LA MTA Hardware Guide Specification                                          2-09


PART 1: GENERAL


      1.     01    Summary

             A.     Section Includes:

                   1.     Work under this section comprises the furnishing and installation
                          of hardware specified herein and noted on drawings for a
                          complete and operational system, including any electrified
                          hardware components, systems and controls.
                   2.     Related documents, drawings and general provisions of contract,
                          including General and Supplementary Conditions, and Division 1.
                   3.     Items include but are not limited to the following:
                          a.      Hinges
                          b.      Exit Devices
                          c.      Locksets
                          d.      Push/Pull Plates
                          e.      Automatic Flush Bolts
                          f.      Closers
                          g.      Kick, Mop and Protection Plates
                          h.      Stops and Overhead Controls
                          I.      Thresholds, Gasket and Door Bottoms
                          j.      Miscellaneous Accessories and Trim

             B.    Related Work:
                          Section 06200 - Finish Carpentry.
                                       Section 08110 - Hollow Metal Work.
                                       Section 08210 - Wood Doors.
                                       Sections within 08800 - Glazing.
                                       Sections within 09900 - Painting.

      1.     02    Substitutions

             A.    References to specific products are used to establish minimum
                   standards of utility and quality. Unless otherwise approved, furnish only
                   the specified products.

             B.    Requests for substitutions to be in accordance with Division 1, General
                   Requirements. Proposed substitutions must be submitted in writing and
                   hand delivered to the architect. Approvals must be by addendum ten
                   [10] days prior to bid opening. Review will include the lock shop rep.

             C.    Requests to be accompanied by two [2] copies of the manufacturer's
                   brochures and sample of each item in the appropriate design and finish.


                                   DOOR HARDWARE
                                      08710 - 1
LA MTA Hardware Guide Specification                                             2-09



                D.   Should the contractor make any substitutions without the written consent
                     of the architect and owner, contractor shall remove all substituted
                     hardware, replacing same with the hardware as specified and at no
                     additional cost to the building owner.

      1.   03        References

                A.   References specified in this section subject to compliance as directed
                     and shall meet requirements of Federal, State and local codes having
                     jurisdiction over this project including:

                B.   Hardware that is furnished and/or installed that does not meet code
                     requirements, shall be removed and replaced with correct material at no
                     additional expense to the building owner.
                     1.      CCR - California Code of Regulations Title 24.
                     2.      ADA - American Disabilities Act - Title III - Public
Accommodations.
                     3.     NFPA 80 2007 - Standard for Fire Doors and Windows.
                     4.     NFPA 101 2009 - Life Safety.
                     5.     ITS - Intertek Testing Service [Warnock Hersey].
                     6.     UL - Underwriters Laboratories.
                     7.     ANSI/BHMA A156 Product Listing.
                     8.     CBC - CA Bldg Code, Local Codes and Authority having
                            Jurisdiction.
                     9.     UL 10C for Positive Pressure Fire Tests of Door Assemblies and
                            UBC 7-2.

      1.        04   Quality Assurance

                A.   Product Uniformity: Except where specified, all hinges, keyed cylinders,
                     electro-mechanical components, locksets, latchsets, exit devices,
                     closers, overhead stop/holders and component parts shall be furnished
                     by one manufacturer.

                B.   Rated Openings: Hardware used in labeled fire or smoke rated
                     openings to be listed for those types of openings and bear the identifying
                     label or mark indicating U.L. [Underwriter's Laboratories] approved for
                     fire. Exit devices in non-labeled openings shall be listed for panic.

                C.   Supplier: Shall be responsible for detailing hardware that meets project
                     standards and where appropriate, retrofit applications which require
                     inspection of openings prior to detailing and ordering respective
                     hardware items.



                                    DOOR HARDWARE
                                       08710 - 2
LA MTA Hardware Guide Specification                                              2-09


             D.     Pre-Installation Conference: Prior to installation of hardware, arrange a
                    conference between supplier, installers, and related trades to review
                    materials, procedures, hardware mounting locations and related work.

             E.     Post-Installation Policing: Will be required by the hardware supplier,
                    contractor and architect to determine compliance with the hardware
                    specification and building standards. Punch list to be completed by MTA
                    Locksmith, hardware contractor and contractor.

             F.       Supplier Qualifications:
             01.      Hardware supplier must be a recognized, Factory Direct contract
             distributor with a minimum five (5) years experience specializing in institutional
             grade builder’s hardware of the type specified herein. Distributors with less than
             two (2) years of history of furnishing builders hardware in the project's vicinity
             will not be acceptable.
                             2.       Supplier must have in his/her employment on a full time
                             basis, or as a consultant to the supplier, a Certified Hardware
                             Consultant [AHC] or person of equal experience who is
                             acceptable to the Architect and CM. This individual shall be
                             available for consultation and service to the architect, contractor,
                             and building owner during construction and on an ongoing
                             consulting service to the building owner following the completion
                             of the project.
                             3.       Supplier who does not maintain personnel in a permanent
                             facility within a reasonable driving radius of the project area for
                             consultation and service with the architect, contractor and
                             building owner will not be acceptable.

      1.     05     General Requirements

             A.     Coordination: Coordinate as necessary with other trades to assure
                    proper and adequate provision in the work of those trades for interface
                    with the work of this Section.

             B.     Sequencing and Scheduling: Any part of the finish hardware required by
                    the frame or door manufacturers or other suppliers, that is needed in
                    order to produce doors or frames is to be sent to those suppliers in a
                    timely manner.

             C.     Defective Hardware: All hardware shall be new and free from defects
                    affecting both serviceability and appearance. Working parts shall be
                    properly fitted, smooth working and without excessive play.

             D.     Function/Modification:
                    1.     Should any hardware fail the intended operational requirements


                                    DOOR HARDWARE
                                       08710 - 3
LA MTA Hardware Guide Specification                                            2-09


                          or require any modification to suit the intended location, this
                          matter, or any other necessary advance information shall be
                          brought to the attention of the architect for correction or advice in
                          ample time to avoid delay in the manufacture and delivery of the
                          hardware.
                   1. Modifications to specified hardware, required by reason of
                   construction characteristics, shall be furnished in the specified
                   operational, functional features, quality and finish. Modifications shall be
                   subject to acceptance of the architect at no additional cost to the building
                   owner.
                   2. Items of hardware not specified herein but necessary for completion of
                   the work shall be furnished at no additional cost to the district. Such
                   items shall be of the type specified and comparable to adjacent
                   hardware.

             E.    Doors and Frames: Hollow metal and wood doors shall be manufactured
                   to templates. If required, physical hardware items shall be furnished to
                   related manufacturers in sufficient time to avoid delay in work.

             E.    Electrical Coordination: Before electrically controlled or operated
                   hardware is ordered, voltages and wiring details shall be coordinated
                   with the contractor and related trades.

             G.    Existing [Modernization] Openings

                   Contractor is responsible for a field survey of doors, frames and
                   hardware to determine compatibility of specified hardware, including, but
                   not limited to: locksets, panic devices, strikes, flushbolts, overhead
                   stops, coordinators, closers, threshold/seal, hinge sizes and weights
                   including wide throw hinges.

                   Unless directed otherwise, Contractor to modify openings to meet ADA
                   elevation threshold requirements. Contractor to survey and where
                   necessary, furnish and install ADA approved ramp threshold systems
                   where applicable and approved by the architect. Work shall comply with
                   minimum ADA specifications as well as create a flat sub-surface for
                   specified thresholds.

                   Existing doors and frames to be modified for hardware as permitted by
                   UL, WHI and local code authority. Where required, contractor shall cut
                   and weld necessary reinforcements to existing jambs and doors, for
                   listed hardware as applicable and required. Contractor to patch sand and
                   repaint/refinish reused door(s) and frame(s) surfaces affected by the
                   removal of hardware, and any modification for replacement hardware.



                                   DOOR HARDWARE
                                      08710 - 4
LA MTA Hardware Guide Specification                                            2-09


                    Whether listed or not, contractor shall furnish frame/door hinge, strike,
                    lock face, panic, closer and overhead auxiliary stop fillers where required
                    for a clean finished appearance. Related costs to field modify existing
                    frames and/doors shall be part of the Contractor's base bid and shall
                    include a $500.00 allowance each site for door and frame fillers.
                    Contractor to allow for the above dollar amount in the base bid.

                    Intertek Testing Service or UL inspection and certification is required for
                    the labeling of non-rated doors and frames, and the modification of any
                    labeled door and frame. Contractor is responsible for contacting and
                    coordinating this required labeling service.

                    The Contractor is responsible for the careful removal, treatment and
                    delivery of all existing replaced and any unused new hardware to the
                    building owner.

              H.    Bar Coding of Door/Frame openings

                    All door/frame openings will have a bar code label attached to the frame
                    near the upper door hinge. The bar code labels will be supplied to the
                    contractor by the MTA Key Shop. Contractor will supply a list of all
                    openings that includes the installed hardware, door number, location,
                    and bar code number in a Microsoft Excel 2003 compatible format.

      1. 06   Submittals

              A.    Hardware Schedule:           Submit typewritten copies of schedule in
                    accordance with Division 1, General Requirements. Schedule to be in
                    vertical format, listing each door opening including; location, handing of
                    opening, all hardware scheduled for each opening or otherwise required
                    to allow for proper function of door opening as intended, finish of
                    hardware, and respective manufacturers. Doors with closers or door
                    controls shall require the degree of door opening.
                    1.      Supply six [6] copies of the schedules within fifteen [15] working
                            day from date of purchase order.
                            a.      The hardware schedule shall conform to DHI's:
                                    "RECOMMENDED PROCEDURE FOR PROCESSING
                                    HARDWARE SCHEDULES AND TEMPLATES."
                            b.      Submit manufacturers' catalog cut sheets of all hardware
                                    items scheduled and any required special mounting
                                    instructions with the hardware schedule.
                            c.      Include recommended mounting location data for each
                                    type of scheduled door hardware. If specified, include
                                    electrified hardware.
                    2.      No hardware item shall be delivered until the hardware schedule


                                   DOOR HARDWARE
                                      08710 - 5
LA MTA Hardware Guide Specification                                           2-09


                          has been approved by the architect.
                   3.     Approval of the hardware schedule by the architect does not
                          relieve the hardware supplier from the responsibility of furnishing
                          the job complete.

             B.    Samples:
                   1.    If directed by the architect, submit physical samples of each item
                         of hardware proposed in work.
                   2.    Samples will be returned on the request of and at the expense of
                         the general contractor.

             C.    Manufacturer's Catalog Illustrations and Hardware Data:
                   1.    Hardware Supplier shall submit, to the Architect, two [2] catalog
                         cuts of every item of hardware furnished for this project. Data
                         shall be contained in a binder appropriately divided by the
                         respective mfrs.
                   2.    Cuts shall include manufacturer's illustrations and shall identify
                         finishes, sizes and product numbers. Abbreviations to be fully
                         explained.

             D.    Operational Data:
                   1.     Deliver to the building owner through the architect,
                                  a.       One (1) set of factory catalogues for hardware
                                  listed in the approved hardware list.
                          b.      One (1) copy factory generated bitting list.
0                         c.      One (1) copy of approved door hardware shop drawings.
                          d.      One (1) copy of door and hardware specifications.

             E.    Templates: Templates for door hardware items to be sent to related
                   door and frame suppliers within three [3] working days of receipt of
                   approved hardware schedule. Templates shall not be issued until the
                   door hardware schedule has been reviewed and approved by the
                   architect.

             F.    Certification Of Compliance: Submit any information necessary to
                   indicate compliance to any or all of these specifications as required.

             G.    Keying Schedule:
                   1.     Submit three [3] copies of a separate detailed keying schedule to
                          the contractor.
                   2.     Indicate keying of all cylinders, exit devices, locksets, and
                          padlocks. Include door and item numbers as set forth in the
                          approved hardware schedule.
                   3.     Keying data shall follow "KEYING SYSTEMS AND
                          NOMENCLATURE" as established by DHI.


                                  DOOR HARDWARE
                                     08710 - 6
LA MTA Hardware Guide Specification                                           2-09


                   4.     Include with the schedule a keying schematic layout
                   5.     Prior to placing a factory order, the key schedule shall be
                          approved in writing by the building owner and contractor.
                   6.     Keying to be done by MTA Key Shop. Contractor shall supply
                          “construction I/C cores” for all locking hardware during
                          construction of the project. The change key and control keys for
                          the construction cores shall be delivered to the MTA Key Shop
                          before the project is turned over to MTA.

                   1.     07     Delivery, Storage and Handling

             A.    Packaging: Each unit of hardware shall be individually packaged in the
                   manufacturer's original containers as required by the respective
                   hardware manufacturers.
                   1.    Packaging shall include factory original installation instructions,
                         fastenings and all items necessary for complete installation.

             B.    Wrapping: Wrap and cushion each item to prevent scratches and dents
                   during delivery and storage.

             C.    Environmental Packaging: Hardware shipped to the jobsite is to be
                   packaged in biodegradable packs, such as paper or cardboard boxes
                   and wrapping. If non-biodegradable packing is utilized, such as plastic,
                   plastic bags or Styrofoam, then the Contractor will be responsible for the
                   disposal of the non-biodegradable packing to a licensed or authorized
                   collector for recycling of the material.

             D.    Markings: Each package shall be clearly marked on the outside,
                   identifying contents with specific opening number corresponding to those
                   listed in the hardware schedule. Include door and item number for each
                   product.

             E.    Delivery: Except as dictated otherwise, deliver all hardware to the job
                   site. The contractor and hardware supplier's representative shall check
                   each item of hardware against the approved finish hardware schedule.

             F.    Storage: All hardware shall be stored in a locked storage space until
                   ready for installation. Hardware shall be protected against damage after
                   application and during construction period.

      1.     08    Warranty

             A.    All door hardware shall be supplied with the following warranties against
                   defects in materials and workmanship commencing with substantial
                   completion of job. The following warranties are subject to listings of


                                  DOOR HARDWARE
                                     08710 - 7
LA MTA Hardware Guide Specification                                              2-09


                    approved manufacturers.
                    1.    Door Closers:           Ten years.
                    3.    Cylindrical Locksets:   Seven years.
                    4.    Exit Devices:           Five years
                    7.    Electromechanical:      Two years.

             B.     One year warranty for the balance of listed hardware.


PART 2: PRODUCT:

      2.     01     Manufacturers

             A.      Acceptable Manufacturers:
             0       1.     All materials or products specified herein shall be furnished as
             specified. Refer Para. 1.02 SUBSTITUTIONS.
                                   2.       Any proposed deviation from listed standards will be
                            reviewed in writing by the building owner’s authorized
                            representatives.

                    PRODUCT               SPECIFIED     MFRS APPROVED MFRS
                    Cont Hinge      McKinney             Markar
                    Butt Hinge      McKinney             Hager, Bommer
                    Cylinders       Stanley-Best         Stanley-Best
                    Exit Device     Von Duprin           Corbin Russwin, Detex, Yale
                    Closer          LCN                  Corbin Russwin, Norton, Yale
                    Push/Pull/KP    McKinney             Rockwood, Trimco
                    Flushbolts      McKinney             Rockwood, Trimco
                    Door Control    McKinney             Rockwood, Trimco
                    O.H. Stop       Rixson               Sargent
                    Door Stop       McKinney             Rockwood, Trimco
                    Thresh/Seal     McKinney             Pemko
                    Door Locks      Sargeant             Stanley-Best,   Schlage,     Corbin


     2.      02     Fastenings

             A.     Furnish hardware with all necessary screws, bolts or other fastenings of
                    suitable type and size to anchor the hardware in position for long life and
                    heavy use. Fasteners shall include expansion shields, sex bolts, toggle
                    bolts, or other approved anchors according to material to which it is
                    applied and as recommended by the respective manufacturers.

             B.     With the exception of flat goods, self-drilling or self-tapping screws are
                    unacceptable in this work. Where used, only factory furnished self-


                                    DOOR HARDWARE
                                       08710 - 8
LA MTA Hardware Guide Specification                                           2-09


                   drilling fasteners are permitted. All moving hardware including hinges,
                   locksets, panic devices, door closers and overhead stops are to be
                   installed with factory furnished machine screws. Exceptions must be
                   reviewed and approved by an authorized building owner’s representative
                   and submitted in writing to the project architect, hardware consultant and
                   construction manager prior to commencement of any work

             C.    Design of all fastenings shall harmonize with hardware as to material
and                      finish.

0     2.     03    Hinges

             A.    All hinges and pivots, including single and double acting types and
                   pocket hinges to be of one manufacturer as listed for continuity and
                   consideration of warranty.

             B.    Unless otherwise specified, furnish five-knuckle as specified; button tip,
                   full mortise template type hinges with non-rising loose pins.

             C.    Out-swinging exterior doors to be furnished with non-removable pins
                   [NRP] or Continuous Hinges where specified and required by owner.

             D.    Exterior doors to be furnished with heavy weight T4A3386, polished and
                   plated to BHMA 626 finish.

             D.    Interior doors to be furnished with standard weight TA2314, polished and
                   plated to BHMA 626 finish.

             E.    Furnish three [3] hinges up to 90 inches high and one [1] additional
                   hinge for every 30 inches or fraction thereof.

             F.    Furnish standard weight hinges on doors up to 36 inches in width, and
                   extra heavy weight on doors exceeding 36" or as indicated in the
                   hardware schedule.

             G.    Furnish 4.5 x 4.5 inch for all 1- 3/4 inch thick doors up to 36 inch wide,
                   and 5 x 4.5 over 36 inch wide. Doors over 1-3/4 inch thru 2-1/4 inch
                   thick, use 5 x 5 inch hinges. Furnish McK WT-T4A3386 5x6, 5x7 as
                   dictated at wide throw conditions.

             H.    Where required, furnish hinges of sufficient width to clear trim and/or
                   permit the door to swing 180 degrees as required by the specific
                   opening.

             I.    Furnish oil-impregnated bearing hinges at doors with door closers and/or


                                  DOOR HARDWARE
                                     08710 - 9
LA MTA Hardware Guide Specification                                            2-09


                   overhead stops.

             J.      No Electrified hinges allowed. Provide Securitron EPT power transfer.


      2.     03A   Continuous Hinges

             A.    Hinge line to be available in concealed flush mount with or without inset,
                   full- surface and half-surface types as specified in the hardware sets.
                   Furnish wide throw hinges as required to clear trim permitting doors to
                   open 180 degrees.

             B.    All hinges to be made of 14 GA. type 304 Stainless Steel with concealed
                   teflon-coated stainless steel pin, and twin self-lubricated nylon bearings
                   at each knuckle.

             C.    All hinges to be UL listed up to and including three (3) hours.

             D.    All concealed hinges to be fire-rated 20, 45 and 90 minutes when
                   incorporated into proper door and frame labeled installations without
                   necessitating the use of fusible link pins.

             E.    All hinges to be available in standard and extra heavy-duty weight
                   mortise and wide throw where required.

             F.    All hinges to be factory cut for door size.

             G.    No Electrified hinges allowed. Provide Securitron EPT power transfer.

             H.    Continuous hinges only as directed by owner.

      2.     04    Cylindrical Locks

             A.    All cylindrical locks, trim and cylinders to be the product of a single
                   manufacturer for continuity of design and consideration of warranty.

             B.    Locksets shall be Sargent 28-70-11 Line Series x LL trim.

              C.   All Locksets shall be able to withstand 2400 inch pounds of torque applied to
the                                                                        locked lever without
gaining access.

             D.    Locksets shall be cycle tested per ANSI A156.2, 1996, to two million
                   cycles without any visible lever sag.



                                   DOOR HARDWARE
                                      08710 - 10
LA MTA Hardware Guide Specification                                                  2-09


               E.      Locksets shall be able to fit a standard 2-1/8 inch (55 mm) bore without
                       the use of thru-bolts. Standard rose size shall be 2-3/4 inches (70 mm)
                       in diameter.

               F.      Lockset levers shall be made of solid material with no plastic fillers.

               G.      Latchbolt head shall be one piece stainless steel.

               I.      Latchbolt assemblies shall be encased within the lock body.

                I.     Cylinders: prefix -70, small format interchangeable core. Provided with plastic
                       disposable cores only. Lock prepped for 7 pin cores.
               J.      Backsets: 2-3/4 inches.
               K.      Provide Strikes: Provide wrought boxes and strikes with proper lip length to
                       protect trim but not to project more than 1/8 inch beyond trim, frame or inactive
                       leaf. Where required, provide open back strike and protected to allow practical
                       and secure operation.

     2.      04A       Electric Strikes

               A.      Acceptable Manufacturers and Series: HES, Folger-Adam

               B.      Provide electric strikes for electrified openings designed for use with Sargent
11-Line cylindrical locks

               C.      Electric Strikes shall be UL Listed as Burglary-Resistant Electric Door Strikes
                       and where required shall be UL Listed as Electric Strikes for Fire Doors and
                       Frames. Provide non fail-safe type electric strikes.

                 D.     Provide transformers and rectifiers for each strike as required. Verify voltage
with electrical contractor.



      2.       05      Exit Devices

               A.      All exit devices and lever trim to be the product of a single manufacturer
                       for continuity of design and consideration of warranty.


               B.      Application for Exit devices on pairs of doors shall be two (2) Rim Exit
                       Devices x Keyed Removable Mullion.

               C.      Exit devices to be "UL" listed for life safety. All exit devices for labeled
                       doors shall have "UL" label for "Fire Exit Hardware". All devices


                                          DOOR HARDWARE
                                             08710 - 11
LA MTA Hardware Guide Specification                                           2-09


                   mounted on labeled wood doors are to be thru-bolted or per the
                   manufacturer's listing requirements. All devices to conform to NFPA 80
                   and 101 requirements.

             D.    All trim to be thru-bolted to the lock stile case.

             E.    Lever trim to be the same as specified with locksets.

             F.    Exit devices shall comply with UBC Std-10-4 and CBC 1003.3.1.9.


       2.    06    Closers

             A.    All closers to be the product of a single manufacturer for continuity of
                   design and consideration of warranty.

             B.     Closers shall be LCN with heavy-duty rigid arms.       Furnish overhead
             arm stop control as required.

             C.    Closers for exterior and interior shall be full rack-and-pinion with cast
                   aluminum alloy shell. Closers shall be surface mounted and shall project
                   no more than 2-1/8” from the surface of the door. Closers shall be non-
                   handed to permit installation on doors of either hand. Hydraulic fluid
                   shall be non-gumming and non-freezing. Closers shall have multi-size
                   spring power adjustment to permit setting of spring from 2 through 6 with
                   additional spring power available. Closers shall have two non-critical
                   valves, hex key adjusted, to independently regulate backcheck
                   cushioning and backcheck position. Closers shall be equipped with
                   adjustable closing speed and adjustable latch speed. Closers shall be
                   /corrosion resistant and shall have all external body components of
                   aluminum, zinc alloy or stainless steel material and all fasteners of
                   stainless steel.

             D.    Size all closers in accordance with the manufacturer's recommendations
                   at the work site and respective openings. Contractor to return and
                   readjust all closers after building pressurization has occurred.

             E.    Supply appropriate arm assembly for each closer so that closer body
                   and arm are mounted on non-public side of door openings, including the
                   room side of corridors, restrooms, exterior and as listed.

             F.    Refer to 3.02.A.8 Installation for CBC opening force requirements.


      2.     07    Push Plates, Door Pulls and Kickplates [McKinney]


                                   DOOR HARDWARE
                                      08710 - 12
LA MTA Hardware Guide Specification                                                2-09



                   A.       Supply 18 [.050] GA. thick bronze, brass, or stainless steel, beveled four
                            (4) sides. Doors with louvers or narrow bottom rails, kickplate height to
                            be 1 inch less than the dimension shown from the door bottom to the
                            bottom of the louver or glass.
                            1.      Kickplates to be 10 inches high and Mop plates to be 6 inches
                                    high, both by 2 inches or 1 inch less than the door width.
                            2.      Required armor plates, edge guards and protective hardware to
                                    be supplied in sizes as scheduled in the hardware sets.

              2.   08       Door Stops [McKinney]

                   A.       Every door to have a floor, wall or overhead stop control as dictated by
                            the respective opening conditions.

                   B.       Furnish McKinney WS02 wall stops at all openings. Where wall stops
                            cannot be installed, furnish McKinney FS30 at doors [exceptions
                            openings requiring overhead control]. Install floor stops within four (4)
                            inches [measured from outside stop face] of the adjacent wall.

                   C.       Where overhead stops and holders are specified, or otherwise required
                            for proper door operation, they are to be heavy duty and of extruded
                            brass or bronze with no plastic parts. No steel channels, arms or
                            brackets allowed.

                            2.      09    Silencers [McKinney]

                   A.       Silencers to be furnished as follows:
                            1.     Three [3] each at single doors and two [2] each at pairs of doors.

0             2.   10       Thresholds And Gasket [McKinney]

                   A.       Supply materials and finishes as listed hardware sets. All thresholds
                            must be in accordance with the requirements of the ADA and ANSI
                            A117.1, and shall comply with CBC Section 1133B.2.4.1.
                            1.    Furnish thresholds with machine screws and lead anchors.
    Furnish all                           necessary anchoring devices for gasket and seal.
                            2.    Thresholds may require modification depending on final drawings
                                  and frame/floor details. Review final plans and elevations to
                                  determine project requirements. Ensure shop drawing submittals
                                  reflect thresholds listed in final drawings and/or as required per
                                  required survey at existing openings where occurring.

    2.   11        Finish



                                           DOOR HARDWARE
                                              08710 - 13
LA MTA Hardware Guide Specification                                           2-09


             A.     Special care shall be taken to coordinate the finish of the various
                    manufacturers to insure a uniform finish. This finish shall match the
                    finish of the locksets.
                    1.      Plated hardware shall be BHMA626 [US26D] or as detailed in
                            [BHMA630] US32D.

             B.     Painted hardware items shall be lacquered to closely match plated
hardware.

      2.     12     Keying [Best]

             A.     Master key or Grand master key cylinders and key in groups.

             B.     Factory masterkey with manufacturer retaining permanent keying records.

              C.    Provide 6 masterkeys for each masterkey set. Provide 3 change keys for each
                    lock. Provide 2 control keys for core removal. Stamp keys "DO NOT
                    DUPLICATE."

              D.    Verify all keying requirements with the MTA Lockshop. If requested, meet with
                    Owner and Architect to review schedule.

             E.       Provide BEST ICP7WC1-626, high security removable core cylinders,
                             with Patented key control, for each lock with construction
masterkeying.                              Permanent cores shall be installed upon
completion of the project.

              F.    Cylinders shall meet the requirements of UL437.


      2.     13     Electronic Hardware Systems

             A.     All wiring running from one hardware electrical component to another
                    electrical component to have shielded wiring.

             B.     All electrical components mounted on door to be capable of operation by
                    24VDC current carried by means of continuous concealed circuit hinge.

             C.     Voltage: unless otherwise specified all electrical components to operate
                    at 24VDC current for purposes of safety and silent operation. Verify with
                    manufacturer and coordinate with electrical.

             D.     Coordinate with listed manufacturer’s for required system riser/elevation
                    to be delivered to the project architect and contractor.



                                    DOOR HARDWARE
                                       08710 - 14
LA MTA Hardware Guide Specification                                            2-09


          2.     14     Proprietary Products

                 A.     Refer to Para 1.02.      Unless otherwise approved, furnish only the
                        specified products.


    PART 3: EXECUTION

    3.    01     Inspection

                 A.     After installation has been completed, hardware supplier shall have a
                        qualified Hardware Consultant [AHC] inspect project to determine the
                        proper application of hardware according to the approved hardware and
                        keying schedules.
                        1.      Check operation and adjustment of all hardware items.
                        2.      Recommended hardware adjustments shall be made by the
                                contractor/installer.
0
1         3.     02     Installation

                 A.     Installation of finish hardware is specified under other sections.
                        However, the following requirements apply to the work as follows:
                        1.      Hardware shall be installed by a QUALIFIED MECHANIC skilled
                                in the application of institutional grade builder’s hardware.
                        2.      Install all hardware in full compliance with MFR'S instructions.
                                When cutting and fitting is required to install hardware onto or
                                into surfaces, which are to be painted or finished, install each
                                item completely, then remove during application and re-install as
                                required.
                        3.      Care shall be exercised not to mar or damage adjacent work.
                                Damaged work shall be repaired or replaced to the satisfaction of
                                the architect and building owner.
                        4.      Provide adequate backing in stud partitions for the attachment of
                                all respective finish hardware.
                        5.      If door swing is changed from original drawings during
                                construction, the contractor shall make necessary changes at no
                                cost to the owner.
                        6.      Latches and bolts shall be installed to automatically engage
                                strikes, whether activated by closers or manual push. In no
                                instance should unusual manual pressure be required to engage
                                latch or bolt in strikes. Install locks with keyways in proper
                                position, with levers, roses, and/or escutcheons firmly affixed.
                                Adjust strikes after silencers and/or seal are in place.
                        7.      Predrill pilot holes in wood for screws. Drill and tap for surface
                                mounted hardware on metal. Set hinge leaf snug and flat in


                                       DOOR HARDWARE
                                          08710 - 15
LA MTA Hardware Guide Specification                                            2-09


                          mortises, turn screws to flat seat [do not drive].
                   2.     Closers are to have opening force adjusted to comply with current
                          applicable handicapped accessibility requirements as follows:
                          interior doors 5 pounds maximum pressure; exterior doors 5
                          pounds maximum pressure; fire doors 15 pounds maximum
                          pressure, per CBC Section 1133B.2.5.              Per CBC Section
                          1133B.2.5, the authority having jurisdiction may increase the
                          maximum effort to operate fire doors to achieve positive latching,
                          but not to exceed 15 lbs. maximum.
                   3.     Door closers when provided then the sweep period of the closer
                          shall be adjusted to so that from an open position of 70 degrees,
                          the door will take at least 3 seconds to move to a point 3” from
                          the latch, measured to the landing side of the door. Refer to
                          1133B2.5.1.
                   4.     Mount closers and overhead stops/holders in accordance with
                          the manufacturer's template for the degree of swing indicated on
                          the drawings [180-degree swing where conditions allow].
                   5.     Floor stops must be installed within (4) four inches of the adjacent
                          wall maximum, and within (4) inches from the strike edge of door
                          Policy 99-08. Wall surfaces to be properly reinforced for wall
                          stops where furnished.
                   6.     All hardware shall meet the requirements of CBC Sections
                          1133B.2.1, 1133B.2.5.1 and 1003.3.1.8.
                   7.     Door Sweeps and Seals to be installed with attachment screws
                          placed within a min. of one [1] inch from the end of the seal &
                          sweep.
                   8.     Panic hardware shall comply with UBC standards 10-4 and shall
                          be mounted between 36” and 44” above the finish floor surface.

                   9.     The unlatching force shall not exceed 15# applied in the direction
                          of travel. Panic devices shall comply with CBC Section
                          1003.3.1.9.
                   10.    All hardware shall meet the requirements of CBC Sections
                          1133B.2.1, 1133B2.5.1 and 1003.3.1.8.

             B.    Hardware Locations: Review and verify mounting locations with the
                   Architect before issuing templates and door/hardware purchase orders.
                   Mounting height of latching hardware shall be 30” to 44” FF per CBC
                   Section 1133B.2.5.2. The following hardware locations shall be adhered
                   to unless modified by the architect. Minor adjustments are permitted to
                   meet specific door mfr’s standards.
                                          1.             40 inches        Locksets,       Panic
                                          Devices and Roller Latches-centerline of strike
                                          from bottom of frame.
                   2.     42 inches       Pull Plates-centerline of grip from bottom of frame.


                                   DOOR HARDWARE
                                      08710 - 16
LA MTA Hardware Guide Specification                                             2-09


                   3.     42 inches       Combination Push Bars-centerline from btm of
                   frame.
                   4.     44 inches       Push Plates-centerline from bottom of frame.
                   5.     Hinges          Per manufacturer’s standard.

             C.    Threshold and Perimeter Seal:
                                 1.     Cut and fit thresholds to profile of door frames,
                         with mitered corners and hairline joints.
                                 2.     On exterior doors, set thresholds in a bed of
                         sealant.
                   3.    Before installation, carefully read manufacturer's instructions to
                         assure tight and contiguous seal at the perimeter and corners of
                         doors and frames.
                   4.    Specified thresholds are subject to modification. Review final
                         plans and elevations. Field survey and verify modernization
                         work.
                   5.    Thresholds shall comply with CBC Section 1133B.2.4.1.


      3.     03    Adjusting and Cleaning

             A.    At completion, all hardware shall be left clean and free from
                   disfigurement. Contractor shall make a final adjustment to all door
                   closers and other items of hardware. Where hardware is found
                   defective, repair, replace, or otherwise correct as directed.
                   1.      Following the activation of building heating and air conditioning,
                           the contractor shall readjust all exterior and interior door closers.

             B.    Adjust and check each operating item of hardware and each door, to
                   ensure proper operation or function of every unit. Adjust hardware so
                   that moving parts operate freely, without bind, or excessive play.
                   Hardware shall be free of paint, corrosion, or damage of any kind.

     3.      04   Protection


                   A.     The contractor is responsible for the proper protection of all items
                   of   hardware until the building owner accepts the project as complete.

     3.      05   Owner's Stock

             A.     Refer to 1.06 for closeout requirements.

             B.    Contractor/Installer to deliver all unused new and/or replaced finish
                   hardware to the building owner’s designated representative.


                                   DOOR HARDWARE
                                      08710 - 17
LA MTA Hardware Guide Specification                                             2-09



Modernizations - Refer to 1.05.g for additional survey requirements.

Site/Building/Opening Surveys must be conducted before shop drawings are submitted for
review and approval. Submittals must incorporate surveyed opening info or be subject to
immediate rejection by reviewer

•   NOTE: all openings to be field inspected for correct hinge size, weight and wide throw
    requirements needed for maximum dr swing.
•   NOTE: Furnish closer brackets as dictated by door/frame & opening condition.
•   NOTE: Refer to threshold elevations. Type to be verified by field survey.
•   NOTE: Contractor to fill, patch, sand and repaint existing wood doors and frames affected
    by the removal of hardware and the machining for replacement hardware to include:
    locksets, panic, strikes, closers, hinges, oh stops, push-pull plates and as required.
•   NOTE: Existing doors with vision lites that conflict with the application of listed panic
    devices, shall be replaced with new doors.
•   NOTE: Install panic at centerline of horizontal door rail where occurring.

NOTE:    Modernization work: DSS recommends that with few exceptions, existing doors be replaced.
         Review related labor cost and impact of modifying existing doors vs. benefits of new
         replacement doors.

Please contact ASSA ABLOY Door Security Solutions of Southern California for door and hardware
        specification assistance. tel: 714.779.3030 or discuss with your DSS Representative.




                                      END OF SECTION




                                     DOOR HARDWARE
                                        08710 - 18

Mais conteúdo relacionado

Semelhante a Locksmith modified MTA hardware specs

Project Specifications and Building Code
Project Specifications and Building CodeProject Specifications and Building Code
Project Specifications and Building Codetboyko
 
Microsoft Word - 27 4127 - Video Conferencing System
Microsoft Word - 27 4127 - Video Conferencing SystemMicrosoft Word - 27 4127 - Video Conferencing System
Microsoft Word - 27 4127 - Video Conferencing SystemVideoguy
 
SmokeDam Glass Smoke Baffle Perth
SmokeDam Glass Smoke Baffle Perth SmokeDam Glass Smoke Baffle Perth
SmokeDam Glass Smoke Baffle Perth lyndaflintof
 
Designers Connect Presentation May 14th 2013
Designers Connect Presentation May 14th 2013Designers Connect Presentation May 14th 2013
Designers Connect Presentation May 14th 2013tboyko
 
070305 gamble-project-manual
070305 gamble-project-manual070305 gamble-project-manual
070305 gamble-project-manuallaneycollege
 
Itt 1.4 20124-010-sr-4110-801-a
Itt 1.4   20124-010-sr-4110-801-aItt 1.4   20124-010-sr-4110-801-a
Itt 1.4 20124-010-sr-4110-801-aDanil Babash
 
Precast Concrete Specifications.doc
Precast Concrete Specifications.docPrecast Concrete Specifications.doc
Precast Concrete Specifications.docAbdallah437436
 
Construction Documents Required by the Connecticut Building Code
Construction Documents Required by the Connecticut Building CodeConstruction Documents Required by the Connecticut Building Code
Construction Documents Required by the Connecticut Building CodeMilton Grew
 
2011 CTM Session 2: Terminology for Products
2011 CTM Session 2: Terminology for Products2011 CTM Session 2: Terminology for Products
2011 CTM Session 2: Terminology for Productsnovacsi
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationHarish Mahavar
 
Wisconsin Standards of Practice
Wisconsin Standards of PracticeWisconsin Standards of Practice
Wisconsin Standards of Practiceorderinspections
 
Wisconsin State DRL Inspector Standards of Practice
Wisconsin State DRL Inspector Standards of PracticeWisconsin State DRL Inspector Standards of Practice
Wisconsin State DRL Inspector Standards of Practicecommercialnetinc
 

Semelhante a Locksmith modified MTA hardware specs (20)

20 01 00
20 01 0020 01 00
20 01 00
 
Spec u kon fsi 2021
Spec u kon fsi 2021Spec u kon fsi 2021
Spec u kon fsi 2021
 
Project Specifications and Building Code
Project Specifications and Building CodeProject Specifications and Building Code
Project Specifications and Building Code
 
Microsoft Word - 27 4127 - Video Conferencing System
Microsoft Word - 27 4127 - Video Conferencing SystemMicrosoft Word - 27 4127 - Video Conferencing System
Microsoft Word - 27 4127 - Video Conferencing System
 
SmokeDam Glass Smoke Baffle Perth
SmokeDam Glass Smoke Baffle Perth SmokeDam Glass Smoke Baffle Perth
SmokeDam Glass Smoke Baffle Perth
 
S
SS
S
 
Designers Connect Presentation May 14th 2013
Designers Connect Presentation May 14th 2013Designers Connect Presentation May 14th 2013
Designers Connect Presentation May 14th 2013
 
Process & power plants
Process & power plantsProcess & power plants
Process & power plants
 
070305 gamble-project-manual
070305 gamble-project-manual070305 gamble-project-manual
070305 gamble-project-manual
 
General structural notes
General structural notesGeneral structural notes
General structural notes
 
Sample Wall Shop Drawings
Sample Wall Shop DrawingsSample Wall Shop Drawings
Sample Wall Shop Drawings
 
Itt 1.4 20124-010-sr-4110-801-a
Itt 1.4   20124-010-sr-4110-801-aItt 1.4   20124-010-sr-4110-801-a
Itt 1.4 20124-010-sr-4110-801-a
 
Precast Concrete Specifications.doc
Precast Concrete Specifications.docPrecast Concrete Specifications.doc
Precast Concrete Specifications.doc
 
Construction Documents Required by the Connecticut Building Code
Construction Documents Required by the Connecticut Building CodeConstruction Documents Required by the Connecticut Building Code
Construction Documents Required by the Connecticut Building Code
 
EESS 2018 Day 1 - Tim Webster
EESS 2018 Day 1 - Tim WebsterEESS 2018 Day 1 - Tim Webster
EESS 2018 Day 1 - Tim Webster
 
2011 CTM Session 2: Terminology for Products
2011 CTM Session 2: Terminology for Products2011 CTM Session 2: Terminology for Products
2011 CTM Session 2: Terminology for Products
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping station
 
Wisconsin Standards of Practice
Wisconsin Standards of PracticeWisconsin Standards of Practice
Wisconsin Standards of Practice
 
Wisconsin State DRL Inspector Standards of Practice
Wisconsin State DRL Inspector Standards of PracticeWisconsin State DRL Inspector Standards of Practice
Wisconsin State DRL Inspector Standards of Practice
 
Wisconsin SOP
Wisconsin SOPWisconsin SOP
Wisconsin SOP
 

Mais de AShestopalov (20)

5.0 release
5.0 release5.0 release
5.0 release
 
File Manager How To
File Manager How ToFile Manager How To
File Manager How To
 
Quickpoint How To
Quickpoint How ToQuickpoint How To
Quickpoint How To
 
Quickword How To
Quickword How ToQuickword How To
Quickword How To
 
!Untitled as
!Untitled as!Untitled as
!Untitled as
 
1ff
1ff1ff
1ff
 
1ff
1ff1ff
1ff
 
1ff
1ff1ff
1ff
 
new
newnew
new
 
Quickpoint How To
Quickpoint How ToQuickpoint How To
Quickpoint How To
 
Quickword How To
Quickword How ToQuickword How To
Quickword How To
 
1st doc
1st doc1st doc
1st doc
 
1ff
1ff1ff
1ff
 
1ff
1ff1ff
1ff
 
1ff
1ff1ff
1ff
 
1ff
1ff1ff
1ff
 
1ff
1ff1ff
1ff
 
1ff
1ff1ff
1ff
 
1ff
1ff1ff
1ff
 
1ff
1ff1ff
1ff
 

Locksmith modified MTA hardware specs

  • 1. LA MTA Hardware Guide Specification 2-09 PART 1: GENERAL 1. 01 Summary A. Section Includes: 1. Work under this section comprises the furnishing and installation of hardware specified herein and noted on drawings for a complete and operational system, including any electrified hardware components, systems and controls. 2. Related documents, drawings and general provisions of contract, including General and Supplementary Conditions, and Division 1. 3. Items include but are not limited to the following: a. Hinges b. Exit Devices c. Locksets d. Push/Pull Plates e. Automatic Flush Bolts f. Closers g. Kick, Mop and Protection Plates h. Stops and Overhead Controls I. Thresholds, Gasket and Door Bottoms j. Miscellaneous Accessories and Trim B. Related Work: Section 06200 - Finish Carpentry. Section 08110 - Hollow Metal Work. Section 08210 - Wood Doors. Sections within 08800 - Glazing. Sections within 09900 - Painting. 1. 02 Substitutions A. References to specific products are used to establish minimum standards of utility and quality. Unless otherwise approved, furnish only the specified products. B. Requests for substitutions to be in accordance with Division 1, General Requirements. Proposed substitutions must be submitted in writing and hand delivered to the architect. Approvals must be by addendum ten [10] days prior to bid opening. Review will include the lock shop rep. C. Requests to be accompanied by two [2] copies of the manufacturer's brochures and sample of each item in the appropriate design and finish. DOOR HARDWARE 08710 - 1
  • 2. LA MTA Hardware Guide Specification 2-09 D. Should the contractor make any substitutions without the written consent of the architect and owner, contractor shall remove all substituted hardware, replacing same with the hardware as specified and at no additional cost to the building owner. 1. 03 References A. References specified in this section subject to compliance as directed and shall meet requirements of Federal, State and local codes having jurisdiction over this project including: B. Hardware that is furnished and/or installed that does not meet code requirements, shall be removed and replaced with correct material at no additional expense to the building owner. 1. CCR - California Code of Regulations Title 24. 2. ADA - American Disabilities Act - Title III - Public Accommodations. 3. NFPA 80 2007 - Standard for Fire Doors and Windows. 4. NFPA 101 2009 - Life Safety. 5. ITS - Intertek Testing Service [Warnock Hersey]. 6. UL - Underwriters Laboratories. 7. ANSI/BHMA A156 Product Listing. 8. CBC - CA Bldg Code, Local Codes and Authority having Jurisdiction. 9. UL 10C for Positive Pressure Fire Tests of Door Assemblies and UBC 7-2. 1. 04 Quality Assurance A. Product Uniformity: Except where specified, all hinges, keyed cylinders, electro-mechanical components, locksets, latchsets, exit devices, closers, overhead stop/holders and component parts shall be furnished by one manufacturer. B. Rated Openings: Hardware used in labeled fire or smoke rated openings to be listed for those types of openings and bear the identifying label or mark indicating U.L. [Underwriter's Laboratories] approved for fire. Exit devices in non-labeled openings shall be listed for panic. C. Supplier: Shall be responsible for detailing hardware that meets project standards and where appropriate, retrofit applications which require inspection of openings prior to detailing and ordering respective hardware items. DOOR HARDWARE 08710 - 2
  • 3. LA MTA Hardware Guide Specification 2-09 D. Pre-Installation Conference: Prior to installation of hardware, arrange a conference between supplier, installers, and related trades to review materials, procedures, hardware mounting locations and related work. E. Post-Installation Policing: Will be required by the hardware supplier, contractor and architect to determine compliance with the hardware specification and building standards. Punch list to be completed by MTA Locksmith, hardware contractor and contractor. F. Supplier Qualifications: 01. Hardware supplier must be a recognized, Factory Direct contract distributor with a minimum five (5) years experience specializing in institutional grade builder’s hardware of the type specified herein. Distributors with less than two (2) years of history of furnishing builders hardware in the project's vicinity will not be acceptable. 2. Supplier must have in his/her employment on a full time basis, or as a consultant to the supplier, a Certified Hardware Consultant [AHC] or person of equal experience who is acceptable to the Architect and CM. This individual shall be available for consultation and service to the architect, contractor, and building owner during construction and on an ongoing consulting service to the building owner following the completion of the project. 3. Supplier who does not maintain personnel in a permanent facility within a reasonable driving radius of the project area for consultation and service with the architect, contractor and building owner will not be acceptable. 1. 05 General Requirements A. Coordination: Coordinate as necessary with other trades to assure proper and adequate provision in the work of those trades for interface with the work of this Section. B. Sequencing and Scheduling: Any part of the finish hardware required by the frame or door manufacturers or other suppliers, that is needed in order to produce doors or frames is to be sent to those suppliers in a timely manner. C. Defective Hardware: All hardware shall be new and free from defects affecting both serviceability and appearance. Working parts shall be properly fitted, smooth working and without excessive play. D. Function/Modification: 1. Should any hardware fail the intended operational requirements DOOR HARDWARE 08710 - 3
  • 4. LA MTA Hardware Guide Specification 2-09 or require any modification to suit the intended location, this matter, or any other necessary advance information shall be brought to the attention of the architect for correction or advice in ample time to avoid delay in the manufacture and delivery of the hardware. 1. Modifications to specified hardware, required by reason of construction characteristics, shall be furnished in the specified operational, functional features, quality and finish. Modifications shall be subject to acceptance of the architect at no additional cost to the building owner. 2. Items of hardware not specified herein but necessary for completion of the work shall be furnished at no additional cost to the district. Such items shall be of the type specified and comparable to adjacent hardware. E. Doors and Frames: Hollow metal and wood doors shall be manufactured to templates. If required, physical hardware items shall be furnished to related manufacturers in sufficient time to avoid delay in work. E. Electrical Coordination: Before electrically controlled or operated hardware is ordered, voltages and wiring details shall be coordinated with the contractor and related trades. G. Existing [Modernization] Openings Contractor is responsible for a field survey of doors, frames and hardware to determine compatibility of specified hardware, including, but not limited to: locksets, panic devices, strikes, flushbolts, overhead stops, coordinators, closers, threshold/seal, hinge sizes and weights including wide throw hinges. Unless directed otherwise, Contractor to modify openings to meet ADA elevation threshold requirements. Contractor to survey and where necessary, furnish and install ADA approved ramp threshold systems where applicable and approved by the architect. Work shall comply with minimum ADA specifications as well as create a flat sub-surface for specified thresholds. Existing doors and frames to be modified for hardware as permitted by UL, WHI and local code authority. Where required, contractor shall cut and weld necessary reinforcements to existing jambs and doors, for listed hardware as applicable and required. Contractor to patch sand and repaint/refinish reused door(s) and frame(s) surfaces affected by the removal of hardware, and any modification for replacement hardware. DOOR HARDWARE 08710 - 4
  • 5. LA MTA Hardware Guide Specification 2-09 Whether listed or not, contractor shall furnish frame/door hinge, strike, lock face, panic, closer and overhead auxiliary stop fillers where required for a clean finished appearance. Related costs to field modify existing frames and/doors shall be part of the Contractor's base bid and shall include a $500.00 allowance each site for door and frame fillers. Contractor to allow for the above dollar amount in the base bid. Intertek Testing Service or UL inspection and certification is required for the labeling of non-rated doors and frames, and the modification of any labeled door and frame. Contractor is responsible for contacting and coordinating this required labeling service. The Contractor is responsible for the careful removal, treatment and delivery of all existing replaced and any unused new hardware to the building owner. H. Bar Coding of Door/Frame openings All door/frame openings will have a bar code label attached to the frame near the upper door hinge. The bar code labels will be supplied to the contractor by the MTA Key Shop. Contractor will supply a list of all openings that includes the installed hardware, door number, location, and bar code number in a Microsoft Excel 2003 compatible format. 1. 06 Submittals A. Hardware Schedule: Submit typewritten copies of schedule in accordance with Division 1, General Requirements. Schedule to be in vertical format, listing each door opening including; location, handing of opening, all hardware scheduled for each opening or otherwise required to allow for proper function of door opening as intended, finish of hardware, and respective manufacturers. Doors with closers or door controls shall require the degree of door opening. 1. Supply six [6] copies of the schedules within fifteen [15] working day from date of purchase order. a. The hardware schedule shall conform to DHI's: "RECOMMENDED PROCEDURE FOR PROCESSING HARDWARE SCHEDULES AND TEMPLATES." b. Submit manufacturers' catalog cut sheets of all hardware items scheduled and any required special mounting instructions with the hardware schedule. c. Include recommended mounting location data for each type of scheduled door hardware. If specified, include electrified hardware. 2. No hardware item shall be delivered until the hardware schedule DOOR HARDWARE 08710 - 5
  • 6. LA MTA Hardware Guide Specification 2-09 has been approved by the architect. 3. Approval of the hardware schedule by the architect does not relieve the hardware supplier from the responsibility of furnishing the job complete. B. Samples: 1. If directed by the architect, submit physical samples of each item of hardware proposed in work. 2. Samples will be returned on the request of and at the expense of the general contractor. C. Manufacturer's Catalog Illustrations and Hardware Data: 1. Hardware Supplier shall submit, to the Architect, two [2] catalog cuts of every item of hardware furnished for this project. Data shall be contained in a binder appropriately divided by the respective mfrs. 2. Cuts shall include manufacturer's illustrations and shall identify finishes, sizes and product numbers. Abbreviations to be fully explained. D. Operational Data: 1. Deliver to the building owner through the architect, a. One (1) set of factory catalogues for hardware listed in the approved hardware list. b. One (1) copy factory generated bitting list. 0 c. One (1) copy of approved door hardware shop drawings. d. One (1) copy of door and hardware specifications. E. Templates: Templates for door hardware items to be sent to related door and frame suppliers within three [3] working days of receipt of approved hardware schedule. Templates shall not be issued until the door hardware schedule has been reviewed and approved by the architect. F. Certification Of Compliance: Submit any information necessary to indicate compliance to any or all of these specifications as required. G. Keying Schedule: 1. Submit three [3] copies of a separate detailed keying schedule to the contractor. 2. Indicate keying of all cylinders, exit devices, locksets, and padlocks. Include door and item numbers as set forth in the approved hardware schedule. 3. Keying data shall follow "KEYING SYSTEMS AND NOMENCLATURE" as established by DHI. DOOR HARDWARE 08710 - 6
  • 7. LA MTA Hardware Guide Specification 2-09 4. Include with the schedule a keying schematic layout 5. Prior to placing a factory order, the key schedule shall be approved in writing by the building owner and contractor. 6. Keying to be done by MTA Key Shop. Contractor shall supply “construction I/C cores” for all locking hardware during construction of the project. The change key and control keys for the construction cores shall be delivered to the MTA Key Shop before the project is turned over to MTA. 1. 07 Delivery, Storage and Handling A. Packaging: Each unit of hardware shall be individually packaged in the manufacturer's original containers as required by the respective hardware manufacturers. 1. Packaging shall include factory original installation instructions, fastenings and all items necessary for complete installation. B. Wrapping: Wrap and cushion each item to prevent scratches and dents during delivery and storage. C. Environmental Packaging: Hardware shipped to the jobsite is to be packaged in biodegradable packs, such as paper or cardboard boxes and wrapping. If non-biodegradable packing is utilized, such as plastic, plastic bags or Styrofoam, then the Contractor will be responsible for the disposal of the non-biodegradable packing to a licensed or authorized collector for recycling of the material. D. Markings: Each package shall be clearly marked on the outside, identifying contents with specific opening number corresponding to those listed in the hardware schedule. Include door and item number for each product. E. Delivery: Except as dictated otherwise, deliver all hardware to the job site. The contractor and hardware supplier's representative shall check each item of hardware against the approved finish hardware schedule. F. Storage: All hardware shall be stored in a locked storage space until ready for installation. Hardware shall be protected against damage after application and during construction period. 1. 08 Warranty A. All door hardware shall be supplied with the following warranties against defects in materials and workmanship commencing with substantial completion of job. The following warranties are subject to listings of DOOR HARDWARE 08710 - 7
  • 8. LA MTA Hardware Guide Specification 2-09 approved manufacturers. 1. Door Closers: Ten years. 3. Cylindrical Locksets: Seven years. 4. Exit Devices: Five years 7. Electromechanical: Two years. B. One year warranty for the balance of listed hardware. PART 2: PRODUCT: 2. 01 Manufacturers A. Acceptable Manufacturers: 0 1. All materials or products specified herein shall be furnished as specified. Refer Para. 1.02 SUBSTITUTIONS. 2. Any proposed deviation from listed standards will be reviewed in writing by the building owner’s authorized representatives. PRODUCT SPECIFIED MFRS APPROVED MFRS Cont Hinge McKinney Markar Butt Hinge McKinney Hager, Bommer Cylinders Stanley-Best Stanley-Best Exit Device Von Duprin Corbin Russwin, Detex, Yale Closer LCN Corbin Russwin, Norton, Yale Push/Pull/KP McKinney Rockwood, Trimco Flushbolts McKinney Rockwood, Trimco Door Control McKinney Rockwood, Trimco O.H. Stop Rixson Sargent Door Stop McKinney Rockwood, Trimco Thresh/Seal McKinney Pemko Door Locks Sargeant Stanley-Best, Schlage, Corbin 2. 02 Fastenings A. Furnish hardware with all necessary screws, bolts or other fastenings of suitable type and size to anchor the hardware in position for long life and heavy use. Fasteners shall include expansion shields, sex bolts, toggle bolts, or other approved anchors according to material to which it is applied and as recommended by the respective manufacturers. B. With the exception of flat goods, self-drilling or self-tapping screws are unacceptable in this work. Where used, only factory furnished self- DOOR HARDWARE 08710 - 8
  • 9. LA MTA Hardware Guide Specification 2-09 drilling fasteners are permitted. All moving hardware including hinges, locksets, panic devices, door closers and overhead stops are to be installed with factory furnished machine screws. Exceptions must be reviewed and approved by an authorized building owner’s representative and submitted in writing to the project architect, hardware consultant and construction manager prior to commencement of any work C. Design of all fastenings shall harmonize with hardware as to material and finish. 0 2. 03 Hinges A. All hinges and pivots, including single and double acting types and pocket hinges to be of one manufacturer as listed for continuity and consideration of warranty. B. Unless otherwise specified, furnish five-knuckle as specified; button tip, full mortise template type hinges with non-rising loose pins. C. Out-swinging exterior doors to be furnished with non-removable pins [NRP] or Continuous Hinges where specified and required by owner. D. Exterior doors to be furnished with heavy weight T4A3386, polished and plated to BHMA 626 finish. D. Interior doors to be furnished with standard weight TA2314, polished and plated to BHMA 626 finish. E. Furnish three [3] hinges up to 90 inches high and one [1] additional hinge for every 30 inches or fraction thereof. F. Furnish standard weight hinges on doors up to 36 inches in width, and extra heavy weight on doors exceeding 36" or as indicated in the hardware schedule. G. Furnish 4.5 x 4.5 inch for all 1- 3/4 inch thick doors up to 36 inch wide, and 5 x 4.5 over 36 inch wide. Doors over 1-3/4 inch thru 2-1/4 inch thick, use 5 x 5 inch hinges. Furnish McK WT-T4A3386 5x6, 5x7 as dictated at wide throw conditions. H. Where required, furnish hinges of sufficient width to clear trim and/or permit the door to swing 180 degrees as required by the specific opening. I. Furnish oil-impregnated bearing hinges at doors with door closers and/or DOOR HARDWARE 08710 - 9
  • 10. LA MTA Hardware Guide Specification 2-09 overhead stops. J. No Electrified hinges allowed. Provide Securitron EPT power transfer. 2. 03A Continuous Hinges A. Hinge line to be available in concealed flush mount with or without inset, full- surface and half-surface types as specified in the hardware sets. Furnish wide throw hinges as required to clear trim permitting doors to open 180 degrees. B. All hinges to be made of 14 GA. type 304 Stainless Steel with concealed teflon-coated stainless steel pin, and twin self-lubricated nylon bearings at each knuckle. C. All hinges to be UL listed up to and including three (3) hours. D. All concealed hinges to be fire-rated 20, 45 and 90 minutes when incorporated into proper door and frame labeled installations without necessitating the use of fusible link pins. E. All hinges to be available in standard and extra heavy-duty weight mortise and wide throw where required. F. All hinges to be factory cut for door size. G. No Electrified hinges allowed. Provide Securitron EPT power transfer. H. Continuous hinges only as directed by owner. 2. 04 Cylindrical Locks A. All cylindrical locks, trim and cylinders to be the product of a single manufacturer for continuity of design and consideration of warranty. B. Locksets shall be Sargent 28-70-11 Line Series x LL trim. C. All Locksets shall be able to withstand 2400 inch pounds of torque applied to the locked lever without gaining access. D. Locksets shall be cycle tested per ANSI A156.2, 1996, to two million cycles without any visible lever sag. DOOR HARDWARE 08710 - 10
  • 11. LA MTA Hardware Guide Specification 2-09 E. Locksets shall be able to fit a standard 2-1/8 inch (55 mm) bore without the use of thru-bolts. Standard rose size shall be 2-3/4 inches (70 mm) in diameter. F. Lockset levers shall be made of solid material with no plastic fillers. G. Latchbolt head shall be one piece stainless steel. I. Latchbolt assemblies shall be encased within the lock body. I. Cylinders: prefix -70, small format interchangeable core. Provided with plastic disposable cores only. Lock prepped for 7 pin cores. J. Backsets: 2-3/4 inches. K. Provide Strikes: Provide wrought boxes and strikes with proper lip length to protect trim but not to project more than 1/8 inch beyond trim, frame or inactive leaf. Where required, provide open back strike and protected to allow practical and secure operation. 2. 04A Electric Strikes A. Acceptable Manufacturers and Series: HES, Folger-Adam B. Provide electric strikes for electrified openings designed for use with Sargent 11-Line cylindrical locks C. Electric Strikes shall be UL Listed as Burglary-Resistant Electric Door Strikes and where required shall be UL Listed as Electric Strikes for Fire Doors and Frames. Provide non fail-safe type electric strikes. D. Provide transformers and rectifiers for each strike as required. Verify voltage with electrical contractor. 2. 05 Exit Devices A. All exit devices and lever trim to be the product of a single manufacturer for continuity of design and consideration of warranty. B. Application for Exit devices on pairs of doors shall be two (2) Rim Exit Devices x Keyed Removable Mullion. C. Exit devices to be "UL" listed for life safety. All exit devices for labeled doors shall have "UL" label for "Fire Exit Hardware". All devices DOOR HARDWARE 08710 - 11
  • 12. LA MTA Hardware Guide Specification 2-09 mounted on labeled wood doors are to be thru-bolted or per the manufacturer's listing requirements. All devices to conform to NFPA 80 and 101 requirements. D. All trim to be thru-bolted to the lock stile case. E. Lever trim to be the same as specified with locksets. F. Exit devices shall comply with UBC Std-10-4 and CBC 1003.3.1.9. 2. 06 Closers A. All closers to be the product of a single manufacturer for continuity of design and consideration of warranty. B. Closers shall be LCN with heavy-duty rigid arms. Furnish overhead arm stop control as required. C. Closers for exterior and interior shall be full rack-and-pinion with cast aluminum alloy shell. Closers shall be surface mounted and shall project no more than 2-1/8” from the surface of the door. Closers shall be non- handed to permit installation on doors of either hand. Hydraulic fluid shall be non-gumming and non-freezing. Closers shall have multi-size spring power adjustment to permit setting of spring from 2 through 6 with additional spring power available. Closers shall have two non-critical valves, hex key adjusted, to independently regulate backcheck cushioning and backcheck position. Closers shall be equipped with adjustable closing speed and adjustable latch speed. Closers shall be /corrosion resistant and shall have all external body components of aluminum, zinc alloy or stainless steel material and all fasteners of stainless steel. D. Size all closers in accordance with the manufacturer's recommendations at the work site and respective openings. Contractor to return and readjust all closers after building pressurization has occurred. E. Supply appropriate arm assembly for each closer so that closer body and arm are mounted on non-public side of door openings, including the room side of corridors, restrooms, exterior and as listed. F. Refer to 3.02.A.8 Installation for CBC opening force requirements. 2. 07 Push Plates, Door Pulls and Kickplates [McKinney] DOOR HARDWARE 08710 - 12
  • 13. LA MTA Hardware Guide Specification 2-09 A. Supply 18 [.050] GA. thick bronze, brass, or stainless steel, beveled four (4) sides. Doors with louvers or narrow bottom rails, kickplate height to be 1 inch less than the dimension shown from the door bottom to the bottom of the louver or glass. 1. Kickplates to be 10 inches high and Mop plates to be 6 inches high, both by 2 inches or 1 inch less than the door width. 2. Required armor plates, edge guards and protective hardware to be supplied in sizes as scheduled in the hardware sets. 2. 08 Door Stops [McKinney] A. Every door to have a floor, wall or overhead stop control as dictated by the respective opening conditions. B. Furnish McKinney WS02 wall stops at all openings. Where wall stops cannot be installed, furnish McKinney FS30 at doors [exceptions openings requiring overhead control]. Install floor stops within four (4) inches [measured from outside stop face] of the adjacent wall. C. Where overhead stops and holders are specified, or otherwise required for proper door operation, they are to be heavy duty and of extruded brass or bronze with no plastic parts. No steel channels, arms or brackets allowed. 2. 09 Silencers [McKinney] A. Silencers to be furnished as follows: 1. Three [3] each at single doors and two [2] each at pairs of doors. 0 2. 10 Thresholds And Gasket [McKinney] A. Supply materials and finishes as listed hardware sets. All thresholds must be in accordance with the requirements of the ADA and ANSI A117.1, and shall comply with CBC Section 1133B.2.4.1. 1. Furnish thresholds with machine screws and lead anchors. Furnish all necessary anchoring devices for gasket and seal. 2. Thresholds may require modification depending on final drawings and frame/floor details. Review final plans and elevations to determine project requirements. Ensure shop drawing submittals reflect thresholds listed in final drawings and/or as required per required survey at existing openings where occurring. 2. 11 Finish DOOR HARDWARE 08710 - 13
  • 14. LA MTA Hardware Guide Specification 2-09 A. Special care shall be taken to coordinate the finish of the various manufacturers to insure a uniform finish. This finish shall match the finish of the locksets. 1. Plated hardware shall be BHMA626 [US26D] or as detailed in [BHMA630] US32D. B. Painted hardware items shall be lacquered to closely match plated hardware. 2. 12 Keying [Best] A. Master key or Grand master key cylinders and key in groups. B. Factory masterkey with manufacturer retaining permanent keying records. C. Provide 6 masterkeys for each masterkey set. Provide 3 change keys for each lock. Provide 2 control keys for core removal. Stamp keys "DO NOT DUPLICATE." D. Verify all keying requirements with the MTA Lockshop. If requested, meet with Owner and Architect to review schedule. E. Provide BEST ICP7WC1-626, high security removable core cylinders, with Patented key control, for each lock with construction masterkeying. Permanent cores shall be installed upon completion of the project. F. Cylinders shall meet the requirements of UL437. 2. 13 Electronic Hardware Systems A. All wiring running from one hardware electrical component to another electrical component to have shielded wiring. B. All electrical components mounted on door to be capable of operation by 24VDC current carried by means of continuous concealed circuit hinge. C. Voltage: unless otherwise specified all electrical components to operate at 24VDC current for purposes of safety and silent operation. Verify with manufacturer and coordinate with electrical. D. Coordinate with listed manufacturer’s for required system riser/elevation to be delivered to the project architect and contractor. DOOR HARDWARE 08710 - 14
  • 15. LA MTA Hardware Guide Specification 2-09 2. 14 Proprietary Products A. Refer to Para 1.02. Unless otherwise approved, furnish only the specified products. PART 3: EXECUTION 3. 01 Inspection A. After installation has been completed, hardware supplier shall have a qualified Hardware Consultant [AHC] inspect project to determine the proper application of hardware according to the approved hardware and keying schedules. 1. Check operation and adjustment of all hardware items. 2. Recommended hardware adjustments shall be made by the contractor/installer. 0 1 3. 02 Installation A. Installation of finish hardware is specified under other sections. However, the following requirements apply to the work as follows: 1. Hardware shall be installed by a QUALIFIED MECHANIC skilled in the application of institutional grade builder’s hardware. 2. Install all hardware in full compliance with MFR'S instructions. When cutting and fitting is required to install hardware onto or into surfaces, which are to be painted or finished, install each item completely, then remove during application and re-install as required. 3. Care shall be exercised not to mar or damage adjacent work. Damaged work shall be repaired or replaced to the satisfaction of the architect and building owner. 4. Provide adequate backing in stud partitions for the attachment of all respective finish hardware. 5. If door swing is changed from original drawings during construction, the contractor shall make necessary changes at no cost to the owner. 6. Latches and bolts shall be installed to automatically engage strikes, whether activated by closers or manual push. In no instance should unusual manual pressure be required to engage latch or bolt in strikes. Install locks with keyways in proper position, with levers, roses, and/or escutcheons firmly affixed. Adjust strikes after silencers and/or seal are in place. 7. Predrill pilot holes in wood for screws. Drill and tap for surface mounted hardware on metal. Set hinge leaf snug and flat in DOOR HARDWARE 08710 - 15
  • 16. LA MTA Hardware Guide Specification 2-09 mortises, turn screws to flat seat [do not drive]. 2. Closers are to have opening force adjusted to comply with current applicable handicapped accessibility requirements as follows: interior doors 5 pounds maximum pressure; exterior doors 5 pounds maximum pressure; fire doors 15 pounds maximum pressure, per CBC Section 1133B.2.5. Per CBC Section 1133B.2.5, the authority having jurisdiction may increase the maximum effort to operate fire doors to achieve positive latching, but not to exceed 15 lbs. maximum. 3. Door closers when provided then the sweep period of the closer shall be adjusted to so that from an open position of 70 degrees, the door will take at least 3 seconds to move to a point 3” from the latch, measured to the landing side of the door. Refer to 1133B2.5.1. 4. Mount closers and overhead stops/holders in accordance with the manufacturer's template for the degree of swing indicated on the drawings [180-degree swing where conditions allow]. 5. Floor stops must be installed within (4) four inches of the adjacent wall maximum, and within (4) inches from the strike edge of door Policy 99-08. Wall surfaces to be properly reinforced for wall stops where furnished. 6. All hardware shall meet the requirements of CBC Sections 1133B.2.1, 1133B.2.5.1 and 1003.3.1.8. 7. Door Sweeps and Seals to be installed with attachment screws placed within a min. of one [1] inch from the end of the seal & sweep. 8. Panic hardware shall comply with UBC standards 10-4 and shall be mounted between 36” and 44” above the finish floor surface. 9. The unlatching force shall not exceed 15# applied in the direction of travel. Panic devices shall comply with CBC Section 1003.3.1.9. 10. All hardware shall meet the requirements of CBC Sections 1133B.2.1, 1133B2.5.1 and 1003.3.1.8. B. Hardware Locations: Review and verify mounting locations with the Architect before issuing templates and door/hardware purchase orders. Mounting height of latching hardware shall be 30” to 44” FF per CBC Section 1133B.2.5.2. The following hardware locations shall be adhered to unless modified by the architect. Minor adjustments are permitted to meet specific door mfr’s standards. 1. 40 inches Locksets, Panic Devices and Roller Latches-centerline of strike from bottom of frame. 2. 42 inches Pull Plates-centerline of grip from bottom of frame. DOOR HARDWARE 08710 - 16
  • 17. LA MTA Hardware Guide Specification 2-09 3. 42 inches Combination Push Bars-centerline from btm of frame. 4. 44 inches Push Plates-centerline from bottom of frame. 5. Hinges Per manufacturer’s standard. C. Threshold and Perimeter Seal: 1. Cut and fit thresholds to profile of door frames, with mitered corners and hairline joints. 2. On exterior doors, set thresholds in a bed of sealant. 3. Before installation, carefully read manufacturer's instructions to assure tight and contiguous seal at the perimeter and corners of doors and frames. 4. Specified thresholds are subject to modification. Review final plans and elevations. Field survey and verify modernization work. 5. Thresholds shall comply with CBC Section 1133B.2.4.1. 3. 03 Adjusting and Cleaning A. At completion, all hardware shall be left clean and free from disfigurement. Contractor shall make a final adjustment to all door closers and other items of hardware. Where hardware is found defective, repair, replace, or otherwise correct as directed. 1. Following the activation of building heating and air conditioning, the contractor shall readjust all exterior and interior door closers. B. Adjust and check each operating item of hardware and each door, to ensure proper operation or function of every unit. Adjust hardware so that moving parts operate freely, without bind, or excessive play. Hardware shall be free of paint, corrosion, or damage of any kind. 3. 04 Protection A. The contractor is responsible for the proper protection of all items of hardware until the building owner accepts the project as complete. 3. 05 Owner's Stock A. Refer to 1.06 for closeout requirements. B. Contractor/Installer to deliver all unused new and/or replaced finish hardware to the building owner’s designated representative. DOOR HARDWARE 08710 - 17
  • 18. LA MTA Hardware Guide Specification 2-09 Modernizations - Refer to 1.05.g for additional survey requirements. Site/Building/Opening Surveys must be conducted before shop drawings are submitted for review and approval. Submittals must incorporate surveyed opening info or be subject to immediate rejection by reviewer • NOTE: all openings to be field inspected for correct hinge size, weight and wide throw requirements needed for maximum dr swing. • NOTE: Furnish closer brackets as dictated by door/frame & opening condition. • NOTE: Refer to threshold elevations. Type to be verified by field survey. • NOTE: Contractor to fill, patch, sand and repaint existing wood doors and frames affected by the removal of hardware and the machining for replacement hardware to include: locksets, panic, strikes, closers, hinges, oh stops, push-pull plates and as required. • NOTE: Existing doors with vision lites that conflict with the application of listed panic devices, shall be replaced with new doors. • NOTE: Install panic at centerline of horizontal door rail where occurring. NOTE: Modernization work: DSS recommends that with few exceptions, existing doors be replaced. Review related labor cost and impact of modifying existing doors vs. benefits of new replacement doors. Please contact ASSA ABLOY Door Security Solutions of Southern California for door and hardware specification assistance. tel: 714.779.3030 or discuss with your DSS Representative. END OF SECTION DOOR HARDWARE 08710 - 18