Presentation Overview
The quality and completeness of engineering design
deliverables have a significant impact on overall project
performance. Thus, project stakeholders should pay close
attention to such issues, with a particular focus on problematic
engineering design deliverables.
This presentation summarizes the findings of the Construction
Industry Institute (CII) Research Team (RT) 320, Definition and
Measurement of Engineering/Design Deliverable Quality,
including the 11 most problematic deliverables and their
significant defects, causal factors, leading/lagging metrics, and
two implementation tools.
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Houston, TX.
February 14, 2018
James T. O’Connor, P.E., Ph.D.
Jeyoung Woo, P.E.
Eliminating Quality Defects
on Problematic Engineering
Design Deliverables
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
~ $75 billion/year
5.4% of total construction cost
Leading cause = Design Errors/Omissions!
14.2 % of Contract value
Direct + Indirect
Case for Action (1/2)
Direct Cost of Rework (CII 2004)
Cost of Rework (Hwang et al. 2009)
Average Cost of Design Errors (Love et al. 2014)
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Case for Action (2/2)
Impact of Design Quality
Poor quality
deliverables
Design
Phase
Construction
Phase
Rework
Project
Performance
(Burati et al. 1992; Eldin 1991; Gransberg and Molenaar 2004; Haydl and Nikiel 2000)
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Dale C. Allen Shell
Ronald August, Jr. AECOM
Robert Beskow Chevron
Lin Budlong General Electric
Daniel C. Chabot Cargill, Inc.
Michael T. Cleary DuPont
Kim Crovetto Hargrove
John Hyland Lauren
Oscar L. Monagas ConocoPhillips
Donald L. Myers U.S. Department of VA
CII Research Team (RT) 320
Period: 2014/09 – 2016/08
21 Members
Dr. James T. O'Connor UT-Austin
Jason Phillips ArcelorMittal
Glenn Raz OXY
Matt Rouse CDI
Hulya Schwimmbeck CB&I
Joel K. Strang Fluor
Gilberto Teixeira Jr. Petrobras
Kelly Watson OXY
Nancy E. Wilkie U.S. DoS
Jeyoung Woo UT-Austin
Carlton Wright Technip
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Research Objectives
• Identify problematic design deliverables,
their defects & causes, and metrics that
facilitate proactive, preventive actions
(O’Connor and Woo 2016)
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
IN-Scope Design deliverable completeness & correctness
Design errors and omissions
OUT-of-scope Cost of design efforts
Cost estimate based on engineering deliverables
Research Scope
Detailed design phase of industrial projects
Concept Detailed scope
Procurement
Fabrication/
Delivery
Construction
Detailed Design
Project Funding Approval IFC (Issued for Construction)
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Design Quality Essentials
Essential criteria of design quality
Timely
Quality
(Andi and Minato 2003; O’Connor et al. 2007; Tilley et al. 1997)
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Research Flow: Facilitating Action
Team
Action
Quality
Detailed
Design
53 Detailed
Design
Deliverables
11
Problematic
Deliverables
Causal
Factors
(n=351)
Leading/Lagging
Metrics (n=141)
& Definitions
TWO Tools
- Leading Metrics Tool
- Completeness Checklist
Usage:
Awareness
Deliverable
Quality
Threats
Validation:
Application
Demonstration
(798 Defects)
3 Defect
Categories
Priorities
Defect
Impacts
Frequency Severity
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Research Methodology
53
DELIVERABLES
11 Problematic
Deliverables
798
DEFECTS
145
UNIQUE
DEFECTS
73 Significant Defects 349 Causal Factors
23 Lagging Metrics 118 Leading Metrics
Frequency
Consolidation
Impact priority
Two Implementation Tools (DDQA / CDDC)
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
53 Engineering Design Deliverables (1/2)
No. Deliverable No. Deliverable
1 Front-End Engineering Design (FEED) Validation 14 3D Model
2 Piping material classes 15 Standard piping details
3 Process data sheets 16 Standard civil details
4 Mechanical data sheets 17 Standard site details
5 Instrument data sheets 18 Standard architecture details
6 Piping & Instrumentation Diagrams (P&IDs) 19 Standard electrical details
7 Stress critical line list 20 Vendor data
8 Line list requiring hydraulic check 21 Equipment list
9 Plot plan 22 Mechanical equipment model volumes
10 Safety review 23 Duct model volumes
11 Constructability Inputs 24 Single line routing
12 Maintainability Inputs 25 Cable/ cable tray routing
13 Level 3 Baseline Schedule 26 Cathodic protection
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
53 Engineering Design Deliverables (2/2)
No. Deliverable No. Deliverable
27 Structure modeling 40 Underground services
28 Electrical equipment/building envelopes 41 Piping routing and isometrics
29 Control equipment/building envelopes 42 Stress analysis
30
Nozzles, ladders, and platforms for
towers/vessels/tanks
43 Hydraulic checks
44 Model updates
31 3D model reviews 45 Bulk material takeoff
32 Structural stress loads 46 Equipment specifications
33 Structure design 47 Inline instrument data
34 Fire protection study 48 Miscellaneous pipe supports drawings
35 Earthwork 49 Electrical design
36 Roads 50 Junction box location
37 Piling 51 Instrumentation design
38 Foundations 52 Lighting
39 Fencing 53 Clash detection
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Survey questionnaire
Relative frequency of quality problematic deliverables
Survey respondents
Problematic Deliverables
Survey Design
Option Very Rarely Sometimes Too Often Don’t know
Point value 1.0 3.0 5.0 0.0
Owner Contractor Total
Number of respondents 34 33 67
Industry
Experience
Total years 861 1,063 1,924
Average years 25.3 32.2 28.7
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Problematic Deliverables
Distribution of Results
46. Equipment Specifications & Data Sheets
6. P&IDs (Piping & Instrumentation Diagrams)
11. Constructability Inputs
13. Level 3 Baseline Schedule
20. Vendor Data
30. Nozzles, Ladders, and Platform for Towers/Vessels/Tanks
48. Miscellaneous Pipe Support Drawings
41. Piping Routing and Isometrics
1. FEED (Front-End Engineering Design) Validation Deliverables
12. Maintainability Inputs
14. 3D Model & 53. Clash Detection
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Problematic Deliverables
Survey Results
Scale: 1.0 = Very Rarely 3.0 = Sometimes 5.0 = Too Often
41 (77%)
10 (19%)
2 (4%)
0
5
10
15
20
25
30
35
40
45
Less than 3.0 3.0 - 3.5 Greater than 3.5
NumberofDeliverables
(n=53)
Most Problematic
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Validation: Statistical Analysis (t-Test)
Problematic vs. Non-Problematic Deliverables: Very Different
Owners vs. Contractors (11 Prob. Deliverables): Very Similar
Problematic
Deliverables
(n=11)
Other
Deliverables
(n=41)
Mean St.Dev. Mean St.Dev. t-score df p-value
Relative Frequency of
Design Quality Problems
3.22 0.28 1.92 0.49 11.43 29
<.001
(Sig.)
Owners
(n=34)
Contractors
(n=33)
Mean St.Dev. Mean St.Dev. t-score df p-value
Relative Frequency of
Design Quality Problems
3.25 0.09 3.19 0.11 0.68 10
0.50
(N.S)
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Impact Screening
Type: Completeness, Correctness, and Timeliness
Data Analysis
Defects
Causal Factors
Leading Metrics
Lagging Metrics
Identified by using “5-Whys” approach
Associated with 349 causal factors
Associated with 73 significant defects
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Data Analysis
Example (1/4)
Deliverable:
Constructability
Inputs
Defects
Failure to develop and
incorporate standard
design elements
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Data Analysis
Example (2/4)
Deliverable:
Constructability
Inputs
Defects Defect Impacts
Failure to develop and
incorporate standard
design elements
Design and
construction
productivity losses
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Data Analysis
Example (3/4)
Deliverable:
Constructability
Inputs
DefectsCausal Factors Defect Impacts
Failure to develop and
incorporate standard
design elements
Failure to recognize
the beneficial tradeoffs
from standardization
Design and
construction
productivity losses
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Data Analysis
Example (4/4)
Deliverable:
Constructability
Inputs
DefectsCausal Factors Defect Impacts
Leading Metrics Lagging Metrics
Did the project owner and/or contractor
utilize standardization resources during
the design (e.g., PIP.org or its equivalent
in other industry sectors)?
Field rework hours resulting
from inadequate
constructability input/reviews
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Defects Analysis Table
No. 3. Constructability Inputs
No. Significant Defect
Defect
Type
Impact
Type
Relative
Freq.
Relative
ImpactSev.
Priority
Score
Causal Factor
Metric
Leading
Lagging
10
Constructability
reviews are
conducted too late
Timeliness
- Late or additional
changes
- Redesign
- Schedule impacts
- Increased cost
H H 9
- Not involving knowledgeable resources at the right
time
- Not scheduling constructability reviews at the right
time (sufficiently in advance)
- Low schedule priority of constructability reviews
- Late contractor involvement in constructability
- Disincentives for contractors to participate in
Constructability
- Lack of contractor interest in pre-construction
services
1) At least one constructability review meeting is conducted in early FEED/ Design Development or
before?
2) The second constructability review meeting is conducted at or before the end of FEED/ Design
Development?
3) The third constructability review meeting is conducted at or before the 60% design complete?
4) Were the constructability reviews conducted too late to incorporate comments into the design?
Leading
Leading
Leading
Lagging
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Timing of Metrics
Concept Detailed scope
Procurement
Fabrication/
Delivery
Construction
Detailed Design
FV 1 30% 2 60% 2 90% 2 IFC 3 IFP 4
Leading Indicators
Lagging Indicators
1 FV: FEED Validation
2 30%, 60%, 90%: Detailed Design Progress
2 IFC: Issued for Construction
3 IFP: Issued for Procurement
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Helps assess current levels of deliverable quality
Helps identify associated potential defects
Facilitates planning/documentation of defect mitigation
strategies
Two Implementation Tools
Design Deliverable Quality Assessment (DDQA) Tool
Completeness of Design Deliverable Checklist (CDDC) Tool
Helps assess current level of deliverable completeness
Helps identify content inclusion items that need to be
completed
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
DDQA Tool
Input
- Targeted Design Deliverables
- Targeted Design Progress
- Leading Metrics
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
DDQA Tool
Output
- Design Quality Indices - List of Potential Defects
(Prompting discussion)
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
CDDC Tool
Input
- Targeted Design Deliverables - Completeness of Checklist Items
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
CDDC Tool
Output
- Completeness Index - List of Incomplete Items
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Recommended Timing of
Completeness Assessment
No. Deliverable
Detailed Design Progress
FV1 30%2 60%2 90%2 IFC3
1 Front-End Engineering Design (FEED) Validation X
2 Level 3 Baseline Schedule X
3 Constructability Inputs X X
4 Piping & Instrumentation Diagrams (P&IDs) X
5 Equipment Specifications & Data Sheets X X
6 Maintainability Inputs X X
7 Vendor Data X X
8 3D Model & Clash Detection X X
9 Piping Routing & Isometrics X X
10 Nozzles, Ladders, Platforms for Towers/Vessels/Tanks X X
11 Miscellaneous Pipe Support Drawings X1 FV: FEED Validation
2 30%, 60%, 90%: Detailed Design Progress
3 IFC: Issued for Construction
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Tool-related Responsibilities
Responsibility Job Titles
Sponsor
• Business Unit Engineering Director
• Business Unit Quality Director
Accountable
• Project Managers (Owner and/or Contractor)
• Project Design/Engineering Manager
Responsible
• Design Discipline Leads
• Project Engineer/Coordinator
Consult
• Construction Managers
• Maintenance Representatives
• Operations Representatives
• Project Controls Representatives
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Tool Validation
18+ yrs. experience each
18 External Reviewers
215 Feedback Comments
18 External Reviewers
Mostly Compliments
Most others Already Addressed, Minor, or Out-of-Scope
“Effective” in contributing to Project Design Quality
“Likely” to be used on future project
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Conclusions
• Identified 11 most problematic deliverables
• Identified 73 significant defects for problematic deliverables
• Identified 118 leading metrics associated with causal factors
• Identified 23 lagging metrics associated with 73 defects
• Developed Two implementation tools (DDQA / CDDC)
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Acknowledgements
Construction Industry Institute (CII)
CII Research Team 320
103 Survey Respondents
67 respondents for problematic deliverables survey
36 respondents for deliverable defects survey
Dale C. Allen Shell
Ronald August, Jr. AECOM
Robert Beskow Chevron
Lin Budlong General Electric
Daniel C. Chabot Cargill, Inc.
Michael T. Cleary DuPont
Kim Crovetto Hargrove
John Hyland Lauren
Oscar L. Monagas ConocoPhillips
Donald L. Myers U.S. Department of VA
Dr. James T. O'Connor UT-Austin
Jason Phillips ArcelorMittal
Glenn Raz OXY
Matt Rouse CDI
Hulya Schwimmbeck CB&I
Joel K. Strang Fluor
Gilberto Teixeira Jr. Petrobras
Kelly Watson OXY
Nancy E. Wilkie U.S. DoS
Jeyoung Woo UT-Austin
Carlton Wright Technip
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
References
Andi and Minato, T. (2003) “Design documents quality in the Japanese construction industry.” Int’l J. Project Management, 21. 537-546.
Burati, J.L, Farrington, J.J., and Ledbetter, W.B. (1992). “Causes of Quality Deviations in Design and Construction.” J. Construction
Engineering and Management, 118(1), 34-49.
Construction Industry Institute (CII) (2004). “Making Zero Rework a Reality.” Research Summary 203-1. Austin, TX.
East, E.W., Kirby, J.G. and Perez, G. (2004). “Improved Design Review through Web Collaboration.” J. Management in Engineering, 20 (2),
51-55.
Eldin, N. N. (1991). “Management of Engineering/Design Phase.” J. Construction Engineering and Management, 117 (1), 163-175.
Gransberg, D.D., and Molenaar, K. (2004). “Analysis of Owner’s Design and Construction Quality Management Approaches in
Design/Build Projects.” J. Management in Engineering, 20 (4), 162-169.
Haydl, H.M. and Nikiel, A.W. (2000). “Design and Construction Errors – Case Studies.” Practice Periodical on Structural Design and
Construction, 5 (3), 126-130.
Hwang, B., Thomas, S., Haas, C., and Caldas, C. (2009). “Measuring the Impact of Rework on Construction Cost Performance.” J.
Construction Engineering and Management, 135(3), 187-198.
Love, P., Lopez, R., Kim, J., and Kim, M. (2014). “Probabilistic Assessment of Design Error Costs.” J. Performance of Constructed Facility,
28(3), 518-527
Nigro, W. T. (2013). “RediCheck Interdisciplinary Coordination.” 4th Edition, Peachtree City, GA.
O’Connor, J.T., O'Brien, W.J., Jarrah, R.T., and Wallner, B. (2007). “Planning for facilitating, and evaluating design effectiveness”
Research Report 233-11, Construction Industry Institute, The University of Texas at Austin, Austin, TX.
O’Connor, J.T., and Woo, J. (2016). “Study of Engineering/Design Deliverable Quality.” Research Report 320-11, Construction Industry
Institute, The University of Texas at Austin, Austin, TX.
Soibelman, L., Liu, L. Y., Kirby, J.G., East, E.W., Caldas, C.H., and Lin, K. (2003). “Design Review Checking System with Corporate
Lessons Learned.” J. Construction Engineering and Management, 129 (5), 475-484.
Tilley, P., Wyatt A., and Mohamed, S.. (1997) "Indicators of design and documentation deficiency." IGLC-5: Proceedings of the Fifth
Annual Conference of the International Group for Lean Construction, 16-17 July, 1997, Gold Coast, Australia.
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Jeyoung Woo / P.E., P.M.P
Ph.D. Candidate
The University of Texas at Austin
woo.jeyoung@utexas.edu
© 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
This presentation may include predictions, estimates, intentions, beliefs
and other statements that are or may be construed as being forward-
looking. While these forward-looking statements represent our current
judgment on what the future holds, they are subject to risks and
uncertainties that could result in actual outcomes differing materially from
those projected in these statements. No statement contained herein
constitutes a commitment by AVEVA to perform any particular action or to
deliver any particular product or product features. Readers are cautioned
not to place undue reliance on these forward-looking statements, which
reflect our opinions only as of the date of this presentation. The Company
shall not be obliged to disclose any revision to these forward-looking
statements to reflect events or circumstances occurring after the date on
which they are made or to reflect the occurrence of future events.

Mais conteúdo relacionado

Mais procurados

AVEVA World Conference NA - Cormac Ryan, AVEVA ISM
AVEVA World Conference NA - Cormac Ryan, AVEVA ISMAVEVA World Conference NA - Cormac Ryan, AVEVA ISM
AVEVA World Conference NA - Cormac Ryan, AVEVA ISMAVEVA-Americas
 
AVEVA World Conference NA - Ryan/Avantsa, CFIHOS Workshop
AVEVA World Conference NA - Ryan/Avantsa, CFIHOS WorkshopAVEVA World Conference NA - Ryan/Avantsa, CFIHOS Workshop
AVEVA World Conference NA - Ryan/Avantsa, CFIHOS WorkshopAVEVA-Americas
 
AVEVA World Conference NA - Amish Sabharwal, AVEVA Welcome
AVEVA World Conference NA - Amish Sabharwal, AVEVA WelcomeAVEVA World Conference NA - Amish Sabharwal, AVEVA Welcome
AVEVA World Conference NA - Amish Sabharwal, AVEVA WelcomeAVEVA-Americas
 
AVEVA World Conference NA - Han Lin, Southern California Gas
AVEVA World Conference NA - Han Lin, Southern California GasAVEVA World Conference NA - Han Lin, Southern California Gas
AVEVA World Conference NA - Han Lin, Southern California GasAVEVA-Americas
 
AVEVA World Conference NA - Patrick Reilly, Vista Projects
AVEVA World Conference NA - Patrick Reilly, Vista ProjectsAVEVA World Conference NA - Patrick Reilly, Vista Projects
AVEVA World Conference NA - Patrick Reilly, Vista ProjectsAVEVA-Americas
 
AVEVA World Conference NA - Jim Purvis, WorleyParsons
AVEVA World Conference NA - Jim Purvis, WorleyParsonsAVEVA World Conference NA - Jim Purvis, WorleyParsons
AVEVA World Conference NA - Jim Purvis, WorleyParsonsAVEVA-Americas
 
AVEVA World Conference NA - Tom Singer, Aker Solutions
AVEVA World Conference NA - Tom Singer, Aker SolutionsAVEVA World Conference NA - Tom Singer, Aker Solutions
AVEVA World Conference NA - Tom Singer, Aker SolutionsVanessa Erickson
 
AVEVA Integrated Engineering & Design Developments
AVEVA Integrated Engineering & Design DevelopmentsAVEVA Integrated Engineering & Design Developments
AVEVA Integrated Engineering & Design DevelopmentsAVEVA Group plc
 
AVEVA World Conference NA - Rabelo/Tedstone, AVEVA ERM & Procon
AVEVA World Conference NA - Rabelo/Tedstone, AVEVA ERM & ProconAVEVA World Conference NA - Rabelo/Tedstone, AVEVA ERM & Procon
AVEVA World Conference NA - Rabelo/Tedstone, AVEVA ERM & ProconAVEVA-Americas
 
AVEVA World Conference NA - AVEVA Procon Panel
AVEVA World Conference NA - AVEVA Procon PanelAVEVA World Conference NA - AVEVA Procon Panel
AVEVA World Conference NA - AVEVA Procon PanelAVEVA-Americas
 
AVEVA’s ERM, Efficient Planning and Management of Project Resources
AVEVA’s ERM, Efficient Planning and Management of Project Resources AVEVA’s ERM, Efficient Planning and Management of Project Resources
AVEVA’s ERM, Efficient Planning and Management of Project Resources AVEVA Group plc
 
AVEVA World Conference NA - Felim Larkin, AVEVA Xchange
AVEVA World Conference NA - Felim Larkin, AVEVA XchangeAVEVA World Conference NA - Felim Larkin, AVEVA Xchange
AVEVA World Conference NA - Felim Larkin, AVEVA XchangeAVEVA-Americas
 
Maximizing efficiency using AVEVA & SDS/2 in the real world
Maximizing efficiency using AVEVA & SDS/2 in the real worldMaximizing efficiency using AVEVA & SDS/2 in the real world
Maximizing efficiency using AVEVA & SDS/2 in the real worldAVEVA Group plc
 
Americas LFM User Meeting 2018 - Gary Farrow, LFM
Americas LFM User Meeting 2018 - Gary Farrow, LFMAmericas LFM User Meeting 2018 - Gary Farrow, LFM
Americas LFM User Meeting 2018 - Gary Farrow, LFMVanessa Erickson
 
AVEVA World Conference NA - Greg Lawes, Point3D
AVEVA World Conference NA - Greg Lawes, Point3DAVEVA World Conference NA - Greg Lawes, Point3D
AVEVA World Conference NA - Greg Lawes, Point3DAVEVA-Americas
 
Transformation Time - AVEVA World UK User Meeting
Transformation Time - AVEVA World UK User MeetingTransformation Time - AVEVA World UK User Meeting
Transformation Time - AVEVA World UK User MeetingAVEVA Group plc
 
AVEVA World Conference NA - Bob Ritter, CII
AVEVA World Conference NA - Bob Ritter, CIIAVEVA World Conference NA - Bob Ritter, CII
AVEVA World Conference NA - Bob Ritter, CIIAVEVA-Americas
 
AVEVA presents at the Rice Global Forum 2017
AVEVA presents at the Rice Global Forum 2017AVEVA presents at the Rice Global Forum 2017
AVEVA presents at the Rice Global Forum 2017AVEVA Group plc
 
Transformational Change in Managing Assets for Operational Excellence by Jan ...
Transformational Change in Managing Assets for Operational Excellence by Jan ...Transformational Change in Managing Assets for Operational Excellence by Jan ...
Transformational Change in Managing Assets for Operational Excellence by Jan ...AVEVA Group plc
 
AVEVA World Conference NA - Jesse Trace, AVEVA E3D
AVEVA World Conference NA - Jesse Trace, AVEVA E3DAVEVA World Conference NA - Jesse Trace, AVEVA E3D
AVEVA World Conference NA - Jesse Trace, AVEVA E3DAVEVA-Americas
 

Mais procurados (20)

AVEVA World Conference NA - Cormac Ryan, AVEVA ISM
AVEVA World Conference NA - Cormac Ryan, AVEVA ISMAVEVA World Conference NA - Cormac Ryan, AVEVA ISM
AVEVA World Conference NA - Cormac Ryan, AVEVA ISM
 
AVEVA World Conference NA - Ryan/Avantsa, CFIHOS Workshop
AVEVA World Conference NA - Ryan/Avantsa, CFIHOS WorkshopAVEVA World Conference NA - Ryan/Avantsa, CFIHOS Workshop
AVEVA World Conference NA - Ryan/Avantsa, CFIHOS Workshop
 
AVEVA World Conference NA - Amish Sabharwal, AVEVA Welcome
AVEVA World Conference NA - Amish Sabharwal, AVEVA WelcomeAVEVA World Conference NA - Amish Sabharwal, AVEVA Welcome
AVEVA World Conference NA - Amish Sabharwal, AVEVA Welcome
 
AVEVA World Conference NA - Han Lin, Southern California Gas
AVEVA World Conference NA - Han Lin, Southern California GasAVEVA World Conference NA - Han Lin, Southern California Gas
AVEVA World Conference NA - Han Lin, Southern California Gas
 
AVEVA World Conference NA - Patrick Reilly, Vista Projects
AVEVA World Conference NA - Patrick Reilly, Vista ProjectsAVEVA World Conference NA - Patrick Reilly, Vista Projects
AVEVA World Conference NA - Patrick Reilly, Vista Projects
 
AVEVA World Conference NA - Jim Purvis, WorleyParsons
AVEVA World Conference NA - Jim Purvis, WorleyParsonsAVEVA World Conference NA - Jim Purvis, WorleyParsons
AVEVA World Conference NA - Jim Purvis, WorleyParsons
 
AVEVA World Conference NA - Tom Singer, Aker Solutions
AVEVA World Conference NA - Tom Singer, Aker SolutionsAVEVA World Conference NA - Tom Singer, Aker Solutions
AVEVA World Conference NA - Tom Singer, Aker Solutions
 
AVEVA Integrated Engineering & Design Developments
AVEVA Integrated Engineering & Design DevelopmentsAVEVA Integrated Engineering & Design Developments
AVEVA Integrated Engineering & Design Developments
 
AVEVA World Conference NA - Rabelo/Tedstone, AVEVA ERM & Procon
AVEVA World Conference NA - Rabelo/Tedstone, AVEVA ERM & ProconAVEVA World Conference NA - Rabelo/Tedstone, AVEVA ERM & Procon
AVEVA World Conference NA - Rabelo/Tedstone, AVEVA ERM & Procon
 
AVEVA World Conference NA - AVEVA Procon Panel
AVEVA World Conference NA - AVEVA Procon PanelAVEVA World Conference NA - AVEVA Procon Panel
AVEVA World Conference NA - AVEVA Procon Panel
 
AVEVA’s ERM, Efficient Planning and Management of Project Resources
AVEVA’s ERM, Efficient Planning and Management of Project Resources AVEVA’s ERM, Efficient Planning and Management of Project Resources
AVEVA’s ERM, Efficient Planning and Management of Project Resources
 
AVEVA World Conference NA - Felim Larkin, AVEVA Xchange
AVEVA World Conference NA - Felim Larkin, AVEVA XchangeAVEVA World Conference NA - Felim Larkin, AVEVA Xchange
AVEVA World Conference NA - Felim Larkin, AVEVA Xchange
 
Maximizing efficiency using AVEVA & SDS/2 in the real world
Maximizing efficiency using AVEVA & SDS/2 in the real worldMaximizing efficiency using AVEVA & SDS/2 in the real world
Maximizing efficiency using AVEVA & SDS/2 in the real world
 
Americas LFM User Meeting 2018 - Gary Farrow, LFM
Americas LFM User Meeting 2018 - Gary Farrow, LFMAmericas LFM User Meeting 2018 - Gary Farrow, LFM
Americas LFM User Meeting 2018 - Gary Farrow, LFM
 
AVEVA World Conference NA - Greg Lawes, Point3D
AVEVA World Conference NA - Greg Lawes, Point3DAVEVA World Conference NA - Greg Lawes, Point3D
AVEVA World Conference NA - Greg Lawes, Point3D
 
Transformation Time - AVEVA World UK User Meeting
Transformation Time - AVEVA World UK User MeetingTransformation Time - AVEVA World UK User Meeting
Transformation Time - AVEVA World UK User Meeting
 
AVEVA World Conference NA - Bob Ritter, CII
AVEVA World Conference NA - Bob Ritter, CIIAVEVA World Conference NA - Bob Ritter, CII
AVEVA World Conference NA - Bob Ritter, CII
 
AVEVA presents at the Rice Global Forum 2017
AVEVA presents at the Rice Global Forum 2017AVEVA presents at the Rice Global Forum 2017
AVEVA presents at the Rice Global Forum 2017
 
Transformational Change in Managing Assets for Operational Excellence by Jan ...
Transformational Change in Managing Assets for Operational Excellence by Jan ...Transformational Change in Managing Assets for Operational Excellence by Jan ...
Transformational Change in Managing Assets for Operational Excellence by Jan ...
 
AVEVA World Conference NA - Jesse Trace, AVEVA E3D
AVEVA World Conference NA - Jesse Trace, AVEVA E3DAVEVA World Conference NA - Jesse Trace, AVEVA E3D
AVEVA World Conference NA - Jesse Trace, AVEVA E3D
 

Semelhante a AVEVA World Conference NA - Jeyoung Woo, University of Texas at Austin

Semelhante a AVEVA World Conference NA - Jeyoung Woo, University of Texas at Austin (20)

Genisision – Sales – 012 – Capability Statement Expanded
Genisision – Sales – 012 – Capability Statement ExpandedGenisision – Sales – 012 – Capability Statement Expanded
Genisision – Sales – 012 – Capability Statement Expanded
 
Presentation
PresentationPresentation
Presentation
 
Presentation
PresentationPresentation
Presentation
 
Sr CAD App Engr - Dec 2015
Sr CAD App Engr - Dec 2015Sr CAD App Engr - Dec 2015
Sr CAD App Engr - Dec 2015
 
Mark A Schmier-II
Mark A Schmier-IIMark A Schmier-II
Mark A Schmier-II
 
MVTatel
MVTatelMVTatel
MVTatel
 
Naval Aviation Materials and Manufacturing Workshop: Accelerating Technolog...
Naval Aviation Materials and Manufacturing Workshop:  Accelerating Technolog...Naval Aviation Materials and Manufacturing Workshop:  Accelerating Technolog...
Naval Aviation Materials and Manufacturing Workshop: Accelerating Technolog...
 
Ashwin_L&T
Ashwin_L&TAshwin_L&T
Ashwin_L&T
 
Jim Cloer Process Engineer Resume
Jim Cloer Process Engineer ResumeJim Cloer Process Engineer Resume
Jim Cloer Process Engineer Resume
 
Resume-Aero
Resume-AeroResume-Aero
Resume-Aero
 
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
 
Resume 4md
Resume 4mdResume 4md
Resume 4md
 
IBM Detailed ALM/ELM for Aerospace & Defence overview
IBM Detailed ALM/ELM  for Aerospace & Defence overviewIBM Detailed ALM/ELM  for Aerospace & Defence overview
IBM Detailed ALM/ELM for Aerospace & Defence overview
 
Pes profile
Pes profilePes profile
Pes profile
 
ELBERT SPEED Liaison Resume 3
ELBERT SPEED Liaison Resume 3ELBERT SPEED Liaison Resume 3
ELBERT SPEED Liaison Resume 3
 
Piping Design Engineering
Piping Design EngineeringPiping Design Engineering
Piping Design Engineering
 
Safety by design
Safety by designSafety by design
Safety by design
 
Detailed engineering-design-phase
Detailed engineering-design-phaseDetailed engineering-design-phase
Detailed engineering-design-phase
 
Resume william bickford
Resume william bickford Resume william bickford
Resume william bickford
 
wjc Retres now
wjc Retres nowwjc Retres now
wjc Retres now
 

Mais de AVEVA-Americas

AVEVA World Conference NA - Tom Singer, Aker Solutions
AVEVA World Conference NA - Tom Singer, Aker SolutionsAVEVA World Conference NA - Tom Singer, Aker Solutions
AVEVA World Conference NA - Tom Singer, Aker SolutionsAVEVA-Americas
 
AVEVA World Conference NA - Mike Curtin, Shell
AVEVA World Conference NA - Mike Curtin, ShellAVEVA World Conference NA - Mike Curtin, Shell
AVEVA World Conference NA - Mike Curtin, ShellAVEVA-Americas
 
Americas LFM User Meeting 2018 - Gary Farrow, LFM
Americas LFM User Meeting 2018 - Gary Farrow, LFMAmericas LFM User Meeting 2018 - Gary Farrow, LFM
Americas LFM User Meeting 2018 - Gary Farrow, LFMAVEVA-Americas
 
Americas LFM User Meeting 2018 - Neil Cocker, LFM
Americas LFM User Meeting 2018 - Neil Cocker, LFMAmericas LFM User Meeting 2018 - Neil Cocker, LFM
Americas LFM User Meeting 2018 - Neil Cocker, LFMAVEVA-Americas
 
Americas LFM User Meeting 2018 - Matt Craig, Becht Engineering
Americas LFM User Meeting 2018 - Matt Craig, Becht EngineeringAmericas LFM User Meeting 2018 - Matt Craig, Becht Engineering
Americas LFM User Meeting 2018 - Matt Craig, Becht EngineeringAVEVA-Americas
 
Americas LFM User Meeting 2018 - Graham Dalton, LFM
Americas LFM User Meeting 2018 - Graham Dalton, LFMAmericas LFM User Meeting 2018 - Graham Dalton, LFM
Americas LFM User Meeting 2018 - Graham Dalton, LFMAVEVA-Americas
 
AVEVA World Conference NA - Graham Dalton, LFM
AVEVA World Conference NA - Graham Dalton, LFMAVEVA World Conference NA - Graham Dalton, LFM
AVEVA World Conference NA - Graham Dalton, LFMAVEVA-Americas
 
AVEVA World Conference NA - Thierry Vermeersch, AVEVA Cloud
AVEVA World Conference NA - Thierry Vermeersch, AVEVA CloudAVEVA World Conference NA - Thierry Vermeersch, AVEVA Cloud
AVEVA World Conference NA - Thierry Vermeersch, AVEVA CloudAVEVA-Americas
 

Mais de AVEVA-Americas (8)

AVEVA World Conference NA - Tom Singer, Aker Solutions
AVEVA World Conference NA - Tom Singer, Aker SolutionsAVEVA World Conference NA - Tom Singer, Aker Solutions
AVEVA World Conference NA - Tom Singer, Aker Solutions
 
AVEVA World Conference NA - Mike Curtin, Shell
AVEVA World Conference NA - Mike Curtin, ShellAVEVA World Conference NA - Mike Curtin, Shell
AVEVA World Conference NA - Mike Curtin, Shell
 
Americas LFM User Meeting 2018 - Gary Farrow, LFM
Americas LFM User Meeting 2018 - Gary Farrow, LFMAmericas LFM User Meeting 2018 - Gary Farrow, LFM
Americas LFM User Meeting 2018 - Gary Farrow, LFM
 
Americas LFM User Meeting 2018 - Neil Cocker, LFM
Americas LFM User Meeting 2018 - Neil Cocker, LFMAmericas LFM User Meeting 2018 - Neil Cocker, LFM
Americas LFM User Meeting 2018 - Neil Cocker, LFM
 
Americas LFM User Meeting 2018 - Matt Craig, Becht Engineering
Americas LFM User Meeting 2018 - Matt Craig, Becht EngineeringAmericas LFM User Meeting 2018 - Matt Craig, Becht Engineering
Americas LFM User Meeting 2018 - Matt Craig, Becht Engineering
 
Americas LFM User Meeting 2018 - Graham Dalton, LFM
Americas LFM User Meeting 2018 - Graham Dalton, LFMAmericas LFM User Meeting 2018 - Graham Dalton, LFM
Americas LFM User Meeting 2018 - Graham Dalton, LFM
 
AVEVA World Conference NA - Graham Dalton, LFM
AVEVA World Conference NA - Graham Dalton, LFMAVEVA World Conference NA - Graham Dalton, LFM
AVEVA World Conference NA - Graham Dalton, LFM
 
AVEVA World Conference NA - Thierry Vermeersch, AVEVA Cloud
AVEVA World Conference NA - Thierry Vermeersch, AVEVA CloudAVEVA World Conference NA - Thierry Vermeersch, AVEVA Cloud
AVEVA World Conference NA - Thierry Vermeersch, AVEVA Cloud
 

Último

Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptJasonTagapanGulla
 

Último (20)

Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.ppt
 

AVEVA World Conference NA - Jeyoung Woo, University of Texas at Austin

  • 1. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Presentation Overview The quality and completeness of engineering design deliverables have a significant impact on overall project performance. Thus, project stakeholders should pay close attention to such issues, with a particular focus on problematic engineering design deliverables. This presentation summarizes the findings of the Construction Industry Institute (CII) Research Team (RT) 320, Definition and Measurement of Engineering/Design Deliverable Quality, including the 11 most problematic deliverables and their significant defects, causal factors, leading/lagging metrics, and two implementation tools.
  • 2. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Houston, TX. February 14, 2018 James T. O’Connor, P.E., Ph.D. Jeyoung Woo, P.E. Eliminating Quality Defects on Problematic Engineering Design Deliverables
  • 3. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. ~ $75 billion/year 5.4% of total construction cost Leading cause = Design Errors/Omissions! 14.2 % of Contract value Direct + Indirect Case for Action (1/2) Direct Cost of Rework (CII 2004) Cost of Rework (Hwang et al. 2009) Average Cost of Design Errors (Love et al. 2014)
  • 4. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Case for Action (2/2) Impact of Design Quality Poor quality deliverables Design Phase Construction Phase Rework Project Performance (Burati et al. 1992; Eldin 1991; Gransberg and Molenaar 2004; Haydl and Nikiel 2000)
  • 5. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Dale C. Allen Shell Ronald August, Jr. AECOM Robert Beskow Chevron Lin Budlong General Electric Daniel C. Chabot Cargill, Inc. Michael T. Cleary DuPont Kim Crovetto Hargrove John Hyland Lauren Oscar L. Monagas ConocoPhillips Donald L. Myers U.S. Department of VA CII Research Team (RT) 320 Period: 2014/09 – 2016/08 21 Members Dr. James T. O'Connor UT-Austin Jason Phillips ArcelorMittal Glenn Raz OXY Matt Rouse CDI Hulya Schwimmbeck CB&I Joel K. Strang Fluor Gilberto Teixeira Jr. Petrobras Kelly Watson OXY Nancy E. Wilkie U.S. DoS Jeyoung Woo UT-Austin Carlton Wright Technip
  • 6. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Research Objectives • Identify problematic design deliverables, their defects & causes, and metrics that facilitate proactive, preventive actions (O’Connor and Woo 2016)
  • 7. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. IN-Scope Design deliverable completeness & correctness Design errors and omissions OUT-of-scope Cost of design efforts Cost estimate based on engineering deliverables Research Scope Detailed design phase of industrial projects Concept Detailed scope Procurement Fabrication/ Delivery Construction Detailed Design Project Funding Approval IFC (Issued for Construction)
  • 8. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Design Quality Essentials Essential criteria of design quality Timely Quality (Andi and Minato 2003; O’Connor et al. 2007; Tilley et al. 1997)
  • 9. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Research Flow: Facilitating Action Team Action Quality Detailed Design 53 Detailed Design Deliverables 11 Problematic Deliverables Causal Factors (n=351) Leading/Lagging Metrics (n=141) & Definitions TWO Tools - Leading Metrics Tool - Completeness Checklist Usage: Awareness Deliverable Quality Threats Validation: Application Demonstration (798 Defects) 3 Defect Categories Priorities Defect Impacts Frequency Severity
  • 10. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Research Methodology 53 DELIVERABLES 11 Problematic Deliverables 798 DEFECTS 145 UNIQUE DEFECTS 73 Significant Defects 349 Causal Factors 23 Lagging Metrics 118 Leading Metrics Frequency Consolidation Impact priority Two Implementation Tools (DDQA / CDDC)
  • 11. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. 53 Engineering Design Deliverables (1/2) No. Deliverable No. Deliverable 1 Front-End Engineering Design (FEED) Validation 14 3D Model 2 Piping material classes 15 Standard piping details 3 Process data sheets 16 Standard civil details 4 Mechanical data sheets 17 Standard site details 5 Instrument data sheets 18 Standard architecture details 6 Piping & Instrumentation Diagrams (P&IDs) 19 Standard electrical details 7 Stress critical line list 20 Vendor data 8 Line list requiring hydraulic check 21 Equipment list 9 Plot plan 22 Mechanical equipment model volumes 10 Safety review 23 Duct model volumes 11 Constructability Inputs 24 Single line routing 12 Maintainability Inputs 25 Cable/ cable tray routing 13 Level 3 Baseline Schedule 26 Cathodic protection
  • 12. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. 53 Engineering Design Deliverables (2/2) No. Deliverable No. Deliverable 27 Structure modeling 40 Underground services 28 Electrical equipment/building envelopes 41 Piping routing and isometrics 29 Control equipment/building envelopes 42 Stress analysis 30 Nozzles, ladders, and platforms for towers/vessels/tanks 43 Hydraulic checks 44 Model updates 31 3D model reviews 45 Bulk material takeoff 32 Structural stress loads 46 Equipment specifications 33 Structure design 47 Inline instrument data 34 Fire protection study 48 Miscellaneous pipe supports drawings 35 Earthwork 49 Electrical design 36 Roads 50 Junction box location 37 Piling 51 Instrumentation design 38 Foundations 52 Lighting 39 Fencing 53 Clash detection
  • 13. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Survey questionnaire Relative frequency of quality problematic deliverables Survey respondents Problematic Deliverables Survey Design Option Very Rarely Sometimes Too Often Don’t know Point value 1.0 3.0 5.0 0.0 Owner Contractor Total Number of respondents 34 33 67 Industry Experience Total years 861 1,063 1,924 Average years 25.3 32.2 28.7
  • 14. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Problematic Deliverables Distribution of Results 46. Equipment Specifications & Data Sheets 6. P&IDs (Piping & Instrumentation Diagrams) 11. Constructability Inputs 13. Level 3 Baseline Schedule 20. Vendor Data 30. Nozzles, Ladders, and Platform for Towers/Vessels/Tanks 48. Miscellaneous Pipe Support Drawings 41. Piping Routing and Isometrics 1. FEED (Front-End Engineering Design) Validation Deliverables 12. Maintainability Inputs 14. 3D Model & 53. Clash Detection
  • 15. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Problematic Deliverables Survey Results Scale: 1.0 = Very Rarely 3.0 = Sometimes 5.0 = Too Often 41 (77%) 10 (19%) 2 (4%) 0 5 10 15 20 25 30 35 40 45 Less than 3.0 3.0 - 3.5 Greater than 3.5 NumberofDeliverables (n=53) Most Problematic
  • 16. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Validation: Statistical Analysis (t-Test) Problematic vs. Non-Problematic Deliverables: Very Different Owners vs. Contractors (11 Prob. Deliverables): Very Similar Problematic Deliverables (n=11) Other Deliverables (n=41) Mean St.Dev. Mean St.Dev. t-score df p-value Relative Frequency of Design Quality Problems 3.22 0.28 1.92 0.49 11.43 29 <.001 (Sig.) Owners (n=34) Contractors (n=33) Mean St.Dev. Mean St.Dev. t-score df p-value Relative Frequency of Design Quality Problems 3.25 0.09 3.19 0.11 0.68 10 0.50 (N.S)
  • 17. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Impact Screening Type: Completeness, Correctness, and Timeliness Data Analysis Defects Causal Factors Leading Metrics Lagging Metrics Identified by using “5-Whys” approach Associated with 349 causal factors Associated with 73 significant defects
  • 18. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Data Analysis Example (1/4) Deliverable: Constructability Inputs Defects Failure to develop and incorporate standard design elements
  • 19. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Data Analysis Example (2/4) Deliverable: Constructability Inputs Defects Defect Impacts Failure to develop and incorporate standard design elements Design and construction productivity losses
  • 20. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Data Analysis Example (3/4) Deliverable: Constructability Inputs DefectsCausal Factors Defect Impacts Failure to develop and incorporate standard design elements Failure to recognize the beneficial tradeoffs from standardization Design and construction productivity losses
  • 21. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Data Analysis Example (4/4) Deliverable: Constructability Inputs DefectsCausal Factors Defect Impacts Leading Metrics Lagging Metrics Did the project owner and/or contractor utilize standardization resources during the design (e.g., PIP.org or its equivalent in other industry sectors)? Field rework hours resulting from inadequate constructability input/reviews
  • 22. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Defects Analysis Table No. 3. Constructability Inputs No. Significant Defect Defect Type Impact Type Relative Freq. Relative ImpactSev. Priority Score Causal Factor Metric Leading Lagging 10 Constructability reviews are conducted too late Timeliness - Late or additional changes - Redesign - Schedule impacts - Increased cost H H 9 - Not involving knowledgeable resources at the right time - Not scheduling constructability reviews at the right time (sufficiently in advance) - Low schedule priority of constructability reviews - Late contractor involvement in constructability - Disincentives for contractors to participate in Constructability - Lack of contractor interest in pre-construction services 1) At least one constructability review meeting is conducted in early FEED/ Design Development or before? 2) The second constructability review meeting is conducted at or before the end of FEED/ Design Development? 3) The third constructability review meeting is conducted at or before the 60% design complete? 4) Were the constructability reviews conducted too late to incorporate comments into the design? Leading Leading Leading Lagging
  • 23. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Timing of Metrics Concept Detailed scope Procurement Fabrication/ Delivery Construction Detailed Design FV 1 30% 2 60% 2 90% 2 IFC 3 IFP 4 Leading Indicators Lagging Indicators 1 FV: FEED Validation 2 30%, 60%, 90%: Detailed Design Progress 2 IFC: Issued for Construction 3 IFP: Issued for Procurement
  • 24. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Helps assess current levels of deliverable quality Helps identify associated potential defects Facilitates planning/documentation of defect mitigation strategies Two Implementation Tools Design Deliverable Quality Assessment (DDQA) Tool Completeness of Design Deliverable Checklist (CDDC) Tool Helps assess current level of deliverable completeness Helps identify content inclusion items that need to be completed
  • 25. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. DDQA Tool Input - Targeted Design Deliverables - Targeted Design Progress - Leading Metrics
  • 26. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. DDQA Tool Output - Design Quality Indices - List of Potential Defects (Prompting discussion)
  • 27. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. CDDC Tool Input - Targeted Design Deliverables - Completeness of Checklist Items
  • 28. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. CDDC Tool Output - Completeness Index - List of Incomplete Items
  • 29. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Recommended Timing of Completeness Assessment No. Deliverable Detailed Design Progress FV1 30%2 60%2 90%2 IFC3 1 Front-End Engineering Design (FEED) Validation X 2 Level 3 Baseline Schedule X 3 Constructability Inputs X X 4 Piping & Instrumentation Diagrams (P&IDs) X 5 Equipment Specifications & Data Sheets X X 6 Maintainability Inputs X X 7 Vendor Data X X 8 3D Model & Clash Detection X X 9 Piping Routing & Isometrics X X 10 Nozzles, Ladders, Platforms for Towers/Vessels/Tanks X X 11 Miscellaneous Pipe Support Drawings X1 FV: FEED Validation 2 30%, 60%, 90%: Detailed Design Progress 3 IFC: Issued for Construction
  • 30. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Tool-related Responsibilities Responsibility Job Titles Sponsor • Business Unit Engineering Director • Business Unit Quality Director Accountable • Project Managers (Owner and/or Contractor) • Project Design/Engineering Manager Responsible • Design Discipline Leads • Project Engineer/Coordinator Consult • Construction Managers • Maintenance Representatives • Operations Representatives • Project Controls Representatives
  • 31. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Tool Validation 18+ yrs. experience each 18 External Reviewers 215 Feedback Comments 18 External Reviewers Mostly Compliments Most others Already Addressed, Minor, or Out-of-Scope “Effective” in contributing to Project Design Quality “Likely” to be used on future project
  • 32. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Conclusions • Identified 11 most problematic deliverables • Identified 73 significant defects for problematic deliverables • Identified 118 leading metrics associated with causal factors • Identified 23 lagging metrics associated with 73 defects • Developed Two implementation tools (DDQA / CDDC)
  • 33. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Acknowledgements Construction Industry Institute (CII) CII Research Team 320 103 Survey Respondents 67 respondents for problematic deliverables survey 36 respondents for deliverable defects survey Dale C. Allen Shell Ronald August, Jr. AECOM Robert Beskow Chevron Lin Budlong General Electric Daniel C. Chabot Cargill, Inc. Michael T. Cleary DuPont Kim Crovetto Hargrove John Hyland Lauren Oscar L. Monagas ConocoPhillips Donald L. Myers U.S. Department of VA Dr. James T. O'Connor UT-Austin Jason Phillips ArcelorMittal Glenn Raz OXY Matt Rouse CDI Hulya Schwimmbeck CB&I Joel K. Strang Fluor Gilberto Teixeira Jr. Petrobras Kelly Watson OXY Nancy E. Wilkie U.S. DoS Jeyoung Woo UT-Austin Carlton Wright Technip
  • 34. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. References Andi and Minato, T. (2003) “Design documents quality in the Japanese construction industry.” Int’l J. Project Management, 21. 537-546. Burati, J.L, Farrington, J.J., and Ledbetter, W.B. (1992). “Causes of Quality Deviations in Design and Construction.” J. Construction Engineering and Management, 118(1), 34-49. Construction Industry Institute (CII) (2004). “Making Zero Rework a Reality.” Research Summary 203-1. Austin, TX. East, E.W., Kirby, J.G. and Perez, G. (2004). “Improved Design Review through Web Collaboration.” J. Management in Engineering, 20 (2), 51-55. Eldin, N. N. (1991). “Management of Engineering/Design Phase.” J. Construction Engineering and Management, 117 (1), 163-175. Gransberg, D.D., and Molenaar, K. (2004). “Analysis of Owner’s Design and Construction Quality Management Approaches in Design/Build Projects.” J. Management in Engineering, 20 (4), 162-169. Haydl, H.M. and Nikiel, A.W. (2000). “Design and Construction Errors – Case Studies.” Practice Periodical on Structural Design and Construction, 5 (3), 126-130. Hwang, B., Thomas, S., Haas, C., and Caldas, C. (2009). “Measuring the Impact of Rework on Construction Cost Performance.” J. Construction Engineering and Management, 135(3), 187-198. Love, P., Lopez, R., Kim, J., and Kim, M. (2014). “Probabilistic Assessment of Design Error Costs.” J. Performance of Constructed Facility, 28(3), 518-527 Nigro, W. T. (2013). “RediCheck Interdisciplinary Coordination.” 4th Edition, Peachtree City, GA. O’Connor, J.T., O'Brien, W.J., Jarrah, R.T., and Wallner, B. (2007). “Planning for facilitating, and evaluating design effectiveness” Research Report 233-11, Construction Industry Institute, The University of Texas at Austin, Austin, TX. O’Connor, J.T., and Woo, J. (2016). “Study of Engineering/Design Deliverable Quality.” Research Report 320-11, Construction Industry Institute, The University of Texas at Austin, Austin, TX. Soibelman, L., Liu, L. Y., Kirby, J.G., East, E.W., Caldas, C.H., and Lin, K. (2003). “Design Review Checking System with Corporate Lessons Learned.” J. Construction Engineering and Management, 129 (5), 475-484. Tilley, P., Wyatt A., and Mohamed, S.. (1997) "Indicators of design and documentation deficiency." IGLC-5: Proceedings of the Fifth Annual Conference of the International Group for Lean Construction, 16-17 July, 1997, Gold Coast, Australia.
  • 35. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. Jeyoung Woo / P.E., P.M.P Ph.D. Candidate The University of Texas at Austin woo.jeyoung@utexas.edu
  • 36. © 2017 AVEVA Solutions Limited and its subsidiaries. All rights reserved. This presentation may include predictions, estimates, intentions, beliefs and other statements that are or may be construed as being forward- looking. While these forward-looking statements represent our current judgment on what the future holds, they are subject to risks and uncertainties that could result in actual outcomes differing materially from those projected in these statements. No statement contained herein constitutes a commitment by AVEVA to perform any particular action or to deliver any particular product or product features. Readers are cautioned not to place undue reliance on these forward-looking statements, which reflect our opinions only as of the date of this presentation. The Company shall not be obliged to disclose any revision to these forward-looking statements to reflect events or circumstances occurring after the date on which they are made or to reflect the occurrence of future events.