Training material for
                                                      VMS-NSN project


Training material for VMS-NSN project / Jul. 2011
                                                            R 0.1           Delta Confidential   1
Contents
                   1              System introduction

                     2             Quick Installation – parameter setting

                     3             Controller introduction

                     4             NRMS software introduction

                     5             Troubleshooting & Maintenance

                     6             Q&A


Training material for VMS-NSN project / Jul. 2011                           Delta Confidential   2
Contents
                   1              System introduction

                     2             Quick Installation – parameter setting

                     3             Controller introduction

                     4             NRMS software introduction

                     5             Troubleshooting & Maintenance

                     6             Q&A


Training material for VMS-NSN project / Jul. 2011                           Delta Confidential   3
Telecom power system concept




                                                                                                                                                   LOAD (Switch ,ADSL…E.T.C.)
      AC Input




                                                                                                 Output DC Distribution Unit
                                                    AC Distribution Unit   Rectifier # 1

    Generator                                                              Rectifier # 2
                                                                                                                               Battery
                                                                           Rectifier # 3
        U.P.S
                                                                                                                                  LVDS
                                                                           Rectifier # N




                                                                           Control Supervisory
                                                                           Unit (CSU)




Training material for VMS-NSN project / Jul. 2011                                                                                        Delta Confidential                     4
INDOOR POWER SYSTEM - ESAA150-FTA11

                 Power System
                    – Three phase / 4 line (3W-N-PE/220V)
                    – Power System with 3 rectifier slots
                    – Distribution:
                           – Load Breaker: (High PL) 20A x 2 + 10A x 2;
                                            (Low PL) 100A x 1 + 40A x 3 (DIN Rail)
                           – Battery Breaker: 125A x 2 (DIN Rail)
                    – Protection:
                           – 01 x AC Surge included
                           – 01 x DC surge included
                    – Alarm relay: 8 positions, 7 positions definable
                 Rectifier module: 3 * DPR 2700
                 DC Output Voltage: 54Vdc (40~59 Vdc)
                 Controller: CSU501+
                 Local access: NRMS through mini USB interface
                 (Optional) Web/SNMP for remote monitoring and control
                                                                                     ESAA150-FTA11




Training material for VMS-NSN project / Jul. 2011                                                    Delta Confidential   5
INDOOR POWER SYSTEM - ESAA150-FTA11
                               High priority load
                               20A x 2 + 10A x 2
                                                                                                   AC surge        AC I/P breaker
                                                                      Low priority load
                                                                                                    arrestor          3P/40A
        Battery breaker                                              100A x 1 + 40A x 3
           125A x 2




                                                     Mini
                   Controller                       USB port                   Alarm dry contact                   Temperature
                    CSU501                                                      Terminal block                    sensor TA & TB

                                                               Web/SNMP                               DC surge
                                                               (Optional)                              arrestor
Training material for VMS-NSN project / Jul. 2011                                                                     Delta Confidential   6
KEYS COMPONENT – ESAA150-FTA11




       Controller CSU 501+                                            Power distribution unit




          Web board (optional)

                                                                       Rectifier DPR2700W




              Battery string                                            19” Rectifier shelf




Training material for VMS-NSN project / Jul. 2011                                        Delta Confidential   7
System Drawing




Training material for VMS-NSN project / Jul. 2011                    Delta Confidential   8
OUTDOOR POWER SYSTEM – ESOA150-FAC01

                 Outdoor Power System
                    – Single Layer / Aluminum / Double Door / IP 54 / Fan Cooling
                    – 12U equipment space reserved
                    – Cable: 1/2" Jumper Cable x 06 + cable Glands x 06.
                    – Fan speed control for reducing audible noise
                 Power System
                    – Three phase / 4 line (3W-N-PE/220V)
                    – Power System with 3 rectifier slots
                    – Distribution:
                           – Load Breaker: (High PL) 20A x 2 + 10A x 2;
                                            (Low PL) 100A x 1 + 40A x 3 (DIN Rail)
                           – Battery Breaker: 125A x 2 (DIN Rail)
                    – Protection:
                           – 01 x AC Surge
                           – 01 x DC Surge
                    – Alarm relay: 8 positions, 7 positions definable
                 Rectifier module: 3 * DPR 2700/ 2900 HE
                 Local access: NRMS through mini USB interface
                 (Optional) Web/SNMP for remote monitoring and control
                 Outline Dim.: (H*W*D): <2000mm x 750mm x 720mm (Body)




Training material for VMS-NSN project / Jul. 2011                                    Delta Confidential   9
OUTDOOR POWER SYSTEM – ESOA150-FAC01



        12U space for NSN                                        Fan cooling
        Customer equipment



     DC Power system
     ESAA150-FTA Series
     Power System with 3
     rectifier slots
     (Rear side access)

        Battery tray 1



        Battery tray 2
                                                                 Cable Gland x 6 +
                                                                 1/2" Jumper Cable x 06

                                                    Front View                            Front Side
 Dimension (H*W*D): < 2000mm x 750mm x 720mm
Training material for VMS-NSN project / Jul. 2011                                                Delta Confidential   10
OUTDOOR POWER SYSTEM – ESOA150-FAC01



        12U space for NSN
        Customer equipment



     DC Power system
     ESAA150-FTA Series
                                                                DPR 2900 /
     Power System with 3
                                                                2700W Rectifier
     rectifier slots
     (Front side access)

        Battery tray 1



        Battery tray 2




                                                    Rear View                     Rear Side
Training material for VMS-NSN project / Jul. 2011                                             Delta Confidential   11
KEY COMPONENTS – ESOA150-FAC01




            Power shelf: SB-23N/HJ E

                                                                        Fan tray (EX-F01B)



                Rectifier DPR2700W




                                                                     Controller CSU 501+




                     Battery string
                                                                      Web board (optional)


Training material for VMS-NSN project / Jul. 2011                                    Delta Confidential   12
Power shelf - ESOA150-FAC01
                               High priority load
                               20A x 2 + 10A x 2
                                                                                                   AC surge        AC I/P breaker
                                                                      Low priority load
                                                                                                    arrestor          3P/40A
        Battery breaker                                              100A x 1 + 40A x 3
           125A x 2




                                                     Mini
                   Controller                       USB port                   Alarm dry contact                   Temperature
                    CSU501                                                      Terminal block                    sensor TA & TB

                                                               Web/SNMP                               DC surge
                                                               (Optional)                              arrestor
Training material for VMS-NSN project / Jul. 2011                                                                     Delta Confidential   13
OUTDOOR POWER SYSTEM – ESOA150-FAC01
   Alarm – CCU Board




             Alarm dry
             contact




                   CCU
                   Board




Training material for VMS-NSN project / Jul. 2011                Delta Confidential   14
OUTDOOR POWER SYSTEM – ESOA150-FAC01
                CCU Relay Positions and Definition




                                                           NO
                                                           COM
                                                           NC
                                                                 Cooling alarm

                                                           NO
                                                           COM   Environments alarm
                                                           NC




                               Environment control Board
Training material for VMS-NSN project / Jul. 2011                                     Delta Confidential   15
OUTDOOR POWER SYSTEM – ESOA150-FAC01
      PDU Relay Positions and Definition
     Alarm
                      PIN              Alarm Setting                      Alarm Description
     Relay

                  1     NO

        1         2     COM         AC off              AC off

                  3     NC

                  4     NO

        2         5     COM         Rectifier failure   Any Rectifier Failure

                  6     NC

                  7     NO
                                                        CSU Hardware Failure
        3         8     COM         CSU Failure
                                                        (Hardware setting can not defined by yourself)
                  9     NC

                 10     NO

        4        11     COM         LVDS trip           Low voltage disconnect

                 12     NC

                 13     NO
                                                        Ambient Temperature High (TA2H)
        5        14     COM         High temperature
                                                        Battery Temperature High (TB1H)
                 15     NC

                 16     NO

        6        17     COM         Major Alarm         Major Alarm

                 18     NC

                 19     NO

        7        20     COM         Minor Alarm         Minor Alarm

                 21     NC

                 22     NO
                                    N/A
        8        23     COM                             Don’t use

                 24     NC

Training material for VMS-NSN project / Jul. 2011                                                        Delta Confidential   16
OUTDOOR POWER SYSTEM – ESOA150-FAC01
   Cable entries

                 6pcs of bottom cable entries reserved




                 1pce MG32A 1-hole Cable Gland
                 For AC input (spare)




                 3pcs MG32A 2-hole Cable Gland
                 For cable range (OD): 12mm




                2pce 3-hole Cable Gland
                For cable range (OD): 12mm


Training material for VMS-NSN project / Jul. 2011                    Delta Confidential   17
OUTDOOR POWER SYSTEM – ESOA150-FAC01
   NSN equipment
   Grounding bus bar




     Main Grounding Bus bar with 6pcs M6
     insert nut for NSN equipment




Training material for VMS-NSN project / Jul. 2011                Delta Confidential   18
OUTDOOR POWER SYSTEM – ESOA150-FAC01
   Power system
   Grounding bus bar




     Main Grounding Bus bar x 1 with 6pcs M6
     insert nut for for Power system grounding.




Training material for VMS-NSN project / Jul. 2011                Delta Confidential   19
OUTDOOR POWER SYSTEM – ESOA150-FAC01
   Air filter module




      Suggestion:
              Clean: 1~2 Months using vacuum cleaner
              Replacement: 6~12 Months

Training material for VMS-NSN project / Jul. 2011                Delta Confidential   20
OUTDOOR POWER SYSTEM – ESOA150-FAC01
       AC terminal & AC Grounding bus bar




Training material for VMS-NSN project / Jul. 2011                Delta Confidential   21
OUTDOOR POWER SYSTEM – ESOA150-FAC01
       AC socket, AC breaker & Fan breaker




Training material for VMS-NSN project / Jul. 2011                Delta Confidential   22
System Drawing




Training material for VMS-NSN project / Jul. 2011                    Delta Confidential   23
48 VDC equipment for RNC (8900W)

                 Power System
                    – Three phase / 4 line (3W-N-PE/220V)
                    – Power System with max.12 rectifier slots
                    – Distribution:
                           1. Main AC breaker 3P 380Vac type
                           2. AC Surge Protection
                           3. Rail 1 Breaker X 16 (DIN rail C120 type ) 125A x1;100A
                              x1; 80A x1
                           4. Rail 2 Breaker x23 (DIN rail C60 type) 63x3; 50Ax1; 40Ax1;
                              32Ax1; 25Ax1;20Ax116Ax1; 10Ax1
                           5. Rail 3 Breaker X 16 (DIN rail C120 type ) 125A x1;100A
                              x1; 80A x1
                           6. Battery Fuse X 4 (400A x2 )
                    – Alarm relay: 8 positions, 7 positions definable
                 Rectifier module: 10 * DPR 2000
                 DC Output Voltage: 54Vdc (40~59 Vdc)
                 Local access: NRMS
                 Optional Web/SNMP for remote monitoring and control



                                                                                           ES 48/600-UBA02
Training material for VMS-NSN project / Jul. 2011                                                     Delta Confidential   24
48 VDC equipment for Transport node Hub Site
                                             (Tellabs) (1000W)
                 Power System
                    – Three phase / 4 line (3W-N-PE/220V)
                    – Power System with 3 rectifier slots
                    – Distribution:
                           – Load Breaker: (High PL)10A x 2;
                                            (Low PL) 32A x 2;
                           – Battery Breaker: 125A x 2 (DIN Rail)
                    – Protection:
                           – 01 x AC Surge included
                           – 01 x DC surge included
                    – Alarm relay: 8 positions, 7 positions definable
                 Rectifier module: 2 * DPR 2000
                 DC Output Voltage: 54Vdc (40~59 Vdc)
                 Controller: CSU501+
                 Local access: NRMS through mini USB interface
                 Optional Web/SNMP for remote monitoring and control
                                                                        ESAA150-FTA Series + 0.75M Lion rack




Training material for VMS-NSN project / Jul. 2011                                                Delta Confidential   25
48 VDC equipment for Transport Node RNC Site
                                               (2000W)
                 Power System
                    – Three phase / 4 line (3W-N-PE/220V)
                    – Power System with 3 rectifier slots
                    – Distribution:
                           – Load Breaker: (High PL)10A x 2;
                                            (Low PL) 32A x 4;
                           – Battery Breaker: 125A x 2 (DIN Rail)
                    – Protection:
                           – 01 x AC Surge included
                           – 01 x DC surge included
                    – Alarm relay: 8 positions, 7 positions definable
                 Rectifier module: 3 * DPR 2000
                 DC Output Voltage: 54Vdc (40~59 Vdc)
                 Controller: CSU501+
                 Local access: NRMS through mini USB interface
                 Optional Web/SNMP for remote monitoring and control
                                                                        ESAA150-FTA Series + 0.75M Lion rack




Training material for VMS-NSN project / Jul. 2011                                                Delta Confidential   26
48 VDC equipment for BSC/PCU site (3200W)

                 Power System
                    – Three phase / 4 line (3W-N-PE/220V)
                    – Power System with 4 rectifier slots
                    – Distribution:
                           – Load Breaker: (High PL)10A x 2 + 20A x 2;
                                            (Low PL) 100A x 2 + 40A x 2;
                           – Battery Breaker: 125A x 3 (DIN Rail)
                    – Protection:
                           – 01 x AC Surge included
                           – 01 x DC surge included
                    – Alarm relay: 8 positions, 7 positions definable
                 Rectifier module: 4 * DPR 2000
                 DC Output Voltage: 54Vdc (40~59 Vdc)
                 Local access: NRMS software
                 Optional Web/SNMP for remote monitoring and control




                                                                           ES 48/200-UQB03
                                                                           + 1.5M Lion rack
Training material for VMS-NSN project / Jul. 2011                                       Delta Confidential   27
48 VDC equipment for TC site (3720W)

                 Power System
                    – Three phase / 4 line (3W-N-PE/220V)
                    – Power System with 4 rectifier slots
                    – Distribution:
                           – Load Breaker: (High PL)10A x 2;
                                            (Low PL) 100A x 2 + 16A x 4;
                           – Battery Breaker: 125A x 3 (DIN Rail)
                    – Protection:
                           – 01 x AC Surge included
                           – 01 x DC surge included
                    – Alarm relay: 8 positions, 7 positions definable
                 Rectifier module: 4 * DPR 2700
                 DC Output Voltage: 54Vdc (40~59 Vdc)
                 Local access: NRMS software
                 Optional Web/SNMP for remote monitoring and control




                                                                           ES 48/200-UQB04
                                                                           + 1.5M Lion rack
Training material for VMS-NSN project / Jul. 2011                                       Delta Confidential   28
DP 2700 Series Rectifier

                                                            Features and Benefits
                                                             -48V/56A, Output; Max. Power 2700W
                                                             Wide Input Voltage Range (90V~300V)
                                                             Power Factor Correction (>0.99)
                                                             Hot-pluggable, All Connectors are at the rear
                                                             Compact Size
                                                                 ≅ 34W/in3 (48V) Power Density
                                                                 Dimension:42mm/1U(H)*125.5mm/2.8U(W)*268mm(D)
                                                                 Light weight:>2 Kg
                                                                 Horizontal(1U)/Vertical(2U) Models Available
                                                             High Efficiency: >91% (48V)
                                                             Fan cooling and Easy replaceable fan design
                                                             Operation temp.:-5oC~+75oC
                                                             UL/CUL,TUV/CE Certificated



Training material for VMS-NSN project / Jul. 2011                                                               Delta Confidential   29
AC Input Characteristic(48V)


              Wide AC input voltage range with derating below 176 V
              Maximum input current 19 A
              Input fuse 25A fast (L and N)




Training material for VMS-NSN project / Jul. 2011                                  Delta Confidential   30
DC Output Characteristic (48V)

              Max. Output Power: 2700W(-48V)
              Constant Power Design
              Output voltage 40 ... 59.5 Vdc
              Output fuse 30A x 3 (- pole)




                                        48




                                                                                 56
Training material for VMS-NSN project / Jul. 2011                                     Delta Confidential   31
Thermal Management (CSU Control)
      OTP = Over Temperature Protection
      Ambient temperature sense for thermal management:
              OTP control is based on internal temperature
              OTP protection is based on critical internal temperature




         Power limit                                             Vinrms: 184
                                                                                       Rectifier
        2700                                                                            restart


        2300


                                                                                                   Ambient
                                                        55 °C                  65 °C       75 °C
Training material for VMS-NSN project / Jul. 2011                                                       Delta Confidential   32
Rectifier - Interface




                                                                                    Pin Number   Signal   Description



                                                                                           P4    VOP      Precharge

                                                                                         P5-P7   VO-      DC Output “-”

                                                                                        P8-P10   VO+      DC Output “+”

                                                                                          H1     SGNDO    Signal ground

                                      I/O Connector                                       H2     RS485+   RS 485 + communication

                                                                                          G1     CGND     Communication ground
                            Input                   Signal                 Output         G2     RS485-   RS 485 – communication

                                                                                           F1    INH      Short pin for well connection

                                                                                           F2    IDA      ID analog

                                                                                           E1    IDD      ID digital
                    Pin Number          Signal       Description
                                                                                           E2    IBUS     Load Sharing Bus
                           P1           AC_L         AC main, L terminal

                           P2           AC_N         AC main, N terminal

                           P3           FG           AC main, frame ground




Training material for VMS-NSN project / Jul. 2011                                                                                    Delta Confidential   33
Rectifier - Dimension




                       W x H x D=4.9 x 1.6 x 11.7 inch =125.5 x 40.5 x 270 mm
Training material for VMS-NSN project / Jul. 2011                           Delta Confidential   34
Contents
                   1              System introduction

                     2             Quick Installation – parameter setting

                     3             Controller introduction

                     4             NRMS software introduction

                     5             Troubleshooting & Maintenance

                     6             Q&A


Training material for VMS-NSN project / Jul. 2011                           Delta Confidential   35
Quick installation – system parameter
   Quick Installation via NRMS software (Step 1: Date & Time setting)




Training material for VMS-NSN project / Jul. 2011                                       Delta Confidential   36
Quick installation – system parameter
Quick Installation via NRMS software (Step 2: Battery capacity setting)
For this case, battery capacity is 300AH.




                                         Default setting
Training material for VMS-NSN project / Jul. 2011                                     Delta Confidential   37
Quick installation – system parameter
   Quick Installation via LCD display (Step 1: Date & Time setting)




                         Step 1-1




                                                          Step 1-2




                                                                             Step 1-3
Training material for VMS-NSN project / Jul. 2011                                       Delta Confidential   38
Quick installation – system parameter
   Quick Installation via LCD display (Step 2: Battery capacity setting). For this case,
   Battery capacity is 300AH




                         Step 2-1                                      Step 2-2




                                 Step 2-4
                                                                       Step 2-3

Training material for VMS-NSN project / Jul. 2011                                       Delta Confidential   39
START - UP PROCEDURE

                  START - UP PROCEDURE: Check-list and inspection before turn-on: Verify
                  all connections prior to starting this section

                  •       Ensure the input AC circuit breaker located on the AC service panel is
                          switched to “Off” position
                  •       Confirm the operating voltage before proceeding

                  •       Ensure the frame ground is properly connected to a permanent earth
                          ground connection

                  •       Ensure all the DC circuit breakers in the equipment are switched to the
                          “Off” position
                  •       Tighten the DC circuit breaker lugs to ensure proper contact is made with
                          the load cable and the trip sense wire as it may cause heat damage




Training material for VMS-NSN project / Jul. 2011                                                     Delta Confidential   40
START - UP PROCEDURE
                   Turn on the system

                                          Step 1     Check all wiring are correct

                                          Step 2     Check and confirm the input voltage is correct

                                          Step 3     Pull out all the rectifiers from the system

                                          Step 4     Switch on the battery breaker(s)

                                          Step 5     Check the monitor of display on the controller

                                          Step 6     Switch on the AC breaker

                                          Step 7     Check the monitor of display on the controller again

                                          Step 8     Push one rectifier into the rectifier slot

                                          Step 9     Check the system works in normal condition.

                                          Step 10    Push all other rectifier(s) into the rectifier slots

                                          Step 11    Switch on the load breaker(s) sequentially

Training material for VMS-NSN project / Jul. 2011                                                           Delta Confidential   41
START - UP PROCEDURE
                    Simple troubleshooting guide
                        Status                       Possible causes             Action
                        LCD display on the           AC utility does not           Check the AC utility
                        controller is “OFF”          supply to the system          Make sure the AC wire is properly connected at the AC input
                                                                                 terminal
                                                                                   Check the AC breaker position to “ON” position
                                                                                   Contact technician if problem still exists
                        All CSU LED are “OFF”        AC utility does not           Check the AC utility
                                                     supply to the system          Make sure the AC wire is properly connected at the AC input
                                                                                 terminal
                                                                                   Check the AC breaker position to “ON” position
                                                                                   Contact technician if problem still exists
                        Rectifier LEDs are           AC utility is not             Check the AC utility
                        “OFF”                        available                     Make sure the AC wire is properly connected at the AC input
                                                     Rectifier is not properly   terminal
                                                     placed                        Check the AC breaker position to “ON” position
                                                                                   Pull out the rectifier and insert it properly
                                                                                   Contact technician if problem still exists
                        System shows in normal       DC breaker is tripped        Check the load breaker position to “ON” position
                        operation but no output      LVDS2 did not re-            Change the breaker if breaker is overloaded in use.
                        to the load                  connect                      Check the system output voltage
                        No battery backup when       Battery breaker is no         Check the battery breaker position to “ON” position and check
                        AC fails                     connected or the            the battery voltage.
                                                     battery voltage too low       Change the battery
                                                     Battery life reaches
                                                     end
Training material for VMS-NSN project / Jul. 2011                                                                                         Delta Confidential   42
Alarm dry contact & SNMP card installation




                                                    ESAA150 – FTA11 Power Shelf


Training material for VMS-NSN project / Jul. 2011                                 Delta Confidential   43
Alarm dry contact




                                                    Alarm dry contact




Training material for VMS-NSN project / Jul. 2011                             Delta Confidential   44
Alarm dry contact

                  Type of contact: Dry contact is a contact
                  that is not initially connected to a voltage
                  source.
                  Alarm relay: 8 positions, 7 positions
                  definable
                  7 positions can be defined by NRMS
                  software
                  Local access: NRMS through mini USB
                  interface.
                                                                 Relay 8 7 6 5   4 3 2 1




Training material for VMS-NSN project / Jul. 2011                                      Delta Confidential   45
Alarm relay define
                                                    Relay & LED       Config




                Relay 8 7 6 5                         4 3 2 1




Training material for VMS-NSN project / Jul. 2011                                      Delta Confidential   46
Config
                                                             Alarm relay define
                                                                   Alarm relay & LED indicator can be defined
      Relay & LED




Training material for VMS-NSN project / Jul. 2011                                                          Delta Confidential   47
SADMIN level
          Pull down list for alarm relay & LED indicator define




Training material for VMS-NSN project / Jul. 2011                  Delta Confidential   48
Alarm dry contact




                                   Using tool to push the button
                                                                        Finish
                                   and connect the signal wire

Training material for VMS-NSN project / Jul. 2011                                Delta Confidential   49
Alarm dry contact – Default setting
  Alarm Relay              PIN                      Alarm Setting                 Alarm Description

                     1       NO

        1            2       COM           AC off                   AC off

                     3       NC

                     4       NO

        2            5       COM           Rectifier failure        Any Rectifier Failure

                     6       NC

                     7       NC
                                                                    CSU Hardware Failure
        3            8       COM           CSU Failure              (Hardware setting can not defined by
                                                                    yourself)
                     9       NO

                    10       NO

        4           11       COM           LVDS trip                Low voltage disconnect

                    12       NC

                    13       NO
                                                                    Ambient Temperature 2 Hi (TA2H)
        5           14       COM           High temperature         (Power bay, threshold= 45 ℃)
                                                                    Battery Temperature Hi
                    15       NC

                    16       NO

        6           17       COM           Major                    Major Alarm

                    18       NC

                    19       NO

        7           20       COM           Minor                    Minor alarm

                    21       NC

                    22       NO
                                           N.A
        8           23       COM                                    No define

                    24       NC


Training material for VMS-NSN project / Jul. 2011                                                          Delta Confidential   50
SNMP Card Installation
                         Web Server Function and Feature (Optional)
                                                            Features:
                                                             Applied in TCP/IP Internet/Intranet Environment
                                                             Complete Supervising to Power System
                                                             User-friendly Graphic Interface
                                                             Dynamic information presentation
                                                             Password function
                                                             Multi Language Support

                       Main Screen                           Microsoft Explorer and Netscape Support




                                                                 Parameter Setting
                         Status                                                         Configuration
                                                    Alarm
Training material for VMS-NSN project / Jul. 2011                                                              Delta Confidential   51
SNMP Card Installation (optional)
       Step 1: Relax 4 screws of controller



                                           4
                        2
                                                         1
            3




Training material for VMS-NSN project / Jul. 2011                                       Delta Confidential   52
SNMP Card Installation (optional)
       Step 2: Move out cover and prepare SNMP card kits




                         Controller without SNMP card                      SNMP card kits


Training material for VMS-NSN project / Jul. 2011                                           Delta Confidential   53
SNMP Card Installation (optional)
       Step 3: Connect signal cables




           Connect signal cables to SNMP terminal                    Connect signal cables to CSU
                                                                     Note: follow this picture to connect 2 cables. Web
                                                                     function may not work because of wrong wiring.
Training material for VMS-NSN project / Jul. 2011                                                              Delta Confidential   54
SNMP Card Installation (optional)
       Step 4: Fix SNMP Card (2 screws)




                                       Fix SNMP Card by 2 screws        SNMP Card connect port


Training material for VMS-NSN project / Jul. 2011                                                Delta Confidential   55
SNMP Card Installation (optional)
       Step 5: Recover CSU cover



                                               4


                                           2
                                                                1
                         3




                                       Fix CSU cover by 4 screws        Controller with SNMP card


Training material for VMS-NSN project / Jul. 2011                                                   Delta Confidential   56
Contents
                   1              System introduction

                     2             Quick Installation – parameter setting

                     3             Controller introduction

                     4             NRMS software introduction

                     5             Troubleshooting & Maintenance

                     6             Q&A


Training material for VMS-NSN project / Jul. 2011                           Delta Confidential   57
Controller – CSU 501+
              Reliable and user friendly controller
              User configurable alarms and settings
              Programmable DC output voltage
              Battery temperature compensated float voltage
              LVD contactor control
              Battery charging control
              Automatic battery testing
              LCD 128 x 64 dots display
              Entry of alarm and system parameters from PC via
              mini USB port
              Internet Web Server Function: By Web Server
              Software/SNMP via RJ45 (Option)
              Green Function / Efficiency management
              Hot plug in design

Training material for VMS-NSN project / Jul. 2011                           Delta Confidential   58
Controller CSU 501+
   User Interfaces


                                                                    Internet Web Server
                                                                   Function port (optional)




                                                                                               Up
    Major LED
    Minor LED                                                                                 Down
    EQU LED
                                                                                              Enter
               ESC




                                                    128 x 64 LCD         Mini USB (slave)
                                                    Dots Display




Training material for VMS-NSN project / Jul. 2011                                                Delta Confidential   59
Controller CSU 501+
   Function architecture (MainData)
                                                                                    Home
                                                                                    DCV
                                                                                     DCI
                                                                             Sys Status(FL/EQU)
                                                                               Alarm Existing




                                                    Sys Info                       Sys Setting                               Current Alarm




       Rectifier                            Battery               Event Log                      Current .setting      AC & Temp            Data &
       I.D. Address                         Batt. String I.D.     Alarm Function Time            DC Setting            ACV Voltage          Version
       Output Current                       Batt.Status           Recover Time                   Alarm Setting         Ambient Temp.        Date/Time
       Status                               Batt. Current                                        Batt.Setting                               H/W version
                                                                                                 Other Setting                              S/W version



                                                                                   * DC/DC Data

                                                                                                      * Function architecture varies in different systems
Training material for VMS-NSN project / Jul. 2011                                                                                            Delta Confidential   60
Controller CSU 501+
   Function architecture (MainData)
                                                                             Home
                                                                             DCV
                                                                              DCI
                                                                      Sys Status(FL/EQU)
                                                                        Alarm Existing




                                          Sys Info                           Sys Setting                              Current Alarm


                                                                             Password




      DC Setting                   Alarm Setting     Batt. Setting     Date Setting        Efficn.t Mgt.         Generator           Temp. Unit
      DCV setting                  ACV,              Batt. Par.        Year/month/            ON/OFF              ON/OFF               ON/OFF
      CL setting                   DCV,LVDS,         T-Comp            day/time
                                   OTP,EQU,          BDT Test                                         Comm.
                                   Batt.Test.        B-EQU                                            Modbus
                                                                                                      Baudrate
                                                                                  Language
                                                                Password          English                                Alarm Reset
                                                                New PW Cfm        繁體中文                                   Reset HVSD
                                                                PW Default        簡體中文                                   Reset Com-fail
                                                                (0000)
                                                                                           * Function architecture varies in different systems
Training material for VMS-NSN project / Jul. 2011                                                                                     Delta Confidential   61
Controller CSU 501+
   Function architecture (MainData)


                                                                           Home
                                                                           DCV
                                                                            DCI
                                                                    Sys Status(FL/EQU)
                                                                      Alarm Existing




                                                Sys Info                 Sys Setting                         Current Alarm


                                                           All Alarm Function show on Display
                                    Show Real Information and Alarm Time in Event Log




                                                                                         * Function architecture varies in different systems
Training material for VMS-NSN project / Jul. 2011                                                                              Delta Confidential   62
Display Menu Tree




Training material for VMS-NSN project / Jul. 2011                       Delta Confidential   63
Display Menu Tree




Training material for VMS-NSN project / Jul. 2011   Delta Confidential   64
Display Menu Tree




Training material for VMS-NSN project / Jul. 2011   Delta Confidential   65
Display Menu Tree




Training material for VMS-NSN project / Jul. 2011   Delta Confidential   66
Display Menu Tree




Training material for VMS-NSN project / Jul. 2011   Delta Confidential   67
Display Menu Tree




Training material for VMS-NSN project / Jul. 2011   Delta Confidential   68
Contents
                   1              System introduction

                     2             Quick Installation – parameter setting

                     3             Controller introduction

                     4             NRMS software introduction

                     5             Troubleshooting & Maintenance

                     6             Q&A


Training material for VMS-NSN project / Jul. 2011                           Delta Confidential   69
NRMS software introduction




                                                                 Mini U
                                                                        SB
                                                                                 Local Access




Training material for VMS-NSN project / Jul. 2011                                         Delta Confidential   70
Mini USB



       The files is **.EXE files,
       So just double clock it                      Local Access




Training material for VMS-NSN project / Jul. 2011                  Delta Confidential   71
NRMS H/W Tools
             1.        H/W Mini USB Cable
             2.        Delta NRMS software
             3.        Computer with USB port




                                                               Mini USB Cable




Training material for VMS-NSN project / Jul. 2011                               Delta Confidential   72
User level login




                                                              The port must be
                                                                match your
                                                                PC/Laptop




Training material for VMS-NSN project / Jul. 2011                                Delta Confidential   73
User level login – Find the
                                                    comm Port in your computer




      Click to Device
         Manager




Training material for VMS-NSN project / Jul. 2011                                  Delta Confidential   74
User level login – Find the
                                                    comm Port in your computer




      Click to Ports (COM
             & LPT)




Training material for VMS-NSN project / Jul. 2011                                  Delta Confidential   75
User level login




                                                            Push this button
                                                             to connect to
                                                                system




Training material for VMS-NSN project / Jul. 2011                              Delta Confidential   76
User level
                                                             NRMS Version
                     CSU

               System data

           DC O/P voltage
            Ambient Temp.
                Load current
               Total current
            (load + battery)
                                                              Buzzer stop
   AC voltage (Phase1)
                                                      Manual battery Test
   AC voltage (Phase 2)
                                                            Manual EQU
    AC voltage (phase 3)




                                                          Software Version
                                                         Firmware Version
              System status                                     Login level
                                                            System voltage
     RMS software status                                      System time



Training material for VMS-NSN project / Jul. 2011                             Delta Confidential   77
User level
                                                  Max.          No. of      No. of        No. of     No. of rectifier      Clear
                                              rectifier slot   rectifier   rectifier     rectifier   communication      communication
                                               in system        failure    working     turned Off        error             error
                   Rectifier




                                                               Rectifiers
                                                                status




Training material for VMS-NSN project / Jul. 2011                                                                                   Delta Confidential   78
User level
              Battery

Total Batt. current
(+: charge)
(-: discharge)
                                                                                        Batt. 1 Temp.
Batt. capacity
                                                                                        Batt. 2 Temp.
                                                     Batt. 1 current                    Batt. 3 Temp.

                                                     Batt. 2 current
                                                     Batt. 3 current




                                              Batt. middle point Vol 1

                                             Batt. middle Point Vol 2
                                              Batt. middle point Vol 3
                                             Batt. middle Point Vol 4




Training material for VMS-NSN project / Jul. 2011                                     Delta Confidential   79
Parameter
                                                                User level

                  System

                                                                                                            AC High
       DCV high setting point                                                                               AC Low
         DCV low setting point
                                                                                                            Energy Saving
   Pre DCV low setting point
                                                                                                            SMR Max. Current
  HV shutdown setting point

                LVDS1 trip point
                LVDS2 trip point                                                                                Time Setting

                LVDS3 trip point                                                                    Manual LVDS1 Trip
                    Float voltage
                                                                                                    Manual LVDS2 Trip
                    EQU voltage

            Ambient temp. high

             Ambient temp. low

        High temp. shutdown
                                                                        Alarm when current over
         Low temp. shutdown                                             80% of rectifier capacity




Training material for VMS-NSN project / Jul. 2011                                                                       Delta Confidential   80
Delta Power System LVDS Behavior

  Power System                                            Battery                         Power System                       Battery
                              Rectifier                             Battery Volt                                                       Battery Volt
                              Volt (54V)                            (54V)                                                              (54V)
         Energy                                           Energy                            Energy                           Energy

                                 BLVD                                                                    BLVD
                                Battery Low                                                              Battery Low
                                Voltage                                       Rectifier                  Voltage
                                Disconnect                                    Volt (0V)                  Disconnect

                                                                    Current                                                            Current
                                                          BLVD      Sensor                                                             Sensor
                                                          Close                                                          BLVD
                                                                                                                         Close
                                                          LVDS2                                                              LVDS2
                                                          Close                                                              Close

                                   PL               NPL                                                  PL            NPL
                                                                                                         Output (Load)
                              Output (Load)

                              Normal (AC)                                                       Discharge (AC break off)
Training material for VMS-NSN project / Jul. 2011                                                                                       Delta Confidential   81
Delta Power System LVDS Behavior


              Power System                                       Battery                     Power System                       Battery


                    Energy                                       Energy    Battery Volt
                                                                                               Energy                           Energy
                                                                           (46V)
                                                                                                                                           Battery Volt
                                              BLVD                                                          BLVD                           (42V)
                                             Battery Low                                                    Battery Low
 Rectifier                                   Voltage                             Rectifier                  Voltage
 Volt (0V)                                   Disconnect                          Volt (0V)                  Disconnect



                                                                 BLVD                                                      BLVD Trip (42V)
                                                                 Close


                                                             LVDS2 Trip (46V)                                                   LVDS2
                                                                                                                                Open
                                                       X                                                         X X
                                               PL          NPL                                              PL            NPL
                                              Output (Load)                                                 Output (Load)


                             Discharge (LVDS2 Trip)                                                Discharge (BLVD Trip)
Training material for VMS-NSN project / Jul. 2011                                                                                     Delta Confidential   82
Delta Power System LVDS Behavior

     Power System                                         Battery                  Power System                Battery


           Energy                                         Energy                     Energy                    Energy
                               Rectifier                            Battery Volt              Rectifier                  Battery Volt
                               Volt (45V)                           (45V)                     Volt (49V)                 (49V)




                                                                                                               BLVD
                                                          BLVD Auto recover                                    Close
                                                          (42V + 3V=45V)


                                                          LVDS2                                                 LVDS2 Auto
                                                          Open                                                  recover (46V +
                                                    X                                                           3V=49V)
                                      PL            NPL                                         PL      NPL
                                  Output (Load)                                                Output (Load)


                 Battery recharge                                                        Battery recharge
                 (BLVD Recover)                                                          (LVDS2 Recover)
Training material for VMS-NSN project / Jul. 2011                                                                        Delta Confidential   83
Parameter
                                                                  User level

            Battery


             Battery capacity                                                  Batt. Test Function

    Batt. Temp. High ALM                                                       Test Time
          Batt. Middle point                                                   Test Criterion
                                                                               Discharge current for test

 SMR max. current limit
    Charge Management
                                                                               Batt. Periodic Test Function
                Charge CL 1
               Charge CL -2                                                    Test Periodic
               Charge CL -3                                                    Which day do the test
                                                                                What time do the test
                                                      Last batt. Test Time

                                                      Next batt. Test Time




Training material for VMS-NSN project / Jul. 2011                                           Delta Confidential   84
Concept of Battery Charge Current Limit



                                                                                                     Battery Capacity x Charge rate = Charger Current

                                                                                                     In this case, battery capacity is 300Ah, so:
                                                                                                                   300Ah x 0.2C = 60A (battery charge current)
                                                                                                                   300Ah x 0.1C = 30A (battery charge current)

                                                                                                  EqulizeVoltage
                                                            Charge Voltage and Charge Current

                                                                                                   Float Voltage

                                                                                                Deeply Discharge
                                                                                                    Voltage


                                                                                                Battery current                 Stage - 1 Current Limit
                                                                                                                                                          Stage - 2 Current Limit

                                                                                                                                                                                           Stage - 3 Current Limit
                                                                                                        0V / 0A                                                                              EQU stop current



                                                                                                                                                                                    Time




Training material for VMS-NSN project / Jul. 2011                                                                                                                                     Delta Confidential        85
Parameter
                                                      User level

      Temp.
   Compensation

  Temp. Compensation                                               Coefficient (per cell) of
  Function                                                         Temp. Compensation
  Compensation Mode                                                Max. Range of Compensation
                                                                   Center of temp.




                                                                      System volt of T0

                                                                      System volt of T1

                                                                      System volt of T2
                                                                      System volt of T3




Training material for VMS-NSN project / Jul. 2011                                    Delta Confidential   86
Parameter
                                                      User level

              EQU



         Equalize charge
                                                                                  Batt. remaining capacity
        EQU Max. Time
                                                                                  System voltage
 Additional EQU Time
                                                                                  AC fail time
 Criterion for stop EQU
                                                                                  Discharge Current

Periodic EQU Function
                                                       Criteria for enforce EQU
                     Periodic
      Which day enforce
       What time enforce

           Last EQU Time

         Next EQU Time




Training material for VMS-NSN project / Jul. 2011                                         Delta Confidential   87
Parameter
                                                      User level

   Alarm Mask


  Rectifier current limit                                                                 TB sensor fail alarm
         One rectifier fail                                                               Battery temp. high
More than 1 rectifier fail                                                                Battery fuse fail
                Major alarm                                                               Battery discharge
                Minor alarm                                                               Battery breaker trip
        Load breaker trip                                                                 Middle test fail
High priority breaker trip                                                                Battery test fail
Low priority breaker trip                                                                 Rect. Over capacity
                                                                   DCV high alarm
              Load fuse fail                                       DCV low alarm
            Load rail alarm                                        LVDS 2 trip
                                                                   LVDS trip alarm
              GMT fuse fail                                        TA high alarm
                                                                   TA low alarm
                                                                   TA sensor fail alarm
                                                                   ACV high alarm
                                                                   ACV low alarm
                                                                   AC breaker trip
                                                                   AC phase lost alarm



Training material for VMS-NSN project / Jul. 2011                                            Delta Confidential   88
Parameter
                                                       User level

                  WEB


                  IP Address

               Subnet Mask

                     Gateway




Training material for VMS-NSN project / Jul. 2011                   Delta Confidential   89
Parameter
                                                       User level

                    CCU



             Fan 1 start point                                                                            Fan 2 start point
             Fan 1 stop point                                                                             Fan 2 stop point
  Duty for fan 1 full speed                                                                               Duty for fan 2 full speed

      Fan 1 full speed point                                                                              Fan 2 full speed point



       Start point for heater



                                                            Push this button then fan 2 run from
                                                            low speed to full speed
                                                             Push this button then fan 2 run full speed




Training material for VMS-NSN project / Jul. 2011                                                                 Delta Confidential   90
Alarm
                                                            User level

                system

     Alarm light with alarm




Training material for VMS-NSN project / Jul. 2011                        Delta Confidential   91
Alarm
                                                            User level

                   CCU



      Alarm light w/o alarm




Training material for VMS-NSN project / Jul. 2011                        Delta Confidential   92
Event
                                                     User level



                                                                  Record items
                                                                  Right now
                                                                  Clear all Event log
    Event log list


                                                                  Down load Event log




Training material for VMS-NSN project / Jul. 2011                     Delta Confidential   93
Setting
                                                              User level




                                                                           Modem configure
               Change permission

                Change password

  Logout (return to user level)




Training material for VMS-NSN project / Jul. 2011                                Delta Confidential   94
SADMIN level login




                       1




                                                                   2


                                                                   3

                                                                   4


                                                                         Password:
                                                                           8888
Training material for VMS-NSN project / Jul. 2011                        Delta Confidential   95
SADMIN level login




                                                                     5




Training material for VMS-NSN project / Jul. 2011                        Delta Confidential   96
SADMIN level
                                                              NRMS Version
                     CSU

               System data

           DC O/P voltage
            Ambient Temp.
                Load current
               Total current
            (load + battery)
                                                               Buzzer stop
   AC voltage (Phase1)
                                                       Manual battery Test
   AC voltage (Phase 2)
                                                             Manual EQU
    AC voltage (phase 3)




                                                           Software Version
                                                          Firmware Version
              System status                                      Login level
                                                             System voltage
     RMS software status                                       System time



Training material for VMS-NSN project / Jul. 2011                              Delta Confidential   97
SADMIN level
                                                  Max.          No. of        No. of        No. of     No. of rectifier        Clear
                                              rectifier slot   rectifier     rectifier     rectifier   communication        communication
                                               in system        failure      working     turned Off        error               error
                   Rectifier




                                                                                                                          Manual on/off
                                                                                                                            rectifier



                                                               Rectifiers
                                                                status




Training material for VMS-NSN project / Jul. 2011                                                                                         Delta Confidential   98
SADMIN level
              Battery

Total Batt. current
(+: charge)
(-: discharge)
                                                                                          Batt. 1 Temp.
Batt. capacity
                                                                                          Batt. 2 Temp.
                                                     Batt. 1 current                      Batt. 3 Temp.

                                                     Batt. 2 current
                                                     Batt. 3 current




                                              Batt. middle point Vol 1

                                             Batt. middle Point Vol 2
                                              Batt. middle point Vol 3
                                             Batt. middle Point Vol 4




Training material for VMS-NSN project / Jul. 2011                                       Delta Confidential   99
Parameter
                                                                SADMIN level

                  System

                                                                                                            AC High
       DCV high setting point                                                                               AC Low
         DCV low setting point
                                                                                                            Energy Saving
   Pre DCV low setting point
                                                                                                            SMR Max. Current
  HV shutdown setting point

                LVDS1 trip point
                LVDS2 trip point                                                                                Time Setting

                LVDS3 trip point                                                                    Manual LVDS1 Trip
                    Float voltage
                                                                                                    Manual LVDS2 Trip
                    EQU voltage

            Ambient temp. high

             Ambient temp. low

        High temp. shutdown
                                                                        Alarm when current over
         Low temp. shutdown                                             80% of rectifier capacity




Training material for VMS-NSN project / Jul. 2011                                                                       Delta Confidential   100
Parameter
                                                              SADMIN level

            Battery


             Battery capacity                                                Batt. Test Function

    Batt. Temp. High ALM                                                     Test Time
          Batt. Middle point                                                 Test Criterion
                                                                             Discharge current for test
 (SMR model selection )
 SMR max. current limit
    Charge Management
                                                                             Batt. Periodic Test Function
                Charge CL 1
               Charge CL -2                                                  Test Periodic
               Charge CL -3                                                  Which day do the test
                                                                              What time do the test
                                                      Last batt. Test Time

                                                      Next batt. Test Time




Training material for VMS-NSN project / Jul. 2011                                         Delta Confidential   101
Parameter
                                                      SADMIN level

      Temp.
   Compensation

  Temp. Compensation                                                 Coefficient (per cell) of
  Function                                                           Temp. Compensation
  Compensation Mode                                                  Max. Range of Compensation
                                                                     Center of temp.




                                                                        System volt of T0

                                                                        System volt of T1

                                                                        System volt of T2
                                                                        System volt of T3




Training material for VMS-NSN project / Jul. 2011                                      Delta Confidential   102
Parameter
                                                      SADMIN level

              EQU



         Equalize charge
                                                                                    Batt. remaining capacity
        EQU Max. Time
                                                                                    System voltage
 Additional EQU Time
                                                                                    AC fail time
 Criterion for stop EQU
                                                                                    Discharge Current

Periodic EQU Function
                                                         Criteria for enforce EQU
                     Periodic
      Which day enforce
       What time enforce

           Last EQU Time

         Next EQU Time




Training material for VMS-NSN project / Jul. 2011                                           Delta Confidential   103
Parameter
                                                      SADMIN level

   Alarm Mask

               System
  Rectifier current limit                                                                   TB sensor fail alarm
         One rectifier fail                                                                 Battery temp. high
More than 1 rectifier fail                                                                  Battery fuse fail
                Major alarm                                                                 Battery discharge
                Minor alarm                                                                 Battery breaker trip
        Load breaker trip                                                                   Middle test fail
High priority breaker trip                                                                  Battery test fail
Low priority breaker trip                                                                   Rect. Over capacity
              Load fuse fail                                         DCV high alarm
                                                                     DCV low alarm
            Load rail alarm                                          LVDS 2 trip
                                                                     LVDS trip alarm
              GMT fuse fail                                          TA high alarm
                                                                     TA low alarm
                                                                     TA sensor fail alarm
                                                                     ACV high alarm
                                                                     ACV low alarm
                                                                     AC breaker trip
                                                                     AC phase lost alarm



Training material for VMS-NSN project / Jul. 2011                                              Delta Confidential   104
Parameter
                                                      SADMIN level

   Alarm Mask

                    CCU

                   Fan 1 fail                                        Door open
                  Fan 2 fail                                         Fan 1 disconnect
                 Heater fail                                         Fan 2 disconnect
             Smoke alarm                                             Heater disconnect
            Humidity alarm                                           TA 2 sensor fail
       Water level alarm




Training material for VMS-NSN project / Jul. 2011                                        Delta Confidential   105
Parameter
                                                       SADMIN level

                  WEB


                  IP Address

               Subnet Mask

                     Gateway




Training material for VMS-NSN project / Jul. 2011                     Delta Confidential   106
Parameter
                                                       SADMIN level

                    CCU



             Fan 1 start point                                                                            Fan 2 start point
             Fan 1 stop point                                                                             Fan 2 stop point
  Duty for fan 1 full speed                                                                               Duty for fan 2 full speed

      Fan 1 full speed point                                                                              Fan 2 full speed point



       Start point for heater



                                                             Push this button then fan 2 run from
                                                             low speed to full speed
                                                             Push this button then fan 2 run full speed




Training material for VMS-NSN project / Jul. 2011                                                                 Delta Confidential   107
Alarm
                                                            SADMIN level

                system

     Alarm light with alarm




Training material for VMS-NSN project / Jul. 2011                          Delta Confidential   108
Alarm
                                                            SADMIN level

                   CCU



      Alarm light w/o alarm




Training material for VMS-NSN project / Jul. 2011                          Delta Confidential   109
Event
                                                     SADMIN level



                                                                    Record items
                                                                    Right now
                                                                    Clear all Event log
    Event log list


                                                                    Down load Event log




Training material for VMS-NSN project / Jul. 2011                       Delta Confidential   110
Config
                                                    SADMIN level
                                                                   Alarm level can be defined
 Alarm level

           System
              DCV high                                                                        High priority load
               DCV low                                                                        Low priority load
            DCV low 2                                                                         Load breaker trip
          HV shutdown                                                                         Load fuse fail
             LVDS trip
                                                                                              Load rail fail
                 TA high
                                                                                              One rectifier fail
                   TA low                                                                     > 1 rectifier fail
         HT shutdown
                                                                                              Rect. over capacity
          LT shutdown                                              ACV high
                                                                   ACV low
         TA sensor fail                                            AC fail
                                                                   AC breaker trip
Rectifier current limit
                                                                   AC phase lost
                                                                   GMT fuse fail
                                                                   TB sensor fail
                                                                   TB high
                                                                   Battery fuse fail
                                                                   Battery middle test fail
                                                                   Battery discharge
                                                                   Battery test fail
                                                                   Battery breaker trip




Training material for VMS-NSN project / Jul. 2011                                               Delta Confidential   111
Config
                                                    SADMIN level
                                                                   Alarm level can be defined
 Alarm level

              CCU

              Fan 1 fail                                              Door open alarm
              Fan 2 fail
                                                                      Fan 1 disconnect

             Heater fail                                              Fan 2 disconnect

          Smoke alarm                                                 Heater disconnect
       Humidity alarm                                                 TA 2 sensor fail

   Water level alarm

            Digital input
            Digital input
            Digital input




Training material for VMS-NSN project / Jul. 2011                                         Delta Confidential   112
SADMIN level
                                                    Relay & LED     Config       Alarm relay define




                Relay 8 7 6 5                         4 3 2 1




Training material for VMS-NSN project / Jul. 2011                                                     Delta Confidential   113
Config
                                                             SADMIN level
                                                                Alarm relay & LED indicator can be defined
      Relay & LED




Training material for VMS-NSN project / Jul. 2011                                                       Delta Confidential   114
SADMIN level
          Pull down list for alarm relay & LED indicator define




Training material for VMS-NSN project / Jul. 2011                  Delta Confidential   115
Config
                                                         SADMIN level

       Rectifier
        model


       Rectifier type 1

       Rectifier type 2




                                                    Rectifier model
                                                       defining




Training material for VMS-NSN project / Jul. 2011                       Delta Confidential   116
Config
                                                           SADMIN level

          Auto
        calibrate

  DCV calibration




    Unnecessary to do the
    calibration in normally



                                                       DCV
                                                    calibration




Training material for VMS-NSN project / Jul. 2011                         Delta Confidential   117
SADMIN level
                                                    Setting




                                                                             Modem configure
              Change permission

               Change password

 Logout (return to user level)




                                                                             Installation notes edit




Training material for VMS-NSN project / Jul. 2011                                 Delta Confidential   118
Contents
                   1              System introduction

                     2             Quick Installation – parameter setting

                     3             Controller introduction

                     4             NRMS software introduction

                     5             Troubleshooting & Maintenance

                     6             Q&A


Training material for VMS-NSN project / Jul. 2011                           Delta Confidential   119
Troubleshooting


                                              Alarm information (Display &Event)
                                       AC Fail/AC High Voltage / AC Low Voltage Alarm
                                     Description
                                           DC Output Voltage High/Low
                                           DC Circuit Breaker Tripped Alarm
                                           Over-Temperature Alarm
                                           Rectifier Failure Alarm
                                           Controller(CSU501) Failure
                                            Cooling System Failure



Training material for VMS-NSN project / Jul. 2011                                       Delta Confidential   120
Training material for vms nsn project rev 0.2 20110906
Training material for vms nsn project rev 0.2 20110906
Training material for vms nsn project rev 0.2 20110906
Training material for vms nsn project rev 0.2 20110906
Training material for vms nsn project rev 0.2 20110906
Training material for vms nsn project rev 0.2 20110906
Training material for vms nsn project rev 0.2 20110906
Training material for vms nsn project rev 0.2 20110906
Training material for vms nsn project rev 0.2 20110906
Training material for vms nsn project rev 0.2 20110906
Training material for vms nsn project rev 0.2 20110906
Training material for vms nsn project rev 0.2 20110906
Training material for vms nsn project rev 0.2 20110906
Training material for vms nsn project rev 0.2 20110906
Training material for vms nsn project rev 0.2 20110906
Training material for vms nsn project rev 0.2 20110906
Training material for vms nsn project rev 0.2 20110906

Mais conteúdo relacionado

Mais procurados

Apostila com 20 comandos elétricos fáceis de fazer
Apostila com 20 comandos elétricos fáceis de fazerApostila com 20 comandos elétricos fáceis de fazer
Apostila com 20 comandos elétricos fáceis de fazerClaudio Arkan
 
Cap 04 disp. e circ. elet. i aula 07
Cap 04 disp. e circ. elet. i   aula 07Cap 04 disp. e circ. elet. i   aula 07
Cap 04 disp. e circ. elet. i aula 07ORCI ALBUQUERQUE
 
Desenho de Instalacoes Eletricas.ppt
Desenho de Instalacoes Eletricas.pptDesenho de Instalacoes Eletricas.ppt
Desenho de Instalacoes Eletricas.pptEngenheiroBenevides
 
LE CONTRÔLE-COMMANDE DES POSTES.pdf
LE CONTRÔLE-COMMANDE DES POSTES.pdfLE CONTRÔLE-COMMANDE DES POSTES.pdf
LE CONTRÔLE-COMMANDE DES POSTES.pdfSAID MASHATE
 
Aula 2 eletrônica industrial
Aula 2 eletrônica industrialAula 2 eletrônica industrial
Aula 2 eletrônica industrialBruno Nora
 
Aula 02 tipos de encapsulamentos e eletricidade
Aula 02 tipos de encapsulamentos e eletricidadeAula 02 tipos de encapsulamentos e eletricidade
Aula 02 tipos de encapsulamentos e eletricidadeAlexandrino Sitoe
 
SE1 - CM Composants - De la diode à l'ADI
SE1 - CM Composants - De la diode à l'ADISE1 - CM Composants - De la diode à l'ADI
SE1 - CM Composants - De la diode à l'ADIPierre Maréchal
 
Resumo nbr 5410
Resumo nbr 5410Resumo nbr 5410
Resumo nbr 5410TECNICORJ1
 
Diodo zener
Diodo zenerDiodo zener
Diodo zenerdraco29
 
Quadro de previsão de cargas
Quadro de previsão de cargasQuadro de previsão de cargas
Quadro de previsão de cargasPaisdaniel
 
Substitution of Lead Sheath by Copper Laminated Covering in HV Cables
Substitution of Lead Sheath by Copper Laminated Covering in HV CablesSubstitution of Lead Sheath by Copper Laminated Covering in HV Cables
Substitution of Lead Sheath by Copper Laminated Covering in HV CablesLeonardo ENERGY
 
1 protection et-surveillance_des_reseaux_de_transport_d_energie_electrique
1 protection et-surveillance_des_reseaux_de_transport_d_energie_electrique1 protection et-surveillance_des_reseaux_de_transport_d_energie_electrique
1 protection et-surveillance_des_reseaux_de_transport_d_energie_electriqueNahla Moursia
 
Cours-Electricité Industrielle.pdf
Cours-Electricité Industrielle.pdfCours-Electricité Industrielle.pdf
Cours-Electricité Industrielle.pdfSAID MASHATE
 
3 - Diodo Zener.ppt
3 - Diodo Zener.ppt3 - Diodo Zener.ppt
3 - Diodo Zener.pptJoberthSilva
 

Mais procurados (20)

Apostila com 20 comandos elétricos fáceis de fazer
Apostila com 20 comandos elétricos fáceis de fazerApostila com 20 comandos elétricos fáceis de fazer
Apostila com 20 comandos elétricos fáceis de fazer
 
Cap 04 disp. e circ. elet. i aula 07
Cap 04 disp. e circ. elet. i   aula 07Cap 04 disp. e circ. elet. i   aula 07
Cap 04 disp. e circ. elet. i aula 07
 
Desenho de Instalacoes Eletricas.ppt
Desenho de Instalacoes Eletricas.pptDesenho de Instalacoes Eletricas.ppt
Desenho de Instalacoes Eletricas.ppt
 
LE CONTRÔLE-COMMANDE DES POSTES.pdf
LE CONTRÔLE-COMMANDE DES POSTES.pdfLE CONTRÔLE-COMMANDE DES POSTES.pdf
LE CONTRÔLE-COMMANDE DES POSTES.pdf
 
Diodes
DiodesDiodes
Diodes
 
Aula 2 eletrônica industrial
Aula 2 eletrônica industrialAula 2 eletrônica industrial
Aula 2 eletrônica industrial
 
Aula 02 tipos de encapsulamentos e eletricidade
Aula 02 tipos de encapsulamentos e eletricidadeAula 02 tipos de encapsulamentos e eletricidade
Aula 02 tipos de encapsulamentos e eletricidade
 
SE1 - CM Composants - De la diode à l'ADI
SE1 - CM Composants - De la diode à l'ADISE1 - CM Composants - De la diode à l'ADI
SE1 - CM Composants - De la diode à l'ADI
 
Resumo nbr 5410
Resumo nbr 5410Resumo nbr 5410
Resumo nbr 5410
 
Les transformateurs
Les transformateursLes transformateurs
Les transformateurs
 
Transistors bipolaires
Transistors bipolairesTransistors bipolaires
Transistors bipolaires
 
Diodo zener
Diodo zenerDiodo zener
Diodo zener
 
Quadro de previsão de cargas
Quadro de previsão de cargasQuadro de previsão de cargas
Quadro de previsão de cargas
 
Transistors
TransistorsTransistors
Transistors
 
Substitution of Lead Sheath by Copper Laminated Covering in HV Cables
Substitution of Lead Sheath by Copper Laminated Covering in HV CablesSubstitution of Lead Sheath by Copper Laminated Covering in HV Cables
Substitution of Lead Sheath by Copper Laminated Covering in HV Cables
 
1 protection et-surveillance_des_reseaux_de_transport_d_energie_electrique
1 protection et-surveillance_des_reseaux_de_transport_d_energie_electrique1 protection et-surveillance_des_reseaux_de_transport_d_energie_electrique
1 protection et-surveillance_des_reseaux_de_transport_d_energie_electrique
 
SLC
SLCSLC
SLC
 
Cours-Electricité Industrielle.pdf
Cours-Electricité Industrielle.pdfCours-Electricité Industrielle.pdf
Cours-Electricité Industrielle.pdf
 
O que são resistores
O que são resistoresO que são resistores
O que são resistores
 
3 - Diodo Zener.ppt
3 - Diodo Zener.ppt3 - Diodo Zener.ppt
3 - Diodo Zener.ppt
 

Destaque (12)

NSN NOKIA 3G KPI for Network planning and optimization
NSN NOKIA 3G KPI for Network planning and optimizationNSN NOKIA 3G KPI for Network planning and optimization
NSN NOKIA 3G KPI for Network planning and optimization
 
04 3 climate control unit
04 3 climate control unit04 3 climate control unit
04 3 climate control unit
 
04 01 dpr 2700 rectifier introduction rev04
04 01 dpr 2700 rectifier introduction rev0404 01 dpr 2700 rectifier introduction rev04
04 01 dpr 2700 rectifier introduction rev04
 
05 nrms install
05 nrms install05 nrms install
05 nrms install
 
04 2 new smart csu r00
04 2 new smart csu r0004 2 new smart csu r00
04 2 new smart csu r00
 
NSN HSDPA Parameters
NSN HSDPA ParametersNSN HSDPA Parameters
NSN HSDPA Parameters
 
01 1 rbs2216 outdoor system proposal by delta
01 1 rbs2216 outdoor system proposal by delta01 1 rbs2216 outdoor system proposal by delta
01 1 rbs2216 outdoor system proposal by delta
 
Ddph drive presentation airtel store
Ddph drive presentation airtel storeDdph drive presentation airtel store
Ddph drive presentation airtel store
 
Nokia kpi and_core_optimization
Nokia kpi and_core_optimizationNokia kpi and_core_optimization
Nokia kpi and_core_optimization
 
Dc Power System
Dc Power SystemDc Power System
Dc Power System
 
Umts Kpi
Umts KpiUmts Kpi
Umts Kpi
 
Bts installation & commisioning
Bts installation & commisioningBts installation & commisioning
Bts installation & commisioning
 

Semelhante a Training material for vms nsn project rev 0.2 20110906

Advanced Network Solutions for Electric Power Application
Advanced Network Solutions for Electric Power ApplicationAdvanced Network Solutions for Electric Power Application
Advanced Network Solutions for Electric Power Applicationchowfei
 
Photovoltaic Training - Session 3 - Plant Operation
Photovoltaic Training - Session 3 - Plant OperationPhotovoltaic Training - Session 3 - Plant Operation
Photovoltaic Training - Session 3 - Plant OperationLeonardo ENERGY
 
Line differential protection 7 sd52x 7sd610. siemens
Line differential protection 7 sd52x  7sd610. siemensLine differential protection 7 sd52x  7sd610. siemens
Line differential protection 7 sd52x 7sd610. siemensshervin shokri
 
10 electrical-systems
10 electrical-systems10 electrical-systems
10 electrical-systemsnitinkumar432
 
Wcdma power control
Wcdma power controlWcdma power control
Wcdma power controlMostafa Adel
 
Reducing Electrical Control Panel Size
Reducing Electrical Control Panel SizeReducing Electrical Control Panel Size
Reducing Electrical Control Panel SizeCMA/Flodyne/Hydradyne
 
Understanding Power Redundancy Levels in Data Centers
Understanding Power Redundancy Levels in Data CentersUnderstanding Power Redundancy Levels in Data Centers
Understanding Power Redundancy Levels in Data CentersMDC Data Centers
 
Smart Monitoring Feasibility Study
Smart Monitoring Feasibility StudySmart Monitoring Feasibility Study
Smart Monitoring Feasibility StudyJahangir_EIT
 
17648889-Introduction-to-Power-System-Protection-Relays.pdf
17648889-Introduction-to-Power-System-Protection-Relays.pdf17648889-Introduction-to-Power-System-Protection-Relays.pdf
17648889-Introduction-to-Power-System-Protection-Relays.pdfThien Phan Bản
 
Voltage Sag and Swell Identification Using FFT Analysis and Mitigation with DVR
Voltage Sag and Swell Identification Using FFT Analysis and Mitigation with DVRVoltage Sag and Swell Identification Using FFT Analysis and Mitigation with DVR
Voltage Sag and Swell Identification Using FFT Analysis and Mitigation with DVRIOSRJEEE
 

Semelhante a Training material for vms nsn project rev 0.2 20110906 (20)

Advanced Network Solutions for Electric Power Application
Advanced Network Solutions for Electric Power ApplicationAdvanced Network Solutions for Electric Power Application
Advanced Network Solutions for Electric Power Application
 
Photovoltaic Training - Session 3 - Plant Operation
Photovoltaic Training - Session 3 - Plant OperationPhotovoltaic Training - Session 3 - Plant Operation
Photovoltaic Training - Session 3 - Plant Operation
 
Lm6171
Lm6171Lm6171
Lm6171
 
Ad9850
Ad9850Ad9850
Ad9850
 
Ad9850
Ad9850Ad9850
Ad9850
 
DS25CP102 (English)
DS25CP102 (English)DS25CP102 (English)
DS25CP102 (English)
 
Line differential protection 7 sd52x 7sd610. siemens
Line differential protection 7 sd52x  7sd610. siemensLine differential protection 7 sd52x  7sd610. siemens
Line differential protection 7 sd52x 7sd610. siemens
 
10 electrical-systems
10 electrical-systems10 electrical-systems
10 electrical-systems
 
Siemens.pptx
Siemens.pptxSiemens.pptx
Siemens.pptx
 
Csmaca
CsmacaCsmaca
Csmaca
 
Slyy027
Slyy027Slyy027
Slyy027
 
Wcdma power control
Wcdma power controlWcdma power control
Wcdma power control
 
Reducing Electrical Control Panel Size
Reducing Electrical Control Panel SizeReducing Electrical Control Panel Size
Reducing Electrical Control Panel Size
 
Understanding Power Redundancy Levels in Data Centers
Understanding Power Redundancy Levels in Data CentersUnderstanding Power Redundancy Levels in Data Centers
Understanding Power Redundancy Levels in Data Centers
 
Smart Monitoring Feasibility Study
Smart Monitoring Feasibility StudySmart Monitoring Feasibility Study
Smart Monitoring Feasibility Study
 
17648889-Introduction-to-Power-System-Protection-Relays.pdf
17648889-Introduction-to-Power-System-Protection-Relays.pdf17648889-Introduction-to-Power-System-Protection-Relays.pdf
17648889-Introduction-to-Power-System-Protection-Relays.pdf
 
Voltage Sag and Swell Identification Using FFT Analysis and Mitigation with DVR
Voltage Sag and Swell Identification Using FFT Analysis and Mitigation with DVRVoltage Sag and Swell Identification Using FFT Analysis and Mitigation with DVR
Voltage Sag and Swell Identification Using FFT Analysis and Mitigation with DVR
 
Adi jul1311
Adi jul1311Adi jul1311
Adi jul1311
 
io-esd
io-esdio-esd
io-esd
 
2014 PV Distribution System Modeling Workshop: Capabilities of Advanced Inver...
2014 PV Distribution System Modeling Workshop: Capabilities of Advanced Inver...2014 PV Distribution System Modeling Workshop: Capabilities of Advanced Inver...
2014 PV Distribution System Modeling Workshop: Capabilities of Advanced Inver...
 

Último

WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure servicePooja Nehwal
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitecturePixlogix Infotech
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024The Digital Insurer
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityPrincipled Technologies
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Paola De la Torre
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...HostedbyConfluent
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 

Último (20)

WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC Architecture
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 

Training material for vms nsn project rev 0.2 20110906

  • 1. Training material for VMS-NSN project Training material for VMS-NSN project / Jul. 2011 R 0.1 Delta Confidential 1
  • 2. Contents 1 System introduction 2 Quick Installation – parameter setting 3 Controller introduction 4 NRMS software introduction 5 Troubleshooting & Maintenance 6 Q&A Training material for VMS-NSN project / Jul. 2011 Delta Confidential 2
  • 3. Contents 1 System introduction 2 Quick Installation – parameter setting 3 Controller introduction 4 NRMS software introduction 5 Troubleshooting & Maintenance 6 Q&A Training material for VMS-NSN project / Jul. 2011 Delta Confidential 3
  • 4. Telecom power system concept LOAD (Switch ,ADSL…E.T.C.) AC Input Output DC Distribution Unit AC Distribution Unit Rectifier # 1 Generator Rectifier # 2 Battery Rectifier # 3 U.P.S LVDS Rectifier # N Control Supervisory Unit (CSU) Training material for VMS-NSN project / Jul. 2011 Delta Confidential 4
  • 5. INDOOR POWER SYSTEM - ESAA150-FTA11 Power System – Three phase / 4 line (3W-N-PE/220V) – Power System with 3 rectifier slots – Distribution: – Load Breaker: (High PL) 20A x 2 + 10A x 2; (Low PL) 100A x 1 + 40A x 3 (DIN Rail) – Battery Breaker: 125A x 2 (DIN Rail) – Protection: – 01 x AC Surge included – 01 x DC surge included – Alarm relay: 8 positions, 7 positions definable Rectifier module: 3 * DPR 2700 DC Output Voltage: 54Vdc (40~59 Vdc) Controller: CSU501+ Local access: NRMS through mini USB interface (Optional) Web/SNMP for remote monitoring and control ESAA150-FTA11 Training material for VMS-NSN project / Jul. 2011 Delta Confidential 5
  • 6. INDOOR POWER SYSTEM - ESAA150-FTA11 High priority load 20A x 2 + 10A x 2 AC surge AC I/P breaker Low priority load arrestor 3P/40A Battery breaker 100A x 1 + 40A x 3 125A x 2 Mini Controller USB port Alarm dry contact Temperature CSU501 Terminal block sensor TA & TB Web/SNMP DC surge (Optional) arrestor Training material for VMS-NSN project / Jul. 2011 Delta Confidential 6
  • 7. KEYS COMPONENT – ESAA150-FTA11 Controller CSU 501+ Power distribution unit Web board (optional) Rectifier DPR2700W Battery string 19” Rectifier shelf Training material for VMS-NSN project / Jul. 2011 Delta Confidential 7
  • 8. System Drawing Training material for VMS-NSN project / Jul. 2011 Delta Confidential 8
  • 9. OUTDOOR POWER SYSTEM – ESOA150-FAC01 Outdoor Power System – Single Layer / Aluminum / Double Door / IP 54 / Fan Cooling – 12U equipment space reserved – Cable: 1/2" Jumper Cable x 06 + cable Glands x 06. – Fan speed control for reducing audible noise Power System – Three phase / 4 line (3W-N-PE/220V) – Power System with 3 rectifier slots – Distribution: – Load Breaker: (High PL) 20A x 2 + 10A x 2; (Low PL) 100A x 1 + 40A x 3 (DIN Rail) – Battery Breaker: 125A x 2 (DIN Rail) – Protection: – 01 x AC Surge – 01 x DC Surge – Alarm relay: 8 positions, 7 positions definable Rectifier module: 3 * DPR 2700/ 2900 HE Local access: NRMS through mini USB interface (Optional) Web/SNMP for remote monitoring and control Outline Dim.: (H*W*D): <2000mm x 750mm x 720mm (Body) Training material for VMS-NSN project / Jul. 2011 Delta Confidential 9
  • 10. OUTDOOR POWER SYSTEM – ESOA150-FAC01 12U space for NSN Fan cooling Customer equipment DC Power system ESAA150-FTA Series Power System with 3 rectifier slots (Rear side access) Battery tray 1 Battery tray 2 Cable Gland x 6 + 1/2" Jumper Cable x 06 Front View Front Side Dimension (H*W*D): < 2000mm x 750mm x 720mm Training material for VMS-NSN project / Jul. 2011 Delta Confidential 10
  • 11. OUTDOOR POWER SYSTEM – ESOA150-FAC01 12U space for NSN Customer equipment DC Power system ESAA150-FTA Series DPR 2900 / Power System with 3 2700W Rectifier rectifier slots (Front side access) Battery tray 1 Battery tray 2 Rear View Rear Side Training material for VMS-NSN project / Jul. 2011 Delta Confidential 11
  • 12. KEY COMPONENTS – ESOA150-FAC01 Power shelf: SB-23N/HJ E Fan tray (EX-F01B) Rectifier DPR2700W Controller CSU 501+ Battery string Web board (optional) Training material for VMS-NSN project / Jul. 2011 Delta Confidential 12
  • 13. Power shelf - ESOA150-FAC01 High priority load 20A x 2 + 10A x 2 AC surge AC I/P breaker Low priority load arrestor 3P/40A Battery breaker 100A x 1 + 40A x 3 125A x 2 Mini Controller USB port Alarm dry contact Temperature CSU501 Terminal block sensor TA & TB Web/SNMP DC surge (Optional) arrestor Training material for VMS-NSN project / Jul. 2011 Delta Confidential 13
  • 14. OUTDOOR POWER SYSTEM – ESOA150-FAC01 Alarm – CCU Board Alarm dry contact CCU Board Training material for VMS-NSN project / Jul. 2011 Delta Confidential 14
  • 15. OUTDOOR POWER SYSTEM – ESOA150-FAC01 CCU Relay Positions and Definition NO COM NC Cooling alarm NO COM Environments alarm NC Environment control Board Training material for VMS-NSN project / Jul. 2011 Delta Confidential 15
  • 16. OUTDOOR POWER SYSTEM – ESOA150-FAC01 PDU Relay Positions and Definition Alarm PIN Alarm Setting Alarm Description Relay 1 NO 1 2 COM AC off AC off 3 NC 4 NO 2 5 COM Rectifier failure Any Rectifier Failure 6 NC 7 NO CSU Hardware Failure 3 8 COM CSU Failure (Hardware setting can not defined by yourself) 9 NC 10 NO 4 11 COM LVDS trip Low voltage disconnect 12 NC 13 NO Ambient Temperature High (TA2H) 5 14 COM High temperature Battery Temperature High (TB1H) 15 NC 16 NO 6 17 COM Major Alarm Major Alarm 18 NC 19 NO 7 20 COM Minor Alarm Minor Alarm 21 NC 22 NO N/A 8 23 COM Don’t use 24 NC Training material for VMS-NSN project / Jul. 2011 Delta Confidential 16
  • 17. OUTDOOR POWER SYSTEM – ESOA150-FAC01 Cable entries 6pcs of bottom cable entries reserved 1pce MG32A 1-hole Cable Gland For AC input (spare) 3pcs MG32A 2-hole Cable Gland For cable range (OD): 12mm 2pce 3-hole Cable Gland For cable range (OD): 12mm Training material for VMS-NSN project / Jul. 2011 Delta Confidential 17
  • 18. OUTDOOR POWER SYSTEM – ESOA150-FAC01 NSN equipment Grounding bus bar Main Grounding Bus bar with 6pcs M6 insert nut for NSN equipment Training material for VMS-NSN project / Jul. 2011 Delta Confidential 18
  • 19. OUTDOOR POWER SYSTEM – ESOA150-FAC01 Power system Grounding bus bar Main Grounding Bus bar x 1 with 6pcs M6 insert nut for for Power system grounding. Training material for VMS-NSN project / Jul. 2011 Delta Confidential 19
  • 20. OUTDOOR POWER SYSTEM – ESOA150-FAC01 Air filter module Suggestion: Clean: 1~2 Months using vacuum cleaner Replacement: 6~12 Months Training material for VMS-NSN project / Jul. 2011 Delta Confidential 20
  • 21. OUTDOOR POWER SYSTEM – ESOA150-FAC01 AC terminal & AC Grounding bus bar Training material for VMS-NSN project / Jul. 2011 Delta Confidential 21
  • 22. OUTDOOR POWER SYSTEM – ESOA150-FAC01 AC socket, AC breaker & Fan breaker Training material for VMS-NSN project / Jul. 2011 Delta Confidential 22
  • 23. System Drawing Training material for VMS-NSN project / Jul. 2011 Delta Confidential 23
  • 24. 48 VDC equipment for RNC (8900W) Power System – Three phase / 4 line (3W-N-PE/220V) – Power System with max.12 rectifier slots – Distribution: 1. Main AC breaker 3P 380Vac type 2. AC Surge Protection 3. Rail 1 Breaker X 16 (DIN rail C120 type ) 125A x1;100A x1; 80A x1 4. Rail 2 Breaker x23 (DIN rail C60 type) 63x3; 50Ax1; 40Ax1; 32Ax1; 25Ax1;20Ax116Ax1; 10Ax1 5. Rail 3 Breaker X 16 (DIN rail C120 type ) 125A x1;100A x1; 80A x1 6. Battery Fuse X 4 (400A x2 ) – Alarm relay: 8 positions, 7 positions definable Rectifier module: 10 * DPR 2000 DC Output Voltage: 54Vdc (40~59 Vdc) Local access: NRMS Optional Web/SNMP for remote monitoring and control ES 48/600-UBA02 Training material for VMS-NSN project / Jul. 2011 Delta Confidential 24
  • 25. 48 VDC equipment for Transport node Hub Site (Tellabs) (1000W) Power System – Three phase / 4 line (3W-N-PE/220V) – Power System with 3 rectifier slots – Distribution: – Load Breaker: (High PL)10A x 2; (Low PL) 32A x 2; – Battery Breaker: 125A x 2 (DIN Rail) – Protection: – 01 x AC Surge included – 01 x DC surge included – Alarm relay: 8 positions, 7 positions definable Rectifier module: 2 * DPR 2000 DC Output Voltage: 54Vdc (40~59 Vdc) Controller: CSU501+ Local access: NRMS through mini USB interface Optional Web/SNMP for remote monitoring and control ESAA150-FTA Series + 0.75M Lion rack Training material for VMS-NSN project / Jul. 2011 Delta Confidential 25
  • 26. 48 VDC equipment for Transport Node RNC Site (2000W) Power System – Three phase / 4 line (3W-N-PE/220V) – Power System with 3 rectifier slots – Distribution: – Load Breaker: (High PL)10A x 2; (Low PL) 32A x 4; – Battery Breaker: 125A x 2 (DIN Rail) – Protection: – 01 x AC Surge included – 01 x DC surge included – Alarm relay: 8 positions, 7 positions definable Rectifier module: 3 * DPR 2000 DC Output Voltage: 54Vdc (40~59 Vdc) Controller: CSU501+ Local access: NRMS through mini USB interface Optional Web/SNMP for remote monitoring and control ESAA150-FTA Series + 0.75M Lion rack Training material for VMS-NSN project / Jul. 2011 Delta Confidential 26
  • 27. 48 VDC equipment for BSC/PCU site (3200W) Power System – Three phase / 4 line (3W-N-PE/220V) – Power System with 4 rectifier slots – Distribution: – Load Breaker: (High PL)10A x 2 + 20A x 2; (Low PL) 100A x 2 + 40A x 2; – Battery Breaker: 125A x 3 (DIN Rail) – Protection: – 01 x AC Surge included – 01 x DC surge included – Alarm relay: 8 positions, 7 positions definable Rectifier module: 4 * DPR 2000 DC Output Voltage: 54Vdc (40~59 Vdc) Local access: NRMS software Optional Web/SNMP for remote monitoring and control ES 48/200-UQB03 + 1.5M Lion rack Training material for VMS-NSN project / Jul. 2011 Delta Confidential 27
  • 28. 48 VDC equipment for TC site (3720W) Power System – Three phase / 4 line (3W-N-PE/220V) – Power System with 4 rectifier slots – Distribution: – Load Breaker: (High PL)10A x 2; (Low PL) 100A x 2 + 16A x 4; – Battery Breaker: 125A x 3 (DIN Rail) – Protection: – 01 x AC Surge included – 01 x DC surge included – Alarm relay: 8 positions, 7 positions definable Rectifier module: 4 * DPR 2700 DC Output Voltage: 54Vdc (40~59 Vdc) Local access: NRMS software Optional Web/SNMP for remote monitoring and control ES 48/200-UQB04 + 1.5M Lion rack Training material for VMS-NSN project / Jul. 2011 Delta Confidential 28
  • 29. DP 2700 Series Rectifier Features and Benefits -48V/56A, Output; Max. Power 2700W Wide Input Voltage Range (90V~300V) Power Factor Correction (>0.99) Hot-pluggable, All Connectors are at the rear Compact Size ≅ 34W/in3 (48V) Power Density Dimension:42mm/1U(H)*125.5mm/2.8U(W)*268mm(D) Light weight:>2 Kg Horizontal(1U)/Vertical(2U) Models Available High Efficiency: >91% (48V) Fan cooling and Easy replaceable fan design Operation temp.:-5oC~+75oC UL/CUL,TUV/CE Certificated Training material for VMS-NSN project / Jul. 2011 Delta Confidential 29
  • 30. AC Input Characteristic(48V) Wide AC input voltage range with derating below 176 V Maximum input current 19 A Input fuse 25A fast (L and N) Training material for VMS-NSN project / Jul. 2011 Delta Confidential 30
  • 31. DC Output Characteristic (48V) Max. Output Power: 2700W(-48V) Constant Power Design Output voltage 40 ... 59.5 Vdc Output fuse 30A x 3 (- pole) 48 56 Training material for VMS-NSN project / Jul. 2011 Delta Confidential 31
  • 32. Thermal Management (CSU Control) OTP = Over Temperature Protection Ambient temperature sense for thermal management: OTP control is based on internal temperature OTP protection is based on critical internal temperature Power limit Vinrms: 184 Rectifier 2700 restart 2300 Ambient 55 °C 65 °C 75 °C Training material for VMS-NSN project / Jul. 2011 Delta Confidential 32
  • 33. Rectifier - Interface Pin Number Signal Description P4 VOP Precharge P5-P7 VO- DC Output “-” P8-P10 VO+ DC Output “+” H1 SGNDO Signal ground I/O Connector H2 RS485+ RS 485 + communication G1 CGND Communication ground Input Signal Output G2 RS485- RS 485 – communication F1 INH Short pin for well connection F2 IDA ID analog E1 IDD ID digital Pin Number Signal Description E2 IBUS Load Sharing Bus P1 AC_L AC main, L terminal P2 AC_N AC main, N terminal P3 FG AC main, frame ground Training material for VMS-NSN project / Jul. 2011 Delta Confidential 33
  • 34. Rectifier - Dimension W x H x D=4.9 x 1.6 x 11.7 inch =125.5 x 40.5 x 270 mm Training material for VMS-NSN project / Jul. 2011 Delta Confidential 34
  • 35. Contents 1 System introduction 2 Quick Installation – parameter setting 3 Controller introduction 4 NRMS software introduction 5 Troubleshooting & Maintenance 6 Q&A Training material for VMS-NSN project / Jul. 2011 Delta Confidential 35
  • 36. Quick installation – system parameter Quick Installation via NRMS software (Step 1: Date & Time setting) Training material for VMS-NSN project / Jul. 2011 Delta Confidential 36
  • 37. Quick installation – system parameter Quick Installation via NRMS software (Step 2: Battery capacity setting) For this case, battery capacity is 300AH. Default setting Training material for VMS-NSN project / Jul. 2011 Delta Confidential 37
  • 38. Quick installation – system parameter Quick Installation via LCD display (Step 1: Date & Time setting) Step 1-1 Step 1-2 Step 1-3 Training material for VMS-NSN project / Jul. 2011 Delta Confidential 38
  • 39. Quick installation – system parameter Quick Installation via LCD display (Step 2: Battery capacity setting). For this case, Battery capacity is 300AH Step 2-1 Step 2-2 Step 2-4 Step 2-3 Training material for VMS-NSN project / Jul. 2011 Delta Confidential 39
  • 40. START - UP PROCEDURE START - UP PROCEDURE: Check-list and inspection before turn-on: Verify all connections prior to starting this section • Ensure the input AC circuit breaker located on the AC service panel is switched to “Off” position • Confirm the operating voltage before proceeding • Ensure the frame ground is properly connected to a permanent earth ground connection • Ensure all the DC circuit breakers in the equipment are switched to the “Off” position • Tighten the DC circuit breaker lugs to ensure proper contact is made with the load cable and the trip sense wire as it may cause heat damage Training material for VMS-NSN project / Jul. 2011 Delta Confidential 40
  • 41. START - UP PROCEDURE Turn on the system Step 1 Check all wiring are correct Step 2 Check and confirm the input voltage is correct Step 3 Pull out all the rectifiers from the system Step 4 Switch on the battery breaker(s) Step 5 Check the monitor of display on the controller Step 6 Switch on the AC breaker Step 7 Check the monitor of display on the controller again Step 8 Push one rectifier into the rectifier slot Step 9 Check the system works in normal condition. Step 10 Push all other rectifier(s) into the rectifier slots Step 11 Switch on the load breaker(s) sequentially Training material for VMS-NSN project / Jul. 2011 Delta Confidential 41
  • 42. START - UP PROCEDURE Simple troubleshooting guide Status Possible causes Action LCD display on the AC utility does not Check the AC utility controller is “OFF” supply to the system Make sure the AC wire is properly connected at the AC input terminal Check the AC breaker position to “ON” position Contact technician if problem still exists All CSU LED are “OFF” AC utility does not Check the AC utility supply to the system Make sure the AC wire is properly connected at the AC input terminal Check the AC breaker position to “ON” position Contact technician if problem still exists Rectifier LEDs are AC utility is not Check the AC utility “OFF” available Make sure the AC wire is properly connected at the AC input Rectifier is not properly terminal placed Check the AC breaker position to “ON” position Pull out the rectifier and insert it properly Contact technician if problem still exists System shows in normal DC breaker is tripped Check the load breaker position to “ON” position operation but no output LVDS2 did not re- Change the breaker if breaker is overloaded in use. to the load connect Check the system output voltage No battery backup when Battery breaker is no Check the battery breaker position to “ON” position and check AC fails connected or the the battery voltage. battery voltage too low Change the battery Battery life reaches end Training material for VMS-NSN project / Jul. 2011 Delta Confidential 42
  • 43. Alarm dry contact & SNMP card installation ESAA150 – FTA11 Power Shelf Training material for VMS-NSN project / Jul. 2011 Delta Confidential 43
  • 44. Alarm dry contact Alarm dry contact Training material for VMS-NSN project / Jul. 2011 Delta Confidential 44
  • 45. Alarm dry contact Type of contact: Dry contact is a contact that is not initially connected to a voltage source. Alarm relay: 8 positions, 7 positions definable 7 positions can be defined by NRMS software Local access: NRMS through mini USB interface. Relay 8 7 6 5 4 3 2 1 Training material for VMS-NSN project / Jul. 2011 Delta Confidential 45
  • 46. Alarm relay define Relay & LED Config Relay 8 7 6 5 4 3 2 1 Training material for VMS-NSN project / Jul. 2011 Delta Confidential 46
  • 47. Config Alarm relay define Alarm relay & LED indicator can be defined Relay & LED Training material for VMS-NSN project / Jul. 2011 Delta Confidential 47
  • 48. SADMIN level Pull down list for alarm relay & LED indicator define Training material for VMS-NSN project / Jul. 2011 Delta Confidential 48
  • 49. Alarm dry contact Using tool to push the button Finish and connect the signal wire Training material for VMS-NSN project / Jul. 2011 Delta Confidential 49
  • 50. Alarm dry contact – Default setting Alarm Relay PIN Alarm Setting Alarm Description 1 NO 1 2 COM AC off AC off 3 NC 4 NO 2 5 COM Rectifier failure Any Rectifier Failure 6 NC 7 NC CSU Hardware Failure 3 8 COM CSU Failure (Hardware setting can not defined by yourself) 9 NO 10 NO 4 11 COM LVDS trip Low voltage disconnect 12 NC 13 NO Ambient Temperature 2 Hi (TA2H) 5 14 COM High temperature (Power bay, threshold= 45 ℃) Battery Temperature Hi 15 NC 16 NO 6 17 COM Major Major Alarm 18 NC 19 NO 7 20 COM Minor Minor alarm 21 NC 22 NO N.A 8 23 COM No define 24 NC Training material for VMS-NSN project / Jul. 2011 Delta Confidential 50
  • 51. SNMP Card Installation Web Server Function and Feature (Optional) Features: Applied in TCP/IP Internet/Intranet Environment Complete Supervising to Power System User-friendly Graphic Interface Dynamic information presentation Password function Multi Language Support Main Screen Microsoft Explorer and Netscape Support Parameter Setting Status Configuration Alarm Training material for VMS-NSN project / Jul. 2011 Delta Confidential 51
  • 52. SNMP Card Installation (optional) Step 1: Relax 4 screws of controller 4 2 1 3 Training material for VMS-NSN project / Jul. 2011 Delta Confidential 52
  • 53. SNMP Card Installation (optional) Step 2: Move out cover and prepare SNMP card kits Controller without SNMP card SNMP card kits Training material for VMS-NSN project / Jul. 2011 Delta Confidential 53
  • 54. SNMP Card Installation (optional) Step 3: Connect signal cables Connect signal cables to SNMP terminal Connect signal cables to CSU Note: follow this picture to connect 2 cables. Web function may not work because of wrong wiring. Training material for VMS-NSN project / Jul. 2011 Delta Confidential 54
  • 55. SNMP Card Installation (optional) Step 4: Fix SNMP Card (2 screws) Fix SNMP Card by 2 screws SNMP Card connect port Training material for VMS-NSN project / Jul. 2011 Delta Confidential 55
  • 56. SNMP Card Installation (optional) Step 5: Recover CSU cover 4 2 1 3 Fix CSU cover by 4 screws Controller with SNMP card Training material for VMS-NSN project / Jul. 2011 Delta Confidential 56
  • 57. Contents 1 System introduction 2 Quick Installation – parameter setting 3 Controller introduction 4 NRMS software introduction 5 Troubleshooting & Maintenance 6 Q&A Training material for VMS-NSN project / Jul. 2011 Delta Confidential 57
  • 58. Controller – CSU 501+ Reliable and user friendly controller User configurable alarms and settings Programmable DC output voltage Battery temperature compensated float voltage LVD contactor control Battery charging control Automatic battery testing LCD 128 x 64 dots display Entry of alarm and system parameters from PC via mini USB port Internet Web Server Function: By Web Server Software/SNMP via RJ45 (Option) Green Function / Efficiency management Hot plug in design Training material for VMS-NSN project / Jul. 2011 Delta Confidential 58
  • 59. Controller CSU 501+ User Interfaces Internet Web Server Function port (optional) Up Major LED Minor LED Down EQU LED Enter ESC 128 x 64 LCD Mini USB (slave) Dots Display Training material for VMS-NSN project / Jul. 2011 Delta Confidential 59
  • 60. Controller CSU 501+ Function architecture (MainData) Home DCV DCI Sys Status(FL/EQU) Alarm Existing Sys Info Sys Setting Current Alarm Rectifier Battery Event Log Current .setting AC & Temp Data & I.D. Address Batt. String I.D. Alarm Function Time DC Setting ACV Voltage Version Output Current Batt.Status Recover Time Alarm Setting Ambient Temp. Date/Time Status Batt. Current Batt.Setting H/W version Other Setting S/W version * DC/DC Data * Function architecture varies in different systems Training material for VMS-NSN project / Jul. 2011 Delta Confidential 60
  • 61. Controller CSU 501+ Function architecture (MainData) Home DCV DCI Sys Status(FL/EQU) Alarm Existing Sys Info Sys Setting Current Alarm Password DC Setting Alarm Setting Batt. Setting Date Setting Efficn.t Mgt. Generator Temp. Unit DCV setting ACV, Batt. Par. Year/month/ ON/OFF ON/OFF ON/OFF CL setting DCV,LVDS, T-Comp day/time OTP,EQU, BDT Test Comm. Batt.Test. B-EQU Modbus Baudrate Language Password English Alarm Reset New PW Cfm 繁體中文 Reset HVSD PW Default 簡體中文 Reset Com-fail (0000) * Function architecture varies in different systems Training material for VMS-NSN project / Jul. 2011 Delta Confidential 61
  • 62. Controller CSU 501+ Function architecture (MainData) Home DCV DCI Sys Status(FL/EQU) Alarm Existing Sys Info Sys Setting Current Alarm All Alarm Function show on Display Show Real Information and Alarm Time in Event Log * Function architecture varies in different systems Training material for VMS-NSN project / Jul. 2011 Delta Confidential 62
  • 63. Display Menu Tree Training material for VMS-NSN project / Jul. 2011 Delta Confidential 63
  • 64. Display Menu Tree Training material for VMS-NSN project / Jul. 2011 Delta Confidential 64
  • 65. Display Menu Tree Training material for VMS-NSN project / Jul. 2011 Delta Confidential 65
  • 66. Display Menu Tree Training material for VMS-NSN project / Jul. 2011 Delta Confidential 66
  • 67. Display Menu Tree Training material for VMS-NSN project / Jul. 2011 Delta Confidential 67
  • 68. Display Menu Tree Training material for VMS-NSN project / Jul. 2011 Delta Confidential 68
  • 69. Contents 1 System introduction 2 Quick Installation – parameter setting 3 Controller introduction 4 NRMS software introduction 5 Troubleshooting & Maintenance 6 Q&A Training material for VMS-NSN project / Jul. 2011 Delta Confidential 69
  • 70. NRMS software introduction Mini U SB Local Access Training material for VMS-NSN project / Jul. 2011 Delta Confidential 70
  • 71. Mini USB The files is **.EXE files, So just double clock it Local Access Training material for VMS-NSN project / Jul. 2011 Delta Confidential 71
  • 72. NRMS H/W Tools 1. H/W Mini USB Cable 2. Delta NRMS software 3. Computer with USB port Mini USB Cable Training material for VMS-NSN project / Jul. 2011 Delta Confidential 72
  • 73. User level login The port must be match your PC/Laptop Training material for VMS-NSN project / Jul. 2011 Delta Confidential 73
  • 74. User level login – Find the comm Port in your computer Click to Device Manager Training material for VMS-NSN project / Jul. 2011 Delta Confidential 74
  • 75. User level login – Find the comm Port in your computer Click to Ports (COM & LPT) Training material for VMS-NSN project / Jul. 2011 Delta Confidential 75
  • 76. User level login Push this button to connect to system Training material for VMS-NSN project / Jul. 2011 Delta Confidential 76
  • 77. User level NRMS Version CSU System data DC O/P voltage Ambient Temp. Load current Total current (load + battery) Buzzer stop AC voltage (Phase1) Manual battery Test AC voltage (Phase 2) Manual EQU AC voltage (phase 3) Software Version Firmware Version System status Login level System voltage RMS software status System time Training material for VMS-NSN project / Jul. 2011 Delta Confidential 77
  • 78. User level Max. No. of No. of No. of No. of rectifier Clear rectifier slot rectifier rectifier rectifier communication communication in system failure working turned Off error error Rectifier Rectifiers status Training material for VMS-NSN project / Jul. 2011 Delta Confidential 78
  • 79. User level Battery Total Batt. current (+: charge) (-: discharge) Batt. 1 Temp. Batt. capacity Batt. 2 Temp. Batt. 1 current Batt. 3 Temp. Batt. 2 current Batt. 3 current Batt. middle point Vol 1 Batt. middle Point Vol 2 Batt. middle point Vol 3 Batt. middle Point Vol 4 Training material for VMS-NSN project / Jul. 2011 Delta Confidential 79
  • 80. Parameter User level System AC High DCV high setting point AC Low DCV low setting point Energy Saving Pre DCV low setting point SMR Max. Current HV shutdown setting point LVDS1 trip point LVDS2 trip point Time Setting LVDS3 trip point Manual LVDS1 Trip Float voltage Manual LVDS2 Trip EQU voltage Ambient temp. high Ambient temp. low High temp. shutdown Alarm when current over Low temp. shutdown 80% of rectifier capacity Training material for VMS-NSN project / Jul. 2011 Delta Confidential 80
  • 81. Delta Power System LVDS Behavior Power System Battery Power System Battery Rectifier Battery Volt Battery Volt Volt (54V) (54V) (54V) Energy Energy Energy Energy BLVD BLVD Battery Low Battery Low Voltage Rectifier Voltage Disconnect Volt (0V) Disconnect Current Current BLVD Sensor Sensor Close BLVD Close LVDS2 LVDS2 Close Close PL NPL PL NPL Output (Load) Output (Load) Normal (AC) Discharge (AC break off) Training material for VMS-NSN project / Jul. 2011 Delta Confidential 81
  • 82. Delta Power System LVDS Behavior Power System Battery Power System Battery Energy Energy Battery Volt Energy Energy (46V) Battery Volt BLVD BLVD (42V) Battery Low Battery Low Rectifier Voltage Rectifier Voltage Volt (0V) Disconnect Volt (0V) Disconnect BLVD BLVD Trip (42V) Close LVDS2 Trip (46V) LVDS2 Open X X X PL NPL PL NPL Output (Load) Output (Load) Discharge (LVDS2 Trip) Discharge (BLVD Trip) Training material for VMS-NSN project / Jul. 2011 Delta Confidential 82
  • 83. Delta Power System LVDS Behavior Power System Battery Power System Battery Energy Energy Energy Energy Rectifier Battery Volt Rectifier Battery Volt Volt (45V) (45V) Volt (49V) (49V) BLVD BLVD Auto recover Close (42V + 3V=45V) LVDS2 LVDS2 Auto Open recover (46V + X 3V=49V) PL NPL PL NPL Output (Load) Output (Load) Battery recharge Battery recharge (BLVD Recover) (LVDS2 Recover) Training material for VMS-NSN project / Jul. 2011 Delta Confidential 83
  • 84. Parameter User level Battery Battery capacity Batt. Test Function Batt. Temp. High ALM Test Time Batt. Middle point Test Criterion Discharge current for test SMR max. current limit Charge Management Batt. Periodic Test Function Charge CL 1 Charge CL -2 Test Periodic Charge CL -3 Which day do the test What time do the test Last batt. Test Time Next batt. Test Time Training material for VMS-NSN project / Jul. 2011 Delta Confidential 84
  • 85. Concept of Battery Charge Current Limit Battery Capacity x Charge rate = Charger Current In this case, battery capacity is 300Ah, so: 300Ah x 0.2C = 60A (battery charge current) 300Ah x 0.1C = 30A (battery charge current) EqulizeVoltage Charge Voltage and Charge Current Float Voltage Deeply Discharge Voltage Battery current Stage - 1 Current Limit Stage - 2 Current Limit Stage - 3 Current Limit 0V / 0A EQU stop current Time Training material for VMS-NSN project / Jul. 2011 Delta Confidential 85
  • 86. Parameter User level Temp. Compensation Temp. Compensation Coefficient (per cell) of Function Temp. Compensation Compensation Mode Max. Range of Compensation Center of temp. System volt of T0 System volt of T1 System volt of T2 System volt of T3 Training material for VMS-NSN project / Jul. 2011 Delta Confidential 86
  • 87. Parameter User level EQU Equalize charge Batt. remaining capacity EQU Max. Time System voltage Additional EQU Time AC fail time Criterion for stop EQU Discharge Current Periodic EQU Function Criteria for enforce EQU Periodic Which day enforce What time enforce Last EQU Time Next EQU Time Training material for VMS-NSN project / Jul. 2011 Delta Confidential 87
  • 88. Parameter User level Alarm Mask Rectifier current limit TB sensor fail alarm One rectifier fail Battery temp. high More than 1 rectifier fail Battery fuse fail Major alarm Battery discharge Minor alarm Battery breaker trip Load breaker trip Middle test fail High priority breaker trip Battery test fail Low priority breaker trip Rect. Over capacity DCV high alarm Load fuse fail DCV low alarm Load rail alarm LVDS 2 trip LVDS trip alarm GMT fuse fail TA high alarm TA low alarm TA sensor fail alarm ACV high alarm ACV low alarm AC breaker trip AC phase lost alarm Training material for VMS-NSN project / Jul. 2011 Delta Confidential 88
  • 89. Parameter User level WEB IP Address Subnet Mask Gateway Training material for VMS-NSN project / Jul. 2011 Delta Confidential 89
  • 90. Parameter User level CCU Fan 1 start point Fan 2 start point Fan 1 stop point Fan 2 stop point Duty for fan 1 full speed Duty for fan 2 full speed Fan 1 full speed point Fan 2 full speed point Start point for heater Push this button then fan 2 run from low speed to full speed Push this button then fan 2 run full speed Training material for VMS-NSN project / Jul. 2011 Delta Confidential 90
  • 91. Alarm User level system Alarm light with alarm Training material for VMS-NSN project / Jul. 2011 Delta Confidential 91
  • 92. Alarm User level CCU Alarm light w/o alarm Training material for VMS-NSN project / Jul. 2011 Delta Confidential 92
  • 93. Event User level Record items Right now Clear all Event log Event log list Down load Event log Training material for VMS-NSN project / Jul. 2011 Delta Confidential 93
  • 94. Setting User level Modem configure Change permission Change password Logout (return to user level) Training material for VMS-NSN project / Jul. 2011 Delta Confidential 94
  • 95. SADMIN level login 1 2 3 4 Password: 8888 Training material for VMS-NSN project / Jul. 2011 Delta Confidential 95
  • 96. SADMIN level login 5 Training material for VMS-NSN project / Jul. 2011 Delta Confidential 96
  • 97. SADMIN level NRMS Version CSU System data DC O/P voltage Ambient Temp. Load current Total current (load + battery) Buzzer stop AC voltage (Phase1) Manual battery Test AC voltage (Phase 2) Manual EQU AC voltage (phase 3) Software Version Firmware Version System status Login level System voltage RMS software status System time Training material for VMS-NSN project / Jul. 2011 Delta Confidential 97
  • 98. SADMIN level Max. No. of No. of No. of No. of rectifier Clear rectifier slot rectifier rectifier rectifier communication communication in system failure working turned Off error error Rectifier Manual on/off rectifier Rectifiers status Training material for VMS-NSN project / Jul. 2011 Delta Confidential 98
  • 99. SADMIN level Battery Total Batt. current (+: charge) (-: discharge) Batt. 1 Temp. Batt. capacity Batt. 2 Temp. Batt. 1 current Batt. 3 Temp. Batt. 2 current Batt. 3 current Batt. middle point Vol 1 Batt. middle Point Vol 2 Batt. middle point Vol 3 Batt. middle Point Vol 4 Training material for VMS-NSN project / Jul. 2011 Delta Confidential 99
  • 100. Parameter SADMIN level System AC High DCV high setting point AC Low DCV low setting point Energy Saving Pre DCV low setting point SMR Max. Current HV shutdown setting point LVDS1 trip point LVDS2 trip point Time Setting LVDS3 trip point Manual LVDS1 Trip Float voltage Manual LVDS2 Trip EQU voltage Ambient temp. high Ambient temp. low High temp. shutdown Alarm when current over Low temp. shutdown 80% of rectifier capacity Training material for VMS-NSN project / Jul. 2011 Delta Confidential 100
  • 101. Parameter SADMIN level Battery Battery capacity Batt. Test Function Batt. Temp. High ALM Test Time Batt. Middle point Test Criterion Discharge current for test (SMR model selection ) SMR max. current limit Charge Management Batt. Periodic Test Function Charge CL 1 Charge CL -2 Test Periodic Charge CL -3 Which day do the test What time do the test Last batt. Test Time Next batt. Test Time Training material for VMS-NSN project / Jul. 2011 Delta Confidential 101
  • 102. Parameter SADMIN level Temp. Compensation Temp. Compensation Coefficient (per cell) of Function Temp. Compensation Compensation Mode Max. Range of Compensation Center of temp. System volt of T0 System volt of T1 System volt of T2 System volt of T3 Training material for VMS-NSN project / Jul. 2011 Delta Confidential 102
  • 103. Parameter SADMIN level EQU Equalize charge Batt. remaining capacity EQU Max. Time System voltage Additional EQU Time AC fail time Criterion for stop EQU Discharge Current Periodic EQU Function Criteria for enforce EQU Periodic Which day enforce What time enforce Last EQU Time Next EQU Time Training material for VMS-NSN project / Jul. 2011 Delta Confidential 103
  • 104. Parameter SADMIN level Alarm Mask System Rectifier current limit TB sensor fail alarm One rectifier fail Battery temp. high More than 1 rectifier fail Battery fuse fail Major alarm Battery discharge Minor alarm Battery breaker trip Load breaker trip Middle test fail High priority breaker trip Battery test fail Low priority breaker trip Rect. Over capacity Load fuse fail DCV high alarm DCV low alarm Load rail alarm LVDS 2 trip LVDS trip alarm GMT fuse fail TA high alarm TA low alarm TA sensor fail alarm ACV high alarm ACV low alarm AC breaker trip AC phase lost alarm Training material for VMS-NSN project / Jul. 2011 Delta Confidential 104
  • 105. Parameter SADMIN level Alarm Mask CCU Fan 1 fail Door open Fan 2 fail Fan 1 disconnect Heater fail Fan 2 disconnect Smoke alarm Heater disconnect Humidity alarm TA 2 sensor fail Water level alarm Training material for VMS-NSN project / Jul. 2011 Delta Confidential 105
  • 106. Parameter SADMIN level WEB IP Address Subnet Mask Gateway Training material for VMS-NSN project / Jul. 2011 Delta Confidential 106
  • 107. Parameter SADMIN level CCU Fan 1 start point Fan 2 start point Fan 1 stop point Fan 2 stop point Duty for fan 1 full speed Duty for fan 2 full speed Fan 1 full speed point Fan 2 full speed point Start point for heater Push this button then fan 2 run from low speed to full speed Push this button then fan 2 run full speed Training material for VMS-NSN project / Jul. 2011 Delta Confidential 107
  • 108. Alarm SADMIN level system Alarm light with alarm Training material for VMS-NSN project / Jul. 2011 Delta Confidential 108
  • 109. Alarm SADMIN level CCU Alarm light w/o alarm Training material for VMS-NSN project / Jul. 2011 Delta Confidential 109
  • 110. Event SADMIN level Record items Right now Clear all Event log Event log list Down load Event log Training material for VMS-NSN project / Jul. 2011 Delta Confidential 110
  • 111. Config SADMIN level Alarm level can be defined Alarm level System DCV high High priority load DCV low Low priority load DCV low 2 Load breaker trip HV shutdown Load fuse fail LVDS trip Load rail fail TA high One rectifier fail TA low > 1 rectifier fail HT shutdown Rect. over capacity LT shutdown ACV high ACV low TA sensor fail AC fail AC breaker trip Rectifier current limit AC phase lost GMT fuse fail TB sensor fail TB high Battery fuse fail Battery middle test fail Battery discharge Battery test fail Battery breaker trip Training material for VMS-NSN project / Jul. 2011 Delta Confidential 111
  • 112. Config SADMIN level Alarm level can be defined Alarm level CCU Fan 1 fail Door open alarm Fan 2 fail Fan 1 disconnect Heater fail Fan 2 disconnect Smoke alarm Heater disconnect Humidity alarm TA 2 sensor fail Water level alarm Digital input Digital input Digital input Training material for VMS-NSN project / Jul. 2011 Delta Confidential 112
  • 113. SADMIN level Relay & LED Config Alarm relay define Relay 8 7 6 5 4 3 2 1 Training material for VMS-NSN project / Jul. 2011 Delta Confidential 113
  • 114. Config SADMIN level Alarm relay & LED indicator can be defined Relay & LED Training material for VMS-NSN project / Jul. 2011 Delta Confidential 114
  • 115. SADMIN level Pull down list for alarm relay & LED indicator define Training material for VMS-NSN project / Jul. 2011 Delta Confidential 115
  • 116. Config SADMIN level Rectifier model Rectifier type 1 Rectifier type 2 Rectifier model defining Training material for VMS-NSN project / Jul. 2011 Delta Confidential 116
  • 117. Config SADMIN level Auto calibrate DCV calibration Unnecessary to do the calibration in normally DCV calibration Training material for VMS-NSN project / Jul. 2011 Delta Confidential 117
  • 118. SADMIN level Setting Modem configure Change permission Change password Logout (return to user level) Installation notes edit Training material for VMS-NSN project / Jul. 2011 Delta Confidential 118
  • 119. Contents 1 System introduction 2 Quick Installation – parameter setting 3 Controller introduction 4 NRMS software introduction 5 Troubleshooting & Maintenance 6 Q&A Training material for VMS-NSN project / Jul. 2011 Delta Confidential 119
  • 120. Troubleshooting Alarm information (Display &Event) AC Fail/AC High Voltage / AC Low Voltage Alarm Description DC Output Voltage High/Low DC Circuit Breaker Tripped Alarm Over-Temperature Alarm Rectifier Failure Alarm Controller(CSU501) Failure Cooling System Failure Training material for VMS-NSN project / Jul. 2011 Delta Confidential 120