CPM and PERT Network techniques
3 December 2016
Contents
 INTRODUCTION
 DEFINITIONS OF PROJECT AND PROJECT MANAGEMENT
 NETWORK PLANNING METHODS
 WHAT IS NETWORK
 CONSTRUCTION OF NETWORK
 CPM
 PERT
 CPM VS PERT
3 December 2016
INTRODUCTION
 To perform any job optimally we should have some planning
 Generally planning and performing job is called project.
 The project requires some techniques to done the project
 Those are CPM and PERT
3 December 2016
Definitions
Project:
 project is a group or combination of activities that must be executed in a certain
fixed order before entire task is completed.
 The projects are non-repetitive large tasks
Project management:
 Project management is a scientific way of planning, implementing, monitoring &
controlling the various aspects of a project such as time, money, materials,
manpower & other resources.
3 December 2016
Real time example for a project
 Project: Getting ready to attend the college
 Wake up in the Morning
 Brush your teeth
 Take bath
 Wear formal dress
 Take break fast
 Walk to the college
 These are the basic activities we need to complete for accomplishment of project.
3 December 2016
Network Planning methods
 Methods used for network planning are:
 CPM
 PERT
 Managing a project with network planning methods involves four steps:
 Describing the project.
 Diagramming the Network.
 Estimating time of completion.
 Monitoring project progress.
3 December 2016
Network Diagram
 Network:
Network is a graphical representation of a project operations and it is
composed of several activities and events which are inter-related.
 Network consists of:
 Event
 Activity
3 December 2016
Basic Building blocks of Network
 Activity:
Activity is a recognizable part of the project which consume time and resources for its
completion.
In network diagram “ARROW” represents activity
 Critical activity
 Dummy activity
 Event:
An event represents the accomplishment of some task. In a network diagram,
beginning and ending of an activity represented by an event.
In network diagram “NODE” represents event.
 Merge event
 Burst event
3 December 2016
Construction of a Network
Rules for drawing network diagram
1. Each activity is represented by one and only one arrow in the network
2. No two activities can be identified by the same end events
3. Before an activity can begin, it preceding activities must be completed.
4. Arrows indicate logical precedence.
5. Flow of the diagram is from left to right
6. Arrows should not intersect.
7. Dangling should be avoided.
3 December 2016
Activity Precedence
A --------
B --------
C A
D B
E A
F B
G C,D
H G,F
I E
J H,I
K J 3 December 2016
CPM
 CPM means “critical path method”.
 It is a network technique used to evaluate the project.
 If the activity times are deterministic then critical path method can be used as a
systematic method.
 CPM evaluates project by determining critical path in the network.
3 December 2016
Critical Path
 Critical path is the longest path in the network from the starting event to ending
event
 Critical path defines minimum time required to complete the project
 In network diagram critical path is represented with double arrows
 Critical path consist:
 Critical event: The events with zero slack
 Critical activity: The activities with zero total float
3 December 2016
Network of CPM
 Earliest Activity start time(EST)
The earliest start time that an activity can be started
 Earliest Activity finish time(EFT)
EFT= EST + Duration
 Latest Activity finish time(LFT)
 Latest Activity start time(LST)
LST= LFT-duration
3 December 2016
Types of Float
 Total float
(TF)ij = (Lj – Tij)- Ei
 Free float
(Ff)Ij =Total float – ( Lj- Ej)
 Independent float
(If)ij = Free float- Tail event slack
Tiji j
Ei Ej
Li Lj
3 December 2016
Draw network diagram and analyzing CPM
Activity Immediate
predecessor
Duration
(months)
A -------------- 2
B -------------- 5
C -------------- 4
D B 5
E A 7
F A 3
G B 3
H C,D 6
I C,D 2
J E 5
K F,G,H 4
L F,G,H 3
M I 12
N J,K 8
3 December 2016
PERT
 PERT means project (or) programme Evaluation & Review Technique.
 When activity times are probabilistic, PERT is an effective tool for evaluate
project.
 PERT is associated with 3 time estimates
 Optimistic Time ( to)
 Pessimistic Time ( tP)
 Most likely Time ( tm)
3 December 2016
Activity Times in PERT
 Optimistic Time: ( To)
It is the minimum time that is required to complete an activity when every
resource is available
 Most likely Time: (Tm)
This is the time required for the completion of activity under normal conditions.
 Pessimistic Time: (Tp)
The most time that is required to complete activity when every resource is not
available
Note: In PERT β – distribution is used to represent these three time estimates
3 December 2016
Formulae used for evaluation of PERT
 Time estimate (Te)=
𝑇𝑜+𝑇𝑝+4𝑇𝑚
6
 Standard deviation ( )= 𝑇𝑝 −𝑇𝑂
6
 Variance =
𝑇𝑝−𝑇𝑜 2
36
3 December 2016
CPM VS PERT
CPM PERT
It is activity oriented It is event oriented
It is associated with deterministic activities It is associated with probabilistic activities
It is based upon single time to complete
an activity
It is based upon 3 time estimate to
complete an activity
It is used mainly for construction project It is used mainly for research and
development project
3 December 2016
References
3 December 2016
1. Wikipedia
2. Mechanical engineering Ace material
3. Some of the YouTube videos
Thank you
3 December 2016

Mais conteúdo relacionado

Mais procurados

Mais procurados (20)

Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and scheduling
 
Pert analysis
Pert analysisPert analysis
Pert analysis
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Scheduling
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Unit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pertUnit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pert
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Pert
PertPert
Pert
 
Pert, cpm & gert
Pert, cpm & gertPert, cpm & gert
Pert, cpm & gert
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing
 
inventory control for construction
inventory control for constructioninventory control for construction
inventory control for construction
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
P E R T
P E R TP E R T
P E R T
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Rules for Network Construction
Rules for Network ConstructionRules for Network Construction
Rules for Network Construction
 
project management information system
project management information systemproject management information system
project management information system
 

Destaque

Layout types
Layout typesLayout types
Layout typesSartaj
 
Plant layout and its types
Plant layout and its typesPlant layout and its types
Plant layout and its typesHammaduddin
 
Process design layout
Process design layoutProcess design layout
Process design layoutAL Kindi
 
The Network Diagram and Critical Path
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Pathdmdk12
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network DiagramsNicola2903
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERTPulchowk Campus
 
Plant layout ppt by me
Plant layout ppt by mePlant layout ppt by me
Plant layout ppt by meAnkit Walia
 
Process And Layout Strategies
Process And Layout StrategiesProcess And Layout Strategies
Process And Layout StrategiesJoanmaines
 

Destaque (13)

Plant location & layout
Plant location & layoutPlant location & layout
Plant location & layout
 
Plant location & layout design
Plant location & layout designPlant location & layout design
Plant location & layout design
 
Layout types
Layout typesLayout types
Layout types
 
Plant layout and its types
Plant layout and its typesPlant layout and its types
Plant layout and its types
 
Process design layout
Process design layoutProcess design layout
Process design layout
 
Types of layouts
Types of layoutsTypes of layouts
Types of layouts
 
The Network Diagram and Critical Path
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Path
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network Diagrams
 
Plant layout
Plant layoutPlant layout
Plant layout
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 
Plant location
Plant locationPlant location
Plant location
 
Plant layout ppt by me
Plant layout ppt by mePlant layout ppt by me
Plant layout ppt by me
 
Process And Layout Strategies
Process And Layout StrategiesProcess And Layout Strategies
Process And Layout Strategies
 

Semelhante a Network Techniques

[Document] MultiProject analysis with Critical Path Method
[Document] MultiProject analysis with Critical Path Method[Document] MultiProject analysis with Critical Path Method
[Document] MultiProject analysis with Critical Path MethodMichele Palumbo
 
L05 time management
L05 time managementL05 time management
L05 time managementAsa Chan
 
Advanced project management mod 4
Advanced project management mod 4Advanced project management mod 4
Advanced project management mod 4POOJA UDAYAN
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managersNaganna Chetty
 
Project Time Management ICTI.ppt
Project Time Management ICTI.pptProject Time Management ICTI.ppt
Project Time Management ICTI.pptMohammadReza60255
 
NET WORK ANALYSIS.pptx
NET WORK ANALYSIS.pptxNET WORK ANALYSIS.pptx
NET WORK ANALYSIS.pptxpaulkinyua6
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptxNaimishKishor
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxannettsparrow
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxTecnicoItca
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 pptahsanrabbani
 
Operations and Supply Chain ManagementMGMT 3306Lecture 02I.docx
Operations and Supply Chain ManagementMGMT 3306Lecture 02I.docxOperations and Supply Chain ManagementMGMT 3306Lecture 02I.docx
Operations and Supply Chain ManagementMGMT 3306Lecture 02I.docxhopeaustin33688
 

Semelhante a Network Techniques (20)

CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
 
[Document] MultiProject analysis with Critical Path Method
[Document] MultiProject analysis with Critical Path Method[Document] MultiProject analysis with Critical Path Method
[Document] MultiProject analysis with Critical Path Method
 
L05 time management
L05 time managementL05 time management
L05 time management
 
Network Analysis- CPM ppt..pptx
Network Analysis- CPM  ppt..pptxNetwork Analysis- CPM  ppt..pptx
Network Analysis- CPM ppt..pptx
 
Advanced project management mod 4
Advanced project management mod 4Advanced project management mod 4
Advanced project management mod 4
 
Lecture 6
Lecture 6Lecture 6
Lecture 6
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
Project Time Management ICTI.ppt
Project Time Management ICTI.pptProject Time Management ICTI.ppt
Project Time Management ICTI.ppt
 
NET WORK ANALYSIS.pptx
NET WORK ANALYSIS.pptxNET WORK ANALYSIS.pptx
NET WORK ANALYSIS.pptx
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
Chap03
Chap03Chap03
Chap03
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docx
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
 
Critical Path Method presentation.
Critical Path Method presentation.Critical Path Method presentation.
Critical Path Method presentation.
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
 
Ii. pert cpm
Ii. pert cpmIi. pert cpm
Ii. pert cpm
 
Operations and Supply Chain ManagementMGMT 3306Lecture 02I.docx
Operations and Supply Chain ManagementMGMT 3306Lecture 02I.docxOperations and Supply Chain ManagementMGMT 3306Lecture 02I.docx
Operations and Supply Chain ManagementMGMT 3306Lecture 02I.docx
 

Último

Mythology Quiz-4th April 2024, Quiz Club NITW
Mythology Quiz-4th April 2024, Quiz Club NITWMythology Quiz-4th April 2024, Quiz Club NITW
Mythology Quiz-4th April 2024, Quiz Club NITWQuiz Club NITW
 
4.9.24 School Desegregation in Boston.pptx
4.9.24 School Desegregation in Boston.pptx4.9.24 School Desegregation in Boston.pptx
4.9.24 School Desegregation in Boston.pptxmary850239
 
MS4 level being good citizen -imperative- (1) (1).pdf
MS4 level   being good citizen -imperative- (1) (1).pdfMS4 level   being good citizen -imperative- (1) (1).pdf
MS4 level being good citizen -imperative- (1) (1).pdfMr Bounab Samir
 
ICS 2208 Lecture Slide Notes for Topic 6
ICS 2208 Lecture Slide Notes for Topic 6ICS 2208 Lecture Slide Notes for Topic 6
ICS 2208 Lecture Slide Notes for Topic 6Vanessa Camilleri
 
ClimART Action | eTwinning Project
ClimART Action    |    eTwinning ProjectClimART Action    |    eTwinning Project
ClimART Action | eTwinning Projectjordimapav
 
Satirical Depths - A Study of Gabriel Okara's Poem - 'You Laughed and Laughed...
Satirical Depths - A Study of Gabriel Okara's Poem - 'You Laughed and Laughed...Satirical Depths - A Study of Gabriel Okara's Poem - 'You Laughed and Laughed...
Satirical Depths - A Study of Gabriel Okara's Poem - 'You Laughed and Laughed...HetalPathak10
 
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...DhatriParmar
 
Tree View Decoration Attribute in the Odoo 17
Tree View Decoration Attribute in the Odoo 17Tree View Decoration Attribute in the Odoo 17
Tree View Decoration Attribute in the Odoo 17Celine George
 
4.9.24 Social Capital and Social Exclusion.pptx
4.9.24 Social Capital and Social Exclusion.pptx4.9.24 Social Capital and Social Exclusion.pptx
4.9.24 Social Capital and Social Exclusion.pptxmary850239
 
How to Manage Buy 3 Get 1 Free in Odoo 17
How to Manage Buy 3 Get 1 Free in Odoo 17How to Manage Buy 3 Get 1 Free in Odoo 17
How to Manage Buy 3 Get 1 Free in Odoo 17Celine George
 
Employablity presentation and Future Career Plan.pptx
Employablity presentation and Future Career Plan.pptxEmployablity presentation and Future Career Plan.pptx
Employablity presentation and Future Career Plan.pptxryandux83rd
 
Sulphonamides, mechanisms and their uses
Sulphonamides, mechanisms and their usesSulphonamides, mechanisms and their uses
Sulphonamides, mechanisms and their usesVijayaLaxmi84
 
CHUYÊN ĐỀ ÔN THEO CÂU CHO HỌC SINH LỚP 12 ĐỂ ĐẠT ĐIỂM 5+ THI TỐT NGHIỆP THPT ...
CHUYÊN ĐỀ ÔN THEO CÂU CHO HỌC SINH LỚP 12 ĐỂ ĐẠT ĐIỂM 5+ THI TỐT NGHIỆP THPT ...CHUYÊN ĐỀ ÔN THEO CÂU CHO HỌC SINH LỚP 12 ĐỂ ĐẠT ĐIỂM 5+ THI TỐT NGHIỆP THPT ...
CHUYÊN ĐỀ ÔN THEO CÂU CHO HỌC SINH LỚP 12 ĐỂ ĐẠT ĐIỂM 5+ THI TỐT NGHIỆP THPT ...Nguyen Thanh Tu Collection
 
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITWQ-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITWQuiz Club NITW
 
6 ways Samsung’s Interactive Display powered by Android changes the classroom
6 ways Samsung’s Interactive Display powered by Android changes the classroom6 ways Samsung’s Interactive Display powered by Android changes the classroom
6 ways Samsung’s Interactive Display powered by Android changes the classroomSamsung Business USA
 
Comparative Literature in India by Amiya dev.pptx
Comparative Literature in India by Amiya dev.pptxComparative Literature in India by Amiya dev.pptx
Comparative Literature in India by Amiya dev.pptxAvaniJani1
 
How to Uninstall a Module in Odoo 17 Using Command Line
How to Uninstall a Module in Odoo 17 Using Command LineHow to Uninstall a Module in Odoo 17 Using Command Line
How to Uninstall a Module in Odoo 17 Using Command LineCeline George
 

Último (20)

Mythology Quiz-4th April 2024, Quiz Club NITW
Mythology Quiz-4th April 2024, Quiz Club NITWMythology Quiz-4th April 2024, Quiz Club NITW
Mythology Quiz-4th April 2024, Quiz Club NITW
 
4.9.24 School Desegregation in Boston.pptx
4.9.24 School Desegregation in Boston.pptx4.9.24 School Desegregation in Boston.pptx
4.9.24 School Desegregation in Boston.pptx
 
MS4 level being good citizen -imperative- (1) (1).pdf
MS4 level   being good citizen -imperative- (1) (1).pdfMS4 level   being good citizen -imperative- (1) (1).pdf
MS4 level being good citizen -imperative- (1) (1).pdf
 
ICS 2208 Lecture Slide Notes for Topic 6
ICS 2208 Lecture Slide Notes for Topic 6ICS 2208 Lecture Slide Notes for Topic 6
ICS 2208 Lecture Slide Notes for Topic 6
 
ClimART Action | eTwinning Project
ClimART Action    |    eTwinning ProjectClimART Action    |    eTwinning Project
ClimART Action | eTwinning Project
 
Spearman's correlation,Formula,Advantages,
Spearman's correlation,Formula,Advantages,Spearman's correlation,Formula,Advantages,
Spearman's correlation,Formula,Advantages,
 
Satirical Depths - A Study of Gabriel Okara's Poem - 'You Laughed and Laughed...
Satirical Depths - A Study of Gabriel Okara's Poem - 'You Laughed and Laughed...Satirical Depths - A Study of Gabriel Okara's Poem - 'You Laughed and Laughed...
Satirical Depths - A Study of Gabriel Okara's Poem - 'You Laughed and Laughed...
 
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
 
Chi-Square Test Non Parametric Test Categorical Variable
Chi-Square Test Non Parametric Test Categorical VariableChi-Square Test Non Parametric Test Categorical Variable
Chi-Square Test Non Parametric Test Categorical Variable
 
Tree View Decoration Attribute in the Odoo 17
Tree View Decoration Attribute in the Odoo 17Tree View Decoration Attribute in the Odoo 17
Tree View Decoration Attribute in the Odoo 17
 
4.9.24 Social Capital and Social Exclusion.pptx
4.9.24 Social Capital and Social Exclusion.pptx4.9.24 Social Capital and Social Exclusion.pptx
4.9.24 Social Capital and Social Exclusion.pptx
 
How to Manage Buy 3 Get 1 Free in Odoo 17
How to Manage Buy 3 Get 1 Free in Odoo 17How to Manage Buy 3 Get 1 Free in Odoo 17
How to Manage Buy 3 Get 1 Free in Odoo 17
 
Mattingly "AI & Prompt Design" - Introduction to Machine Learning"
Mattingly "AI & Prompt Design" - Introduction to Machine Learning"Mattingly "AI & Prompt Design" - Introduction to Machine Learning"
Mattingly "AI & Prompt Design" - Introduction to Machine Learning"
 
Employablity presentation and Future Career Plan.pptx
Employablity presentation and Future Career Plan.pptxEmployablity presentation and Future Career Plan.pptx
Employablity presentation and Future Career Plan.pptx
 
Sulphonamides, mechanisms and their uses
Sulphonamides, mechanisms and their usesSulphonamides, mechanisms and their uses
Sulphonamides, mechanisms and their uses
 
CHUYÊN ĐỀ ÔN THEO CÂU CHO HỌC SINH LỚP 12 ĐỂ ĐẠT ĐIỂM 5+ THI TỐT NGHIỆP THPT ...
CHUYÊN ĐỀ ÔN THEO CÂU CHO HỌC SINH LỚP 12 ĐỂ ĐẠT ĐIỂM 5+ THI TỐT NGHIỆP THPT ...CHUYÊN ĐỀ ÔN THEO CÂU CHO HỌC SINH LỚP 12 ĐỂ ĐẠT ĐIỂM 5+ THI TỐT NGHIỆP THPT ...
CHUYÊN ĐỀ ÔN THEO CÂU CHO HỌC SINH LỚP 12 ĐỂ ĐẠT ĐIỂM 5+ THI TỐT NGHIỆP THPT ...
 
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITWQ-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
 
6 ways Samsung’s Interactive Display powered by Android changes the classroom
6 ways Samsung’s Interactive Display powered by Android changes the classroom6 ways Samsung’s Interactive Display powered by Android changes the classroom
6 ways Samsung’s Interactive Display powered by Android changes the classroom
 
Comparative Literature in India by Amiya dev.pptx
Comparative Literature in India by Amiya dev.pptxComparative Literature in India by Amiya dev.pptx
Comparative Literature in India by Amiya dev.pptx
 
How to Uninstall a Module in Odoo 17 Using Command Line
How to Uninstall a Module in Odoo 17 Using Command LineHow to Uninstall a Module in Odoo 17 Using Command Line
How to Uninstall a Module in Odoo 17 Using Command Line
 

Network Techniques

  • 1. NAME : AVULA ANIL KUMAR ROLL NO : 1007-15-508-010 SUBJECT : APPLIED STATISTICS SEMISTER : III TOPIC : Network Techniques 3 December 2016
  • 2. CPM and PERT Network techniques 3 December 2016
  • 3. Contents  INTRODUCTION  DEFINITIONS OF PROJECT AND PROJECT MANAGEMENT  NETWORK PLANNING METHODS  WHAT IS NETWORK  CONSTRUCTION OF NETWORK  CPM  PERT  CPM VS PERT 3 December 2016
  • 4. INTRODUCTION  To perform any job optimally we should have some planning  Generally planning and performing job is called project.  The project requires some techniques to done the project  Those are CPM and PERT 3 December 2016
  • 5. Definitions Project:  project is a group or combination of activities that must be executed in a certain fixed order before entire task is completed.  The projects are non-repetitive large tasks Project management:  Project management is a scientific way of planning, implementing, monitoring & controlling the various aspects of a project such as time, money, materials, manpower & other resources. 3 December 2016
  • 6. Real time example for a project  Project: Getting ready to attend the college  Wake up in the Morning  Brush your teeth  Take bath  Wear formal dress  Take break fast  Walk to the college  These are the basic activities we need to complete for accomplishment of project. 3 December 2016
  • 7. Network Planning methods  Methods used for network planning are:  CPM  PERT  Managing a project with network planning methods involves four steps:  Describing the project.  Diagramming the Network.  Estimating time of completion.  Monitoring project progress. 3 December 2016
  • 8. Network Diagram  Network: Network is a graphical representation of a project operations and it is composed of several activities and events which are inter-related.  Network consists of:  Event  Activity 3 December 2016
  • 9. Basic Building blocks of Network  Activity: Activity is a recognizable part of the project which consume time and resources for its completion. In network diagram “ARROW” represents activity  Critical activity  Dummy activity  Event: An event represents the accomplishment of some task. In a network diagram, beginning and ending of an activity represented by an event. In network diagram “NODE” represents event.  Merge event  Burst event 3 December 2016
  • 10. Construction of a Network Rules for drawing network diagram 1. Each activity is represented by one and only one arrow in the network 2. No two activities can be identified by the same end events 3. Before an activity can begin, it preceding activities must be completed. 4. Arrows indicate logical precedence. 5. Flow of the diagram is from left to right 6. Arrows should not intersect. 7. Dangling should be avoided. 3 December 2016
  • 11. Activity Precedence A -------- B -------- C A D B E A F B G C,D H G,F I E J H,I K J 3 December 2016
  • 12. CPM  CPM means “critical path method”.  It is a network technique used to evaluate the project.  If the activity times are deterministic then critical path method can be used as a systematic method.  CPM evaluates project by determining critical path in the network. 3 December 2016
  • 13. Critical Path  Critical path is the longest path in the network from the starting event to ending event  Critical path defines minimum time required to complete the project  In network diagram critical path is represented with double arrows  Critical path consist:  Critical event: The events with zero slack  Critical activity: The activities with zero total float 3 December 2016
  • 14. Network of CPM  Earliest Activity start time(EST) The earliest start time that an activity can be started  Earliest Activity finish time(EFT) EFT= EST + Duration  Latest Activity finish time(LFT)  Latest Activity start time(LST) LST= LFT-duration 3 December 2016
  • 15. Types of Float  Total float (TF)ij = (Lj – Tij)- Ei  Free float (Ff)Ij =Total float – ( Lj- Ej)  Independent float (If)ij = Free float- Tail event slack Tiji j Ei Ej Li Lj 3 December 2016
  • 16. Draw network diagram and analyzing CPM Activity Immediate predecessor Duration (months) A -------------- 2 B -------------- 5 C -------------- 4 D B 5 E A 7 F A 3 G B 3 H C,D 6 I C,D 2 J E 5 K F,G,H 4 L F,G,H 3 M I 12 N J,K 8 3 December 2016
  • 17. PERT  PERT means project (or) programme Evaluation & Review Technique.  When activity times are probabilistic, PERT is an effective tool for evaluate project.  PERT is associated with 3 time estimates  Optimistic Time ( to)  Pessimistic Time ( tP)  Most likely Time ( tm) 3 December 2016
  • 18. Activity Times in PERT  Optimistic Time: ( To) It is the minimum time that is required to complete an activity when every resource is available  Most likely Time: (Tm) This is the time required for the completion of activity under normal conditions.  Pessimistic Time: (Tp) The most time that is required to complete activity when every resource is not available Note: In PERT β – distribution is used to represent these three time estimates 3 December 2016
  • 19. Formulae used for evaluation of PERT  Time estimate (Te)= 𝑇𝑜+𝑇𝑝+4𝑇𝑚 6  Standard deviation ( )= 𝑇𝑝 −𝑇𝑂 6  Variance = 𝑇𝑝−𝑇𝑜 2 36 3 December 2016
  • 20. CPM VS PERT CPM PERT It is activity oriented It is event oriented It is associated with deterministic activities It is associated with probabilistic activities It is based upon single time to complete an activity It is based upon 3 time estimate to complete an activity It is used mainly for construction project It is used mainly for research and development project 3 December 2016