SlideShare a Scribd company logo
1 of 72
1
PREPARED BY : ASST. PROF. VATSAL D. PATEL
MAHATMA GANDHI INSTITUTE OF
TECHNICAL EDUCATION &
RESEARCH CENTRE, NAVSARI.
Foundation is the lowest load-bearing part of a building, typically below
ground level.
PURPOSE OF FOUNDATION
1. Distribution of loads
2. Stability against sliding & overturning
3. Minimize differential settlement
4. Safe against undermining
5. Provide level surface
6. Minimize distress against soil movement
 Shallow Foundation (D<B)
 Spread Footing
 Combined Footing
 Strap Footing
 Mat or Raft Foundation
 Grillage Foundation
 Deep foundation (D>B)
 Pile Foundation
 Caissons or Well Foundation
 Coffers Dam
 Also known as a footer or footing
 It’s an enlargement at the bottom of a column/bearing wall that spreads the
applied structural loads over a sufficiently large soil area.
 Each column & each bearing wall has its own spread footing, so each structure
may include dozens of individual footings.
 Wall footing
 Simple Wall Footing
 Stepped Wall Footing
 Reinforced concrete footing
 Inverted arch footing
 Column footing
 Simple Wall Footing
A wall footing or strip footing is
a continuous strip of concrete that
serves to spread the weight of
a load-bearing wall across an area
of soil.
 Stepped Wall Footing
A footing in which the desired
width is secured by a series of
steps.
P C C
WALL
SIMPLE
FOUNDATION
P C C
I FOOTING
WALL
STEPPED
FOUNDATION
II FOOTING
 Inverted Arch Footing /Foundation is
used to be provided for multi-storeyed
buildings in olden times.
 One of the drawbacks in this type of
construction is that the end piles have to
be specially strengthened by buttresses
to avoid the arch thrust tending to
rapture the pier junction.
 Used to spread the load of the structure over a large base to reduce the load per
unit area being imposed on the ground
 Particularly useful where low bearing capacity soils are encountered & where
individual column loads are heavy.
 A spread footing which supports two or more columns is termed as combined
footing
 It is used when the two columns are so close to each other that their individual
footings would overlap.
 A combined footing is also provided when the property line is so close.
 Trapezoidal footing is provided when the load on one of the columns is larger
than the other column.
 It consists of two isolated footings connected with a structural strap or a
lever.
 The strap connects the footing such that they behave as one unit.
 A strap footing is more economical than a combined footing when the
allowable soil pressure is relatively high and distance between the columns
is large
Strap Footing
 It consists of one, two or more tiers
of steel beams superimposed on a
layer of concrete, adjacent tiers
being placed at right angles to each
other.
 Grillage foundation is the most
economical foundation in case of
transferring heavy loads from
columns to soil of low bearing
capacity.
 Caisson is derived from French word “caisse” meaning a box.
 It is relatively large deep foundation.
 It is a box structure in shape of rectangular, round which is sunk from the surface
of water or land to the desire depth.
 It is permanent structure and part of the sub- structure.
Box Caisson
Well or Open
Caisson
•Single
•Multiple
•Cylinder
Pneumatic
Caisson
 Caisson is a watertight retaining structure.
 It is used, for the purpose of placing a foundation in correct position under water.
 It is strong water tight vessel open at top and closed at bottom and made of
timber, steel or RCC.
 It is build on land, cured and then float or launched to pier site where it is
placed in position.
 Mainly it is used for shallow depth and for light weight.
 The caisson is sunk by filling sand, gravel, or concrete in the empty space inside.
 The place where the caisson base is to rest must be levelled and as such box
caissons are used in places where the strata of sufficient bearing capacity is
available near the ground.
 In normal practice, the soft natural bottom soil of the river bed is dredged out to
some depth and the trench thus formed is filled with sand to have a levelled base.
 The function of the sand layer is to uniformly distribute the superimposed loads
over the soil below and thus avoid tilting of the caisson.
 common shapes of caisson
 Cutting edge
 Curb
 Steining
 Bottom plug
 Well cap
 Topplug
 Sand filling
 Cutting edge : provides sharp edge to cut the soil below during sinking operation.
 Curb : during sinking it acts as extension of cutting edge and provide support the
well. It is made of RCC.
 Steining : it is main body of the well. Made of RCC or masonry with minimum
thickness of 45 cm.
 Bottom plug : made of concrete and designed for an upward load equal to the soil
pressure minus self weight of the bottom plug and sand filling.
 Topplug : it supports the well cap.
 Well cap : it transfers the load from pier to the well.
 Sand filling : it transfers a portion of load from well cap to the bottom plug.
 This type of caisson is closed at top and open (during construction) at the
bottom. The water is excluded from the caisson chamber by means of
compressed air.
 The construction of the pneumatic caisson is similar to the types described
above, except that, the working chamber and shaft are made air-tight. In order
that the workmen may carry out excavation work underneath the caisson and
the water may not find its way inside from below, the pressure of the
compressed air in the shaft is kept just higher than that of the water at that
depth.
 Each caisson has two air locks. Through one air lock workmen go down for
working while through the other excavated material is taken out. An air lock
essentially consists of a steel chamber having two air-tight
 When workers working under compressed air inside the working chamber,
they suffer certain type of disease when they return to the atmospheric
pressure. This disease is known as “Caisson Sickness” or “Caisson Disease”.
 The main symptoms of the diseases are:
 Dizziness (vertigo)
 Double vision
 Headache
 Trouble to speaking
 Pain in body
 No person should work for more than one shift in a day. Shift should not exceed 12
hours.
 Temperature of the working chamber should be maintain 25 degree centigrade.
 The main locks should be well ventilated.
 Persons with strong heart, low blood pressure and good circulation should be
employed on the work.
 Use of alcoholic drinks should be prohibited.
 Medical facility or chamber should be provided nearer to the work
 The workers should take enough meal before the shift starts.
 All the passages, shafts etc. of the caisson should be well ventilated and properly
lighted.
 The worker use man locks for entry, interval and exit.
 A pile is basically a long cylinder of a strong material such as concrete that
is pushed into the ground to act as a steady support for structures built on top
of it.
 Pile foundations are used in the following situations:
 When a building has very heavy, concentrated loads, such as in a high rise
structure, bridge, or water tank
 When there is a layer of weak soil at
the surface. This layer cannot support
the weight of the building, so the
loads of the building have to bypass
this layer and be transferred to the
layer of stronger soil or rock that is
below the weak layer
 A Cofferdam is a structure that retains water and soil that allows the enclosed area
to be pumped out and excavated dry.
 Cofferdams are commonly used for construction of bridge piers and other support
structures built within water.
Earth fill
Coffer Dam
Rockfill
Coffer Dam
Rockfill
Crib Coffer
Dam
Single Wall
Coffer Dam
Double
Wall Coffer
Dam
Cellular
Coffer Dam
Earthfill Coffer Dam Rockfill Coffer Dam
Crib Coffer Dam Single Wall Coffer Dam
Double wall Coffer Dam Diaphragm Cellular Coffer Dam
 On the basis of Sub soil condition
 On the basis of loads from building
 Seismic force
 Unequal settlement of the sub –soil
 Unequal settlement of masonry
 Sub-soil moisture movement
 Lateral movement of sub soil
 Lateral pressure on the wall
 Weathering of sub –soil due to trees and shrubs
 Atmospheric action
 The process of collection soil data for the assessment soil properties at a site
through series of laboratory and field investigation is collectively called Sub-soil
Exploration or site investigation
 Purpose of site investigation
 Determining the nature of soil at the site and its stratification.
 Selecting the type and depth of foundation suitable for a given structure.
 Evaluating the load-bearing capacity of the foundation.
 Estimating the probable settlement of a structure.
 Determining the location of water table.
 Determining the depth and nature of bedrock, if and when encountered
 Enables the engineers to draw soil profile indicating the sequence of soil strata
and the properties of soil involved.
 Collection of Preliminary Information
 Reconnaissance
 Site Investigation
 This step includes obtaining information regarding the type of structure to be
built and its general use. The following are examples explain the needed
information about different types of structures:
 For the construction of building:
 The approximate column loads and their spacing.
 Local building-codes.
 Basement requirement.
 For the construction of bridge:
 The length of their spans.
 The loading on piers and abutments
 The engineer should always make a visual inspection (field trip) of the site to
obtain information about:
 The general topography of the site, the possible existence of drainage ditches,
and other materials present at the site.
 Evidence of creep of slopes and deep, wide shrinkage cracks at regularly spaced
intervals may be indicative of expansive soil.
 Soil stratification from deep cuts, such as those made for the construction of
nearby highways and railroads.
 The type of vegetation at the site, which may indicate the nature of the soil.
 Groundwater levels, which can be determined by checking nearby wells.
 The type of construction nearby and the existence of any cracks in walls
(indication for settlement) or other problems.
 The nature of the stratification and physical properties of the soil nearby also
can be obtained from any available soil-exploration reports on existing
structures.
 This phase consists of:
 Planning (adopting steps for site investigation, and future vision for the site)
 Making test boreholes.
 Collecting soil samples at desired intervals for visual observation and
laboratory tests.
o Drilling a hole into the soil strata up to specified depth is known as boring
 Auger boring
Auger and shell boring
Wash boring
Percussion drilling
Rotary drilling
 A soil sample is the representative of the whole lot from which it is taken.
It completely represents all the characteristics of the lot from which it is
recovered.
 TYPES OF SOIL SAMPLES
Disturbed soil samples (DS)
Undisturbed soil samples (UDS)
 Open drive sampler
Split spoon sampler
Shelby tube – thin walled sampler
 Stationary Sampler
 Rotary Sampler
SPLIT SPOON SAMPLER
 Generally used for Cohesion less soils
 To determine relative density , angle of shearing resistance, UCC
 A bore hole is made using drilling tools and a hammer of weight 63.5
falling from the height of 750 mm at the rate of 30 blows/minute
 After reaching the specified depth, the drilling tool is replaced by a split
spoon sampler to collect soil sample.
 First 150 mm penetration is taken as seating drive and the no. of blows
required for that penetration is discarded
 No of blows required for next 300mm penetration after seating drive is
taken as standard penetration number (N)
 No of blows greater than 50 are taken as refusal and the test is
discontinued
 Corrections are applied to the observed N value
 Frictional resistance = Combined resistance – Cone resistance
 Modified Cone penetrometer is known as Refined Dutch Cone
 Cone penetration resistance is denoted as qc in kN/m2
 Unlike SPT, this method is also suitable for clayey deposits
 Unsuitable for gravels and dense sand. For such soil dynamic Cone
penetration is used
 The stratification of soils and rocks can be determined by geophysical methods
of exploration which messures changes in certain physical characteristics of
these materials,for example density, magnetism, electrical, resistivity etc.
 The following two geophysical methods are commonly used:
(i)Seismic refraction method
(ii)Electrical resistivity method
GEOPHYSICAL METHODS
SEISMIC REFRACTION METHOD
The seismic refraction method is based on the principal that seismic waves have
different velocities in different types of soil.
72

More Related Content

What's hot

Types Of Foundation
Types Of FoundationTypes Of Foundation
Types Of Foundation
stooty s
 
footing
footingfooting
footing
illpa
 

What's hot (20)

Pile foundation
Pile foundationPile foundation
Pile foundation
 
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)
 
DIFFERENT TYPE OF SHALLOW FOUNDATION
DIFFERENT TYPE OF SHALLOW FOUNDATIONDIFFERENT TYPE OF SHALLOW FOUNDATION
DIFFERENT TYPE OF SHALLOW FOUNDATION
 
Deep foundation.types and design
Deep foundation.types and designDeep foundation.types and design
Deep foundation.types and design
 
Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundation
 
Types Of Foundation
Types Of FoundationTypes Of Foundation
Types Of Foundation
 
Foundation types
Foundation typesFoundation types
Foundation types
 
Foundation selection
Foundation selectionFoundation selection
Foundation selection
 
Footing and Its Types
Footing and Its TypesFooting and Its Types
Footing and Its Types
 
types of Foundations with animated sketches
types of Foundations with animated sketchestypes of Foundations with animated sketches
types of Foundations with animated sketches
 
Bearing capacity of soil final
Bearing capacity of soil  final Bearing capacity of soil  final
Bearing capacity of soil final
 
footing
footingfooting
footing
 
Foundation
FoundationFoundation
Foundation
 
Foundation and its types and detailed explanation
Foundation and its types and detailed explanationFoundation and its types and detailed explanation
Foundation and its types and detailed explanation
 
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONSPILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
 
Shallow foundation(by indrajit mitra)01
Shallow   foundation(by indrajit mitra)01Shallow   foundation(by indrajit mitra)01
Shallow foundation(by indrajit mitra)01
 
Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma
 
Retaining walls
Retaining wallsRetaining walls
Retaining walls
 
Cofferdams
Cofferdams Cofferdams
Cofferdams
 
Introduction to Foundation Engineering
Introduction to Foundation EngineeringIntroduction to Foundation Engineering
Introduction to Foundation Engineering
 

Similar to 1. SELECTION OF FOUNDATION AND SUBSOIL EXPLORATION/INVESTIGATION (FE) 2180609 GTU

CHAPTER-2.1 FOUNDATIONS.ppt
CHAPTER-2.1 FOUNDATIONS.pptCHAPTER-2.1 FOUNDATIONS.ppt
CHAPTER-2.1 FOUNDATIONS.ppt
BossGold
 
Building foundation: Types, Conditions, and Safety Precautions
Building foundation: Types, Conditions, and Safety PrecautionsBuilding foundation: Types, Conditions, and Safety Precautions
Building foundation: Types, Conditions, and Safety Precautions
James Tolentino
 

Similar to 1. SELECTION OF FOUNDATION AND SUBSOIL EXPLORATION/INVESTIGATION (FE) 2180609 GTU (20)

Bridge foundation
Bridge  foundation Bridge  foundation
Bridge foundation
 
2. CAISSONS (ACE) 2160601 GTU
2. CAISSONS (ACE) 2160601 GTU2. CAISSONS (ACE) 2160601 GTU
2. CAISSONS (ACE) 2160601 GTU
 
Foundation
FoundationFoundation
Foundation
 
special foundation techniques
 special foundation techniques special foundation techniques
special foundation techniques
 
Foundation
FoundationFoundation
Foundation
 
BCT MODULE 2 - Caisson
BCT MODULE 2 - CaissonBCT MODULE 2 - Caisson
BCT MODULE 2 - Caisson
 
FOUNDATION.pptx
FOUNDATION.pptxFOUNDATION.pptx
FOUNDATION.pptx
 
Types of pile foundation
Types of pile foundationTypes of pile foundation
Types of pile foundation
 
Saurav_FOUNDATION IN LAKE AND RIVER BEDS.pptx
Saurav_FOUNDATION IN LAKE AND RIVER BEDS.pptxSaurav_FOUNDATION IN LAKE AND RIVER BEDS.pptx
Saurav_FOUNDATION IN LAKE AND RIVER BEDS.pptx
 
Foundation and its types
Foundation and its types Foundation and its types
Foundation and its types
 
CHAPTER-2.1 FOUNDATIONS.ppt
CHAPTER-2.1 FOUNDATIONS.pptCHAPTER-2.1 FOUNDATIONS.ppt
CHAPTER-2.1 FOUNDATIONS.ppt
 
2-basics-of-foundation.ppt
2-basics-of-foundation.ppt2-basics-of-foundation.ppt
2-basics-of-foundation.ppt
 
Types of deep foundation
Types of deep foundationTypes of deep foundation
Types of deep foundation
 
Tos ppt foundation
Tos ppt foundationTos ppt foundation
Tos ppt foundation
 
Types of foundations.
Types of foundations.Types of foundations.
Types of foundations.
 
LECT 6 UPDATE.pdf
LECT  6 UPDATE.pdfLECT  6 UPDATE.pdf
LECT 6 UPDATE.pdf
 
Foundations
FoundationsFoundations
Foundations
 
Building foundation: Types, Conditions, and Safety Precautions
Building foundation: Types, Conditions, and Safety PrecautionsBuilding foundation: Types, Conditions, and Safety Precautions
Building foundation: Types, Conditions, and Safety Precautions
 
Notes on introduction and design of caissons
Notes on introduction and design of caissonsNotes on introduction and design of caissons
Notes on introduction and design of caissons
 
Pile foundation power point ptesentation
Pile foundation power point ptesentationPile foundation power point ptesentation
Pile foundation power point ptesentation
 

More from VATSAL PATEL

More from VATSAL PATEL (20)

5. AIR TRANSPORTATION (TRE) GTU 3150611
5. AIR TRANSPORTATION (TRE) GTU 31506115. AIR TRANSPORTATION (TRE) GTU 3150611
5. AIR TRANSPORTATION (TRE) GTU 3150611
 
3. RAIL TRANSPORTATION (TRE) GTU 3150611
3. RAIL TRANSPORTATION (TRE) GTU 31506113. RAIL TRANSPORTATION (TRE) GTU 3150611
3. RAIL TRANSPORTATION (TRE) GTU 3150611
 
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
 
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...
 
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
 
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
 
2. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 31706232. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 3170623
 
4. WATER TRANSPORTATION (TRE) GTU 3150611
4. WATER TRANSPORTATION (TRE) GTU 31506114. WATER TRANSPORTATION (TRE) GTU 3150611
4. WATER TRANSPORTATION (TRE) GTU 3150611
 
8. IMPACT ANALYSIS (PHE) GTU 3170623
8. IMPACT ANALYSIS (PHE) GTU 31706238. IMPACT ANALYSIS (PHE) GTU 3170623
8. IMPACT ANALYSIS (PHE) GTU 3170623
 
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
 
7. SEAPORT MAINTENANCE (PHE) GTU 3170623
7. SEAPORT MAINTENANCE (PHE) GTU 31706237. SEAPORT MAINTENANCE (PHE) GTU 3170623
7. SEAPORT MAINTENANCE (PHE) GTU 3170623
 
6. NAVIGATIONAL AIDS (PHE) GTU 3170623
6. NAVIGATIONAL AIDS (PHE) GTU 31706236. NAVIGATIONAL AIDS (PHE) GTU 3170623
6. NAVIGATIONAL AIDS (PHE) GTU 3170623
 
5. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623
5. PORT AMENITIES & OPERATIONS (PHE) GTU 31706235. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623
5. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623
 
4. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
4. HARBOUR INFRASTRUCTURES (PHE) GTU 31706234. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
4. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
 
3. NATURAL PHENOMENA (PHE) GTU 3170623
3. NATURAL PHENOMENA (PHE) GTU 31706233. NATURAL PHENOMENA (PHE) GTU 3170623
3. NATURAL PHENOMENA (PHE) GTU 3170623
 
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
 
1. INTRODUCTION TO WATER TRANSPORTATION (PHE) GTU 3170623
1. INTRODUCTION  TO WATER TRANSPORTATION (PHE) GTU 31706231. INTRODUCTION  TO WATER TRANSPORTATION (PHE) GTU 3170623
1. INTRODUCTION TO WATER TRANSPORTATION (PHE) GTU 3170623
 
2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU
2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU
2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU
 
1. INTRODUCTION (TRE) 3150611 GTU
1. INTRODUCTION (TRE) 3150611 GTU1. INTRODUCTION (TRE) 3150611 GTU
1. INTRODUCTION (TRE) 3150611 GTU
 
9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU
9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU
9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU
 

Recently uploaded

Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Recently uploaded (20)

Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Intro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfIntro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdf
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 

1. SELECTION OF FOUNDATION AND SUBSOIL EXPLORATION/INVESTIGATION (FE) 2180609 GTU

  • 1. 1 PREPARED BY : ASST. PROF. VATSAL D. PATEL MAHATMA GANDHI INSTITUTE OF TECHNICAL EDUCATION & RESEARCH CENTRE, NAVSARI.
  • 2. Foundation is the lowest load-bearing part of a building, typically below ground level. PURPOSE OF FOUNDATION 1. Distribution of loads 2. Stability against sliding & overturning 3. Minimize differential settlement 4. Safe against undermining 5. Provide level surface 6. Minimize distress against soil movement
  • 3.  Shallow Foundation (D<B)  Spread Footing  Combined Footing  Strap Footing  Mat or Raft Foundation  Grillage Foundation  Deep foundation (D>B)  Pile Foundation  Caissons or Well Foundation  Coffers Dam
  • 4.  Also known as a footer or footing  It’s an enlargement at the bottom of a column/bearing wall that spreads the applied structural loads over a sufficiently large soil area.  Each column & each bearing wall has its own spread footing, so each structure may include dozens of individual footings.
  • 5.  Wall footing  Simple Wall Footing  Stepped Wall Footing  Reinforced concrete footing  Inverted arch footing  Column footing
  • 6.  Simple Wall Footing A wall footing or strip footing is a continuous strip of concrete that serves to spread the weight of a load-bearing wall across an area of soil.  Stepped Wall Footing A footing in which the desired width is secured by a series of steps.
  • 7. P C C WALL SIMPLE FOUNDATION P C C I FOOTING WALL STEPPED FOUNDATION II FOOTING
  • 8.
  • 9.  Inverted Arch Footing /Foundation is used to be provided for multi-storeyed buildings in olden times.  One of the drawbacks in this type of construction is that the end piles have to be specially strengthened by buttresses to avoid the arch thrust tending to rapture the pier junction.
  • 10.
  • 11.  Used to spread the load of the structure over a large base to reduce the load per unit area being imposed on the ground  Particularly useful where low bearing capacity soils are encountered & where individual column loads are heavy.
  • 12.  A spread footing which supports two or more columns is termed as combined footing  It is used when the two columns are so close to each other that their individual footings would overlap.  A combined footing is also provided when the property line is so close.  Trapezoidal footing is provided when the load on one of the columns is larger than the other column.
  • 13.
  • 14.  It consists of two isolated footings connected with a structural strap or a lever.  The strap connects the footing such that they behave as one unit.  A strap footing is more economical than a combined footing when the allowable soil pressure is relatively high and distance between the columns is large
  • 16.  It consists of one, two or more tiers of steel beams superimposed on a layer of concrete, adjacent tiers being placed at right angles to each other.  Grillage foundation is the most economical foundation in case of transferring heavy loads from columns to soil of low bearing capacity.
  • 17.  Caisson is derived from French word “caisse” meaning a box.  It is relatively large deep foundation.  It is a box structure in shape of rectangular, round which is sunk from the surface of water or land to the desire depth.  It is permanent structure and part of the sub- structure.
  • 18. Box Caisson Well or Open Caisson •Single •Multiple •Cylinder Pneumatic Caisson  Caisson is a watertight retaining structure.  It is used, for the purpose of placing a foundation in correct position under water.
  • 19.  It is strong water tight vessel open at top and closed at bottom and made of timber, steel or RCC.  It is build on land, cured and then float or launched to pier site where it is placed in position.  Mainly it is used for shallow depth and for light weight.
  • 20.  The caisson is sunk by filling sand, gravel, or concrete in the empty space inside.  The place where the caisson base is to rest must be levelled and as such box caissons are used in places where the strata of sufficient bearing capacity is available near the ground.  In normal practice, the soft natural bottom soil of the river bed is dredged out to some depth and the trench thus formed is filled with sand to have a levelled base.  The function of the sand layer is to uniformly distribute the superimposed loads over the soil below and thus avoid tilting of the caisson.
  • 21.
  • 22.
  • 23.  common shapes of caisson
  • 24.  Cutting edge  Curb  Steining  Bottom plug  Well cap  Topplug  Sand filling
  • 25.  Cutting edge : provides sharp edge to cut the soil below during sinking operation.  Curb : during sinking it acts as extension of cutting edge and provide support the well. It is made of RCC.  Steining : it is main body of the well. Made of RCC or masonry with minimum thickness of 45 cm.  Bottom plug : made of concrete and designed for an upward load equal to the soil pressure minus self weight of the bottom plug and sand filling.  Topplug : it supports the well cap.  Well cap : it transfers the load from pier to the well.  Sand filling : it transfers a portion of load from well cap to the bottom plug.
  • 26.  This type of caisson is closed at top and open (during construction) at the bottom. The water is excluded from the caisson chamber by means of compressed air.  The construction of the pneumatic caisson is similar to the types described above, except that, the working chamber and shaft are made air-tight. In order that the workmen may carry out excavation work underneath the caisson and the water may not find its way inside from below, the pressure of the compressed air in the shaft is kept just higher than that of the water at that depth.  Each caisson has two air locks. Through one air lock workmen go down for working while through the other excavated material is taken out. An air lock essentially consists of a steel chamber having two air-tight
  • 27.
  • 28.  When workers working under compressed air inside the working chamber, they suffer certain type of disease when they return to the atmospheric pressure. This disease is known as “Caisson Sickness” or “Caisson Disease”.  The main symptoms of the diseases are:  Dizziness (vertigo)  Double vision  Headache  Trouble to speaking  Pain in body
  • 29.  No person should work for more than one shift in a day. Shift should not exceed 12 hours.  Temperature of the working chamber should be maintain 25 degree centigrade.  The main locks should be well ventilated.  Persons with strong heart, low blood pressure and good circulation should be employed on the work.  Use of alcoholic drinks should be prohibited.
  • 30.  Medical facility or chamber should be provided nearer to the work  The workers should take enough meal before the shift starts.  All the passages, shafts etc. of the caisson should be well ventilated and properly lighted.  The worker use man locks for entry, interval and exit.
  • 31.  A pile is basically a long cylinder of a strong material such as concrete that is pushed into the ground to act as a steady support for structures built on top of it.  Pile foundations are used in the following situations:  When a building has very heavy, concentrated loads, such as in a high rise structure, bridge, or water tank
  • 32.  When there is a layer of weak soil at the surface. This layer cannot support the weight of the building, so the loads of the building have to bypass this layer and be transferred to the layer of stronger soil or rock that is below the weak layer
  • 33.  A Cofferdam is a structure that retains water and soil that allows the enclosed area to be pumped out and excavated dry.  Cofferdams are commonly used for construction of bridge piers and other support structures built within water. Earth fill Coffer Dam Rockfill Coffer Dam Rockfill Crib Coffer Dam Single Wall Coffer Dam Double Wall Coffer Dam Cellular Coffer Dam
  • 34. Earthfill Coffer Dam Rockfill Coffer Dam
  • 35.
  • 36.
  • 37. Crib Coffer Dam Single Wall Coffer Dam
  • 38.
  • 39.
  • 40. Double wall Coffer Dam Diaphragm Cellular Coffer Dam
  • 41.
  • 42.  On the basis of Sub soil condition  On the basis of loads from building  Seismic force
  • 43.
  • 44.
  • 45.
  • 46.
  • 47.
  • 48.  Unequal settlement of the sub –soil  Unequal settlement of masonry  Sub-soil moisture movement  Lateral movement of sub soil  Lateral pressure on the wall  Weathering of sub –soil due to trees and shrubs  Atmospheric action
  • 49.
  • 50.  The process of collection soil data for the assessment soil properties at a site through series of laboratory and field investigation is collectively called Sub-soil Exploration or site investigation  Purpose of site investigation  Determining the nature of soil at the site and its stratification.  Selecting the type and depth of foundation suitable for a given structure.  Evaluating the load-bearing capacity of the foundation.  Estimating the probable settlement of a structure.  Determining the location of water table.  Determining the depth and nature of bedrock, if and when encountered  Enables the engineers to draw soil profile indicating the sequence of soil strata and the properties of soil involved.
  • 51.  Collection of Preliminary Information  Reconnaissance  Site Investigation
  • 52.  This step includes obtaining information regarding the type of structure to be built and its general use. The following are examples explain the needed information about different types of structures:  For the construction of building:  The approximate column loads and their spacing.  Local building-codes.  Basement requirement.  For the construction of bridge:  The length of their spans.  The loading on piers and abutments
  • 53.  The engineer should always make a visual inspection (field trip) of the site to obtain information about:  The general topography of the site, the possible existence of drainage ditches, and other materials present at the site.  Evidence of creep of slopes and deep, wide shrinkage cracks at regularly spaced intervals may be indicative of expansive soil.  Soil stratification from deep cuts, such as those made for the construction of nearby highways and railroads.  The type of vegetation at the site, which may indicate the nature of the soil.  Groundwater levels, which can be determined by checking nearby wells.  The type of construction nearby and the existence of any cracks in walls (indication for settlement) or other problems.  The nature of the stratification and physical properties of the soil nearby also can be obtained from any available soil-exploration reports on existing structures.
  • 54.  This phase consists of:  Planning (adopting steps for site investigation, and future vision for the site)  Making test boreholes.  Collecting soil samples at desired intervals for visual observation and laboratory tests.
  • 55.
  • 56.
  • 57. o Drilling a hole into the soil strata up to specified depth is known as boring  Auger boring Auger and shell boring Wash boring Percussion drilling Rotary drilling
  • 58.
  • 59.
  • 60.  A soil sample is the representative of the whole lot from which it is taken. It completely represents all the characteristics of the lot from which it is recovered.  TYPES OF SOIL SAMPLES Disturbed soil samples (DS) Undisturbed soil samples (UDS)
  • 61.  Open drive sampler Split spoon sampler Shelby tube – thin walled sampler  Stationary Sampler  Rotary Sampler
  • 63.
  • 64.  Generally used for Cohesion less soils  To determine relative density , angle of shearing resistance, UCC  A bore hole is made using drilling tools and a hammer of weight 63.5 falling from the height of 750 mm at the rate of 30 blows/minute  After reaching the specified depth, the drilling tool is replaced by a split spoon sampler to collect soil sample.  First 150 mm penetration is taken as seating drive and the no. of blows required for that penetration is discarded  No of blows required for next 300mm penetration after seating drive is taken as standard penetration number (N)  No of blows greater than 50 are taken as refusal and the test is discontinued  Corrections are applied to the observed N value
  • 65.
  • 66.  Frictional resistance = Combined resistance – Cone resistance  Modified Cone penetrometer is known as Refined Dutch Cone  Cone penetration resistance is denoted as qc in kN/m2  Unlike SPT, this method is also suitable for clayey deposits  Unsuitable for gravels and dense sand. For such soil dynamic Cone penetration is used
  • 67.
  • 68.
  • 69.  The stratification of soils and rocks can be determined by geophysical methods of exploration which messures changes in certain physical characteristics of these materials,for example density, magnetism, electrical, resistivity etc.  The following two geophysical methods are commonly used: (i)Seismic refraction method (ii)Electrical resistivity method GEOPHYSICAL METHODS
  • 70. SEISMIC REFRACTION METHOD The seismic refraction method is based on the principal that seismic waves have different velocities in different types of soil.
  • 71.
  • 72. 72