2. 6:00PM Introduction & Timeline
6:05PM Project Overview
Construction Logistics
Improvements for
Marshall Elementary School
6:30PM Questions & Discussion
7:15PM Adjorn!
TODAY’S AGENDA
3. CITY AGENCIES AND SFUSD MEETINGS
COMMUNITY GROUP MEETINGS
Preliminary Project
Assessment (PPA)
Filed
October 2013
Environmental
Evaluation (EE)
Filed
January 2014
Conditional Use (CU)
Application
CU Review
Spring – Fall 2014
Construction
Anticipated
Early 2015 – Fall 2016
NEIGHBORHOOD MEETINGS
TIMELINE
EE CONSTRUCTIONPPA CU
TODAY
4. CONCERNS FROM THE MARSHALL SCHOOL COMMUNITY
CONSTRUCTION LOGISTICS
SHADOWS
PICK UP & DROP OFF
NEED FOR ADDITIONAL SPACE
11. 16TH STREET
Five story
building (55’)
Ten story
buildings
(105’)
CAPPSTREET
MISSIONSTREET
BUILDINGS COMPLY WITH ZONING
345 total new
apartments
42 new affordable
homes
13. CONSTRUCTION LOGISTICS
CAPPSTREET
MISSIONSTREET
16TH STREET
ADAIR STREET
Construction
office
BART
Movable
fence
15TH STREET
Hours
• Weekdays 7am-4pm
• Some weekends 8am-4pm
Demolition
• Permits
• Containment
• Removal of hazardous
materials
• Third party air monitoring
• Demolition
• Dust control
Barricade
w/ overhead
Temporary
Barricade
14. CONSTRUCTION LOGISTICS
16TH STREET
CAPPSTREET
MISSIONSTREET
ADAIR STREET
Flagger
BART
Movable
fence
15TH STREET
Flagger
Covered
walkway
Barricade
w/ overhead
Barricade
Hours
• Weekdays 7am-4pm
• Some weekends 8am-4pm
Demolition
• Permits
• Containment
• Removal of hazardous
materials
• Third party air monitoring
• Demolition
• Dust control
Safety
15. CONSTRUCTION LOGISTICS
16TH STREET
CAPPSTREET
MISSIONSTREET
ADAIR STREET
BART
15TH STREET
Loading
zone
Access
Hours
• Weekdays 7am-4pm
• Some weekends 8am-4pm
Demolition
• Permits
• Containment
• Removal of hazardous
materials
• Third party air monitoring
• Demolition
• Dust control
Safety
Loading
16. CONSTRUCTION LOGISTICS
16TH STREET
CAPPSTREET
MISSIONSTREET
ADAIR STREET
BART
15TH STREET
Water misters
Wash down
Hours
• Weekdays 7am-4pm
• Some weekends 8am-4pm
Demolition
• Permits
• Containment
• Removal of hazardous
materials
• Third party air monitoring
• Demolition
• Dust control
Safety
Loading
Dust / Noise
17. SITE PLAN - EXISTING
42’9’ 9’
SCHOOL
COURTYARD
SCHOOL
GARDEN
37. SUN ANGLE BY MONTH - 12:00
JUNE
JULY
MARSHALL SCHOOL PLAYGROUND
MARSHALL SCHOOL BUILDING
1979 MISSION
38. SHADOW COMPARISON – Sept 21 - 2:00 pm
PROPOSED - Original
PROPOSED with
PLAYGROUND
EXISTING
39. SHADOW COMPARISON – Oct 21 - 2:00 pm
PROPOSED - Original
PROPOSED with
PLAYGROUND
EXISTING
40. SHADOW COMPARISON – Nov 21 - 2:00 pm
PROPOSED - Original
PROPOSED with
PLAYGROUND
EXISTING
41. SHADOW COMPARISON – Dec 21 - 2:00 pm
PROPOSED - Original
PROPOSED with
PLAYGROUND
EXISTING
42. SHADOW COMPARISON – Jan 21 - 2:00 pm
PROPOSED - Original
PROPOSED with
PLAYGROUND
EXISTING
43. SHADOW COMPARISON – Feb 21 - 2:00 pm
PROPOSED - Original
PROPOSED with
PLAYGROUND
EXISTING
44. SHADOW COMPARISON – Mar 21 - 2:00 pm
PROPOSED - Original
PROPOSED with
PLAYGROUND
EXISTING
45. SHADOW COMPARISON – Apr 21 - 2:00 pm
PROPOSED - Original
PROPOSED with
PLAYGROUND
EXISTING
46. SHADOW COMPARISON – May 21 - 2:00 pm
PROPOSED - Original
PROPOSED with
PLAYGROUND
EXISTING
47. SHADOW COMPARISON – June 21 - 2:00 pm
PROPOSED - Original
PROPOSED with
PLAYGROUND
EXISTING
48. SHADOW COMPARISON – Jul 21 - 2:00 pm
PROPOSED - Original
PROPOSED with
PLAYGROUND
EXISTING
49. SHADOW COMPARISON – Aug 21 - 2:00 pm
PROPOSED - Original
PROPOSED with
PLAYGROUND
EXISTING
50.
51. LEVEL 2 - PROPOSED
SCHOOL
GARDEN
SCHOOL
COURTYARD
52. LEVEL 1 - PROPOSED
POTENTIAL USES
Library
Classroom
Community Room
Early Childhood
Development/Daycare
After School Programs
SCHOOL
GARDEN
SCHOOL
COURTYARD