Company Background
3
 World’s largest manufacture of storage devices
 Largest producer of server and PC hard drives in 1996
 Revenue of $4.4 billion
 Purchased Digital Equipment Corp. (DEC) storage business
in October 1994
 Competitors – Seagate, IBM, and Western Digital
 Outsource production of hard drives
Current Situation
 Legacy systems
 Material requirement planning (MRP) system maintained
separate databases and transactions had to be manually
consolidated
 Delays in obtaining updated information
 Acquisition of DEC caused implementation issues
4
ERP Project – Started April 1994
 Worldwide Ask Replacement System - WARP
 Three project teams
 Steering committee – VP’s of Finance, IS, Logistics,
Manufacturing, Purchasing, Sales, and Rep. from PW
 Core team – 16 managers from department and business
units
 Project team (100 Members) – Members from IS and
business unit key employees
 Teams analyzed and improved business process
 Selected Oracle, HP, and Price Waterhouse to assist with
ERP implementation
 Oracle 7 Database, Oracle Financial, and Manufacturing
Modules
 Expected implementation in Summer of 1995
5
Problems with the ERP Implementation
 Acquisition of DEC slowed implementation process of ERP
System
 Project was more complex with the acquisition of DEC
 Duplicate systems, processes, and artifacts
 Project was put on hold – Project teams focused on the DEC
acquisition (October 1994)
 ERP was restarted in January of 1995
 Project team had to redo a large part of the original ERP
implementation in order to take into account the DEC
acquisition
6
Quantum’s Current Systems
 Nine different legacy systems that could not share
information
 Legacy system kept each division’s transactions in separate
functional and business unit databases
 Information was manually consolidated, since databases
could not share information
 Gathering faxes, emails, and written information took four
days
 Closing the books took seventeen days
 Inventory availability could not be confirmed and delivery
could take days or weeks
7
Quantum’s Requirements for ERP System
 Sales people to take and confirm an order in real time.
 Sales have to be able to confirm a delivery time and follow
up to ensure that order was delivered in real time
 Ability to access current inventory and to reserve that order
for the customer in real time
 ATP (Available To Promise) – ability to confirm and allocate
inventory
8
ERP Implementation
Phased implementation:
Like the name implies means
that modules are
implemented one at a time or
in a group of modules –often
at a single location before
moving on to more locations.
 The installation of phase one could be
the implementation of finance,
controlling, accounts receivable,
accounts payable, and purchasing
modules.
 Phase two could be to include
materials management, production
planning, and quality planning
modules.
 Following phases mean the
deployment and implementation of
remaining modules over a period of
time.
9
“Phased” and “big-bang” are the two primary approaches used to
implement ERP systems.
Big-Bang Implementation
 Big-Bang Implementation: “everything is
changed at once!” Once an ERP solution has been
chosen to meet organizational needs –the system
goes from a test version to being the actual
system used to capture transactions in only a
matter of days.
10
ERP Implementation:
Consideration Factors
 Organizational size and complexity. This includes
factors related to the type of product that organization sells
and the size and complexity of the customer
 The organizations hierarchy and controls. Flat
organizations with loose controls would have more difficulty
deploying a phased implementation because its difficult to
maintain commitment throughout the process. Organizations
that have extensive hierarchy and tighter controls have the
necessary mechanisms in place to sustain a phased
approach
 Extent of the implementation: based on the number
of modules and the degree to which the organization
changes those modules.
11
Phased Implementation
12
Big-Bang Implementation
13
Which do you Choose?
1. BIG BANG
Or
Phased-In
Implementation?
2. What factors made you
choose your
implementation choice and
why?
Additional Questions:
3. What are a few benefits
that could be gained from
the implementation of your
ERP choice? Be specific!
Add value when writing the
case study by looking up
information about the
Quantum online and
include any finding in
your answers
14
Questions?
15

Mais conteúdo relacionado

Mais procurados

Cisco System Inc. Implementing ERP
Cisco System Inc. Implementing ERPCisco System Inc. Implementing ERP
Cisco System Inc. Implementing ERP
Vinay Gk
 
Erp Failure In Hershey’s
Erp Failure In Hershey’sErp Failure In Hershey’s
Erp Failure In Hershey’s
Ankit Malhotra
 

Mais procurados (20)

Cisco System Inc. Implementing ERP
Cisco System Inc. Implementing ERPCisco System Inc. Implementing ERP
Cisco System Inc. Implementing ERP
 
Erp failure- Implementation Failure Hershey Foods Corporation
Erp failure- Implementation Failure Hershey Foods CorporationErp failure- Implementation Failure Hershey Foods Corporation
Erp failure- Implementation Failure Hershey Foods Corporation
 
Nestle ERP Failure
Nestle ERP FailureNestle ERP Failure
Nestle ERP Failure
 
Enterprise Resource Planning - ERP
Enterprise Resource Planning - ERPEnterprise Resource Planning - ERP
Enterprise Resource Planning - ERP
 
Rolls royce
Rolls royceRolls royce
Rolls royce
 
ERP implementation
ERP implementationERP implementation
ERP implementation
 
Erp ppt
Erp pptErp ppt
Erp ppt
 
ERP Project: Implementation Failure in HP
ERP Project: Implementation Failure in HPERP Project: Implementation Failure in HP
ERP Project: Implementation Failure in HP
 
Case study on erp failures
Case study on erp failuresCase study on erp failures
Case study on erp failures
 
Erp
ErpErp
Erp
 
Success and Failure Examples of ERP Implementation
Success and Failure Examples of ERP ImplementationSuccess and Failure Examples of ERP Implementation
Success and Failure Examples of ERP Implementation
 
Erp rEPORT ON TATA STEEL
Erp rEPORT ON TATA STEELErp rEPORT ON TATA STEEL
Erp rEPORT ON TATA STEEL
 
Erp presentation
Erp presentationErp presentation
Erp presentation
 
ERP-Case Study- Changes before and after implementing ERP in a company
ERP-Case Study- Changes before and after implementing ERP in a companyERP-Case Study- Changes before and after implementing ERP in a company
ERP-Case Study- Changes before and after implementing ERP in a company
 
E.P.R. (ENTERPRISE RESOURCE PLANNING)
E.P.R. (ENTERPRISE RESOURCE PLANNING)E.P.R. (ENTERPRISE RESOURCE PLANNING)
E.P.R. (ENTERPRISE RESOURCE PLANNING)
 
Erp Failure In Hershey’s
Erp Failure In Hershey’sErp Failure In Hershey’s
Erp Failure In Hershey’s
 
Hp Network Printer Design for Universality
Hp Network Printer Design for UniversalityHp Network Printer Design for Universality
Hp Network Printer Design for Universality
 
Erp in cadbury
Erp in cadburyErp in cadbury
Erp in cadbury
 
Role Of ERP In Supply Chain
Role Of ERP In Supply ChainRole Of ERP In Supply Chain
Role Of ERP In Supply Chain
 
Walmart Supply Chain Management ( Case study)
Walmart Supply Chain Management ( Case study)Walmart Supply Chain Management ( Case study)
Walmart Supply Chain Management ( Case study)
 

Semelhante a Erp case study

Enterprise resource-planning-erp-1218631405959212-8
Enterprise resource-planning-erp-1218631405959212-8Enterprise resource-planning-erp-1218631405959212-8
Enterprise resource-planning-erp-1218631405959212-8
Pratik Van
 
Business strategic information management.docx
Business strategic information management.docxBusiness strategic information management.docx
Business strategic information management.docx
write31
 

Semelhante a Erp case study (20)

Enterprise Resource Planning
Enterprise Resource PlanningEnterprise Resource Planning
Enterprise Resource Planning
 
ERP - Implementation is The Challenge
ERP - Implementation is The ChallengeERP - Implementation is The Challenge
ERP - Implementation is The Challenge
 
ERP, SAP
ERP, SAPERP, SAP
ERP, SAP
 
Enterprise Resource Plannning
Enterprise Resource PlannningEnterprise Resource Plannning
Enterprise Resource Plannning
 
Cisco ERP Implementation
Cisco ERP ImplementationCisco ERP Implementation
Cisco ERP Implementation
 
Enabling Business Transformation with DRM & FDMEE
Enabling Business Transformation with DRM & FDMEEEnabling Business Transformation with DRM & FDMEE
Enabling Business Transformation with DRM & FDMEE
 
Enterprise resource-planning-erp-1218631405959212-8
Enterprise resource-planning-erp-1218631405959212-8Enterprise resource-planning-erp-1218631405959212-8
Enterprise resource-planning-erp-1218631405959212-8
 
Erp
ErpErp
Erp
 
Erp presentation
Erp presentationErp presentation
Erp presentation
 
ERP Implementation Phases
ERP Implementation PhasesERP Implementation Phases
ERP Implementation Phases
 
Creating a Solid EPM Punch List
Creating a Solid EPM Punch ListCreating a Solid EPM Punch List
Creating a Solid EPM Punch List
 
ERP Implementation Coca-Cola Hellenic
ERP Implementation Coca-Cola HellenicERP Implementation Coca-Cola Hellenic
ERP Implementation Coca-Cola Hellenic
 
ERP implementation at steel mill
ERP implementation at steel millERP implementation at steel mill
ERP implementation at steel mill
 
Business strategic information management.docx
Business strategic information management.docxBusiness strategic information management.docx
Business strategic information management.docx
 
ERP
ERPERP
ERP
 
vandelay case analysis
vandelay case analysisvandelay case analysis
vandelay case analysis
 
Mba ii ewis u iv erp
Mba ii ewis u iv erpMba ii ewis u iv erp
Mba ii ewis u iv erp
 
modules of erp
modules of erpmodules of erp
modules of erp
 
Erp
ErpErp
Erp
 
erp ppt
erp ppterp ppt
erp ppt
 

Mais de UMaine

Information ethics & intro to information security
Information ethics & intro to information securityInformation ethics & intro to information security
Information ethics & intro to information security
UMaine
 
Information security management
Information security managementInformation security management
Information security management
UMaine
 
Information systems management
Information systems managementInformation systems management
Information systems management
UMaine
 
Erp case study
Erp case studyErp case study
Erp case study
UMaine
 
Bua 235 teamwork
Bua 235 teamwork Bua 235 teamwork
Bua 235 teamwork
UMaine
 
Bua 235 teamwork
Bua 235 teamwork Bua 235 teamwork
Bua 235 teamwork
UMaine
 
Business intelligence systems
Business intelligence systemsBusiness intelligence systems
Business intelligence systems
UMaine
 
Chap 8 ecommerce-scm
Chap 8  ecommerce-scmChap 8  ecommerce-scm
Chap 8 ecommerce-scm
UMaine
 
Bua 235 bpm-chap 7
Bua 235 bpm-chap 7Bua 235 bpm-chap 7
Bua 235 bpm-chap 7
UMaine
 
Data communications
Data communicationsData communications
Data communications
UMaine
 
Chapter 5 data processing
Chapter 5 data processingChapter 5 data processing
Chapter 5 data processing
UMaine
 
Chap 4 hardware & software
Chap 4 hardware & softwareChap 4 hardware & software
Chap 4 hardware & software
UMaine
 
Is for competitive advantage
Is for competitive advantageIs for competitive advantage
Is for competitive advantage
UMaine
 
Chap 2 collaboration information systems and teamwork
Chap 2 collaboration information systems and teamworkChap 2 collaboration information systems and teamwork
Chap 2 collaboration information systems and teamwork
UMaine
 
Week 1 bua 235
Week 1 bua 235Week 1 bua 235
Week 1 bua 235
UMaine
 
E Business & E Commerce +
E Business & E Commerce +E Business & E Commerce +
E Business & E Commerce +
UMaine
 
Chapter 3 E Business
Chapter 3 E BusinessChapter 3 E Business
Chapter 3 E Business
UMaine
 
Chapter 2 Decision Making
Chapter 2 Decision MakingChapter 2 Decision Making
Chapter 2 Decision Making
UMaine
 
Welcome To BUA 235-Intro
Welcome To BUA 235-IntroWelcome To BUA 235-Intro
Welcome To BUA 235-Intro
UMaine
 
Enterprise Systems: SCM, CRM, & ERP
Enterprise Systems: SCM, CRM, & ERPEnterprise Systems: SCM, CRM, & ERP
Enterprise Systems: SCM, CRM, & ERP
UMaine
 

Mais de UMaine (20)

Information ethics & intro to information security
Information ethics & intro to information securityInformation ethics & intro to information security
Information ethics & intro to information security
 
Information security management
Information security managementInformation security management
Information security management
 
Information systems management
Information systems managementInformation systems management
Information systems management
 
Erp case study
Erp case studyErp case study
Erp case study
 
Bua 235 teamwork
Bua 235 teamwork Bua 235 teamwork
Bua 235 teamwork
 
Bua 235 teamwork
Bua 235 teamwork Bua 235 teamwork
Bua 235 teamwork
 
Business intelligence systems
Business intelligence systemsBusiness intelligence systems
Business intelligence systems
 
Chap 8 ecommerce-scm
Chap 8  ecommerce-scmChap 8  ecommerce-scm
Chap 8 ecommerce-scm
 
Bua 235 bpm-chap 7
Bua 235 bpm-chap 7Bua 235 bpm-chap 7
Bua 235 bpm-chap 7
 
Data communications
Data communicationsData communications
Data communications
 
Chapter 5 data processing
Chapter 5 data processingChapter 5 data processing
Chapter 5 data processing
 
Chap 4 hardware & software
Chap 4 hardware & softwareChap 4 hardware & software
Chap 4 hardware & software
 
Is for competitive advantage
Is for competitive advantageIs for competitive advantage
Is for competitive advantage
 
Chap 2 collaboration information systems and teamwork
Chap 2 collaboration information systems and teamworkChap 2 collaboration information systems and teamwork
Chap 2 collaboration information systems and teamwork
 
Week 1 bua 235
Week 1 bua 235Week 1 bua 235
Week 1 bua 235
 
E Business & E Commerce +
E Business & E Commerce +E Business & E Commerce +
E Business & E Commerce +
 
Chapter 3 E Business
Chapter 3 E BusinessChapter 3 E Business
Chapter 3 E Business
 
Chapter 2 Decision Making
Chapter 2 Decision MakingChapter 2 Decision Making
Chapter 2 Decision Making
 
Welcome To BUA 235-Intro
Welcome To BUA 235-IntroWelcome To BUA 235-Intro
Welcome To BUA 235-Intro
 
Enterprise Systems: SCM, CRM, & ERP
Enterprise Systems: SCM, CRM, & ERPEnterprise Systems: SCM, CRM, & ERP
Enterprise Systems: SCM, CRM, & ERP
 

Último

IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
Enterprise Knowledge
 

Último (20)

Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 

Erp case study

  • 1.
  • 2. Agenda  Company Background, Current Situation, and ERP Project  Current Systems and Requirements for ERP System  ERP Implementation  Big-Bang vs. Phased In Approach  Conclusion and Questions
  • 3. Company Background 3  World’s largest manufacture of storage devices  Largest producer of server and PC hard drives in 1996  Revenue of $4.4 billion  Purchased Digital Equipment Corp. (DEC) storage business in October 1994  Competitors – Seagate, IBM, and Western Digital  Outsource production of hard drives
  • 4. Current Situation  Legacy systems  Material requirement planning (MRP) system maintained separate databases and transactions had to be manually consolidated  Delays in obtaining updated information  Acquisition of DEC caused implementation issues 4
  • 5. ERP Project – Started April 1994  Worldwide Ask Replacement System - WARP  Three project teams  Steering committee – VP’s of Finance, IS, Logistics, Manufacturing, Purchasing, Sales, and Rep. from PW  Core team – 16 managers from department and business units  Project team (100 Members) – Members from IS and business unit key employees  Teams analyzed and improved business process  Selected Oracle, HP, and Price Waterhouse to assist with ERP implementation  Oracle 7 Database, Oracle Financial, and Manufacturing Modules  Expected implementation in Summer of 1995 5
  • 6. Problems with the ERP Implementation  Acquisition of DEC slowed implementation process of ERP System  Project was more complex with the acquisition of DEC  Duplicate systems, processes, and artifacts  Project was put on hold – Project teams focused on the DEC acquisition (October 1994)  ERP was restarted in January of 1995  Project team had to redo a large part of the original ERP implementation in order to take into account the DEC acquisition 6
  • 7. Quantum’s Current Systems  Nine different legacy systems that could not share information  Legacy system kept each division’s transactions in separate functional and business unit databases  Information was manually consolidated, since databases could not share information  Gathering faxes, emails, and written information took four days  Closing the books took seventeen days  Inventory availability could not be confirmed and delivery could take days or weeks 7
  • 8. Quantum’s Requirements for ERP System  Sales people to take and confirm an order in real time.  Sales have to be able to confirm a delivery time and follow up to ensure that order was delivered in real time  Ability to access current inventory and to reserve that order for the customer in real time  ATP (Available To Promise) – ability to confirm and allocate inventory 8
  • 9. ERP Implementation Phased implementation: Like the name implies means that modules are implemented one at a time or in a group of modules –often at a single location before moving on to more locations.  The installation of phase one could be the implementation of finance, controlling, accounts receivable, accounts payable, and purchasing modules.  Phase two could be to include materials management, production planning, and quality planning modules.  Following phases mean the deployment and implementation of remaining modules over a period of time. 9 “Phased” and “big-bang” are the two primary approaches used to implement ERP systems.
  • 10. Big-Bang Implementation  Big-Bang Implementation: “everything is changed at once!” Once an ERP solution has been chosen to meet organizational needs –the system goes from a test version to being the actual system used to capture transactions in only a matter of days. 10
  • 11. ERP Implementation: Consideration Factors  Organizational size and complexity. This includes factors related to the type of product that organization sells and the size and complexity of the customer  The organizations hierarchy and controls. Flat organizations with loose controls would have more difficulty deploying a phased implementation because its difficult to maintain commitment throughout the process. Organizations that have extensive hierarchy and tighter controls have the necessary mechanisms in place to sustain a phased approach  Extent of the implementation: based on the number of modules and the degree to which the organization changes those modules. 11
  • 14. Which do you Choose? 1. BIG BANG Or Phased-In Implementation? 2. What factors made you choose your implementation choice and why? Additional Questions: 3. What are a few benefits that could be gained from the implementation of your ERP choice? Be specific! Add value when writing the case study by looking up information about the Quantum online and include any finding in your answers 14