Project Proposal
Result Analysis Tool (RAT)
Date: 26-Feb-2015
Project Proposal
Result Analysis Tool (RAT)
Course: SE-505 (Software Project Lab II)
Submitted by
BSSE0509 - Minhas Kamal
BSSE0522 - Saif Uddin Mahmud
BSSE0530 - Mostaque Ahmed
Submitted to
Sheikh Muhammad Sarwar
Lecturer
Institute of Information Technology
University of Dhaka
Submission Date
26th February, 2015
Table of Contents
1. Overview 1
1.1 Background 1
1.2 Objectives 1
1.3 Scope 2
1.4 Dependencies and Risks 2
2. Project Delivery 2
2.1 Deliverables 2
2.2 Time Scales
2.3 Project Resources
3
3
3. Summary 4
References 4
Project: Result Analysis Tool (RAT)
1
1. Overview
In this document we will put light upon the basic idea of our Software Project
Lab-II. We will specify the problem & the solution that our software will
provide. We will also specify the radius of the project, obstacles, dependencies,
risks, time scale & deliverables.
1.1 Background
These days, almost all the governmental & non-governmental institutions hold
MCQ exams. They deliver the OMR sheets to third-parties for evaluation. This
third party is often a company who uses OMR scanners which requires high
end technical abilities. They are also very expensive. Our research shows- the
mediocre institutions, mainly schools and colleges, often evaluate their OMR
sheets with the help of students which is highly error prone.
We wish to alleviate this problem by developing an advanced result processing
and analysis tool, which takes images produced by OMR scanner as input. And
then it will output final result & report as well.
1.2 Objectives
Result Processing Tool (RAT) is a software system which will improve the
traditional system of MCQ result processing method. The user have to use a
roll feed scanner with the software which will get the images to process. The
software will process the images and produce the reports & results. Our
software will-
i. Scan OMR sheets & receive image.
ii. Produce data by processing image.
iii. Discover and correct errors.
iv. Generate result.
v. Produce & deliver complete result and final report.
By completing this project, we wish to achieve skills regarding team work &
real life industrial software production.
Project: Result Analysis Tool (RAT)
2
1.3 Scope
Our software will be mainly used by the institutional authorities. The interface
will be very easy and it will require no additional technical knowledge. It will
require a roll feed scanner with the software. There will be necessary
authentication in the future. This software will run on every platform. It will
not produce any graphical representation of the statistics.
1.4 Dependencies and Risks
The outcome of this project is dependent on Java Runtime Environment. The
main technical risk of this project is to ensure ease of use of the user interface.
We will try to make the Graphical User Interface more appealing and more
gorgeous. We will also make it easier to understand for the non-technical
person.
The main development risk of this project is the time factor. The quality of
application is largely dependent on the testing time. To ensure this, the time
scale will be planned very conservatively. The main challenge in testing is using
a large amount of data sample to emulate a real time situation.
2. Project Delivery
Here, we will discuss about the project materials and the milestones. We will
follow a definite timescale, work breakdown structure (WBS) and deliverable.
2.1 Deliverables
The following deliverables will be delivered after the completion of the project-
i. Software installation file
ii. Project documentation (Soft copy)
iii. User manual
iv. Complete video tutorial
Project: Result Analysis Tool (RAT)
3
2.2 Time Scales
The time frame for implementing the project is given below. From here, we
can see that, we will study our project prior to coding. As we develop different
modules, we will start testing the finished ones, and make necessary changes.
Finally, we will integrate all the modules. We shall mostly follow Agile Model in
this process.
10
days
10
days
10
days
10
days
10
days
10
days
20
days
20
days
20
days
Project
proposal
Study
Coding
Testing
Integration
2.3 Project Resources
The resources required to finish the project is given in the table below. This
software requires very little hardware compared to the systems used today.
We will also need a scanner for complete testing.
Hardware Requirements
Processor Dual Core or Higher
RAM
Hard Disc Space
200 MB or Higher
50 MB or Higher
Software Requirement
This software is platform independent.
JRE will be required.
Project: Result Analysis Tool (RAT)
4
3. Summary
Here, we have tried our best to describe the project in details. We have
discussed the parameters regarding this project. Time & money are valuable
assets. They both will be saved using RAT. This will also improve the efficiency
of the educational institutions. We will cover every aspect so that our software
meets the modern industrial requirements.
References
I. http://www.ece.rutgers.edu/~marsic/Teaching/SE/proposal.html
II. http://www.proposaltemplatespro.com/software-project-proposal/
III. http://www.flatbed-scanner-
review.org/wide_format_sheet_fed_scanners/wide_format_scanner_g
gat.html
IV. www.gravic.com/remark/Office-OMR-Scanning-Software/
V. http://onnorokomsoftware.com/Products

Mais conteúdo relacionado

Mais procurados

Learn the SECRETS to passing your PRINCE2 Foundation exam with flying colours!
Learn the SECRETS to passing your PRINCE2 Foundation exam with flying colours! Learn the SECRETS to passing your PRINCE2 Foundation exam with flying colours!
Learn the SECRETS to passing your PRINCE2 Foundation exam with flying colours! Knowledge Train
 
Basics of project management - Week 1
Basics of project management - Week 1Basics of project management - Week 1
Basics of project management - Week 1Thuan Ng
 
organizational breakdown structure (OBS)
organizational breakdown structure (OBS)organizational breakdown structure (OBS)
organizational breakdown structure (OBS)Nikhil Raj
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
Software Project Management: Project Initiation
Software Project Management: Project InitiationSoftware Project Management: Project Initiation
Software Project Management: Project InitiationMinhas Kamal
 
C. Burcham - Project Closure Report
C. Burcham - Project Closure ReportC. Burcham - Project Closure Report
C. Burcham - Project Closure ReportCheryl Burcham
 
Project Management - An Introduction
Project Management - An IntroductionProject Management - An Introduction
Project Management - An IntroductionSundar Raghavan
 
Application Assessment Techniques
Application Assessment TechniquesApplication Assessment Techniques
Application Assessment TechniquesDenim Group
 
WBS presentation
WBS presentationWBS presentation
WBS presentationjpstewar
 
The 7 minute accessibility assessment and app rating system
The 7 minute accessibility assessment and app rating systemThe 7 minute accessibility assessment and app rating system
The 7 minute accessibility assessment and app rating systemAidan Tierney
 
What is a Work Breakdown Structure?
What is a Work Breakdown Structure?What is a Work Breakdown Structure?
What is a Work Breakdown Structure?Kenny Hirschmann
 
Nonprofit Accounting and Form 990 Overview
Nonprofit Accounting and Form 990 OverviewNonprofit Accounting and Form 990 Overview
Nonprofit Accounting and Form 990 OverviewSerenity Accounting
 
Software Project Management
Software Project ManagementSoftware Project Management
Software Project Managementasim78
 
PgMP Course Training Material Slides PowerPoint Presentation
PgMP Course Training Material Slides PowerPoint PresentationPgMP Course Training Material Slides PowerPoint Presentation
PgMP Course Training Material Slides PowerPoint PresentationOsama Zarzour
 
Case study successfully planning and executing a p6 eppm implementation roa...
Case study   successfully planning and executing a p6 eppm implementation roa...Case study   successfully planning and executing a p6 eppm implementation roa...
Case study successfully planning and executing a p6 eppm implementation roa...p6academy
 
Top Ten Reasons Why Projects Fail
Top Ten Reasons Why Projects FailTop Ten Reasons Why Projects Fail
Top Ten Reasons Why Projects Failjpstewar
 
Agile Software Development Overview
Agile Software Development OverviewAgile Software Development Overview
Agile Software Development OverviewDUONG Trong Tan
 

Mais procurados (20)

Presentation on Project Risk Management
Presentation on Project Risk ManagementPresentation on Project Risk Management
Presentation on Project Risk Management
 
Learn the SECRETS to passing your PRINCE2 Foundation exam with flying colours!
Learn the SECRETS to passing your PRINCE2 Foundation exam with flying colours! Learn the SECRETS to passing your PRINCE2 Foundation exam with flying colours!
Learn the SECRETS to passing your PRINCE2 Foundation exam with flying colours!
 
Agile Methodology - Agile Project Management Training
Agile Methodology - Agile Project Management TrainingAgile Methodology - Agile Project Management Training
Agile Methodology - Agile Project Management Training
 
Basics of project management - Week 1
Basics of project management - Week 1Basics of project management - Week 1
Basics of project management - Week 1
 
organizational breakdown structure (OBS)
organizational breakdown structure (OBS)organizational breakdown structure (OBS)
organizational breakdown structure (OBS)
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
Software Project Management: Project Initiation
Software Project Management: Project InitiationSoftware Project Management: Project Initiation
Software Project Management: Project Initiation
 
C. Burcham - Project Closure Report
C. Burcham - Project Closure ReportC. Burcham - Project Closure Report
C. Burcham - Project Closure Report
 
Project Management - An Introduction
Project Management - An IntroductionProject Management - An Introduction
Project Management - An Introduction
 
Application Assessment Techniques
Application Assessment TechniquesApplication Assessment Techniques
Application Assessment Techniques
 
WBS presentation
WBS presentationWBS presentation
WBS presentation
 
The 7 minute accessibility assessment and app rating system
The 7 minute accessibility assessment and app rating systemThe 7 minute accessibility assessment and app rating system
The 7 minute accessibility assessment and app rating system
 
What is a Work Breakdown Structure?
What is a Work Breakdown Structure?What is a Work Breakdown Structure?
What is a Work Breakdown Structure?
 
Nonprofit Accounting and Form 990 Overview
Nonprofit Accounting and Form 990 OverviewNonprofit Accounting and Form 990 Overview
Nonprofit Accounting and Form 990 Overview
 
Software Project Management
Software Project ManagementSoftware Project Management
Software Project Management
 
My experience on the PgMP Application (1/3)
My experience on the PgMP Application (1/3)My experience on the PgMP Application (1/3)
My experience on the PgMP Application (1/3)
 
PgMP Course Training Material Slides PowerPoint Presentation
PgMP Course Training Material Slides PowerPoint PresentationPgMP Course Training Material Slides PowerPoint Presentation
PgMP Course Training Material Slides PowerPoint Presentation
 
Case study successfully planning and executing a p6 eppm implementation roa...
Case study   successfully planning and executing a p6 eppm implementation roa...Case study   successfully planning and executing a p6 eppm implementation roa...
Case study successfully planning and executing a p6 eppm implementation roa...
 
Top Ten Reasons Why Projects Fail
Top Ten Reasons Why Projects FailTop Ten Reasons Why Projects Fail
Top Ten Reasons Why Projects Fail
 
Agile Software Development Overview
Agile Software Development OverviewAgile Software Development Overview
Agile Software Development Overview
 

Semelhante a Software Project Proposal- Result Analysis Tool

“Scrumbear” framework for solving traditional scrum model problems
“Scrumbear” framework for solving traditional scrum model problems“Scrumbear” framework for solving traditional scrum model problems
“Scrumbear” framework for solving traditional scrum model problemsjournalBEEI
 
construction management system final year report
construction management system final year reportconstruction management system final year report
construction management system final year reportchiragbarasiya
 
IRJET- Research Study on Testing Mantle in SDLC
IRJET- Research Study on Testing Mantle in SDLCIRJET- Research Study on Testing Mantle in SDLC
IRJET- Research Study on Testing Mantle in SDLCIRJET Journal
 
ContentsTeam Work Schedule3Team Task Assignment3Project .docx
ContentsTeam Work Schedule3Team Task Assignment3Project .docxContentsTeam Work Schedule3Team Task Assignment3Project .docx
ContentsTeam Work Schedule3Team Task Assignment3Project .docxbobbywlane695641
 
Pm 430 develop a quality management/tutorialoutlet
Pm 430 develop a quality management/tutorialoutletPm 430 develop a quality management/tutorialoutlet
Pm 430 develop a quality management/tutorialoutletPlunkettz
 
Project Proposal Service Center Management software
Project Proposal  Service Center Management softwareProject Proposal  Service Center Management software
Project Proposal Service Center Management softwareAdam Waheed
 
Project charter and plan document for millennium upgrade
Project charter and plan document for millennium upgradeProject charter and plan document for millennium upgrade
Project charter and plan document for millennium upgradeTheodore Van Patten, Jr.
 
MACHINE LEARNING AUTOMATIONS PIPELINE WITH CI/CD
MACHINE LEARNING AUTOMATIONS PIPELINE WITH CI/CDMACHINE LEARNING AUTOMATIONS PIPELINE WITH CI/CD
MACHINE LEARNING AUTOMATIONS PIPELINE WITH CI/CDIRJET Journal
 
SOFTWARE BUILD AUTOMATION TOOLS A COMPARATIVE STUDY BETWEEN MAVEN, GRADLE, BA...
SOFTWARE BUILD AUTOMATION TOOLS A COMPARATIVE STUDY BETWEEN MAVEN, GRADLE, BA...SOFTWARE BUILD AUTOMATION TOOLS A COMPARATIVE STUDY BETWEEN MAVEN, GRADLE, BA...
SOFTWARE BUILD AUTOMATION TOOLS A COMPARATIVE STUDY BETWEEN MAVEN, GRADLE, BA...ijseajournal
 
Spm project planning
Spm project planning Spm project planning
Spm project planning Kanchana Devi
 
Online News Portal System
Online News Portal SystemOnline News Portal System
Online News Portal SystemRajib Roy
 
Software Requirement Specification (SRS) on Result Analysis Tool
Software Requirement Specification (SRS) on Result Analysis ToolSoftware Requirement Specification (SRS) on Result Analysis Tool
Software Requirement Specification (SRS) on Result Analysis ToolMinhas Kamal
 
Software engineering study materials
Software engineering study materialsSoftware engineering study materials
Software engineering study materialssmruti sarangi
 
Testing material (1).docx
Testing material (1).docxTesting material (1).docx
Testing material (1).docxKVamshiKrishna5
 
Software Engineering Overview
Software Engineering OverviewSoftware Engineering Overview
Software Engineering OverviewPrachi Sasankar
 

Semelhante a Software Project Proposal- Result Analysis Tool (20)

“Scrumbear” framework for solving traditional scrum model problems
“Scrumbear” framework for solving traditional scrum model problems“Scrumbear” framework for solving traditional scrum model problems
“Scrumbear” framework for solving traditional scrum model problems
 
construction management system final year report
construction management system final year reportconstruction management system final year report
construction management system final year report
 
IRJET- Research Study on Testing Mantle in SDLC
IRJET- Research Study on Testing Mantle in SDLCIRJET- Research Study on Testing Mantle in SDLC
IRJET- Research Study on Testing Mantle in SDLC
 
ContentsTeam Work Schedule3Team Task Assignment3Project .docx
ContentsTeam Work Schedule3Team Task Assignment3Project .docxContentsTeam Work Schedule3Team Task Assignment3Project .docx
ContentsTeam Work Schedule3Team Task Assignment3Project .docx
 
project plan
project planproject plan
project plan
 
Pm 430 develop a quality management/tutorialoutlet
Pm 430 develop a quality management/tutorialoutletPm 430 develop a quality management/tutorialoutlet
Pm 430 develop a quality management/tutorialoutlet
 
Project Proposal Service Center Management software
Project Proposal  Service Center Management softwareProject Proposal  Service Center Management software
Project Proposal Service Center Management software
 
Project charter and plan document for millennium upgrade
Project charter and plan document for millennium upgradeProject charter and plan document for millennium upgrade
Project charter and plan document for millennium upgrade
 
MACHINE LEARNING AUTOMATIONS PIPELINE WITH CI/CD
MACHINE LEARNING AUTOMATIONS PIPELINE WITH CI/CDMACHINE LEARNING AUTOMATIONS PIPELINE WITH CI/CD
MACHINE LEARNING AUTOMATIONS PIPELINE WITH CI/CD
 
Sample report
Sample reportSample report
Sample report
 
PPT.pptx
PPT.pptxPPT.pptx
PPT.pptx
 
PPT.pptx
PPT.pptxPPT.pptx
PPT.pptx
 
SOFTWARE BUILD AUTOMATION TOOLS A COMPARATIVE STUDY BETWEEN MAVEN, GRADLE, BA...
SOFTWARE BUILD AUTOMATION TOOLS A COMPARATIVE STUDY BETWEEN MAVEN, GRADLE, BA...SOFTWARE BUILD AUTOMATION TOOLS A COMPARATIVE STUDY BETWEEN MAVEN, GRADLE, BA...
SOFTWARE BUILD AUTOMATION TOOLS A COMPARATIVE STUDY BETWEEN MAVEN, GRADLE, BA...
 
Spm unit1
Spm unit1Spm unit1
Spm unit1
 
Spm project planning
Spm project planning Spm project planning
Spm project planning
 
Online News Portal System
Online News Portal SystemOnline News Portal System
Online News Portal System
 
Software Requirement Specification (SRS) on Result Analysis Tool
Software Requirement Specification (SRS) on Result Analysis ToolSoftware Requirement Specification (SRS) on Result Analysis Tool
Software Requirement Specification (SRS) on Result Analysis Tool
 
Software engineering study materials
Software engineering study materialsSoftware engineering study materials
Software engineering study materials
 
Testing material (1).docx
Testing material (1).docxTesting material (1).docx
Testing material (1).docx
 
Software Engineering Overview
Software Engineering OverviewSoftware Engineering Overview
Software Engineering Overview
 

Mais de Minhas Kamal

Digital Image Processing
Digital Image ProcessingDigital Image Processing
Digital Image ProcessingMinhas Kamal
 
Deep Learning - Exploring The Magical World of Neural Network
Deep Learning - Exploring The Magical World of Neural NetworkDeep Learning - Exploring The Magical World of Neural Network
Deep Learning - Exploring The Magical World of Neural NetworkMinhas Kamal
 
Machine Learning - Entering into The Wonderful Galaxy of Machine Learning
Machine Learning - Entering into The Wonderful Galaxy of Machine LearningMachine Learning - Entering into The Wonderful Galaxy of Machine Learning
Machine Learning - Entering into The Wonderful Galaxy of Machine LearningMinhas Kamal
 
Artificial Intelligence - Staring at The Grand Universe of AI (1)
Artificial Intelligence - Staring at The Grand Universe of AI (1)Artificial Intelligence - Staring at The Grand Universe of AI (1)
Artificial Intelligence - Staring at The Grand Universe of AI (1)Minhas Kamal
 
Final Project Report- Bengali Braille to Text Translator
Final Project Report- Bengali Braille to Text TranslatorFinal Project Report- Bengali Braille to Text Translator
Final Project Report- Bengali Braille to Text TranslatorMinhas Kamal
 
Abstract- Bengali Braille to Text Translator
Abstract- Bengali Braille to Text TranslatorAbstract- Bengali Braille to Text Translator
Abstract- Bengali Braille to Text TranslatorMinhas Kamal
 
Software Project Management: Project Summary
Software Project Management: Project SummarySoftware Project Management: Project Summary
Software Project Management: Project SummaryMinhas Kamal
 
Software Project Management: Budget
Software Project Management: BudgetSoftware Project Management: Budget
Software Project Management: BudgetMinhas Kamal
 
Software Project Management: Testing Document
Software Project Management: Testing DocumentSoftware Project Management: Testing Document
Software Project Management: Testing DocumentMinhas Kamal
 
Software Project Management: Change Control
Software Project Management: Change ControlSoftware Project Management: Change Control
Software Project Management: Change ControlMinhas Kamal
 
Software Project Management: Release Notes
Software Project Management: Release NotesSoftware Project Management: Release Notes
Software Project Management: Release NotesMinhas Kamal
 
Software Project Management: Configuration Management
Software Project Management: Configuration ManagementSoftware Project Management: Configuration Management
Software Project Management: Configuration ManagementMinhas Kamal
 
Software Project Management: Risk Management
Software Project Management: Risk ManagementSoftware Project Management: Risk Management
Software Project Management: Risk ManagementMinhas Kamal
 
Software Project Management: Software Architecture
Software Project Management: Software ArchitectureSoftware Project Management: Software Architecture
Software Project Management: Software ArchitectureMinhas Kamal
 
Software Project Management: Software Requirement Specification
Software Project Management: Software Requirement SpecificationSoftware Project Management: Software Requirement Specification
Software Project Management: Software Requirement SpecificationMinhas Kamal
 
Software Project Management: Project Planning
Software Project Management: Project PlanningSoftware Project Management: Project Planning
Software Project Management: Project PlanningMinhas Kamal
 
Software Project Management: Business Case
Software Project Management: Business CaseSoftware Project Management: Business Case
Software Project Management: Business CaseMinhas Kamal
 
Software Project Management: Project Charter
Software Project Management: Project CharterSoftware Project Management: Project Charter
Software Project Management: Project CharterMinhas Kamal
 
Software Project Management Presentation Final
Software Project Management Presentation FinalSoftware Project Management Presentation Final
Software Project Management Presentation FinalMinhas Kamal
 
Software Requirements Specification on Bengali Braille to Text Translator
Software Requirements Specification on Bengali Braille to Text TranslatorSoftware Requirements Specification on Bengali Braille to Text Translator
Software Requirements Specification on Bengali Braille to Text TranslatorMinhas Kamal
 

Mais de Minhas Kamal (20)

Digital Image Processing
Digital Image ProcessingDigital Image Processing
Digital Image Processing
 
Deep Learning - Exploring The Magical World of Neural Network
Deep Learning - Exploring The Magical World of Neural NetworkDeep Learning - Exploring The Magical World of Neural Network
Deep Learning - Exploring The Magical World of Neural Network
 
Machine Learning - Entering into The Wonderful Galaxy of Machine Learning
Machine Learning - Entering into The Wonderful Galaxy of Machine LearningMachine Learning - Entering into The Wonderful Galaxy of Machine Learning
Machine Learning - Entering into The Wonderful Galaxy of Machine Learning
 
Artificial Intelligence - Staring at The Grand Universe of AI (1)
Artificial Intelligence - Staring at The Grand Universe of AI (1)Artificial Intelligence - Staring at The Grand Universe of AI (1)
Artificial Intelligence - Staring at The Grand Universe of AI (1)
 
Final Project Report- Bengali Braille to Text Translator
Final Project Report- Bengali Braille to Text TranslatorFinal Project Report- Bengali Braille to Text Translator
Final Project Report- Bengali Braille to Text Translator
 
Abstract- Bengali Braille to Text Translator
Abstract- Bengali Braille to Text TranslatorAbstract- Bengali Braille to Text Translator
Abstract- Bengali Braille to Text Translator
 
Software Project Management: Project Summary
Software Project Management: Project SummarySoftware Project Management: Project Summary
Software Project Management: Project Summary
 
Software Project Management: Budget
Software Project Management: BudgetSoftware Project Management: Budget
Software Project Management: Budget
 
Software Project Management: Testing Document
Software Project Management: Testing DocumentSoftware Project Management: Testing Document
Software Project Management: Testing Document
 
Software Project Management: Change Control
Software Project Management: Change ControlSoftware Project Management: Change Control
Software Project Management: Change Control
 
Software Project Management: Release Notes
Software Project Management: Release NotesSoftware Project Management: Release Notes
Software Project Management: Release Notes
 
Software Project Management: Configuration Management
Software Project Management: Configuration ManagementSoftware Project Management: Configuration Management
Software Project Management: Configuration Management
 
Software Project Management: Risk Management
Software Project Management: Risk ManagementSoftware Project Management: Risk Management
Software Project Management: Risk Management
 
Software Project Management: Software Architecture
Software Project Management: Software ArchitectureSoftware Project Management: Software Architecture
Software Project Management: Software Architecture
 
Software Project Management: Software Requirement Specification
Software Project Management: Software Requirement SpecificationSoftware Project Management: Software Requirement Specification
Software Project Management: Software Requirement Specification
 
Software Project Management: Project Planning
Software Project Management: Project PlanningSoftware Project Management: Project Planning
Software Project Management: Project Planning
 
Software Project Management: Business Case
Software Project Management: Business CaseSoftware Project Management: Business Case
Software Project Management: Business Case
 
Software Project Management: Project Charter
Software Project Management: Project CharterSoftware Project Management: Project Charter
Software Project Management: Project Charter
 
Software Project Management Presentation Final
Software Project Management Presentation FinalSoftware Project Management Presentation Final
Software Project Management Presentation Final
 
Software Requirements Specification on Bengali Braille to Text Translator
Software Requirements Specification on Bengali Braille to Text TranslatorSoftware Requirements Specification on Bengali Braille to Text Translator
Software Requirements Specification on Bengali Braille to Text Translator
 

Último

Xen Safety Embedded OSS Summit April 2024 v4.pdf
Xen Safety Embedded OSS Summit April 2024 v4.pdfXen Safety Embedded OSS Summit April 2024 v4.pdf
Xen Safety Embedded OSS Summit April 2024 v4.pdfStefano Stabellini
 
PREDICTING RIVER WATER QUALITY ppt presentation
PREDICTING  RIVER  WATER QUALITY  ppt presentationPREDICTING  RIVER  WATER QUALITY  ppt presentation
PREDICTING RIVER WATER QUALITY ppt presentationvaddepallysandeep122
 
Implementing Zero Trust strategy with Azure
Implementing Zero Trust strategy with AzureImplementing Zero Trust strategy with Azure
Implementing Zero Trust strategy with AzureDinusha Kumarasiri
 
Unveiling the Future: Sylius 2.0 New Features
Unveiling the Future: Sylius 2.0 New FeaturesUnveiling the Future: Sylius 2.0 New Features
Unveiling the Future: Sylius 2.0 New FeaturesŁukasz Chruściel
 
Alfresco TTL#157 - Troubleshooting Made Easy: Deciphering Alfresco mTLS Confi...
Alfresco TTL#157 - Troubleshooting Made Easy: Deciphering Alfresco mTLS Confi...Alfresco TTL#157 - Troubleshooting Made Easy: Deciphering Alfresco mTLS Confi...
Alfresco TTL#157 - Troubleshooting Made Easy: Deciphering Alfresco mTLS Confi...Angel Borroy López
 
Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024
Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024
Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024StefanoLambiase
 
Global Identity Enrolment and Verification Pro Solution - Cizo Technology Ser...
Global Identity Enrolment and Verification Pro Solution - Cizo Technology Ser...Global Identity Enrolment and Verification Pro Solution - Cizo Technology Ser...
Global Identity Enrolment and Verification Pro Solution - Cizo Technology Ser...Cizo Technology Services
 
BATTLEFIELD ORM: TIPS, TACTICS AND STRATEGIES FOR CONQUERING YOUR DATABASE
BATTLEFIELD ORM: TIPS, TACTICS AND STRATEGIES FOR CONQUERING YOUR DATABASEBATTLEFIELD ORM: TIPS, TACTICS AND STRATEGIES FOR CONQUERING YOUR DATABASE
BATTLEFIELD ORM: TIPS, TACTICS AND STRATEGIES FOR CONQUERING YOUR DATABASEOrtus Solutions, Corp
 
Alluxio Monthly Webinar | Cloud-Native Model Training on Distributed Data
Alluxio Monthly Webinar | Cloud-Native Model Training on Distributed DataAlluxio Monthly Webinar | Cloud-Native Model Training on Distributed Data
Alluxio Monthly Webinar | Cloud-Native Model Training on Distributed DataAlluxio, Inc.
 
Maximizing Efficiency and Profitability with OnePlan’s Professional Service A...
Maximizing Efficiency and Profitability with OnePlan’s Professional Service A...Maximizing Efficiency and Profitability with OnePlan’s Professional Service A...
Maximizing Efficiency and Profitability with OnePlan’s Professional Service A...OnePlan Solutions
 
What is Fashion PLM and Why Do You Need It
What is Fashion PLM and Why Do You Need ItWhat is Fashion PLM and Why Do You Need It
What is Fashion PLM and Why Do You Need ItWave PLM
 
How to Track Employee Performance A Comprehensive Guide.pdf
How to Track Employee Performance A Comprehensive Guide.pdfHow to Track Employee Performance A Comprehensive Guide.pdf
How to Track Employee Performance A Comprehensive Guide.pdfLivetecs LLC
 
Software Project Health Check: Best Practices and Techniques for Your Product...
Software Project Health Check: Best Practices and Techniques for Your Product...Software Project Health Check: Best Practices and Techniques for Your Product...
Software Project Health Check: Best Practices and Techniques for Your Product...Velvetech LLC
 
Intelligent Home Wi-Fi Solutions | ThinkPalm
Intelligent Home Wi-Fi Solutions | ThinkPalmIntelligent Home Wi-Fi Solutions | ThinkPalm
Intelligent Home Wi-Fi Solutions | ThinkPalmSujith Sukumaran
 
What are the key points to focus on before starting to learn ETL Development....
What are the key points to focus on before starting to learn ETL Development....What are the key points to focus on before starting to learn ETL Development....
What are the key points to focus on before starting to learn ETL Development....kzayra69
 
GOING AOT WITH GRAALVM – DEVOXX GREECE.pdf
GOING AOT WITH GRAALVM – DEVOXX GREECE.pdfGOING AOT WITH GRAALVM – DEVOXX GREECE.pdf
GOING AOT WITH GRAALVM – DEVOXX GREECE.pdfAlina Yurenko
 
Cloud Data Center Network Construction - IEEE
Cloud Data Center Network Construction - IEEECloud Data Center Network Construction - IEEE
Cloud Data Center Network Construction - IEEEVICTOR MAESTRE RAMIREZ
 
A healthy diet for your Java application Devoxx France.pdf
A healthy diet for your Java application Devoxx France.pdfA healthy diet for your Java application Devoxx France.pdf
A healthy diet for your Java application Devoxx France.pdfMarharyta Nedzelska
 
Open Source Summit NA 2024: Open Source Cloud Costs - OpenCost's Impact on En...
Open Source Summit NA 2024: Open Source Cloud Costs - OpenCost's Impact on En...Open Source Summit NA 2024: Open Source Cloud Costs - OpenCost's Impact on En...
Open Source Summit NA 2024: Open Source Cloud Costs - OpenCost's Impact on En...Matt Ray
 

Último (20)

Xen Safety Embedded OSS Summit April 2024 v4.pdf
Xen Safety Embedded OSS Summit April 2024 v4.pdfXen Safety Embedded OSS Summit April 2024 v4.pdf
Xen Safety Embedded OSS Summit April 2024 v4.pdf
 
PREDICTING RIVER WATER QUALITY ppt presentation
PREDICTING  RIVER  WATER QUALITY  ppt presentationPREDICTING  RIVER  WATER QUALITY  ppt presentation
PREDICTING RIVER WATER QUALITY ppt presentation
 
Implementing Zero Trust strategy with Azure
Implementing Zero Trust strategy with AzureImplementing Zero Trust strategy with Azure
Implementing Zero Trust strategy with Azure
 
Unveiling the Future: Sylius 2.0 New Features
Unveiling the Future: Sylius 2.0 New FeaturesUnveiling the Future: Sylius 2.0 New Features
Unveiling the Future: Sylius 2.0 New Features
 
Alfresco TTL#157 - Troubleshooting Made Easy: Deciphering Alfresco mTLS Confi...
Alfresco TTL#157 - Troubleshooting Made Easy: Deciphering Alfresco mTLS Confi...Alfresco TTL#157 - Troubleshooting Made Easy: Deciphering Alfresco mTLS Confi...
Alfresco TTL#157 - Troubleshooting Made Easy: Deciphering Alfresco mTLS Confi...
 
Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024
Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024
Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024
 
Global Identity Enrolment and Verification Pro Solution - Cizo Technology Ser...
Global Identity Enrolment and Verification Pro Solution - Cizo Technology Ser...Global Identity Enrolment and Verification Pro Solution - Cizo Technology Ser...
Global Identity Enrolment and Verification Pro Solution - Cizo Technology Ser...
 
BATTLEFIELD ORM: TIPS, TACTICS AND STRATEGIES FOR CONQUERING YOUR DATABASE
BATTLEFIELD ORM: TIPS, TACTICS AND STRATEGIES FOR CONQUERING YOUR DATABASEBATTLEFIELD ORM: TIPS, TACTICS AND STRATEGIES FOR CONQUERING YOUR DATABASE
BATTLEFIELD ORM: TIPS, TACTICS AND STRATEGIES FOR CONQUERING YOUR DATABASE
 
Alluxio Monthly Webinar | Cloud-Native Model Training on Distributed Data
Alluxio Monthly Webinar | Cloud-Native Model Training on Distributed DataAlluxio Monthly Webinar | Cloud-Native Model Training on Distributed Data
Alluxio Monthly Webinar | Cloud-Native Model Training on Distributed Data
 
Maximizing Efficiency and Profitability with OnePlan’s Professional Service A...
Maximizing Efficiency and Profitability with OnePlan’s Professional Service A...Maximizing Efficiency and Profitability with OnePlan’s Professional Service A...
Maximizing Efficiency and Profitability with OnePlan’s Professional Service A...
 
What is Fashion PLM and Why Do You Need It
What is Fashion PLM and Why Do You Need ItWhat is Fashion PLM and Why Do You Need It
What is Fashion PLM and Why Do You Need It
 
How to Track Employee Performance A Comprehensive Guide.pdf
How to Track Employee Performance A Comprehensive Guide.pdfHow to Track Employee Performance A Comprehensive Guide.pdf
How to Track Employee Performance A Comprehensive Guide.pdf
 
Software Project Health Check: Best Practices and Techniques for Your Product...
Software Project Health Check: Best Practices and Techniques for Your Product...Software Project Health Check: Best Practices and Techniques for Your Product...
Software Project Health Check: Best Practices and Techniques for Your Product...
 
Intelligent Home Wi-Fi Solutions | ThinkPalm
Intelligent Home Wi-Fi Solutions | ThinkPalmIntelligent Home Wi-Fi Solutions | ThinkPalm
Intelligent Home Wi-Fi Solutions | ThinkPalm
 
What are the key points to focus on before starting to learn ETL Development....
What are the key points to focus on before starting to learn ETL Development....What are the key points to focus on before starting to learn ETL Development....
What are the key points to focus on before starting to learn ETL Development....
 
GOING AOT WITH GRAALVM – DEVOXX GREECE.pdf
GOING AOT WITH GRAALVM – DEVOXX GREECE.pdfGOING AOT WITH GRAALVM – DEVOXX GREECE.pdf
GOING AOT WITH GRAALVM – DEVOXX GREECE.pdf
 
2.pdf Ejercicios de programación competitiva
2.pdf Ejercicios de programación competitiva2.pdf Ejercicios de programación competitiva
2.pdf Ejercicios de programación competitiva
 
Cloud Data Center Network Construction - IEEE
Cloud Data Center Network Construction - IEEECloud Data Center Network Construction - IEEE
Cloud Data Center Network Construction - IEEE
 
A healthy diet for your Java application Devoxx France.pdf
A healthy diet for your Java application Devoxx France.pdfA healthy diet for your Java application Devoxx France.pdf
A healthy diet for your Java application Devoxx France.pdf
 
Open Source Summit NA 2024: Open Source Cloud Costs - OpenCost's Impact on En...
Open Source Summit NA 2024: Open Source Cloud Costs - OpenCost's Impact on En...Open Source Summit NA 2024: Open Source Cloud Costs - OpenCost's Impact on En...
Open Source Summit NA 2024: Open Source Cloud Costs - OpenCost's Impact on En...
 

Software Project Proposal- Result Analysis Tool

  • 1. Project Proposal Result Analysis Tool (RAT) Date: 26-Feb-2015
  • 2. Project Proposal Result Analysis Tool (RAT) Course: SE-505 (Software Project Lab II) Submitted by BSSE0509 - Minhas Kamal BSSE0522 - Saif Uddin Mahmud BSSE0530 - Mostaque Ahmed Submitted to Sheikh Muhammad Sarwar Lecturer Institute of Information Technology University of Dhaka Submission Date 26th February, 2015
  • 3. Table of Contents 1. Overview 1 1.1 Background 1 1.2 Objectives 1 1.3 Scope 2 1.4 Dependencies and Risks 2 2. Project Delivery 2 2.1 Deliverables 2 2.2 Time Scales 2.3 Project Resources 3 3 3. Summary 4 References 4
  • 4. Project: Result Analysis Tool (RAT) 1 1. Overview In this document we will put light upon the basic idea of our Software Project Lab-II. We will specify the problem & the solution that our software will provide. We will also specify the radius of the project, obstacles, dependencies, risks, time scale & deliverables. 1.1 Background These days, almost all the governmental & non-governmental institutions hold MCQ exams. They deliver the OMR sheets to third-parties for evaluation. This third party is often a company who uses OMR scanners which requires high end technical abilities. They are also very expensive. Our research shows- the mediocre institutions, mainly schools and colleges, often evaluate their OMR sheets with the help of students which is highly error prone. We wish to alleviate this problem by developing an advanced result processing and analysis tool, which takes images produced by OMR scanner as input. And then it will output final result & report as well. 1.2 Objectives Result Processing Tool (RAT) is a software system which will improve the traditional system of MCQ result processing method. The user have to use a roll feed scanner with the software which will get the images to process. The software will process the images and produce the reports & results. Our software will- i. Scan OMR sheets & receive image. ii. Produce data by processing image. iii. Discover and correct errors. iv. Generate result. v. Produce & deliver complete result and final report. By completing this project, we wish to achieve skills regarding team work & real life industrial software production.
  • 5. Project: Result Analysis Tool (RAT) 2 1.3 Scope Our software will be mainly used by the institutional authorities. The interface will be very easy and it will require no additional technical knowledge. It will require a roll feed scanner with the software. There will be necessary authentication in the future. This software will run on every platform. It will not produce any graphical representation of the statistics. 1.4 Dependencies and Risks The outcome of this project is dependent on Java Runtime Environment. The main technical risk of this project is to ensure ease of use of the user interface. We will try to make the Graphical User Interface more appealing and more gorgeous. We will also make it easier to understand for the non-technical person. The main development risk of this project is the time factor. The quality of application is largely dependent on the testing time. To ensure this, the time scale will be planned very conservatively. The main challenge in testing is using a large amount of data sample to emulate a real time situation. 2. Project Delivery Here, we will discuss about the project materials and the milestones. We will follow a definite timescale, work breakdown structure (WBS) and deliverable. 2.1 Deliverables The following deliverables will be delivered after the completion of the project- i. Software installation file ii. Project documentation (Soft copy) iii. User manual iv. Complete video tutorial
  • 6. Project: Result Analysis Tool (RAT) 3 2.2 Time Scales The time frame for implementing the project is given below. From here, we can see that, we will study our project prior to coding. As we develop different modules, we will start testing the finished ones, and make necessary changes. Finally, we will integrate all the modules. We shall mostly follow Agile Model in this process. 10 days 10 days 10 days 10 days 10 days 10 days 20 days 20 days 20 days Project proposal Study Coding Testing Integration 2.3 Project Resources The resources required to finish the project is given in the table below. This software requires very little hardware compared to the systems used today. We will also need a scanner for complete testing. Hardware Requirements Processor Dual Core or Higher RAM Hard Disc Space 200 MB or Higher 50 MB or Higher Software Requirement This software is platform independent. JRE will be required.
  • 7. Project: Result Analysis Tool (RAT) 4 3. Summary Here, we have tried our best to describe the project in details. We have discussed the parameters regarding this project. Time & money are valuable assets. They both will be saved using RAT. This will also improve the efficiency of the educational institutions. We will cover every aspect so that our software meets the modern industrial requirements. References I. http://www.ece.rutgers.edu/~marsic/Teaching/SE/proposal.html II. http://www.proposaltemplatespro.com/software-project-proposal/ III. http://www.flatbed-scanner- review.org/wide_format_sheet_fed_scanners/wide_format_scanner_g gat.html IV. www.gravic.com/remark/Office-OMR-Scanning-Software/ V. http://onnorokomsoftware.com/Products