e-Governance Initiative Update
   October 4th, 2010


Rama Vedashree
rama@nasscom.in
eGov & IT Services Procurement Issues,
      Challenges, Preliminary Recommendations
                  a NASSCOM Study




6-Oct-10
                                                2
Methodology
  • Discuss with cross section of Industry and obtain feedback, on all
    phases of eGov Projects Life Cycle
     o Large / SME System Integrators both incumbents and aspirants
     o OEMs
     o Consultancy Organizations (Both Technology/eGov and
       Infrastructure Advisory)
  • Discuss with cross section of State & Central Government
     o Central Government – Cross Section of Mission Mode Project
       Teams
     o State Government IT Departments and Nodal Agencies
     o Ex - IT Secretaries
  • Study Best practices from Infrastructure Sector
  • Study International practices
  Questionnaire for IT Services Companies
  Points for Discussion for TN Government
  West Bengal Response
  Points for Discussion for Mr J Satyanarayana
GOVERNMENT PERSPECTIVE
Feedback to Industry



  • eGov and Functional/Domain Expertise very low – Consultants & SIs
  • Delivery Resources Assigned to eGov projects, is not satisfactory
  • Low, unviable commercial bids being submitted by Vendors
     o Entry Strategy
     o Low Price Bids without estimating complete scope
     o “Throwing Due Diligence and Project Estimation to Winds”

  • “Industry should change its focus from product orientation to citizen
    service delivery in e-Governance projects. The industry is still oriented
    towards supply of goods and services, the service orientation which is
    the core of all e-Governance services is lacking”
Capacity within Government

• Government officers not tuned to core technology issues related to
  e-Gov Projects
• Expertise in devising Service Level Agreements and issues related
  to Contract Management for IT Projects
• Two solutions
   o Bolster capacity within Government by training , recruiting staff
       • Some states have established dedicated empowered
         organization for implementation of E-Gov Projects
   o Establish a specialist service for handling e-Gov Projects & IT
     Function
• Capacity can be supplemented by officers of Public Works and
  Finance Departments (for Contracting Phase)
• Need for Government to develop overall capacity of Government
  employees in managing IT
Project Conceptualization and Development


  • Need for Financial modeling / risk assessment of e-
    Governance Projects – Specially PPP
  • Need to identify policy changes to ensure
    implementation of e-Gov projects and Electronic
    Service Delivery
  • Framework for IIIrd party audit, and Impact
    Assessment
  • Calculation of current cost of delivering service in
    manual mode
    o Cost Estimation Practices of PWD
  • E-Gov projects should have realistic achievable
    SLA’s, with corresponding penalties
INDUSTRY PERSPECTIVE
Discussions with Industry


                         Response

       SI's Large        TCS, Wipro, 3i Infotech, NIIT, Mastek,
       Incumbents &      Mindtree, L & T, HCL Technologies
       Aspirants Cross
       Section           Infosys (Only eBiz feedback)
       SI's SME          Ram Info, COMAT, ABM , Radiant, UTL, CMS,
                         Zylog, Humanitics)
       Consultancy       PwC, E & Y, IL&FS, NISG, IDFC (for
                         Infrastructure Best practices)
       OEM               Microsoft
       Total             23



   •   Discussion through Face to Face as well as Telephonic Interviews
   •   Several SIs Provided Formal Written Feedback
Summary of Industry Responses


  • The Respondents, provided a total of 277 issues which were
    distilled to 170 unique issues related to Procurement of IT Services
  • These issues were grouped into 19 Categories of issues - Project
    Conceptualization, Scope of Work, Project Execution .. For a
    complete list, click here
  • Maximum Issues & Challenges
      1. Project Execution
      2. Project Conceptualization & SOW
      3. Contract, T&C
Issues of Industry – A Summary
  S No.         Issue         OEM Incumbent Incumbent Aspirant   Consultant    Total Total No.
                               ( 1) Large      SME     Large        (5)        No. of of Unique
                                      ( 3)      ( 8)    (6)                   Respon Issues
                                                                                ses


   1      Project Execution    0       8        29       12          8          57       32

   2      Project              1       5        16       14          4          40       26
          Conceptualization
          and Development

   3      Contract ( Terms     0      20        3        12          3          38       24
          and Conditions
          Document)
   4      Pre Qualification    2       2        18       15          1          38       12
   5      Tender Evaluation    1       8        3        11          2          25       16

   6      Scope of Work        2       4        8        7           0          21       15
   7      Other Issues ( 13    0      15        17       19          7          58       45
          broad types of
          issues)
                               6      62        94       90         25         277      170
Issues Related to Project Execution


Timely Payment
• Lack of timely payment despite fulfillment of the deliverables of the
  Vendor, and Acceptance of Deliverables
• Lack of Continuity of Project Champion
• Delays in deliverables from Government
    • Investments made by the Vendor remaining idle and not paid for
        • The RFP may have a service level for procurement of goods
          by a certain date, however Site, provisioning of power supply
          may not be ready
        • Equipment of the Vendor will need to be stored in a
          Wearhouse
    • Budgetary Sanctions/Transfer to Line Department
• Delays in giving timely signoffs to Vendors both by TPA and
  Department
Project Execution Issues ( Contd..)


  • During Project Execution many issues come up which may not
    have been anticipated in the RFP

  • Department PMU not empowered to take appropriate
    decisions, in the interest of project implementation

  • Signoff's given by a Government Officer regarding a
    project, are not respected by the successor. Many times
    the successor likes to re-evaluate / review the certification
    of work, and even SoW & Contract

  • Lack of dedicated team within the Government Department for
    Project Monitoring
Project Conceptualization Issues

    • Projects incorporate many Non IT items as well, which increase
      the Project Cost. This leads to an increase in prequalification
      turnover norms, and also risk assessment of Vendors
    • Acceptance criteria / specifications for such non IT work, is not well
      defined
    • By clubbing requirements and entrusting the Turnkey job to a Prime
      SI, the Government does not take advantage of best of breed
      solutions from specialized Vendors
    • This issue has been highlighted by both Incumbent and Aspirant
      Large IT Services companies
    • Projects incorporate requirements like Lease Rental, Diesel for
      running of Gensets
        • Cost Estimation is guesswork, both on the extent of Grid
          Power Outages, and cost of diesel over a 5 Year Tenure.
          Indexing such input costs to a base price and factoring
          escalation is missing
Scope of Work, Specifications


 • There are many activities that only the Government Department can
   accomplish, but even these are given as scope of work of the
   Vendor . Some Examples:
    o Obtaining space from another Government Agency, access to
      the database/systems of another Government Department
    o Consent from participating departments to come on board an
      integrated services project, and enable integration to backends
    o No Counter Guarantees built into the SLAs for default by
      Govt and Govt Agencies
Payment Model / Business Model

• The Payment terms in Government Projects discourage growing the
  ecosystem of service providers
   o Payments in many cases are not milestone based, and even when
      milestone based, the Payments are skewed towards the end (telescopic)
• The payment for the early milestones does not cover the complete cost of
  production – Cash Flow Challenges for SMEs
• Many Projects increase the amount of investment, expenses of the Vendor
  by asking for heavy bank guarantees
   o In IT infrastructure projects with deferred (QGR) payment model, the
      investment by the Vendor in IT equipment, is not factored in Security
      against default
• Escrow mechanism not being adopted in most Projects
Pre Qualification

 •   Framing of prequalification norms is a pain point specially for
     Incumbent SME and Aspirant large organizations
 •   Redundant pre-qualification criteria like CMMI Level 5 for consultants or
     CMMi certification not relevant to projects
 •   Pre Qualification criteria favours incumbents who have experience only in
     Government Sector
      • No Level Playing field for firms, that have good credentials in other
        sectors, and now want to participate in Government Projects
      • Similar experience from non government sector in India (Telcos/Banks),
        not given due weightage
      • Relevant global experience in International Government Sector projects
        or relevant international private sector projects, not given weightage
 •   In consistency in Pre-Qualification Criteria across similar types of
     projects, or almost the same project across states
 •   Some projects pre-qualification criteria require net worth, in some
     profitability, in some case 3 or 5 years past revenues. Lack of
     standardized criteria tends to impact ‘Level Playing Field’
Contract (T&C/ MSA Document)

  •   Contracts have unlimited liability terms with no Caps linked to Contract Value
      and Payments to Date
  •   Contracts one sided and no counter SLAs on Govt Deliverables – Risk
      Overload for Vendors
  •   Liquidated Damages for Delays is disproportional to the Contract Value,
      Payments to Date
  •   eGov Contracts donot incorporate accepted best practices from World Bank Standard
      Bidding Documents, tender documents of well managed PSUs
  •   Termination for convenience by the Customer
       o Where Vendor has made investments, termination for convenience is an unfair
         practice
       o Exit management clauses donot adequately compensate the Vendor for
         investments
  Dispute Resolution
  •   Arbitration Clause - Arbitrators to be mutually decided as per Indian Arbitration Act.
  •   Arbitrator should not be a Officer of the same Line Department
  •   Arbitrator should be a neutral person like a retired judge/civil servant
  •   The judgment of the arbitrator should be binding on both the parties
  •   Many times, the same type of dispute with two different companies, is resolved in
      different ways
Tender Evaluation

 • Communication of scores to bidders, on the technical selection criteria
   not followed – reinforces misperceptions of Transparency
 • Evaluation Criteria, not in line with Industry Staffing & Resourcing
   practices
     • Bid Process expects Vendor to give names of employees that
       will be assigned to the Project. Given the Time Lag in
       Evaluation, Bid Award, Contract & Project Kick-Off, this is not
       practically feasible
 • "Available tender capacity" not considered while evaluating bidders,
   leading to some vendors being over leveraged
 • Significant difference between L1 and L2, Predatory pricing by
   some bidders. Floor Price Estimation is not adopted
 • Multiple Bid Validity Extensions are unreasonable
PPP Projects

•   Most PPP projects are first of a kind project and it is difficult to anticipate
    transaction volumes. Further they are dependent on a number of upstream
    activities like computerization of Government Departments
     • Given the risk of these projects, there should be some risk mitigation
       measures, counter guarantees to reduce the investment risk of the
       bidders
•   In PPP projects, SPV between the Government and winning bidder not being
    encouraged
•   In PPP Projects, Service Fee to Vendors not allowed to be deducted at source
•   Risks in PPP projects due to wide variance in estimate of likely services and
    volumes to be delivered through the Project.
•   Service cost is dependent on the numerator ( Anticipated investment which has
    a fixed and variable component ) and denominator ( Anticipated number of
    services, Expected Transaction Volumes) – Under/Overestimation Risks
•   PPP Project not designed in a manner to enable re-negotiation in both
    cases of excessive profitability or losses to vendor, compared to
    Infrastructure Sector
Broad issues related to e-Gov Procurement

  1.    Project Conceptualization and Development
  2.    Payment Model / Business Model
  3.    Scope of Work
  4.    Misprocurement
  5.    Tender publication
  6.    Bidding terms and conditions
  7.    Contract ( Terms and Conditions Document)
  8.    Pre Qualification
  9.    Pre-Bid meetings / Pre- Bid Clarifications
  10.   Tender Submission
  11.   Tender Evaluation
  12.   Post Tender Process
  13.   Third Party Audit
  14.   Project Execution
  15.   Post Implementation
  16.   PPP Projects
  17.   Consultant Issues
  18.   Dispute Resolution
  19.   Other Issues                             Go Back to Summary of Responses Slide
Preliminary Recommendations

 • Rationalize Eligibility Criteria Norms across different category, size of
   eGov Projects – Enable level playing field
 • Model RFPs, Contracts, MSA for different Category of Projects
       o To be prepared by a joint Government-Industry Team (include Reps
         from Banking Sector, NISG, Consultants)
       o Review by a Panel including DIT, Department of Expenditure, MoF
             o Customize these for state projects, and drive uniformity
       o SLAs should incorporate SLA and events of default for both Vendor
         & Govt/Govt Agencies
       o Incorporate Best practices of Model Documents Published by
         Planning Commission for Infrastructure Sector PPP
       o Toolkits for PPP, BOOT Projects and Business Model options to
         guide departments


  6-Oct-10
                                                                               22
Preliminary Recommendations
 •    Similar to Process followed for Pre-Bid Meetings, standardize on Suppliers
      debriefing, post vendor selection
        • Initiate a practice of sharing techno-commercial evaluation scores
 •    Project Governance Structure Publish a Model for different category of projects
        • Resourcing & Skills Profile across Lifecycle stages
        • Consult Enterprise CIOs, Industry and Banking PSUs
 •    Decide a Dispute Resolution & Arbitration Guidelines
        • Panel of retired officers from Government and Academia, knowledgeable
          with IT Projects Execution
        • Alternative Dispute Resolution mechanism on lines of procurement
          Ombudsman of Canada
 •    Centralized digital repository of all Information assets of Bids, Projects – on a
      secure Govt Network
                • RFPS, Pre-Bid Queries, Bid Amendments, Contracts, MSAs
                • Project Reviews, Audit Reports, Impact Assessment Reports
                • Vendor defaults/force majeure Situations
     6-Oct-10
                                                                                          23
Industry Actionables

  • eGov Functional/Domain Expertise
        • eGov Orientation/Functional Skills Development Programs
  • Project Estimation Rigor and Bid Review Process
        • Do we need leadership attention ?
        • CSC Bids have become a negative showcase for, NeGP,
          Outsourcing, PPP
              • Several states going through long drawn litigation or rebids
  • Initiate Impact Assessment of Projects Executed
        • Success Stories, Case Studies
        • Learnings from Failed projects




   6-Oct-10
                                                                               24
Thank You

Mais conteúdo relacionado

Mais procurados

Cobit, itil and cmmi - a tutorial
Cobit, itil and cmmi  - a tutorialCobit, itil and cmmi  - a tutorial
Cobit, itil and cmmi - a tutorialseveman
 
PPP identification & STRUCTURING Conceptualising
PPP identification & STRUCTURINGConceptualisingPPP identification & STRUCTURINGConceptualising
PPP identification & STRUCTURING ConceptualisingDr. Heera Lal IAS
 
Integrating PPM with Service Portfolio Management: The GEIT Perspective
Integrating PPM with Service Portfolio Management: The GEIT PerspectiveIntegrating PPM with Service Portfolio Management: The GEIT Perspective
Integrating PPM with Service Portfolio Management: The GEIT PerspectiveGeorge Papoulias
 
An improved, productive, skilled, innovative and efficient sector
An improved, productive, skilled, innovative and efficient sectorAn improved, productive, skilled, innovative and efficient sector
An improved, productive, skilled, innovative and efficient sectorLAZOVOY
 
SaaS Companies: What Costs Should Be Capitalized?
SaaS Companies: What Costs Should Be Capitalized?SaaS Companies: What Costs Should Be Capitalized?
SaaS Companies: What Costs Should Be Capitalized?Armanino LLP
 
Procurement - A Reflection on 2012-2013 and the Way Forward
Procurement - A Reflection on 2012-2013 and the Way ForwardProcurement - A Reflection on 2012-2013 and the Way Forward
Procurement - A Reflection on 2012-2013 and the Way ForwardKBIZEAU
 
雲端服務系統之專案管理
雲端服務系統之專案管理雲端服務系統之專案管理
雲端服務系統之專案管理Ray James X
 
Architecting for the Cloud with TOGAF®
Architecting for the Cloud with TOGAF®Architecting for the Cloud with TOGAF®
Architecting for the Cloud with TOGAF®Sunil Kempegowda
 
Enterprise Architecture Implementation And The Open Group Architecture Framew...
Enterprise Architecture Implementation And The Open Group Architecture Framew...Enterprise Architecture Implementation And The Open Group Architecture Framew...
Enterprise Architecture Implementation And The Open Group Architecture Framew...Alan McSweeney
 
CC&B SMECO Success Story
CC&B SMECO Success StoryCC&B SMECO Success Story
CC&B SMECO Success Storyvijaikrishnan
 
Accelerating Requirements with Process-Centric Prototyping
Accelerating Requirements with Process-Centric PrototypingAccelerating Requirements with Process-Centric Prototyping
Accelerating Requirements with Process-Centric Prototypingjamieraut
 
From Value Governance To Benefits Realization In A Controlled Environment
From Value Governance To Benefits Realization In A Controlled EnvironmentFrom Value Governance To Benefits Realization In A Controlled Environment
From Value Governance To Benefits Realization In A Controlled EnvironmentGeorge Papoulias
 

Mais procurados (13)

Cobit, itil and cmmi - a tutorial
Cobit, itil and cmmi  - a tutorialCobit, itil and cmmi  - a tutorial
Cobit, itil and cmmi - a tutorial
 
PPP identification & STRUCTURING Conceptualising
PPP identification & STRUCTURINGConceptualisingPPP identification & STRUCTURINGConceptualising
PPP identification & STRUCTURING Conceptualising
 
Integrating PPM with Service Portfolio Management: The GEIT Perspective
Integrating PPM with Service Portfolio Management: The GEIT PerspectiveIntegrating PPM with Service Portfolio Management: The GEIT Perspective
Integrating PPM with Service Portfolio Management: The GEIT Perspective
 
An improved, productive, skilled, innovative and efficient sector
An improved, productive, skilled, innovative and efficient sectorAn improved, productive, skilled, innovative and efficient sector
An improved, productive, skilled, innovative and efficient sector
 
SaaS Companies: What Costs Should Be Capitalized?
SaaS Companies: What Costs Should Be Capitalized?SaaS Companies: What Costs Should Be Capitalized?
SaaS Companies: What Costs Should Be Capitalized?
 
Dallas Mpug
Dallas MpugDallas Mpug
Dallas Mpug
 
Procurement - A Reflection on 2012-2013 and the Way Forward
Procurement - A Reflection on 2012-2013 and the Way ForwardProcurement - A Reflection on 2012-2013 and the Way Forward
Procurement - A Reflection on 2012-2013 and the Way Forward
 
雲端服務系統之專案管理
雲端服務系統之專案管理雲端服務系統之專案管理
雲端服務系統之專案管理
 
Architecting for the Cloud with TOGAF®
Architecting for the Cloud with TOGAF®Architecting for the Cloud with TOGAF®
Architecting for the Cloud with TOGAF®
 
Enterprise Architecture Implementation And The Open Group Architecture Framew...
Enterprise Architecture Implementation And The Open Group Architecture Framew...Enterprise Architecture Implementation And The Open Group Architecture Framew...
Enterprise Architecture Implementation And The Open Group Architecture Framew...
 
CC&B SMECO Success Story
CC&B SMECO Success StoryCC&B SMECO Success Story
CC&B SMECO Success Story
 
Accelerating Requirements with Process-Centric Prototyping
Accelerating Requirements with Process-Centric PrototypingAccelerating Requirements with Process-Centric Prototyping
Accelerating Requirements with Process-Centric Prototyping
 
From Value Governance To Benefits Realization In A Controlled Environment
From Value Governance To Benefits Realization In A Controlled EnvironmentFrom Value Governance To Benefits Realization In A Controlled Environment
From Value Governance To Benefits Realization In A Controlled Environment
 

Destaque

Kuppam backgrounder ver 2.101 cp december
Kuppam backgrounder ver 2.101 cp decemberKuppam backgrounder ver 2.101 cp december
Kuppam backgrounder ver 2.101 cp decemberAnirban Mukerji
 
Kuppam HP i-community Children's Coffee table book
Kuppam HP i-community Children's Coffee table bookKuppam HP i-community Children's Coffee table book
Kuppam HP i-community Children's Coffee table bookAnirban Mukerji
 
Urban property ownership records background document
Urban property ownership records background documentUrban property ownership records background document
Urban property ownership records background documentAnirban Mukerji
 
Electronic Delivery of services Bill, 2011 as introduced in Lok Sabha
Electronic Delivery of services Bill, 2011 as introduced in Lok SabhaElectronic Delivery of services Bill, 2011 as introduced in Lok Sabha
Electronic Delivery of services Bill, 2011 as introduced in Lok SabhaAnirban Mukerji
 
Ibtada Annual report 2009-10
Ibtada Annual report 2009-10Ibtada Annual report 2009-10
Ibtada Annual report 2009-10Anirban Mukerji
 
Shankar agarwal interview
Shankar agarwal interviewShankar agarwal interview
Shankar agarwal interviewAnirban Mukerji
 
Nemmadi program in karnataka july2007
Nemmadi program in karnataka july2007Nemmadi program in karnataka july2007
Nemmadi program in karnataka july2007Anirban Mukerji
 
Modernization Of State Government Treasury
Modernization Of State Government TreasuryModernization Of State Government Treasury
Modernization Of State Government TreasuryAnirban Mukerji
 
IRMA Network Magazine dedicated to Dr. V Kurien
IRMA Network Magazine dedicated to Dr. V KurienIRMA Network Magazine dedicated to Dr. V Kurien
IRMA Network Magazine dedicated to Dr. V KurienAnirban Mukerji
 
Guidelines for preparation of a RFP for e governance projects
Guidelines for preparation of a RFP for e governance projectsGuidelines for preparation of a RFP for e governance projects
Guidelines for preparation of a RFP for e governance projectsAnirban Mukerji
 
Egovernance Initiatives Of Karnataka
Egovernance Initiatives Of KarnatakaEgovernance Initiatives Of Karnataka
Egovernance Initiatives Of KarnatakaAnirban Mukerji
 
Introduction to the e-District MMP
Introduction to the e-District MMPIntroduction to the e-District MMP
Introduction to the e-District MMPAnirban Mukerji
 

Destaque (13)

Kuppam backgrounder ver 2.101 cp december
Kuppam backgrounder ver 2.101 cp decemberKuppam backgrounder ver 2.101 cp december
Kuppam backgrounder ver 2.101 cp december
 
Kuppam HP i-community Children's Coffee table book
Kuppam HP i-community Children's Coffee table bookKuppam HP i-community Children's Coffee table book
Kuppam HP i-community Children's Coffee table book
 
Urban property ownership records background document
Urban property ownership records background documentUrban property ownership records background document
Urban property ownership records background document
 
Electronic Delivery of services Bill, 2011 as introduced in Lok Sabha
Electronic Delivery of services Bill, 2011 as introduced in Lok SabhaElectronic Delivery of services Bill, 2011 as introduced in Lok Sabha
Electronic Delivery of services Bill, 2011 as introduced in Lok Sabha
 
Ibtada Annual report 2009-10
Ibtada Annual report 2009-10Ibtada Annual report 2009-10
Ibtada Annual report 2009-10
 
Shankar agarwal interview
Shankar agarwal interviewShankar agarwal interview
Shankar agarwal interview
 
Nemmadi program in karnataka july2007
Nemmadi program in karnataka july2007Nemmadi program in karnataka july2007
Nemmadi program in karnataka july2007
 
Modernization Of State Government Treasury
Modernization Of State Government TreasuryModernization Of State Government Treasury
Modernization Of State Government Treasury
 
IRMA Network Magazine dedicated to Dr. V Kurien
IRMA Network Magazine dedicated to Dr. V KurienIRMA Network Magazine dedicated to Dr. V Kurien
IRMA Network Magazine dedicated to Dr. V Kurien
 
Guidelines for preparation of a RFP for e governance projects
Guidelines for preparation of a RFP for e governance projectsGuidelines for preparation of a RFP for e governance projects
Guidelines for preparation of a RFP for e governance projects
 
Egovernance Initiatives Of Karnataka
Egovernance Initiatives Of KarnatakaEgovernance Initiatives Of Karnataka
Egovernance Initiatives Of Karnataka
 
Introduction to the e-District MMP
Introduction to the e-District MMPIntroduction to the e-District MMP
Introduction to the e-District MMP
 
Negp Presentation
Negp PresentationNegp Presentation
Negp Presentation
 

Semelhante a Nasscom mumbai workshop

E governance project conceptualisation to implementation
E governance project conceptualisation to implementationE governance project conceptualisation to implementation
E governance project conceptualisation to implementationAnirban Mukerji
 
Kick-Starting Digital Transformation: Four IT Strategies
Kick-Starting Digital Transformation: Four IT StrategiesKick-Starting Digital Transformation: Four IT Strategies
Kick-Starting Digital Transformation: Four IT StrategiesCognizant
 
Critical Success Factors Affecting Project Performance in Turkish IT Sector -...
Critical Success Factors Affecting Project Performance in Turkish IT Sector -...Critical Success Factors Affecting Project Performance in Turkish IT Sector -...
Critical Success Factors Affecting Project Performance in Turkish IT Sector -...systred
 
PMI-ACP Case Study
PMI-ACP Case StudyPMI-ACP Case Study
PMI-ACP Case StudyThanh Nguyen
 
Boddington Modelling Services
Boddington Modelling ServicesBoddington Modelling Services
Boddington Modelling ServicesBoddingt
 
CompTIA Project+ Objectives
CompTIA Project+ ObjectivesCompTIA Project+ Objectives
CompTIA Project+ Objectivessombat nirund
 
Mahesh_Umanath_06_2015
Mahesh_Umanath_06_2015Mahesh_Umanath_06_2015
Mahesh_Umanath_06_2015Mahesh Rao
 
TVPM - Good Lec.pptx
TVPM - Good Lec.pptxTVPM - Good Lec.pptx
TVPM - Good Lec.pptxbramepk1
 
Agile Development with Agile Contract
Agile Development with Agile ContractAgile Development with Agile Contract
Agile Development with Agile ContractNUS-ISS
 
Automotive IT Strategy: IT Sourcing
Automotive IT Strategy: IT SourcingAutomotive IT Strategy: IT Sourcing
Automotive IT Strategy: IT SourcingDeloitte Deutschland
 
Aravinda Nadig - Business Analyst
Aravinda Nadig - Business AnalystAravinda Nadig - Business Analyst
Aravinda Nadig - Business AnalystAravinda Nadig
 
Agile in LTU Public Sector (PMI Georgia Chapter 2021 09)
Agile in LTU Public Sector (PMI Georgia Chapter 2021 09)Agile in LTU Public Sector (PMI Georgia Chapter 2021 09)
Agile in LTU Public Sector (PMI Georgia Chapter 2021 09)Alexey Kovalyov
 

Semelhante a Nasscom mumbai workshop (20)

E governance project conceptualisation to implementation
E governance project conceptualisation to implementationE governance project conceptualisation to implementation
E governance project conceptualisation to implementation
 
Kick-Starting Digital Transformation: Four IT Strategies
Kick-Starting Digital Transformation: Four IT StrategiesKick-Starting Digital Transformation: Four IT Strategies
Kick-Starting Digital Transformation: Four IT Strategies
 
Critical Success Factors Affecting Project Performance in Turkish IT Sector -...
Critical Success Factors Affecting Project Performance in Turkish IT Sector -...Critical Success Factors Affecting Project Performance in Turkish IT Sector -...
Critical Success Factors Affecting Project Performance in Turkish IT Sector -...
 
PMI-ACP Case Study
PMI-ACP Case StudyPMI-ACP Case Study
PMI-ACP Case Study
 
Boddington Modelling Services
Boddington Modelling ServicesBoddington Modelling Services
Boddington Modelling Services
 
Automotive IT Strategy 2021
Automotive IT Strategy 2021Automotive IT Strategy 2021
Automotive IT Strategy 2021
 
CCRG 2005 Alberta Assessors Association Conference Seminar
CCRG 2005 Alberta Assessors Association Conference SeminarCCRG 2005 Alberta Assessors Association Conference Seminar
CCRG 2005 Alberta Assessors Association Conference Seminar
 
ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4
ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4
ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4
 
CompTIA Project+ Objectives
CompTIA Project+ ObjectivesCompTIA Project+ Objectives
CompTIA Project+ Objectives
 
Mahesh_Umanath_06_2015
Mahesh_Umanath_06_2015Mahesh_Umanath_06_2015
Mahesh_Umanath_06_2015
 
Guruprasad_Srinivasamurthy - CV
Guruprasad_Srinivasamurthy - CVGuruprasad_Srinivasamurthy - CV
Guruprasad_Srinivasamurthy - CV
 
TVPM - Good Lec.pptx
TVPM - Good Lec.pptxTVPM - Good Lec.pptx
TVPM - Good Lec.pptx
 
Agile Development with Agile Contract
Agile Development with Agile ContractAgile Development with Agile Contract
Agile Development with Agile Contract
 
PMI Presentation2
PMI Presentation2PMI Presentation2
PMI Presentation2
 
Automotive IT Strategy: IT Sourcing
Automotive IT Strategy: IT SourcingAutomotive IT Strategy: IT Sourcing
Automotive IT Strategy: IT Sourcing
 
TVRK_RESUME
TVRK_RESUMETVRK_RESUME
TVRK_RESUME
 
Shafi_QA Architect
Shafi_QA ArchitectShafi_QA Architect
Shafi_QA Architect
 
AmolBhate_CV
AmolBhate_CVAmolBhate_CV
AmolBhate_CV
 
Aravinda Nadig - Business Analyst
Aravinda Nadig - Business AnalystAravinda Nadig - Business Analyst
Aravinda Nadig - Business Analyst
 
Agile in LTU Public Sector (PMI Georgia Chapter 2021 09)
Agile in LTU Public Sector (PMI Georgia Chapter 2021 09)Agile in LTU Public Sector (PMI Georgia Chapter 2021 09)
Agile in LTU Public Sector (PMI Georgia Chapter 2021 09)
 

Mais de Anirban Mukerji

Ibtada Quarterly Newsletter Jan - March 2017
Ibtada Quarterly Newsletter Jan - March 2017Ibtada Quarterly Newsletter Jan - March 2017
Ibtada Quarterly Newsletter Jan - March 2017Anirban Mukerji
 
CaseStudy_SesInd_PlyNLrn_Eng_Aug2015
CaseStudy_SesInd_PlyNLrn_Eng_Aug2015CaseStudy_SesInd_PlyNLrn_Eng_Aug2015
CaseStudy_SesInd_PlyNLrn_Eng_Aug2015Anirban Mukerji
 
CaseStudy_India_CIDP_Eng_July2015_v1r4
CaseStudy_India_CIDP_Eng_July2015_v1r4CaseStudy_India_CIDP_Eng_July2015_v1r4
CaseStudy_India_CIDP_Eng_July2015_v1r4Anirban Mukerji
 
Mobile-technology-for-financial-inclusion-in-India-A-recap
Mobile-technology-for-financial-inclusion-in-India-A-recapMobile-technology-for-financial-inclusion-in-India-A-recap
Mobile-technology-for-financial-inclusion-in-India-A-recapAnirban Mukerji
 
Electronic delivery of services bill 2011
Electronic delivery of services bill 2011Electronic delivery of services bill 2011
Electronic delivery of services bill 2011Anirban Mukerji
 
Brief note on e district
Brief note on e districtBrief note on e district
Brief note on e districtAnirban Mukerji
 
Cvc guidelines on selection and employment of consultants
Cvc guidelines on selection and employment of consultantsCvc guidelines on selection and employment of consultants
Cvc guidelines on selection and employment of consultantsAnirban Mukerji
 
Nasscom e-Governance Study
Nasscom e-Governance StudyNasscom e-Governance Study
Nasscom e-Governance StudyAnirban Mukerji
 
Government Process Re-engineering
Government Process Re-engineeringGovernment Process Re-engineering
Government Process Re-engineeringAnirban Mukerji
 

Mais de Anirban Mukerji (10)

Ibtada Quarterly Newsletter Jan - March 2017
Ibtada Quarterly Newsletter Jan - March 2017Ibtada Quarterly Newsletter Jan - March 2017
Ibtada Quarterly Newsletter Jan - March 2017
 
CaseStudy_SesInd_PlyNLrn_Eng_Aug2015
CaseStudy_SesInd_PlyNLrn_Eng_Aug2015CaseStudy_SesInd_PlyNLrn_Eng_Aug2015
CaseStudy_SesInd_PlyNLrn_Eng_Aug2015
 
CaseStudy_India_CIDP_Eng_July2015_v1r4
CaseStudy_India_CIDP_Eng_July2015_v1r4CaseStudy_India_CIDP_Eng_July2015_v1r4
CaseStudy_India_CIDP_Eng_July2015_v1r4
 
india-fisher-friend (2)
india-fisher-friend (2)india-fisher-friend (2)
india-fisher-friend (2)
 
Mobile-technology-for-financial-inclusion-in-India-A-recap
Mobile-technology-for-financial-inclusion-in-India-A-recapMobile-technology-for-financial-inclusion-in-India-A-recap
Mobile-technology-for-financial-inclusion-in-India-A-recap
 
Electronic delivery of services bill 2011
Electronic delivery of services bill 2011Electronic delivery of services bill 2011
Electronic delivery of services bill 2011
 
Brief note on e district
Brief note on e districtBrief note on e district
Brief note on e district
 
Cvc guidelines on selection and employment of consultants
Cvc guidelines on selection and employment of consultantsCvc guidelines on selection and employment of consultants
Cvc guidelines on selection and employment of consultants
 
Nasscom e-Governance Study
Nasscom e-Governance StudyNasscom e-Governance Study
Nasscom e-Governance Study
 
Government Process Re-engineering
Government Process Re-engineeringGovernment Process Re-engineering
Government Process Re-engineering
 

Nasscom mumbai workshop

  • 1. e-Governance Initiative Update October 4th, 2010 Rama Vedashree rama@nasscom.in
  • 2. eGov & IT Services Procurement Issues, Challenges, Preliminary Recommendations a NASSCOM Study 6-Oct-10 2
  • 3. Methodology • Discuss with cross section of Industry and obtain feedback, on all phases of eGov Projects Life Cycle o Large / SME System Integrators both incumbents and aspirants o OEMs o Consultancy Organizations (Both Technology/eGov and Infrastructure Advisory) • Discuss with cross section of State & Central Government o Central Government – Cross Section of Mission Mode Project Teams o State Government IT Departments and Nodal Agencies o Ex - IT Secretaries • Study Best practices from Infrastructure Sector • Study International practices Questionnaire for IT Services Companies Points for Discussion for TN Government West Bengal Response Points for Discussion for Mr J Satyanarayana
  • 5. Feedback to Industry • eGov and Functional/Domain Expertise very low – Consultants & SIs • Delivery Resources Assigned to eGov projects, is not satisfactory • Low, unviable commercial bids being submitted by Vendors o Entry Strategy o Low Price Bids without estimating complete scope o “Throwing Due Diligence and Project Estimation to Winds” • “Industry should change its focus from product orientation to citizen service delivery in e-Governance projects. The industry is still oriented towards supply of goods and services, the service orientation which is the core of all e-Governance services is lacking”
  • 6. Capacity within Government • Government officers not tuned to core technology issues related to e-Gov Projects • Expertise in devising Service Level Agreements and issues related to Contract Management for IT Projects • Two solutions o Bolster capacity within Government by training , recruiting staff • Some states have established dedicated empowered organization for implementation of E-Gov Projects o Establish a specialist service for handling e-Gov Projects & IT Function • Capacity can be supplemented by officers of Public Works and Finance Departments (for Contracting Phase) • Need for Government to develop overall capacity of Government employees in managing IT
  • 7. Project Conceptualization and Development • Need for Financial modeling / risk assessment of e- Governance Projects – Specially PPP • Need to identify policy changes to ensure implementation of e-Gov projects and Electronic Service Delivery • Framework for IIIrd party audit, and Impact Assessment • Calculation of current cost of delivering service in manual mode o Cost Estimation Practices of PWD • E-Gov projects should have realistic achievable SLA’s, with corresponding penalties
  • 9. Discussions with Industry Response SI's Large TCS, Wipro, 3i Infotech, NIIT, Mastek, Incumbents & Mindtree, L & T, HCL Technologies Aspirants Cross Section Infosys (Only eBiz feedback) SI's SME Ram Info, COMAT, ABM , Radiant, UTL, CMS, Zylog, Humanitics) Consultancy PwC, E & Y, IL&FS, NISG, IDFC (for Infrastructure Best practices) OEM Microsoft Total 23 • Discussion through Face to Face as well as Telephonic Interviews • Several SIs Provided Formal Written Feedback
  • 10. Summary of Industry Responses • The Respondents, provided a total of 277 issues which were distilled to 170 unique issues related to Procurement of IT Services • These issues were grouped into 19 Categories of issues - Project Conceptualization, Scope of Work, Project Execution .. For a complete list, click here • Maximum Issues & Challenges 1. Project Execution 2. Project Conceptualization & SOW 3. Contract, T&C
  • 11. Issues of Industry – A Summary S No. Issue OEM Incumbent Incumbent Aspirant Consultant Total Total No. ( 1) Large SME Large (5) No. of of Unique ( 3) ( 8) (6) Respon Issues ses 1 Project Execution 0 8 29 12 8 57 32 2 Project 1 5 16 14 4 40 26 Conceptualization and Development 3 Contract ( Terms 0 20 3 12 3 38 24 and Conditions Document) 4 Pre Qualification 2 2 18 15 1 38 12 5 Tender Evaluation 1 8 3 11 2 25 16 6 Scope of Work 2 4 8 7 0 21 15 7 Other Issues ( 13 0 15 17 19 7 58 45 broad types of issues) 6 62 94 90 25 277 170
  • 12. Issues Related to Project Execution Timely Payment • Lack of timely payment despite fulfillment of the deliverables of the Vendor, and Acceptance of Deliverables • Lack of Continuity of Project Champion • Delays in deliverables from Government • Investments made by the Vendor remaining idle and not paid for • The RFP may have a service level for procurement of goods by a certain date, however Site, provisioning of power supply may not be ready • Equipment of the Vendor will need to be stored in a Wearhouse • Budgetary Sanctions/Transfer to Line Department • Delays in giving timely signoffs to Vendors both by TPA and Department
  • 13. Project Execution Issues ( Contd..) • During Project Execution many issues come up which may not have been anticipated in the RFP • Department PMU not empowered to take appropriate decisions, in the interest of project implementation • Signoff's given by a Government Officer regarding a project, are not respected by the successor. Many times the successor likes to re-evaluate / review the certification of work, and even SoW & Contract • Lack of dedicated team within the Government Department for Project Monitoring
  • 14. Project Conceptualization Issues • Projects incorporate many Non IT items as well, which increase the Project Cost. This leads to an increase in prequalification turnover norms, and also risk assessment of Vendors • Acceptance criteria / specifications for such non IT work, is not well defined • By clubbing requirements and entrusting the Turnkey job to a Prime SI, the Government does not take advantage of best of breed solutions from specialized Vendors • This issue has been highlighted by both Incumbent and Aspirant Large IT Services companies • Projects incorporate requirements like Lease Rental, Diesel for running of Gensets • Cost Estimation is guesswork, both on the extent of Grid Power Outages, and cost of diesel over a 5 Year Tenure. Indexing such input costs to a base price and factoring escalation is missing
  • 15. Scope of Work, Specifications • There are many activities that only the Government Department can accomplish, but even these are given as scope of work of the Vendor . Some Examples: o Obtaining space from another Government Agency, access to the database/systems of another Government Department o Consent from participating departments to come on board an integrated services project, and enable integration to backends o No Counter Guarantees built into the SLAs for default by Govt and Govt Agencies
  • 16. Payment Model / Business Model • The Payment terms in Government Projects discourage growing the ecosystem of service providers o Payments in many cases are not milestone based, and even when milestone based, the Payments are skewed towards the end (telescopic) • The payment for the early milestones does not cover the complete cost of production – Cash Flow Challenges for SMEs • Many Projects increase the amount of investment, expenses of the Vendor by asking for heavy bank guarantees o In IT infrastructure projects with deferred (QGR) payment model, the investment by the Vendor in IT equipment, is not factored in Security against default • Escrow mechanism not being adopted in most Projects
  • 17. Pre Qualification • Framing of prequalification norms is a pain point specially for Incumbent SME and Aspirant large organizations • Redundant pre-qualification criteria like CMMI Level 5 for consultants or CMMi certification not relevant to projects • Pre Qualification criteria favours incumbents who have experience only in Government Sector • No Level Playing field for firms, that have good credentials in other sectors, and now want to participate in Government Projects • Similar experience from non government sector in India (Telcos/Banks), not given due weightage • Relevant global experience in International Government Sector projects or relevant international private sector projects, not given weightage • In consistency in Pre-Qualification Criteria across similar types of projects, or almost the same project across states • Some projects pre-qualification criteria require net worth, in some profitability, in some case 3 or 5 years past revenues. Lack of standardized criteria tends to impact ‘Level Playing Field’
  • 18. Contract (T&C/ MSA Document) • Contracts have unlimited liability terms with no Caps linked to Contract Value and Payments to Date • Contracts one sided and no counter SLAs on Govt Deliverables – Risk Overload for Vendors • Liquidated Damages for Delays is disproportional to the Contract Value, Payments to Date • eGov Contracts donot incorporate accepted best practices from World Bank Standard Bidding Documents, tender documents of well managed PSUs • Termination for convenience by the Customer o Where Vendor has made investments, termination for convenience is an unfair practice o Exit management clauses donot adequately compensate the Vendor for investments Dispute Resolution • Arbitration Clause - Arbitrators to be mutually decided as per Indian Arbitration Act. • Arbitrator should not be a Officer of the same Line Department • Arbitrator should be a neutral person like a retired judge/civil servant • The judgment of the arbitrator should be binding on both the parties • Many times, the same type of dispute with two different companies, is resolved in different ways
  • 19. Tender Evaluation • Communication of scores to bidders, on the technical selection criteria not followed – reinforces misperceptions of Transparency • Evaluation Criteria, not in line with Industry Staffing & Resourcing practices • Bid Process expects Vendor to give names of employees that will be assigned to the Project. Given the Time Lag in Evaluation, Bid Award, Contract & Project Kick-Off, this is not practically feasible • "Available tender capacity" not considered while evaluating bidders, leading to some vendors being over leveraged • Significant difference between L1 and L2, Predatory pricing by some bidders. Floor Price Estimation is not adopted • Multiple Bid Validity Extensions are unreasonable
  • 20. PPP Projects • Most PPP projects are first of a kind project and it is difficult to anticipate transaction volumes. Further they are dependent on a number of upstream activities like computerization of Government Departments • Given the risk of these projects, there should be some risk mitigation measures, counter guarantees to reduce the investment risk of the bidders • In PPP projects, SPV between the Government and winning bidder not being encouraged • In PPP Projects, Service Fee to Vendors not allowed to be deducted at source • Risks in PPP projects due to wide variance in estimate of likely services and volumes to be delivered through the Project. • Service cost is dependent on the numerator ( Anticipated investment which has a fixed and variable component ) and denominator ( Anticipated number of services, Expected Transaction Volumes) – Under/Overestimation Risks • PPP Project not designed in a manner to enable re-negotiation in both cases of excessive profitability or losses to vendor, compared to Infrastructure Sector
  • 21. Broad issues related to e-Gov Procurement 1. Project Conceptualization and Development 2. Payment Model / Business Model 3. Scope of Work 4. Misprocurement 5. Tender publication 6. Bidding terms and conditions 7. Contract ( Terms and Conditions Document) 8. Pre Qualification 9. Pre-Bid meetings / Pre- Bid Clarifications 10. Tender Submission 11. Tender Evaluation 12. Post Tender Process 13. Third Party Audit 14. Project Execution 15. Post Implementation 16. PPP Projects 17. Consultant Issues 18. Dispute Resolution 19. Other Issues Go Back to Summary of Responses Slide
  • 22. Preliminary Recommendations • Rationalize Eligibility Criteria Norms across different category, size of eGov Projects – Enable level playing field • Model RFPs, Contracts, MSA for different Category of Projects o To be prepared by a joint Government-Industry Team (include Reps from Banking Sector, NISG, Consultants) o Review by a Panel including DIT, Department of Expenditure, MoF o Customize these for state projects, and drive uniformity o SLAs should incorporate SLA and events of default for both Vendor & Govt/Govt Agencies o Incorporate Best practices of Model Documents Published by Planning Commission for Infrastructure Sector PPP o Toolkits for PPP, BOOT Projects and Business Model options to guide departments 6-Oct-10 22
  • 23. Preliminary Recommendations • Similar to Process followed for Pre-Bid Meetings, standardize on Suppliers debriefing, post vendor selection • Initiate a practice of sharing techno-commercial evaluation scores • Project Governance Structure Publish a Model for different category of projects • Resourcing & Skills Profile across Lifecycle stages • Consult Enterprise CIOs, Industry and Banking PSUs • Decide a Dispute Resolution & Arbitration Guidelines • Panel of retired officers from Government and Academia, knowledgeable with IT Projects Execution • Alternative Dispute Resolution mechanism on lines of procurement Ombudsman of Canada • Centralized digital repository of all Information assets of Bids, Projects – on a secure Govt Network • RFPS, Pre-Bid Queries, Bid Amendments, Contracts, MSAs • Project Reviews, Audit Reports, Impact Assessment Reports • Vendor defaults/force majeure Situations 6-Oct-10 23
  • 24. Industry Actionables • eGov Functional/Domain Expertise • eGov Orientation/Functional Skills Development Programs • Project Estimation Rigor and Bid Review Process • Do we need leadership attention ? • CSC Bids have become a negative showcase for, NeGP, Outsourcing, PPP • Several states going through long drawn litigation or rebids • Initiate Impact Assessment of Projects Executed • Success Stories, Case Studies • Learnings from Failed projects 6-Oct-10 24