SlideShare uma empresa Scribd logo
1 de 1
Baixar para ler offline
Construction Period:
03/2003 –02/2005
Client:
Obajana Cement Factory,
Dangote Industries
Services:
Construction of process
and auxiliary buildings
for the cement plant plus
design and construction of
all infrastructure works
Cement Plant,
Obajana
In March 2003, Julius Berger Nigeria PLC
was awarded the contract for the civil works
and construction of process and auxiliary
buildings for a new cement factory. The plant
was to be located on a greenfield area of
350ha in Obajana, Kogi State.
Historically, a large percentage of Nigeria´s
demand for cement was covered through
imports. The construction of the Obajana
Cement Plant, with a maximum daily output
of 14,000 tons of high quality cement,
changed this situation and allowed the
importation of cement to be reduced
considerably.
Within a period of 24 months, two production
lines were completed by Julius Berger
Nigeria PLC including two 83m high raw mill
silos and four 60m high cement silos. The
work was carried out using pre-stressed
concrete and specially designed sliding
formwork.
All foundations, including bored pile
foundations for the silos, pre-heater, rotary
kiln and the ground slabs for several
departments of the two production lines and
as the foundation for the pre-crushers in the
quarry were part of Julius Berger Nigeria
PLC´s scope of work.
The design of the auxiliary buildings and
facilities such as the power plant, the water
storage tanks, the central control building
and twelve substations allowed for insitu
reinforced concrete using traditional
formwork methods.
An eight km long, elevated belt conveyor
was built from the quarry to the cement plant.
The foundation works as well as the pre-cast
Picture
were constructed by Julius Berger
Nigeria PLC.
The main quantities of work comprised
approx. 200,000cbm of reinforced
concrete and 36,000cbm of blinding
concrete; 25,000 tons of high tensile
steel; 240,000sqm of traditional and
84,100sqm of slip formwork.
All infrastructure works including
general earthworks and the construction
of roads and concrete paved areas, as
well as storm water drainage, were
designed and executed by Julius Berger
Nigeria PLC.
The project was handed over in
February 2005.

Mais conteúdo relacionado

Mais procurados

Concrete Mixer liner
Concrete Mixer linerConcrete Mixer liner
Concrete Mixer linerVenoth Kumar
 
Construction green breakfast - you don't have to be a hippy to build with hemp!
Construction green breakfast - you don't have to be a hippy to build with hemp!Construction green breakfast - you don't have to be a hippy to build with hemp!
Construction green breakfast - you don't have to be a hippy to build with hemp!Blake Morgan
 
PREFABRICATION BUILDING
PREFABRICATION BUILDINGPREFABRICATION BUILDING
PREFABRICATION BUILDINGsathish sak
 
Hemp Lime Concrete (HLC): A carbon-negative construction material
Hemp Lime Concrete (HLC): A carbon-negative construction materialHemp Lime Concrete (HLC): A carbon-negative construction material
Hemp Lime Concrete (HLC): A carbon-negative construction materialDidier Lesueur
 
Glass Fiber Reinforced Gypsum Panel use in Building Construction
Glass Fiber Reinforced Gypsum Panel use in Building ConstructionGlass Fiber Reinforced Gypsum Panel use in Building Construction
Glass Fiber Reinforced Gypsum Panel use in Building ConstructionGRD Journals
 
What are Highways Works, Street works, Road works and Diversionary Works
What are Highways Works, Street works, Road works and Diversionary WorksWhat are Highways Works, Street works, Road works and Diversionary Works
What are Highways Works, Street works, Road works and Diversionary WorksCarlo Gabriele Borri MACostE AMICE
 
Setting up a Ready-Mix Concrete Manufacturing Plant
Setting up a Ready-Mix Concrete Manufacturing PlantSetting up a Ready-Mix Concrete Manufacturing Plant
Setting up a Ready-Mix Concrete Manufacturing PlantAjjay Kumar Gupta
 
HC PRECAST SYSTEM's Technical Property
HC PRECAST SYSTEM's Technical PropertyHC PRECAST SYSTEM's Technical Property
HC PRECAST SYSTEM's Technical PropertyTeow Beng Hur
 
Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingDavid H Moloney
 
Construction methode ash yard
Construction methode   ash yardConstruction methode   ash yard
Construction methode ash yardranow
 
JAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyJAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyMike Bisland
 
Ready mix concrete
Ready mix concreteReady mix concrete
Ready mix concreteSahil Khan
 
Ready-Mix Concrete (RMC Plant)
Ready-Mix Concrete (RMC Plant)Ready-Mix Concrete (RMC Plant)
Ready-Mix Concrete (RMC Plant)Ajjay Kumar Gupta
 

Mais procurados (20)

Building system using GFRG panels
Building system using GFRG panels Building system using GFRG panels
Building system using GFRG panels
 
Concrete Mixer liner
Concrete Mixer linerConcrete Mixer liner
Concrete Mixer liner
 
attcofinal
attcofinalattcofinal
attcofinal
 
Construction green breakfast - you don't have to be a hippy to build with hemp!
Construction green breakfast - you don't have to be a hippy to build with hemp!Construction green breakfast - you don't have to be a hippy to build with hemp!
Construction green breakfast - you don't have to be a hippy to build with hemp!
 
PREFABRICATION BUILDING
PREFABRICATION BUILDINGPREFABRICATION BUILDING
PREFABRICATION BUILDING
 
Hemp Lime Concrete (HLC): A carbon-negative construction material
Hemp Lime Concrete (HLC): A carbon-negative construction materialHemp Lime Concrete (HLC): A carbon-negative construction material
Hemp Lime Concrete (HLC): A carbon-negative construction material
 
Gfrg
GfrgGfrg
Gfrg
 
Glass Fiber Reinforced Gypsum Panel use in Building Construction
Glass Fiber Reinforced Gypsum Panel use in Building ConstructionGlass Fiber Reinforced Gypsum Panel use in Building Construction
Glass Fiber Reinforced Gypsum Panel use in Building Construction
 
What are Highways Works, Street works, Road works and Diversionary Works
What are Highways Works, Street works, Road works and Diversionary WorksWhat are Highways Works, Street works, Road works and Diversionary Works
What are Highways Works, Street works, Road works and Diversionary Works
 
Ready mix concrete
Ready mix concreteReady mix concrete
Ready mix concrete
 
Setting up a Ready-Mix Concrete Manufacturing Plant
Setting up a Ready-Mix Concrete Manufacturing PlantSetting up a Ready-Mix Concrete Manufacturing Plant
Setting up a Ready-Mix Concrete Manufacturing Plant
 
HC PRECAST SYSTEM's Technical Property
HC PRECAST SYSTEM's Technical PropertyHC PRECAST SYSTEM's Technical Property
HC PRECAST SYSTEM's Technical Property
 
READY MIX CONCRETE
READY MIX CONCRETEREADY MIX CONCRETE
READY MIX CONCRETE
 
Ready Mix Concrete
Ready Mix ConcreteReady Mix Concrete
Ready Mix Concrete
 
Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise Building
 
Construction methode ash yard
Construction methode   ash yardConstruction methode   ash yard
Construction methode ash yard
 
JAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyJAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE Navy
 
Ready mix concrete
Ready mix concreteReady mix concrete
Ready mix concrete
 
Vertical roller grinding mill0601
Vertical roller grinding mill0601Vertical roller grinding mill0601
Vertical roller grinding mill0601
 
Ready-Mix Concrete (RMC Plant)
Ready-Mix Concrete (RMC Plant)Ready-Mix Concrete (RMC Plant)
Ready-Mix Concrete (RMC Plant)
 

Destaque

Lista reavaliação - 3º bimestre - 8º ano - 2015
Lista   reavaliação - 3º bimestre - 8º ano - 2015Lista   reavaliação - 3º bimestre - 8º ano - 2015
Lista reavaliação - 3º bimestre - 8º ano - 2015proffelipemat
 
حج متمتع Haj mutamata
حج متمتع Haj mutamataحج متمتع Haj mutamata
حج متمتع Haj mutamataMohammad Ali
 
Valeria Y Ashley
 Valeria Y Ashley Valeria Y Ashley
Valeria Y Ashleyguestbb2c4f
 
PIS Infrastructure Abuja
PIS Infrastructure AbujaPIS Infrastructure Abuja
PIS Infrastructure AbujaSven Maedler
 
26ictericias 1216203957215814-9
26ictericias 1216203957215814-926ictericias 1216203957215814-9
26ictericias 1216203957215814-9Mocte Salaiza
 
PIS Uyo - Ikot Ekpene Road Phase I
PIS Uyo - Ikot Ekpene Road Phase IPIS Uyo - Ikot Ekpene Road Phase I
PIS Uyo - Ikot Ekpene Road Phase ISven Maedler
 
533 honras sejam ao cordeiro
533   honras sejam ao cordeiro533   honras sejam ao cordeiro
533 honras sejam ao cordeiroSUSSURRO DE AMOR
 
ヨーロッパの火薬庫
ヨーロッパの火薬庫ヨーロッパの火薬庫
ヨーロッパの火薬庫belocump
 
PIS Uyo - Stadium Complex
PIS Uyo - Stadium ComplexPIS Uyo - Stadium Complex
PIS Uyo - Stadium ComplexSven Maedler
 
MSW degree issued by University of Delhi
MSW degree issued by University of DelhiMSW degree issued by University of Delhi
MSW degree issued by University of DelhiOm Prakash Poddar
 
Advanced OSB in 21 Days
Advanced OSB in 21 DaysAdvanced OSB in 21 Days
Advanced OSB in 21 DaysVijay Reddy
 
Vicente5a
Vicente5aVicente5a
Vicente5aChasedi
 
EAIESB Oracle SOA Poster 2.0
EAIESB Oracle SOA Poster 2.0EAIESB Oracle SOA Poster 2.0
EAIESB Oracle SOA Poster 2.0Vijay Reddy
 
Evolución de los avances tecnológicos en diferentes áreas
Evolución de los avances tecnológicos en diferentes áreasEvolución de los avances tecnológicos en diferentes áreas
Evolución de los avances tecnológicos en diferentes áreasJoseph Grandet
 
Ilaria Barra Inail - sicurezza lavoro nei parchi eolici
Ilaria Barra Inail - sicurezza lavoro nei parchi eoliciIlaria Barra Inail - sicurezza lavoro nei parchi eolici
Ilaria Barra Inail - sicurezza lavoro nei parchi eolicicanaleenergia
 

Destaque (20)

Lista reavaliação - 3º bimestre - 8º ano - 2015
Lista   reavaliação - 3º bimestre - 8º ano - 2015Lista   reavaliação - 3º bimestre - 8º ano - 2015
Lista reavaliação - 3º bimestre - 8º ano - 2015
 
حج متمتع Haj mutamata
حج متمتع Haj mutamataحج متمتع Haj mutamata
حج متمتع Haj mutamata
 
Ideal Vila Cordovil
Ideal Vila CordovilIdeal Vila Cordovil
Ideal Vila Cordovil
 
Question 2 media
Question 2   mediaQuestion 2   media
Question 2 media
 
Valeria Y Ashley
 Valeria Y Ashley Valeria Y Ashley
Valeria Y Ashley
 
PIS Infrastructure Abuja
PIS Infrastructure AbujaPIS Infrastructure Abuja
PIS Infrastructure Abuja
 
Haynes pamphlet (1)
Haynes pamphlet (1)Haynes pamphlet (1)
Haynes pamphlet (1)
 
26ictericias 1216203957215814-9
26ictericias 1216203957215814-926ictericias 1216203957215814-9
26ictericias 1216203957215814-9
 
PIS Uyo - Ikot Ekpene Road Phase I
PIS Uyo - Ikot Ekpene Road Phase IPIS Uyo - Ikot Ekpene Road Phase I
PIS Uyo - Ikot Ekpene Road Phase I
 
533 honras sejam ao cordeiro
533   honras sejam ao cordeiro533   honras sejam ao cordeiro
533 honras sejam ao cordeiro
 
ヨーロッパの火薬庫
ヨーロッパの火薬庫ヨーロッパの火薬庫
ヨーロッパの火薬庫
 
PIS Uyo - Stadium Complex
PIS Uyo - Stadium ComplexPIS Uyo - Stadium Complex
PIS Uyo - Stadium Complex
 
O cordeiro
O cordeiro O cordeiro
O cordeiro
 
MSW degree issued by University of Delhi
MSW degree issued by University of DelhiMSW degree issued by University of Delhi
MSW degree issued by University of Delhi
 
Advanced OSB in 21 Days
Advanced OSB in 21 DaysAdvanced OSB in 21 Days
Advanced OSB in 21 Days
 
Vicente5a
Vicente5aVicente5a
Vicente5a
 
EAIESB Oracle SOA Poster 2.0
EAIESB Oracle SOA Poster 2.0EAIESB Oracle SOA Poster 2.0
EAIESB Oracle SOA Poster 2.0
 
Communication
Communication Communication
Communication
 
Evolución de los avances tecnológicos en diferentes áreas
Evolución de los avances tecnológicos en diferentes áreasEvolución de los avances tecnológicos en diferentes áreas
Evolución de los avances tecnológicos en diferentes áreas
 
Ilaria Barra Inail - sicurezza lavoro nei parchi eolici
Ilaria Barra Inail - sicurezza lavoro nei parchi eoliciIlaria Barra Inail - sicurezza lavoro nei parchi eolici
Ilaria Barra Inail - sicurezza lavoro nei parchi eolici
 

Semelhante a PIS Obajana - Cement Factory

Semelhante a PIS Obajana - Cement Factory (20)

New PPT
New PPT New PPT
New PPT
 
PIS Uyo - Government House Phase II
PIS Uyo - Government House Phase IIPIS Uyo - Government House Phase II
PIS Uyo - Government House Phase II
 
South Jetty
South JettySouth Jetty
South Jetty
 
E n e r g o Cement Plant - Projects
E n e r g o Cement Plant - ProjectsE n e r g o Cement Plant - Projects
E n e r g o Cement Plant - Projects
 
Aac booklet
Aac bookletAac booklet
Aac booklet
 
Pic booklet screen view 2
Pic booklet   screen view 2Pic booklet   screen view 2
Pic booklet screen view 2
 
AHMED YEHIA MARCH 2015
AHMED YEHIA MARCH 2015AHMED YEHIA MARCH 2015
AHMED YEHIA MARCH 2015
 
Rmc plant
Rmc plantRmc plant
Rmc plant
 
Muhammad_Aslam_CV
Muhammad_Aslam_CVMuhammad_Aslam_CV
Muhammad_Aslam_CV
 
Company portfolio
Company portfolioCompany portfolio
Company portfolio
 
wagdy garas CV 1
wagdy garas CV 1wagdy garas CV 1
wagdy garas CV 1
 
19-07-06 Scheme Description details
19-07-06 Scheme Description details19-07-06 Scheme Description details
19-07-06 Scheme Description details
 
State Company for Mining Industries
State Company for Mining IndustriesState Company for Mining Industries
State Company for Mining Industries
 
Alu Plant
Alu PlantAlu Plant
Alu Plant
 
self leveling concrete
self leveling concreteself leveling concrete
self leveling concrete
 
Pebbles II site report
Pebbles II site reportPebbles II site report
Pebbles II site report
 
Final Report BSp
Final Report BSpFinal Report BSp
Final Report BSp
 
Burj al arab
Burj al arabBurj al arab
Burj al arab
 
2000_Charleston_cement
2000_Charleston_cement2000_Charleston_cement
2000_Charleston_cement
 
Csc Presentation
Csc PresentationCsc Presentation
Csc Presentation
 

PIS Obajana - Cement Factory

  • 1. Construction Period: 03/2003 –02/2005 Client: Obajana Cement Factory, Dangote Industries Services: Construction of process and auxiliary buildings for the cement plant plus design and construction of all infrastructure works Cement Plant, Obajana In March 2003, Julius Berger Nigeria PLC was awarded the contract for the civil works and construction of process and auxiliary buildings for a new cement factory. The plant was to be located on a greenfield area of 350ha in Obajana, Kogi State. Historically, a large percentage of Nigeria´s demand for cement was covered through imports. The construction of the Obajana Cement Plant, with a maximum daily output of 14,000 tons of high quality cement, changed this situation and allowed the importation of cement to be reduced considerably. Within a period of 24 months, two production lines were completed by Julius Berger Nigeria PLC including two 83m high raw mill silos and four 60m high cement silos. The work was carried out using pre-stressed concrete and specially designed sliding formwork. All foundations, including bored pile foundations for the silos, pre-heater, rotary kiln and the ground slabs for several departments of the two production lines and as the foundation for the pre-crushers in the quarry were part of Julius Berger Nigeria PLC´s scope of work. The design of the auxiliary buildings and facilities such as the power plant, the water storage tanks, the central control building and twelve substations allowed for insitu reinforced concrete using traditional formwork methods. An eight km long, elevated belt conveyor was built from the quarry to the cement plant. The foundation works as well as the pre-cast Picture were constructed by Julius Berger Nigeria PLC. The main quantities of work comprised approx. 200,000cbm of reinforced concrete and 36,000cbm of blinding concrete; 25,000 tons of high tensile steel; 240,000sqm of traditional and 84,100sqm of slip formwork. All infrastructure works including general earthworks and the construction of roads and concrete paved areas, as well as storm water drainage, were designed and executed by Julius Berger Nigeria PLC. The project was handed over in February 2005.