SlideShare uma empresa Scribd logo
1 de 37
Process Evaluation and Design II – Spring 2016
Process Evaluation and Design II – Spring 2016
CHEG 407 – A
CASE 3: PRODUCTION FRESH WATER FROM SEA
WATER BY MULTI-EFFECT EVAPORATOR SYSTEM
Instructor: Dr. Jacob R. Borden
Submitted by:
An Minh Tran
College of Engineering and Technology
McNeese State University
Date Submitted: May 3, 2016
2
Table of Contents
Executive Summary........................................................................................................................ 3
Introduction..................................................................................................................................... 3
Overall Process Description............................................................................................................ 3
Process with one Effect Evaporator System...........................…………………………………….4
A. Mass and Energy Balance………………..…………………………………………….5
B. Major Equipment List and Purchased Cost…………………………………………….8
C. Project Economics……………………………………………………………………...9
Process with three Effects Evaporator System……………………………………………..........11
A. Mass and Energy Balance…………………………………………………………….11
B. Major Equipment List and Purchased Cost…………………………………………...15
C. Project Economics…………………………………………………………………….16
Process with four Effects Evaporator System……………………………………………………19
A. Mass and Energy Balance…………………………………………………………….19
B. Major Equipment List and Purchased Cost…………………………………………...22
C. Project Economics…………………………………………………………………….24
Process with six Effects Evaporator System……………………………………………………..27
A. Mass and Energy Balance…………………………………………………………….27
B. Major Equipment List and Purchased Cost…………………………………………...29
C. Project Economics…………………………………………………………………….31
Options…………………………………………………………………………………………...33
Safety Concerns ............................................................................................................................ 34
A. Over Process………………………………………………………………………….34
B. Hazard and operability study (HAZOP)………………………………………………35
Conclusion and Recommendation ................................................................................................ 36
3
EXECUTIVE SUMMARY
This report is a process design for the production of fresh water from sea water that contains 3.5
wt% salt. A multi – effect evaporator system that includes of number of effect, 1 boiler, and 1
condenser is used in this process. This paper provides a basic plant design with process flow
diagram, mass and energy balance, total equipment cost, economics analysis, and safety concerns
of the plant. The plant design basis is 400,000 pounds of fresh water is produced per day,
operating 300 days per year. The expected life of the equipment is 10 years and salvage value of
all equipment is 15% of the total equipment cost. Depreciate the equipment is calculated by
straight-line depreciation. Fixed charged are 15% of the installed cost of the evaporators
excluding depreciation. Maintenance charges are 5% of the total equipment cost. In this report,
the economics analysis is used base on different system with 1 effect, 3 effects, 4 effects, and 6
effects; then which option will give the highest total NPV will be chose to design the plant.
INTRORUCTION
Water is very important for human’s life. People drink water everyday to survive. The plants
need water in their photosynthesis process. Many factories use water for their cooling system.
Electricity can also produce by water; and many application of water in the real life. However,
because of the climate change and the increasing of population, souce of fresh water from nature
such as river or ground water seems like not enough to provide for human life. Besides, sea
water is the unlimit souce of water from natural. Therefore, a multi-effect evaporator need to be
designed to desalinate sea water to fresh water to provide for human life is very necessary.
OVERALL PROCESS DESCRIPTION
Sea water that pump to each evaporator is heated by hot steam which comes from the boiler.
After heated by hot steam, sea water turns to be hot vapor and is lead to the next evaporator to
4
heat the next sea water flow of next evaporator. The cooling water on the other hand is pumped
to boiler. On next evaporater the sea water fed and the sea water coming from first evaporator are
heated by the steam coming from same evaporator to produce fresh water. Similarly, the process
keeps continuous until it goes to the last evaporator. At the last evaporator, the steam is cooled
by cooling water of the condenser. The figure below shown in the flow diagram of the Process
with four effect evaporator is used to make fresh water from sea water.
Figure 1: Flow Diagram of four Effects Evaporator System
PROCESS WITH ONE EFFECT EVAPORATOR SYSTEM
A. Mass and Energy Balance
With pressure of the boiler P = 40 bar, pressure of the effect P = 30 bar, and pressure of
condenser P = 1 bar, the base is given for mass flowrate of fresh water is 400,000 lb/day and is
produced from sea water that contains 3.5 wt% salt, from the steam tables combine with mass
5
and energy balance equations, the mass of brine coming out of effect, mass of cooling water
coming in to the condenser, mass of steam needed to heat up in the boiler, the heat duty of
natural gas that is required to heat up the steam in the boiler, the heat duty of condenser and its
area need to design to cool the hot stream are calculated.
Figure 2: Mass and Energy Balance Calculation for one Effect Evaporator System
Based on the values are calculated, the summary for mass and energy balance for the system is
shown in these figures below
6
Figure 3: Mass Balance of the Process with one Effect Evaporator System
Figure 4: Energy Balance of the Boiler and one Effect Evaporator System
7
Figure 5: Mass and Energy Balance of Condenser for one Effect Evaporator System
From those values of mass flowrate and heat duty that are calculated above, the unit such as
power of the pumps or area of evaporators are find out to estimate for equipment cost of the
project.
B. Major Equipment List and Purchased Cost
Figure 6: Cost Equipment Calculation for one Effect Evaporator System
8
From those calculations that are presented above, the table of total equipment cost of process
is show in below
Name Unit of Size Value a b n Material Cost in 2010 Cost in 2016
Boiler Steam (liters/s) 9437.41 124000 10 1 Carbon Steel $ 218,374.07 $ 262,048.88
Condenser Area (m2) 64.01 1900 2500 1 Carbon Steel $ 161,929.16 $ 194,314.99
Effect 1 Area (m2) 40.29 330 36000 0.55 Carbon Steel $ 275,225.40 $ 330,270.48
Feed Pump Flow (liter/s) 2.12 8000 240 0.9 Carbon Steel $ 8,471.31 $ 10,165.57
Pump 1 Flow (liter/s) 3.19 800 240 0.9 Carbon Steel $ 8,681.82 $ 10,418.18
Total Equipment Cost $ 807,218.10
Table 1: Total Equipment Cost for one Effect Evaporator System
The total equipment cost for the process system with one evaporator equals $807,218.
C. Project Economics
1) Annual Depreciation
Annual depreciation is calculated by straight-line depreciation with the salvage value of all
equipment is estimated to be 15% of the equipment cost with the expected life of the
equipment is 10 years.
Total Equipment Cost $ 807,218.10
Salvage Value $ 121,082.72
Depreciable Asset Cost $ 686,135.39
Depreciation Rate/Year 10%
Annual Depreciation $ 68,613.54
Table 2: Annual Depreciation for one Effect Evaporator System
Annual depreciation for one effect evaporator system is $68,613.54
2) Variables Cost of Production
To calculate variables cost of production, the number of water comes from cooling water of
condenser and steam for the boiler, electricity is used for the feed pump of sea water, and natural
gas is used for the boiler to heat water the run the system.
Utilities Consumption/day Cost $/unit Cost $/day Cost $/year
Water (gal) 3,953,301.72 0.005 19,766.51 5,929,952.58
Electricity (kWh) 731,531.69 0.046 33,650.46 10,095,137.39
9
Natural – gas (MM BTU) 714.69 2.178 1,556.60 466,981.00
Total variable cost $/year 16,492,070.97
Table 3: Variables Cost of Production for one Effect Evaporator System
From the table above, the main costs that effect to the variables cost of production are cost of
cooling water for the condenser and cost of electricity for the sea water feed pump. However,
based on mass balance, to produce 400,000 lb/day of fresh water, the flowrate of sea water is
414,508 lb/day, which is 2.12 liters/s, and this value is constant, so the electricity cost is
constant; therefore, the main utilities that effects to the changing variables cost of production is
volume flowrate of cooling water.
3) Annual Labor, Maintenance, and Fixed Charges
The calculation for annual labor, maintenance, and fixed charged are shown in table below with
the maintenance charged are 5% of the initial total equipment cost, and fixed charges excluding
depreciation are 15% of the installed cost of the evaporators
Number of operators/shift 2
Operator salary $/hr 15
Number of engineers 1
Engineer Salary/season 25000
Over head 100% labor cost
Total labor cost $/year $ 632,000.00
Maintenance (5% Total equipment cost/year) $ 40,360.91
Fixed Charge ( 15%installed evaporator cost) $ 49,540.57
Table 4: Annual Labor, Maintenance, and Fixed Charges
4) Variables cost per gallon fresh water production
From all the costs that are calculated above, with 400,000 lb/day or 14.3 MM gal/day of fresh
water produce, the variables cost per gallon fresh water production is shown in table below
$/year $/gal of Water
Utilities $ 16,492,070.97 $ 1.15
Depreciation $ 74,892.38 $ 0.01
Labor $ 632,000.00 $ 0.04
Maintenance $ 40,360.91 $ 0.00
10
Fixed Charge $ 49,540.57 $ 0.00
Total $ 17,288,864.83 $ 1.20
Table 5: Variables cost per gallon fresh water production
From the table above, the cost of utilities is the highest cost that need to spend for the process.
5) Cash Flow and NPV Analysis
A cash flow analysis is done based on Annual Depreciation, Variables Cost of Production,
Annual Labor, Maintenance, and Fixed Charges for this project with the total is equal $17MM
each year. Net Present Value (NPV) method is applied to assess the economic value of the
project. A common Internal Rate of Return (IRR) of 8.5% is used for calculation. Tax is
incorporated and equals 28% of the net income. Desalinated water is sold for $1/gal. 400,000
lb/year or 14.3 MM gal/year of fresh water is produced. It means the revenue of this project
equals $14.3MM. The NPV of this plant is calculated in 10 years.
Year Cost Revenue Tax Cash Flow NPV Total NPV to year
0 $ 807,218.10 $ (807,218.10) $ (807,218.10) $ (807,218.10)
1 $ 17,288,864.83 $ 14,392,090.56 $ (811,096.79) $ (2,085,677.47) $ (1,772,825.85) $ (2,580,043.95)
2 $ 17,288,864.83 $ 14,392,090.56 $ (811,096.79) $ (2,085,677.47) $ (1,506,901.97) $ (4,086,945.93)
3 $ 17,288,864.83 $ 14,392,090.56 $ (811,096.79) $ (2,085,677.47) $ (1,280,866.68) $ (5,367,812.60)
4 $ 17,288,864.83 $ 14,392,090.56 $ (811,096.79) $ (2,085,677.47) $ (1,088,736.68) $ (6,456,549.28)
5 $ 17,288,864.83 $ 14,392,090.56 $ (811,096.79) $ (2,085,677.47) $ (925,426.17) $ (7,381,975.46)
6 $ 17,288,864.83 $ 14,392,090.56 $ (811,096.79) $ (2,085,677.47) $ (786,612.25) $ (8,168,587.70)
7 $ 17,288,864.83 $ 14,392,090.56 $ (811,096.79) $ (2,085,677.47) $ (668,620.41) $ (8,837,208.11)
8 $ 17,288,864.83 $ 14,392,090.56 $ (811,096.79) $ (2,085,677.47) $ (568,327.35) $ (9,405,535.46)
9 $ 17,288,864.83 $ 14,392,090.56 $ (811,096.79) $ (2,085,677.47) $ (483,078.25) $ (9,888,613.71)
10 $ 17,288,864.83 $ 14,392,090.56 $ (811,096.79) $ (2,085,677.47) $ (410,616.51) $ (10,299,230.22)
Table 6: Cash Flow and NPV Analysis
Table above shown that the project is not profit if one desalinated water will sell for $1/gal for
one effect evaporator system.
PROCESS WITH THREE EFFECTS EVAPORATOR SYSTEM
A. Mass and Energy Balance
11
With pressure of the boiler P = 40 bar, pressure of the 1st effect P = 30 bar, pressure of the 2nd
effect P = 20 bar, pressure of the 3rd effect P = 10 bar, and pressure of the condenser P = 1 bar,
the base is given for mass flowrate of fresh water is 400,000 lb/day and is produced from sea
water that contains 3.5 wt% salt, from the steam tables combine with mass and energy balance
equations, the mass of steam and brine coming out of each effect, mass of cooling water coming
in to the condenser, mass of steam needed to heat up in the boiler, the heat duty of natural gas
that is required to heat up the steam in the boiler, the heat duty of condenser and its area need to
design to cool the hot stream are calculated.
12
Figure 7: Mass and Energy Balance Calculation for three Effects Evaporator System
13
Based on the values are calculated, the summary for mass and energy balance for the system is
shown in these figures below
Figure 8: Mass Balance of the Process with three Effects Evaporator System
14
Figure 9: Energy Balance of the Boiler and three Effects Evaporator System
Figure 10: Mass and Energy Balance of Condenser for three Effects Evaporator System
From those values of mass flowrate and heat duty that are calculated above, the unit such as
power of the pumps or area of evaporators are find out to estimate for equipment cost of the
project.
B. Major Equipment List and Purchased Cost
15
Figure 11: Cost Equipment Calculation for three Effects Evaporator System
From those calculations that are presented above, the table of total equipment cost of process
is show in below
Name Unit of Size Value a b n Material Cost in 2010 Cost in 2016
Boiler Steam (liters/s) 4093.07 124000 10 1 Carbon Steel $ 164,930.69 $ 197,916.82
Condenser Area (m2) 20.90 1900 2500 1 Carbon Steel $ 54,154.69 $ 64,985.63
Effect 1 Area (m2) 17.47 330 36000 0.55 Carbon Steel $ 173,960.28 $ 208,752.33
Effect 2 Area (m2) 16.13 330 36000 0.55 Carbon Steel $ 166,457.58 $ 199,749.09
Effect 3 Area (m2) 12.00 330 36000 0.55 Carbon Steel $ 141,521.21 $ 169,825.46
Feed Pump Flow (liter/s) 2.12 8000 240 0.9 Carbon Steel $ 8,471.31 $ 10,165.57
Pump 1 Flow (liter/s) 1.38 800 240 0.9 Carbon Steel $ 8,321.47 $ 9,985.77
Pump 2 Flow (liter/s) 1.00 800 240 0.9 Carbon Steel $ 8,239.58 $ 9,887.50
Pump 3 Flow (liter/s) 0.74 800 240 0.9 Carbon Steel $ 8,182.22 $ 9,818.67
Total Equipment Cost $ 881,086.84
Table 7: Total Equipment Cost for three Effects Evaporator System
The total equipment cost for the process system with three effects evaporator system equals
$881,086.84
C. Project Economics
1) Annual Depreciation
Annual depreciation is calculated by straight-line depreciation with the salvage value of all
equipment is estimated to be 15% of the equipment cost with the expected life of the
equipment is 10 years.
Total Equipment Cost $ 881,086.84
Salvage Value $ 132,163.03
16
Depreciable Asset Cost $ 748,923.82
Depreciation Rate/Year 10%
Annual Depreciation $ 74,892.38
Table 8: Annual Depreciation for three Effects Evaporator System
Annual depreciation for three effect evaporator system is $74,892.38
2) Variables Cost of Production
To calculate variables cost of production, the number of water comes from cooling water of
condenser and steam for the boiler, electricity is used for the feed pump of sea water, and natural
gas is used for the boiler to heat water the run the system.
Utilities Consumption/day Cost $/unit Cost $/day Cost $/year
Cooling water (gal) 1,063,043.26 0.005 5,315.22 1,594,564.88
Electricity (kWh) 731,531.69 0.046 33,650.46 10,095,137.39
Natural - gas (MM BTU) 309.97 2.178 675.11 202,532.89
Total variable cost $/year $ 11,892,235.16
Table 9: Variables Cost of Production for three Effects Evaporator System
From the table above, the main costs that effect to the variables cost of production are cost of
cooling water for the condenser and cost of electricity for the sea water feed pump. However,
based on mass balance, to produce 400,000 lb/day of fresh water, the flowrate of sea water is
414,508 lb/day, which is 2.12 liters/s, and this value is constant, so the electricity cost is
constant; therefore, the main utilities that effects to the changing variables cost of production is
volume flowrate of cooling water.
3) Annual Labor, Maintenance, and Fixed Charges
The calculation for annual labor, maintenance, and fixed charged are shown in table below with
the maintenance charged are 5% of the initial total equipment cost, and fixed charges excluding
depreciation are 15% of the installed cost of the evaporators
Number of operators/shift 4
Operator salary $/hr 15
Number of engineers 2
17
Engineer Salary/season 25000
Plant Manager 1
Manager salary/season 37000
Over head 100% labor cost
Total labor cost $/year $ 1,560,000.00
Maintenance (5% Total equipment cost/year) $ 44,054.34
Fixed Charge ( 15% installed evaporator cost) $ 86,749.03
Table 10: Annual Labor, Maintenance, and Fixed Charges
4) Variables cost per gallon fresh water production
From all the costs that are calculated above, with 400,000 lb/day or 14.3 MM gal/day of fresh
water produce, the variables cost per gallon fresh water production is shown in table below
$/year $/gal of Water
Utilities $ 11,892,235.16 $ 0.83
Depreciation $ 74,892.38 $ 0.01
Labor $ 1,560,000.00 $ 0.11
Maintenance $ 44,054.34 $ 0.00
Fixed Charge $ 86,749.03 $ 0.01
Total $ 13,657,930.92 $ 0.95
Table 11: Variables cost per gallon fresh water production
From the table above, the cost of utilities is the highest cost that need to spend for the process.
5) Cash Flow and NPV Analysis
A cash flow analysis is done based on Annual Depreciation, Variables Cost of Production,
Annual Labor, Maintenance, and Fixed Charges for this project with the total is equal $17MM
each year. Net Present Value (NPV) method is applied to assess the economic value of the
project. A common Internal Rate of Return (IRR) of 8.5% is used for calculation. Tax is
incorporated and equals 28% of the net income. Desalinated water is sold for $1/gal. 400,000
lb/year or 14.3MM gal/year of fresh water is produced. It means the revenue of this project
equals $14.3 MM. The NPV of this plant is calculated in 10 years.
Year Cost Revenue Tax Cash Flow NPV Total NPV to year
0 $ 881,086.84 $ (881,086.84) $ (881,086.84) $ (881,086.84)
18
1 $ 13,657,930.92 $ 14,392,090.56 $ 205,564.70 $ 528,594.94 $ 449,305.70 $ (431,781.14)
2 $ 13,657,930.92 $ 14,392,090.56 $ 205,564.70 $ 528,594.94 $ 381,909.85 $ (49,871.30)
3 $ 13,657,930.92 $ 14,392,090.56 $ 205,564.70 $ 528,594.94 $ 324,623.37 $ 274,752.07
4 $ 13,657,930.92 $ 14,392,090.56 $ 205,564.70 $ 528,594.94 $ 275,929.86 $ 550,681.93
5 $ 13,657,930.92 $ 14,392,090.56 $ 205,564.70 $ 528,594.94 $ 234,540.38 $ 785,222.32
6 $ 13,657,930.92 $ 14,392,090.56 $ 205,564.70 $ 528,594.94 $ 199,359.33 $ 984,581.64
7 $ 13,657,930.92 $ 14,392,090.56 $ 205,564.70 $ 528,594.94 $ 169,455.43 $ 1,154,037.07
8 $ 13,657,930.92 $ 14,392,090.56 $ 205,564.70 $ 528,594.94 $ 144,037.11 $ 1,298,074.18
9 $ 13,657,930.92 $ 14,392,090.56 $ 205,564.70 $ 528,594.94 $ 122,431.55 $ 1,420,505.73
10 $ 13,657,930.92 $ 14,392,090.56 $ 205,564.70 $ 528,594.94 $ 104,066.81 $ 1,524,572.55
Table 12: Cash Flow and NPV Analysis
The NPV of this plant after 10 years is $1.5MM. The payback period is 2 years; the profit being
earned on the third year. With the NPV equal $1.5MM, which is 1.7 of the capital investment,
this project is worth implementing.
PROCESS WITH FOUR EFFECTS EVAPORATOR SYSTEM
A. Mass and Energy Balance
With pressure of the boiler P = 40 bar, pressure of the 1st effect P = 30 bar, pressure of the 2nd
effect P = 20 bar, pressure of the 3rd effect P = 10 bar, pressure of the 4th effect P = 4 bar, and
pressure of the condenser P = 1 bar, the base is given for mass flowrate of fresh water is 400,000
lb/day and is produced from sea water that contains 3.5 wt% salt, from the steam tables combine
with mass and energy balance equations, the mass of steam and brine coming out of each effect,
mass of cooling water coming in to the condenser, mass of steam needed to heat up in the boiler,
the heat duty of natural gas that is required to heat up the steam in the boiler, the heat duty of
condenser and its area need to design to cool the hot stream are calculated.
19
20
Figure 12: Mass and Energy Balance Calculation for four Effects Evaporator System
Based on the values are calculated, the summary for mass and energy balance for the system is
shown in these figures below
Figure 13: Mass Balance of the Process with four Effects Evaporator System
21
Figure 14: Energy Balance of the Boiler and four Effects Evaporator System
Figure 15: Mass and Energy Balance of Condenser for four Effects Evaporator System
22
From those values of mass flowrate and heat duty that are calculated above, the unit such as
power of the pumps or area of evaporators are find out to estimate for equipment cost of the
project.
B. Major Equipment List and Purchased Cost
Figure 16: Cost Equipment Calculation for four Effects Evaporator System
From those calculations that are presented above, the table of total equipment cost of process
is show in below
Name Unit of Size Value a b n Material Cost in 2010 Cost in 2016
Boiler Steam (liters/s) 3552.11 124000 10 1 Carbon Steel $ 159,521.07 $ 191,425.29
Condenser Area (m2) 19.36 1900 2500 1 Carbon Steel $ 50,293.17 $ 60,351.81
Effect 1 Area (m2) 15.17 330 36000 0.55 Carbon Steel $ 160,937.50 $ 193,125.00
23
Effect 2 Area (m2) 14.29 330 36000 0.55 Carbon Steel $ 155,794.81 $ 186,953.77
Effect 3 Area (m2) 11.05 330 36000 0.55 Carbon Steel $ 135,244.07 $ 162,292.88
Effect 4 Area (m2) 9.93 330 36000 0.55 Carbon Steel $ 127,565.84 $ 153,079.01
Feed Pump Flow (liter/s) 2.12 8000 240 0.9 Carbon Steel $ 8,471.31 $ 10,165.57
Pump 1 Flow (liter/s) 1.20 800 240 0.9 Carbon Steel $ 8,282.97 $ 9,939.56
Pump 2 Flow (liter/s) 0.79 800 240 0.9 Carbon Steel $ 8,194.46 $ 9,833.35
Pump 3 Flow (liter/s) 0.53 800 240 0.9 Carbon Steel $ 8,135.62 $ 9,762.74
Pump 4 Flow (liter/s) 0.50 800 240 0.9 Carbon Steel $ 8,128.77 $ 9,754.52
Total Equipment Cost $ 996,683.49
Table 13: Total Equipment Cost for four Effects Evaporator System
The total equipment cost for the process system with four effects evaporator system equals
$996,683.49
C. Project Economics
1) Annual Depreciation
Annual depreciation is calculated by straight-line depreciation with the salvage value of all
equipment is estimated to be 15% of the equipment cost with the expected life of the
equipment is 10 years.
Table 14: Annual Depreciation for four Effects Evaporator System
Annual depreciation for four effect evaporator system is $84,719.28
2) Variables Cost of Production
To calculate variables cost of production, the number of water comes from cooling water of
condenser and steam for the boiler, electricity is used for the feed pump of sea water, and natural
gas is used for the boiler to heat water the run the system.
Utilities Consumption/day Cost $/unit Cost $/day Cost $/year
Cooling water (gal) 821,680.70 0.005 4,108.40 1,232,521.05
Total Equipment Cost $ 996,697.45
Salvage Value $ 149,504.62
Depreciable Asset Cost $ 847,192.84
Depreciation Rate/Year 10%
Annual Depreciation $ 84,719.28
24
Electricity (kWh) 731,531.69 0.046 33,891.90 10,167,570.51
Natural – gas (MM BTU) 269.04 2.178 585.97 175,790.74
Total variables cost $/year 11,575,882.30
Table 15: Variables Cost of Production for four Effects Evaporator System
From the table above, the main costs that effect to the variables cost of production are cost of
cooling water for the condenser and cost of electricity for the sea water feed pump. However,
based on mass balance, to produce 400,000 lb/day of fresh water, the flowrate of sea water is
414,508 lb/day, which is 2.12 liters/s, and this value is constant, so the electricity cost is
constant; therefore, the main utilities that effects to the changing variables cost of production is
volume flowrate of cooling water.
3) Annual Labor, Maintenance, and Fixed Charges
The calculation for annual labor, maintenance, and fixed charged are shown in table below with
the maintenance charged are 5% of the initial total equipment cost, and fixed charges excluding
depreciation are 15% of the installed cost of the evaporators
Number of operators/shift 5
Operator salary $/hr 15
Number of engineers 2
Engineer Salary/season 25000
Plant Manager 1
Manager salary/season 37000
Over head 100% labor cost
Total labor cost $/year $ 1,560,000.00
Maintenance (5% Total equipment cost/year) $ 44,054.34
Fixed Charge ( 15% installed evaporator cost) $ 86,749.03
Table 16: Annual Labor, Maintenance, and Fixed Charges
4) Variables cost per gallon fresh water production
From all the costs that are calculated above, with 400,000 lb/day or 14.3 MM gal/day of fresh
water produce, the variables cost per gallon fresh water production is shown in table below
25
$/year $/gal of Water
Utilities $ 11,892,235.16 $ 0.83
Depreciation $ 74,892.38 $ 0.01
Labor $ 1,560,000.00 $ 0.11
Maintenance $ 44,054.34 $ 0.00
Fixed Charge $ 86,749.03 $ 0.01
Total $ 13,657,930.92 $ 0.95
Table 17: Variables cost per gallon fresh water production
From the table above, the cost of utilities is the highest cost that need to spend for the process.
5) Cash Flow and NPV Analysis
A cash flow analysis is done based on Annual Depreciation, Variables Cost of Production,
Annual Labor, Maintenance, and Fixed Charges for this project with the total is equal $17MM
each year. Net Present Value (NPV) method is applied to assess the economic value of the
project. A common Internal Rate of Return (IRR) of 8.5% is used for calculation. Tax is
incorporated and equals 28% of the net income. Desalinated water is sold for $1/gal. 400,000
lb/year or 14.3MM gal/year of fresh water is produced. It means the revenue of this project
equals $14.3 MM. The NPV of this plant is calculated in 10 years.
Year Cost Revenue Tax Cash Flow NPV Total NPVto year
0 $ 996,683.49 $ (996,683.49) $ (996,683.49) $ (996,683.49)
1 $ 13,590,755.37 $ 14,392,090.56 $ 224,373.85 $ 576,961.34 $ 490,417.14 $ (506,266.36)
2 $ 13,590,755.37 $ 14,392,090.56 $ 224,373.85 $ 576,961.34 $ 416,854.57 $ (89,411.79)
3 $ 13,590,755.37 $ 14,392,090.56 $ 224,373.85 $ 576,961.34 $ 354,326.38 $ 264,914.59
4 $ 13,590,755.37 $ 14,392,090.56 $ 224,373.85 $ 576,961.34 $ 301,177.42 $ 566,092.01
5 $ 13,590,755.37 $ 14,392,090.56 $ 224,373.85 $ 576,961.34 $ 256,000.81 $ 822,092.82
6 $ 13,590,755.37 $ 14,392,090.56 $ 224,373.85 $ 576,961.34 $ 217,600.69 $ 1,039,693.51
7 $ 13,590,755.37 $ 14,392,090.56 $ 224,373.85 $ 576,961.34 $ 184,960.59 $ 1,224,654.10
8 $ 13,590,755.37 $ 14,392,090.56 $ 224,373.85 $ 576,961.34 $ 157,216.50 $ 1,381,870.60
9 $ 13,590,755.37 $ 14,392,090.56 $ 224,373.85 $ 576,961.34 $ 133,634.02 $ 1,515,504.62
10 $ 13,590,755.37 $ 14,392,090.56 $ 224,373.85 $ 576,961.34 $ 113,588.92 $ 1,629,093.54
Table 18: Cash Flow and NPV Analysis
26
The NPV of this plant after 10 years is $1.63MM. The payback period is 2 years; the profit being
earned on the third year. With the NPV equal $1.63MM, which is 1.63 of the capital investment,
this project is worth implementing.
PROCESS WITH SIX EFFECTS EVAPORATOR SYSTEM
A. Mass and Energy Balance
With pressure of the boiler P = 40 bar, pressure of the 1st effect P = 30 bar, pressure of the 2nd
effect P = 25 bar, pressure of the 3rd effect P = 20 bar, pressure of the 4th effect P = 15 bar,
pressure of the 5th effect P = 10 bar, pressure of the 6th effect P = 4 bar, and pressure of the
condenser P = 1 bar, the base is given for mass flowrate of fresh water is 400,000 lb/day and is
produced from sea water that contains 3.5 wt% salt, from the steam tables combine with mass
and energy balance equations, the mass of steam and brine coming out of each effect, mass of
cooling water coming in to the condenser, mass of steam needed to heat up in the boiler, the heat
duty of natural gas that is required to heat up the steam in the boiler, the heat duty of condenser
and its area need to design to cool the hot stream are calculated.
27
28
Figure 17: Mass and Energy Balance Calculation for six Effects Evaporator System
From those values of mass flowrate and heat duty that are calculated above, the unit such as
power of the pumps or area of evaporators are find out to estimate for equipment cost of the
project.
B. Major Equipment List and Purchased Cost
29
Figure 18: Cost Equipment Calculation for six Effects Evaporator System
From those calculations that are presented above, the table of total equipment cost of process
is show in below
Name Unit of Size Value a b n Material Cost in 2010 Cost in 2016
Boiler Steam(liters/s) 2969.32 124000 10 1 Carbon Steel $ 153,693.15 $ 184,431.78
Condenser Area (m2) 7.09 1900 2500 1 Carbon Steel $ 19,630.07 $ 23,556.09
Effect 1 Area (m2) 12.63 330 36000 0.55 Carbon Steel $ 145,565.34 $ 174,678.41
Effect 2 Area (m2) 12.73 330 36000 0.55 Carbon Steel $ 146,190.10 $ 175,428.12
Effect 3 Area (m2) 10.48 330 36000 0.55 Carbon Steel $ 131,398.89 $ 157,678.67
Effect 4 Area (m2) 7.37 330 36000 0.55 Carbon Steel $ 108,323.70 $ 129,988.44
30
Effect 5 Area (m2) 6.8143 330 36000 0.55 Carbon Steel $ 103,769.04 $ 124,522.85
Effect 6 Area (m2) 4.3441 330 36000 0.55 Carbon Steel $ 81,081.04 $ 97,297.25
Feed Pump Flow (liter/s) 2.12 8000 240 0.9 Carbon Steel $ 8,471.31 $ 10,165.57
Pump 1 Flow (liter/s) 1.00 800 240 0.9 Carbon Steel $ 8,240.82 $ 9,888.98
Pump 2 Flow (liter/s) 52.75 800 240 0.9 Carbon Steel $ 16,515.52 $ 19,818.62
Pump 3 Flow (liter/s) 48.92 800 240 0.9 Carbon Steel $ 15,957.56 $ 19,149.08
Pump 4 Flow (liter/s) 48.26 800 240 0.9 Carbon Steel $ 15,859.62 $ 19,031.54
Pump 5 Flow (liter/s) 47.32 800 240 0.9 Carbon Steel $ 8,522.38 $ 10,226.86
Pump 6 Flow (liter/s) 85.88 800 240 0.9 Carbon Steel $ 14,004.62 $ 16,805.54
Total Equipment Cost $ 1,172,667.79
Table 19: Total Equipment Cost for six Effects Evaporator System
The total equipment cost for the process system with six effects evaporator system equals
$1.172MM
C. Project Economics
1) Annual Depreciation
Annual depreciation is calculated by straight-line depreciation with the salvage value of all
equipment is estimated to be 15% of the equipment cost with the expected life of the
equipment is 10 years.
Table 20: Annual Depreciation for six Effects Evaporator System
Annual depreciation for six effect evaporator system is $99,676.76
2) Variables Cost of Production
To calculate variables cost of production, the number of water comes from cooling water of
condenser and steam for the boiler, electricity is used for the feed pump of sea water, and natural
gas is used for the boiler to heat water the run the system.
Utilities Consumption/day Cost $/unit Cost $/day Cost $/year
Total Equipment Cost $ 1,172,667.79
Salvage Value $ 175,900.17
Depreciable Asset Cost $ 996,767.62
Depreciation Rate/Year 10%
Annual Depreciation $ 99,676.76
31
Cooling water (gal) 312,683.35 0.005 1,563.42 469,025.03
Electricity (kWh) 731,531.69 0.046 33,650.46 10,095,137.39
Natural - gas (MM BTU) 225.43 2.178 491.00 147,299.22
Total variable cost $/year 10,711,461.64
Table 21: Variables Cost of Production for six Effects Evaporator System
From the table above, the main costs that effect to the variables cost of production are cost of
cooling water for the condenser and cost of electricity for the sea water feed pump. However,
based on mass balance, to produce 400,000 lb/day of fresh water, the flowrate of sea water is
414,508 lb/day, which is 2.12 liters/s, and this value is constant, so the electricity cost is
constant; therefore, the main utilities that effects to the changing variables cost of production is
volume flowrate of cooling water.
3) Annual Labor, Maintenance, and Fixed Charges
The calculation for annual labor, maintenance, and fixed charged are shown in table below with
the maintenance charged are 5% of the initial total equipment cost, and fixed charges excluding
depreciation are 15% of the installed cost of the evaporators
Number of operators/shift 7
Operator salary $/hr 15
Number of engineers 2
Engineer Salary/season 25000
Plant Manager 1
Manager salary/season 37000
Over head 100% labor cost
Total labor cost $/year $ 2,208,000.00
Maintenance (5% Total equipment cost/year) $ 58,633.39
Fixed Charge ( 15% installed evaporator cost) $ 128,939.06
Table 22: Annual Labor, Maintenance, and Fixed Charges
4) Variables cost per gallon fresh water production
From all the costs that are calculated above, with 400,000 lb/day or 14.3 MM gal/day of fresh
water produce, the variables cost per gallon fresh water production is shown in table below
32
$/year $/gal of Water
Utilities $ 10,711,461.64 $ 0.74
Depreciation $ 99,676.76 $ 0.01
Labor $ 2,208,000.00 $ 0.15
Maintenance $ 58,633.39 $ 0.00
Fixed Charge $ 128,939.06 $ 0.01
Total $ 13,206,710.85 $ 0.92
Table 23: Variables cost per gallon fresh water production
From the table above, the cost of utilities is the highest cost that need to spend for the process.
5) Cash Flow and NPV Analysis
A cash flow analysis is done based on Annual Depreciation, Variables Cost of Production,
Annual Labor, Maintenance, and Fixed Charges for this project with the total is equal $17MM
each year. Net Present Value (NPV) method is applied to assess the economic value of the
project. A common Internal Rate of Return (IRR) of 8.5% is used for calculation. Tax is
incorporated and equals 28% of the net income. Desalinated water is sold for $1/gal. 400,000
lb/year or 14.3MM gal/year of fresh water is produced. It means the revenue of this project
equals $14.3 MM. The NPV of this plant is calculated in 10 years.
Year Cost Revenue Tax Cash Flow NPV Total NPVto year
0 $ 1,172,667.79 $ (1,172,667.79) $ (1,172,667.79) $ (1,172,667.79)
1 $ 13,206,710.85 $ 14,392,090.56 $ 331,906.32 $ 853,473.39 $ 725,452.38 $ (447,215.40)
2 $ 13,206,710.85 $ 14,392,090.56 $ 331,906.32 $ 853,473.39 $ 616,634.53 $ 169,419.12
3 $ 13,206,710.85 $ 14,392,090.56 $ 331,906.32 $ 853,473.39 $ 524,139.35 $ 693,558.47
4 $ 13,206,710.85 $ 14,392,090.56 $ 331,906.32 $ 853,473.39 $ 445,518.45 $ 1,139,076.92
5 $ 13,206,710.85 $ 14,392,090.56 $ 331,906.32 $ 853,473.39 $ 378,690.68 $ 1,517,767.60
6 $ 13,206,710.85 $ 14,392,090.56 $ 331,906.32 $ 853,473.39 $ 321,887.08 $ 1,839,654.67
7 $ 13,206,710.85 $ 14,392,090.56 $ 331,906.32 $ 853,473.39 $ 273,604.02 $ 2,113,258.69
8 $ 13,206,710.85 $ 14,392,090.56 $ 331,906.32 $ 853,473.39 $ 232,563.41 $ 2,345,822.10
9 $ 13,206,710.85 $ 14,392,090.56 $ 331,906.32 $ 853,473.39 $ 197,678.90 $ 2,543,501.00
10 $ 13,206,710.85 $ 14,392,090.56 $ 331,906.32 $ 853,473.39 $ 168,027.07 $ 2,711,528.07
Table 24: Cash Flow and NPV Analysis
33
The NPV of this plant after 10 years is $2.7MM. The payback period is 1 years; the profit being
earned on the 2nd year. With the NPV equal $2.7MM, which is 1.6 of the capital investment, this
project is worth implementing.
OPTIONS:
From all the analysis economics parts that show in table 6, 12, 18, and 24, the more number of
effects evaporator, the higher NPV for this plant. The relation between number of effects
evaporator and NPV is shown in the table and graph below.
Table 25: Number of Effect to total NPV to 10th year
Figure 19: Number of Effect to Total NPV to 10th year
From the table and the graph above, 6 effects evaporator system should be used to design the
plant because it gives the highest NPV value. Also, the main cost that need to spend that effect
$(12,000,000.00)
$(10,000,000.00)
$(8,000,000.00)
$(6,000,000.00)
$(4,000,000.00)
$(2,000,000.00)
$-
$2,000,000.00
$4,000,000.00
0 1 2 3 4 5 6 7
TotalNPVto10years
Number of Effect
# of Effecct Vs Total NPV
Number of Effect total NPV to 10th year
1 $ (10,299,230.22)
3 $ 1,524,572.55
4 $ 1,629,093.54
6 $ 2,711,528.07
34
the most changing to the NPV value is the cost of volume flowrate of cooling water for the
condenser. It is show in table and graph below.
Cooling Water Flowrate (MM gal/day) NPV to 10th year ($)
3.95 $ (10,299,230.22)
1.06 $ 1,524,572.55
0.82 $ 1,629,093.54
0.31 $ 2,711,528.07
Table 26: Cooling Water Flowrate to Total NPV to 10th year
Figure 20: Cooling Water Flowrate (MM gal/day) to Total NPV to 10th year
The more effects evaporator, the less steam need to cool, so the less cooling water need to use in
condenser; therefore, the higher total NPV.
In conclude, system should be design with 6 effects evaporator.
SAFETY CONCERN
A. Overall Process
The chemicals involved in this process are sea water, and desalinated water. They are not
harmful so all the preventions for this plant are wearing protective gloves, safety goggles, and be
careful with the place that have hot steam.
1 effect
3 effects
4 effects
6 effects
$(12,000,000.00)
$(10,000,000.00)
$(8,000,000.00)
$(6,000,000.00)
$(4,000,000.00)
$(2,000,000.00)
$-
$2,000,000.00
$4,000,000.00
- 0.50 1.00 1.50 2.00 2.50 3.00 3.50 4.00 4.50
Cooling Water Vs Total NPV
35
B. Hazard and Operability study (HAZOP)
HAZOP Table and figure below is used for Steam at Boiler and Cooling Water in Condenser
Incident Effects Recommendations Likelihood Severity Detection
Overall
Risk
STEAM OF BOILER
1
Reverse
Flow No steam in each effect
Check valves to prevent
back flow and place a flow
meter 1 10 3 30
2 No Flow No steam in each effect Place a flow meter 1 7 3 30
3 More Flow
Too much steam in each
effect
Place a flow meter and
pressure transmitter 3 7 3 63
4 Less Flow
Less steam in each effect,
so less fresh water produce
Place a flow meter and
pressure transmitter 3 5 3 27
5
High
Temperature Combust or over pressure
Place a Temperature
Transmitter 5 3 5 75
6
Low
Temperature
Less steam in each effect,
so less fresh water produce
Place a Temperature
Transmitter 3 3 3 27
7
High
Pressure Rupture steam tube
Place a pressure
transmitter 3 5 3 45
8
Low
Pressure Rupture steam tube
Place a pressure
transmitter 1 5 5 25
COOLING WATER OF CONDENSER
9
Reverse
Flow
Too hot of fresh water
out of condenser
Check valves to prevent
back flow and place a flow
meter 1 7 3 21
10 No Flow No fresh water condense Place a flow meter 1 5 3 15
11 More Flow
Over pressure and
cause rupture Place a flow meter 3 5 5 75
12 Less Flow
Temperature of Fresh
water would increase Place a flow meter 3 5 3 45
13
High
Temperature
Temperature of Fresh
water would increase
Place a Temperature
Transmitter 5 3 3 45
14
Low
Temperature
Temperature of Fresh
water would decrease
Place a Temperature
Transmitter 3 3 1 9
15
High
Pressure Rupture cooling water tube
Place a Pressure
Transmitter 3 5 3 45
16
Low
Pressure Rupture cooling water tube
Place a Pressure
Transmitter 1 5 3 15
Table 27: HAZOP for Steam at Boiler and Cooling Water in Condenser
36
Figure 22: Boston square for Boiler and Condenser HAZOP
CONCLUSION and RECOMMENDATION:
This report is about a general plant design 400,000 lb/day of fresh water from sea water with 3.5
wt% salt. From all economics analysis, the system will have 1 boiler, 6 effects evaporator, 6
pumps and 1 condenser. The project requires $1.2 MM capital investment and annual $14.4 MM
cost for production. After 1 years, the investment starts to earn profit. At the end of year 10th,
NPV is about $2.7 MM. And the flowrate of cooling water is the most effective to changing
NPV value with the more effects evaporator, the less steam need to cool, so the less cooling
water need to use in condenser; therefore, the higher total NPV. And the recommendation for
this process is add the pressure transmitter, flowrate transmitter, and temperature transmitter in
each effect to guarantee the plant work well as its expectation.
1
2, 9 3
4, 7 11, 12 15
6, 14
8, 10, 16
0
2
4
6
8
10
12
0 2 4 6 8 10 12
Severity
Likelihood
Boston squarefor Boiler and Condenser HAZOP
5, 13
37

Mais conteúdo relacionado

Mais procurados

F E R T I L I Z E R I N D U S T R Y L E C T U R E 1
F E R T I L I Z E R  I N D U S T R Y  L E C T U R E 1F E R T I L I Z E R  I N D U S T R Y  L E C T U R E 1
F E R T I L I Z E R I N D U S T R Y L E C T U R E 1Rishi Yadav
 
Design finalreport2
Design finalreport2Design finalreport2
Design finalreport2jic050
 
Styrene Production by Catalytic Dehydrogenation of Ethylbenzene
Styrene Production by Catalytic Dehydrogenation of Ethylbenzene Styrene Production by Catalytic Dehydrogenation of Ethylbenzene
Styrene Production by Catalytic Dehydrogenation of Ethylbenzene Michelle Otutu
 
Deyab a. aspen hysys 2013 workbook
Deyab a.  aspen hysys 2013   workbookDeyab a.  aspen hysys 2013   workbook
Deyab a. aspen hysys 2013 workbookLito Aguirre
 
ChE184B - FinalDesign
ChE184B - FinalDesignChE184B - FinalDesign
ChE184B - FinalDesignRussell Wong
 
ChE184b Final Design
ChE184b Final DesignChE184b Final Design
ChE184b Final DesignRussell Wong
 
Analysis of BHOPAL Plant Gas Tragedy
 Analysis of BHOPAL Plant Gas Tragedy Analysis of BHOPAL Plant Gas Tragedy
Analysis of BHOPAL Plant Gas TragedyRita EL Khoury
 
Thyssenkrupp uhde advanced ammonia processes dual pressure
Thyssenkrupp uhde advanced ammonia processes dual pressureThyssenkrupp uhde advanced ammonia processes dual pressure
Thyssenkrupp uhde advanced ammonia processes dual pressureSteve Wittrig
 
Ammonia plant efficiency
Ammonia plant efficiencyAmmonia plant efficiency
Ammonia plant efficiencyHimanshu Sharma
 
Methanol Loop Start Up and Shut Down
Methanol Loop Start Up and Shut DownMethanol Loop Start Up and Shut Down
Methanol Loop Start Up and Shut DownGerard B. Hawkins
 
Urea manufacturing process
Urea manufacturing processUrea manufacturing process
Urea manufacturing processAshvani Shukla
 
Optimization of H2 Production in a Hydrogen Generation Unit
Optimization of H2 Production in a Hydrogen Generation UnitOptimization of H2 Production in a Hydrogen Generation Unit
Optimization of H2 Production in a Hydrogen Generation UnitMárcio Garcia
 
PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independ...
PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independ...PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independ...
PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independ...Mumin HACIMUSALAR
 
Hydrogen Production steam reforming
Hydrogen Production steam reformingHydrogen Production steam reforming
Hydrogen Production steam reformingTanay_Bobde
 
Full design for acetone production
Full design for acetone productionFull design for acetone production
Full design for acetone productiondinaelgayar83
 
Important Conversion Factors in Petroleum Technology
Important Conversion Factors in Petroleum Technology Important Conversion Factors in Petroleum Technology
Important Conversion Factors in Petroleum Technology Muhammed Fuad Al-Barznji
 

Mais procurados (20)

F E R T I L I Z E R I N D U S T R Y L E C T U R E 1
F E R T I L I Z E R  I N D U S T R Y  L E C T U R E 1F E R T I L I Z E R  I N D U S T R Y  L E C T U R E 1
F E R T I L I Z E R I N D U S T R Y L E C T U R E 1
 
289109277 design-project-1-final
289109277 design-project-1-final289109277 design-project-1-final
289109277 design-project-1-final
 
Design finalreport2
Design finalreport2Design finalreport2
Design finalreport2
 
Senior Project
Senior ProjectSenior Project
Senior Project
 
Styrene Production by Catalytic Dehydrogenation of Ethylbenzene
Styrene Production by Catalytic Dehydrogenation of Ethylbenzene Styrene Production by Catalytic Dehydrogenation of Ethylbenzene
Styrene Production by Catalytic Dehydrogenation of Ethylbenzene
 
Deyab a. aspen hysys 2013 workbook
Deyab a.  aspen hysys 2013   workbookDeyab a.  aspen hysys 2013   workbook
Deyab a. aspen hysys 2013 workbook
 
ChE184B - FinalDesign
ChE184B - FinalDesignChE184B - FinalDesign
ChE184B - FinalDesign
 
ChE184b Final Design
ChE184b Final DesignChE184b Final Design
ChE184b Final Design
 
Analysis of BHOPAL Plant Gas Tragedy
 Analysis of BHOPAL Plant Gas Tragedy Analysis of BHOPAL Plant Gas Tragedy
Analysis of BHOPAL Plant Gas Tragedy
 
Thyssenkrupp uhde advanced ammonia processes dual pressure
Thyssenkrupp uhde advanced ammonia processes dual pressureThyssenkrupp uhde advanced ammonia processes dual pressure
Thyssenkrupp uhde advanced ammonia processes dual pressure
 
Ammonia plant efficiency
Ammonia plant efficiencyAmmonia plant efficiency
Ammonia plant efficiency
 
Methanol Loop Start Up and Shut Down
Methanol Loop Start Up and Shut DownMethanol Loop Start Up and Shut Down
Methanol Loop Start Up and Shut Down
 
Urea manufacturing process
Urea manufacturing processUrea manufacturing process
Urea manufacturing process
 
Uhde ammonia
Uhde ammoniaUhde ammonia
Uhde ammonia
 
Optimization of H2 Production in a Hydrogen Generation Unit
Optimization of H2 Production in a Hydrogen Generation UnitOptimization of H2 Production in a Hydrogen Generation Unit
Optimization of H2 Production in a Hydrogen Generation Unit
 
PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independ...
PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independ...PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independ...
PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independ...
 
Ammonia and urea production
Ammonia and urea productionAmmonia and urea production
Ammonia and urea production
 
Hydrogen Production steam reforming
Hydrogen Production steam reformingHydrogen Production steam reforming
Hydrogen Production steam reforming
 
Full design for acetone production
Full design for acetone productionFull design for acetone production
Full design for acetone production
 
Important Conversion Factors in Petroleum Technology
Important Conversion Factors in Petroleum Technology Important Conversion Factors in Petroleum Technology
Important Conversion Factors in Petroleum Technology
 

Destaque

PID Advances in Industrial Control
PID Advances in Industrial ControlPID Advances in Industrial Control
PID Advances in Industrial ControlEmerson Exchange
 
Agitated film evaporator
Agitated film evaporatorAgitated film evaporator
Agitated film evaporatorNurhairuna Sari
 
RITUXIMAB PLANT DESIGN
RITUXIMAB PLANT DESIGNRITUXIMAB PLANT DESIGN
RITUXIMAB PLANT DESIGNAnil Vibhute
 
Evaporators and evaporation under reduce pressure.
Evaporators and evaporation under reduce pressure.Evaporators and evaporation under reduce pressure.
Evaporators and evaporation under reduce pressure.Umair hanif
 
HAZOP - AN INTEGRATED SAFETY ASSESSMENT STUDY
HAZOP - AN INTEGRATED SAFETY ASSESSMENT STUDYHAZOP - AN INTEGRATED SAFETY ASSESSMENT STUDY
HAZOP - AN INTEGRATED SAFETY ASSESSMENT STUDYOsho Shemil Baba
 

Destaque (9)

PID Advances in Industrial Control
PID Advances in Industrial ControlPID Advances in Industrial Control
PID Advances in Industrial Control
 
Agitated film evaporator
Agitated film evaporatorAgitated film evaporator
Agitated film evaporator
 
RITUXIMAB PLANT DESIGN
RITUXIMAB PLANT DESIGNRITUXIMAB PLANT DESIGN
RITUXIMAB PLANT DESIGN
 
FYDP Sem 2
FYDP Sem 2FYDP Sem 2
FYDP Sem 2
 
Evaporator
EvaporatorEvaporator
Evaporator
 
Evaporators
EvaporatorsEvaporators
Evaporators
 
Lecture 3 bioprocess control
Lecture 3  bioprocess controlLecture 3  bioprocess control
Lecture 3 bioprocess control
 
Evaporators and evaporation under reduce pressure.
Evaporators and evaporation under reduce pressure.Evaporators and evaporation under reduce pressure.
Evaporators and evaporation under reduce pressure.
 
HAZOP - AN INTEGRATED SAFETY ASSESSMENT STUDY
HAZOP - AN INTEGRATED SAFETY ASSESSMENT STUDYHAZOP - AN INTEGRATED SAFETY ASSESSMENT STUDY
HAZOP - AN INTEGRATED SAFETY ASSESSMENT STUDY
 

Semelhante a An Minh Tran - Case 3 - Cheg 407

Heat recovery design for starbucks store retrofit_BS
Heat recovery design for starbucks store retrofit_BSHeat recovery design for starbucks store retrofit_BS
Heat recovery design for starbucks store retrofit_BSChris Anderson
 
AICHE Senior Design Project
AICHE Senior Design ProjectAICHE Senior Design Project
AICHE Senior Design ProjectJonathan Sherwin
 
IRJET- Removal of CO2 from Raw Biogas using Water Scrubbing based Up-Gradatio...
IRJET- Removal of CO2 from Raw Biogas using Water Scrubbing based Up-Gradatio...IRJET- Removal of CO2 from Raw Biogas using Water Scrubbing based Up-Gradatio...
IRJET- Removal of CO2 from Raw Biogas using Water Scrubbing based Up-Gradatio...IRJET Journal
 
IRJET- Design and Development of a Waste Heat Recovery Unit for Household Ref...
IRJET- Design and Development of a Waste Heat Recovery Unit for Household Ref...IRJET- Design and Development of a Waste Heat Recovery Unit for Household Ref...
IRJET- Design and Development of a Waste Heat Recovery Unit for Household Ref...IRJET Journal
 
Ocean_Thermal_Energy_Conversion_Using_Double-Stage.pdf
Ocean_Thermal_Energy_Conversion_Using_Double-Stage.pdfOcean_Thermal_Energy_Conversion_Using_Double-Stage.pdf
Ocean_Thermal_Energy_Conversion_Using_Double-Stage.pdfIreneKoronaki1
 
Effect of approching temperature on the performance and size of li br water v...
Effect of approching temperature on the performance and size of li br water v...Effect of approching temperature on the performance and size of li br water v...
Effect of approching temperature on the performance and size of li br water v...eSAT Publishing House
 
An Experimental Study on Treatment of Dairy Waste Water using Microbial Fuel ...
An Experimental Study on Treatment of Dairy Waste Water using Microbial Fuel ...An Experimental Study on Treatment of Dairy Waste Water using Microbial Fuel ...
An Experimental Study on Treatment of Dairy Waste Water using Microbial Fuel ...IRJET Journal
 
Mitacs hydrofuel-uoit nov 2015 200 pp cost and tech analysis of a wide variet...
Mitacs hydrofuel-uoit nov 2015 200 pp cost and tech analysis of a wide variet...Mitacs hydrofuel-uoit nov 2015 200 pp cost and tech analysis of a wide variet...
Mitacs hydrofuel-uoit nov 2015 200 pp cost and tech analysis of a wide variet...Steve Wittrig
 
Condensate Recovery System for Large AHU with Enthalpy Wheel
Condensate Recovery System for  Large AHU with Enthalpy WheelCondensate Recovery System for  Large AHU with Enthalpy Wheel
Condensate Recovery System for Large AHU with Enthalpy WheelRaji Panicker
 
INDUSTRIAL WASTE HEAT USED IN TYPICAL THERMAL POWER PLANT
  INDUSTRIAL WASTE HEAT USED IN TYPICAL THERMAL POWER PLANT  INDUSTRIAL WASTE HEAT USED IN TYPICAL THERMAL POWER PLANT
INDUSTRIAL WASTE HEAT USED IN TYPICAL THERMAL POWER PLANTIAEME Publication
 
International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)inventionjournals
 
IRJET- Experimental Research of Heat Transfer using Nano – Fluid in Radiator
IRJET- Experimental Research of Heat Transfer using Nano – Fluid in RadiatorIRJET- Experimental Research of Heat Transfer using Nano – Fluid in Radiator
IRJET- Experimental Research of Heat Transfer using Nano – Fluid in RadiatorIRJET Journal
 
case study on dance food processing industry(process integration)
case study on dance food processing industry(process integration)case study on dance food processing industry(process integration)
case study on dance food processing industry(process integration)Vikram Kataria
 
CSP Training series : solar desalination (2/2)
CSP Training series : solar desalination (2/2)CSP Training series : solar desalination (2/2)
CSP Training series : solar desalination (2/2)Leonardo ENERGY
 
MECE4410U - Project Report (Final)
MECE4410U - Project Report (Final)MECE4410U - Project Report (Final)
MECE4410U - Project Report (Final)Tushar Karanwal
 
IRJET-Detailed Energy Audit in a Captive Cogeneration Plant
IRJET-Detailed Energy Audit in a Captive Cogeneration PlantIRJET-Detailed Energy Audit in a Captive Cogeneration Plant
IRJET-Detailed Energy Audit in a Captive Cogeneration PlantIRJET Journal
 

Semelhante a An Minh Tran - Case 3 - Cheg 407 (20)

Heat recovery design for starbucks store retrofit_BS
Heat recovery design for starbucks store retrofit_BSHeat recovery design for starbucks store retrofit_BS
Heat recovery design for starbucks store retrofit_BS
 
AICHE Senior Design Project
AICHE Senior Design ProjectAICHE Senior Design Project
AICHE Senior Design Project
 
CBE480ProjectReport
CBE480ProjectReportCBE480ProjectReport
CBE480ProjectReport
 
299
299299
299
 
IRJET- Removal of CO2 from Raw Biogas using Water Scrubbing based Up-Gradatio...
IRJET- Removal of CO2 from Raw Biogas using Water Scrubbing based Up-Gradatio...IRJET- Removal of CO2 from Raw Biogas using Water Scrubbing based Up-Gradatio...
IRJET- Removal of CO2 from Raw Biogas using Water Scrubbing based Up-Gradatio...
 
IRJET- Design and Development of a Waste Heat Recovery Unit for Household Ref...
IRJET- Design and Development of a Waste Heat Recovery Unit for Household Ref...IRJET- Design and Development of a Waste Heat Recovery Unit for Household Ref...
IRJET- Design and Development of a Waste Heat Recovery Unit for Household Ref...
 
Ocean_Thermal_Energy_Conversion_Using_Double-Stage.pdf
Ocean_Thermal_Energy_Conversion_Using_Double-Stage.pdfOcean_Thermal_Energy_Conversion_Using_Double-Stage.pdf
Ocean_Thermal_Energy_Conversion_Using_Double-Stage.pdf
 
Effect of approching temperature on the performance and size of li br water v...
Effect of approching temperature on the performance and size of li br water v...Effect of approching temperature on the performance and size of li br water v...
Effect of approching temperature on the performance and size of li br water v...
 
An Experimental Study on Treatment of Dairy Waste Water using Microbial Fuel ...
An Experimental Study on Treatment of Dairy Waste Water using Microbial Fuel ...An Experimental Study on Treatment of Dairy Waste Water using Microbial Fuel ...
An Experimental Study on Treatment of Dairy Waste Water using Microbial Fuel ...
 
Mitacs hydrofuel-uoit nov 2015 200 pp cost and tech analysis of a wide variet...
Mitacs hydrofuel-uoit nov 2015 200 pp cost and tech analysis of a wide variet...Mitacs hydrofuel-uoit nov 2015 200 pp cost and tech analysis of a wide variet...
Mitacs hydrofuel-uoit nov 2015 200 pp cost and tech analysis of a wide variet...
 
Condensate Recovery System for Large AHU with Enthalpy Wheel
Condensate Recovery System for  Large AHU with Enthalpy WheelCondensate Recovery System for  Large AHU with Enthalpy Wheel
Condensate Recovery System for Large AHU with Enthalpy Wheel
 
INDUSTRIAL WASTE HEAT USED IN TYPICAL THERMAL POWER PLANT
  INDUSTRIAL WASTE HEAT USED IN TYPICAL THERMAL POWER PLANT  INDUSTRIAL WASTE HEAT USED IN TYPICAL THERMAL POWER PLANT
INDUSTRIAL WASTE HEAT USED IN TYPICAL THERMAL POWER PLANT
 
International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)
 
IRJET- Experimental Research of Heat Transfer using Nano – Fluid in Radiator
IRJET- Experimental Research of Heat Transfer using Nano – Fluid in RadiatorIRJET- Experimental Research of Heat Transfer using Nano – Fluid in Radiator
IRJET- Experimental Research of Heat Transfer using Nano – Fluid in Radiator
 
case study on dance food processing industry(process integration)
case study on dance food processing industry(process integration)case study on dance food processing industry(process integration)
case study on dance food processing industry(process integration)
 
P044058595
P044058595P044058595
P044058595
 
CSP Training series : solar desalination (2/2)
CSP Training series : solar desalination (2/2)CSP Training series : solar desalination (2/2)
CSP Training series : solar desalination (2/2)
 
IJET-V2I6P2
IJET-V2I6P2IJET-V2I6P2
IJET-V2I6P2
 
MECE4410U - Project Report (Final)
MECE4410U - Project Report (Final)MECE4410U - Project Report (Final)
MECE4410U - Project Report (Final)
 
IRJET-Detailed Energy Audit in a Captive Cogeneration Plant
IRJET-Detailed Energy Audit in a Captive Cogeneration PlantIRJET-Detailed Energy Audit in a Captive Cogeneration Plant
IRJET-Detailed Energy Audit in a Captive Cogeneration Plant
 

An Minh Tran - Case 3 - Cheg 407

  • 1. Process Evaluation and Design II – Spring 2016 Process Evaluation and Design II – Spring 2016 CHEG 407 – A CASE 3: PRODUCTION FRESH WATER FROM SEA WATER BY MULTI-EFFECT EVAPORATOR SYSTEM Instructor: Dr. Jacob R. Borden Submitted by: An Minh Tran College of Engineering and Technology McNeese State University Date Submitted: May 3, 2016
  • 2. 2 Table of Contents Executive Summary........................................................................................................................ 3 Introduction..................................................................................................................................... 3 Overall Process Description............................................................................................................ 3 Process with one Effect Evaporator System...........................…………………………………….4 A. Mass and Energy Balance………………..…………………………………………….5 B. Major Equipment List and Purchased Cost…………………………………………….8 C. Project Economics……………………………………………………………………...9 Process with three Effects Evaporator System……………………………………………..........11 A. Mass and Energy Balance…………………………………………………………….11 B. Major Equipment List and Purchased Cost…………………………………………...15 C. Project Economics…………………………………………………………………….16 Process with four Effects Evaporator System……………………………………………………19 A. Mass and Energy Balance…………………………………………………………….19 B. Major Equipment List and Purchased Cost…………………………………………...22 C. Project Economics…………………………………………………………………….24 Process with six Effects Evaporator System……………………………………………………..27 A. Mass and Energy Balance…………………………………………………………….27 B. Major Equipment List and Purchased Cost…………………………………………...29 C. Project Economics…………………………………………………………………….31 Options…………………………………………………………………………………………...33 Safety Concerns ............................................................................................................................ 34 A. Over Process………………………………………………………………………….34 B. Hazard and operability study (HAZOP)………………………………………………35 Conclusion and Recommendation ................................................................................................ 36
  • 3. 3 EXECUTIVE SUMMARY This report is a process design for the production of fresh water from sea water that contains 3.5 wt% salt. A multi – effect evaporator system that includes of number of effect, 1 boiler, and 1 condenser is used in this process. This paper provides a basic plant design with process flow diagram, mass and energy balance, total equipment cost, economics analysis, and safety concerns of the plant. The plant design basis is 400,000 pounds of fresh water is produced per day, operating 300 days per year. The expected life of the equipment is 10 years and salvage value of all equipment is 15% of the total equipment cost. Depreciate the equipment is calculated by straight-line depreciation. Fixed charged are 15% of the installed cost of the evaporators excluding depreciation. Maintenance charges are 5% of the total equipment cost. In this report, the economics analysis is used base on different system with 1 effect, 3 effects, 4 effects, and 6 effects; then which option will give the highest total NPV will be chose to design the plant. INTRORUCTION Water is very important for human’s life. People drink water everyday to survive. The plants need water in their photosynthesis process. Many factories use water for their cooling system. Electricity can also produce by water; and many application of water in the real life. However, because of the climate change and the increasing of population, souce of fresh water from nature such as river or ground water seems like not enough to provide for human life. Besides, sea water is the unlimit souce of water from natural. Therefore, a multi-effect evaporator need to be designed to desalinate sea water to fresh water to provide for human life is very necessary. OVERALL PROCESS DESCRIPTION Sea water that pump to each evaporator is heated by hot steam which comes from the boiler. After heated by hot steam, sea water turns to be hot vapor and is lead to the next evaporator to
  • 4. 4 heat the next sea water flow of next evaporator. The cooling water on the other hand is pumped to boiler. On next evaporater the sea water fed and the sea water coming from first evaporator are heated by the steam coming from same evaporator to produce fresh water. Similarly, the process keeps continuous until it goes to the last evaporator. At the last evaporator, the steam is cooled by cooling water of the condenser. The figure below shown in the flow diagram of the Process with four effect evaporator is used to make fresh water from sea water. Figure 1: Flow Diagram of four Effects Evaporator System PROCESS WITH ONE EFFECT EVAPORATOR SYSTEM A. Mass and Energy Balance With pressure of the boiler P = 40 bar, pressure of the effect P = 30 bar, and pressure of condenser P = 1 bar, the base is given for mass flowrate of fresh water is 400,000 lb/day and is produced from sea water that contains 3.5 wt% salt, from the steam tables combine with mass
  • 5. 5 and energy balance equations, the mass of brine coming out of effect, mass of cooling water coming in to the condenser, mass of steam needed to heat up in the boiler, the heat duty of natural gas that is required to heat up the steam in the boiler, the heat duty of condenser and its area need to design to cool the hot stream are calculated. Figure 2: Mass and Energy Balance Calculation for one Effect Evaporator System Based on the values are calculated, the summary for mass and energy balance for the system is shown in these figures below
  • 6. 6 Figure 3: Mass Balance of the Process with one Effect Evaporator System Figure 4: Energy Balance of the Boiler and one Effect Evaporator System
  • 7. 7 Figure 5: Mass and Energy Balance of Condenser for one Effect Evaporator System From those values of mass flowrate and heat duty that are calculated above, the unit such as power of the pumps or area of evaporators are find out to estimate for equipment cost of the project. B. Major Equipment List and Purchased Cost Figure 6: Cost Equipment Calculation for one Effect Evaporator System
  • 8. 8 From those calculations that are presented above, the table of total equipment cost of process is show in below Name Unit of Size Value a b n Material Cost in 2010 Cost in 2016 Boiler Steam (liters/s) 9437.41 124000 10 1 Carbon Steel $ 218,374.07 $ 262,048.88 Condenser Area (m2) 64.01 1900 2500 1 Carbon Steel $ 161,929.16 $ 194,314.99 Effect 1 Area (m2) 40.29 330 36000 0.55 Carbon Steel $ 275,225.40 $ 330,270.48 Feed Pump Flow (liter/s) 2.12 8000 240 0.9 Carbon Steel $ 8,471.31 $ 10,165.57 Pump 1 Flow (liter/s) 3.19 800 240 0.9 Carbon Steel $ 8,681.82 $ 10,418.18 Total Equipment Cost $ 807,218.10 Table 1: Total Equipment Cost for one Effect Evaporator System The total equipment cost for the process system with one evaporator equals $807,218. C. Project Economics 1) Annual Depreciation Annual depreciation is calculated by straight-line depreciation with the salvage value of all equipment is estimated to be 15% of the equipment cost with the expected life of the equipment is 10 years. Total Equipment Cost $ 807,218.10 Salvage Value $ 121,082.72 Depreciable Asset Cost $ 686,135.39 Depreciation Rate/Year 10% Annual Depreciation $ 68,613.54 Table 2: Annual Depreciation for one Effect Evaporator System Annual depreciation for one effect evaporator system is $68,613.54 2) Variables Cost of Production To calculate variables cost of production, the number of water comes from cooling water of condenser and steam for the boiler, electricity is used for the feed pump of sea water, and natural gas is used for the boiler to heat water the run the system. Utilities Consumption/day Cost $/unit Cost $/day Cost $/year Water (gal) 3,953,301.72 0.005 19,766.51 5,929,952.58 Electricity (kWh) 731,531.69 0.046 33,650.46 10,095,137.39
  • 9. 9 Natural – gas (MM BTU) 714.69 2.178 1,556.60 466,981.00 Total variable cost $/year 16,492,070.97 Table 3: Variables Cost of Production for one Effect Evaporator System From the table above, the main costs that effect to the variables cost of production are cost of cooling water for the condenser and cost of electricity for the sea water feed pump. However, based on mass balance, to produce 400,000 lb/day of fresh water, the flowrate of sea water is 414,508 lb/day, which is 2.12 liters/s, and this value is constant, so the electricity cost is constant; therefore, the main utilities that effects to the changing variables cost of production is volume flowrate of cooling water. 3) Annual Labor, Maintenance, and Fixed Charges The calculation for annual labor, maintenance, and fixed charged are shown in table below with the maintenance charged are 5% of the initial total equipment cost, and fixed charges excluding depreciation are 15% of the installed cost of the evaporators Number of operators/shift 2 Operator salary $/hr 15 Number of engineers 1 Engineer Salary/season 25000 Over head 100% labor cost Total labor cost $/year $ 632,000.00 Maintenance (5% Total equipment cost/year) $ 40,360.91 Fixed Charge ( 15%installed evaporator cost) $ 49,540.57 Table 4: Annual Labor, Maintenance, and Fixed Charges 4) Variables cost per gallon fresh water production From all the costs that are calculated above, with 400,000 lb/day or 14.3 MM gal/day of fresh water produce, the variables cost per gallon fresh water production is shown in table below $/year $/gal of Water Utilities $ 16,492,070.97 $ 1.15 Depreciation $ 74,892.38 $ 0.01 Labor $ 632,000.00 $ 0.04 Maintenance $ 40,360.91 $ 0.00
  • 10. 10 Fixed Charge $ 49,540.57 $ 0.00 Total $ 17,288,864.83 $ 1.20 Table 5: Variables cost per gallon fresh water production From the table above, the cost of utilities is the highest cost that need to spend for the process. 5) Cash Flow and NPV Analysis A cash flow analysis is done based on Annual Depreciation, Variables Cost of Production, Annual Labor, Maintenance, and Fixed Charges for this project with the total is equal $17MM each year. Net Present Value (NPV) method is applied to assess the economic value of the project. A common Internal Rate of Return (IRR) of 8.5% is used for calculation. Tax is incorporated and equals 28% of the net income. Desalinated water is sold for $1/gal. 400,000 lb/year or 14.3 MM gal/year of fresh water is produced. It means the revenue of this project equals $14.3MM. The NPV of this plant is calculated in 10 years. Year Cost Revenue Tax Cash Flow NPV Total NPV to year 0 $ 807,218.10 $ (807,218.10) $ (807,218.10) $ (807,218.10) 1 $ 17,288,864.83 $ 14,392,090.56 $ (811,096.79) $ (2,085,677.47) $ (1,772,825.85) $ (2,580,043.95) 2 $ 17,288,864.83 $ 14,392,090.56 $ (811,096.79) $ (2,085,677.47) $ (1,506,901.97) $ (4,086,945.93) 3 $ 17,288,864.83 $ 14,392,090.56 $ (811,096.79) $ (2,085,677.47) $ (1,280,866.68) $ (5,367,812.60) 4 $ 17,288,864.83 $ 14,392,090.56 $ (811,096.79) $ (2,085,677.47) $ (1,088,736.68) $ (6,456,549.28) 5 $ 17,288,864.83 $ 14,392,090.56 $ (811,096.79) $ (2,085,677.47) $ (925,426.17) $ (7,381,975.46) 6 $ 17,288,864.83 $ 14,392,090.56 $ (811,096.79) $ (2,085,677.47) $ (786,612.25) $ (8,168,587.70) 7 $ 17,288,864.83 $ 14,392,090.56 $ (811,096.79) $ (2,085,677.47) $ (668,620.41) $ (8,837,208.11) 8 $ 17,288,864.83 $ 14,392,090.56 $ (811,096.79) $ (2,085,677.47) $ (568,327.35) $ (9,405,535.46) 9 $ 17,288,864.83 $ 14,392,090.56 $ (811,096.79) $ (2,085,677.47) $ (483,078.25) $ (9,888,613.71) 10 $ 17,288,864.83 $ 14,392,090.56 $ (811,096.79) $ (2,085,677.47) $ (410,616.51) $ (10,299,230.22) Table 6: Cash Flow and NPV Analysis Table above shown that the project is not profit if one desalinated water will sell for $1/gal for one effect evaporator system. PROCESS WITH THREE EFFECTS EVAPORATOR SYSTEM A. Mass and Energy Balance
  • 11. 11 With pressure of the boiler P = 40 bar, pressure of the 1st effect P = 30 bar, pressure of the 2nd effect P = 20 bar, pressure of the 3rd effect P = 10 bar, and pressure of the condenser P = 1 bar, the base is given for mass flowrate of fresh water is 400,000 lb/day and is produced from sea water that contains 3.5 wt% salt, from the steam tables combine with mass and energy balance equations, the mass of steam and brine coming out of each effect, mass of cooling water coming in to the condenser, mass of steam needed to heat up in the boiler, the heat duty of natural gas that is required to heat up the steam in the boiler, the heat duty of condenser and its area need to design to cool the hot stream are calculated.
  • 12. 12 Figure 7: Mass and Energy Balance Calculation for three Effects Evaporator System
  • 13. 13 Based on the values are calculated, the summary for mass and energy balance for the system is shown in these figures below Figure 8: Mass Balance of the Process with three Effects Evaporator System
  • 14. 14 Figure 9: Energy Balance of the Boiler and three Effects Evaporator System Figure 10: Mass and Energy Balance of Condenser for three Effects Evaporator System From those values of mass flowrate and heat duty that are calculated above, the unit such as power of the pumps or area of evaporators are find out to estimate for equipment cost of the project. B. Major Equipment List and Purchased Cost
  • 15. 15 Figure 11: Cost Equipment Calculation for three Effects Evaporator System From those calculations that are presented above, the table of total equipment cost of process is show in below Name Unit of Size Value a b n Material Cost in 2010 Cost in 2016 Boiler Steam (liters/s) 4093.07 124000 10 1 Carbon Steel $ 164,930.69 $ 197,916.82 Condenser Area (m2) 20.90 1900 2500 1 Carbon Steel $ 54,154.69 $ 64,985.63 Effect 1 Area (m2) 17.47 330 36000 0.55 Carbon Steel $ 173,960.28 $ 208,752.33 Effect 2 Area (m2) 16.13 330 36000 0.55 Carbon Steel $ 166,457.58 $ 199,749.09 Effect 3 Area (m2) 12.00 330 36000 0.55 Carbon Steel $ 141,521.21 $ 169,825.46 Feed Pump Flow (liter/s) 2.12 8000 240 0.9 Carbon Steel $ 8,471.31 $ 10,165.57 Pump 1 Flow (liter/s) 1.38 800 240 0.9 Carbon Steel $ 8,321.47 $ 9,985.77 Pump 2 Flow (liter/s) 1.00 800 240 0.9 Carbon Steel $ 8,239.58 $ 9,887.50 Pump 3 Flow (liter/s) 0.74 800 240 0.9 Carbon Steel $ 8,182.22 $ 9,818.67 Total Equipment Cost $ 881,086.84 Table 7: Total Equipment Cost for three Effects Evaporator System The total equipment cost for the process system with three effects evaporator system equals $881,086.84 C. Project Economics 1) Annual Depreciation Annual depreciation is calculated by straight-line depreciation with the salvage value of all equipment is estimated to be 15% of the equipment cost with the expected life of the equipment is 10 years. Total Equipment Cost $ 881,086.84 Salvage Value $ 132,163.03
  • 16. 16 Depreciable Asset Cost $ 748,923.82 Depreciation Rate/Year 10% Annual Depreciation $ 74,892.38 Table 8: Annual Depreciation for three Effects Evaporator System Annual depreciation for three effect evaporator system is $74,892.38 2) Variables Cost of Production To calculate variables cost of production, the number of water comes from cooling water of condenser and steam for the boiler, electricity is used for the feed pump of sea water, and natural gas is used for the boiler to heat water the run the system. Utilities Consumption/day Cost $/unit Cost $/day Cost $/year Cooling water (gal) 1,063,043.26 0.005 5,315.22 1,594,564.88 Electricity (kWh) 731,531.69 0.046 33,650.46 10,095,137.39 Natural - gas (MM BTU) 309.97 2.178 675.11 202,532.89 Total variable cost $/year $ 11,892,235.16 Table 9: Variables Cost of Production for three Effects Evaporator System From the table above, the main costs that effect to the variables cost of production are cost of cooling water for the condenser and cost of electricity for the sea water feed pump. However, based on mass balance, to produce 400,000 lb/day of fresh water, the flowrate of sea water is 414,508 lb/day, which is 2.12 liters/s, and this value is constant, so the electricity cost is constant; therefore, the main utilities that effects to the changing variables cost of production is volume flowrate of cooling water. 3) Annual Labor, Maintenance, and Fixed Charges The calculation for annual labor, maintenance, and fixed charged are shown in table below with the maintenance charged are 5% of the initial total equipment cost, and fixed charges excluding depreciation are 15% of the installed cost of the evaporators Number of operators/shift 4 Operator salary $/hr 15 Number of engineers 2
  • 17. 17 Engineer Salary/season 25000 Plant Manager 1 Manager salary/season 37000 Over head 100% labor cost Total labor cost $/year $ 1,560,000.00 Maintenance (5% Total equipment cost/year) $ 44,054.34 Fixed Charge ( 15% installed evaporator cost) $ 86,749.03 Table 10: Annual Labor, Maintenance, and Fixed Charges 4) Variables cost per gallon fresh water production From all the costs that are calculated above, with 400,000 lb/day or 14.3 MM gal/day of fresh water produce, the variables cost per gallon fresh water production is shown in table below $/year $/gal of Water Utilities $ 11,892,235.16 $ 0.83 Depreciation $ 74,892.38 $ 0.01 Labor $ 1,560,000.00 $ 0.11 Maintenance $ 44,054.34 $ 0.00 Fixed Charge $ 86,749.03 $ 0.01 Total $ 13,657,930.92 $ 0.95 Table 11: Variables cost per gallon fresh water production From the table above, the cost of utilities is the highest cost that need to spend for the process. 5) Cash Flow and NPV Analysis A cash flow analysis is done based on Annual Depreciation, Variables Cost of Production, Annual Labor, Maintenance, and Fixed Charges for this project with the total is equal $17MM each year. Net Present Value (NPV) method is applied to assess the economic value of the project. A common Internal Rate of Return (IRR) of 8.5% is used for calculation. Tax is incorporated and equals 28% of the net income. Desalinated water is sold for $1/gal. 400,000 lb/year or 14.3MM gal/year of fresh water is produced. It means the revenue of this project equals $14.3 MM. The NPV of this plant is calculated in 10 years. Year Cost Revenue Tax Cash Flow NPV Total NPV to year 0 $ 881,086.84 $ (881,086.84) $ (881,086.84) $ (881,086.84)
  • 18. 18 1 $ 13,657,930.92 $ 14,392,090.56 $ 205,564.70 $ 528,594.94 $ 449,305.70 $ (431,781.14) 2 $ 13,657,930.92 $ 14,392,090.56 $ 205,564.70 $ 528,594.94 $ 381,909.85 $ (49,871.30) 3 $ 13,657,930.92 $ 14,392,090.56 $ 205,564.70 $ 528,594.94 $ 324,623.37 $ 274,752.07 4 $ 13,657,930.92 $ 14,392,090.56 $ 205,564.70 $ 528,594.94 $ 275,929.86 $ 550,681.93 5 $ 13,657,930.92 $ 14,392,090.56 $ 205,564.70 $ 528,594.94 $ 234,540.38 $ 785,222.32 6 $ 13,657,930.92 $ 14,392,090.56 $ 205,564.70 $ 528,594.94 $ 199,359.33 $ 984,581.64 7 $ 13,657,930.92 $ 14,392,090.56 $ 205,564.70 $ 528,594.94 $ 169,455.43 $ 1,154,037.07 8 $ 13,657,930.92 $ 14,392,090.56 $ 205,564.70 $ 528,594.94 $ 144,037.11 $ 1,298,074.18 9 $ 13,657,930.92 $ 14,392,090.56 $ 205,564.70 $ 528,594.94 $ 122,431.55 $ 1,420,505.73 10 $ 13,657,930.92 $ 14,392,090.56 $ 205,564.70 $ 528,594.94 $ 104,066.81 $ 1,524,572.55 Table 12: Cash Flow and NPV Analysis The NPV of this plant after 10 years is $1.5MM. The payback period is 2 years; the profit being earned on the third year. With the NPV equal $1.5MM, which is 1.7 of the capital investment, this project is worth implementing. PROCESS WITH FOUR EFFECTS EVAPORATOR SYSTEM A. Mass and Energy Balance With pressure of the boiler P = 40 bar, pressure of the 1st effect P = 30 bar, pressure of the 2nd effect P = 20 bar, pressure of the 3rd effect P = 10 bar, pressure of the 4th effect P = 4 bar, and pressure of the condenser P = 1 bar, the base is given for mass flowrate of fresh water is 400,000 lb/day and is produced from sea water that contains 3.5 wt% salt, from the steam tables combine with mass and energy balance equations, the mass of steam and brine coming out of each effect, mass of cooling water coming in to the condenser, mass of steam needed to heat up in the boiler, the heat duty of natural gas that is required to heat up the steam in the boiler, the heat duty of condenser and its area need to design to cool the hot stream are calculated.
  • 19. 19
  • 20. 20 Figure 12: Mass and Energy Balance Calculation for four Effects Evaporator System Based on the values are calculated, the summary for mass and energy balance for the system is shown in these figures below Figure 13: Mass Balance of the Process with four Effects Evaporator System
  • 21. 21 Figure 14: Energy Balance of the Boiler and four Effects Evaporator System Figure 15: Mass and Energy Balance of Condenser for four Effects Evaporator System
  • 22. 22 From those values of mass flowrate and heat duty that are calculated above, the unit such as power of the pumps or area of evaporators are find out to estimate for equipment cost of the project. B. Major Equipment List and Purchased Cost Figure 16: Cost Equipment Calculation for four Effects Evaporator System From those calculations that are presented above, the table of total equipment cost of process is show in below Name Unit of Size Value a b n Material Cost in 2010 Cost in 2016 Boiler Steam (liters/s) 3552.11 124000 10 1 Carbon Steel $ 159,521.07 $ 191,425.29 Condenser Area (m2) 19.36 1900 2500 1 Carbon Steel $ 50,293.17 $ 60,351.81 Effect 1 Area (m2) 15.17 330 36000 0.55 Carbon Steel $ 160,937.50 $ 193,125.00
  • 23. 23 Effect 2 Area (m2) 14.29 330 36000 0.55 Carbon Steel $ 155,794.81 $ 186,953.77 Effect 3 Area (m2) 11.05 330 36000 0.55 Carbon Steel $ 135,244.07 $ 162,292.88 Effect 4 Area (m2) 9.93 330 36000 0.55 Carbon Steel $ 127,565.84 $ 153,079.01 Feed Pump Flow (liter/s) 2.12 8000 240 0.9 Carbon Steel $ 8,471.31 $ 10,165.57 Pump 1 Flow (liter/s) 1.20 800 240 0.9 Carbon Steel $ 8,282.97 $ 9,939.56 Pump 2 Flow (liter/s) 0.79 800 240 0.9 Carbon Steel $ 8,194.46 $ 9,833.35 Pump 3 Flow (liter/s) 0.53 800 240 0.9 Carbon Steel $ 8,135.62 $ 9,762.74 Pump 4 Flow (liter/s) 0.50 800 240 0.9 Carbon Steel $ 8,128.77 $ 9,754.52 Total Equipment Cost $ 996,683.49 Table 13: Total Equipment Cost for four Effects Evaporator System The total equipment cost for the process system with four effects evaporator system equals $996,683.49 C. Project Economics 1) Annual Depreciation Annual depreciation is calculated by straight-line depreciation with the salvage value of all equipment is estimated to be 15% of the equipment cost with the expected life of the equipment is 10 years. Table 14: Annual Depreciation for four Effects Evaporator System Annual depreciation for four effect evaporator system is $84,719.28 2) Variables Cost of Production To calculate variables cost of production, the number of water comes from cooling water of condenser and steam for the boiler, electricity is used for the feed pump of sea water, and natural gas is used for the boiler to heat water the run the system. Utilities Consumption/day Cost $/unit Cost $/day Cost $/year Cooling water (gal) 821,680.70 0.005 4,108.40 1,232,521.05 Total Equipment Cost $ 996,697.45 Salvage Value $ 149,504.62 Depreciable Asset Cost $ 847,192.84 Depreciation Rate/Year 10% Annual Depreciation $ 84,719.28
  • 24. 24 Electricity (kWh) 731,531.69 0.046 33,891.90 10,167,570.51 Natural – gas (MM BTU) 269.04 2.178 585.97 175,790.74 Total variables cost $/year 11,575,882.30 Table 15: Variables Cost of Production for four Effects Evaporator System From the table above, the main costs that effect to the variables cost of production are cost of cooling water for the condenser and cost of electricity for the sea water feed pump. However, based on mass balance, to produce 400,000 lb/day of fresh water, the flowrate of sea water is 414,508 lb/day, which is 2.12 liters/s, and this value is constant, so the electricity cost is constant; therefore, the main utilities that effects to the changing variables cost of production is volume flowrate of cooling water. 3) Annual Labor, Maintenance, and Fixed Charges The calculation for annual labor, maintenance, and fixed charged are shown in table below with the maintenance charged are 5% of the initial total equipment cost, and fixed charges excluding depreciation are 15% of the installed cost of the evaporators Number of operators/shift 5 Operator salary $/hr 15 Number of engineers 2 Engineer Salary/season 25000 Plant Manager 1 Manager salary/season 37000 Over head 100% labor cost Total labor cost $/year $ 1,560,000.00 Maintenance (5% Total equipment cost/year) $ 44,054.34 Fixed Charge ( 15% installed evaporator cost) $ 86,749.03 Table 16: Annual Labor, Maintenance, and Fixed Charges 4) Variables cost per gallon fresh water production From all the costs that are calculated above, with 400,000 lb/day or 14.3 MM gal/day of fresh water produce, the variables cost per gallon fresh water production is shown in table below
  • 25. 25 $/year $/gal of Water Utilities $ 11,892,235.16 $ 0.83 Depreciation $ 74,892.38 $ 0.01 Labor $ 1,560,000.00 $ 0.11 Maintenance $ 44,054.34 $ 0.00 Fixed Charge $ 86,749.03 $ 0.01 Total $ 13,657,930.92 $ 0.95 Table 17: Variables cost per gallon fresh water production From the table above, the cost of utilities is the highest cost that need to spend for the process. 5) Cash Flow and NPV Analysis A cash flow analysis is done based on Annual Depreciation, Variables Cost of Production, Annual Labor, Maintenance, and Fixed Charges for this project with the total is equal $17MM each year. Net Present Value (NPV) method is applied to assess the economic value of the project. A common Internal Rate of Return (IRR) of 8.5% is used for calculation. Tax is incorporated and equals 28% of the net income. Desalinated water is sold for $1/gal. 400,000 lb/year or 14.3MM gal/year of fresh water is produced. It means the revenue of this project equals $14.3 MM. The NPV of this plant is calculated in 10 years. Year Cost Revenue Tax Cash Flow NPV Total NPVto year 0 $ 996,683.49 $ (996,683.49) $ (996,683.49) $ (996,683.49) 1 $ 13,590,755.37 $ 14,392,090.56 $ 224,373.85 $ 576,961.34 $ 490,417.14 $ (506,266.36) 2 $ 13,590,755.37 $ 14,392,090.56 $ 224,373.85 $ 576,961.34 $ 416,854.57 $ (89,411.79) 3 $ 13,590,755.37 $ 14,392,090.56 $ 224,373.85 $ 576,961.34 $ 354,326.38 $ 264,914.59 4 $ 13,590,755.37 $ 14,392,090.56 $ 224,373.85 $ 576,961.34 $ 301,177.42 $ 566,092.01 5 $ 13,590,755.37 $ 14,392,090.56 $ 224,373.85 $ 576,961.34 $ 256,000.81 $ 822,092.82 6 $ 13,590,755.37 $ 14,392,090.56 $ 224,373.85 $ 576,961.34 $ 217,600.69 $ 1,039,693.51 7 $ 13,590,755.37 $ 14,392,090.56 $ 224,373.85 $ 576,961.34 $ 184,960.59 $ 1,224,654.10 8 $ 13,590,755.37 $ 14,392,090.56 $ 224,373.85 $ 576,961.34 $ 157,216.50 $ 1,381,870.60 9 $ 13,590,755.37 $ 14,392,090.56 $ 224,373.85 $ 576,961.34 $ 133,634.02 $ 1,515,504.62 10 $ 13,590,755.37 $ 14,392,090.56 $ 224,373.85 $ 576,961.34 $ 113,588.92 $ 1,629,093.54 Table 18: Cash Flow and NPV Analysis
  • 26. 26 The NPV of this plant after 10 years is $1.63MM. The payback period is 2 years; the profit being earned on the third year. With the NPV equal $1.63MM, which is 1.63 of the capital investment, this project is worth implementing. PROCESS WITH SIX EFFECTS EVAPORATOR SYSTEM A. Mass and Energy Balance With pressure of the boiler P = 40 bar, pressure of the 1st effect P = 30 bar, pressure of the 2nd effect P = 25 bar, pressure of the 3rd effect P = 20 bar, pressure of the 4th effect P = 15 bar, pressure of the 5th effect P = 10 bar, pressure of the 6th effect P = 4 bar, and pressure of the condenser P = 1 bar, the base is given for mass flowrate of fresh water is 400,000 lb/day and is produced from sea water that contains 3.5 wt% salt, from the steam tables combine with mass and energy balance equations, the mass of steam and brine coming out of each effect, mass of cooling water coming in to the condenser, mass of steam needed to heat up in the boiler, the heat duty of natural gas that is required to heat up the steam in the boiler, the heat duty of condenser and its area need to design to cool the hot stream are calculated.
  • 27. 27
  • 28. 28 Figure 17: Mass and Energy Balance Calculation for six Effects Evaporator System From those values of mass flowrate and heat duty that are calculated above, the unit such as power of the pumps or area of evaporators are find out to estimate for equipment cost of the project. B. Major Equipment List and Purchased Cost
  • 29. 29 Figure 18: Cost Equipment Calculation for six Effects Evaporator System From those calculations that are presented above, the table of total equipment cost of process is show in below Name Unit of Size Value a b n Material Cost in 2010 Cost in 2016 Boiler Steam(liters/s) 2969.32 124000 10 1 Carbon Steel $ 153,693.15 $ 184,431.78 Condenser Area (m2) 7.09 1900 2500 1 Carbon Steel $ 19,630.07 $ 23,556.09 Effect 1 Area (m2) 12.63 330 36000 0.55 Carbon Steel $ 145,565.34 $ 174,678.41 Effect 2 Area (m2) 12.73 330 36000 0.55 Carbon Steel $ 146,190.10 $ 175,428.12 Effect 3 Area (m2) 10.48 330 36000 0.55 Carbon Steel $ 131,398.89 $ 157,678.67 Effect 4 Area (m2) 7.37 330 36000 0.55 Carbon Steel $ 108,323.70 $ 129,988.44
  • 30. 30 Effect 5 Area (m2) 6.8143 330 36000 0.55 Carbon Steel $ 103,769.04 $ 124,522.85 Effect 6 Area (m2) 4.3441 330 36000 0.55 Carbon Steel $ 81,081.04 $ 97,297.25 Feed Pump Flow (liter/s) 2.12 8000 240 0.9 Carbon Steel $ 8,471.31 $ 10,165.57 Pump 1 Flow (liter/s) 1.00 800 240 0.9 Carbon Steel $ 8,240.82 $ 9,888.98 Pump 2 Flow (liter/s) 52.75 800 240 0.9 Carbon Steel $ 16,515.52 $ 19,818.62 Pump 3 Flow (liter/s) 48.92 800 240 0.9 Carbon Steel $ 15,957.56 $ 19,149.08 Pump 4 Flow (liter/s) 48.26 800 240 0.9 Carbon Steel $ 15,859.62 $ 19,031.54 Pump 5 Flow (liter/s) 47.32 800 240 0.9 Carbon Steel $ 8,522.38 $ 10,226.86 Pump 6 Flow (liter/s) 85.88 800 240 0.9 Carbon Steel $ 14,004.62 $ 16,805.54 Total Equipment Cost $ 1,172,667.79 Table 19: Total Equipment Cost for six Effects Evaporator System The total equipment cost for the process system with six effects evaporator system equals $1.172MM C. Project Economics 1) Annual Depreciation Annual depreciation is calculated by straight-line depreciation with the salvage value of all equipment is estimated to be 15% of the equipment cost with the expected life of the equipment is 10 years. Table 20: Annual Depreciation for six Effects Evaporator System Annual depreciation for six effect evaporator system is $99,676.76 2) Variables Cost of Production To calculate variables cost of production, the number of water comes from cooling water of condenser and steam for the boiler, electricity is used for the feed pump of sea water, and natural gas is used for the boiler to heat water the run the system. Utilities Consumption/day Cost $/unit Cost $/day Cost $/year Total Equipment Cost $ 1,172,667.79 Salvage Value $ 175,900.17 Depreciable Asset Cost $ 996,767.62 Depreciation Rate/Year 10% Annual Depreciation $ 99,676.76
  • 31. 31 Cooling water (gal) 312,683.35 0.005 1,563.42 469,025.03 Electricity (kWh) 731,531.69 0.046 33,650.46 10,095,137.39 Natural - gas (MM BTU) 225.43 2.178 491.00 147,299.22 Total variable cost $/year 10,711,461.64 Table 21: Variables Cost of Production for six Effects Evaporator System From the table above, the main costs that effect to the variables cost of production are cost of cooling water for the condenser and cost of electricity for the sea water feed pump. However, based on mass balance, to produce 400,000 lb/day of fresh water, the flowrate of sea water is 414,508 lb/day, which is 2.12 liters/s, and this value is constant, so the electricity cost is constant; therefore, the main utilities that effects to the changing variables cost of production is volume flowrate of cooling water. 3) Annual Labor, Maintenance, and Fixed Charges The calculation for annual labor, maintenance, and fixed charged are shown in table below with the maintenance charged are 5% of the initial total equipment cost, and fixed charges excluding depreciation are 15% of the installed cost of the evaporators Number of operators/shift 7 Operator salary $/hr 15 Number of engineers 2 Engineer Salary/season 25000 Plant Manager 1 Manager salary/season 37000 Over head 100% labor cost Total labor cost $/year $ 2,208,000.00 Maintenance (5% Total equipment cost/year) $ 58,633.39 Fixed Charge ( 15% installed evaporator cost) $ 128,939.06 Table 22: Annual Labor, Maintenance, and Fixed Charges 4) Variables cost per gallon fresh water production From all the costs that are calculated above, with 400,000 lb/day or 14.3 MM gal/day of fresh water produce, the variables cost per gallon fresh water production is shown in table below
  • 32. 32 $/year $/gal of Water Utilities $ 10,711,461.64 $ 0.74 Depreciation $ 99,676.76 $ 0.01 Labor $ 2,208,000.00 $ 0.15 Maintenance $ 58,633.39 $ 0.00 Fixed Charge $ 128,939.06 $ 0.01 Total $ 13,206,710.85 $ 0.92 Table 23: Variables cost per gallon fresh water production From the table above, the cost of utilities is the highest cost that need to spend for the process. 5) Cash Flow and NPV Analysis A cash flow analysis is done based on Annual Depreciation, Variables Cost of Production, Annual Labor, Maintenance, and Fixed Charges for this project with the total is equal $17MM each year. Net Present Value (NPV) method is applied to assess the economic value of the project. A common Internal Rate of Return (IRR) of 8.5% is used for calculation. Tax is incorporated and equals 28% of the net income. Desalinated water is sold for $1/gal. 400,000 lb/year or 14.3MM gal/year of fresh water is produced. It means the revenue of this project equals $14.3 MM. The NPV of this plant is calculated in 10 years. Year Cost Revenue Tax Cash Flow NPV Total NPVto year 0 $ 1,172,667.79 $ (1,172,667.79) $ (1,172,667.79) $ (1,172,667.79) 1 $ 13,206,710.85 $ 14,392,090.56 $ 331,906.32 $ 853,473.39 $ 725,452.38 $ (447,215.40) 2 $ 13,206,710.85 $ 14,392,090.56 $ 331,906.32 $ 853,473.39 $ 616,634.53 $ 169,419.12 3 $ 13,206,710.85 $ 14,392,090.56 $ 331,906.32 $ 853,473.39 $ 524,139.35 $ 693,558.47 4 $ 13,206,710.85 $ 14,392,090.56 $ 331,906.32 $ 853,473.39 $ 445,518.45 $ 1,139,076.92 5 $ 13,206,710.85 $ 14,392,090.56 $ 331,906.32 $ 853,473.39 $ 378,690.68 $ 1,517,767.60 6 $ 13,206,710.85 $ 14,392,090.56 $ 331,906.32 $ 853,473.39 $ 321,887.08 $ 1,839,654.67 7 $ 13,206,710.85 $ 14,392,090.56 $ 331,906.32 $ 853,473.39 $ 273,604.02 $ 2,113,258.69 8 $ 13,206,710.85 $ 14,392,090.56 $ 331,906.32 $ 853,473.39 $ 232,563.41 $ 2,345,822.10 9 $ 13,206,710.85 $ 14,392,090.56 $ 331,906.32 $ 853,473.39 $ 197,678.90 $ 2,543,501.00 10 $ 13,206,710.85 $ 14,392,090.56 $ 331,906.32 $ 853,473.39 $ 168,027.07 $ 2,711,528.07 Table 24: Cash Flow and NPV Analysis
  • 33. 33 The NPV of this plant after 10 years is $2.7MM. The payback period is 1 years; the profit being earned on the 2nd year. With the NPV equal $2.7MM, which is 1.6 of the capital investment, this project is worth implementing. OPTIONS: From all the analysis economics parts that show in table 6, 12, 18, and 24, the more number of effects evaporator, the higher NPV for this plant. The relation between number of effects evaporator and NPV is shown in the table and graph below. Table 25: Number of Effect to total NPV to 10th year Figure 19: Number of Effect to Total NPV to 10th year From the table and the graph above, 6 effects evaporator system should be used to design the plant because it gives the highest NPV value. Also, the main cost that need to spend that effect $(12,000,000.00) $(10,000,000.00) $(8,000,000.00) $(6,000,000.00) $(4,000,000.00) $(2,000,000.00) $- $2,000,000.00 $4,000,000.00 0 1 2 3 4 5 6 7 TotalNPVto10years Number of Effect # of Effecct Vs Total NPV Number of Effect total NPV to 10th year 1 $ (10,299,230.22) 3 $ 1,524,572.55 4 $ 1,629,093.54 6 $ 2,711,528.07
  • 34. 34 the most changing to the NPV value is the cost of volume flowrate of cooling water for the condenser. It is show in table and graph below. Cooling Water Flowrate (MM gal/day) NPV to 10th year ($) 3.95 $ (10,299,230.22) 1.06 $ 1,524,572.55 0.82 $ 1,629,093.54 0.31 $ 2,711,528.07 Table 26: Cooling Water Flowrate to Total NPV to 10th year Figure 20: Cooling Water Flowrate (MM gal/day) to Total NPV to 10th year The more effects evaporator, the less steam need to cool, so the less cooling water need to use in condenser; therefore, the higher total NPV. In conclude, system should be design with 6 effects evaporator. SAFETY CONCERN A. Overall Process The chemicals involved in this process are sea water, and desalinated water. They are not harmful so all the preventions for this plant are wearing protective gloves, safety goggles, and be careful with the place that have hot steam. 1 effect 3 effects 4 effects 6 effects $(12,000,000.00) $(10,000,000.00) $(8,000,000.00) $(6,000,000.00) $(4,000,000.00) $(2,000,000.00) $- $2,000,000.00 $4,000,000.00 - 0.50 1.00 1.50 2.00 2.50 3.00 3.50 4.00 4.50 Cooling Water Vs Total NPV
  • 35. 35 B. Hazard and Operability study (HAZOP) HAZOP Table and figure below is used for Steam at Boiler and Cooling Water in Condenser Incident Effects Recommendations Likelihood Severity Detection Overall Risk STEAM OF BOILER 1 Reverse Flow No steam in each effect Check valves to prevent back flow and place a flow meter 1 10 3 30 2 No Flow No steam in each effect Place a flow meter 1 7 3 30 3 More Flow Too much steam in each effect Place a flow meter and pressure transmitter 3 7 3 63 4 Less Flow Less steam in each effect, so less fresh water produce Place a flow meter and pressure transmitter 3 5 3 27 5 High Temperature Combust or over pressure Place a Temperature Transmitter 5 3 5 75 6 Low Temperature Less steam in each effect, so less fresh water produce Place a Temperature Transmitter 3 3 3 27 7 High Pressure Rupture steam tube Place a pressure transmitter 3 5 3 45 8 Low Pressure Rupture steam tube Place a pressure transmitter 1 5 5 25 COOLING WATER OF CONDENSER 9 Reverse Flow Too hot of fresh water out of condenser Check valves to prevent back flow and place a flow meter 1 7 3 21 10 No Flow No fresh water condense Place a flow meter 1 5 3 15 11 More Flow Over pressure and cause rupture Place a flow meter 3 5 5 75 12 Less Flow Temperature of Fresh water would increase Place a flow meter 3 5 3 45 13 High Temperature Temperature of Fresh water would increase Place a Temperature Transmitter 5 3 3 45 14 Low Temperature Temperature of Fresh water would decrease Place a Temperature Transmitter 3 3 1 9 15 High Pressure Rupture cooling water tube Place a Pressure Transmitter 3 5 3 45 16 Low Pressure Rupture cooling water tube Place a Pressure Transmitter 1 5 3 15 Table 27: HAZOP for Steam at Boiler and Cooling Water in Condenser
  • 36. 36 Figure 22: Boston square for Boiler and Condenser HAZOP CONCLUSION and RECOMMENDATION: This report is about a general plant design 400,000 lb/day of fresh water from sea water with 3.5 wt% salt. From all economics analysis, the system will have 1 boiler, 6 effects evaporator, 6 pumps and 1 condenser. The project requires $1.2 MM capital investment and annual $14.4 MM cost for production. After 1 years, the investment starts to earn profit. At the end of year 10th, NPV is about $2.7 MM. And the flowrate of cooling water is the most effective to changing NPV value with the more effects evaporator, the less steam need to cool, so the less cooling water need to use in condenser; therefore, the higher total NPV. And the recommendation for this process is add the pressure transmitter, flowrate transmitter, and temperature transmitter in each effect to guarantee the plant work well as its expectation. 1 2, 9 3 4, 7 11, 12 15 6, 14 8, 10, 16 0 2 4 6 8 10 12 0 2 4 6 8 10 12 Severity Likelihood Boston squarefor Boiler and Condenser HAZOP 5, 13
  • 37. 37