SlideShare uma empresa Scribd logo
1 de 40
(PS-1862) Modelling Line of Balance Schedules
with Start-Finish Relationships
Ricardo Viana Vargas
Felipe Fernandes Moreira
Authors
Ricardo Viana Vargas
ricardo@ricardo-
vargas.com
ricardo-vargas.com
@rvvargas
/in/ricardovargas
+45 4533 7673
Felipe Fernandes Moreira
felipef@gmail.com
/in/felipefmoreira
@ffmot
+55 85 32675722
+55 85 86999108
INTRODUCTION
3
Project Planning
4
Activity
List
Precedence
Diagram Method Network
Diagram
Activities Dependencies
5
PREDECESSOR SUCCESSOR
Logical Relationships
≠
Chronological Relationships
Line of Balance Scheduling Method (LBSM)
• Absent from PMBOK (discusses the CPM network
concepts most prominently);
• Technique used at construction industry at Brazil,
Finland and Australia (HENRICH & KOSKELA, 2006);
• Related with Lean Construction and Last Planner
System;
• Surging in recent years: need to go further than just the
critical path;
• Drawback: lack of software support.
Line of Balance Scheduling Method
• “Unit of Production x Time” Chart;
• Different from the usual “Activity x Time” Gantt Chart;
• Focus on the workflow;
• Scheduling according to the rate of production;
• Number of working units delivered by a working crew.
OBJECTIVES
8
Objectives
• Since LBSM lacks software support;
• Propose a method for modelling a Line of Balance with
CPM calculations software;
• Method involves the use of “Start-Finish” logical
relationship.
The main objective of this paper is to propose how to
model a Line of Balance schedule, while the secondary
objective is to investigate the “unexpected results” of
this sort of modelling.
LINE OF BALANCE SCHEDULING METHOD
10
Line of Balance Scheduling Method
• Scheduling according to the rate of production
• Number of working units delivered by a working
crew
List of Activities
Line of Balance Scheduling Method
Schedule using the Gantt chart
Line of Balance Scheduling Method
Schedule using the LBSM
Line of Balance Scheduling Method
Schedule using the LBSM
Rate of Activities
Production
Angular
Coefficient of
each line
0.25
units/day
0.50
units/day
0.33
units/day
Line of Balance Scheduling Method
Balancing the
lines
Make the rate of
production of the
activities to be as
similar as possible
Reduce the
Task 2 “speed”
(make its angular
coefficient smaller)
Reduce its
resources by half –
increase duration
from 2 to 4 days
Line of Balance Scheduling Method
Balancing lines to achieve a schedule reduction
0.25
units/day
0.50
units/day
0.33
units/day
Project finishing earlier
Line of Balance Scheduling Method
4 lines (4 production units)
12 lines
(3 tasks for 4 floors)
Line of Balance Scheduling Method
• Significant reduction of lines
• The bigger the number of repetitions, the bigger
the reduction
• Applicable at all sort of repetitive processes
– Eg.: Construction of 100 km, with 20 tasks for
each kilometer
Line of Balance Scheduling Method
• Construction industry: tasks are scheduled
continuously (KENLEY & SEPPÄNEN, 2010)
• Could be scheduled without this restriction
Line of Balance without the continuity of repetition
Line of Balance Scheduling Method
0.250
units/day
0.286
units/day
0.267
units/day
3-day reduction
Line Balacing Schedule Reduction
Line Balacing is a “Crashing Method!”
Line of Balance Scheduling Method
Breaking the continuity restriction will
increase the total time of resource allocation!
16 days
14 days 15 days
16 days 8 days 12 days
Line of Balance Scheduling Method
Line of Balance Scheduling Method
Peculiarity: how to model this schedule?
Two proposals
Network Approach
•Envolves CPM network calculations
Linear Scheduling Approach
•Drops the CPM network
calculations
NETWORK APPROACH
25
The Network Approach
Task 1 on the 4th floor defines the start
date of Task 2 on the 4th floor
The last task offers the time
constraint for the task progression!
Task 2
faster than
Task 1
“FS relations”
Connected at the 4th floor
The Network Approach
Network Diagram with the logical relationship between tasks
The Network Approach
Can’t use the
“FS” relation
Time constraint is transmitted
“downward” from 4th to 1st floor.
Done with the “SF” relation.
The Network Approach
SF relation between the repetitions of Task 2
The Network Approach
Connected at
the 1st floor
4th floor is no longer the time constraint for the task progression.
Time constraint move “upwards” using the “FS” relation!
The Network Approach
Complete network diagram for the example
Important: PM softwares will show every task as critical
The Network Approach
Task 2 on the 2nd, 3rd and 4th floor are not critical!
The Network Approach
• “FS” logical relationships + As Late As Possible (ALAP)
Breaks the
continuity
Results in a different schedule! Finishes earlier
The Network Approach
• Both “SF” and “FS” + ALAP structures offer viable
options for LBSM modelling;
• “SF”:
– Ensures continuous task progressions;
– No risk related to discontinuity.
• “FS” + ALAP:
– Shorter Project duration;
– Risks related with discontinuity.
LINEAR SCHEDULE APPROACH
35
The Linear Schedule Approach
• Drops the CPM network calculations;
• Uses the software as a “graphical tool”;
• Focus on the fundamentals: flow of work.
The Linear Schedule Approach
• Control by flow? Avoid clashes
Clash = Rupture in the workflow
• Modelling lines by chaining tasks and subordinating it to
milestones.
“SF” relationships
“FS” relationships
CONCLUSION
39
Conclusion
• Line of Balance x Gantt Chart;
• LBSM x CPM network;
• Flow x Critical Path;
• Utilization of “Start-Finish” on scheduling;
• Line of Balance as a CPM network:
– “SF” relationships ensures the task progression
continuity;
– “FS” + ALAP potencially reduces the project duration at
the cost of higher risk;
• CPM software as a “graphical tool”:
– End Milestones: “SF” relationships;
– Start Milestones: “FS” relationships.

Mais conteúdo relacionado

Mais procurados

MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...Aravind NC
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2Abdelhay Ghanem
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Use of forward pass and backward pass in primavera
Use of forward pass and backward pass in primaveraUse of forward pass and backward pass in primavera
Use of forward pass and backward pass in primaveraAmit Kumar Senapati, PMP®
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineeringrathodjaydeep2
 
4 an activity analysis of project scheduling problem a case study 1
4 an activity analysis of project scheduling problem   a case study 14 an activity analysis of project scheduling problem   a case study 1
4 an activity analysis of project scheduling problem a case study 1pmb25
 
Scheduling Optimization with Line of Balance and Start-to-Finish Relations
Scheduling Optimization with Line of Balance and Start-to-Finish RelationsScheduling Optimization with Line of Balance and Start-to-Finish Relations
Scheduling Optimization with Line of Balance and Start-to-Finish RelationsRicardo Viana Vargas
 
Seven Basic Steps to Build Realistic Schedule in Project 2010
Seven Basic Steps to Build Realistic Schedule in Project 2010Seven Basic Steps to Build Realistic Schedule in Project 2010
Seven Basic Steps to Build Realistic Schedule in Project 2010B Sai Prasad
 
09 lecture project scheduling 1
09 lecture project scheduling 109 lecture project scheduling 1
09 lecture project scheduling 1Ahmad Basim Hamza
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project schedulingSoe Naing Win
 
PDM - Precedence Diagram Method
PDM - Precedence Diagram MethodPDM - Precedence Diagram Method
PDM - Precedence Diagram Methodphantai24
 
A credible pmb is the window to program
A credible pmb is the window to programA credible pmb is the window to program
A credible pmb is the window to programGlen Alleman
 
CPMaxis General Information Presentation
CPMaxis General Information PresentationCPMaxis General Information Presentation
CPMaxis General Information PresentationOlivia Wilson
 
5.project scopemanagement
5.project scopemanagement5.project scopemanagement
5.project scopemanagementNiranjana K.R.
 
Wbs & Bar chart for Civil engg
Wbs & Bar chart for Civil engg Wbs & Bar chart for Civil engg
Wbs & Bar chart for Civil engg Meet Shah
 
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET Journal
 

Mais procurados (20)

MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2
 
Lesson in fs cpm,cpa
Lesson in fs cpm,cpaLesson in fs cpm,cpa
Lesson in fs cpm,cpa
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Use of forward pass and backward pass in primavera
Use of forward pass and backward pass in primaveraUse of forward pass and backward pass in primavera
Use of forward pass and backward pass in primavera
 
6.3 sequence activities
6.3 sequence activities6.3 sequence activities
6.3 sequence activities
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineering
 
4 an activity analysis of project scheduling problem a case study 1
4 an activity analysis of project scheduling problem   a case study 14 an activity analysis of project scheduling problem   a case study 1
4 an activity analysis of project scheduling problem a case study 1
 
Scheduling Optimization with Line of Balance and Start-to-Finish Relations
Scheduling Optimization with Line of Balance and Start-to-Finish RelationsScheduling Optimization with Line of Balance and Start-to-Finish Relations
Scheduling Optimization with Line of Balance and Start-to-Finish Relations
 
Seven Basic Steps to Build Realistic Schedule in Project 2010
Seven Basic Steps to Build Realistic Schedule in Project 2010Seven Basic Steps to Build Realistic Schedule in Project 2010
Seven Basic Steps to Build Realistic Schedule in Project 2010
 
Ijmet 09 11_006
Ijmet 09 11_006Ijmet 09 11_006
Ijmet 09 11_006
 
09 lecture project scheduling 1
09 lecture project scheduling 109 lecture project scheduling 1
09 lecture project scheduling 1
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
PDM - Precedence Diagram Method
PDM - Precedence Diagram MethodPDM - Precedence Diagram Method
PDM - Precedence Diagram Method
 
A credible pmb is the window to program
A credible pmb is the window to programA credible pmb is the window to program
A credible pmb is the window to program
 
CPMaxis General Information Presentation
CPMaxis General Information PresentationCPMaxis General Information Presentation
CPMaxis General Information Presentation
 
5.project scopemanagement
5.project scopemanagement5.project scopemanagement
5.project scopemanagement
 
Wbs & Bar chart for Civil engg
Wbs & Bar chart for Civil engg Wbs & Bar chart for Civil engg
Wbs & Bar chart for Civil engg
 
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
 

Destaque

Lecture slides5; LINE OF BALANCE PROGRAMMING
Lecture slides5; LINE OF BALANCE PROGRAMMINGLecture slides5; LINE OF BALANCE PROGRAMMING
Lecture slides5; LINE OF BALANCE PROGRAMMINGJB Nartey
 
Modelando Linhas de Balanço com Relacionamentos "Início-Término"
Modelando Linhas de Balanço com Relacionamentos "Início-Término"Modelando Linhas de Balanço com Relacionamentos "Início-Término"
Modelando Linhas de Balanço com Relacionamentos "Início-Término"Felipe Moreira
 
Modeling a Global Software Development Project as a Complex Socio-Technical S...
Modeling a Global Software Development Project as a Complex Socio-Technical S...Modeling a Global Software Development Project as a Complex Socio-Technical S...
Modeling a Global Software Development Project as a Complex Socio-Technical S...Ilia Bider
 
OS AVANÇOS NA EDUCAÇÃO DO ENSINO SUPERIOR DE ENGENHARIA
OS AVANÇOS NA EDUCAÇÃO DOENSINO SUPERIOR DE ENGENHARIAOS AVANÇOS NA EDUCAÇÃO DOENSINO SUPERIOR DE ENGENHARIA
OS AVANÇOS NA EDUCAÇÃO DO ENSINO SUPERIOR DE ENGENHARIACADWARE-TECHNOLOGY
 
10 things to improve project management
10 things to improve project management10 things to improve project management
10 things to improve project managementStriking Group Pty Ltd
 
Productivity Improvement Study
Productivity Improvement StudyProductivity Improvement Study
Productivity Improvement Studysaranshshah
 
Five ways to improve productivity at the construction site
Five ways to improve productivity at the construction siteFive ways to improve productivity at the construction site
Five ways to improve productivity at the construction siteVikaslal2006
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)Anand Subramaniam
 

Destaque (12)

Linear scheduling LSM
Linear scheduling LSMLinear scheduling LSM
Linear scheduling LSM
 
Lecture slides5; LINE OF BALANCE PROGRAMMING
Lecture slides5; LINE OF BALANCE PROGRAMMINGLecture slides5; LINE OF BALANCE PROGRAMMING
Lecture slides5; LINE OF BALANCE PROGRAMMING
 
Modelando Linhas de Balanço com Relacionamentos "Início-Término"
Modelando Linhas de Balanço com Relacionamentos "Início-Término"Modelando Linhas de Balanço com Relacionamentos "Início-Término"
Modelando Linhas de Balanço com Relacionamentos "Início-Término"
 
Modeling a Global Software Development Project as a Complex Socio-Technical S...
Modeling a Global Software Development Project as a Complex Socio-Technical S...Modeling a Global Software Development Project as a Complex Socio-Technical S...
Modeling a Global Software Development Project as a Complex Socio-Technical S...
 
TECNOLOGIA BIM
TECNOLOGIA BIMTECNOLOGIA BIM
TECNOLOGIA BIM
 
OS AVANÇOS NA EDUCAÇÃO DO ENSINO SUPERIOR DE ENGENHARIA
OS AVANÇOS NA EDUCAÇÃO DOENSINO SUPERIOR DE ENGENHARIAOS AVANÇOS NA EDUCAÇÃO DOENSINO SUPERIOR DE ENGENHARIA
OS AVANÇOS NA EDUCAÇÃO DO ENSINO SUPERIOR DE ENGENHARIA
 
Size chart j crew
Size chart j crewSize chart j crew
Size chart j crew
 
10 things to improve project management
10 things to improve project management10 things to improve project management
10 things to improve project management
 
Productivity Improvement Study
Productivity Improvement StudyProductivity Improvement Study
Productivity Improvement Study
 
Line balancing
Line balancingLine balancing
Line balancing
 
Five ways to improve productivity at the construction site
Five ways to improve productivity at the construction siteFive ways to improve productivity at the construction site
Five ways to improve productivity at the construction site
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)
 

Semelhante a Modelling Line of Balance Schedules with Start-Finish Relationships

Schedule_Module_V.10.ppt
Schedule_Module_V.10.pptSchedule_Module_V.10.ppt
Schedule_Module_V.10.pptssusere57332
 
BIM, Lean & Advanced Work Packaging - How do they fit together?
BIM, Lean & Advanced Work Packaging - How do they fit together? BIM, Lean & Advanced Work Packaging - How do they fit together?
BIM, Lean & Advanced Work Packaging - How do they fit together? CCT International
 
Software Project Scheduling Diagrams
Software Project Scheduling DiagramsSoftware Project Scheduling Diagrams
Software Project Scheduling DiagramsSaqib Raza
 
Network diagrams
Network diagramsNetwork diagrams
Network diagramsLii Van
 
AWIN presentation it's only logical-a scheduling overview
AWIN presentation it's only logical-a scheduling overviewAWIN presentation it's only logical-a scheduling overview
AWIN presentation it's only logical-a scheduling overviewDanielle Murphy
 
3210cpmslideshare-1610302073773770419.pdf
3210cpmslideshare-1610302073773770419.pdf3210cpmslideshare-1610302073773770419.pdf
3210cpmslideshare-1610302073773770419.pdfPabitraMitra3
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisAsif Sultan Razu
 
Lect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMLect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMMubashir Ali
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptxPigPug1
 
vnc_1660543731.pptx
vnc_1660543731.pptxvnc_1660543731.pptx
vnc_1660543731.pptxPigPug1
 
Capella Days 2021 | A STEP towards Model-based: Case Study covering Conceptua...
Capella Days 2021 | A STEP towards Model-based: Case Study covering Conceptua...Capella Days 2021 | A STEP towards Model-based: Case Study covering Conceptua...
Capella Days 2021 | A STEP towards Model-based: Case Study covering Conceptua...Obeo
 
Neptune: Scheduling Suspendable Tasks for Unified Stream/Batch Applications
Neptune: Scheduling Suspendable Tasks for Unified Stream/Batch ApplicationsNeptune: Scheduling Suspendable Tasks for Unified Stream/Batch Applications
Neptune: Scheduling Suspendable Tasks for Unified Stream/Batch ApplicationsPanagiotis Garefalakis
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-seminiMaya
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptxPigPug1
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptxPigPug1
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTsalsa moyara
 
Software_effort_estimation for Software engineering.pdf
Software_effort_estimation for Software engineering.pdfSoftware_effort_estimation for Software engineering.pdf
Software_effort_estimation for Software engineering.pdfsnehan789
 
06 project time management
06  project time management06  project time management
06 project time managementAla Ibrahim
 

Semelhante a Modelling Line of Balance Schedules with Start-Finish Relationships (20)

Schedule_Module_V.10.ppt
Schedule_Module_V.10.pptSchedule_Module_V.10.ppt
Schedule_Module_V.10.ppt
 
BIM, Lean & Advanced Work Packaging - How do they fit together?
BIM, Lean & Advanced Work Packaging - How do they fit together? BIM, Lean & Advanced Work Packaging - How do they fit together?
BIM, Lean & Advanced Work Packaging - How do they fit together?
 
Software Project Scheduling Diagrams
Software Project Scheduling DiagramsSoftware Project Scheduling Diagrams
Software Project Scheduling Diagrams
 
Network diagrams
Network diagramsNetwork diagrams
Network diagrams
 
AWIN presentation it's only logical-a scheduling overview
AWIN presentation it's only logical-a scheduling overviewAWIN presentation it's only logical-a scheduling overview
AWIN presentation it's only logical-a scheduling overview
 
3210cpmslideshare-1610302073773770419.pdf
3210cpmslideshare-1610302073773770419.pdf3210cpmslideshare-1610302073773770419.pdf
3210cpmslideshare-1610302073773770419.pdf
 
Chapter 4.pptx
Chapter 4.pptxChapter 4.pptx
Chapter 4.pptx
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 
Lect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMLect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPM
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptx
 
vnc_1660543731.pptx
vnc_1660543731.pptxvnc_1660543731.pptx
vnc_1660543731.pptx
 
Capella Days 2021 | A STEP towards Model-based: Case Study covering Conceptua...
Capella Days 2021 | A STEP towards Model-based: Case Study covering Conceptua...Capella Days 2021 | A STEP towards Model-based: Case Study covering Conceptua...
Capella Days 2021 | A STEP towards Model-based: Case Study covering Conceptua...
 
Neptune: Scheduling Suspendable Tasks for Unified Stream/Batch Applications
Neptune: Scheduling Suspendable Tasks for Unified Stream/Batch ApplicationsNeptune: Scheduling Suspendable Tasks for Unified Stream/Batch Applications
Neptune: Scheduling Suspendable Tasks for Unified Stream/Batch Applications
 
lec11.ppt
lec11.pptlec11.ppt
lec11.ppt
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptx
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptx
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 
Software_effort_estimation for Software engineering.pdf
Software_effort_estimation for Software engineering.pdfSoftware_effort_estimation for Software engineering.pdf
Software_effort_estimation for Software engineering.pdf
 
06 project time management
06  project time management06  project time management
06 project time management
 

Último

High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 

Último (20)

High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 

Modelling Line of Balance Schedules with Start-Finish Relationships

  • 1. (PS-1862) Modelling Line of Balance Schedules with Start-Finish Relationships Ricardo Viana Vargas Felipe Fernandes Moreira
  • 2. Authors Ricardo Viana Vargas ricardo@ricardo- vargas.com ricardo-vargas.com @rvvargas /in/ricardovargas +45 4533 7673 Felipe Fernandes Moreira felipef@gmail.com /in/felipefmoreira @ffmot +55 85 32675722 +55 85 86999108
  • 5. Activities Dependencies 5 PREDECESSOR SUCCESSOR Logical Relationships ≠ Chronological Relationships
  • 6. Line of Balance Scheduling Method (LBSM) • Absent from PMBOK (discusses the CPM network concepts most prominently); • Technique used at construction industry at Brazil, Finland and Australia (HENRICH & KOSKELA, 2006); • Related with Lean Construction and Last Planner System; • Surging in recent years: need to go further than just the critical path; • Drawback: lack of software support.
  • 7. Line of Balance Scheduling Method • “Unit of Production x Time” Chart; • Different from the usual “Activity x Time” Gantt Chart; • Focus on the workflow; • Scheduling according to the rate of production; • Number of working units delivered by a working crew.
  • 9. Objectives • Since LBSM lacks software support; • Propose a method for modelling a Line of Balance with CPM calculations software; • Method involves the use of “Start-Finish” logical relationship. The main objective of this paper is to propose how to model a Line of Balance schedule, while the secondary objective is to investigate the “unexpected results” of this sort of modelling.
  • 10. LINE OF BALANCE SCHEDULING METHOD 10
  • 11. Line of Balance Scheduling Method • Scheduling according to the rate of production • Number of working units delivered by a working crew List of Activities
  • 12. Line of Balance Scheduling Method Schedule using the Gantt chart
  • 13. Line of Balance Scheduling Method Schedule using the LBSM
  • 14. Line of Balance Scheduling Method Schedule using the LBSM Rate of Activities Production Angular Coefficient of each line 0.25 units/day 0.50 units/day 0.33 units/day
  • 15. Line of Balance Scheduling Method Balancing the lines Make the rate of production of the activities to be as similar as possible Reduce the Task 2 “speed” (make its angular coefficient smaller) Reduce its resources by half – increase duration from 2 to 4 days
  • 16. Line of Balance Scheduling Method Balancing lines to achieve a schedule reduction 0.25 units/day 0.50 units/day 0.33 units/day Project finishing earlier
  • 17. Line of Balance Scheduling Method 4 lines (4 production units) 12 lines (3 tasks for 4 floors)
  • 18. Line of Balance Scheduling Method • Significant reduction of lines • The bigger the number of repetitions, the bigger the reduction • Applicable at all sort of repetitive processes – Eg.: Construction of 100 km, with 20 tasks for each kilometer
  • 19. Line of Balance Scheduling Method • Construction industry: tasks are scheduled continuously (KENLEY & SEPPÄNEN, 2010) • Could be scheduled without this restriction Line of Balance without the continuity of repetition
  • 20. Line of Balance Scheduling Method 0.250 units/day 0.286 units/day 0.267 units/day
  • 21. 3-day reduction Line Balacing Schedule Reduction Line Balacing is a “Crashing Method!” Line of Balance Scheduling Method
  • 22. Breaking the continuity restriction will increase the total time of resource allocation! 16 days 14 days 15 days 16 days 8 days 12 days Line of Balance Scheduling Method
  • 23. Line of Balance Scheduling Method Peculiarity: how to model this schedule?
  • 24. Two proposals Network Approach •Envolves CPM network calculations Linear Scheduling Approach •Drops the CPM network calculations
  • 26. The Network Approach Task 1 on the 4th floor defines the start date of Task 2 on the 4th floor The last task offers the time constraint for the task progression! Task 2 faster than Task 1 “FS relations” Connected at the 4th floor
  • 27. The Network Approach Network Diagram with the logical relationship between tasks
  • 28. The Network Approach Can’t use the “FS” relation Time constraint is transmitted “downward” from 4th to 1st floor. Done with the “SF” relation.
  • 29. The Network Approach SF relation between the repetitions of Task 2
  • 30. The Network Approach Connected at the 1st floor 4th floor is no longer the time constraint for the task progression. Time constraint move “upwards” using the “FS” relation!
  • 31. The Network Approach Complete network diagram for the example Important: PM softwares will show every task as critical
  • 32. The Network Approach Task 2 on the 2nd, 3rd and 4th floor are not critical!
  • 33. The Network Approach • “FS” logical relationships + As Late As Possible (ALAP) Breaks the continuity Results in a different schedule! Finishes earlier
  • 34. The Network Approach • Both “SF” and “FS” + ALAP structures offer viable options for LBSM modelling; • “SF”: – Ensures continuous task progressions; – No risk related to discontinuity. • “FS” + ALAP: – Shorter Project duration; – Risks related with discontinuity.
  • 36. The Linear Schedule Approach • Drops the CPM network calculations; • Uses the software as a “graphical tool”; • Focus on the fundamentals: flow of work.
  • 37. The Linear Schedule Approach • Control by flow? Avoid clashes Clash = Rupture in the workflow
  • 38. • Modelling lines by chaining tasks and subordinating it to milestones. “SF” relationships “FS” relationships
  • 40. Conclusion • Line of Balance x Gantt Chart; • LBSM x CPM network; • Flow x Critical Path; • Utilization of “Start-Finish” on scheduling; • Line of Balance as a CPM network: – “SF” relationships ensures the task progression continuity; – “FS” + ALAP potencially reduces the project duration at the cost of higher risk; • CPM software as a “graphical tool”: – End Milestones: “SF” relationships; – Start Milestones: “FS” relationships.