Independent Reviews Can Be a Valuable
      Partner in Program Success

                           J. H. Rothenberg
                           25 February 2009
Objectives & Stakeholders

Ingredients of a Value Added Review

Project Manager’s View & Experiences

Center Director’s View & Experience

Associate Administrator’s View & Experiences
Project visibility, cost or other factors dictate

  Management Plan - One or more Standing Review
  Committees - Design & Oversight

  Ad hoc - Problem Solving or Critical Event

  Committee Composition - Internal or External
  Stakeholders and/or Customers
Project Manager/Program Executive

HQ Directorate Associate Administrator

Center Director

Administrator/PA&E/Chief Engineer

Congress/GAO/OMB/OSTP
Project Management Process Reviews –
Gate/Progress/Risk understanding

Problem Assessment Reviews– Understand &
recover with or without public flogging
 Technical – Expertise
 Programmatic – Schedule and Cost Overruns

Confidence
 External opinion
 “ We did everything we can”
Knowledgeable Review Committee, including
customer and/or scientific community

Focused and jointly planned with the
Program/Project

Consolidated conflict free recommendations
and actions in context of review objectives

Timely actions/recommendations - days to
weeks after review and not months
Standing Reviews
 Project Management Process
    Focuses decisions but always a resource challenge
 Independent Review Committee’s
   Necessary evil and can only break-even at best


Ad hoc Reviews
 Educating Committee costly
 Technical reviews with focused expertise helpful
 Programmatic review means you are in trouble
 Confidence reviews can be an opportunity
Project Management Review process are critical to
Project Success

Process rigor, review members competence & life
cycle involvement are critical as exemplified by:
   Lewis /STS 49/MARS 98/ HST /Shuttle “Light-
   Weight” P/L Carrier/ISS Treadmill/………

Center or discipline institutionalized review
committees & process help ensure success

From Project Mangers viewpoint standing IRT
value is upward communication
Ad hoc technical reviews can be extremely valuable
  HST Sensor Bearings/COSTAR Light Baffles
  Shuttle wiring

Ad Hoc Programmatic and Confidence Reviews provide
both opportunities and threats for a Project Manager
  Health of program to stakeholders
  Communicate need for Senior Management support
    HST EVA /Crew assignments
    ISS Budget
  On more than one occasion resulted in a new Project
  Manager

Review Teams are not substitutes for independent test
capabilities in the Project Management process
   ISS MEIT/HST VEST
Center initiated Review by committee external
to Project
  Independent assessment of Project Plan,
  resource needs, progress & gate for next phase
  Problem understanding and resolution

Center initiated Review by committee external
to the Center
  Stakeholder buy-in
  Need help beyond Center resources

Stakeholder initiated review by committee
external to the Center
  Confidence
  Problem understanding and resolution
Center standing Systems Review process critical
to maintaining technical mission success

IPAO beneficial to Project but not to cost
control

Making stakeholders partners in Center projects
critical
  EOS/EOS DIS/ BoD

Independent external review of Institutional
operations beneficial
  Center Reorg/ Laboratory Visiting Committees
Reviews generally initiated by AA
  Internal committee/IPAO
  External committee

Independent reviews provide assessments of
  Programmatic status & issues
  Hi –visibility technical risks/concerns
  Readiness of proposed new Programs

 Critical independent input for external
stakeholders
  Credibility in question
  Keep it sold
Independent assessment of programmatic status
critical to credibility – external better than
internal
 ISS costs overrun (s)
 Stafford Committee

Independent review and recommendations for
major technical risks increased AA & stakeholder
confidence
 Shuttle aging/wiring/upgrade priorities
 X-38 technical approach & cost projections
Reviews are necessary tools that help ensure mission
and project success

Independent Reviews help manage stakeholders
expectations and retain or obtain their support
  Keep stakeholders informed of problems and what you
  are doing about them – i.e.; “Top Ten”
  Make stakeholders partners in the Project/Program at
  every opportunity

Project Manager’s need to
  Maximize the value toward mission success of standing
  reviews
  Manage stakeholders expectation so that they reduce
  the number of non-value added ad hoc reviews

Mais conteúdo relacionado

Mais procurados

Kelly.elliott
Kelly.elliottKelly.elliott
Kelly.elliottNASAPMC
 
Software management disciplines
Software management disciplinesSoftware management disciplines
Software management disciplinesKuppusamy P
 
2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adbTa Ngoc
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Cassidy.jim
Cassidy.jimCassidy.jim
Cassidy.jimNASAPMC
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
A Beginner's Guide to IT Project Management
A Beginner's Guide to IT Project ManagementA Beginner's Guide to IT Project Management
A Beginner's Guide to IT Project ManagementWorkfront
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Project Management Principles
Project Management PrinciplesProject Management Principles
Project Management PrinciplesAnand Subramaniam
 
Healy edward
Healy edwardHealy edward
Healy edwardNASAPMC
 
Spm project planning
Spm project planning Spm project planning
Spm project planning Kanchana Devi
 
How NYU Langone Med Center integrated Primavera Unifier and PeopleSoft to enh...
How NYU Langone Med Center integrated Primavera Unifier and PeopleSoft to enh...How NYU Langone Med Center integrated Primavera Unifier and PeopleSoft to enh...
How NYU Langone Med Center integrated Primavera Unifier and PeopleSoft to enh...p6academy
 
1 2. project management
1 2. project management1 2. project management
1 2. project managementakashsaini8
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management FrameworkRahul Sudame
 
Five immutable principles
Five immutable principlesFive immutable principles
Five immutable principlesGlen Alleman
 

Mais procurados (20)

Kelly.elliott
Kelly.elliottKelly.elliott
Kelly.elliott
 
Software management disciplines
Software management disciplinesSoftware management disciplines
Software management disciplines
 
2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Spm unit 1
Spm unit 1Spm unit 1
Spm unit 1
 
Spm l01
Spm l01Spm l01
Spm l01
 
Cassidy.jim
Cassidy.jimCassidy.jim
Cassidy.jim
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
A Beginner's Guide to IT Project Management
A Beginner's Guide to IT Project ManagementA Beginner's Guide to IT Project Management
A Beginner's Guide to IT Project Management
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Project managemen concept
Project managemen conceptProject managemen concept
Project managemen concept
 
Project Management Principles
Project Management PrinciplesProject Management Principles
Project Management Principles
 
Healy edward
Healy edwardHealy edward
Healy edward
 
It2403 spm
It2403 spmIt2403 spm
It2403 spm
 
Spm project planning
Spm project planning Spm project planning
Spm project planning
 
How NYU Langone Med Center integrated Primavera Unifier and PeopleSoft to enh...
How NYU Langone Med Center integrated Primavera Unifier and PeopleSoft to enh...How NYU Langone Med Center integrated Primavera Unifier and PeopleSoft to enh...
How NYU Langone Med Center integrated Primavera Unifier and PeopleSoft to enh...
 
1 2. project management
1 2. project management1 2. project management
1 2. project management
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Five immutable principles
Five immutable principlesFive immutable principles
Five immutable principles
 
Resolving TIAs
Resolving TIAsResolving TIAs
Resolving TIAs
 

Destaque

Ray.ronald
Ray.ronaldRay.ronald
Ray.ronaldNASAPMC
 
Charles.leising
Charles.leisingCharles.leising
Charles.leisingNASAPMC
 
Newman.steve
Newman.steveNewman.steve
Newman.steveNASAPMC
 
Zavala.ed
Zavala.edZavala.ed
Zavala.edNASAPMC
 
John.baniszewski
John.baniszewskiJohn.baniszewski
John.baniszewskiNASAPMC
 
Claunch.cathy
Claunch.cathyClaunch.cathy
Claunch.cathyNASAPMC
 
Anil.rekha
Anil.rekhaAnil.rekha
Anil.rekhaNASAPMC
 
Gary.humphreys
Gary.humphreysGary.humphreys
Gary.humphreysNASAPMC
 
Manzer fred
Manzer fredManzer fred
Manzer fredNASAPMC
 
Denver PMI Symposium 2009
Denver PMI Symposium 2009Denver PMI Symposium 2009
Denver PMI Symposium 2009Glen Alleman
 
Performance Based Management Handbook
Performance Based Management HandbookPerformance Based Management Handbook
Performance Based Management HandbookGlen Alleman
 
Applying the checklist manifesto for project management success
Applying the checklist manifesto for project management successApplying the checklist manifesto for project management success
Applying the checklist manifesto for project management successGlen Alleman
 

Destaque (13)

Ray.ronald
Ray.ronaldRay.ronald
Ray.ronald
 
Charles.leising
Charles.leisingCharles.leising
Charles.leising
 
Newman.steve
Newman.steveNewman.steve
Newman.steve
 
Zavala.ed
Zavala.edZavala.ed
Zavala.ed
 
John.baniszewski
John.baniszewskiJohn.baniszewski
John.baniszewski
 
Claunch.cathy
Claunch.cathyClaunch.cathy
Claunch.cathy
 
Noor
NoorNoor
Noor
 
Anil.rekha
Anil.rekhaAnil.rekha
Anil.rekha
 
Gary.humphreys
Gary.humphreysGary.humphreys
Gary.humphreys
 
Manzer fred
Manzer fredManzer fred
Manzer fred
 
Denver PMI Symposium 2009
Denver PMI Symposium 2009Denver PMI Symposium 2009
Denver PMI Symposium 2009
 
Performance Based Management Handbook
Performance Based Management HandbookPerformance Based Management Handbook
Performance Based Management Handbook
 
Applying the checklist manifesto for project management success
Applying the checklist manifesto for project management successApplying the checklist manifesto for project management success
Applying the checklist manifesto for project management success
 

Semelhante a Rothenberg.joe

Project Auditing.ppt
Project Auditing.pptProject Auditing.ppt
Project Auditing.pptkcsekar77
 
2 a. project auditing
2 a. project auditing2 a. project auditing
2 a. project auditingDr.R. SELVAM
 
It Project Management
It Project ManagementIt Project Management
It Project ManagementTJ Rains
 
Final Class Presentation on Project Audit and Closure.ppt
Final Class Presentation on Project Audit and Closure.pptFinal Class Presentation on Project Audit and Closure.ppt
Final Class Presentation on Project Audit and Closure.pptGeorgeKabongah2
 
Project management lecture 11 slide 11
Project management lecture 11 slide 11Project management lecture 11 slide 11
Project management lecture 11 slide 11beautyshine
 
Project Management: More Caught Than Taught
Project Management: More Caught Than TaughtProject Management: More Caught Than Taught
Project Management: More Caught Than Taughtedward_uy
 
PMO Proposal For Global Sales Operations
PMO Proposal For Global Sales OperationsPMO Proposal For Global Sales Operations
PMO Proposal For Global Sales Operationstonyhinojosa
 
Simonsen.vonnie
Simonsen.vonnieSimonsen.vonnie
Simonsen.vonnieNASAPMC
 
NUR 350 Journal Guidelines and Rubric Journal ac.docx
NUR 350 Journal Guidelines and Rubric   Journal ac.docxNUR 350 Journal Guidelines and Rubric   Journal ac.docx
NUR 350 Journal Guidelines and Rubric Journal ac.docxvannagoforth
 
PMP Training - 04 project integration management
PMP Training - 04 project integration managementPMP Training - 04 project integration management
PMP Training - 04 project integration managementejlp12
 
Pharmaceutical Project Management Checklist
Pharmaceutical Project Management ChecklistPharmaceutical Project Management Checklist
Pharmaceutical Project Management ChecklistMuthu Krishnan
 
Project management unit 5(1)
Project management unit 5(1)Project management unit 5(1)
Project management unit 5(1)Rintu Das
 
Enterprise Content Management (ECM) System
Enterprise Content Management (ECM) SystemEnterprise Content Management (ECM) System
Enterprise Content Management (ECM) SystemAnand Subramaniam
 
New Change Implementation
New Change ImplementationNew Change Implementation
New Change Implementationguest7471d9a
 
Project assurance - make sure your projects delivers as expected
Project assurance - make sure your projects delivers as expectedProject assurance - make sure your projects delivers as expected
Project assurance - make sure your projects delivers as expectedTerje Sæbø
 

Semelhante a Rothenberg.joe (20)

Project Auditing.ppt
Project Auditing.pptProject Auditing.ppt
Project Auditing.ppt
 
Project Health Checks
Project Health ChecksProject Health Checks
Project Health Checks
 
2 a. project auditing
2 a. project auditing2 a. project auditing
2 a. project auditing
 
It Project Management
It Project ManagementIt Project Management
It Project Management
 
Real example of PMO deployment
Real example of PMO deploymentReal example of PMO deployment
Real example of PMO deployment
 
Final Class Presentation on Project Audit and Closure.ppt
Final Class Presentation on Project Audit and Closure.pptFinal Class Presentation on Project Audit and Closure.ppt
Final Class Presentation on Project Audit and Closure.ppt
 
Project management lecture 11 slide 11
Project management lecture 11 slide 11Project management lecture 11 slide 11
Project management lecture 11 slide 11
 
Project Management: More Caught Than Taught
Project Management: More Caught Than TaughtProject Management: More Caught Than Taught
Project Management: More Caught Than Taught
 
PMO Proposal For Global Sales Operations
PMO Proposal For Global Sales OperationsPMO Proposal For Global Sales Operations
PMO Proposal For Global Sales Operations
 
Simonsen.vonnie
Simonsen.vonnieSimonsen.vonnie
Simonsen.vonnie
 
NUR 350 Journal Guidelines and Rubric Journal ac.docx
NUR 350 Journal Guidelines and Rubric   Journal ac.docxNUR 350 Journal Guidelines and Rubric   Journal ac.docx
NUR 350 Journal Guidelines and Rubric Journal ac.docx
 
PMP Training - 04 project integration management
PMP Training - 04 project integration managementPMP Training - 04 project integration management
PMP Training - 04 project integration management
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Pharmaceutical Project Management Checklist
Pharmaceutical Project Management ChecklistPharmaceutical Project Management Checklist
Pharmaceutical Project Management Checklist
 
Project management unit 5(1)
Project management unit 5(1)Project management unit 5(1)
Project management unit 5(1)
 
Enterprise Content Management (ECM) System
Enterprise Content Management (ECM) SystemEnterprise Content Management (ECM) System
Enterprise Content Management (ECM) System
 
Project Management
Project ManagementProject Management
Project Management
 
New Change Implementation
New Change ImplementationNew Change Implementation
New Change Implementation
 
New Change Implementation
New Change ImplementationNew Change Implementation
New Change Implementation
 
Project assurance - make sure your projects delivers as expected
Project assurance - make sure your projects delivers as expectedProject assurance - make sure your projects delivers as expected
Project assurance - make sure your projects delivers as expected
 

Mais de NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 

Mais de NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 

Último

Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with CultureSeta Wicaksana
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecZurliaSoop
 
PARK STREET 💋 Call Girl 9827461493 Call Girls in Escort service book now
PARK STREET 💋 Call Girl 9827461493 Call Girls in  Escort service book nowPARK STREET 💋 Call Girl 9827461493 Call Girls in  Escort service book now
PARK STREET 💋 Call Girl 9827461493 Call Girls in Escort service book nowkapoorjyoti4444
 
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service AvailableNashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Availablepr788182
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizharallensay1
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...daisycvs
 
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGpr788182
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxCynthia Clay
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingNauman Safdar
 
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGpr788182
 
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...pujan9679
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...ssuserf63bd7
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
Cannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannaBusinessPlans
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon investment
 
Kalyan Call Girl 98350*37198 Call Girls in Escort service book now
Kalyan Call Girl 98350*37198 Call Girls in Escort service book nowKalyan Call Girl 98350*37198 Call Girls in Escort service book now
Kalyan Call Girl 98350*37198 Call Girls in Escort service book nowranineha57744
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwaitdaisycvs
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Timegargpaaro
 

Último (20)

Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
 
PARK STREET 💋 Call Girl 9827461493 Call Girls in Escort service book now
PARK STREET 💋 Call Girl 9827461493 Call Girls in  Escort service book nowPARK STREET 💋 Call Girl 9827461493 Call Girls in  Escort service book now
PARK STREET 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service AvailableNashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
 
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Cannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 Updated
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
WheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond InsightsWheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond Insights
 
Kalyan Call Girl 98350*37198 Call Girls in Escort service book now
Kalyan Call Girl 98350*37198 Call Girls in Escort service book nowKalyan Call Girl 98350*37198 Call Girls in Escort service book now
Kalyan Call Girl 98350*37198 Call Girls in Escort service book now
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
 

Rothenberg.joe

  • 1. Independent Reviews Can Be a Valuable Partner in Program Success J. H. Rothenberg 25 February 2009
  • 2. Objectives & Stakeholders Ingredients of a Value Added Review Project Manager’s View & Experiences Center Director’s View & Experience Associate Administrator’s View & Experiences
  • 3.
  • 4. Project visibility, cost or other factors dictate Management Plan - One or more Standing Review Committees - Design & Oversight Ad hoc - Problem Solving or Critical Event Committee Composition - Internal or External Stakeholders and/or Customers
  • 5. Project Manager/Program Executive HQ Directorate Associate Administrator Center Director Administrator/PA&E/Chief Engineer Congress/GAO/OMB/OSTP
  • 6. Project Management Process Reviews – Gate/Progress/Risk understanding Problem Assessment Reviews– Understand & recover with or without public flogging Technical – Expertise Programmatic – Schedule and Cost Overruns Confidence External opinion “ We did everything we can”
  • 7.
  • 8. Knowledgeable Review Committee, including customer and/or scientific community Focused and jointly planned with the Program/Project Consolidated conflict free recommendations and actions in context of review objectives Timely actions/recommendations - days to weeks after review and not months
  • 9.
  • 10. Standing Reviews Project Management Process Focuses decisions but always a resource challenge Independent Review Committee’s Necessary evil and can only break-even at best Ad hoc Reviews Educating Committee costly Technical reviews with focused expertise helpful Programmatic review means you are in trouble Confidence reviews can be an opportunity
  • 11. Project Management Review process are critical to Project Success Process rigor, review members competence & life cycle involvement are critical as exemplified by: Lewis /STS 49/MARS 98/ HST /Shuttle “Light- Weight” P/L Carrier/ISS Treadmill/……… Center or discipline institutionalized review committees & process help ensure success From Project Mangers viewpoint standing IRT value is upward communication
  • 12. Ad hoc technical reviews can be extremely valuable HST Sensor Bearings/COSTAR Light Baffles Shuttle wiring Ad Hoc Programmatic and Confidence Reviews provide both opportunities and threats for a Project Manager Health of program to stakeholders Communicate need for Senior Management support HST EVA /Crew assignments ISS Budget On more than one occasion resulted in a new Project Manager Review Teams are not substitutes for independent test capabilities in the Project Management process ISS MEIT/HST VEST
  • 13.
  • 14. Center initiated Review by committee external to Project Independent assessment of Project Plan, resource needs, progress & gate for next phase Problem understanding and resolution Center initiated Review by committee external to the Center Stakeholder buy-in Need help beyond Center resources Stakeholder initiated review by committee external to the Center Confidence Problem understanding and resolution
  • 15. Center standing Systems Review process critical to maintaining technical mission success IPAO beneficial to Project but not to cost control Making stakeholders partners in Center projects critical EOS/EOS DIS/ BoD Independent external review of Institutional operations beneficial Center Reorg/ Laboratory Visiting Committees
  • 16.
  • 17. Reviews generally initiated by AA Internal committee/IPAO External committee Independent reviews provide assessments of Programmatic status & issues Hi –visibility technical risks/concerns Readiness of proposed new Programs Critical independent input for external stakeholders Credibility in question Keep it sold
  • 18. Independent assessment of programmatic status critical to credibility – external better than internal ISS costs overrun (s) Stafford Committee Independent review and recommendations for major technical risks increased AA & stakeholder confidence Shuttle aging/wiring/upgrade priorities X-38 technical approach & cost projections
  • 19. Reviews are necessary tools that help ensure mission and project success Independent Reviews help manage stakeholders expectations and retain or obtain their support Keep stakeholders informed of problems and what you are doing about them – i.e.; “Top Ten” Make stakeholders partners in the Project/Program at every opportunity Project Manager’s need to Maximize the value toward mission success of standing reviews Manage stakeholders expectation so that they reduce the number of non-value added ad hoc reviews