2. ResourcesResources
Construction Documents and Contracting, Joseph D.
Coleman , 2004, Prentice Hall
Construction Contracts, Keith Collier, 1987, Prentice
Hall
“Construction Management”, by Daniel W. Halpin and
Ronald W. Woodhead, 2nd Edition , John Wiley & Sons
Fidic Conditions of Contract for Construction, FOR
BUILDING AND ENGINEERING WORKS DESIGNED BY
THE EMPLOYER, 2005
Fidic Tendering Procedures, prequalification, tendering
and award the contract, 1994.
Handouts and lecture notes
4. Course OutlineCourse Outline
1. Introduction to construction project stages, overview of
the construction contracting methods, and contracts
types.
2. Bidding document
Invitation to bid
Instruction to bidders
Information to bidders & bid data
Biding Forms
General conditions of contract
Specific condition of contract
Specification
BOQ
Drawings
Contract forms
3. Methods of Tendering, Bidding and Awarding
4. Contract Documents and Conditions
6. Major Project PhasesMajor Project Phases
The major phases in the project cycle that are common to most design
and construction projects are :
Project Planning
Design
Schematic Design
Design Development
Contract Documents
Construction Procurement (Bidding Phase)
Construction
Post Construction
7. Construction Project CharacteristicsConstruction Project Characteristics
Construction projects are different than other types of
projects due to the following characteristics;
Construction projects are complex undertaking.
Every construction project is unique.
Construction projects involve a lot of uncertainties,
lack of information and variables.
8. Project Life Cycle
Most of Construction projects life-cycle have common
characteristics, Construction projects start with low cost and
resources, high risk and uncertainty.
The life-cycle of a typical construction project could be summarized
as following :
Stage I : represents the project formulation, feasibility studies,
and the strategic decisions needed for project continue.
Stage II : represents planning, basic design, budgeting,
tendering and placing the project major contracts.
Stage III : involves the construction phase of the project,
equipment installation and testing.
Stage IV : represents the final phase in the project which
includes the project turnover, final testing and start-up.
10. PercentComplete
Stage I
Stage II Stage III Stage IV
Project "GO"
Decision
Major Contracts
Let
Installation Substantially
Complete
Full
Operations
F e a s a bility
- Project Formulation
- Feasabiltiy Studies
- Strategies Design &
Approval
P la nning & D e s ign
- Base Design
- Cost & Schedule
- Contract Terms &
Conditions.
- Detailed P lanning
T urno v e r
& S ta rt Up
- Final Testing
- M aintenance
C o ns truc tio n
- M anufacturing
- Delivery
- Civil Work
- Installation
- Testing
Figure 1.1 : Construction Projects Life-Cycle (Ref: PMBK, 2000(
11. Construction Contracting MethodConstruction Contracting Method
(delivery methods(delivery methods((
Traditional Approach (D-B-B):
The most common delivery system is called “the
traditional or standard approach” or “design-bid-
build”, in which the employer assigns the design and
construction phases to two different firms
(consultant/designer and contractor).
Constructing
Designing
Appointing
Consultant
Appointing Main
Contractor
12. Traditional Approach (D-B-B(:
For many years, DBB has been the most common method of
project delivery for public projects, and for many private projects
as well.
Design Bid-Build is effective on projects
where the owner needs both professional design services and
construction services
where the designer does not require detailed knowledge of the
means and methods of construction.
DBB provides the owner with a high degree of control. That’s why
it is the preferred project delivery system for owners who:
13. Traditional Approach (D-B-BTraditional Approach (D-B-B(:(:
The owner defines project goals and objectives, secures the financing,
and specifies the standards and contract terms.
The owner may perform planning, conceptual design and full design,
or may engage an outside design professional (designer) for some or
all of these tasks.
During this planning and preliminary stage, owner and designer work
as a team to obtain required permits and conduct necessary site
investigations.
The designer prepares the construction bid documents to reflect the
owner’s project goals and objectives, the project’s site conditions, and
sound engineering practices.
Prospective contractors prepare their bids from these complete and
specific bid documents.
The bidders submit their proposals to the owner, who determines the
most responsive (typically the lowest) bid meeting project
requirements.
In certain circumstances, owner may be justified in selecting a
contractor outright and negotiating contract terms directly.
14. Advantages of D-B-B ApproachAdvantages of D-B-B Approach
Applicable to a wide range of projects.
Well established and easily understood.
Clearly defined roles for all parties.
Provides the lowest initial price that competitive
bidders can offer.
Extensive litigation has resulted in well established
legal precedents.
Insurance and bonding are well defined.
15. Disadvantages of D-B-B ApproachDisadvantages of D-B-B Approach
Least-cost approach requires higher level of inspection.
Initial low bid might not result in ultimate lowest cost or
final best value.
Designers may have limited knowledge of the true cost
and scheduling implication of design decisions.
16. Design-Build ApproachDesign-Build Approach
Design-build approach is a project delivery system involving a
single contract between the project employer and a
design-build contractor covering both the design
and construction of a project.
The design-builder performs design, construction
engineering, and construction according to design
parameters, performance criteria and other
requirements established by the employer or his
representative.
ConstructingDesigning
Appointing design & construction
contractor
Tendering
17. Design-Build ApproachDesign-Build Approach
The owner contracts with a single entity to provide the design
and to construct the project according to that design.
The contract might be negotiated with a single design-builder
or result from competitive proposals.
The selection can be based on low price or on a set of value
criteria (experience, staff, bonding capacity, etc.).
Design-build provides the owner with a single point of contact
for project responsibilities, eliminating the need to assist in
resolving designer-contractor disputes.
With the contractor playing a major role in design, costs are
typically defined and maintained to a greater degree, and the
coordination of fast-track management to achieve early
completion is greatly simplified.
The design-builder makes many decisions that owner would
make under DBB, due to delegation of greatly increased
authority.
18. Design-Build ApproachDesign-Build Approach
For many owners, delegation of responsibilities leads to
satisfactory projects. However, if the parties are
inexperienced and do not cooperate, the transfer of control
and risk can be disappointing.
The owner may need to restructure his/her internal
procedures to accommodate design-build approach.
Compared to DBB, this involves a significantly different set
of requirements and expectations for process, timelines and
communications.
A clear understanding and documentation of design-build
processes enhances the quality of design-build projects
19. Advantage of Design-Build ApproachAdvantage of Design-Build Approach
Innovation and quality improvements through:
- Alternative designs and construction methods
suited to the contractor’s capabilities
- Flexibility in the selection of design, materials, and
construction methods.
• Earlier schedule and cost certainty
20. Disadvantage of Design-Build ApproachDisadvantage of Design-Build Approach
Reduced opportunities for smaller, local construction firms.
Fewer competitors and increased risk may result in higher
initial costs.
Elimination of traditional checks and balances. Quality may
be subordinated by cost or schedule considerations.
Less Engineer control over final design.
Higher procurement costs.
Traditional funding may not support fast-tracking
construction or may require accelerated cash flow.
Accelerated construction can potentially overextend the
workforce.
21. Others
TurnkeyTurnkey
Turnkey VariationsTurnkey Variations
Direct Labor Approach.Direct Labor Approach.
Construction managementConstruction management
22. Turnkey
Turnkey adds to the design-builder’s
responsibilities the operation and/or maintenance
of the completed project.
Turnkey delivery has the potential for bringing a
new project on line more quickly.
Three forms of turnkey project delivery:
Design-build-operate-transfer
Design-build-operate-maintain
Design-build-own-operate-transfer
23. Turnkey Variation
Variations on turnkey add financing as a key
component. While financing arrangements are
unique for each project, developer financed
projects generally resemble one of the turnkey
delivery methods:
FDBT (Finance, design, build, transfer)
FDBOT (Finance, design, build, operate, transfer)
FDBOOT (Finance, design, build ,own, operate, transfer)
In each case, the transfer of the project occurs
only after the developer’s interests and financial
obligations have been satisfied.
24. Assignment (1Assignment (1((
Describe the turnkey methods, turnkey
variation methods, direct labor approach,
and construction management method,
highlighting on advantage and
disadvantage of each one.
26. Contract DefinitionContract Definition
Agreement of at least two parties with purpose of
creating legal obligation between the parties and
capable of being enforced by the court of law.
Contract = offer + acceptance + consideration
27. Introduction to contractsIntroduction to contracts
Why Use contract in construction:
Describe scope of work
Establish time frame
Establish cost and payment provision
Set fourth obligations and relationship
Minimize disputes
Improve economic return of investment
28. Content of the contractContent of the contract
o Identify the parties
o Promises and responsibilities
o Scope of work
o Price and payment terms
o Commercial terms and conditions
o Project execution plan.
30. Lump Sum Contract
One price for the whole contract
Lump sum includes costs plus overheads and profits
Higher risk to contractor
Price quoted is a guaranteed price as per contract
documents.
Payment based on a scheduled percentage scheme
(monthly progress claims)
The contractor is free to use means and methods to
complete the work and responsible for proper performance
Work must be well defined at bid time.
Fully developed plans and specifications
31. Lump Sum Contract/ advantage
Low risk on the owner, Higher risk to
the contractor
Cost known at outset
Contractor will assign best personnel
Contractor selection is easy.
32. Lump Sum Contract/disadvantage
Changes is difficult and costly.
Contractor is free to use the lowest cost of
material equipment, methods.
33. Unit Price
Quote Rates / Prices by units
No total final price
Re-negotiate for rates if the quantity or work
considerably exceeds the initial target
Payment to contractor is based on the measure.
Unbalanced bids
Higher risk to owner
Ideal for work where quantities can not be accurately
established before construction starts.
34. Unit Price contract
Require sufficient design definition to estimate
quantities of units
Contractors bid based on units of works
Time & cost risk (shared)
Owner : at risk for total quantities
Contractor : at risk for fixed unit price.
Large quantities changes (>15-25%) can lead to
increase or decrease of unit price.
35. Unit Price / Requirement
Adequate breakdown and definition of work units
Good quantity surveying and reporting system.
Adequate drawings.
Experience in developing BOQ
Payment based on the measurement of the finished
works.
Quantity sensitive analysis of unit prices to
evaluate total bid price for potential quantity
variation.
36. Unit Price / advantagesUnit Price / advantages
Suitable for competitive bid
Easy for contract selection
Early start is possible
Flexibility : quantities and scope can be easily
adjusted
37. Unit Price / disadvantagesUnit Price / disadvantages
Final cost not known from the beginning (BOQ
only is estimated)
Staff needed to measure the finished quantities
and report on the units not completed.
Unit price sometime tend to draw unbalanced bid.
(For Unit-Price Contracts, a balanced bid is one in which each bid
is priced to carry its share of the cost of the work and also its
share of the contractor’s profit.
Contractors raise prices on certain items and make corresponding
reductions of the prices on other items ,without changing the total
amount of the bid)
38. Cost Plus
1. Actual cost plus a negotiated reimbursement to
cover overheads and profit.
2. different methods of reimbursement :
Cost + percentage
Cost + fixed fee
Cost + fixed fee + profit-sharing clause.
3. Higher risk to owner
4. Compromise : guaranteed maximum price
(GMP) reduces risk to owner while maintain
advantage of cost plus contract.
5. By using this type of contract the contractor can start
work without a clearly defined project scope, since all
costs will be reimbursed and a profit guaranteed.
39. Cost + Percent of Cost
Fee = percentage of the
total project cost
(Cost = $500.000,Fee =
2%)
AdvantagesAdvantages DisadvantagesDisadvantages
profitable forprofitable for
the contractorthe contractor
No incentiveNo incentive
to finish jobto finish job
quicklyquickly
Owner doesOwner does
not know totalnot know total
priceprice
Larger theLarger the
cost of thecost of the
job, thejob, the
higher the feehigher the fee
the ownerthe owner
payspays
40. Cost + Fixed Fee
Fee = percentage of the
original estimated total figure
Utilized on large multi-
year jobs
Ex: WW treatment plant
Facility (Cost = $20
million, Fee = 1%)
$20 Million 1% fee =
$200,000 Million
AdvantagesAdvantages DisadvantagesDisadvantages
Fee amount isFee amount is
fixedfixed
regardlessregardless
of priceof price
fluctuationfluctuation
ExpensiveExpensive
materials andmaterials and
constructionconstruction
techniques maytechniques may
be used tobe used to
expediteexpedite
constructionconstruction
ProvidesProvides
incentive toincentive to
completecomplete
the projectthe project
quicklyquickly
41. Cost Plus Fixed Fee
Most common form of negotiated contracts
COST = expenses incurred by the contractor
for the construction of the facility
Includes: Labor, equipment, materials, and
administrative costs
FEE = compensation for expertise
Includes: profit
42. Cost + Fixed Fee +
Profit-Sharing Clause
Rewards contractors
who minimize cost
Percentage of cost
under GMP is
considered profit
and shared with the
contractor
Guaranteed Maximum
Price (GMP)
% of profit sharing is
specified in contract
AdvantagAdvantag
eses
DisadvantagesDisadvantages
ProvidesProvides
incentiveincentive
to theto the
contractocontracto
r to saver to save
moneymoney
ContractorContractor
must absorbmust absorb
anyany
amount overamount over
the GMPthe GMP
Plans & specs.Plans & specs.
need toneed to
detaileddetailed
43. Cost + Fixed Fee +
Profit-Sharing Clause
variation of this type of contract is calledvariation of this type of contract is called a guaranteeda guaranteed
maximum price (GMP).maximum price (GMP).
In this type of contract the contractor is reimbursed at costIn this type of contract the contractor is reimbursed at cost
with an agreed-upon fee up to the GMP, which is essentiallywith an agreed-upon fee up to the GMP, which is essentially
a cap; beyond this point the contractor is responsible fora cap; beyond this point the contractor is responsible for
covering any additional costs within the original projectcovering any additional costs within the original project
scopescope
AnAn incentive clause,incentive clause, which specifies that the contractorwhich specifies that the contractor
will receive additional profit for bringing the project inwill receive additional profit for bringing the project in
under the GMP.under the GMP.
44. Construction Documents
Bidding requirements
Notice to Bidders
Instruction to Bidders
Proposal Form
Contract Documents
Contract Forms
Conditions of the Contract
Specifications
Drawings
Addenda
Change Orders
Agreement.
45. Construction Documents
Construction Documents are defined as the written and graphic documents
prepared or assembled by the A/E for communicating the design of the
project and administering the contract for its construction.
2 major groups
1.Bidding Requirements
Used to attract bidders & explains bidding process
2.Contract Documents
Legally enforceable requirements that become part of the contract
Include all construction documents except bidding forms
47. CONSTRUCTION DOCUMENTS
BIDDING REQUIREMENTS
BIDDING REQUIREMENTS
Bidding Requirements are used to attract bidders and explain the procedures to be followed
in preparing and submitting bids .
Bidding requirements help bidders follow established procedures and submit bids that will
not be disqualified because of technicalities. They do not become part of the contract
documents
Bidding documents
All of the construction documents issued to bidders before the signing of an owner-
contractor agreement.
48. Bid Package
Documents available to the contractor and on which he must make a decision to bid
or not
A set of plans and technical specifications, Proposal form, general conditions,
special conditions,
Description of the project to be constructed
Bid Package is prepared by: