Perencanaan Gaya-gaya
Pondasi pada Bangunan
Gedung dengan 1 Basement
Made based on experience as Structural Engineer
29-Aug-14
Tutorial Structural Engineer
Afret Nobel, ST & Yudhistira Achmad, ST
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 2
Table of ContentsTable of ContentsTable of ContentsTable of Contents
1 PRAKATA ........................................................................................................................... 3
2 PEMBATASAN MASALAH....................................................................................................... 4
3 PENDAHULUAN ................................................................................................................... 5
3.1 File Struktur Atas.......................................................................................................... 7
3.2 File Struktur Total ......................................................................................................... 8
3.3 File Struktur Bawah....................................................................................................... 9
4 PROSEDUR PERENCANAAN................................................................................................. 10
4.1 Perencanaan Struktur Total.......................................................................................... 10
4.1.1 Langkah-langkah memodelkan struktur total:........................................................... 10
4.2 Perencanaan Struktur Bawah........................................................................................ 18
4.2.1 Langkah-langkahnya memodelkan struktur bawah:................................................... 19
4.3 Resume Support Reaction ............................................................................................ 24
5 KESIMPULAN .................................................................................................................... 26
6 PROFIL PENULIS ..............................................................................................................27s
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 3
1 PRAKATA
Ebook ini adalah ebook gratis yang proses mendapatkannya memerlukan upaya dan keberanian untuk
bertindak. Banyak orang yang membaca publikasi tentang gratisnya ebook ini tapi tetap tak bertindak,
bisa jadi karena:
• Ragu, “Masa sih hari gini ada ebook yang dibagi gratis?”.
• Menunda, “Nanti aja ahh, toh gratis.”
• Putus asa, “Kok susah amat sih mau dapat yang gratisan!”
• Pikiran Kotor, “Paling ebooknya hanya untuk promosi blognya saja.”
• Atau alasan-alasan lainnya...
Bagi Anda yang berhasil mendapatkan ebook ini, berarti Anda bukan bagian dari orang-orang diatas.
Maka dari itu, kami berani mengatakan,
“Anda adalah orang-orang hebat”.
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 4
Bacalah dengan teliti!...
Karena kami menulisnya juga dengan teliti, artinya banyak pesan tersembunyi (ilmu) yang baru akan
Anda pahami saat Anda baca berulang. Lagipula materi yang kami sampaikan bukanlah bahan bacaan,
tapi adalah bahan praktik. Anda akan lebih mengerti jika membaca dan mempraktekkannya.
(Pembukaan by @JayaYEA dengan editan seperlunya)
2 PEMBATASAN MASALAH
• Pemodelan yang kami lakukan di sini merupakan hasil dari pengalaman kami sebagai Structural
Engineer di konsultan. Anda bisa saja menggunakan cara Anda sendiri jika Anda sudah tahu
prinsipnya.
• Pemodelan dilakukan 3 Dimensi menggunakan program Etabs
• Bangunan yang digunakan sebagai contoh merupakan bangunan 4 lantai dengan 1 basement.
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 5
• Perencanaan dilakukan secara berurutan, mulai dari struktur atas, struktur total, dan struktur
bawah.
3 PENDAHULUAN
• Basement adalah lantai bangunan sebagian atau seluruhnya yang terletak di bawah permukaan
tanah. Basement biasanya digunakan sebagai tempat parkir kendaraan dan meletakkan
peralatan mekanikal/elektrikal seperti: Water Threatment Plan, Sewage Threatment Plan, dll
• Merencanakan gaya-gaya pondasi merupakan langkah pekerjaan yang harus Anda lakukan
sebelum merencanakan pondasi
• Karena fungsi pondasi pada bangunan yang sangat vital, perencanaan gaya-gaya pada pondasi
harus benar-benar dilakukan dengan cermat dan teliti
• Gaya-gaya pondasi tidak sama persis dengan reaksi perletakan. Perbedaannya terletak pada
arah kerja momen. Karena untuk merencanakan pondasi, reaksi yang terjadi merupakan Aksi
pada pondasi
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 6
• Struktur atas adalah struktur yang berada di atas permukaan tanah, sedangkan struktur bawah
adalah struktur yang berada di bawah permukaan tanah.
• Perencanaan gaya-gaya pondasi pada bangunan dengan 1 basement bisa Anda lakukan dengan
cara memisah struktur atas dan struktur bawah.
• Ada 3 file yang saling terkait dan harus Anda buat dalam program Etabs untuk merencanakan
gaya-gaya pondasi, yaitu:
1. File Model Struktur Atas
2. File Model Struktur Total (File Struktur Atas + Lantai di bawah muka tanah)
3. File Model Struktur Bawah (Tie Beam + Pelat Basement)
www.LaporanTeknikSipil.wordpress.com
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 7
1. File Model Struktur Atas 2. File Model Struktur Total 3. File Model Struktur Bawah
3.1 File Struktur Atas
• File model struktur atas adalah file yang harus Anda buat pertama kali dalam pemodelan
• Mulai dari pembebanan, mode, drift dan persyaratan lainnya harus benar-benar fix di sini
• Kami tidak akan menjelaskan secara rinci mengenai perencanaan struktur atas karena sudah
pernah kami bahas pada ebook dengan judul ”ANALISIS STRUKTUR GEDUNG BERTINGKAT
RENDAH DENGAN SOFTWARE ETABS V9”
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 8
3.2 File Struktur Total
• File struktur total merupakan penggabungan antara file struktur atas dengan lantai terbawah
• Beban-beban yang bekerja pada struktur total adalah sama dengan beban pada struktur atas,
kecuali beban gempa.
• Menurut peraturan, gaya gempa pada struktur bagian bawah dan pondasi harus lebih besar dari
pada gaya gempa struktur di atasnya.
• Hal ini dilakukan untuk menjamin bahwa struktur bawah tidak runtuh terlebih dahulu sebelum
struktur atas.
• File struktur total digunakan untuk mengeluarkan reaksi perletakan dan mendesain struktur di
bawah tanah saja.
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 9
3.3 File Struktur Bawah
• Struktur bawah terdiri dari tie beam dan pelat basement.
• Pembebanan yang bekerja pada struktur bawah adalah beban mati, bebah hidup, dan beban
Uplift.
• Untuk keamanan, beban uplift boleh Anda ambil setinggi muka air banjir atau setinggi lantai
basement. Misalkan Tinggi air 2 meter maka beban uplift = (h x bj. air) – (tebal pelat basement
x bj. Beton)= 2 m x 1000 kg/m3
+ 0.25 m x 2400 kg/m3
= 1400 kg/m2
• Beban mati dan beban hidup bekerja secara gravitasi, sedangkan beban uplift bekerja
sebaliknya. Input beban mati dan beban hidup sesuai layout dan fungsi lantai.
• Tidak ada momen yang terjadi pada perletakan struktur bawah, oleh karena itu perletakannya
Anda modelkan sebagai sendi (pin).
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 10
4 PROSEDUR PERENCANAAN
4.1 Perencanaan Struktur Total
<<<File Struktur Total
4.1.1 Langkah-langkah memodelkan struktur total:
1. Save as Struktur Atas dan beri nama file >> Struktur Total
2. Tambahkan story pada bagian paling bawah model Anda! (jika tipikal dengan lantai di atasnya,
cukup dicopy-kan saja)
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 11
3. Masukkan pembebanan pada lantai ground sesuai layout dan fungsi lantai
4. Beri diapragma pada lantai ground Anda sama seperti pada lantai lainnya untuk memasukkan
beban gempa
5. Update beban gempa bangunan Anda menjadi beban gempa untuk struktur total
Story
x y x y
STORY4 28,809 26,465 43,214 39,698
STORY3 22,676 19,709 34,014 29,563
STORY2 15,615 13,529 23,423 20,294
STORY1 7,393 6,554 11,089 9,831
GROUND 18,227 18,227
Fi
Struktur Atas
Fi Total
Struktur Total
<<< Input Beban Gempa
Fi = Gaya gempa pada STRUKTUR ATAS
Fi Total = Gaya gempa pada STRUKTUR TOTAL = (Gaya gempa pada STRUKTUR ATAS x
Faktor Kuat Lebih sesuai nilai R yang digunakan)
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 12
6. Gaya gempa yang digunakan pada struktur total Anda adalah Fi Total
7. Gaya gempa pada lantai Ground dihitung sebagai berikut:
Gaya Gempa Pada Struktur Bawah
Lantai Massa Lantai G Reduksi Wb Fb
(Kg) (m / det2) (Kg) (Kg)
Base 23,023 9.8065 0.3 225,776 18,227
Fp = 0.133 * Sds * I * Wb
= 0.133 * 0.607 * 1.00 *225,776 = 18,227 Kg
Fp = Beban gempa horisontal terpusat
Sds = Parameter respon spektra percepatan desain pada periode pendek
I = Faktor Keutamaan
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 13
Wb = Berat lantai
8. Sebelum melakukan Run Analysis, lakukan check model terlebih dahulu.
9. Jika terjadi error maka perbaiki errornya, lihat caranya pada ebook dengan judul “Solving
Warning Pada Etabs – Afret Nobel & Muhammad Faisal”
10. Show table > Support Reaction
11. Tabelkan output-output sebagai berikut:
www.LaporanTeknikSipil.wordpress.com
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 14
Support Reaction Dead Load (kg.m)
Story Point Load FX FY FZ MX MY MZ
BASE 5 DEAD 4371 -4558 45947 672 1668 0
BASE 6 DEAD 1591 -2439 50192 130 1568 0
BASE 8 DEAD 1591 2439 50192 -130 1568 0
BASE 9 DEAD 4371 4558 45947 -672 1668 0
BASE 10 DEAD 1242 629 62419 -624 -370 0
BASE 11 DEAD 20 45 63716 -44 19 0
BASE 12 DEAD 20 -45 63716 44 19 0
BASE 13 DEAD 1242 -629 62419 624 -370 0
BASE 14 DEAD -1242 -629 62419 624 370 0
BASE 15 DEAD -20 -45 63716 44 -19 0
BASE 16 DEAD -20 45 63716 -44 -19 0
BASE 17 DEAD -1242 629 62419 -624 370 0
BASE 18 DEAD -4371 -4558 45947 672 -1668 0
BASE 19 DEAD -1591 -2439 50192 130 -1568 0
BASE 20 DEAD -1591 2439 50192 -130 -1568 0
BASE 21 DEAD -4371 4558 45947 -672 -1668 0
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 15
Support Reaction Live Load (kg.m)
Story Point Load FX FY FZ MX MY MZ
BASE 5 LIVE 1,336 -1,632 9,050 259 523 0
BASE 6 LIVE 854 -1,274 13,659 106 841 0
BASE 8 LIVE 854 1,178 13,622 -80 841 0
BASE 9 LIVE 1,412 1,584 9,053 -247 526 0
BASE 10 LIVE 733 337 14,945 -334 -101 0
BASE 11 LIVE 2 21 29,812 -20 2 0
BASE 12 LIVE -5 -21 29,751 21 -4 0
BASE 13 LIVE 1,103 -342 15,250 340 -139 0
BASE 14 LIVE -42 -436 19,230 433 498 0
BASE 15 LIVE 287 -26 38,838 25 279 0
BASE 16 LIVE 140 80 34,427 -78 137 0
BASE 17 LIVE -763 339 14,899 -335 103 0
BASE 18 LIVE -1,952 -2,659 14,425 429 -887 0
BASE 19 LIVE -1,374 -1,478 21,249 116 -1,350 0
BASE 20 LIVE -1,130 2,290 18,252 -256 -1,116 0
BASE 21 LIVE -1,454 2,037 9,538 -265 -526 0
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 16
Support Reaction EQX Load (kg.m)
Story Point Load FX FY FZ MX MY MZ
BASE 5 EQX -12,359 351 -29,452 -191 5,072 -16
BASE 6 EQX 6,813 -2,200 -17,441 90 6,449 0
BASE 8 EQX 6,562 -43 -17,110 -121 6,215 0
BASE 9 EQX -11,644 -855 -31,168 -400 4,333 14
BASE 10 EQX -30,185 200 -2,265 -189 747 0
BASE 11 EQX 4,207 135 1,042 -131 4,049 0
BASE 12 EQX 4,378 135 1,041 -130 4,215 0
BASE 13 EQX -32,756 198 -839 -187 1,189 0
BASE 14 EQX -32,756 -198 839 187 1,189 0
BASE 15 EQX 4,378 -135 -1,041 130 4,215 0
BASE 16 EQX 4,207 -135 -1,042 131 4,049 0
BASE 17 EQX -30,185 -200 2,265 189 747 0
BASE 18 EQX -12,359 -351 29,452 191 5,072 -16
BASE 19 EQX 6,813 2,200 17,441 -90 6,449 0
BASE 20 EQX 6,562 43 17,110 121 6,215 0
BASE 21 EQX -11,644 855 31,168 400 4,333 14
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 17
Support Reaction EQY Load (kg.m)
Story Point Load FX FY FZ MX MY MZ
BASE 5 EQY 607 -11,398 37,760 -885 -506 -20
BASE 6 EQY -178 -27,676 4,157 3,928 -166 -1
BASE 8 EQY 178 -27,676 -4,157 3,928 166 -1
BASE 9 EQY -607 -11,398 -37,760 -885 506 -20
BASE 10 EQY 241 6,755 -22,217 -6,210 300 -1
BASE 11 EQY 121 4,413 804 -4,231 117 -1
BASE 12 EQY -121 4,413 -804 -4,231 -117 -1
BASE 13 EQY -241 6,755 22,217 -6,210 -300 -1
BASE 14 EQY 3,913 7,316 24,243 -6,740 -316 -1
BASE 15 EQY -121 4,793 -806 -4,598 -117 -1
BASE 16 EQY 121 4,793 806 -4,598 117 -1
BASE 17 EQY -3,913 7,316 -24,243 -6,740 316 -1
BASE 18 EQY 420 -12,129 40,200 -1,714 -532 22
BASE 19 EQY -176 -30,880 3,688 3,894 -164 -1
BASE 20 EQY 176 -30,880 -3,688 3,894 164 -1
BASE 21 EQY -420 -12,129 -40,200 -1,714 532 22
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 18
4.2 Perencanaan Struktur Bawah
3 dimensi struktur bawah Menunjukkan perletakan
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 19
4.2.1 Langkah-langkahnya memodelkan struktur bawah:
1. Save as file Struktur Total dan beri nama file >> Struktur Bawah
2. Delete semua lantai dan sisakan hanya lantai terbawah. Pada contoh ini adalah Lantai Ground.
Karena lantai basement yang kami buat adalah tipikal dengan lantai ground
3. Hapus semua kolom dan beri perletakan sendi pada titik joint kolom tersebut
4. Usahakan untuk membuat lantai basement di atas grid base, agar tidak ada perletakan yang
tumbuh secara otomatis
5. Masukkan pembebanan pada basement berupa Dead Load, Live Load, dan Uplift (jika ada)
6. Masukkan dinding basement sebagai beban pada balok di bawahnya
7. Desain dinding basement dilakukan secara terpisah dengan pembebanan sederhana. Pelajari
caranya pada ebook dengan judul “Perancangan Dinding Basement dg Bantuan Software Etabs
- Afret Nobel”
8. Hapus semua properti gaya gempa pada file ini karena Anda tidak membutuhkannya
9. Sebelum melakukan Run Analysis, lakukan check model terlebih dahulu.
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 20
10. Jika terjadi error maka perbaiki errornya terlebih dahulu, lihat caranya pada ebook dengan judul
“Solving Warning Pada Etabs – Afret Nobel & Muhammad Faisal”
11. Show table > Support Reaction
12. Tabelkan output-output sebagai berikut:
KATA-KATA PENTING:
1. Salah merencanakan = merencanakan yang salah
2. Software hanyalah software, jika yang Anda masukkan sampah maka yang
keluar juga sampah
3. Engineering judgement sangat diperlukan dalam hal ini
4. Kritik dan saran yang membangun sangat kami butuhkan demi penyempurnaan
tulisan ini dimasa mendatang
5. Structural Engineer more as an ART than SCIENE
6. Semua ebook yang menjadi rujukan pada pembahasan ini bisa Anda download
di sini! http://www.LaporanTeknikSipil.Wordpress.com
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 21
Support Reaction Dead Load (kg.m)
Story Point Load FX FY FZ MX MY MZ
UG 5 DEAD 0 0 4,076 0 0 0
UG 6 DEAD 0 0 6,754 0 0 0
UG 8 DEAD 0 0 6,754 0 0 0
UG 9 DEAD 0 0 4,076 0 0 0
UG 10 DEAD 0 0 8,688 0 0 0
UG 11 DEAD 0 0 11,514 0 0 0
UG 12 DEAD 0 0 11,514 0 0 0
UG 13 DEAD 0 0 8,688 0 0 0
UG 14 DEAD 0 0 8,688 0 0 0
UG 15 DEAD 0 0 11,514 0 0 0
UG 16 DEAD 0 0 11,514 0 0 0
UG 17 DEAD 0 0 8,688 0 0 0
UG 18 DEAD 0 0 4,076 0 0 0
UG 19 DEAD 0 0 6,754 0 0 0
UG 20 DEAD 0 0 6,754 0 0 0
UG 21 DEAD 0 0 4,076 0 0 0
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 22
Support Reaction Live Load (kg.m)
Story Point Load FX FY FZ MX MY MZ
UG 5 LIVE 0 0 1,796 0 0 0
UG 6 LIVE 0 0 4,232 0 0 0
UG 8 LIVE 0 0 4,232 0 0 0
UG 9 LIVE 0 0 1,796 0 0 0
UG 10 LIVE 0 0 4,805 0 0 0
UG 11 LIVE 0 0 10,768 0 0 0
UG 12 LIVE 0 0 10,768 0 0 0
UG 13 LIVE 0 0 4,805 0 0 0
UG 14 LIVE 0 0 4,805 0 0 0
UG 15 LIVE 0 0 10,768 0 0 0
UG 16 LIVE 0 0 10,768 0 0 0
UG 17 LIVE 0 0 4,805 0 0 0
UG 18 LIVE 0 0 1,796 0 0 0
UG 19 LIVE 0 0 4,232 0 0 0
UG 20 LIVE 0 0 4,232 0 0 0
UG 21 LIVE 0 0 1,796 0 0 0
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 23
Support Reaction Uplift (kg.m)
Story Point Load FX FY FZ MX MY MZ
UG 5 UPLIFT 0 0 -4,489 0 0 0
UG 6 UPLIFT 0 0 -10,580 0 0 0
UG 8 UPLIFT 0 0 -10,580 0 0 0
UG 9 UPLIFT 0 0 -4,489 0 0 0
UG 10 UPLIFT 0 0 -12,012 0 0 0
UG 11 UPLIFT 0 0 -26,919 0 0 0
UG 12 UPLIFT 0 0 -26,919 0 0 0
UG 13 UPLIFT 0 0 -12,012 0 0 0
UG 14 UPLIFT 0 0 -12,012 0 0 0
UG 15 UPLIFT 0 0 -26,919 0 0 0
UG 16 UPLIFT 0 0 -26,919 0 0 0
UG 17 UPLIFT 0 0 -12,012 0 0 0
UG 18 UPLIFT 0 0 -4,489 0 0 0
UG 19 UPLIFT 0 0 -10,580 0 0 0
UG 20 UPLIFT 0 0 -10,580 0 0 0
UG 21 UPLIFT 0 0 -4,489 0 0 0
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 24
4.3 Resume Support Reaction
Resume Support Reaction
UPLIFT
N Mxx Myy N Mxx Myy N N Mxx Myy N Mxx Myy
(TON) (KGM) (KGM) (TON) (KGM) (KGM) (TON) (TON) (KGM) (KGM) (TON) (KGM) (KGM)
5 BASE 50 -672 -1,668 3 -259 -523 -4 -29 191 -5,072 -1 506 20
6 BASE 57 -130 -1,568 5 -106 -841 -11 -17 -90 -6,449 4 166 1
8 BASE 57 130 -1,568 5 80 -841 -11 -17 121 -6,215 4 -166 1
9 BASE 50 672 -1,668 3 247 -526 -4 -31 400 -4,333 -1 -506 20
10 BASE 71 624 370 6 334 101 -12 -2 189 -747 -6 -300 1
11 BASE 75 44 -19 11 20 -2 -27 1 131 -4,049 -4 -117 1
12 BASE 75 -44 -19 11 -21 4 -27 1 130 -4,215 -4 117 1
13 BASE 71 -624 370 6 -340 139 -12 -1 187 -1,189 -6 300 1
14 BASE 71 -624 -370 5 -433 -498 -12 1 -187 -1,189 -7 316 1
15 BASE 75 -44 19 11 -25 -279 -27 -1 -130 -4,215 -5 117 1
16 BASE 75 44 19 11 78 -137 -27 -1 -131 -4,049 -5 -117 1
17 BASE 71 624 -370 4 335 -103 -12 2 -189 -747 -7 -316 1
18 BASE 50 -672 1,668 0 -429 887 -4 29 -191 -5,072 -2 532 -22
19 BASE 57 -130 1,568 3 -116 1,350 -11 17 90 -6,449 4 164 1
20 BASE 57 130 1,568 3 256 1,116 -11 17 -121 -6,215 4 -164 1
21 BASE 50 672 1,668 0 265 526 -4 31 -400 -4,333 -2 -532 -22
NO
ETABS
STORY
DEAD LOAD LIVE LOAD GEMPA ARAH - X GEMPA ARAH - Y
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 25
Titik-titik perletakan
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 26
5 KESIMPULAN
1. Dead load = Dead Load Struktur Atas + Dead Load Struktur Bawah
2. Live Load = Live Load Struktur Atas + Live Load Struktur Bawah
3. Eqx dan Eqy = reaksi perletakan akibat beban gempa struktur total
4. Uplift = reaksi perletakan akibat Uplift dari struktur bawah
5. Arah gaya momen dibalik Dari reaksi menjadi aksi, dari positive+ menjadi negative-
6. Gaya -gaya perletakan yang diperoleh pada perhitungan di atas adalah gaya yang akan
digunakan sebagai acuan dalam merencanakan pondasi.
7. Panduan merencanakan pondasi tiang pancang dapat Anda pelajari pada ebook dengan judul
“Perhitungan Reaksi Tiang Pondasi dengan Kombinasi Pembebanan SNI 1726 - 2012 & SAFE
12”
8. Pada setiap program perhitungan struktur akan memiliki perjanjian arah, dan jangan sampai
salah dalam pembacaan output, (ada local axes dan ada global axes).
[PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014
Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 27
9. File save as digunakan agar nomor point kolom tetap konsisten untuk memudahkan pengolahan
output dengan tabel excel
6 PROFIL PENULIS
Afret Nobel adalah alumni
Diploma Teknik Sipil
Universitas Gadjah Mada
Angkatan 2005 dan Alumni
Ekstensi Teknik Sipil
Universitas Indonesia
Angkatan 2009. Papanya
seorang petani dan Mamanya
pedagang. Founder at
www.NobelConsultant.com
Yudhistira Achmad
alumni Diploma Teknik
Sipil Universitas Gadjah
Mada Angkatan 2008 dan
Alumni Ekstensi Teknik
Sipil Universitas
Indonesia Angkatan
2011. Papanya udah
diatas sana dan Mama
nya seorang pedagang.
Anda diperbolehkan untuk mengirimkan lewat pos dan email dan memberikan buku elektronik ini
kepada siapa saja yang Anda inginkan, selama Anda tidak mengubah, atau mengedit isinya dan format
digitalnya.
Sebenarnya, kami akan sangat senang bila Anda membuat duplikat buku elektronik ini sebanyak-
banyaknya. Tetapi bagaimanapun, hak untuk membuat buku dalam bentuk cetak atas naskah ini untuk
dijual adalah tindakan yang tidak dibenarkan.

Mais conteúdo relacionado

Mais procurados

Daya dukung pondasi dengan analisis terzaghi
Daya dukung pondasi dengan analisis terzaghiDaya dukung pondasi dengan analisis terzaghi
Daya dukung pondasi dengan analisis terzaghi
Ayu Fatimah Zahra
 
2. analisis tenaga alat berat
2. analisis tenaga alat berat2. analisis tenaga alat berat
2. analisis tenaga alat berat
Ahmad Wiratama
 
Barchart dan Penjadwalan proyek
Barchart dan Penjadwalan proyekBarchart dan Penjadwalan proyek
Barchart dan Penjadwalan proyek
Nurul Angreliany
 
Baja tulangan beton SNI 2052-2014
Baja tulangan beton SNI 2052-2014Baja tulangan beton SNI 2052-2014
Baja tulangan beton SNI 2052-2014
WSKT
 

Mais procurados (20)

SNI 2847-2013 Persyaratan Beton Struktural Untuk Bangunan Gedung
SNI 2847-2013 Persyaratan Beton Struktural Untuk Bangunan GedungSNI 2847-2013 Persyaratan Beton Struktural Untuk Bangunan Gedung
SNI 2847-2013 Persyaratan Beton Struktural Untuk Bangunan Gedung
 
Perhitungan dinding penahan tanah
Perhitungan dinding penahan tanahPerhitungan dinding penahan tanah
Perhitungan dinding penahan tanah
 
Daya dukung pondasi dengan analisis terzaghi
Daya dukung pondasi dengan analisis terzaghiDaya dukung pondasi dengan analisis terzaghi
Daya dukung pondasi dengan analisis terzaghi
 
Preliminary design kel. 3revisi
Preliminary design kel. 3revisiPreliminary design kel. 3revisi
Preliminary design kel. 3revisi
 
150509326 tabel-baja-profil-wf-pdf
150509326 tabel-baja-profil-wf-pdf150509326 tabel-baja-profil-wf-pdf
150509326 tabel-baja-profil-wf-pdf
 
perhitungan-atap
perhitungan-atapperhitungan-atap
perhitungan-atap
 
Tabel Profil Konstruksi Baja
Tabel Profil Konstruksi BajaTabel Profil Konstruksi Baja
Tabel Profil Konstruksi Baja
 
perhitungan bekisting
perhitungan bekistingperhitungan bekisting
perhitungan bekisting
 
2. analisis tenaga alat berat
2. analisis tenaga alat berat2. analisis tenaga alat berat
2. analisis tenaga alat berat
 
Tutorial perhitungan struktur dengan sap 2000 v
Tutorial perhitungan struktur dengan sap 2000 vTutorial perhitungan struktur dengan sap 2000 v
Tutorial perhitungan struktur dengan sap 2000 v
 
Klasifikasi tanah AASHTO DAN UNIFIED
Klasifikasi tanah AASHTO DAN UNIFIEDKlasifikasi tanah AASHTO DAN UNIFIED
Klasifikasi tanah AASHTO DAN UNIFIED
 
Perencanaan struktur kolom komposit
Perencanaan struktur kolom kompositPerencanaan struktur kolom komposit
Perencanaan struktur kolom komposit
 
Barchart dan Penjadwalan proyek
Barchart dan Penjadwalan proyekBarchart dan Penjadwalan proyek
Barchart dan Penjadwalan proyek
 
PERENCANAAN GEDUNG BETON BERTULANG TAHAN GEMPA
PERENCANAAN GEDUNG BETON BERTULANG TAHAN GEMPAPERENCANAAN GEDUNG BETON BERTULANG TAHAN GEMPA
PERENCANAAN GEDUNG BETON BERTULANG TAHAN GEMPA
 
Baja tulangan beton SNI 2052-2014
Baja tulangan beton SNI 2052-2014Baja tulangan beton SNI 2052-2014
Baja tulangan beton SNI 2052-2014
 
Pemadatan tanah
Pemadatan tanahPemadatan tanah
Pemadatan tanah
 
Perencanaan pondasi telapak persegi beton bertulang
Perencanaan pondasi telapak persegi beton bertulangPerencanaan pondasi telapak persegi beton bertulang
Perencanaan pondasi telapak persegi beton bertulang
 
Makalah perkerasan jalan
Makalah perkerasan jalan Makalah perkerasan jalan
Makalah perkerasan jalan
 
2007 07-pekerjaan tanah
2007 07-pekerjaan tanah2007 07-pekerjaan tanah
2007 07-pekerjaan tanah
 
penulangan kolom, balok dan plat bangunan gedung
penulangan kolom, balok dan plat bangunan gedungpenulangan kolom, balok dan plat bangunan gedung
penulangan kolom, balok dan plat bangunan gedung
 

Destaque

Eksentrisitas pada-pondasi
Eksentrisitas pada-pondasiEksentrisitas pada-pondasi
Eksentrisitas pada-pondasi
dwidam
 
53309952 utf-8-desain-struktur-beton-bertulang-dengan-sap2000
53309952 utf-8-desain-struktur-beton-bertulang-dengan-sap200053309952 utf-8-desain-struktur-beton-bertulang-dengan-sap2000
53309952 utf-8-desain-struktur-beton-bertulang-dengan-sap2000
Botak Doohan Jr
 
Bab ii-sistem-perletakan-dan-gaya-reaksi
Bab ii-sistem-perletakan-dan-gaya-reaksiBab ii-sistem-perletakan-dan-gaya-reaksi
Bab ii-sistem-perletakan-dan-gaya-reaksi
Masnia Siti
 
Peraturan bangunan 2006
Peraturan bangunan 2006Peraturan bangunan 2006
Peraturan bangunan 2006
herimul
 

Destaque (20)

Perhitungan rumah tinggal (beton1)
Perhitungan rumah tinggal (beton1)Perhitungan rumah tinggal (beton1)
Perhitungan rumah tinggal (beton1)
 
Perancangan dinding basement dg bantuan software etabs
Perancangan dinding basement dg bantuan software etabsPerancangan dinding basement dg bantuan software etabs
Perancangan dinding basement dg bantuan software etabs
 
Analisis struktur gedung bertingkat rendah dengan software etabs v9
Analisis struktur gedung bertingkat rendah dengan software etabs v9Analisis struktur gedung bertingkat rendah dengan software etabs v9
Analisis struktur gedung bertingkat rendah dengan software etabs v9
 
Desain dinding geser beton bertulang menggunakan software ETABS
Desain dinding geser beton bertulang menggunakan software ETABSDesain dinding geser beton bertulang menggunakan software ETABS
Desain dinding geser beton bertulang menggunakan software ETABS
 
Perancangan struktur beton perpustakaan 4 lantai
Perancangan struktur beton perpustakaan 4 lantaiPerancangan struktur beton perpustakaan 4 lantai
Perancangan struktur beton perpustakaan 4 lantai
 
Eksentrisitas pada-pondasi
Eksentrisitas pada-pondasiEksentrisitas pada-pondasi
Eksentrisitas pada-pondasi
 
Step by step desain kolom menggunakan software pca col
Step by step desain kolom menggunakan software pca colStep by step desain kolom menggunakan software pca col
Step by step desain kolom menggunakan software pca col
 
Auto select list pada etabs - afret nobel
Auto select list pada etabs - afret nobelAuto select list pada etabs - afret nobel
Auto select list pada etabs - afret nobel
 
Desain balok castellated
Desain balok castellatedDesain balok castellated
Desain balok castellated
 
Balok komposit vs balok biasa - afret nobel
Balok komposit vs balok biasa - afret nobelBalok komposit vs balok biasa - afret nobel
Balok komposit vs balok biasa - afret nobel
 
Diagram interaksi kolom beton menggunakan software PCA COL
Diagram interaksi kolom beton menggunakan software PCA COLDiagram interaksi kolom beton menggunakan software PCA COL
Diagram interaksi kolom beton menggunakan software PCA COL
 
53309952 utf-8-desain-struktur-beton-bertulang-dengan-sap2000
53309952 utf-8-desain-struktur-beton-bertulang-dengan-sap200053309952 utf-8-desain-struktur-beton-bertulang-dengan-sap2000
53309952 utf-8-desain-struktur-beton-bertulang-dengan-sap2000
 
Bab ii-sistem-perletakan-dan-gaya-reaksi
Bab ii-sistem-perletakan-dan-gaya-reaksiBab ii-sistem-perletakan-dan-gaya-reaksi
Bab ii-sistem-perletakan-dan-gaya-reaksi
 
Tahap tahap pembangunan gedung lima lantai
Tahap tahap pembangunan gedung lima lantaiTahap tahap pembangunan gedung lima lantai
Tahap tahap pembangunan gedung lima lantai
 
Laporan Struktur Rumah Tinggal
Laporan Struktur Rumah TinggalLaporan Struktur Rumah Tinggal
Laporan Struktur Rumah Tinggal
 
Buku ajar-analisa-struktur-i
Buku ajar-analisa-struktur-iBuku ajar-analisa-struktur-i
Buku ajar-analisa-struktur-i
 
beton pratekan
beton pratekanbeton pratekan
beton pratekan
 
Peraturan bangunan 2006
Peraturan bangunan 2006Peraturan bangunan 2006
Peraturan bangunan 2006
 
Activation Flyer
Activation FlyerActivation Flyer
Activation Flyer
 
Cosmic Energy Healing
Cosmic Energy HealingCosmic Energy Healing
Cosmic Energy Healing
 

Semelhante a Perencanaan gaya gaya pondasi pada bangunan gedung dengan 1 basement

File_Soal_17_158_29_1666928742 - Abdul Azis.pptx
File_Soal_17_158_29_1666928742 - Abdul Azis.pptxFile_Soal_17_158_29_1666928742 - Abdul Azis.pptx
File_Soal_17_158_29_1666928742 - Abdul Azis.pptx
HaniDul
 
File_Soal_17_158_29_1666928742 - Pelaksana Konstruksi Bangunan Unit Distribus...
File_Soal_17_158_29_1666928742 - Pelaksana Konstruksi Bangunan Unit Distribus...File_Soal_17_158_29_1666928742 - Pelaksana Konstruksi Bangunan Unit Distribus...
File_Soal_17_158_29_1666928742 - Pelaksana Konstruksi Bangunan Unit Distribus...
HaniDul
 
File_Soal_17_158_29_1666928742 - PPT Gedung EDI KURNIAWAN.pptx
File_Soal_17_158_29_1666928742 - PPT Gedung EDI KURNIAWAN.pptxFile_Soal_17_158_29_1666928742 - PPT Gedung EDI KURNIAWAN.pptx
File_Soal_17_158_29_1666928742 - PPT Gedung EDI KURNIAWAN.pptx
HaniDul
 
File_Soal_17_158_29_1666928742 - PPT Gedung HIMSAN.pptx
File_Soal_17_158_29_1666928742 - PPT Gedung HIMSAN.pptxFile_Soal_17_158_29_1666928742 - PPT Gedung HIMSAN.pptx
File_Soal_17_158_29_1666928742 - PPT Gedung HIMSAN.pptx
HaniDul
 
powerpointgedung-230319035554-9b4f284e.pptx
powerpointgedung-230319035554-9b4f284e.pptxpowerpointgedung-230319035554-9b4f284e.pptx
powerpointgedung-230319035554-9b4f284e.pptx
sugiyankurnia
 
699724443-Manajer-Pelaksana-Bangunan-Gedung-Jenjang-6.pdf
699724443-Manajer-Pelaksana-Bangunan-Gedung-Jenjang-6.pdf699724443-Manajer-Pelaksana-Bangunan-Gedung-Jenjang-6.pdf
699724443-Manajer-Pelaksana-Bangunan-Gedung-Jenjang-6.pdf
panduwinotobagus
 
Tugas_SRI_ARYATI_GEDUNG_J4[1] DFDFFDFFGVF
Tugas_SRI_ARYATI_GEDUNG_J4[1] DFDFFDFFGVFTugas_SRI_ARYATI_GEDUNG_J4[1] DFDFFDFFGVF
Tugas_SRI_ARYATI_GEDUNG_J4[1] DFDFFDFFGVF
SriAryati4
 

Semelhante a Perencanaan gaya gaya pondasi pada bangunan gedung dengan 1 basement (14)

File_Soal_17_158_29_1666928742 - Abdul Azis.pptx
File_Soal_17_158_29_1666928742 - Abdul Azis.pptxFile_Soal_17_158_29_1666928742 - Abdul Azis.pptx
File_Soal_17_158_29_1666928742 - Abdul Azis.pptx
 
File_Soal_17_158_29_1666928742 - Pelaksana Konstruksi Bangunan Unit Distribus...
File_Soal_17_158_29_1666928742 - Pelaksana Konstruksi Bangunan Unit Distribus...File_Soal_17_158_29_1666928742 - Pelaksana Konstruksi Bangunan Unit Distribus...
File_Soal_17_158_29_1666928742 - Pelaksana Konstruksi Bangunan Unit Distribus...
 
File_Soal_17_158_29_1666928742 - PPT Gedung EDI KURNIAWAN.pptx
File_Soal_17_158_29_1666928742 - PPT Gedung EDI KURNIAWAN.pptxFile_Soal_17_158_29_1666928742 - PPT Gedung EDI KURNIAWAN.pptx
File_Soal_17_158_29_1666928742 - PPT Gedung EDI KURNIAWAN.pptx
 
File_Soal_17_158_29_1666928742 - PPT Gedung HIMSAN.pptx
File_Soal_17_158_29_1666928742 - PPT Gedung HIMSAN.pptxFile_Soal_17_158_29_1666928742 - PPT Gedung HIMSAN.pptx
File_Soal_17_158_29_1666928742 - PPT Gedung HIMSAN.pptx
 
Bahan Uji PPT pelaksana Lapangan Gedung
Bahan Uji PPT pelaksana Lapangan  GedungBahan Uji PPT pelaksana Lapangan  Gedung
Bahan Uji PPT pelaksana Lapangan Gedung
 
powerpointgedung-230319035554-9b4f284e.pptx
powerpointgedung-230319035554-9b4f284e.pptxpowerpointgedung-230319035554-9b4f284e.pptx
powerpointgedung-230319035554-9b4f284e.pptx
 
powerpointgedung-230319035554-9b4f284e.pdf
powerpointgedung-230319035554-9b4f284e.pdfpowerpointgedung-230319035554-9b4f284e.pdf
powerpointgedung-230319035554-9b4f284e.pdf
 
POWER POINT gedung.pptx
POWER POINT gedung.pptxPOWER POINT gedung.pptx
POWER POINT gedung.pptx
 
Makalah metode pelaksanaan_konstruksi
Makalah metode pelaksanaan_konstruksiMakalah metode pelaksanaan_konstruksi
Makalah metode pelaksanaan_konstruksi
 
PELAKSANA LAPANGAN PEKERJAAN GEDUNG MAXI.pptx
PELAKSANA LAPANGAN PEKERJAAN GEDUNG MAXI.pptxPELAKSANA LAPANGAN PEKERJAAN GEDUNG MAXI.pptx
PELAKSANA LAPANGAN PEKERJAAN GEDUNG MAXI.pptx
 
699724443-Manajer-Pelaksana-Bangunan-Gedung-Jenjang-6.pdf
699724443-Manajer-Pelaksana-Bangunan-Gedung-Jenjang-6.pdf699724443-Manajer-Pelaksana-Bangunan-Gedung-Jenjang-6.pdf
699724443-Manajer-Pelaksana-Bangunan-Gedung-Jenjang-6.pdf
 
Presentasi Ferdi Yunianto - Jenjang5.pptx_1685070544 (1).pptx
Presentasi Ferdi Yunianto - Jenjang5.pptx_1685070544 (1).pptxPresentasi Ferdi Yunianto - Jenjang5.pptx_1685070544 (1).pptx
Presentasi Ferdi Yunianto - Jenjang5.pptx_1685070544 (1).pptx
 
Tugas_SRI_ARYATI_GEDUNG_J4[1] DFDFFDFFGVF
Tugas_SRI_ARYATI_GEDUNG_J4[1] DFDFFDFFGVFTugas_SRI_ARYATI_GEDUNG_J4[1] DFDFFDFFGVF
Tugas_SRI_ARYATI_GEDUNG_J4[1] DFDFFDFFGVF
 
Revisi_Ahli_muda_teknik_bangunan_gedung_jenjang_7_ABDURROHMANSYAH.pptx
Revisi_Ahli_muda_teknik_bangunan_gedung_jenjang_7_ABDURROHMANSYAH.pptxRevisi_Ahli_muda_teknik_bangunan_gedung_jenjang_7_ABDURROHMANSYAH.pptx
Revisi_Ahli_muda_teknik_bangunan_gedung_jenjang_7_ABDURROHMANSYAH.pptx
 

Mais de Afret Nobel (6)

Perhitungan sambungan lentur dan geser balok baja
Perhitungan sambungan lentur dan geser balok bajaPerhitungan sambungan lentur dan geser balok baja
Perhitungan sambungan lentur dan geser balok baja
 
Perancangan struktur kuda kuda baja tipe gable
Perancangan struktur kuda kuda baja tipe gablePerancangan struktur kuda kuda baja tipe gable
Perancangan struktur kuda kuda baja tipe gable
 
Cek penampang kolom baja gable
Cek penampang kolom baja gableCek penampang kolom baja gable
Cek penampang kolom baja gable
 
Cek penampang balok rafter baja gable
Cek penampang balok rafter baja gableCek penampang balok rafter baja gable
Cek penampang balok rafter baja gable
 
10 langkah cek tegangan pondasi tiang menggunakan software safe 12
10 langkah cek tegangan pondasi tiang menggunakan software safe 1210 langkah cek tegangan pondasi tiang menggunakan software safe 12
10 langkah cek tegangan pondasi tiang menggunakan software safe 12
 
6 formula jitu nge cad secepat kilat
6 formula jitu nge cad secepat kilat6 formula jitu nge cad secepat kilat
6 formula jitu nge cad secepat kilat
 

Último

Kenakalan Remaja (Penggunaan Narkoba).ppt
Kenakalan Remaja (Penggunaan Narkoba).pptKenakalan Remaja (Penggunaan Narkoba).ppt
Kenakalan Remaja (Penggunaan Narkoba).ppt
novibernadina
 
KISI-KISI SOAL DAN KARTU SOAL BAHASA INGGRIS.docx
KISI-KISI SOAL DAN KARTU SOAL BAHASA INGGRIS.docxKISI-KISI SOAL DAN KARTU SOAL BAHASA INGGRIS.docx
KISI-KISI SOAL DAN KARTU SOAL BAHASA INGGRIS.docx
DewiUmbar
 
PPT SOSIALISASI PENGELOLAAN KINERJA GURU DAN KS 2024.pptx
PPT SOSIALISASI PENGELOLAAN KINERJA GURU DAN KS 2024.pptxPPT SOSIALISASI PENGELOLAAN KINERJA GURU DAN KS 2024.pptx
PPT SOSIALISASI PENGELOLAAN KINERJA GURU DAN KS 2024.pptx
MaskuratulMunawaroh
 

Último (20)

MODUL PENDIDIKAN PANCASILA KELAS 6 KURIKULUM MERDEKA.pdf
MODUL PENDIDIKAN PANCASILA KELAS 6 KURIKULUM MERDEKA.pdfMODUL PENDIDIKAN PANCASILA KELAS 6 KURIKULUM MERDEKA.pdf
MODUL PENDIDIKAN PANCASILA KELAS 6 KURIKULUM MERDEKA.pdf
 
AKSI NYATA Numerasi Meningkatkan Kompetensi Murid_compressed (1) (1).pptx
AKSI NYATA  Numerasi  Meningkatkan Kompetensi Murid_compressed (1) (1).pptxAKSI NYATA  Numerasi  Meningkatkan Kompetensi Murid_compressed (1) (1).pptx
AKSI NYATA Numerasi Meningkatkan Kompetensi Murid_compressed (1) (1).pptx
 
Memperkasakan Dialog Prestasi Sekolah.pptx
Memperkasakan Dialog Prestasi Sekolah.pptxMemperkasakan Dialog Prestasi Sekolah.pptx
Memperkasakan Dialog Prestasi Sekolah.pptx
 
Penyebaran Pemahaman Merdeka Belajar Aksi Nyata PMM
Penyebaran Pemahaman Merdeka Belajar Aksi Nyata PMMPenyebaran Pemahaman Merdeka Belajar Aksi Nyata PMM
Penyebaran Pemahaman Merdeka Belajar Aksi Nyata PMM
 
Aksi Nyata Menyebarkan (Pemahaman Mengapa Kurikulum Perlu Berubah) Oleh Nur A...
Aksi Nyata Menyebarkan (Pemahaman Mengapa Kurikulum Perlu Berubah) Oleh Nur A...Aksi Nyata Menyebarkan (Pemahaman Mengapa Kurikulum Perlu Berubah) Oleh Nur A...
Aksi Nyata Menyebarkan (Pemahaman Mengapa Kurikulum Perlu Berubah) Oleh Nur A...
 
BAHAN PAPARAN UU DESA NOMOR 3 TAHUN 2024
BAHAN PAPARAN UU DESA NOMOR 3 TAHUN 2024BAHAN PAPARAN UU DESA NOMOR 3 TAHUN 2024
BAHAN PAPARAN UU DESA NOMOR 3 TAHUN 2024
 
Kenakalan Remaja (Penggunaan Narkoba).ppt
Kenakalan Remaja (Penggunaan Narkoba).pptKenakalan Remaja (Penggunaan Narkoba).ppt
Kenakalan Remaja (Penggunaan Narkoba).ppt
 
KISI-KISI SOAL DAN KARTU SOAL BAHASA INGGRIS.docx
KISI-KISI SOAL DAN KARTU SOAL BAHASA INGGRIS.docxKISI-KISI SOAL DAN KARTU SOAL BAHASA INGGRIS.docx
KISI-KISI SOAL DAN KARTU SOAL BAHASA INGGRIS.docx
 
Prakarsa Perubahan dan kanvas ATAP (1).pptx
Prakarsa Perubahan dan kanvas ATAP (1).pptxPrakarsa Perubahan dan kanvas ATAP (1).pptx
Prakarsa Perubahan dan kanvas ATAP (1).pptx
 
Prov.Jabar_1504_Pengumuman Seleksi Tahap 2_CGP A11 (2).pdf
Prov.Jabar_1504_Pengumuman Seleksi Tahap 2_CGP A11 (2).pdfProv.Jabar_1504_Pengumuman Seleksi Tahap 2_CGP A11 (2).pdf
Prov.Jabar_1504_Pengumuman Seleksi Tahap 2_CGP A11 (2).pdf
 
TUGAS RUANG KOLABORASI 1.3 PRAKARSA PERUBAHAN
TUGAS RUANG KOLABORASI 1.3 PRAKARSA PERUBAHANTUGAS RUANG KOLABORASI 1.3 PRAKARSA PERUBAHAN
TUGAS RUANG KOLABORASI 1.3 PRAKARSA PERUBAHAN
 
DEMONSTRASI KONTEKSTUAL MODUL 1.3 CGP 10.pptx
DEMONSTRASI KONTEKSTUAL MODUL 1.3 CGP 10.pptxDEMONSTRASI KONTEKSTUAL MODUL 1.3 CGP 10.pptx
DEMONSTRASI KONTEKSTUAL MODUL 1.3 CGP 10.pptx
 
MODUL AJAR BAHASA INGGRIS KELAS 6 KURIKULUM MERDEKA.pdf
MODUL AJAR BAHASA INGGRIS KELAS 6 KURIKULUM MERDEKA.pdfMODUL AJAR BAHASA INGGRIS KELAS 6 KURIKULUM MERDEKA.pdf
MODUL AJAR BAHASA INGGRIS KELAS 6 KURIKULUM MERDEKA.pdf
 
Topik 4_Eksplorasi Konsep LK Kelompok_Pendidikan Berkelanjutan
Topik 4_Eksplorasi Konsep LK Kelompok_Pendidikan BerkelanjutanTopik 4_Eksplorasi Konsep LK Kelompok_Pendidikan Berkelanjutan
Topik 4_Eksplorasi Konsep LK Kelompok_Pendidikan Berkelanjutan
 
Bab 4 Persatuan dan Kesatuan di Lingkup Wilayah Kabupaten dan Kota.pptx
Bab 4 Persatuan dan Kesatuan di Lingkup Wilayah Kabupaten dan Kota.pptxBab 4 Persatuan dan Kesatuan di Lingkup Wilayah Kabupaten dan Kota.pptx
Bab 4 Persatuan dan Kesatuan di Lingkup Wilayah Kabupaten dan Kota.pptx
 
MODUL AJAR MATEMATIKA KELAS 3 KURIKULUM MERDEKA.pdf
MODUL AJAR MATEMATIKA KELAS 3 KURIKULUM MERDEKA.pdfMODUL AJAR MATEMATIKA KELAS 3 KURIKULUM MERDEKA.pdf
MODUL AJAR MATEMATIKA KELAS 3 KURIKULUM MERDEKA.pdf
 
PPT MODUL 6 DAN 7 PDGK4105 KELOMPOK.pptx
PPT MODUL 6 DAN 7 PDGK4105 KELOMPOK.pptxPPT MODUL 6 DAN 7 PDGK4105 KELOMPOK.pptx
PPT MODUL 6 DAN 7 PDGK4105 KELOMPOK.pptx
 
PPT SOSIALISASI PENGELOLAAN KINERJA GURU DAN KS 2024.pptx
PPT SOSIALISASI PENGELOLAAN KINERJA GURU DAN KS 2024.pptxPPT SOSIALISASI PENGELOLAAN KINERJA GURU DAN KS 2024.pptx
PPT SOSIALISASI PENGELOLAAN KINERJA GURU DAN KS 2024.pptx
 
power point bahasa indonesia "Karya Ilmiah"
power point bahasa indonesia "Karya Ilmiah"power point bahasa indonesia "Karya Ilmiah"
power point bahasa indonesia "Karya Ilmiah"
 
OPTIMALISASI KOMUNITAS BELAJAR DI SEKOLAH.pptx
OPTIMALISASI KOMUNITAS BELAJAR DI SEKOLAH.pptxOPTIMALISASI KOMUNITAS BELAJAR DI SEKOLAH.pptx
OPTIMALISASI KOMUNITAS BELAJAR DI SEKOLAH.pptx
 

Perencanaan gaya gaya pondasi pada bangunan gedung dengan 1 basement

  • 1. Perencanaan Gaya-gaya Pondasi pada Bangunan Gedung dengan 1 Basement Made based on experience as Structural Engineer 29-Aug-14 Tutorial Structural Engineer Afret Nobel, ST & Yudhistira Achmad, ST
  • 2. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 2 Table of ContentsTable of ContentsTable of ContentsTable of Contents 1 PRAKATA ........................................................................................................................... 3 2 PEMBATASAN MASALAH....................................................................................................... 4 3 PENDAHULUAN ................................................................................................................... 5 3.1 File Struktur Atas.......................................................................................................... 7 3.2 File Struktur Total ......................................................................................................... 8 3.3 File Struktur Bawah....................................................................................................... 9 4 PROSEDUR PERENCANAAN................................................................................................. 10 4.1 Perencanaan Struktur Total.......................................................................................... 10 4.1.1 Langkah-langkah memodelkan struktur total:........................................................... 10 4.2 Perencanaan Struktur Bawah........................................................................................ 18 4.2.1 Langkah-langkahnya memodelkan struktur bawah:................................................... 19 4.3 Resume Support Reaction ............................................................................................ 24 5 KESIMPULAN .................................................................................................................... 26 6 PROFIL PENULIS ..............................................................................................................27s
  • 3. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 3 1 PRAKATA Ebook ini adalah ebook gratis yang proses mendapatkannya memerlukan upaya dan keberanian untuk bertindak. Banyak orang yang membaca publikasi tentang gratisnya ebook ini tapi tetap tak bertindak, bisa jadi karena: • Ragu, “Masa sih hari gini ada ebook yang dibagi gratis?”. • Menunda, “Nanti aja ahh, toh gratis.” • Putus asa, “Kok susah amat sih mau dapat yang gratisan!” • Pikiran Kotor, “Paling ebooknya hanya untuk promosi blognya saja.” • Atau alasan-alasan lainnya... Bagi Anda yang berhasil mendapatkan ebook ini, berarti Anda bukan bagian dari orang-orang diatas. Maka dari itu, kami berani mengatakan, “Anda adalah orang-orang hebat”.
  • 4. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 4 Bacalah dengan teliti!... Karena kami menulisnya juga dengan teliti, artinya banyak pesan tersembunyi (ilmu) yang baru akan Anda pahami saat Anda baca berulang. Lagipula materi yang kami sampaikan bukanlah bahan bacaan, tapi adalah bahan praktik. Anda akan lebih mengerti jika membaca dan mempraktekkannya. (Pembukaan by @JayaYEA dengan editan seperlunya) 2 PEMBATASAN MASALAH • Pemodelan yang kami lakukan di sini merupakan hasil dari pengalaman kami sebagai Structural Engineer di konsultan. Anda bisa saja menggunakan cara Anda sendiri jika Anda sudah tahu prinsipnya. • Pemodelan dilakukan 3 Dimensi menggunakan program Etabs • Bangunan yang digunakan sebagai contoh merupakan bangunan 4 lantai dengan 1 basement.
  • 5. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 5 • Perencanaan dilakukan secara berurutan, mulai dari struktur atas, struktur total, dan struktur bawah. 3 PENDAHULUAN • Basement adalah lantai bangunan sebagian atau seluruhnya yang terletak di bawah permukaan tanah. Basement biasanya digunakan sebagai tempat parkir kendaraan dan meletakkan peralatan mekanikal/elektrikal seperti: Water Threatment Plan, Sewage Threatment Plan, dll • Merencanakan gaya-gaya pondasi merupakan langkah pekerjaan yang harus Anda lakukan sebelum merencanakan pondasi • Karena fungsi pondasi pada bangunan yang sangat vital, perencanaan gaya-gaya pada pondasi harus benar-benar dilakukan dengan cermat dan teliti • Gaya-gaya pondasi tidak sama persis dengan reaksi perletakan. Perbedaannya terletak pada arah kerja momen. Karena untuk merencanakan pondasi, reaksi yang terjadi merupakan Aksi pada pondasi
  • 6. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 6 • Struktur atas adalah struktur yang berada di atas permukaan tanah, sedangkan struktur bawah adalah struktur yang berada di bawah permukaan tanah. • Perencanaan gaya-gaya pondasi pada bangunan dengan 1 basement bisa Anda lakukan dengan cara memisah struktur atas dan struktur bawah. • Ada 3 file yang saling terkait dan harus Anda buat dalam program Etabs untuk merencanakan gaya-gaya pondasi, yaitu: 1. File Model Struktur Atas 2. File Model Struktur Total (File Struktur Atas + Lantai di bawah muka tanah) 3. File Model Struktur Bawah (Tie Beam + Pelat Basement) www.LaporanTeknikSipil.wordpress.com
  • 7. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 7 1. File Model Struktur Atas 2. File Model Struktur Total 3. File Model Struktur Bawah 3.1 File Struktur Atas • File model struktur atas adalah file yang harus Anda buat pertama kali dalam pemodelan • Mulai dari pembebanan, mode, drift dan persyaratan lainnya harus benar-benar fix di sini • Kami tidak akan menjelaskan secara rinci mengenai perencanaan struktur atas karena sudah pernah kami bahas pada ebook dengan judul ”ANALISIS STRUKTUR GEDUNG BERTINGKAT RENDAH DENGAN SOFTWARE ETABS V9”
  • 8. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 8 3.2 File Struktur Total • File struktur total merupakan penggabungan antara file struktur atas dengan lantai terbawah • Beban-beban yang bekerja pada struktur total adalah sama dengan beban pada struktur atas, kecuali beban gempa. • Menurut peraturan, gaya gempa pada struktur bagian bawah dan pondasi harus lebih besar dari pada gaya gempa struktur di atasnya. • Hal ini dilakukan untuk menjamin bahwa struktur bawah tidak runtuh terlebih dahulu sebelum struktur atas. • File struktur total digunakan untuk mengeluarkan reaksi perletakan dan mendesain struktur di bawah tanah saja.
  • 9. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 9 3.3 File Struktur Bawah • Struktur bawah terdiri dari tie beam dan pelat basement. • Pembebanan yang bekerja pada struktur bawah adalah beban mati, bebah hidup, dan beban Uplift. • Untuk keamanan, beban uplift boleh Anda ambil setinggi muka air banjir atau setinggi lantai basement. Misalkan Tinggi air 2 meter maka beban uplift = (h x bj. air) – (tebal pelat basement x bj. Beton)= 2 m x 1000 kg/m3 + 0.25 m x 2400 kg/m3 = 1400 kg/m2 • Beban mati dan beban hidup bekerja secara gravitasi, sedangkan beban uplift bekerja sebaliknya. Input beban mati dan beban hidup sesuai layout dan fungsi lantai. • Tidak ada momen yang terjadi pada perletakan struktur bawah, oleh karena itu perletakannya Anda modelkan sebagai sendi (pin).
  • 10. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 10 4 PROSEDUR PERENCANAAN 4.1 Perencanaan Struktur Total <<<File Struktur Total 4.1.1 Langkah-langkah memodelkan struktur total: 1. Save as Struktur Atas dan beri nama file >> Struktur Total 2. Tambahkan story pada bagian paling bawah model Anda! (jika tipikal dengan lantai di atasnya, cukup dicopy-kan saja)
  • 11. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 11 3. Masukkan pembebanan pada lantai ground sesuai layout dan fungsi lantai 4. Beri diapragma pada lantai ground Anda sama seperti pada lantai lainnya untuk memasukkan beban gempa 5. Update beban gempa bangunan Anda menjadi beban gempa untuk struktur total Story x y x y STORY4 28,809 26,465 43,214 39,698 STORY3 22,676 19,709 34,014 29,563 STORY2 15,615 13,529 23,423 20,294 STORY1 7,393 6,554 11,089 9,831 GROUND 18,227 18,227 Fi Struktur Atas Fi Total Struktur Total <<< Input Beban Gempa Fi = Gaya gempa pada STRUKTUR ATAS Fi Total = Gaya gempa pada STRUKTUR TOTAL = (Gaya gempa pada STRUKTUR ATAS x Faktor Kuat Lebih sesuai nilai R yang digunakan)
  • 12. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 12 6. Gaya gempa yang digunakan pada struktur total Anda adalah Fi Total 7. Gaya gempa pada lantai Ground dihitung sebagai berikut: Gaya Gempa Pada Struktur Bawah Lantai Massa Lantai G Reduksi Wb Fb (Kg) (m / det2) (Kg) (Kg) Base 23,023 9.8065 0.3 225,776 18,227 Fp = 0.133 * Sds * I * Wb = 0.133 * 0.607 * 1.00 *225,776 = 18,227 Kg Fp = Beban gempa horisontal terpusat Sds = Parameter respon spektra percepatan desain pada periode pendek I = Faktor Keutamaan
  • 13. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 13 Wb = Berat lantai 8. Sebelum melakukan Run Analysis, lakukan check model terlebih dahulu. 9. Jika terjadi error maka perbaiki errornya, lihat caranya pada ebook dengan judul “Solving Warning Pada Etabs – Afret Nobel & Muhammad Faisal” 10. Show table > Support Reaction 11. Tabelkan output-output sebagai berikut: www.LaporanTeknikSipil.wordpress.com
  • 14. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 14 Support Reaction Dead Load (kg.m) Story Point Load FX FY FZ MX MY MZ BASE 5 DEAD 4371 -4558 45947 672 1668 0 BASE 6 DEAD 1591 -2439 50192 130 1568 0 BASE 8 DEAD 1591 2439 50192 -130 1568 0 BASE 9 DEAD 4371 4558 45947 -672 1668 0 BASE 10 DEAD 1242 629 62419 -624 -370 0 BASE 11 DEAD 20 45 63716 -44 19 0 BASE 12 DEAD 20 -45 63716 44 19 0 BASE 13 DEAD 1242 -629 62419 624 -370 0 BASE 14 DEAD -1242 -629 62419 624 370 0 BASE 15 DEAD -20 -45 63716 44 -19 0 BASE 16 DEAD -20 45 63716 -44 -19 0 BASE 17 DEAD -1242 629 62419 -624 370 0 BASE 18 DEAD -4371 -4558 45947 672 -1668 0 BASE 19 DEAD -1591 -2439 50192 130 -1568 0 BASE 20 DEAD -1591 2439 50192 -130 -1568 0 BASE 21 DEAD -4371 4558 45947 -672 -1668 0
  • 15. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 15 Support Reaction Live Load (kg.m) Story Point Load FX FY FZ MX MY MZ BASE 5 LIVE 1,336 -1,632 9,050 259 523 0 BASE 6 LIVE 854 -1,274 13,659 106 841 0 BASE 8 LIVE 854 1,178 13,622 -80 841 0 BASE 9 LIVE 1,412 1,584 9,053 -247 526 0 BASE 10 LIVE 733 337 14,945 -334 -101 0 BASE 11 LIVE 2 21 29,812 -20 2 0 BASE 12 LIVE -5 -21 29,751 21 -4 0 BASE 13 LIVE 1,103 -342 15,250 340 -139 0 BASE 14 LIVE -42 -436 19,230 433 498 0 BASE 15 LIVE 287 -26 38,838 25 279 0 BASE 16 LIVE 140 80 34,427 -78 137 0 BASE 17 LIVE -763 339 14,899 -335 103 0 BASE 18 LIVE -1,952 -2,659 14,425 429 -887 0 BASE 19 LIVE -1,374 -1,478 21,249 116 -1,350 0 BASE 20 LIVE -1,130 2,290 18,252 -256 -1,116 0 BASE 21 LIVE -1,454 2,037 9,538 -265 -526 0
  • 16. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 16 Support Reaction EQX Load (kg.m) Story Point Load FX FY FZ MX MY MZ BASE 5 EQX -12,359 351 -29,452 -191 5,072 -16 BASE 6 EQX 6,813 -2,200 -17,441 90 6,449 0 BASE 8 EQX 6,562 -43 -17,110 -121 6,215 0 BASE 9 EQX -11,644 -855 -31,168 -400 4,333 14 BASE 10 EQX -30,185 200 -2,265 -189 747 0 BASE 11 EQX 4,207 135 1,042 -131 4,049 0 BASE 12 EQX 4,378 135 1,041 -130 4,215 0 BASE 13 EQX -32,756 198 -839 -187 1,189 0 BASE 14 EQX -32,756 -198 839 187 1,189 0 BASE 15 EQX 4,378 -135 -1,041 130 4,215 0 BASE 16 EQX 4,207 -135 -1,042 131 4,049 0 BASE 17 EQX -30,185 -200 2,265 189 747 0 BASE 18 EQX -12,359 -351 29,452 191 5,072 -16 BASE 19 EQX 6,813 2,200 17,441 -90 6,449 0 BASE 20 EQX 6,562 43 17,110 121 6,215 0 BASE 21 EQX -11,644 855 31,168 400 4,333 14
  • 17. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 17 Support Reaction EQY Load (kg.m) Story Point Load FX FY FZ MX MY MZ BASE 5 EQY 607 -11,398 37,760 -885 -506 -20 BASE 6 EQY -178 -27,676 4,157 3,928 -166 -1 BASE 8 EQY 178 -27,676 -4,157 3,928 166 -1 BASE 9 EQY -607 -11,398 -37,760 -885 506 -20 BASE 10 EQY 241 6,755 -22,217 -6,210 300 -1 BASE 11 EQY 121 4,413 804 -4,231 117 -1 BASE 12 EQY -121 4,413 -804 -4,231 -117 -1 BASE 13 EQY -241 6,755 22,217 -6,210 -300 -1 BASE 14 EQY 3,913 7,316 24,243 -6,740 -316 -1 BASE 15 EQY -121 4,793 -806 -4,598 -117 -1 BASE 16 EQY 121 4,793 806 -4,598 117 -1 BASE 17 EQY -3,913 7,316 -24,243 -6,740 316 -1 BASE 18 EQY 420 -12,129 40,200 -1,714 -532 22 BASE 19 EQY -176 -30,880 3,688 3,894 -164 -1 BASE 20 EQY 176 -30,880 -3,688 3,894 164 -1 BASE 21 EQY -420 -12,129 -40,200 -1,714 532 22
  • 18. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 18 4.2 Perencanaan Struktur Bawah 3 dimensi struktur bawah Menunjukkan perletakan
  • 19. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 19 4.2.1 Langkah-langkahnya memodelkan struktur bawah: 1. Save as file Struktur Total dan beri nama file >> Struktur Bawah 2. Delete semua lantai dan sisakan hanya lantai terbawah. Pada contoh ini adalah Lantai Ground. Karena lantai basement yang kami buat adalah tipikal dengan lantai ground 3. Hapus semua kolom dan beri perletakan sendi pada titik joint kolom tersebut 4. Usahakan untuk membuat lantai basement di atas grid base, agar tidak ada perletakan yang tumbuh secara otomatis 5. Masukkan pembebanan pada basement berupa Dead Load, Live Load, dan Uplift (jika ada) 6. Masukkan dinding basement sebagai beban pada balok di bawahnya 7. Desain dinding basement dilakukan secara terpisah dengan pembebanan sederhana. Pelajari caranya pada ebook dengan judul “Perancangan Dinding Basement dg Bantuan Software Etabs - Afret Nobel” 8. Hapus semua properti gaya gempa pada file ini karena Anda tidak membutuhkannya 9. Sebelum melakukan Run Analysis, lakukan check model terlebih dahulu.
  • 20. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 20 10. Jika terjadi error maka perbaiki errornya terlebih dahulu, lihat caranya pada ebook dengan judul “Solving Warning Pada Etabs – Afret Nobel & Muhammad Faisal” 11. Show table > Support Reaction 12. Tabelkan output-output sebagai berikut: KATA-KATA PENTING: 1. Salah merencanakan = merencanakan yang salah 2. Software hanyalah software, jika yang Anda masukkan sampah maka yang keluar juga sampah 3. Engineering judgement sangat diperlukan dalam hal ini 4. Kritik dan saran yang membangun sangat kami butuhkan demi penyempurnaan tulisan ini dimasa mendatang 5. Structural Engineer more as an ART than SCIENE 6. Semua ebook yang menjadi rujukan pada pembahasan ini bisa Anda download di sini! http://www.LaporanTeknikSipil.Wordpress.com
  • 21. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 21 Support Reaction Dead Load (kg.m) Story Point Load FX FY FZ MX MY MZ UG 5 DEAD 0 0 4,076 0 0 0 UG 6 DEAD 0 0 6,754 0 0 0 UG 8 DEAD 0 0 6,754 0 0 0 UG 9 DEAD 0 0 4,076 0 0 0 UG 10 DEAD 0 0 8,688 0 0 0 UG 11 DEAD 0 0 11,514 0 0 0 UG 12 DEAD 0 0 11,514 0 0 0 UG 13 DEAD 0 0 8,688 0 0 0 UG 14 DEAD 0 0 8,688 0 0 0 UG 15 DEAD 0 0 11,514 0 0 0 UG 16 DEAD 0 0 11,514 0 0 0 UG 17 DEAD 0 0 8,688 0 0 0 UG 18 DEAD 0 0 4,076 0 0 0 UG 19 DEAD 0 0 6,754 0 0 0 UG 20 DEAD 0 0 6,754 0 0 0 UG 21 DEAD 0 0 4,076 0 0 0
  • 22. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 22 Support Reaction Live Load (kg.m) Story Point Load FX FY FZ MX MY MZ UG 5 LIVE 0 0 1,796 0 0 0 UG 6 LIVE 0 0 4,232 0 0 0 UG 8 LIVE 0 0 4,232 0 0 0 UG 9 LIVE 0 0 1,796 0 0 0 UG 10 LIVE 0 0 4,805 0 0 0 UG 11 LIVE 0 0 10,768 0 0 0 UG 12 LIVE 0 0 10,768 0 0 0 UG 13 LIVE 0 0 4,805 0 0 0 UG 14 LIVE 0 0 4,805 0 0 0 UG 15 LIVE 0 0 10,768 0 0 0 UG 16 LIVE 0 0 10,768 0 0 0 UG 17 LIVE 0 0 4,805 0 0 0 UG 18 LIVE 0 0 1,796 0 0 0 UG 19 LIVE 0 0 4,232 0 0 0 UG 20 LIVE 0 0 4,232 0 0 0 UG 21 LIVE 0 0 1,796 0 0 0
  • 23. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 23 Support Reaction Uplift (kg.m) Story Point Load FX FY FZ MX MY MZ UG 5 UPLIFT 0 0 -4,489 0 0 0 UG 6 UPLIFT 0 0 -10,580 0 0 0 UG 8 UPLIFT 0 0 -10,580 0 0 0 UG 9 UPLIFT 0 0 -4,489 0 0 0 UG 10 UPLIFT 0 0 -12,012 0 0 0 UG 11 UPLIFT 0 0 -26,919 0 0 0 UG 12 UPLIFT 0 0 -26,919 0 0 0 UG 13 UPLIFT 0 0 -12,012 0 0 0 UG 14 UPLIFT 0 0 -12,012 0 0 0 UG 15 UPLIFT 0 0 -26,919 0 0 0 UG 16 UPLIFT 0 0 -26,919 0 0 0 UG 17 UPLIFT 0 0 -12,012 0 0 0 UG 18 UPLIFT 0 0 -4,489 0 0 0 UG 19 UPLIFT 0 0 -10,580 0 0 0 UG 20 UPLIFT 0 0 -10,580 0 0 0 UG 21 UPLIFT 0 0 -4,489 0 0 0
  • 24. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 24 4.3 Resume Support Reaction Resume Support Reaction UPLIFT N Mxx Myy N Mxx Myy N N Mxx Myy N Mxx Myy (TON) (KGM) (KGM) (TON) (KGM) (KGM) (TON) (TON) (KGM) (KGM) (TON) (KGM) (KGM) 5 BASE 50 -672 -1,668 3 -259 -523 -4 -29 191 -5,072 -1 506 20 6 BASE 57 -130 -1,568 5 -106 -841 -11 -17 -90 -6,449 4 166 1 8 BASE 57 130 -1,568 5 80 -841 -11 -17 121 -6,215 4 -166 1 9 BASE 50 672 -1,668 3 247 -526 -4 -31 400 -4,333 -1 -506 20 10 BASE 71 624 370 6 334 101 -12 -2 189 -747 -6 -300 1 11 BASE 75 44 -19 11 20 -2 -27 1 131 -4,049 -4 -117 1 12 BASE 75 -44 -19 11 -21 4 -27 1 130 -4,215 -4 117 1 13 BASE 71 -624 370 6 -340 139 -12 -1 187 -1,189 -6 300 1 14 BASE 71 -624 -370 5 -433 -498 -12 1 -187 -1,189 -7 316 1 15 BASE 75 -44 19 11 -25 -279 -27 -1 -130 -4,215 -5 117 1 16 BASE 75 44 19 11 78 -137 -27 -1 -131 -4,049 -5 -117 1 17 BASE 71 624 -370 4 335 -103 -12 2 -189 -747 -7 -316 1 18 BASE 50 -672 1,668 0 -429 887 -4 29 -191 -5,072 -2 532 -22 19 BASE 57 -130 1,568 3 -116 1,350 -11 17 90 -6,449 4 164 1 20 BASE 57 130 1,568 3 256 1,116 -11 17 -121 -6,215 4 -164 1 21 BASE 50 672 1,668 0 265 526 -4 31 -400 -4,333 -2 -532 -22 NO ETABS STORY DEAD LOAD LIVE LOAD GEMPA ARAH - X GEMPA ARAH - Y
  • 25. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 25 Titik-titik perletakan
  • 26. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 26 5 KESIMPULAN 1. Dead load = Dead Load Struktur Atas + Dead Load Struktur Bawah 2. Live Load = Live Load Struktur Atas + Live Load Struktur Bawah 3. Eqx dan Eqy = reaksi perletakan akibat beban gempa struktur total 4. Uplift = reaksi perletakan akibat Uplift dari struktur bawah 5. Arah gaya momen dibalik Dari reaksi menjadi aksi, dari positive+ menjadi negative- 6. Gaya -gaya perletakan yang diperoleh pada perhitungan di atas adalah gaya yang akan digunakan sebagai acuan dalam merencanakan pondasi. 7. Panduan merencanakan pondasi tiang pancang dapat Anda pelajari pada ebook dengan judul “Perhitungan Reaksi Tiang Pondasi dengan Kombinasi Pembebanan SNI 1726 - 2012 & SAFE 12” 8. Pada setiap program perhitungan struktur akan memiliki perjanjian arah, dan jangan sampai salah dalam pembacaan output, (ada local axes dan ada global axes).
  • 27. [PERENCANAAN GAYA-GAYA PONDASI PADA BANGUNAN GEDUNG DENGAN 1 BASEMENT] August 29, 2014 Tutorial Structural Engineer | https://www.facebook.com/afretnobel | https://www.facebook.com/yudhistiraachmad 27 9. File save as digunakan agar nomor point kolom tetap konsisten untuk memudahkan pengolahan output dengan tabel excel 6 PROFIL PENULIS Afret Nobel adalah alumni Diploma Teknik Sipil Universitas Gadjah Mada Angkatan 2005 dan Alumni Ekstensi Teknik Sipil Universitas Indonesia Angkatan 2009. Papanya seorang petani dan Mamanya pedagang. Founder at www.NobelConsultant.com Yudhistira Achmad alumni Diploma Teknik Sipil Universitas Gadjah Mada Angkatan 2008 dan Alumni Ekstensi Teknik Sipil Universitas Indonesia Angkatan 2011. Papanya udah diatas sana dan Mama nya seorang pedagang. Anda diperbolehkan untuk mengirimkan lewat pos dan email dan memberikan buku elektronik ini kepada siapa saja yang Anda inginkan, selama Anda tidak mengubah, atau mengedit isinya dan format digitalnya. Sebenarnya, kami akan sangat senang bila Anda membuat duplikat buku elektronik ini sebanyak- banyaknya. Tetapi bagaimanapun, hak untuk membuat buku dalam bentuk cetak atas naskah ini untuk dijual adalah tindakan yang tidak dibenarkan.