SlideShare uma empresa Scribd logo
1 de 88
Operations Management Chapter 14 –  Material Requirements  Planning (MRP) and ERP PowerPoint presentation to accompany  Heizer/Render  Principles of Operations Management, 7e Operations Management, 9e
Outline ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Outline – Continued ,[object Object],[object Object],[object Object],[object Object],[object Object]
Outline – Continued ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Outline – Continued ,[object Object],[object Object],[object Object]
Learning Objectives ,[object Object],[object Object],[object Object],[object Object],[object Object]
Learning Objectives ,[object Object],[object Object],[object Object],[object Object]
Wheeled Coach ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Wheeled Coach ,[object Object],[object Object],[object Object],[object Object],[object Object]
Benefits of MRP ,[object Object],[object Object],[object Object],[object Object]
Dependent Demand ,[object Object],[object Object],[object Object],[object Object]
Dependent Demand ,[object Object],[object Object],[object Object],[object Object],[object Object],Effective use of dependent demand inventory models requires the following
Master Production Schedule (MPS) ,[object Object],[object Object],[object Object],[object Object],[object Object]
Master Production Schedule (MPS) ,[object Object],[object Object],[object Object],[object Object],[object Object]
The Planning Process Figure 14.1 Change production plan? Master production schedule Management Return on investment Capital Engineering Design completion Aggregate production plan Procurement Supplier performance Human resources Manpower planning Production Capacity Inventory Marketing Customer demand Finance Cash flow
The Planning Process Figure 14.1 Is capacity plan being met? Is execution meeting the plan? Change master production schedule? Change capacity? Change requirements? No Execute  material plans Execute capacity plans Yes Realistic? Capacity requirements plan Material requirements plan Master production schedule
Aggregate  Production Plan Figure 14.2 Months January February Aggregate Production Plan 1,500 1,200 (Shows the total quantity of amplifiers) Weeks 1 2 3 4 5 6 7 8 Master Production Schedule (Shows the specific type and quantity of amplifier to be produced 240-watt amplifier 100 100 100 100 150-watt amplifier 500 500 450 450 75-watt amplifier 300 100
Master Production Schedule (MPS) ,[object Object],[object Object],[object Object],Can be expressed in any of the following terms:
Focus for Different  Process Strategies Figure 14.3 Stock to Forecast (Product Focus) Schedule finished product Assemble to Order or Forecast (Repetitive) Schedule modules Make to Order (Process Focus) Schedule orders Examples: Print shop Motorcycles Steel, Beer, Bread Machine shop Autos, TVs Lightbulbs Fine-dining restaurant Fast-food restaurant Paper Typical focus of the master production schedule Number of end items Number of inputs
MPS Examples Table 14.1 For Nancy’s Specialty Foods Gross Requirements for Crabmeat Quiche Gross Requirements for Spinach Quiche Day 6 7 8 9 10 11 12 13 14 and so on Amount 50 100 47 60 110 75 Day 7 8 9 10 11 12 13 14 15 16 and so on Amount 100 200 150 60 75 100
Bills of Material ,[object Object],[object Object],[object Object],[object Object]
BOM Example B (2)   Std. 12” Speaker kit C (3) Std. 12” Speaker kit w/ amp-booster 1 E (2) E (2) F (2) Packing box and installation kit of wire, bolts, and screws Std. 12” Speaker booster assembly 2 D (2) 12” Speaker D (2) 12” Speaker G (1) Amp-booster 3 Product structure for “Awesome”  ( A ) A Level 0
BOM Example Part B: 2  x number of As  = (2)(50) = 100 Part C: 3  x number of As  = (3)(50) = 150 Part D: 2  x number of Bs    + 2  x number of Fs  = (2)(100) + (2)(300) = 800 Part E: 2  x number of Bs    + 2  x number of Cs  = (2)(100) + (2)(150) = 500 Part F: 2  x number of Cs  = (2)(150) = 300 Part G: 1  x number of Fs  = (1)(300) = 300 B (2)   Std. 12” Speaker kit C (3) Std. 12” Speaker kit w/ amp-booster 1 E (2) E (2) F (2) Packing box and installation kit of wire, bolts, and screws Std. 12” Speaker booster assembly 2 D (2) 12” Speaker D (2) 12” Speaker G (1) Amp-booster 3 Product structure for “Awesome”  ( A ) A Level 0
Bills of Material ,[object Object],[object Object],[object Object]
Bills of Material ,[object Object],[object Object],[object Object],[object Object]
Bills of Material ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Accurate Records ,[object Object],[object Object],[object Object]
Lead Times ,[object Object],[object Object],[object Object]
Time-Phased Product Structure Figure 14.4 | | | | | | | | 1 2 3 4 5 6 7 8 Time in weeks F 2 weeks 3 weeks 1 week A 2 weeks 1 week D E 2 weeks D G 1 week 1 week 2 weeks to produce B C E Start production of D Must have D and E completed here so production can begin on B
MRP Structure Figure 14.5 Output Reports MRP by period report MRP by date report Planned order report Purchase advice Exception reports Order early or late or not needed Order quantity too small or too large Data Files Purchasing data BOM Lead times (Item master file) Inventory data Master production schedule Material requirement planning programs (computer and software)
Determining Gross Requirements ,[object Object],[object Object],[object Object]
Determining Gross Requirements ,[object Object],[object Object],[object Object]
Determining Gross Requirements ,[object Object],[object Object],[object Object]
Gross Requirements Plan Table 14.3 Week ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Net Requirements Plan
Net Requirements Plan
Determining Net Requirements ,[object Object],[object Object],[object Object]
Determining Net Requirements ,[object Object],[object Object],[object Object],[object Object]
Determining Net Requirements ,[object Object],[object Object],[object Object]
Net Requirements Plan The logic of net requirements Available inventory Net requirements On hand Scheduled receipts + – = Total requirements Gross requirements Allocations +
Gross Requirements Schedule Figure 14.6 A B C 5 6 7 8 9 10 11 40 50 15 Lead time = 4 for A Master schedule for A S B C 12 13 8 9 10 11 20 30 40 Lead time = 6 for S Master schedule for S 1 2 3 10 10 Master schedule for  B sold directly Periods Therefore, these are the gross requirements for B Gross requirements: B 10 40 50 20 40+10 15+30 =50 =45 1 2 3 4 5 6 7 8 Periods
MRP Planning Sheet Figure 14.7
Safety Stock ,[object Object],[object Object],[object Object],[object Object]
MRP Management ,[object Object],[object Object],[object Object],[object Object],[object Object]
MRP and JIT ,[object Object],[object Object],[object Object]
Finite Capacity Scheduling ,[object Object],[object Object],[object Object]
Small Bucket Approach ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Balanced Flow ,[object Object],[object Object],[object Object]
Supermarket ,[object Object],[object Object],[object Object],[object Object]
Lot-Sizing Techniques ,[object Object],[object Object],[object Object],[object Object],[object Object]
Lot-Sizing Techniques ,[object Object],[object Object],[object Object],[object Object]
Lot-for-Lot Example Holding cost =  $1 /week; Setup cost =  $100;  Lead time =  1  week 55 30 30 40 10 40 30 Planned order releases 55 30 30 40 10 40 30 Planned order receipts 55 30 0 30 40 10 0 40 30 0 Net requirements 0 0 0 0 0 0 0 0 0 35 35 Projected on hand Scheduled receipts 55 30 0 30 40 10 0 40 30 35 Gross requirements 10 9 8 7 6 5 4 3 2 1
Lot-for-Lot Example Holding cost =  $1 /week; Setup cost =  $100;  Lead time =  1  week No on-hand inventory is carried through the system Total holding cost  = $0 There are seven setups for this item in this plan Total setup cost  = 7 x $100 = $700 55 30 30 40 10 40 30 Planned order releases 55 30 30 40 10 40 30 Planned order receipts 55 30 0 30 40 10 0 40 30 0 Net requirements 0 0 0 0 0 0 0 0 0 35 35 Projected on hand Scheduled receipts 55 30 0 30 40 10 0 40 30 35 Gross requirements 10 9 8 7 6 5 4 3 2 1
EOQ Lot Size Example Holding cost =  $1 /week; Setup cost =  $100;  Lead time =  1  week Average weekly gross requirements  =  27;  EOQ  = 73  units 73 73 73 73 Planned order releases 73 73 73 73 Planned order receipts 16 0 0 4 0 7 0 0 30 0 Net requirements 39 69 69 26 66 3 3 43 0 35 35 Projected on hand Scheduled receipts 55 30 0 30 40 10 0 40 30 35 Gross requirements 10 9 8 7 6 5 4 3 2 1
EOQ Lot Size Example Holding cost =  $1 /week; Setup cost =  $100;  Lead time =  1  week Average weekly gross requirements  =  27;  EOQ  = 73  units Annual demand  = 1,404 Total cost = setup cost + holding cost Total cost  = (1,404 / 73)  x  $100 + (73 / 2)  x  ($1  x  52  weeks ) Total cost  = $3,798 Cost for  10  weeks  = $3,798  x  (10  weeks/ 52  weeks ) = $730 73 73 73 73 Planned order releases 73 73 73 73 Planned order receipts 16 0 0 4 0 7 0 0 30 0 Net requirements 0 0 0 0 0 0 0 0 0 35 35 Projected on hand Scheduled receipts 55 30 0 30 40 10 0 40 30 35 Gross requirements 10 9 8 7 6 5 4 3 2 1
PPB Example Holding cost =  $1 /week; Setup cost =  $100;  Lead time =  1  week EPP  = 100  units Planned order releases Planned order receipts Net requirements 35 Projected on hand Scheduled receipts 55 30 0 30 40 10 0 40 30 35 Gross requirements 10 9 8 7 6 5 4 3 2 1
PPB Example Holding cost =  $1 /week; Setup cost =  $100; EPP  = 100  units Planned order releases Planned order receipts Net requirements 35 Projected on hand Scheduled receipts 55 30 0 30 40 10 0 40 30 35 Gross requirements 10 9 8 7 6 5 4 3 2 1 2 30 0 2, 3 70 40 = 40 x 1 2, 3, 4 70 40 2, 3, 4, 5 80 70 = 40 x 1 + 10 x 3 100 70 170 2, 3, 4, 5, 6 120 230 = 40 x 1 + 10 x 3   + 40 x 4 + = Combine periods 2 - 5 as this results in the Part Period closest to the EPP Combine periods 6 - 9 as this results in the Part Period closest to the EPP 6 40 0 6, 7 70 30 = 30 x 1 6, 7, 8 70 30 = 30 x 1 + 0 x 2 6, 7, 8, 9 100 120 = 30 x 1 + 30 x 3 100 120 220 + = 10 55 0 100 0 100 Total cost 300 190 490 + = + = Trial Lot Size Periods (cumulative net Costs Combined requirements) Part Periods Setup Holding Total
PPB Example Holding cost =  $1 /week; Setup cost =  $100;  Lead time =  1  week EPP  = 100  units 55 100 80 Planned order releases 55 100 80 Planned order receipts 55 0 0 0 40 0 0 0 30 0 Net requirements 0 30 30 60 0 10 10 50 0 35 35 Projected on hand Scheduled receipts 55 30 0 30 40 10 0 40 30 35 Gross requirements 10 9 8 7 6 5 4 3 2 1
Lot-Sizing Summary For these three examples Wagner-Whitin would have yielded a plan with a total cost of  $455 Lot-for-lot $700 EOQ $730 PPB $490
Lot-Sizing Summary ,[object Object],[object Object],[object Object]
Lot-Sizing Summary ,[object Object],[object Object],[object Object]
Extensions of MRP ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Material Requirements Planning II ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Material Resource Planning Table 14.4 Week 5 6 7 8 ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Closed-Loop MRP System Figure 14.8
Closed-Loop MRP System Figure 14.8 Capacity Planning Resource planning First cut capacity No Capacity requirements  (detailed) Yes Material requirements  (detailed) Priority Planning Desired  master production schedule Realistic? Production plan Planning
Closed-Loop MRP System Figure 14.8 Capacity Control (work center throughput) Priority Control (detailed scheduling) Execution Yes Execute the plan No No Input/output report Is average capacity adequate ? Dispatch list Is specific capacity adequate ?
Resource Requirements Profile Figure 14.9 Lot 1 Lot 2 Lot 4 Lot 7 Lot 8 Lot 3 Lot 5 Lot 10 Lot 13 Lot 9 Lot 12 Lot 14 Lot 16 Lot 6 Lot 15 Lot 11 Available capacity Capacity exceeded in periods 4 & 6 Lot 1 Lot 2 Lot 4 Lot 7 Lot 8 Lot 3 Lot 5 Lot 10 Lot 13 Lot 9 Lot 12 Lot 14 Lot 16 Lot 6 Lot 15 Lot 11 Available capacity Lot 6 “split” Lot 11 moved 200  – 150  – 100  – 50  – – 1 2 3 4 5 6 7 8 Period (a) Standard labor hours 200  – 150  – 100  – 50  – – 1 2 3 4 5 6 7 8 Period (b) Standard labor hours
Resource Requirements Profile It is also possible to split lots 6 and 11 and move them earlier in the schedule. This would avoid any potential problems with late orders but would increase inventory holding cost. Figure 14.9 Lot 1 Lot 2 Lot 4 Lot 7 Lot 8 Lot 3 Lot 5 Lot 10 Lot 13 Lot 9 Lot 12 Lot 14 Lot 16 Lot 6 Lot 15 Lot 11 Available capacity Capacity exceeded in periods 4 & 6 Lot 1 Lot 2 Lot 4 Lot 7 Lot 8 Lot 3 Lot 5 Lot 10 Lot 13 Lot 9 Lot 12 Lot 14 Lot 16 Lot 6 Lot 15 Lot 11 Available capacity Lot 6 “split” Lot 11 moved 200  – 150  – 100  – 50  – – 1 2 3 4 5 6 7 8 Period (a) Standard labor hours 200  – 150  – 100  – 50  – – 1 2 3 4 5 6 7 8 Period (b) Standard labor hours
Smoothing Tactics ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
MRP in Services ,[object Object],[object Object],[object Object],[object Object],[object Object]
MRP in Services (a) PRODUCT STRUCTURE TREE Figure 14.10 Uncooked linguini #30004 Sauce #30006 Veal #30005 Chef; Work Center #1 Helper one; Work Center #2 Asst. Chef; Work Center #3 Cooked linguini #20002 Spinach #20004 Prepared veal and sauce #20003 Veal picante #10001
MRP in Services (b) BILL OF MATERIALS 0.80 Serving 1 Sauce 30006 2.15 Serving 1 Veal 30005 — Pound 0.5 Uncooked linguini 30004 0.94 Bag 0.1 Spinach 20004 — Serving 1 Prepared veal and sauce 20003 — Serving 1 Cooked linguini 20002 — Serving 1 Veal picante 10001 Unit cost Unit of Measure Quantity Description Part Number
MRP in Services (c) BILL OF LABOR FOR VEAL PICANTE .0500 .0125 Assistant Chef Cook veal  and sauce 3 .0022 .0005 Helper one Cook linguini 2 .0041 .0069 Chef Assemble dish 1 Run Time Setup Time Labor Type Operation Work Center Hours Labor
Distribution Resource Planning (DRP) Using dependent demand techniques through the supply chain ,[object Object],[object Object],[object Object],[object Object]
Enterprise Resource Planning (ERP) ,[object Object],[object Object],[object Object],[object Object],[object Object]
Enterprise Resource Planning (ERP) ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
ERP and MRP Figure 14.11
ERP and MRP Figure 14.11 Customer Relationship Management Invoicing Shipping Distributors, retailers, and end users Sales Order (order entry, product configuration, sales management)
ERP and MRP Figure 14.11 Table 13.6 Bills of Material Work Orders Purchasing and Lead Times Routings and Lead Times Master Production Schedule Inventory Management MRP
ERP and MRP Figure 14.11 Supply Chain Management Vendor Communication (schedules, EDI, advanced shipping notice, e-commerce, etc.)
ERP and MRP Figure 14.11 Table 13.6 Finance/ Accounting General Ledger Accounts Receivable Payroll Accounts Payable
Enterprise Resource Planning (ERP) ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Enterprise Resource Planning (ERP) ,[object Object],[object Object],[object Object],[object Object]
Advantages  of ERP Systems ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Disadvantages  of ERP Systems ,[object Object],[object Object],[object Object],[object Object],[object Object]
SAP’s ERP Modules Figure 14.12 Cash to Cash Covers all financial related activity: Accounts receivable General ledger Cash management Accounts payable Treasury Asset management Dock to Dispatch Covers internal inventory management: Warehousing Forecasting Physical inventory Distribution planning Replenishment planning Material handling Promote to Deliver Covers front-end   customer-oriented    activities: Marketing Quote and order    processing Transportation Documentation and    labeling After sales service Warranty and    guarantees Procure to Pay Covers sourcing  activities: Vendor sourcing Purchase    requisitioning Purchase ordering Purchase contracts Inbound logistics Supplier invoicing/   matching Supplier payment/   settlement Supplier    performance Design to Manufacture Covers internal production activities: Design  Shop floor   engineering    reporting Production  Contract/project   engineering    management Plant  Subcontractor   maintenance    management Recruit to Hire Covers all HR- and payroll-oriented   activity: Time and attendance Payroll Travel and expenses
ERP in the Service Sector ,[object Object],[object Object],[object Object]

Mais conteúdo relacionado

Mais procurados

Mais procurados (20)

MRP and ERP
MRP and ERPMRP and ERP
MRP and ERP
 
Heizer 05
Heizer 05Heizer 05
Heizer 05
 
Capacity planning
Capacity planningCapacity planning
Capacity planning
 
Heizer 11
Heizer 11Heizer 11
Heizer 11
 
Heizer 03
Heizer 03Heizer 03
Heizer 03
 
Operational strategy
Operational strategyOperational strategy
Operational strategy
 
Heizer 10
Heizer 10Heizer 10
Heizer 10
 
Heizer om10 ch11_r
Heizer om10 ch11_rHeizer om10 ch11_r
Heizer om10 ch11_r
 
Heizer 06
Heizer 06Heizer 06
Heizer 06
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planning
 
Heizer 02
Heizer 02Heizer 02
Heizer 02
 
Layout strategies
Layout strategiesLayout strategies
Layout strategies
 
Capacity planning ppt
Capacity planning pptCapacity planning ppt
Capacity planning ppt
 
Process Strategy
Process StrategyProcess Strategy
Process Strategy
 
CAPACITY PLANNING
CAPACITY PLANNINGCAPACITY PLANNING
CAPACITY PLANNING
 
Capacity planning
Capacity planningCapacity planning
Capacity planning
 
What is strategic fit
What is strategic fitWhat is strategic fit
What is strategic fit
 
Latest Trends in Operation Management
Latest Trends in Operation ManagementLatest Trends in Operation Management
Latest Trends in Operation Management
 
13 supply chain planning and control_Operations Management
13 supply chain planning and control_Operations Management13 supply chain planning and control_Operations Management
13 supply chain planning and control_Operations Management
 
Bullwhip effect ppt
Bullwhip effect pptBullwhip effect ppt
Bullwhip effect ppt
 

Semelhante a MRP and ERP Operations Management

Session 5
Session 5Session 5
Session 5thangv
 
Material requirements planning & erp ppt @ bec doms
Material requirements planning & erp  ppt @ bec domsMaterial requirements planning & erp  ppt @ bec doms
Material requirements planning & erp ppt @ bec domsBabasab Patil
 
Scps -materials_requirements_planning
Scps  -materials_requirements_planningScps  -materials_requirements_planning
Scps -materials_requirements_planningDaniel Romero
 
Operations Management Material Requirements Planning (MRP)
Operations ManagementMaterial Requirements Planning (MRP)Operations ManagementMaterial Requirements Planning (MRP)
Operations Management Material Requirements Planning (MRP)Mostafa Ewees
 
Module11. Material requirement plan..pdf
Module11. Material requirement plan..pdfModule11. Material requirement plan..pdf
Module11. Material requirement plan..pdfJOHN PAUL ROBERTO
 
MATERIAL REQUIREMENTS PLANNING (MRP)
MATERIAL REQUIREMENTS PLANNING (MRP)MATERIAL REQUIREMENTS PLANNING (MRP)
MATERIAL REQUIREMENTS PLANNING (MRP)Dipesh Pandey
 
Material Resource Planning
Material Resource PlanningMaterial Resource Planning
Material Resource PlanningBiswajit Ghosh
 
Material Requisite Planning
Material Requisite PlanningMaterial Requisite Planning
Material Requisite Planningajithsrc
 
Kcf bp-project-module
Kcf bp-project-moduleKcf bp-project-module
Kcf bp-project-moduleEsh_Crystal
 
MASTER PRODUCTION SCHEDULE (MPS).pptx
MASTER PRODUCTION SCHEDULE (MPS).pptxMASTER PRODUCTION SCHEDULE (MPS).pptx
MASTER PRODUCTION SCHEDULE (MPS).pptxGulaHangus
 
Inventory Management And Mrp Erp
Inventory Management And Mrp   ErpInventory Management And Mrp   Erp
Inventory Management And Mrp ErpJoanmaines
 
Material requirement planning (mrp1)
Material requirement planning (mrp1)Material requirement planning (mrp1)
Material requirement planning (mrp1)saleh asgari
 

Semelhante a MRP and ERP Operations Management (20)

Session 5
Session 5Session 5
Session 5
 
Chapter 5_OM
Chapter 5_OMChapter 5_OM
Chapter 5_OM
 
Material requirements planning & erp ppt @ bec doms
Material requirements planning & erp  ppt @ bec domsMaterial requirements planning & erp  ppt @ bec doms
Material requirements planning & erp ppt @ bec doms
 
Scps -materials_requirements_planning
Scps  -materials_requirements_planningScps  -materials_requirements_planning
Scps -materials_requirements_planning
 
Operations Management Material Requirements Planning (MRP)
Operations ManagementMaterial Requirements Planning (MRP)Operations ManagementMaterial Requirements Planning (MRP)
Operations Management Material Requirements Planning (MRP)
 
Mrpmep
MrpmepMrpmep
Mrpmep
 
Module11. Material requirement plan..pdf
Module11. Material requirement plan..pdfModule11. Material requirement plan..pdf
Module11. Material requirement plan..pdf
 
MATERIAL REQUIREMENTS PLANNING (MRP)
MATERIAL REQUIREMENTS PLANNING (MRP)MATERIAL REQUIREMENTS PLANNING (MRP)
MATERIAL REQUIREMENTS PLANNING (MRP)
 
Material Resource Planning
Material Resource PlanningMaterial Resource Planning
Material Resource Planning
 
Mrp 1
Mrp 1Mrp 1
Mrp 1
 
Material requirement planning
Material requirement planningMaterial requirement planning
Material requirement planning
 
Operations MRP
Operations MRPOperations MRP
Operations MRP
 
Material Requisite Planning
Material Requisite PlanningMaterial Requisite Planning
Material Requisite Planning
 
Kcf bp-project-module
Kcf bp-project-moduleKcf bp-project-module
Kcf bp-project-module
 
MASTER PRODUCTION SCHEDULE (MPS).pptx
MASTER PRODUCTION SCHEDULE (MPS).pptxMASTER PRODUCTION SCHEDULE (MPS).pptx
MASTER PRODUCTION SCHEDULE (MPS).pptx
 
Mrp
Mrp Mrp
Mrp
 
MRP MPS.ppt
MRP MPS.pptMRP MPS.ppt
MRP MPS.ppt
 
SAP Production Planning
SAP Production PlanningSAP Production Planning
SAP Production Planning
 
Inventory Management And Mrp Erp
Inventory Management And Mrp   ErpInventory Management And Mrp   Erp
Inventory Management And Mrp Erp
 
Material requirement planning (mrp1)
Material requirement planning (mrp1)Material requirement planning (mrp1)
Material requirement planning (mrp1)
 

Mais de ajithsrc

Business Plan On Retail Mall
Business Plan On Retail MallBusiness Plan On Retail Mall
Business Plan On Retail Mallajithsrc
 
New Ethics 5
New Ethics 5New Ethics 5
New Ethics 5ajithsrc
 
New Ethics 4
New Ethics 4New Ethics 4
New Ethics 4ajithsrc
 
Valuation Of S Ecurities
Valuation Of S EcuritiesValuation Of S Ecurities
Valuation Of S Ecuritiesajithsrc
 
Ajith Resume
Ajith ResumeAjith Resume
Ajith Resumeajithsrc
 
Operations Research
Operations ResearchOperations Research
Operations Researchajithsrc
 
Evolution Of Operations Management
Evolution Of Operations ManagementEvolution Of Operations Management
Evolution Of Operations Managementajithsrc
 
Textile Industry
Textile IndustryTextile Industry
Textile Industryajithsrc
 
Syndicate 1 Tqm
Syndicate 1 TqmSyndicate 1 Tqm
Syndicate 1 Tqmajithsrc
 
Supply Chain Mgmt Jit
Supply Chain Mgmt JitSupply Chain Mgmt Jit
Supply Chain Mgmt Jitajithsrc
 
Stevenson9e Ch04
Stevenson9e Ch04Stevenson9e Ch04
Stevenson9e Ch04ajithsrc
 

Mais de ajithsrc (20)

Business Plan On Retail Mall
Business Plan On Retail MallBusiness Plan On Retail Mall
Business Plan On Retail Mall
 
Ethics
EthicsEthics
Ethics
 
Ethics
EthicsEthics
Ethics
 
Ethics
EthicsEthics
Ethics
 
New Ethics 5
New Ethics 5New Ethics 5
New Ethics 5
 
New Ethics 4
New Ethics 4New Ethics 4
New Ethics 4
 
Valuation Of S Ecurities
Valuation Of S EcuritiesValuation Of S Ecurities
Valuation Of S Ecurities
 
Transport
TransportTransport
Transport
 
Inflation
InflationInflation
Inflation
 
Auto
AutoAuto
Auto
 
Ajith Resume
Ajith ResumeAjith Resume
Ajith Resume
 
Ksrtc
KsrtcKsrtc
Ksrtc
 
Operations Research
Operations ResearchOperations Research
Operations Research
 
Evolution Of Operations Management
Evolution Of Operations ManagementEvolution Of Operations Management
Evolution Of Operations Management
 
Tqm Tool2
Tqm Tool2Tqm Tool2
Tqm Tool2
 
Tqm Tool1
Tqm Tool1Tqm Tool1
Tqm Tool1
 
Textile Industry
Textile IndustryTextile Industry
Textile Industry
 
Syndicate 1 Tqm
Syndicate 1 TqmSyndicate 1 Tqm
Syndicate 1 Tqm
 
Supply Chain Mgmt Jit
Supply Chain Mgmt JitSupply Chain Mgmt Jit
Supply Chain Mgmt Jit
 
Stevenson9e Ch04
Stevenson9e Ch04Stevenson9e Ch04
Stevenson9e Ch04
 

MRP and ERP Operations Management

  • 1. Operations Management Chapter 14 – Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer/Render Principles of Operations Management, 7e Operations Management, 9e
  • 2.
  • 3.
  • 4.
  • 5.
  • 6.
  • 7.
  • 8.
  • 9.
  • 10.
  • 11.
  • 12.
  • 13.
  • 14.
  • 15. The Planning Process Figure 14.1 Change production plan? Master production schedule Management Return on investment Capital Engineering Design completion Aggregate production plan Procurement Supplier performance Human resources Manpower planning Production Capacity Inventory Marketing Customer demand Finance Cash flow
  • 16. The Planning Process Figure 14.1 Is capacity plan being met? Is execution meeting the plan? Change master production schedule? Change capacity? Change requirements? No Execute material plans Execute capacity plans Yes Realistic? Capacity requirements plan Material requirements plan Master production schedule
  • 17. Aggregate Production Plan Figure 14.2 Months January February Aggregate Production Plan 1,500 1,200 (Shows the total quantity of amplifiers) Weeks 1 2 3 4 5 6 7 8 Master Production Schedule (Shows the specific type and quantity of amplifier to be produced 240-watt amplifier 100 100 100 100 150-watt amplifier 500 500 450 450 75-watt amplifier 300 100
  • 18.
  • 19. Focus for Different Process Strategies Figure 14.3 Stock to Forecast (Product Focus) Schedule finished product Assemble to Order or Forecast (Repetitive) Schedule modules Make to Order (Process Focus) Schedule orders Examples: Print shop Motorcycles Steel, Beer, Bread Machine shop Autos, TVs Lightbulbs Fine-dining restaurant Fast-food restaurant Paper Typical focus of the master production schedule Number of end items Number of inputs
  • 20. MPS Examples Table 14.1 For Nancy’s Specialty Foods Gross Requirements for Crabmeat Quiche Gross Requirements for Spinach Quiche Day 6 7 8 9 10 11 12 13 14 and so on Amount 50 100 47 60 110 75 Day 7 8 9 10 11 12 13 14 15 16 and so on Amount 100 200 150 60 75 100
  • 21.
  • 22. BOM Example B (2) Std. 12” Speaker kit C (3) Std. 12” Speaker kit w/ amp-booster 1 E (2) E (2) F (2) Packing box and installation kit of wire, bolts, and screws Std. 12” Speaker booster assembly 2 D (2) 12” Speaker D (2) 12” Speaker G (1) Amp-booster 3 Product structure for “Awesome” ( A ) A Level 0
  • 23. BOM Example Part B: 2 x number of As = (2)(50) = 100 Part C: 3 x number of As = (3)(50) = 150 Part D: 2 x number of Bs + 2 x number of Fs = (2)(100) + (2)(300) = 800 Part E: 2 x number of Bs + 2 x number of Cs = (2)(100) + (2)(150) = 500 Part F: 2 x number of Cs = (2)(150) = 300 Part G: 1 x number of Fs = (1)(300) = 300 B (2) Std. 12” Speaker kit C (3) Std. 12” Speaker kit w/ amp-booster 1 E (2) E (2) F (2) Packing box and installation kit of wire, bolts, and screws Std. 12” Speaker booster assembly 2 D (2) 12” Speaker D (2) 12” Speaker G (1) Amp-booster 3 Product structure for “Awesome” ( A ) A Level 0
  • 24.
  • 25.
  • 26.
  • 27.
  • 28.
  • 29. Time-Phased Product Structure Figure 14.4 | | | | | | | | 1 2 3 4 5 6 7 8 Time in weeks F 2 weeks 3 weeks 1 week A 2 weeks 1 week D E 2 weeks D G 1 week 1 week 2 weeks to produce B C E Start production of D Must have D and E completed here so production can begin on B
  • 30. MRP Structure Figure 14.5 Output Reports MRP by period report MRP by date report Planned order report Purchase advice Exception reports Order early or late or not needed Order quantity too small or too large Data Files Purchasing data BOM Lead times (Item master file) Inventory data Master production schedule Material requirement planning programs (computer and software)
  • 31.
  • 32.
  • 33.
  • 34.
  • 37.
  • 38.
  • 39.
  • 40. Net Requirements Plan The logic of net requirements Available inventory Net requirements On hand Scheduled receipts + – = Total requirements Gross requirements Allocations +
  • 41. Gross Requirements Schedule Figure 14.6 A B C 5 6 7 8 9 10 11 40 50 15 Lead time = 4 for A Master schedule for A S B C 12 13 8 9 10 11 20 30 40 Lead time = 6 for S Master schedule for S 1 2 3 10 10 Master schedule for B sold directly Periods Therefore, these are the gross requirements for B Gross requirements: B 10 40 50 20 40+10 15+30 =50 =45 1 2 3 4 5 6 7 8 Periods
  • 42. MRP Planning Sheet Figure 14.7
  • 43.
  • 44.
  • 45.
  • 46.
  • 47.
  • 48.
  • 49.
  • 50.
  • 51.
  • 52. Lot-for-Lot Example Holding cost = $1 /week; Setup cost = $100; Lead time = 1 week 55 30 30 40 10 40 30 Planned order releases 55 30 30 40 10 40 30 Planned order receipts 55 30 0 30 40 10 0 40 30 0 Net requirements 0 0 0 0 0 0 0 0 0 35 35 Projected on hand Scheduled receipts 55 30 0 30 40 10 0 40 30 35 Gross requirements 10 9 8 7 6 5 4 3 2 1
  • 53. Lot-for-Lot Example Holding cost = $1 /week; Setup cost = $100; Lead time = 1 week No on-hand inventory is carried through the system Total holding cost = $0 There are seven setups for this item in this plan Total setup cost = 7 x $100 = $700 55 30 30 40 10 40 30 Planned order releases 55 30 30 40 10 40 30 Planned order receipts 55 30 0 30 40 10 0 40 30 0 Net requirements 0 0 0 0 0 0 0 0 0 35 35 Projected on hand Scheduled receipts 55 30 0 30 40 10 0 40 30 35 Gross requirements 10 9 8 7 6 5 4 3 2 1
  • 54. EOQ Lot Size Example Holding cost = $1 /week; Setup cost = $100; Lead time = 1 week Average weekly gross requirements = 27; EOQ = 73 units 73 73 73 73 Planned order releases 73 73 73 73 Planned order receipts 16 0 0 4 0 7 0 0 30 0 Net requirements 39 69 69 26 66 3 3 43 0 35 35 Projected on hand Scheduled receipts 55 30 0 30 40 10 0 40 30 35 Gross requirements 10 9 8 7 6 5 4 3 2 1
  • 55. EOQ Lot Size Example Holding cost = $1 /week; Setup cost = $100; Lead time = 1 week Average weekly gross requirements = 27; EOQ = 73 units Annual demand = 1,404 Total cost = setup cost + holding cost Total cost = (1,404 / 73) x $100 + (73 / 2) x ($1 x 52 weeks ) Total cost = $3,798 Cost for 10 weeks = $3,798 x (10 weeks/ 52 weeks ) = $730 73 73 73 73 Planned order releases 73 73 73 73 Planned order receipts 16 0 0 4 0 7 0 0 30 0 Net requirements 0 0 0 0 0 0 0 0 0 35 35 Projected on hand Scheduled receipts 55 30 0 30 40 10 0 40 30 35 Gross requirements 10 9 8 7 6 5 4 3 2 1
  • 56. PPB Example Holding cost = $1 /week; Setup cost = $100; Lead time = 1 week EPP = 100 units Planned order releases Planned order receipts Net requirements 35 Projected on hand Scheduled receipts 55 30 0 30 40 10 0 40 30 35 Gross requirements 10 9 8 7 6 5 4 3 2 1
  • 57. PPB Example Holding cost = $1 /week; Setup cost = $100; EPP = 100 units Planned order releases Planned order receipts Net requirements 35 Projected on hand Scheduled receipts 55 30 0 30 40 10 0 40 30 35 Gross requirements 10 9 8 7 6 5 4 3 2 1 2 30 0 2, 3 70 40 = 40 x 1 2, 3, 4 70 40 2, 3, 4, 5 80 70 = 40 x 1 + 10 x 3 100 70 170 2, 3, 4, 5, 6 120 230 = 40 x 1 + 10 x 3 + 40 x 4 + = Combine periods 2 - 5 as this results in the Part Period closest to the EPP Combine periods 6 - 9 as this results in the Part Period closest to the EPP 6 40 0 6, 7 70 30 = 30 x 1 6, 7, 8 70 30 = 30 x 1 + 0 x 2 6, 7, 8, 9 100 120 = 30 x 1 + 30 x 3 100 120 220 + = 10 55 0 100 0 100 Total cost 300 190 490 + = + = Trial Lot Size Periods (cumulative net Costs Combined requirements) Part Periods Setup Holding Total
  • 58. PPB Example Holding cost = $1 /week; Setup cost = $100; Lead time = 1 week EPP = 100 units 55 100 80 Planned order releases 55 100 80 Planned order receipts 55 0 0 0 40 0 0 0 30 0 Net requirements 0 30 30 60 0 10 10 50 0 35 35 Projected on hand Scheduled receipts 55 30 0 30 40 10 0 40 30 35 Gross requirements 10 9 8 7 6 5 4 3 2 1
  • 59. Lot-Sizing Summary For these three examples Wagner-Whitin would have yielded a plan with a total cost of $455 Lot-for-lot $700 EOQ $730 PPB $490
  • 60.
  • 61.
  • 62.
  • 63.
  • 64.
  • 65. Closed-Loop MRP System Figure 14.8
  • 66. Closed-Loop MRP System Figure 14.8 Capacity Planning Resource planning First cut capacity No Capacity requirements (detailed) Yes Material requirements (detailed) Priority Planning Desired master production schedule Realistic? Production plan Planning
  • 67. Closed-Loop MRP System Figure 14.8 Capacity Control (work center throughput) Priority Control (detailed scheduling) Execution Yes Execute the plan No No Input/output report Is average capacity adequate ? Dispatch list Is specific capacity adequate ?
  • 68. Resource Requirements Profile Figure 14.9 Lot 1 Lot 2 Lot 4 Lot 7 Lot 8 Lot 3 Lot 5 Lot 10 Lot 13 Lot 9 Lot 12 Lot 14 Lot 16 Lot 6 Lot 15 Lot 11 Available capacity Capacity exceeded in periods 4 & 6 Lot 1 Lot 2 Lot 4 Lot 7 Lot 8 Lot 3 Lot 5 Lot 10 Lot 13 Lot 9 Lot 12 Lot 14 Lot 16 Lot 6 Lot 15 Lot 11 Available capacity Lot 6 “split” Lot 11 moved 200 – 150 – 100 – 50 – – 1 2 3 4 5 6 7 8 Period (a) Standard labor hours 200 – 150 – 100 – 50 – – 1 2 3 4 5 6 7 8 Period (b) Standard labor hours
  • 69. Resource Requirements Profile It is also possible to split lots 6 and 11 and move them earlier in the schedule. This would avoid any potential problems with late orders but would increase inventory holding cost. Figure 14.9 Lot 1 Lot 2 Lot 4 Lot 7 Lot 8 Lot 3 Lot 5 Lot 10 Lot 13 Lot 9 Lot 12 Lot 14 Lot 16 Lot 6 Lot 15 Lot 11 Available capacity Capacity exceeded in periods 4 & 6 Lot 1 Lot 2 Lot 4 Lot 7 Lot 8 Lot 3 Lot 5 Lot 10 Lot 13 Lot 9 Lot 12 Lot 14 Lot 16 Lot 6 Lot 15 Lot 11 Available capacity Lot 6 “split” Lot 11 moved 200 – 150 – 100 – 50 – – 1 2 3 4 5 6 7 8 Period (a) Standard labor hours 200 – 150 – 100 – 50 – – 1 2 3 4 5 6 7 8 Period (b) Standard labor hours
  • 70.
  • 71.
  • 72. MRP in Services (a) PRODUCT STRUCTURE TREE Figure 14.10 Uncooked linguini #30004 Sauce #30006 Veal #30005 Chef; Work Center #1 Helper one; Work Center #2 Asst. Chef; Work Center #3 Cooked linguini #20002 Spinach #20004 Prepared veal and sauce #20003 Veal picante #10001
  • 73. MRP in Services (b) BILL OF MATERIALS 0.80 Serving 1 Sauce 30006 2.15 Serving 1 Veal 30005 — Pound 0.5 Uncooked linguini 30004 0.94 Bag 0.1 Spinach 20004 — Serving 1 Prepared veal and sauce 20003 — Serving 1 Cooked linguini 20002 — Serving 1 Veal picante 10001 Unit cost Unit of Measure Quantity Description Part Number
  • 74. MRP in Services (c) BILL OF LABOR FOR VEAL PICANTE .0500 .0125 Assistant Chef Cook veal and sauce 3 .0022 .0005 Helper one Cook linguini 2 .0041 .0069 Chef Assemble dish 1 Run Time Setup Time Labor Type Operation Work Center Hours Labor
  • 75.
  • 76.
  • 77.
  • 78. ERP and MRP Figure 14.11
  • 79. ERP and MRP Figure 14.11 Customer Relationship Management Invoicing Shipping Distributors, retailers, and end users Sales Order (order entry, product configuration, sales management)
  • 80. ERP and MRP Figure 14.11 Table 13.6 Bills of Material Work Orders Purchasing and Lead Times Routings and Lead Times Master Production Schedule Inventory Management MRP
  • 81. ERP and MRP Figure 14.11 Supply Chain Management Vendor Communication (schedules, EDI, advanced shipping notice, e-commerce, etc.)
  • 82. ERP and MRP Figure 14.11 Table 13.6 Finance/ Accounting General Ledger Accounts Receivable Payroll Accounts Payable
  • 83.
  • 84.
  • 85.
  • 86.
  • 87. SAP’s ERP Modules Figure 14.12 Cash to Cash Covers all financial related activity: Accounts receivable General ledger Cash management Accounts payable Treasury Asset management Dock to Dispatch Covers internal inventory management: Warehousing Forecasting Physical inventory Distribution planning Replenishment planning Material handling Promote to Deliver Covers front-end customer-oriented activities: Marketing Quote and order processing Transportation Documentation and labeling After sales service Warranty and guarantees Procure to Pay Covers sourcing activities: Vendor sourcing Purchase requisitioning Purchase ordering Purchase contracts Inbound logistics Supplier invoicing/ matching Supplier payment/ settlement Supplier performance Design to Manufacture Covers internal production activities: Design Shop floor engineering reporting Production Contract/project engineering management Plant Subcontractor maintenance management Recruit to Hire Covers all HR- and payroll-oriented activity: Time and attendance Payroll Travel and expenses
  • 88.