Implementation
set to commence in October 2014.
35
set to commence in October 2014.
Tanzania No Talks ongoing with TMEA to fund implementation.
Rwanda Yes, partially Stakeholders integrated are Rwanda Revenue
Authority, Rwanda Bureau of Standards, Rwanda
Development Board, Ministry of Health, Airlines &
Clearing Agents.
Ethiopia No Project Implementation Team formed & Study Visits
ongoing (KENTRADE Visited).
South Sudan No No known plans yet.
Burundi No Talks ongoing with TMEA to fund implementation.
Towards a Regional SWS
Under the leadership of the EAC Secretariat, develop and
implement a cooperation framework.
Assist the EAC region collectively by funding the EAC Regional
Single Window System implementation Project.Single Window System implementation Project.
36
Areas of CooperationAreas of Cooperation
Tuesday, February 10, 2015 37
Areas of cooperation
Proposals for Funding
Area Description Estimated costs (USD)
Set up of Secondary site Setup of secondary site to
ensure high availability.
Cost to cover servers,
supporting software,
storage, and network
6,000,000
Tuesday, February 10, 2015 38
storage, and network
infrastructure.
Automation of partner
government agencies
In order to improve
efficiency in the end to end
process, it will be
necessary to support the
automation of back end
approval processes and
integrate the systems with
the KNESWS. USD 200,000
per stakeholder.
2,000,000
Proposals for Funding
Area Description Estimated costs (USD)
Implementation of the
KENTRADE Business
Model
The Kentrade business
model has been developed
with support of TMEA. The
same needs to be
implemented
700,000
Areas of cooperation – Cont’d
Tuesday, February 10, 2015 39
implemented
Set up of Facilitation
Centres at key border
stations. Set up and
out- source the
facilitation centres to
the youth for
management
Set up of each estimated at
USD 50,000. Costs include
• Computers
• Furniture
• LAN/Electricals
• Rent for 1 year
250,000
KENTRADE Contact Centre
Questions
Thank You

Mais conteúdo relacionado

Mais procurados

Import and export of goods customs law
Import and export of goods customs lawImport and export of goods customs law
Import and export of goods customs lawDVSResearchFoundatio
 
Transshipment and shipside
Transshipment  and shipsideTransshipment  and shipside
Transshipment and shipsideDanna
 
Next Generation Service Platforms for Multimedia and Value Added Services
Next Generation Service Platforms for Multimedia and Value Added ServicesNext Generation Service Platforms for Multimedia and Value Added Services
Next Generation Service Platforms for Multimedia and Value Added ServicesAli Saghaeian
 
Implementation of the Kenya National Single Window System_KENTRADE_SWC2016
Implementation of the Kenya National Single Window System_KENTRADE_SWC2016Implementation of the Kenya National Single Window System_KENTRADE_SWC2016
Implementation of the Kenya National Single Window System_KENTRADE_SWC2016AAEC_AFRICAN
 
Presentation E-WAY bill
Presentation E-WAY billPresentation E-WAY bill
Presentation E-WAY billPiyush tyagi
 
Custom clearance procedure for export
Custom clearance procedure for exportCustom clearance procedure for export
Custom clearance procedure for exportStudsPlanet.com
 
Presentation _FTP 2023 31.03.2023 Final.pdf
Presentation _FTP 2023 31.03.2023 Final.pdfPresentation _FTP 2023 31.03.2023 Final.pdf
Presentation _FTP 2023 31.03.2023 Final.pdfmsfjm67hr9
 
Freight Forwarding System Features Ver 1
Freight Forwarding System Features Ver 1Freight Forwarding System Features Ver 1
Freight Forwarding System Features Ver 1csenthilmurugan
 
Ericsson NFVi solution
Ericsson NFVi solutionEricsson NFVi solution
Ericsson NFVi solutionEricsson
 
Ericsson Radio System reaches new heights
Ericsson Radio System reaches new heightsEricsson Radio System reaches new heights
Ericsson Radio System reaches new heightsEricsson
 
Containerization and India - Status
Containerization and India - StatusContainerization and India - Status
Containerization and India - StatusAniruddha Ray (Ani)
 
Import export documentation
Import export documentationImport export documentation
Import export documentationAMIR KHAN
 
Vectoriangiottomanual
VectoriangiottomanualVectoriangiottomanual
Vectoriangiottomanualgusti007
 
E way bill and all the concept in it
E way bill and all the concept in itE way bill and all the concept in it
E way bill and all the concept in itsajal789
 

Mais procurados (20)

Import and export of goods customs law
Import and export of goods customs lawImport and export of goods customs law
Import and export of goods customs law
 
export import procedure
export import procedureexport import procedure
export import procedure
 
Transshipment and shipside
Transshipment  and shipsideTransshipment  and shipside
Transshipment and shipside
 
Next Generation Service Platforms for Multimedia and Value Added Services
Next Generation Service Platforms for Multimedia and Value Added ServicesNext Generation Service Platforms for Multimedia and Value Added Services
Next Generation Service Platforms for Multimedia and Value Added Services
 
Implementation of the Kenya National Single Window System_KENTRADE_SWC2016
Implementation of the Kenya National Single Window System_KENTRADE_SWC2016Implementation of the Kenya National Single Window System_KENTRADE_SWC2016
Implementation of the Kenya National Single Window System_KENTRADE_SWC2016
 
Presentation E-WAY bill
Presentation E-WAY billPresentation E-WAY bill
Presentation E-WAY bill
 
Gst and technology
Gst and technologyGst and technology
Gst and technology
 
Custom clearance procedure for export
Custom clearance procedure for exportCustom clearance procedure for export
Custom clearance procedure for export
 
Presentation _FTP 2023 31.03.2023 Final.pdf
Presentation _FTP 2023 31.03.2023 Final.pdfPresentation _FTP 2023 31.03.2023 Final.pdf
Presentation _FTP 2023 31.03.2023 Final.pdf
 
Freight Forwarding System Features Ver 1
Freight Forwarding System Features Ver 1Freight Forwarding System Features Ver 1
Freight Forwarding System Features Ver 1
 
VoLTE Testing Explained
VoLTE Testing ExplainedVoLTE Testing Explained
VoLTE Testing Explained
 
E way-bill
E way-billE way-bill
E way-bill
 
Ericsson NFVi solution
Ericsson NFVi solutionEricsson NFVi solution
Ericsson NFVi solution
 
Ericsson Radio System reaches new heights
Ericsson Radio System reaches new heightsEricsson Radio System reaches new heights
Ericsson Radio System reaches new heights
 
Containerization and India - Status
Containerization and India - StatusContainerization and India - Status
Containerization and India - Status
 
Converged & Efficient Licensing Framework
Converged & Efficient Licensing FrameworkConverged & Efficient Licensing Framework
Converged & Efficient Licensing Framework
 
Import export documentation
Import export documentationImport export documentation
Import export documentation
 
Vectoriangiottomanual
VectoriangiottomanualVectoriangiottomanual
Vectoriangiottomanual
 
E way bill and all the concept in it
E way bill and all the concept in itE way bill and all the concept in it
E way bill and all the concept in it
 
Custom clearance
Custom clearanceCustom clearance
Custom clearance
 

Destaque

Industrial Property Landscape in Kenya: Facts, figures and trends
Industrial Property Landscape in Kenya: Facts, figures and trendsIndustrial Property Landscape in Kenya: Facts, figures and trends
Industrial Property Landscape in Kenya: Facts, figures and trendsThe Scinnovent Centre
 
Doing Business in Kenya 2015
Doing Business in Kenya 2015Doing Business in Kenya 2015
Doing Business in Kenya 2015AdanRashid
 
Dairy value chain actors and their roles and linkages in Arsi Highlands, Ethi...
Dairy value chain actors and their roles and linkages in Arsi Highlands, Ethi...Dairy value chain actors and their roles and linkages in Arsi Highlands, Ethi...
Dairy value chain actors and their roles and linkages in Arsi Highlands, Ethi...ILRI
 
Kenya livestock projections
Kenya livestock projectionsKenya livestock projections
Kenya livestock projectionsILRI
 
Planing for slaughter house 2015 (final) eng
Planing for slaughter house 2015 (final)   engPlaning for slaughter house 2015 (final)   eng
Planing for slaughter house 2015 (final) engNguyen Quoc Trung
 

Destaque (8)

Industrial Property Landscape in Kenya: Facts, figures and trends
Industrial Property Landscape in Kenya: Facts, figures and trendsIndustrial Property Landscape in Kenya: Facts, figures and trends
Industrial Property Landscape in Kenya: Facts, figures and trends
 
Commercialisation of fodder & fodder seed production by louise mugweni
Commercialisation of fodder & fodder seed production by louise mugweniCommercialisation of fodder & fodder seed production by louise mugweni
Commercialisation of fodder & fodder seed production by louise mugweni
 
Doing Business in Kenya 2015
Doing Business in Kenya 2015Doing Business in Kenya 2015
Doing Business in Kenya 2015
 
Dairy value chain actors and their roles and linkages in Arsi Highlands, Ethi...
Dairy value chain actors and their roles and linkages in Arsi Highlands, Ethi...Dairy value chain actors and their roles and linkages in Arsi Highlands, Ethi...
Dairy value chain actors and their roles and linkages in Arsi Highlands, Ethi...
 
Livestock value chains
Livestock value chains Livestock value chains
Livestock value chains
 
Kenya animal genetic resources centre (kagrc) profile h.k wamukuru
Kenya animal genetic resources centre (kagrc) profile   h.k wamukuruKenya animal genetic resources centre (kagrc) profile   h.k wamukuru
Kenya animal genetic resources centre (kagrc) profile h.k wamukuru
 
Kenya livestock projections
Kenya livestock projectionsKenya livestock projections
Kenya livestock projections
 
Planing for slaughter house 2015 (final) eng
Planing for slaughter house 2015 (final)   engPlaning for slaughter house 2015 (final)   eng
Planing for slaughter house 2015 (final) eng
 

Semelhante a Implementation of the Single Window System in Kenya 2015

Challenges on single windows implementation - KENTRADE - Kenya
Challenges on single windows implementation  - KENTRADE - KenyaChallenges on single windows implementation  - KENTRADE - Kenya
Challenges on single windows implementation - KENTRADE - KenyaAAEC_AFRICAN
 
Challenge of implementation of single window in kenya 2014
Challenge of implementation of single window in kenya 2014Challenge of implementation of single window in kenya 2014
Challenge of implementation of single window in kenya 2014AAEC_AFRICAN
 
Cameroon - Peer review country report 2014
Cameroon - Peer review country report 2014Cameroon - Peer review country report 2014
Cameroon - Peer review country report 2014AAEC_AFRICAN
 
New insights and wto tfa implementation status GCNet GHANA
New insights and wto tfa implementation status  GCNet GHANANew insights and wto tfa implementation status  GCNet GHANA
New insights and wto tfa implementation status GCNet GHANAAAEC_AFRICAN
 
Senegal - Peer review country report - swc douala 2014
Senegal - Peer review country report - swc douala 2014Senegal - Peer review country report - swc douala 2014
Senegal - Peer review country report - swc douala 2014AAEC_AFRICAN
 
Last Developments_GCNet_SWC2016
Last Developments_GCNet_SWC2016Last Developments_GCNet_SWC2016
Last Developments_GCNet_SWC2016AAEC_AFRICAN
 
Weldon- Ministerial brief Final MH Mark (3)
Weldon- Ministerial brief Final MH Mark (3)Weldon- Ministerial brief Final MH Mark (3)
Weldon- Ministerial brief Final MH Mark (3)Weldon K.
 
SARS customs modernisation
SARS customs modernisationSARS customs modernisation
SARS customs modernisationTristan Wiggill
 
Summary and recommendations of the SW Peer review project
Summary and recommendations of the SW Peer review projectSummary and recommendations of the SW Peer review project
Summary and recommendations of the SW Peer review projectAAEC_AFRICAN
 
Regulatory initiatives
Regulatory initiatives  Regulatory initiatives
Regulatory initiatives CA
 
Regulatory initiatives CA overview
Regulatory initiatives   CA overviewRegulatory initiatives   CA overview
Regulatory initiatives CA overviewCA
 
Regulatory initiatives
Regulatory initiativesRegulatory initiatives
Regulatory initiativesCA
 
Korea Online e-Procurement System
Korea Online e-Procurement SystemKorea Online e-Procurement System
Korea Online e-Procurement SystemDadang Solihin
 
National and regional challenges in implementing the bali agreement WORLD BAN...
National and regional challenges in implementing the bali agreement WORLD BAN...National and regional challenges in implementing the bali agreement WORLD BAN...
National and regional challenges in implementing the bali agreement WORLD BAN...AAEC_AFRICAN
 
The Australian Taxation Office change program – lessons about IT procurement
The Australian Taxation Office change program – lessons about IT procurementThe Australian Taxation Office change program – lessons about IT procurement
The Australian Taxation Office change program – lessons about IT procurementTom Augustsson CPA
 
Single window for trade facilitation in asia and the pacific by UN ESCAP
Single window for trade facilitation in asia and the pacific by UN ESCAPSingle window for trade facilitation in asia and the pacific by UN ESCAP
Single window for trade facilitation in asia and the pacific by UN ESCAPAAEC_AFRICAN
 

Semelhante a Implementation of the Single Window System in Kenya 2015 (20)

Challenges on single windows implementation - KENTRADE - Kenya
Challenges on single windows implementation  - KENTRADE - KenyaChallenges on single windows implementation  - KENTRADE - Kenya
Challenges on single windows implementation - KENTRADE - Kenya
 
Challenge of implementation of single window in kenya 2014
Challenge of implementation of single window in kenya 2014Challenge of implementation of single window in kenya 2014
Challenge of implementation of single window in kenya 2014
 
single_window_nga_e.ppt
single_window_nga_e.pptsingle_window_nga_e.ppt
single_window_nga_e.ppt
 
Cameroon - Peer review country report 2014
Cameroon - Peer review country report 2014Cameroon - Peer review country report 2014
Cameroon - Peer review country report 2014
 
New insights and wto tfa implementation status GCNet GHANA
New insights and wto tfa implementation status  GCNet GHANANew insights and wto tfa implementation status  GCNet GHANA
New insights and wto tfa implementation status GCNet GHANA
 
Senegal - Peer review country report - swc douala 2014
Senegal - Peer review country report - swc douala 2014Senegal - Peer review country report - swc douala 2014
Senegal - Peer review country report - swc douala 2014
 
Last Developments_GCNet_SWC2016
Last Developments_GCNet_SWC2016Last Developments_GCNet_SWC2016
Last Developments_GCNet_SWC2016
 
Weldon- Ministerial brief Final MH Mark (3)
Weldon- Ministerial brief Final MH Mark (3)Weldon- Ministerial brief Final MH Mark (3)
Weldon- Ministerial brief Final MH Mark (3)
 
Tradenet case
Tradenet caseTradenet case
Tradenet case
 
SARS customs modernisation
SARS customs modernisationSARS customs modernisation
SARS customs modernisation
 
Summary and recommendations of the SW Peer review project
Summary and recommendations of the SW Peer review projectSummary and recommendations of the SW Peer review project
Summary and recommendations of the SW Peer review project
 
Session 7 ppt 2 mauritius Trading Across Borders; the reform experiences of ...
Session 7 ppt 2 mauritius Trading Across Borders;  the reform experiences of ...Session 7 ppt 2 mauritius Trading Across Borders;  the reform experiences of ...
Session 7 ppt 2 mauritius Trading Across Borders; the reform experiences of ...
 
Trade and Investment Forum
Trade and Investment ForumTrade and Investment Forum
Trade and Investment Forum
 
Regulatory initiatives
Regulatory initiatives  Regulatory initiatives
Regulatory initiatives
 
Regulatory initiatives CA overview
Regulatory initiatives   CA overviewRegulatory initiatives   CA overview
Regulatory initiatives CA overview
 
Regulatory initiatives
Regulatory initiativesRegulatory initiatives
Regulatory initiatives
 
Korea Online e-Procurement System
Korea Online e-Procurement SystemKorea Online e-Procurement System
Korea Online e-Procurement System
 
National and regional challenges in implementing the bali agreement WORLD BAN...
National and regional challenges in implementing the bali agreement WORLD BAN...National and regional challenges in implementing the bali agreement WORLD BAN...
National and regional challenges in implementing the bali agreement WORLD BAN...
 
The Australian Taxation Office change program – lessons about IT procurement
The Australian Taxation Office change program – lessons about IT procurementThe Australian Taxation Office change program – lessons about IT procurement
The Australian Taxation Office change program – lessons about IT procurement
 
Single window for trade facilitation in asia and the pacific by UN ESCAP
Single window for trade facilitation in asia and the pacific by UN ESCAPSingle window for trade facilitation in asia and the pacific by UN ESCAP
Single window for trade facilitation in asia and the pacific by UN ESCAP
 

Mais de AAEC_AFRICAN

Challenges with single window implementation - The Ghana experience - GCNET
Challenges with single window implementation - The Ghana experience - GCNETChallenges with single window implementation - The Ghana experience - GCNET
Challenges with single window implementation - The Ghana experience - GCNETAAEC_AFRICAN
 
Challenges on single windows implementation - the case of madagascar - GASYNET
Challenges on single windows implementation - the case of madagascar - GASYNETChallenges on single windows implementation - the case of madagascar - GASYNET
Challenges on single windows implementation - the case of madagascar - GASYNETAAEC_AFRICAN
 
The single form for foreign trade operators - GUCE GIE - Cameroon
The single form for foreign trade operators - GUCE GIE - CameroonThe single form for foreign trade operators - GUCE GIE - Cameroon
The single form for foreign trade operators - GUCE GIE - CameroonAAEC_AFRICAN
 
Single windows standards and interoperability - GAINDE 2000 - Senegal
Single windows standards and interoperability - GAINDE 2000 - SenegalSingle windows standards and interoperability - GAINDE 2000 - Senegal
Single windows standards and interoperability - GAINDE 2000 - SenegalAAEC_AFRICAN
 
Single window experience sharing workshop - CRIMSONLOGIC
Single window experience sharing workshop - CRIMSONLOGICSingle window experience sharing workshop - CRIMSONLOGIC
Single window experience sharing workshop - CRIMSONLOGICAAEC_AFRICAN
 
Réalisations et perspectives - la facture électronique tunisie tradenet
Réalisations et perspectives  - la facture électronique   tunisie tradenetRéalisations et perspectives  - la facture électronique   tunisie tradenet
Réalisations et perspectives - la facture électronique tunisie tradenetAAEC_AFRICAN
 
Les défis dans la mise en oeuvre des Guichets Uniques - GUOT - republique du ...
Les défis dans la mise en oeuvre des Guichets Uniques - GUOT - republique du ...Les défis dans la mise en oeuvre des Guichets Uniques - GUOT - republique du ...
Les défis dans la mise en oeuvre des Guichets Uniques - GUOT - republique du ...AAEC_AFRICAN
 
Challenges for an implementation of an electronic single window - Guichet Un...
Challenges for an implementation of an electronic single window -  Guichet Un...Challenges for an implementation of an electronic single window -  Guichet Un...
Challenges for an implementation of an electronic single window - Guichet Un...AAEC_AFRICAN
 
Trade Facilitation: the new accelerators_AUC_SWC2016
Trade Facilitation: the new accelerators_AUC_SWC2016Trade Facilitation: the new accelerators_AUC_SWC2016
Trade Facilitation: the new accelerators_AUC_SWC2016AAEC_AFRICAN
 
The Trade Portal_UNCTAD_SWC2016
The Trade Portal_UNCTAD_SWC2016The Trade Portal_UNCTAD_SWC2016
The Trade Portal_UNCTAD_SWC2016AAEC_AFRICAN
 
Single Windows- The new accelerators_UNECE_SWC2016
Single Windows- The new accelerators_UNECE_SWC2016Single Windows- The new accelerators_UNECE_SWC2016
Single Windows- The new accelerators_UNECE_SWC2016AAEC_AFRICAN
 
Mercator programme_WCO_SWC2016
Mercator programme_WCO_SWC2016Mercator programme_WCO_SWC2016
Mercator programme_WCO_SWC2016AAEC_AFRICAN
 
Un outil innovant pour le Congo_GUOT_SWC2016
Un outil innovant pour le Congo_GUOT_SWC2016Un outil innovant pour le Congo_GUOT_SWC2016
Un outil innovant pour le Congo_GUOT_SWC2016AAEC_AFRICAN
 
The Role of Data Models, Communication and Security Controls in a Single Wind...
The Role of Data Models, Communication and Security Controls in a Single Wind...The Role of Data Models, Communication and Security Controls in a Single Wind...
The Role of Data Models, Communication and Security Controls in a Single Wind...AAEC_AFRICAN
 
Les Nouvelles Evolutions_GASYNET_SWC2016
Les Nouvelles Evolutions_GASYNET_SWC2016Les Nouvelles Evolutions_GASYNET_SWC2016
Les Nouvelles Evolutions_GASYNET_SWC2016AAEC_AFRICAN
 
Le Guichet Unique du Commerce Exterieur du Sénégal - Qualité et Performances_...
Le Guichet Unique du Commerce Exterieur du Sénégal - Qualité et Performances_...Le Guichet Unique du Commerce Exterieur du Sénégal - Qualité et Performances_...
Le Guichet Unique du Commerce Exterieur du Sénégal - Qualité et Performances_...AAEC_AFRICAN
 
Le Guichet Unique de la Cote d'Ivoire_SWC2016
Le Guichet Unique de la Cote d'Ivoire_SWC2016Le Guichet Unique de la Cote d'Ivoire_SWC2016
Le Guichet Unique de la Cote d'Ivoire_SWC2016AAEC_AFRICAN
 
Last Developments, Best Practices and Recommendations_SEGUB_SWC2016
Last Developments, Best Practices and Recommendations_SEGUB_SWC2016Last Developments, Best Practices and Recommendations_SEGUB_SWC2016
Last Developments, Best Practices and Recommendations_SEGUB_SWC2016AAEC_AFRICAN
 
Dernières Evolutions_PORTNET_SWC2016
Dernières Evolutions_PORTNET_SWC2016Dernières Evolutions_PORTNET_SWC2016
Dernières Evolutions_PORTNET_SWC2016AAEC_AFRICAN
 
Dernieres Evolutions du déploiement du GUCE_GUCE Cameroun_SWC2016
Dernieres Evolutions du déploiement du GUCE_GUCE Cameroun_SWC2016Dernieres Evolutions du déploiement du GUCE_GUCE Cameroun_SWC2016
Dernieres Evolutions du déploiement du GUCE_GUCE Cameroun_SWC2016AAEC_AFRICAN
 

Mais de AAEC_AFRICAN (20)

Challenges with single window implementation - The Ghana experience - GCNET
Challenges with single window implementation - The Ghana experience - GCNETChallenges with single window implementation - The Ghana experience - GCNET
Challenges with single window implementation - The Ghana experience - GCNET
 
Challenges on single windows implementation - the case of madagascar - GASYNET
Challenges on single windows implementation - the case of madagascar - GASYNETChallenges on single windows implementation - the case of madagascar - GASYNET
Challenges on single windows implementation - the case of madagascar - GASYNET
 
The single form for foreign trade operators - GUCE GIE - Cameroon
The single form for foreign trade operators - GUCE GIE - CameroonThe single form for foreign trade operators - GUCE GIE - Cameroon
The single form for foreign trade operators - GUCE GIE - Cameroon
 
Single windows standards and interoperability - GAINDE 2000 - Senegal
Single windows standards and interoperability - GAINDE 2000 - SenegalSingle windows standards and interoperability - GAINDE 2000 - Senegal
Single windows standards and interoperability - GAINDE 2000 - Senegal
 
Single window experience sharing workshop - CRIMSONLOGIC
Single window experience sharing workshop - CRIMSONLOGICSingle window experience sharing workshop - CRIMSONLOGIC
Single window experience sharing workshop - CRIMSONLOGIC
 
Réalisations et perspectives - la facture électronique tunisie tradenet
Réalisations et perspectives  - la facture électronique   tunisie tradenetRéalisations et perspectives  - la facture électronique   tunisie tradenet
Réalisations et perspectives - la facture électronique tunisie tradenet
 
Les défis dans la mise en oeuvre des Guichets Uniques - GUOT - republique du ...
Les défis dans la mise en oeuvre des Guichets Uniques - GUOT - republique du ...Les défis dans la mise en oeuvre des Guichets Uniques - GUOT - republique du ...
Les défis dans la mise en oeuvre des Guichets Uniques - GUOT - republique du ...
 
Challenges for an implementation of an electronic single window - Guichet Un...
Challenges for an implementation of an electronic single window -  Guichet Un...Challenges for an implementation of an electronic single window -  Guichet Un...
Challenges for an implementation of an electronic single window - Guichet Un...
 
Trade Facilitation: the new accelerators_AUC_SWC2016
Trade Facilitation: the new accelerators_AUC_SWC2016Trade Facilitation: the new accelerators_AUC_SWC2016
Trade Facilitation: the new accelerators_AUC_SWC2016
 
The Trade Portal_UNCTAD_SWC2016
The Trade Portal_UNCTAD_SWC2016The Trade Portal_UNCTAD_SWC2016
The Trade Portal_UNCTAD_SWC2016
 
Single Windows- The new accelerators_UNECE_SWC2016
Single Windows- The new accelerators_UNECE_SWC2016Single Windows- The new accelerators_UNECE_SWC2016
Single Windows- The new accelerators_UNECE_SWC2016
 
Mercator programme_WCO_SWC2016
Mercator programme_WCO_SWC2016Mercator programme_WCO_SWC2016
Mercator programme_WCO_SWC2016
 
Un outil innovant pour le Congo_GUOT_SWC2016
Un outil innovant pour le Congo_GUOT_SWC2016Un outil innovant pour le Congo_GUOT_SWC2016
Un outil innovant pour le Congo_GUOT_SWC2016
 
The Role of Data Models, Communication and Security Controls in a Single Wind...
The Role of Data Models, Communication and Security Controls in a Single Wind...The Role of Data Models, Communication and Security Controls in a Single Wind...
The Role of Data Models, Communication and Security Controls in a Single Wind...
 
Les Nouvelles Evolutions_GASYNET_SWC2016
Les Nouvelles Evolutions_GASYNET_SWC2016Les Nouvelles Evolutions_GASYNET_SWC2016
Les Nouvelles Evolutions_GASYNET_SWC2016
 
Le Guichet Unique du Commerce Exterieur du Sénégal - Qualité et Performances_...
Le Guichet Unique du Commerce Exterieur du Sénégal - Qualité et Performances_...Le Guichet Unique du Commerce Exterieur du Sénégal - Qualité et Performances_...
Le Guichet Unique du Commerce Exterieur du Sénégal - Qualité et Performances_...
 
Le Guichet Unique de la Cote d'Ivoire_SWC2016
Le Guichet Unique de la Cote d'Ivoire_SWC2016Le Guichet Unique de la Cote d'Ivoire_SWC2016
Le Guichet Unique de la Cote d'Ivoire_SWC2016
 
Last Developments, Best Practices and Recommendations_SEGUB_SWC2016
Last Developments, Best Practices and Recommendations_SEGUB_SWC2016Last Developments, Best Practices and Recommendations_SEGUB_SWC2016
Last Developments, Best Practices and Recommendations_SEGUB_SWC2016
 
Dernières Evolutions_PORTNET_SWC2016
Dernières Evolutions_PORTNET_SWC2016Dernières Evolutions_PORTNET_SWC2016
Dernières Evolutions_PORTNET_SWC2016
 
Dernieres Evolutions du déploiement du GUCE_GUCE Cameroun_SWC2016
Dernieres Evolutions du déploiement du GUCE_GUCE Cameroun_SWC2016Dernieres Evolutions du déploiement du GUCE_GUCE Cameroun_SWC2016
Dernieres Evolutions du déploiement du GUCE_GUCE Cameroun_SWC2016
 

Último

WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.Christina Parmionova
 
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxPeter Miles
 
↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...ranjana rawat
 
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...Hemant Purohit
 
Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Christina Parmionova
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlEdouardHusson
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxtsionhagos36
 
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...nservice241
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfSamirsinh Parmar
 
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...aartirawatdelhi
 
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...tanu pandey
 
Climate change and safety and health at work
Climate change and safety and health at workClimate change and safety and health at work
Climate change and safety and health at workChristina Parmionova
 
Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...MOHANI PANDEY
 
VIP Call Girl mohali 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl mohali 7001035870 Enjoy Call Girls With Our EscortsVIP Call Girl mohali 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl mohali 7001035870 Enjoy Call Girls With Our Escortssonatiwari757
 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024ARCResearch
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30JSchaus & Associates
 
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...tanu pandey
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...ranjana rawat
 

Último (20)

WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
 
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
 
↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
 
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
 
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...
 
Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptx
 
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdf
 
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
 
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
 
Climate change and safety and health at work
Climate change and safety and health at workClimate change and safety and health at work
Climate change and safety and health at work
 
Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
 
VIP Call Girl mohali 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl mohali 7001035870 Enjoy Call Girls With Our EscortsVIP Call Girl mohali 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl mohali 7001035870 Enjoy Call Girls With Our Escorts
 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30
 
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
 

Implementation of the Single Window System in Kenya 2015

  • 1. Implementation of the Single Window System in Kenya Presentation to: African Alliance for Electronic Commerce Meeting- Dakar, Senegal. Venue: Hotel Decameron Date: Monday, February 2nd , 2015
  • 2. Presentation Outline 1. Background 2. SWS Project in Kenya 3. Project Stakeholders 4. Project Status Tuesday, February 10, 2015 2 4. Project Status 5. Key Achievements 6. Challenges, Success factors & Lessons learnt 7. Recognition 8. Single Window Systems in EAC 9. Areas of cooperation
  • 3. Background 2005 : Preliminary assessment of a Port Community Based System (PCBS) Project – Conceptualization of the PCBS 2006 : Started Port Based Community System Project Spearheaded by KPA and KRA Steering Committee -MD -KPA & KRA- CG 2007 : Why Kenya National Electronic Single Window System Cross cutting national Project –conceptual approach Include all Government regulatory agencies Give initiative GoK authority Trade facilitation a GoK function Steering Committee elevated to Government /Ministerial level PS Treasury-Chair, PS Transport, PS Trade, KPA.KRA.KEBS 2011 : Kenya Trade Network Agency - KENTRADE
  • 4. Background – Cont’d A State Corporation established in January 2010 vide Legal Notice No 6 of 2011. Principal Objectives: To Facilitate International TradeTo Facilitate International Trade To implement, operationalize and manage the Kenya Electronic Single Window System (Kenya Tradenet). Parent Ministry: National Treasury
  • 5. Background: Why Single Window? Trade procedures in Kenya have been inefficient, lengthy and slow resulting in high cost of trade transactions/doing business. The main reasons are as follows: Many stakeholders involved in cargo clearance process. Stakeholders exchange many documents among themselves. Stakeholder ends up sending the same document to eachStakeholder ends up sending the same document to each other many times. Exchanges are in hard copy form and in most cases, processing of information is carried out manually. Perennial congestion at the port, long truck queues at the border posts, corruption, Underutilization of port facilities, and ultimately, loss of competitiveness for the country.
  • 6. Kenya’s Ease of Doing Business Ranking Ease of Doing Business in Population 44,353,691 GNI Per Capita (US$) 930 Doing Business 2015 Rank Doing Business 2014 Rank*** Change in Rank 136 137 1 Topics DB 2015 Rank DB 2014 Rank Change in Rank Starting a Business 143 134 -9 Tuesday, February 10, 2015 6 Starting a Business 143 134 -9 Dealing with Construction Permits 95 35 -60 Getting Electricity 151 151 No change Getting Credit 116 111 -5 Protecting Minority Investors 122 118 -4 Paying Taxes 102 146 44 Trading Across Borders 153 152 -1 Enforcing Contracts 137 137 No change
  • 7. Inefficient processes addressed by the Kenya Electronic Single Window System KRA PCPB KPA PPB Other related government agencies NBA KEBS Many government regulatory agencies Chamber of Commerce TBK Carriers Importer/Buyer Exporter/Seller Freight Forwarder /Shipping Insurance Company Numerous lodgments Many Duplicated data elements ACA
  • 8. Results of Inefficiencies Tons of trade documentsCongestion at Borders & Port Impossible d'afficher l'image. Votre ordinateur manque peut-être de mémoire pour ouvrir l'image ou l'image est endommagée. Redémarrez l'ordinateur, puis ouvrez à nouveau le fichier. Si le x rouge est toujours affiché, vous devrez peut-être supprimer l'image avant de la réinsérer. Impossible d'afficher l'image. Votre ordinateur manque peut-être de mémoire pour ouvrir l'image ou l'image est endommagée. Redémarrez l'ordinateur, puis ouvrez à nouveau le fichier. Si le x rouge est toujours affiché, vous devrez peut-être supprimer l'image avant de la réinsérer. Human Intervention leading to corruption
  • 9. The Solution -Single Window System UN CEFACT RECOMMENDATION 33; A facility that allows parties involved in trade and transport to lodge standardized information and documents with a single entry point to fulfill all import, export, and transit-related regulatory requirements. Trader or Agent submits allTrader or Agent submits all information required for clearance once to the Single Window System Responses from various Authorities and Financial Institutions are returned to Trader or Agent Kenya Revenue Authority Kenya Ports Authority Other Control Agencies Banks
  • 10. Bali Package & Single Window Systems The Bali Package - a trade agreement resulting from the 9th Ministerial Conference of the World Trade Organization held in Bali, Indonesia from 3rd to 7th December 2013. Single Window Systems relevant to implementation of 8 of the 13 articles of the Trade Facilitation Agreement.13 articles of the Trade Facilitation Agreement. Article 7: Release and Clearance of Goods Article 10: Formalities connected with Importation and Exportation and Transit most significant. Article 10 specifically encourages member states to establish and maintain Single Window Systems.
  • 11. Benefits to Government 1. Enhanced Revenue yields 7. Enforcement of controls laid down by domestic policies and International agreements 2. Improved trader Compliance 8. Improved international competitiveness of Kenya Tuesday, February 10, 2015 11 3. Enable use of sophisticated “Risk Management” techniques for control and enforcement purposes 9. Facilitate economic growth – Vision 2030 4. More effective and efficient deployment of resources 10. Improved Infrastructure utilization at ports 5. Availability of Trade Statistics 11. Enhance Transparency 6. Enhance e-Government G2B, G2G
  • 12. Benefits to Business 1. Simplified trade information exchange 2. Faster trade documentation processing - electronic 3. Reduced errors with minimized data re-entry Tuesday, February 10, 2015 12 3. Reduced errors with minimized data re-entry 4. Improved efficiency & transparency – eliminates manual processes 5. Lower business costs e.g. port storage charges 6. Security in supply chain process -traceability
  • 13. Benefits to the Kenyan Economy 1. Based on the volume of goods imported/exported:- •First 3 years – US$ 150m and US$ 250m per annum •Thereafter - US$ 300m to US$ 450m per annum 2. Arising from improved services e.g. •Reduced trade transaction costs Tuesday, February 10, 2015 13 •Reduced trade transaction costs •Reduced delays •Reduced Inefficiencies •Reduced corruption •Reduced manual documents/paperwork •Reduced cost of capital ( JIT Concept) •Reduced demurrage •Improved space utilization at ports/Airports-Increased capacity utilization
  • 14. Average Cargo Dwell Time GovernmentEnterprises Current Single Window Objective 7 days maximum - 3 days7 days maximum - 3 days 5 days 2 days maximum - 1 day maximum - 1 hr.
  • 16. Project Stakeholders (27)Project Stakeholders 1. Kenya Revenue Authority 7. Horticultural Crop Development Authority 2. Kenya Ports Authority 8. Directorate of Veterinary Services 3. Kenya Bureau of Standards 9. Kenya Sugar Board 4. Kenya Plant Inspectorate Service 10. Kenya Dairy Board 5. Pharmacy & Poisons Board 11. Radiation Protection Board 6. Port Health 12. Pest Control Produce Board
  • 17. Project Stakeholders (27)Project Stakeholders – Cont’d 13. Directorate of Mining 19. Anti-Counterfeit Agency 14. Kenya Wildlife Services 20. Kenya National Police Service 15. Central Bank of Kenya 21. Kenya National Chamber of Commerce & IndustryCommerce & Industry 16. National Biosafety Authority 22. Ethics and Anti-Corruption Authority 17. Agriculture, Fisheries and Food Authority - Tea Directorate 23. National Environment Management Authority 18. Nursing Council of Kenya 24. Kenya Maritime Authority
  • 18. Project Stakeholders (27)Project Stakeholders – Cont’d 25. Office of Intermodal Freight Management) of the DR Congo (OGEFREM) 31. Kenya Bankers Association 26. Kenya Medical Laboratory Technicians and Technologists Board 32. Association of Kenya Insurers 27. The National Treasury 33. Kenya Ship Agents Association 28. Kenya Association of Manufacturers 34. Container Freight Stations Association of Kenya 29. Kenya International Freight & Warehousing Association 35. Kenya Groupage Cargo Handling Association 30. East African Shippers Council
  • 20. Project Status • October 31, 2013 – Kenya TradeNet System go live • May 2, 2014 – Official launch of the System. • 3 Project Phases Phases 1A – Pre-clearance Documentation Modules Phase 1B – Declaration Submission Module Phase 2 – Permits Module Phase 3 – Permits Module Implementation of 16 Modules & functionalities completed. Implementation of 4 Modules & functionalities ongoing.
  • 21. Launch of the Kenya TradeNet System - May 2, 2014
  • 22. Implementation Status: Completed Modules Module/ Functionality Date Gone Live 1. Unique Consignment Reference (UCR) Oct 31, 2013 2 Impending Arrival Report (IAR) Dec 02, 2013 3 Bay Plan (BAPLIE) submission Mar 28, 20143 Bay Plan (BAPLIE) submission Mar 28, 2014 4 Manifest Sea Mar 28, 2014 5 Manifest Air Apr 15, 2014 6 Permits Mar 28, 2014 7 Import Declaration Form (IDF) Mar 28, 2014
  • 23. Implementation Status: Completed Modules 8. Payments Oct 31, 2013 9. Availability of attachments Oct 31, 2013 10. Cargo Release Nov 21, 2013 11. Reports Nov 15, 2013 12 User Admin Oct 31, 2013 13 Integration with Kenya Revenue Authority systems Oct 31, 2013 14 Integration with Kenya Ports Authority Systems Oct 31, 2013 15 Integration with KEPHIS System Oct 31, 2013 16 Dynamic Risk Management Sept 31, 2014
  • 24. Implementation Status: Ongoing Modules A. Pending Modules/ Functionalities Completion Date 1. Security Bonds February 28, 2015 2. Declaration Submission February 28, 2015 3. Exemptions Module February 28, 2015 4. Outbound Processes February 28, 2015 B. Other Ongoing Activities Completion Date 1. Permits - Phase 3 Training of End Users ( C & F Agents, PGAs) January 31, 2015 2. Declaration Module Training of End Users ( C & F Agents February 28, 2015 3. Piloting of Declaration Module February 28, 2015 4. Outbound Processes February 28, 2015
  • 26. Key Achievements Unique Consignment Reference (UCR) Module - new concept in Kenya. Electronic application of permits by the traders on 24 hours basis. Electronic processing and approval of permits by the PGAs. Electronic confirmation of Payments and provision of multiple payments instruments. Ksh 124,875,700.00 (USD 1,387,508) has been collected byinstruments. Ksh 124,875,700.00 (USD 1,387,508) has been collected by government agencies through the SWS Payment Gateway. Integrated Risk Management System accessible by a number of the Partner Government Agencies. Full Integration with 3 major stakeholder systems (KRA, KPA, KEPHIS). Ongoing integration work with other Agencies. Real-time generation of reports Compliance levels have gone up e.g. traders have to provide permits
  • 27. Implementation Challenges, Success Factors & Lessons learnedFactors & Lessons learned
  • 28. Implementation challenges 1. Resistance to change 7. Inadequate legislation 2. Scope Creep 8. Inadequate funding 3. Payments System Challenges 9. Data Harmonisation challenges Tuesday, February 10, 2015 28 4. Low ICT maturity of some PGAs 10. National Telecommunication Infrastructure limitations 5. Slow roll out due to lethargy by some PGAs 11. Uncoordinated system developments among PGAs. 6. Large number of PGAs involved (24) 12. Slow resolution of issues by PGAs during piloting.
  • 29. Key Success Factors 1. Strong political goodwill and Government support 5. A strong business case 2. Development partners’ support 6. Sustained stakeholder Tuesday, February 10, 2015 29 2. Development partners’ support 6. Sustained stakeholder engagement 3. Clear requirements specification 7. Diverse & Competent Project Implementation Team 4. Competent Project Implementation Partner 8. A Practical Project Plan.
  • 30. Lessons learnt 1. Need for formalization of inter - organizational collaboration. 5. Continuous BPR to ensure optimal performance and improvement of processes. 2. Need for continuous engagement 6. Continuous knowledge transfer Tuesday, February 10, 2015 30 2. Need for continuous engagement with stakeholders (Internal & External ) e.g sensitization forums & trainings. 6. Continuous knowledge transfer through trainings , workshops , conferences. 3. Increased collaboration with relevant international bodies. 7. Competent project team. 4. Development of trade policy and legislation that governs implementation of SW concept.
  • 32. CIO100 Awards 2014: Best Public Sector ICT Project
  • 33. Single Window Systems in the EAC RegionSingle Window Systems in the EAC Region 33
  • 34. NSW GW NSW Centralized Gateway ModelDistributed Gateway Model => ASW Regional Single Window Models NSW NS W Regional Service GW GW GW GW GW NSW Central GW NS W NSWNSW RSW
  • 35. EAC National Single Window Systems Implementation Status Country Single Window Implementation status Remarks Kenya Yes Implementation to be completed in April 2015. Uganda No Funding obtained through TMEA & Implementation set to commence in October 2014. 35 set to commence in October 2014. Tanzania No Talks ongoing with TMEA to fund implementation. Rwanda Yes, partially Stakeholders integrated are Rwanda Revenue Authority, Rwanda Bureau of Standards, Rwanda Development Board, Ministry of Health, Airlines & Clearing Agents. Ethiopia No Project Implementation Team formed & Study Visits ongoing (KENTRADE Visited). South Sudan No No known plans yet. Burundi No Talks ongoing with TMEA to fund implementation.
  • 36. Towards a Regional SWS Under the leadership of the EAC Secretariat, develop and implement a cooperation framework. Assist the EAC region collectively by funding the EAC Regional Single Window System implementation Project.Single Window System implementation Project. 36
  • 37. Areas of CooperationAreas of Cooperation Tuesday, February 10, 2015 37
  • 38. Areas of cooperation Proposals for Funding Area Description Estimated costs (USD) Set up of Secondary site Setup of secondary site to ensure high availability. Cost to cover servers, supporting software, storage, and network 6,000,000 Tuesday, February 10, 2015 38 storage, and network infrastructure. Automation of partner government agencies In order to improve efficiency in the end to end process, it will be necessary to support the automation of back end approval processes and integrate the systems with the KNESWS. USD 200,000 per stakeholder. 2,000,000
  • 39. Proposals for Funding Area Description Estimated costs (USD) Implementation of the KENTRADE Business Model The Kentrade business model has been developed with support of TMEA. The same needs to be implemented 700,000 Areas of cooperation – Cont’d Tuesday, February 10, 2015 39 implemented Set up of Facilitation Centres at key border stations. Set up and out- source the facilitation centres to the youth for management Set up of each estimated at USD 50,000. Costs include • Computers • Furniture • LAN/Electricals • Rent for 1 year 250,000