SlideShare uma empresa Scribd logo
1 de 1
Baixar para ler offline
Acknowledgments
We would like to thank Mark Legacy from
Humpback Hydro passing this project along
to the UBC Capstone program and giving
us the opportunity to work on this project.
We would also like to thank our faculty
supervisor Dr. Joshua Brinkerhoff for
taking the time to support us through the
Capstone project.
Introduction
The purpose of this project is to complete
proof of concept design of Humpback Hydro’s
patented Ocean Hydro Energy Storage System.
A conventional Pumped Storage Hydro system
uses two reservoirs to store energy. The top
reservoir is land locked and requires a high
elevation, while the bottom reservoir is either a
lake or an ocean. During peak energy demand,
water is run from the high reservoir to the low
reservoir through a turbine to generate
electrical power through a hydro turbine.
During low energy demand, the upper
reservoir is replenished. The Humpback Hydro
system takes this conventional Hydro Energy
storage principle found on shore and places it
in an offshore environment.
There are four main deliverables for this
project which includes determining the system
efficiency, developing a computer program to
aid in sizing these facilities, selecting power
generation equipment and completing CAD
modelling of the system.
Design Requirements
System Analysis
The system was analyzed to estimate the
efficiency of the system and the amount of
concrete required. This analysis also indicated
reservoir volumes, penstock and pipe
diameters, power requirements, required head,
and flow rates.
The efficiency of the system was analyzed
by modelling the system and including the
efficiencies of the turbomachinery [2] and
accounting for head losses. Figure 2 below
shows the efficiency for various combinations
of head ratio (HR) which is the upper turbine
head divided by lower turbine head.
Conclusions
All objectives were met with the following
deliverables:
1) Determined that a 10 MW facility, with 3
hours of storage time, and 6 hours to
replenish the upper reservoir, can achieve
an efficiency of 70.2% and requires
220,000 cubic meters of concrete.
2) Developed a MATLAB Graphical User
Interface which enables the user to input
required power, storage time, and low
demand duration to calculate efficiency,
concrete amount, flow rates, penstock
sizes, and required head.
3) Selected power transmission equipment
including a TMEIC 4 Pole Generator and a
three phase HPS transformer.
4) Completed CAD modelling of the system
including an animation illustrating the
operating principles of the Ocean Hydro
Energy Storage System.
Ocean Hydro Energy Storage System
Shariq Codabux, Mitchell Lamoureux, David Martens, Billy Su
Faculty Advisor: Joshua Brinkerhoff, Industry Collaborator: Humpback Hydro
Group #8
References
[1] M. A. Herzog, Practical dam analysis,
London: Thomas Telford Publishing,
1999.
[2] S. L. Dixon and C. A. Hall, Fluid
Mechanics and Thermodynamics of
Turbomachinery, Oxford: Elsevier, 2010.
[3] T. M. E. I. C. CORPORATION,
"http://www.tmeic.com/Repository/Other
s/4P%20TG.pdf," [Online].
[4] H. P. Systems, "Dry-Type Medium
Voltage Distribution [Power]
Transformer," Hammond Power Solutions
Inc. , 2014.
[5] Humpback Hydro, "Humpback Hydro
Inc, Grid Scale Energy Storage
Technology," Vancouver, 2014.
For further information
For further information contact Mitchell
Lamoureux Mitchell.Lamoureux@gmail.com
Fig. 1. Schematic showing
operation of the Ocean Hydro
Energy Storage System [5]
Design Description
The Humpback Hydro System as shown in
Figure 1 operates using the following
processes:
•
1-2 Water is run through the lower turbine
generating power
•
2-3 Water is pumped to the upper reservoir
•
3-1 Water is released through the upper
turbine again generating power
Processes 1-2 and 3-1 occur
simultaneously during peak electricity demand
and process 2-3 will occur during low demand.
Fig. 2. Efficiency of 10 MW System for
Various Combinations of Head Ratios
Electrical
The power transmission set includes a
generator and a power transformer to meet
local power grid standards. This set consists
of a generator and transformer as described in
Table 3.
Graphical User Interface
The design of the Ocean Energy Storage System
will vary depending on the end user requirements. A
graphical user interface (GUI) was developed using
MATLAB to aid in the sizing of the system (Figure
3). The GUI performs calculations to size penstocks,
piping, reservoir volume, and heights of the system.
It optimizes the system based on the highest
efficiency and minimal concrete when provided with
the following inputs from the user:
•
Required Power
•
Storage Time
•
Low Demand Duration
CAD Modelling/FEA
Solid modelling was completed using the values
from Table 2. This system will have a provide
10MW of power over three hours, and replenish the
upper reservoir in six hours.
Using these values, the system was modelled
using Autodesk Inventor. Figure 4 shows a cross
section of the system showing the components of the
system. The components in green include the lower
penstock, generator, and turbine. the blue shows the
pumping and piping system, and the red shows the
lower penstock and generator.
Fig. 3. Graphical User Interface 1) User
Inputs 2) Push Button To Calculate 3) GUI
Outputs
The gravity dam surrounding the system is
designed to withstand the hydrostatic and
dead loads acting upon it. Specifically, the
dam is designed to have:
•
Safety Factor in Compression > 3
•
Safety Factor Against Sliding > 1.5
•
0 tensile stresses [1]
Table 2 list the parameters calculated
for a plant generating 10 MW, storage time of
3 hours, and replenishing the upper reservoir
in 6 hours. This system was the most efficient
with the least amount of concrete from the
analysis.
Requirements
• Dam shall be designed to withstand the
hydrostatic and dead loads acting on the
structure
• Structure/Components will withstand the
corrosive nature and extreme weather
conditions of the ocean.
• Power will output as 50 or 60 Hz AC as
specified by regional power requirements
• The design should address the life cycle of
the plant to be 65-80 years
• The design should allow for maintenance to
the electrical/mechanical components
• The selected facility will sustain 10 MW of
power over 3 hours, and replenish the upper
reservoir in 6 hours.
Table 2. Calculated Parameters for the
10 MW Ocean Hydro Storage System
Parameter Value
Lower Turbine Power Output 2.86 MW
Lower Turbine Head 20 m
Lower Penstock Diameter 1.6 m
Lower Reservoir Volume 170,000
Upper Turbine Power Output 7.14 MW
Upper Turbine Head 50 m
Upper Penstock Diameter 1.6 m
Upper Reservoir Volume 170,000
Pump Flow Rate 7.9 /s
Pump Power 7.12 MW
Total Amount of Concrete 220,000
Total System Efficiency 70.2%
Parameter Value
Lower Turbine Power Output 2.86 MW
Lower Turbine Head 20 m
Lower Penstock Diameter 1.6 m
Lower Reservoir Volume
Upper Turbine Power Output 7.14 MW
Upper Turbine Head 50 m
Upper Penstock Diameter 1.6 m
Upper Reservoir Volume
Pump Flow Rate
Pump Power 7.12 MW
Total Amount of Concrete
Total System Efficiency 70.2%
Table 1. List of Design Requirements
Using the CAD model a finite element analysis (FEA)
stress analysis was completed. The FEA examined the
stresses in a full upper reservoir, to indicate the
maximum stresses and minimum safety factors obtained
in the structure. Figure 5a below shows the safety factor
of the structure, while Figure 5b shows the von misses
stress in the structure.
Fig. 4. System Overview showing all
components
Fig. 5. Stress simulation of fluid acting on
the upper reservoir a) Safety Factor b) Von
Mises Stress
Component Description
4 Pole
Generator
• The required generator must be
rated for 1-10 MW, with a
frequency of 60 Hz
• A TMEIC 4 Pole generator is a
viable option [3]
Power
Transformer
• The transformer must have the
same frequency, power rating, and
input voltage as the generator
• A three phase HPS Dry Type
transformer is a viable option [4]
Table 3. Electrical Components and their
descriptions
1
2
3
Efficiency vs. Lower Turbine Head
a) b)

Mais conteúdo relacionado

Mais procurados

Cem 350 gilbane corp mep retrofit systems overview 4 2011
Cem 350 gilbane corp mep retrofit systems overview  4 2011Cem 350 gilbane corp mep retrofit systems overview  4 2011
Cem 350 gilbane corp mep retrofit systems overview 4 2011
miresmaeil
 
What subsea control systems low res
What   subsea control systems low resWhat   subsea control systems low res
What subsea control systems low res
Tomásio Leite
 
Gas Combustion Turbine System
Gas Combustion Turbine SystemGas Combustion Turbine System
Gas Combustion Turbine System
Peter Bright
 
Bruce Power Project-Description
Bruce Power Project-DescriptionBruce Power Project-Description
Bruce Power Project-Description
hernandezgerardo
 
Final Year Project
Final Year ProjectFinal Year Project
Final Year Project
Yaqoob Ali
 

Mais procurados (20)

Industrial training report on NHPC TLD-III
Industrial training report on NHPC TLD-IIIIndustrial training report on NHPC TLD-III
Industrial training report on NHPC TLD-III
 
International Journal of Computational Engineering Research(IJCER)
International Journal of Computational Engineering Research(IJCER)International Journal of Computational Engineering Research(IJCER)
International Journal of Computational Engineering Research(IJCER)
 
Vocational training report NHPC TANAKPUR Uttarakhand
Vocational training report NHPC TANAKPUR UttarakhandVocational training report NHPC TANAKPUR Uttarakhand
Vocational training report NHPC TANAKPUR Uttarakhand
 
Siemens - Power Generation Power Plants
Siemens - Power Generation Power PlantsSiemens - Power Generation Power Plants
Siemens - Power Generation Power Plants
 
Gulpur Hydropower Plant Project Full Report 2019
Gulpur Hydropower Plant Project Full Report 2019Gulpur Hydropower Plant Project Full Report 2019
Gulpur Hydropower Plant Project Full Report 2019
 
Hydro Turbine Project Final Report
Hydro Turbine Project Final ReportHydro Turbine Project Final Report
Hydro Turbine Project Final Report
 
Homebuilt Micro Hydro Turbine
Homebuilt Micro Hydro TurbineHomebuilt Micro Hydro Turbine
Homebuilt Micro Hydro Turbine
 
Base Load Plants and Peak Load Plant
Base Load Plants and Peak Load PlantBase Load Plants and Peak Load Plant
Base Load Plants and Peak Load Plant
 
Solar system
Solar systemSolar system
Solar system
 
Cem 350 gilbane corp mep retrofit systems overview 4 2011
Cem 350 gilbane corp mep retrofit systems overview  4 2011Cem 350 gilbane corp mep retrofit systems overview  4 2011
Cem 350 gilbane corp mep retrofit systems overview 4 2011
 
What subsea control systems low res
What   subsea control systems low resWhat   subsea control systems low res
What subsea control systems low res
 
Mini project presentation
Mini project presentation   Mini project presentation
Mini project presentation
 
Gas Combustion Turbine System
Gas Combustion Turbine SystemGas Combustion Turbine System
Gas Combustion Turbine System
 
Summer Training Presentation
Summer Training PresentationSummer Training Presentation
Summer Training Presentation
 
Bruce Power Project-Description
Bruce Power Project-DescriptionBruce Power Project-Description
Bruce Power Project-Description
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
NTPC
NTPCNTPC
NTPC
 
Shivesh ntpc ppt
Shivesh ntpc pptShivesh ntpc ppt
Shivesh ntpc ppt
 
Lecture 3.1 Turbines in Micro Hydro
Lecture 3.1 Turbines in Micro HydroLecture 3.1 Turbines in Micro Hydro
Lecture 3.1 Turbines in Micro Hydro
 
Final Year Project
Final Year ProjectFinal Year Project
Final Year Project
 

Destaque (7)

2016 Dance Resume (admin) copy
2016 Dance Resume (admin) copy2016 Dance Resume (admin) copy
2016 Dance Resume (admin) copy
 
Case Study: Marketing Philippine Sports by Strengthening Government Consisten...
Case Study: Marketing Philippine Sports by Strengthening Government Consisten...Case Study: Marketing Philippine Sports by Strengthening Government Consisten...
Case Study: Marketing Philippine Sports by Strengthening Government Consisten...
 
Good Roommate Guide FULL (Final)
Good Roommate Guide FULL (Final)Good Roommate Guide FULL (Final)
Good Roommate Guide FULL (Final)
 
RESUME 2016
RESUME 2016RESUME 2016
RESUME 2016
 
Anuncio das vagas apple
Anuncio das vagas appleAnuncio das vagas apple
Anuncio das vagas apple
 
Tr Trio leadership challenge
Tr Trio leadership challengeTr Trio leadership challenge
Tr Trio leadership challenge
 
WidlerPortfolio2015
WidlerPortfolio2015WidlerPortfolio2015
WidlerPortfolio2015
 

Semelhante a Poster_Humpback_Hydro

Final_Presentation_Humpback_Hydro
Final_Presentation_Humpback_HydroFinal_Presentation_Humpback_Hydro
Final_Presentation_Humpback_Hydro
Mark Legacy
 
Iaetsd load frequency control for a distributed grid
Iaetsd load frequency control for a distributed gridIaetsd load frequency control for a distributed grid
Iaetsd load frequency control for a distributed grid
Iaetsd Iaetsd
 
New Library Ship Energy Systems
New Library Ship Energy SystemsNew Library Ship Energy Systems
New Library Ship Energy Systems
SimulationX
 
BAKUN Hydropower Project
BAKUN Hydropower ProjectBAKUN Hydropower Project
BAKUN Hydropower Project
Hugo Sena, PMP
 
2 PCCE White_Paper-Rev5
2 PCCE White_Paper-Rev52 PCCE White_Paper-Rev5
2 PCCE White_Paper-Rev5
Victor Sauers
 

Semelhante a Poster_Humpback_Hydro (20)

Final_Presentation_Humpback_Hydro
Final_Presentation_Humpback_HydroFinal_Presentation_Humpback_Hydro
Final_Presentation_Humpback_Hydro
 
Overview of Water cycles, wastewater treatment processes, wastewater plant en...
Overview of Water cycles, wastewater treatment processes, wastewater plant en...Overview of Water cycles, wastewater treatment processes, wastewater plant en...
Overview of Water cycles, wastewater treatment processes, wastewater plant en...
 
DESIGN OF A MULTIFUNCTIONAL FLYBACK DC-DC CONVERTER WITH CURRENT CONTROL
DESIGN OF A MULTIFUNCTIONAL FLYBACK DC-DC CONVERTER WITH CURRENT CONTROLDESIGN OF A MULTIFUNCTIONAL FLYBACK DC-DC CONVERTER WITH CURRENT CONTROL
DESIGN OF A MULTIFUNCTIONAL FLYBACK DC-DC CONVERTER WITH CURRENT CONTROL
 
Iaetsd load frequency control for a distributed grid
Iaetsd load frequency control for a distributed gridIaetsd load frequency control for a distributed grid
Iaetsd load frequency control for a distributed grid
 
Modeling and Analysis of Canal Type Small Hydro Power Plant and Performance E...
Modeling and Analysis of Canal Type Small Hydro Power Plant and Performance E...Modeling and Analysis of Canal Type Small Hydro Power Plant and Performance E...
Modeling and Analysis of Canal Type Small Hydro Power Plant and Performance E...
 
Development of a Bench-Top Air-to-Water Heat Pump Experimental Apparatus
Development of a Bench-Top Air-to-Water Heat Pump Experimental ApparatusDevelopment of a Bench-Top Air-to-Water Heat Pump Experimental Apparatus
Development of a Bench-Top Air-to-Water Heat Pump Experimental Apparatus
 
Green mechatronics project pelton wheel
Green mechatronics project pelton wheelGreen mechatronics project pelton wheel
Green mechatronics project pelton wheel
 
Design and implementation of micro hydro turbine for power generation and its...
Design and implementation of micro hydro turbine for power generation and its...Design and implementation of micro hydro turbine for power generation and its...
Design and implementation of micro hydro turbine for power generation and its...
 
Pump efficiency
Pump efficiencyPump efficiency
Pump efficiency
 
Design and development of pico micro hydro system by using house hold water s...
Design and development of pico micro hydro system by using house hold water s...Design and development of pico micro hydro system by using house hold water s...
Design and development of pico micro hydro system by using house hold water s...
 
New Library Ship Energy Systems
New Library Ship Energy SystemsNew Library Ship Energy Systems
New Library Ship Energy Systems
 
Cooling tower management
Cooling tower managementCooling tower management
Cooling tower management
 
BAKUN Hydropower Project
BAKUN Hydropower ProjectBAKUN Hydropower Project
BAKUN Hydropower Project
 
Proposed Design Models of Axial-Flux Permanent Magnet Synchronous Generator ...
Proposed Design Models of Axial-Flux Permanent Magnet  Synchronous Generator ...Proposed Design Models of Axial-Flux Permanent Magnet  Synchronous Generator ...
Proposed Design Models of Axial-Flux Permanent Magnet Synchronous Generator ...
 
IJSRED-V2I2P6
IJSRED-V2I2P6IJSRED-V2I2P6
IJSRED-V2I2P6
 
International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)
 
Ntpc barh (bstpp)
Ntpc barh (bstpp)Ntpc barh (bstpp)
Ntpc barh (bstpp)
 
XANT SPS wind powered water pumping for africa and the middle east
XANT SPS   wind powered water pumping for africa and the middle eastXANT SPS   wind powered water pumping for africa and the middle east
XANT SPS wind powered water pumping for africa and the middle east
 
XANT SPS WindWell wind powered water pumping for africa and the middle east
XANT SPS WindWell  wind powered water pumping for africa and the middle eastXANT SPS WindWell  wind powered water pumping for africa and the middle east
XANT SPS WindWell wind powered water pumping for africa and the middle east
 
2 PCCE White_Paper-Rev5
2 PCCE White_Paper-Rev52 PCCE White_Paper-Rev5
2 PCCE White_Paper-Rev5
 

Poster_Humpback_Hydro

  • 1. Acknowledgments We would like to thank Mark Legacy from Humpback Hydro passing this project along to the UBC Capstone program and giving us the opportunity to work on this project. We would also like to thank our faculty supervisor Dr. Joshua Brinkerhoff for taking the time to support us through the Capstone project. Introduction The purpose of this project is to complete proof of concept design of Humpback Hydro’s patented Ocean Hydro Energy Storage System. A conventional Pumped Storage Hydro system uses two reservoirs to store energy. The top reservoir is land locked and requires a high elevation, while the bottom reservoir is either a lake or an ocean. During peak energy demand, water is run from the high reservoir to the low reservoir through a turbine to generate electrical power through a hydro turbine. During low energy demand, the upper reservoir is replenished. The Humpback Hydro system takes this conventional Hydro Energy storage principle found on shore and places it in an offshore environment. There are four main deliverables for this project which includes determining the system efficiency, developing a computer program to aid in sizing these facilities, selecting power generation equipment and completing CAD modelling of the system. Design Requirements System Analysis The system was analyzed to estimate the efficiency of the system and the amount of concrete required. This analysis also indicated reservoir volumes, penstock and pipe diameters, power requirements, required head, and flow rates. The efficiency of the system was analyzed by modelling the system and including the efficiencies of the turbomachinery [2] and accounting for head losses. Figure 2 below shows the efficiency for various combinations of head ratio (HR) which is the upper turbine head divided by lower turbine head. Conclusions All objectives were met with the following deliverables: 1) Determined that a 10 MW facility, with 3 hours of storage time, and 6 hours to replenish the upper reservoir, can achieve an efficiency of 70.2% and requires 220,000 cubic meters of concrete. 2) Developed a MATLAB Graphical User Interface which enables the user to input required power, storage time, and low demand duration to calculate efficiency, concrete amount, flow rates, penstock sizes, and required head. 3) Selected power transmission equipment including a TMEIC 4 Pole Generator and a three phase HPS transformer. 4) Completed CAD modelling of the system including an animation illustrating the operating principles of the Ocean Hydro Energy Storage System. Ocean Hydro Energy Storage System Shariq Codabux, Mitchell Lamoureux, David Martens, Billy Su Faculty Advisor: Joshua Brinkerhoff, Industry Collaborator: Humpback Hydro Group #8 References [1] M. A. Herzog, Practical dam analysis, London: Thomas Telford Publishing, 1999. [2] S. L. Dixon and C. A. Hall, Fluid Mechanics and Thermodynamics of Turbomachinery, Oxford: Elsevier, 2010. [3] T. M. E. I. C. CORPORATION, "http://www.tmeic.com/Repository/Other s/4P%20TG.pdf," [Online]. [4] H. P. Systems, "Dry-Type Medium Voltage Distribution [Power] Transformer," Hammond Power Solutions Inc. , 2014. [5] Humpback Hydro, "Humpback Hydro Inc, Grid Scale Energy Storage Technology," Vancouver, 2014. For further information For further information contact Mitchell Lamoureux Mitchell.Lamoureux@gmail.com Fig. 1. Schematic showing operation of the Ocean Hydro Energy Storage System [5] Design Description The Humpback Hydro System as shown in Figure 1 operates using the following processes: • 1-2 Water is run through the lower turbine generating power • 2-3 Water is pumped to the upper reservoir • 3-1 Water is released through the upper turbine again generating power Processes 1-2 and 3-1 occur simultaneously during peak electricity demand and process 2-3 will occur during low demand. Fig. 2. Efficiency of 10 MW System for Various Combinations of Head Ratios Electrical The power transmission set includes a generator and a power transformer to meet local power grid standards. This set consists of a generator and transformer as described in Table 3. Graphical User Interface The design of the Ocean Energy Storage System will vary depending on the end user requirements. A graphical user interface (GUI) was developed using MATLAB to aid in the sizing of the system (Figure 3). The GUI performs calculations to size penstocks, piping, reservoir volume, and heights of the system. It optimizes the system based on the highest efficiency and minimal concrete when provided with the following inputs from the user: • Required Power • Storage Time • Low Demand Duration CAD Modelling/FEA Solid modelling was completed using the values from Table 2. This system will have a provide 10MW of power over three hours, and replenish the upper reservoir in six hours. Using these values, the system was modelled using Autodesk Inventor. Figure 4 shows a cross section of the system showing the components of the system. The components in green include the lower penstock, generator, and turbine. the blue shows the pumping and piping system, and the red shows the lower penstock and generator. Fig. 3. Graphical User Interface 1) User Inputs 2) Push Button To Calculate 3) GUI Outputs The gravity dam surrounding the system is designed to withstand the hydrostatic and dead loads acting upon it. Specifically, the dam is designed to have: • Safety Factor in Compression > 3 • Safety Factor Against Sliding > 1.5 • 0 tensile stresses [1] Table 2 list the parameters calculated for a plant generating 10 MW, storage time of 3 hours, and replenishing the upper reservoir in 6 hours. This system was the most efficient with the least amount of concrete from the analysis. Requirements • Dam shall be designed to withstand the hydrostatic and dead loads acting on the structure • Structure/Components will withstand the corrosive nature and extreme weather conditions of the ocean. • Power will output as 50 or 60 Hz AC as specified by regional power requirements • The design should address the life cycle of the plant to be 65-80 years • The design should allow for maintenance to the electrical/mechanical components • The selected facility will sustain 10 MW of power over 3 hours, and replenish the upper reservoir in 6 hours. Table 2. Calculated Parameters for the 10 MW Ocean Hydro Storage System Parameter Value Lower Turbine Power Output 2.86 MW Lower Turbine Head 20 m Lower Penstock Diameter 1.6 m Lower Reservoir Volume 170,000 Upper Turbine Power Output 7.14 MW Upper Turbine Head 50 m Upper Penstock Diameter 1.6 m Upper Reservoir Volume 170,000 Pump Flow Rate 7.9 /s Pump Power 7.12 MW Total Amount of Concrete 220,000 Total System Efficiency 70.2% Parameter Value Lower Turbine Power Output 2.86 MW Lower Turbine Head 20 m Lower Penstock Diameter 1.6 m Lower Reservoir Volume Upper Turbine Power Output 7.14 MW Upper Turbine Head 50 m Upper Penstock Diameter 1.6 m Upper Reservoir Volume Pump Flow Rate Pump Power 7.12 MW Total Amount of Concrete Total System Efficiency 70.2% Table 1. List of Design Requirements Using the CAD model a finite element analysis (FEA) stress analysis was completed. The FEA examined the stresses in a full upper reservoir, to indicate the maximum stresses and minimum safety factors obtained in the structure. Figure 5a below shows the safety factor of the structure, while Figure 5b shows the von misses stress in the structure. Fig. 4. System Overview showing all components Fig. 5. Stress simulation of fluid acting on the upper reservoir a) Safety Factor b) Von Mises Stress Component Description 4 Pole Generator • The required generator must be rated for 1-10 MW, with a frequency of 60 Hz • A TMEIC 4 Pole generator is a viable option [3] Power Transformer • The transformer must have the same frequency, power rating, and input voltage as the generator • A three phase HPS Dry Type transformer is a viable option [4] Table 3. Electrical Components and their descriptions 1 2 3 Efficiency vs. Lower Turbine Head a) b)