SlideShare uma empresa Scribd logo
1 de 15
Adam Goodin
Fossil Hydro Operations
Co-op Development Program
August 13, 2015
About Me
■ University of Kentucky
– Senior
– Civil Engineering
– Graduation: 8/16
■ 3rd Rotation with Duke
– Woodsdale (Spring 14)
– Plainfield (Fall 14)
– Gibson Station (Current)
■ Gibson Station, Capital Group
– Mentor: Mick Harpenau
My Safety Moment
■ Participated in Sitewide Safety Stand-down
– Walkdown with experienced Duke and Contractor
Management with the sole purpose of eliminating
hazards in the workplace
■ Looked for technical malfunctions
– Deteriorating grounding equipment
– Broken/corroded conduit
■ Housekeeping
– Ladders in isleway
– Stray pieces of wood and metal could become falling
object
Responsibilities this Rotation
■ Document Control on Unit 5 FGD Structural Refurbishment
– Maintained IFC Drawings and updated for revisions
– Provided Field Support
■ U5 Mercury Re-emission project
– Developed P&IDs
– Created Valve Lists and Valve Numbers
■ Involved in fall outage coordination meetings
– Logistics of large scale project
– Schedule formed, laydown areas designated, scope of work
Dry Bottom Ash Conversion
■ Support Engineering Efforts on the recently
initiated Dry Bottom Ash Conversion Project
– April 2015 EPA Ruling
– Gibson to adopt a Continuous Dewatering and
Recirculation (CDR) System
– Locate Existing Underground Drawings
– Obtain Existing Area General Arrangement (GA’s)
Drawings
– Layout Route for new Sanitation System piping
Dry Bottom Ash Conversion (Cont.)
– Locate Existing Sanitation System Drawings for
locating tie points
– Layout new Sanitation System GA’s,
■ Effluent Guidelines
– Review EPA’s proposed rules
– Gained Consensus on liner requirements as they
pertain to the DBA design
■ Researched and scoped out equipment for installation of a Water
Table Monitoring System
ELG & CCR Ruling
Typical Wet-to-Dry Ash Conversion Project Durations
Task
January
February
March
April
May
June
July
AugustSeptemberOctoberNovemberDecemberJanuary
February
March
April
May
June
July
AugustSeptemberOctoberNovemberDecemberJanuary
February
March
April
May
June
July
AugustSeptemberOctoberNovemberDecemberJanuary
February
March
April
May
June
2015 2016 2017 2018
Planning Study/
Spec. Development/
Permitting
Request for Proposal/
Procurement
Engineering
Procurement/
Fabrication
Construction/
Commissioning
TOTAL PROJECT DURATION 36-42 months
2015 2016 2017
6-12 months
3-6 months
9-12 months
12 months
12-18 months
2018
Water Table Testing
■ CCR Impoundments must be constructed with a
base/liner located 5 feet above the water table
■ Researched EPA regulations “uppermost aquifer”
■ Developed a Request for and obtained Proposal
for a groundwater measuring system (Solonist)
■ Project Manager currently working with Site
Environmental Representative to obtain approval
for installation.
■ Some of this slide will be moved to slide #
Bottom Ash WTD Conversion Alternatives
Continuous Dewatering & Recirculation System (CDR) with Remote Submerged
Flight Conveyor (RSFC)
Bottom Ash WTD Conversion Alternatives
Continuous Dewatering & Recirculation System (CDR) with Remote SFC’s
Benefits
■ Allow Gibson Station To Stay in Operation
■ Learned basics about the business aspect of power generation
– How EPA rules impact Utilities and ultimately the Ratepayer
– Investing in Capital
■ Doubled the workforce on this project
■ Saved the team time
Conclusion/Summary
■ Going forward, the project team will continue juggling the outage
projects and work towards meeting the deadline on the WTD Ash
project
■ The drawings I have accumulated will be used along with the 3Ds
from UCC to place the high pressure pipes in the plant
■ We will hopefully begin the construction process on the
piezometer soon, then we will be able to determine if the base of
the Continuous Dewatering System will need to be built on
ground level or not
This Rotation
■ More opportunity to get involved
■ More responsibility
■ Transitioning from a corporate setting
■ Work alongside other engineering disciplines
■ The potential benefit of 2 consecutive terms
Looking Ahead
■ After graduation, I would like to build upon my knowledge in the
power industry
■ Potential project management/ structural focus
Questions?

Mais conteúdo relacionado

Mais procurados

Earthwork Volume Calculation Methods
Earthwork Volume Calculation MethodsEarthwork Volume Calculation Methods
Earthwork Volume Calculation Methodsriyasood003
 
2015.10.29--PENC_Presentation_XPSWMM
2015.10.29--PENC_Presentation_XPSWMM2015.10.29--PENC_Presentation_XPSWMM
2015.10.29--PENC_Presentation_XPSWMMDanee McGee
 
Turkey Run at Truro Subdivision Stream Restoration
Turkey Run at Truro Subdivision Stream RestorationTurkey Run at Truro Subdivision Stream Restoration
Turkey Run at Truro Subdivision Stream RestorationFairfax County
 
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...DOE Office of River Protection
 
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank ReplacementLong Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank ReplacementFairfax County
 
Wastewater Master Plan Update -- Northgate
Wastewater Master Plan Update -- NorthgateWastewater Master Plan Update -- Northgate
Wastewater Master Plan Update -- NorthgateCity of College Station
 
Project synopsis for East West Gas Pipeline and Effective GIS Implementation
Project synopsis for East West Gas Pipeline and Effective GIS ImplementationProject synopsis for East West Gas Pipeline and Effective GIS Implementation
Project synopsis for East West Gas Pipeline and Effective GIS ImplementationSoumik Chakraborty
 
Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3Fairfax County
 
Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectCommunity Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectFairfax County
 
140416 oak_harbor_workshp_presentation
140416 oak_harbor_workshp_presentation140416 oak_harbor_workshp_presentation
140416 oak_harbor_workshp_presentationpublicinvolvement
 
Joshua sensor progress_final
Joshua sensor progress_finalJoshua sensor progress_final
Joshua sensor progress_finalJoshua Irungu
 
CopyMegan.Hixon.Resume.doc (1)
CopyMegan.Hixon.Resume.doc (1)CopyMegan.Hixon.Resume.doc (1)
CopyMegan.Hixon.Resume.doc (1)Megan Hixon
 
Stop Don't R&R Contractors Flyer
Stop Don't R&R Contractors FlyerStop Don't R&R Contractors Flyer
Stop Don't R&R Contractors FlyerCraig Harrington
 
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014Joseph Merzlak
 

Mais procurados (20)

Earthwork Volume Calculation Methods
Earthwork Volume Calculation MethodsEarthwork Volume Calculation Methods
Earthwork Volume Calculation Methods
 
Water Master Plan Northgate Update
Water Master Plan Northgate UpdateWater Master Plan Northgate Update
Water Master Plan Northgate Update
 
2015.10.29--PENC_Presentation_XPSWMM
2015.10.29--PENC_Presentation_XPSWMM2015.10.29--PENC_Presentation_XPSWMM
2015.10.29--PENC_Presentation_XPSWMM
 
Turkey Run at Truro Subdivision Stream Restoration
Turkey Run at Truro Subdivision Stream RestorationTurkey Run at Truro Subdivision Stream Restoration
Turkey Run at Truro Subdivision Stream Restoration
 
Gec pest
Gec pestGec pest
Gec pest
 
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
 
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank ReplacementLong Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
 
Wastewater Master Plan Update -- Northgate
Wastewater Master Plan Update -- NorthgateWastewater Master Plan Update -- Northgate
Wastewater Master Plan Update -- Northgate
 
Project synopsis for East West Gas Pipeline and Effective GIS Implementation
Project synopsis for East West Gas Pipeline and Effective GIS ImplementationProject synopsis for East West Gas Pipeline and Effective GIS Implementation
Project synopsis for East West Gas Pipeline and Effective GIS Implementation
 
Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3
 
State of the City of Norman
State of the City of NormanState of the City of Norman
State of the City of Norman
 
Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectCommunity Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
 
140416 oak_harbor_workshp_presentation
140416 oak_harbor_workshp_presentation140416 oak_harbor_workshp_presentation
140416 oak_harbor_workshp_presentation
 
Gec 1997
Gec 1997Gec 1997
Gec 1997
 
Joshua sensor progress_final
Joshua sensor progress_finalJoshua sensor progress_final
Joshua sensor progress_final
 
CopyMegan.Hixon.Resume.doc (1)
CopyMegan.Hixon.Resume.doc (1)CopyMegan.Hixon.Resume.doc (1)
CopyMegan.Hixon.Resume.doc (1)
 
Arup Da1
Arup Da1Arup Da1
Arup Da1
 
Stop Don't R&R Contractors Flyer
Stop Don't R&R Contractors FlyerStop Don't R&R Contractors Flyer
Stop Don't R&R Contractors Flyer
 
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014
 
Master Plan Public Hearing Presentation - January 9, 2014
Master Plan Public Hearing Presentation - January 9, 2014Master Plan Public Hearing Presentation - January 9, 2014
Master Plan Public Hearing Presentation - January 9, 2014
 

Destaque (20)

245 mri scanner
245 mri scanner245 mri scanner
245 mri scanner
 
Dual immersion 1
Dual immersion 1 Dual immersion 1
Dual immersion 1
 
Book_Cover_2014
Book_Cover_2014Book_Cover_2014
Book_Cover_2014
 
Weeklynews 101113113504-phpapp01
Weeklynews 101113113504-phpapp01Weeklynews 101113113504-phpapp01
Weeklynews 101113113504-phpapp01
 
Dual immersion 1
Dual immersion 1 Dual immersion 1
Dual immersion 1
 
Dual immersion 1
Dual immersion 1 Dual immersion 1
Dual immersion 1
 
Aov vergelijken
Aov vergelijkenAov vergelijken
Aov vergelijken
 
Acc presentation lipid coated(2)
Acc presentation lipid coated(2)Acc presentation lipid coated(2)
Acc presentation lipid coated(2)
 
Ajay Samaddar Resume 1
Ajay Samaddar Resume 1Ajay Samaddar Resume 1
Ajay Samaddar Resume 1
 
Tom Parr Candidate Profile July 2016
Tom Parr Candidate Profile July 2016Tom Parr Candidate Profile July 2016
Tom Parr Candidate Profile July 2016
 
Haiku
HaikuHaiku
Haiku
 
คอมพิวเตอร์
คอมพิวเตอร์คอมพิวเตอร์
คอมพิวเตอร์
 
Wbates_Sept_2016
Wbates_Sept_2016Wbates_Sept_2016
Wbates_Sept_2016
 
Vivix
VivixVivix
Vivix
 
kitchens 1
kitchens 1kitchens 1
kitchens 1
 
BizBashTop100'10
BizBashTop100'10BizBashTop100'10
BizBashTop100'10
 
The Prefrontal Cortex
The Prefrontal CortexThe Prefrontal Cortex
The Prefrontal Cortex
 
Timothy Fowler Report
Timothy Fowler ReportTimothy Fowler Report
Timothy Fowler Report
 
Work factor-Anant Patel
Work factor-Anant PatelWork factor-Anant Patel
Work factor-Anant Patel
 
News file from 16th nov to 22nd nov
News file from 16th nov to 22nd novNews file from 16th nov to 22nd nov
News file from 16th nov to 22nd nov
 

Semelhante a gibson

Sarah Hartman ROP - Gibson Tech Team
Sarah Hartman ROP - Gibson Tech TeamSarah Hartman ROP - Gibson Tech Team
Sarah Hartman ROP - Gibson Tech TeamSarah Hartman
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
Lakevale Sewer Improvements Community Meeting
Lakevale Sewer Improvements Community MeetingLakevale Sewer Improvements Community Meeting
Lakevale Sewer Improvements Community MeetingFairfax County
 
Lorton Landfill Closure Status Update 3 13-18 SCF mtg
Lorton Landfill Closure Status Update 3 13-18 SCF mtgLorton Landfill Closure Status Update 3 13-18 SCF mtg
Lorton Landfill Closure Status Update 3 13-18 SCF mtgFairfax County
 
Status of County Oversight - Lorton Landfill Closure Activities 3-13-2018
Status of County Oversight - Lorton Landfill Closure Activities 3-13-2018Status of County Oversight - Lorton Landfill Closure Activities 3-13-2018
Status of County Oversight - Lorton Landfill Closure Activities 3-13-2018Fairfax County
 
Crook at Mantua Elementary School Stream Restoration
Crook at Mantua Elementary School Stream RestorationCrook at Mantua Elementary School Stream Restoration
Crook at Mantua Elementary School Stream RestorationFairfax County
 
EUCI Presentation: "Are You Prepared to Close Your Ash Ponds?" by Kent Nilsson
EUCI Presentation: "Are You Prepared to Close Your Ash Ponds?" by Kent NilssonEUCI Presentation: "Are You Prepared to Close Your Ash Ponds?" by Kent Nilsson
EUCI Presentation: "Are You Prepared to Close Your Ash Ponds?" by Kent NilssonTRC Companies, Inc.
 
Negdc presentation december 2013
Negdc presentation   december 2013 Negdc presentation   december 2013
Negdc presentation december 2013 carsoncorporation
 
Sustainable Design of Fant's Grove Recycling and Compost Facility
Sustainable Design of Fant's Grove Recycling and Compost FacilitySustainable Design of Fant's Grove Recycling and Compost Facility
Sustainable Design of Fant's Grove Recycling and Compost FacilityAdrianna Thompson
 
WET Feature 4 - Building bigger and better - Jan_16
WET Feature 4 - Building bigger and better - Jan_16WET Feature 4 - Building bigger and better - Jan_16
WET Feature 4 - Building bigger and better - Jan_16Tim Bail
 
Springfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
Springfield Estates Pump Station Gravity Sewer Replacement - Community MeetingSpringfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
Springfield Estates Pump Station Gravity Sewer Replacement - Community MeetingFairfax County
 
Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016
Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016
Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016Fairfax County
 
K.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectK.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectascemiami-dade
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarAssociation for Project Management
 

Semelhante a gibson (20)

Sarah Hartman ROP - Gibson Tech Team
Sarah Hartman ROP - Gibson Tech TeamSarah Hartman ROP - Gibson Tech Team
Sarah Hartman ROP - Gibson Tech Team
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
Gude Landfill Remediation - June 15, 2017
Gude Landfill Remediation - June 15, 2017Gude Landfill Remediation - June 15, 2017
Gude Landfill Remediation - June 15, 2017
 
Gude Landfill Remediation update
Gude Landfill Remediation updateGude Landfill Remediation update
Gude Landfill Remediation update
 
Downsview Area Long Term Water Servicing
Downsview Area Long Term Water Servicing Downsview Area Long Term Water Servicing
Downsview Area Long Term Water Servicing
 
Lakevale Sewer Improvements Community Meeting
Lakevale Sewer Improvements Community MeetingLakevale Sewer Improvements Community Meeting
Lakevale Sewer Improvements Community Meeting
 
Master Plan
Master PlanMaster Plan
Master Plan
 
Lorton Landfill Closure Status Update 3 13-18 SCF mtg
Lorton Landfill Closure Status Update 3 13-18 SCF mtgLorton Landfill Closure Status Update 3 13-18 SCF mtg
Lorton Landfill Closure Status Update 3 13-18 SCF mtg
 
Status of County Oversight - Lorton Landfill Closure Activities 3-13-2018
Status of County Oversight - Lorton Landfill Closure Activities 3-13-2018Status of County Oversight - Lorton Landfill Closure Activities 3-13-2018
Status of County Oversight - Lorton Landfill Closure Activities 3-13-2018
 
Crook at Mantua Elementary School Stream Restoration
Crook at Mantua Elementary School Stream RestorationCrook at Mantua Elementary School Stream Restoration
Crook at Mantua Elementary School Stream Restoration
 
EUCI Presentation: "Are You Prepared to Close Your Ash Ponds?" by Kent Nilsson
EUCI Presentation: "Are You Prepared to Close Your Ash Ponds?" by Kent NilssonEUCI Presentation: "Are You Prepared to Close Your Ash Ponds?" by Kent Nilsson
EUCI Presentation: "Are You Prepared to Close Your Ash Ponds?" by Kent Nilsson
 
Wellborn Community Plan
Wellborn Community PlanWellborn Community Plan
Wellborn Community Plan
 
Negdc presentation december 2013
Negdc presentation   december 2013 Negdc presentation   december 2013
Negdc presentation december 2013
 
Senior Design
Senior DesignSenior Design
Senior Design
 
Sustainable Design of Fant's Grove Recycling and Compost Facility
Sustainable Design of Fant's Grove Recycling and Compost FacilitySustainable Design of Fant's Grove Recycling and Compost Facility
Sustainable Design of Fant's Grove Recycling and Compost Facility
 
WET Feature 4 - Building bigger and better - Jan_16
WET Feature 4 - Building bigger and better - Jan_16WET Feature 4 - Building bigger and better - Jan_16
WET Feature 4 - Building bigger and better - Jan_16
 
Springfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
Springfield Estates Pump Station Gravity Sewer Replacement - Community MeetingSpringfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
Springfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
 
Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016
Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016
Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016
 
K.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectK.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 project
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
 

gibson

  • 1. Adam Goodin Fossil Hydro Operations Co-op Development Program August 13, 2015
  • 2. About Me ■ University of Kentucky – Senior – Civil Engineering – Graduation: 8/16 ■ 3rd Rotation with Duke – Woodsdale (Spring 14) – Plainfield (Fall 14) – Gibson Station (Current) ■ Gibson Station, Capital Group – Mentor: Mick Harpenau
  • 3. My Safety Moment ■ Participated in Sitewide Safety Stand-down – Walkdown with experienced Duke and Contractor Management with the sole purpose of eliminating hazards in the workplace ■ Looked for technical malfunctions – Deteriorating grounding equipment – Broken/corroded conduit ■ Housekeeping – Ladders in isleway – Stray pieces of wood and metal could become falling object
  • 4. Responsibilities this Rotation ■ Document Control on Unit 5 FGD Structural Refurbishment – Maintained IFC Drawings and updated for revisions – Provided Field Support ■ U5 Mercury Re-emission project – Developed P&IDs – Created Valve Lists and Valve Numbers ■ Involved in fall outage coordination meetings – Logistics of large scale project – Schedule formed, laydown areas designated, scope of work
  • 5. Dry Bottom Ash Conversion ■ Support Engineering Efforts on the recently initiated Dry Bottom Ash Conversion Project – April 2015 EPA Ruling – Gibson to adopt a Continuous Dewatering and Recirculation (CDR) System – Locate Existing Underground Drawings – Obtain Existing Area General Arrangement (GA’s) Drawings – Layout Route for new Sanitation System piping
  • 6. Dry Bottom Ash Conversion (Cont.) – Locate Existing Sanitation System Drawings for locating tie points – Layout new Sanitation System GA’s, ■ Effluent Guidelines – Review EPA’s proposed rules – Gained Consensus on liner requirements as they pertain to the DBA design ■ Researched and scoped out equipment for installation of a Water Table Monitoring System
  • 7. ELG & CCR Ruling Typical Wet-to-Dry Ash Conversion Project Durations Task January February March April May June July AugustSeptemberOctoberNovemberDecemberJanuary February March April May June July AugustSeptemberOctoberNovemberDecemberJanuary February March April May June July AugustSeptemberOctoberNovemberDecemberJanuary February March April May June 2015 2016 2017 2018 Planning Study/ Spec. Development/ Permitting Request for Proposal/ Procurement Engineering Procurement/ Fabrication Construction/ Commissioning TOTAL PROJECT DURATION 36-42 months 2015 2016 2017 6-12 months 3-6 months 9-12 months 12 months 12-18 months 2018
  • 8. Water Table Testing ■ CCR Impoundments must be constructed with a base/liner located 5 feet above the water table ■ Researched EPA regulations “uppermost aquifer” ■ Developed a Request for and obtained Proposal for a groundwater measuring system (Solonist) ■ Project Manager currently working with Site Environmental Representative to obtain approval for installation. ■ Some of this slide will be moved to slide #
  • 9. Bottom Ash WTD Conversion Alternatives Continuous Dewatering & Recirculation System (CDR) with Remote Submerged Flight Conveyor (RSFC)
  • 10. Bottom Ash WTD Conversion Alternatives Continuous Dewatering & Recirculation System (CDR) with Remote SFC’s
  • 11. Benefits ■ Allow Gibson Station To Stay in Operation ■ Learned basics about the business aspect of power generation – How EPA rules impact Utilities and ultimately the Ratepayer – Investing in Capital ■ Doubled the workforce on this project ■ Saved the team time
  • 12. Conclusion/Summary ■ Going forward, the project team will continue juggling the outage projects and work towards meeting the deadline on the WTD Ash project ■ The drawings I have accumulated will be used along with the 3Ds from UCC to place the high pressure pipes in the plant ■ We will hopefully begin the construction process on the piezometer soon, then we will be able to determine if the base of the Continuous Dewatering System will need to be built on ground level or not
  • 13. This Rotation ■ More opportunity to get involved ■ More responsibility ■ Transitioning from a corporate setting ■ Work alongside other engineering disciplines ■ The potential benefit of 2 consecutive terms
  • 14. Looking Ahead ■ After graduation, I would like to build upon my knowledge in the power industry ■ Potential project management/ structural focus