National Aeronautics and Space Administration
Commercial Orbital Transportation
Services (COTS) Program
Lessons Learned
HEOMD Knowledge Sharing Forum
November 13, 2013
NASA HQ
Alan Lindenmoyer
Program Manager
Mike Horkachuck Gwynne Shotwell
COTS Project Executive for SpaceX President, SpaceX
Bruce Manners Frank Culbertson
COTS Project Executive for Orbital Executive VP and General Manager, Orbital
2
Agenda
• COTS Summary
– SpaceX
– Orbital
• Key Lessons Learned
– From Program
– From SpaceX
– From Orbital
3
SpaceX COTS Summary
• COTS Space Act Agreement awarded
August 2006 and amended in December
2010 with additional risk reduction
milestones
• All 40 milestones completed in August
2012 for payments totaling $396M
– Demo Mission 1: December 8, 2010
– Demo Mission 2/3: May 22-31, 2012
• Key Facts:
– New Falcon 9 U.S. launch vehicle
– New autonomous Dragon cargo
spacecraft capable of carrying cargo to
and from the ISS and LEO
– New commercial launch facility at
CCAFS, FL
Cape Canaveral Launch Site
ISS Capture of Dragon
Falcon 9
4
SpaceX C2+ Launch
May 22, 2012SpaceX COTS Demonstration Launches
C1 Launch
December 8, 2010
C2+ Launch
May 22, 2012
5
SpaceX COTS Demo Mission C2+
Cargo Return
Dragon splashdown in Pacific May 31,2012
Returned ISS cargoDragon in McGregor, TX
On recovery ship
6
$M $M 2006 2007 2008 2009 2010 2011 2012
Milestones Total Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
278.0
1 Project Mgmt Plan 23.1 23.1
2 Demo 1 SRR 5.0 28.1
3 Demo 1 PDR 18.1 46.2
4 Financing Round 1 10.0 56.2
5 Demo 2 SRR 31.1 87.4
6 Demo 1 CDR 8.1 95.5
7 Demo 3 SRR 22.3 117.8
8 Demo 2 PDR 21.1 139.0
9 Draco Init. Hot fire 6.0 145.0
10 Financing Round 2 10.0 155.0
11 Demo 3 PDR 22.0 177.0
12 Multi-Engine Test 22.0 199.0
13 Demo 2/3 CDR 25.0 224.0
14 Financing Round 3 10.0 234.0
15 Demo 1 RR 5.0 239.0
16 CUCU Flight Unit 9.0 248.0
17 Demo 1 Mission 5.0 253.0
18 Demo 2 RR 5.0 258.0
19 Demo 2 Mission 5.0 263.0
20 Cargo Int. Demo 5.0 268.0
21 Demo 3 RR 5.0 273.0
22 Demo 3 Mission 5.0 278.0
SpaceX COTS Milestones
08-27-12
Feb
May Jul 23
Feb 8
Nov 29
Aug 22
Sep 15
Mar 1
Mar 15
Aug 4
Mar Jun 8
Feb 8
Dec 18 Jan
Mar 21
Mar 21
Dec 19
Oct 29
Jun 27Apr
Sep
Mar
JunSep Dec 15
Jun Nov
JanDec 18
Dec Sep
Jul Dec
Sep Jun 7
Current Plan
Actual Completion Date
Initial SAA Plan
Jan
Mar 9
Jun 7
Aug 22
7
$M $M 2007 2008 2009 2010 2011 2012
Milestones Total Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
118.0
23 Modal Test Plan 5.0 5.0
24 Modal Test 5.0 10.0
25 LIDAR Test (open loop) 5.0 15.0
26 Solar Array Deploy Test 5.0 20.0
27
LIDAR Test Plan
(closed loop) 5.0 25.0
28
Thermal Vacuum Test
Plan 5.0 30.0
29 Infrastructure Plan 10.0 40.0
30 Thermal Vacuum Test 20.0 60.0
31
Test site Infrastructure
Implementation 5.0 65.0
32
Dragon Trunk Acoustic
Test 10.0 75.0
33
LIDAR Test 6 DOF
(closed loop) 5.0 80.0
34
Design Rev. Enhanced
Powered Cargo Accom. 5.0 85.0
35
Design Rev. Pressurized
Cargo Vol Increase 5.0 90.0
36
Dragon EMI/EMC Test
(HITL) 10.0 100.0
37
Dragon Cargo Racks &
Hatch Simulator 3.0 103.0
38
Ground Demo Enhanced
Powered Cargo 5.0 108.0
39
Launch site Infrastructure
Implementation 5.0 113.0
40
Production Infrastructure
Implementation 5.0 118.0
SAA Total 396.0 396.0
SpaceX Augmented COTS Milestones
10-27-11
Dec 16
Dec 16
Dec 16
Dec 16
Mar 31
Mar
Mar
Current Plan
Actual Completion Date
Initial SAA Plan
Apr 6
May 10
Jul
Jun 23
Jun 23
Jul
Aug
Sep 14
Oct 26
Aug 24
Aug 24
Aug 26
Sep 20
Sep Oct 26
Sep Oct 26
Sep Oct 26
8
Orbital COTS Summary
• Space Act Agreement awarded February
2008 and amended in December 2010
with additional risk reduction milestones
• All 29 milestones completed in November
2013 for payments totaling $288M
– Maiden Test Flight: April 21, 2013
– ISS Demo Mission: Sep. 18-23, 2013
• Key Facts:
– New Antares U.S. launch vehicle
– New autonomous Cygnus cargo spacecraft
capable of carrying cargo to the ISS and
disposing cargo from the ISS
– New commercial launch facility at Wallops
Island, VA
Antares MARS/Wallops Launch Site
Cygnus Approaching ISS
9
Orbital COTS Demonstration Launches
A-ONE Launch
April 21, 2013
Orb-D1 Launch
September 21, 2013
10
Orbital D-1 ISS Demonstration Mission
D-1
Orb-1
D-1
Cygnus
11
$M $M 2008 2009 2010 2011 2012 2013
Milestones Total Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
170.0
1 Program Plan Review 10.0 10.0
2 Demo Mission SRR 20.0 30.0
3 UCM PDR 10.0 40.0
4 DELETED
5 COTS Int/Ops Facility 10.0 50.0
6 PCM PDR 10.0 60.0
7 DELETED
8 IP&CL Submission 10.0 70.0
9 ISS Phase 1 SRP 10.0 80.0
10 COTS System PDR 20.0 100.0
11 PCM CDR 10.0 110.0
12 Cygnus Avionics Test 10.0 120.0
13 ISS Phase 2 SRP 10.0 130.0
14 COTS System CDR 10.0 140.0
15
SM Core Assembly
Complete 7.5 147.5
16 SM Test Readiness Review 7.5 155.0
17 SM Initial CPT 5.0 160.0
18 LV Stage I Assy. Complete 2.5 162.5
19 Cargo Int. Demo 2.5 165.0
20 Mission Readiness Review 2.5 167.5
21 System Demo Flight 2.5 170.0
Orbital COTS Milestones
08-05-13
Current Plan
Actual Completion Date
Initial SAA Plan
Aug Nov 6
Apr May 22
Mar 27
Sep
Aug 14
Jul 17
Feb 18
Oct 9
Sep 22
Jun
Nov
Oct
Jul
Mar 31
Aug 13
Jul 31
Jun
Mar Mar 23Sep
Aug 30
Nov 17
DecOct
Sep Sep
Dec
Oct
Dec 6
Oct
Dec
JunMay
AprJan
Nov 6
Jul 27
Dec 14
Jul 11
12
$M $M 2008 2009 2010 2011 2012 2013
Milestones Total Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
118.0
22 Test Flight Mission Review 20.0 20.0
23 Test Flight Mission Analys. 10.0 30.0
24
Cygnus Mass Sim. (CMS)
Design Review 10.0 40.0
25
Install Add’l PITL
Simulators 5.0 45.0
26 PROX FEU Test Unit 5.0 50.0
27 Maiden Flt Stg 1 Core Del. 24.0 74.0
28 Maiden Flt Uppr Stage Del. 20.0 94.0
29 Maiden Flt CMS Delivered 10.0 104.0
30 Maiden Flt Stage 1 Assy. 10.0 114.0
31 Maiden Test Flight 4.0 118.0
SAA Total 288.0 280.5
Orbital Augmented COTS Milestones
05-16-13
Current Plan
Actual Completion Date
Initial SAA Plan
Dec 15
Feb 23
Mar 03
Apr
May
Apr 28
Jun 21
Jun 20
Jul
Oct
May 6
Jun 17
May 9
Sep 17
13
Key Lessons Learned from Program
• Government seed money was highly leveraged
– Commercial partners funded over 50% of COTS development costs
• Fixed price milestone payments maximized incentive to control cost and minimize
schedule delays
• Minimum firm requirements along with commensurate Government oversight were key to
fostering innovation and reducing life cycle development costs
– Goals (vs. requirements) were established to open trade space and optimize design
– Firm requirements were identified only where necessary to assure the safety of the ISS and crew
– ISS interface requirements evolved over time and were coordinated in a collaborative manner with
the commercial partners
• A portfolio of multiple partners with different capabilities assured a balanced approach to
technical and business risks
– Increased the chances of at least one successful partner
– Market forces kept development and operational costs in check
• Commercial friendly intellectual property/data rights and limited termination liability
encouraged investment of private capital
14
Lessons Learned from Program (Cont.)
• NASA commitment to purchase operational services greatly improves the ability for
companies to raise funds
• NASA does not have the statutory authority to provide Government Furnished Equipment
(GFE) under a SAA
– Even though originally contemplated in the SAA and in the best interest of the Government, COTS
had to revert to loan agreements and cumbersome GSA excess procedures to transfer equipment
to facilitate berthing with the ISS
• Augmentation of funding late in the program enabled additional risk reduction testing not
initially affordable
– Directly contributed to the successful first attempt berthing of SpaceX Dragon to ISS
– Would be difficult to predict how much, if any, to hold in reserve during program formulation and
initialization to protect for such milestone adjustments
• COTS model for public-private partnerships worked!
15
Key Lessons Learned from SpaceX
• Design, Test and Repeat (engineering units prior to qualification)
– This philosophy can be better than just detailed analysis and only one test –learn much more
– Need to have a team that can react and make changes quickly
• Use of COTS electronics parts is feasible (instead of all S-level parts) thru use of some
radiation screening/tests and better architecture decisions (redundancy and reboot
capability)
– Saves significant cost and schedule over traditional avionics
– Previous Cost "GE Price" modeling experience was ”No matter how many runs done with varying
complexity, similarity vs new design, etc– the cost and schedule of the Avionics and software
drove the project cost.” Much more expensive than even massive structure or thermal systems.
 Note: if total length of a project can be reduced 6-12 months by using readily available parts and
processes, you really save the monthly burn rate of the whole project for that many months.
– Just gets projects done faster, so NASA could be more responsive and can do more things
• Design with cost in mind
– SpaceX paid much more attention to the cost of parts and component in the initial design phases
than NASA contractors traditionally do; to the point of building many things in house, because it
was perceived to be too expensive to buy vendor part. They always questioned why it can’t be
done less expensively and pushed back on costly requirements.
– In-house production has the added benefit of allowing better schedule control than from sub-tier
suppliers and allows a streamlined change/update process.
16
Key Lessons Learned from SpaceX (Cont.)
• NASA observed SpaceX’s use of “WIKI tools” for multiple critical business and
engineering processes saves time—trying to move to a paperless environment.
– Microsoft SharePoint and Confluence primarily for team processes and general info that they want
teams to have instead of some team meetings
– Provided models instead of large documents in some cases (FEM models and summary vs
structural analysis report)
– TRAC tickets are being used for issues, changes and risks by many teams.
 Provides a "virtual" meeting to ask questions and throw out ideas. Tracks all the comments for others to
look at. Eventually, bringing them to closure and having all the managers and responsible engineers
sign off on it.
 Saves time (schedule) by letting people look at ticket when they can fit it in their schedule and not have
to wait for a meeting to be called when everyone can attend.  a Virtual board/review if you will.
– NASA use suggested for simple issues, changes and risk (identify them as such), but move quickly
to a meeting if not coming to timely closure or unclear questions arise.
17
Key Lessons Learned from Orbital
• Design Review Process – Independent Review Teams
– Use of independent review team (IRT) of “experienced” experts to serve as design review team can
be very effective
– IRT typically not bound by cost or schedule and can serve as a common sense sounding board for
design and programmatic decisions
– Membership of team should remain consistent throughout program (to the extent practical)
– Review team findings should go to level of management above program manager for
disposition/review
• Use of “standard building block” designs
– NASA standard practices typically utilize custom or first use designs, whereas commercial
leverages existing “product line” designs
– Lowers technical risk due to vast experience with designs/components
– Could also potentially lower cost & schedule due to potentially eliminating the need for additional
qualification testing (where applicable)
– Does not come without risk however…
• Leveraging common goals with all constituents (i.e. States, local governments, DOD,…)
– NASA frequently “goes it alone” on programs and supplies all funding
– Commercial industry realizes the benefits of competition and synergistic desires
 Example – State of Virginia had interests in developing spaceport (i.e. MARS) and supplied significant
funding
 Example – Industry partners, in some cases, provided funding for unique hardware in exchange for IP
rights
18
Key Lessons Learned from Orbital
• NASA can embrace cultural shift of working with “Commercial” partners, but it is a
continuing challenge
– NASA has immense technical capability
– NASA needs to understand partner challenges, both technical and programmatic
– NASA needs to avoid “grading” systems designs and offer solutions that consider partner
challenges
– If we show value, industry will “open up”
• Communication & trust is essential
– Partners, not customers or “suppliers”
– Regular tag-ups
– Talk often and early…
– Relationship should be built to last and therefore needs to be protected and nurtured
• Breaking interfaces/systems which were not designed for multi-party use is difficult and
needs careful thought & consideration
19

Mais conteúdo relacionado

Destaque

NAMII Initiative 2013 Part2
NAMII Initiative 2013 Part2NAMII Initiative 2013 Part2
NAMII Initiative 2013 Part2Dmitry Tseitlin
 
U.S. Energy Information Administration _ Oil and Gas Sept 2014
U.S. Energy Information Administration _ Oil and Gas Sept 2014U.S. Energy Information Administration _ Oil and Gas Sept 2014
U.S. Energy Information Administration _ Oil and Gas Sept 2014Dmitry Tseitlin
 
Закон о гражданстве уведомление 4 июня 2014
Закон о гражданстве уведомление 4 июня 2014Закон о гражданстве уведомление 4 июня 2014
Закон о гражданстве уведомление 4 июня 2014Dmitry Tseitlin
 
GE industrial internetatwork
GE industrial internetatworkGE industrial internetatwork
GE industrial internetatworkDmitry Tseitlin
 
NAMII Initiative 2013 Part1
NAMII Initiative 2013 Part1NAMII Initiative 2013 Part1
NAMII Initiative 2013 Part1Dmitry Tseitlin
 
презентация спектралазер 2 июня 2014 сколково окончат
презентация спектралазер 2 июня 2014 сколково окончатпрезентация спектралазер 2 июня 2014 сколково окончат
презентация спектралазер 2 июня 2014 сколково окончатDmitry Tseitlin
 
Turning the corner_vc_insights_2013_lo_res
Turning the corner_vc_insights_2013_lo_resTurning the corner_vc_insights_2013_lo_res
Turning the corner_vc_insights_2013_lo_resDmitry Tseitlin
 
2013 Satellite Industry Association
2013 Satellite Industry Association2013 Satellite Industry Association
2013 Satellite Industry AssociationDmitry Tseitlin
 
Orbital Investors December 2014
Orbital  Investors December 2014Orbital  Investors December 2014
Orbital Investors December 2014Dmitry Tseitlin
 
Booz co 2013-global-innovation-1000-study-navigating-the-digital-future_fact-...
Booz co 2013-global-innovation-1000-study-navigating-the-digital-future_fact-...Booz co 2013-global-innovation-1000-study-navigating-the-digital-future_fact-...
Booz co 2013-global-innovation-1000-study-navigating-the-digital-future_fact-...Dmitry Tseitlin
 
Инновационное предпринимательство, управление НИОКР и трансфер технологий.Кур...
Инновационное предпринимательство, управление НИОКР и трансфер технологий.Кур...Инновационное предпринимательство, управление НИОКР и трансфер технологий.Кур...
Инновационное предпринимательство, управление НИОКР и трансфер технологий.Кур...Dmitry Tseitlin
 
ТП Жигулевская Долина
ТП Жигулевская ДолинаТП Жигулевская Долина
ТП Жигулевская ДолинаDmitry Tseitlin
 
2014 01-29-rosnano business-plan-2020
2014 01-29-rosnano business-plan-20202014 01-29-rosnano business-plan-2020
2014 01-29-rosnano business-plan-2020Dmitry Tseitlin
 

Destaque (18)

Leo final presentation
Leo final presentationLeo final presentation
Leo final presentation
 
NAMII Initiative 2013 Part2
NAMII Initiative 2013 Part2NAMII Initiative 2013 Part2
NAMII Initiative 2013 Part2
 
U.S. Energy Information Administration _ Oil and Gas Sept 2014
U.S. Energy Information Administration _ Oil and Gas Sept 2014U.S. Energy Information Administration _ Oil and Gas Sept 2014
U.S. Energy Information Administration _ Oil and Gas Sept 2014
 
Закон о гражданстве уведомление 4 июня 2014
Закон о гражданстве уведомление 4 июня 2014Закон о гражданстве уведомление 4 июня 2014
Закон о гражданстве уведомление 4 июня 2014
 
GE industrial internetatwork
GE industrial internetatworkGE industrial internetatwork
GE industrial internetatwork
 
L 07820140317en00060015
L 07820140317en00060015L 07820140317en00060015
L 07820140317en00060015
 
NAMII Initiative 2013 Part1
NAMII Initiative 2013 Part1NAMII Initiative 2013 Part1
NAMII Initiative 2013 Part1
 
Sk Space June 2014
Sk Space June 2014Sk Space June 2014
Sk Space June 2014
 
Laser projection
Laser projection Laser projection
Laser projection
 
презентация спектралазер 2 июня 2014 сколково окончат
презентация спектралазер 2 июня 2014 сколково окончатпрезентация спектралазер 2 июня 2014 сколково окончат
презентация спектралазер 2 июня 2014 сколково окончат
 
Turning the corner_vc_insights_2013_lo_res
Turning the corner_vc_insights_2013_lo_resTurning the corner_vc_insights_2013_lo_res
Turning the corner_vc_insights_2013_lo_res
 
2013 Satellite Industry Association
2013 Satellite Industry Association2013 Satellite Industry Association
2013 Satellite Industry Association
 
Orbital Investors December 2014
Orbital  Investors December 2014Orbital  Investors December 2014
Orbital Investors December 2014
 
Booz co 2013-global-innovation-1000-study-navigating-the-digital-future_fact-...
Booz co 2013-global-innovation-1000-study-navigating-the-digital-future_fact-...Booz co 2013-global-innovation-1000-study-navigating-the-digital-future_fact-...
Booz co 2013-global-innovation-1000-study-navigating-the-digital-future_fact-...
 
Инновационное предпринимательство, управление НИОКР и трансфер технологий.Кур...
Инновационное предпринимательство, управление НИОКР и трансфер технологий.Кур...Инновационное предпринимательство, управление НИОКР и трансфер технологий.Кур...
Инновационное предпринимательство, управление НИОКР и трансфер технологий.Кур...
 
ТП Жигулевская Долина
ТП Жигулевская ДолинаТП Жигулевская Долина
ТП Жигулевская Долина
 
Ресурс П
Ресурс ПРесурс П
Ресурс П
 
2014 01-29-rosnano business-plan-2020
2014 01-29-rosnano business-plan-20202014 01-29-rosnano business-plan-2020
2014 01-29-rosnano business-plan-2020
 

Semelhante a Cots lessons learned_2013_nov13

COTS_lessons learned_2013_nov_13
COTS_lessons learned_2013_nov_13COTS_lessons learned_2013_nov_13
COTS_lessons learned_2013_nov_13Dmitry Tseitlin
 
Commercial Crew Program status-update-1-9-13
Commercial Crew Program status-update-1-9-13Commercial Crew Program status-update-1-9-13
Commercial Crew Program status-update-1-9-13Dmitry Tseitlin
 
CCCProgram_TIMM-COMSTAC_ 5-16-07.ppt
CCCProgram_TIMM-COMSTAC_ 5-16-07.pptCCCProgram_TIMM-COMSTAC_ 5-16-07.ppt
CCCProgram_TIMM-COMSTAC_ 5-16-07.pptBUSTOSZUIGAMARLONGUS
 
NASA_CCO_status-2013 update
NASA_CCO_status-2013 updateNASA_CCO_status-2013 update
NASA_CCO_status-2013 updateDmitry Tseitlin
 
Investor space ops-presentation_2_dec2017
Investor  space ops-presentation_2_dec2017Investor  space ops-presentation_2_dec2017
Investor space ops-presentation_2_dec2017BillPannell1
 
Briefing - The Atlast V Aft Bulkhead Carrier Update - Past Missions, Upcoming...
Briefing - The Atlast V Aft Bulkhead Carrier Update - Past Missions, Upcoming...Briefing - The Atlast V Aft Bulkhead Carrier Update - Past Missions, Upcoming...
Briefing - The Atlast V Aft Bulkhead Carrier Update - Past Missions, Upcoming...Dave Callen
 
DLA End of Fall Semester Report
DLA End of Fall Semester ReportDLA End of Fall Semester Report
DLA End of Fall Semester ReportAaron Aboaf
 
4 Super Lightweight Tank - Risk Management
4 Super Lightweight Tank - Risk Management4 Super Lightweight Tank - Risk Management
4 Super Lightweight Tank - Risk Managementpmb25
 
Cook.richard
Cook.richardCook.richard
Cook.richardNASAPMC
 
Patrick.guske.update
Patrick.guske.updatePatrick.guske.update
Patrick.guske.updateNASAPMC
 
Patrick.guske.update
Patrick.guske.updatePatrick.guske.update
Patrick.guske.updateNASAPMC
 
Project management @ bec doms
Project management @ bec domsProject management @ bec doms
Project management @ bec domsBabasab Patil
 
Project Plan - Risk Management & Integration
Project Plan - Risk Management & IntegrationProject Plan - Risk Management & Integration
Project Plan - Risk Management & IntegrationPrachi Dikshit
 
Project management@ ppt doms
Project management@ ppt doms Project management@ ppt doms
Project management@ ppt doms Babasab Patil
 
PMI Global 2007 - Urucu/Manaus
PMI Global 2007 - Urucu/ManausPMI Global 2007 - Urucu/Manaus
PMI Global 2007 - Urucu/ManausPeter Mello
 
SpaceX Rocket Data
SpaceX Rocket DataSpaceX Rocket Data
SpaceX Rocket DataK Jagannath
 

Semelhante a Cots lessons learned_2013_nov13 (20)

COTS_lessons learned_2013_nov_13
COTS_lessons learned_2013_nov_13COTS_lessons learned_2013_nov_13
COTS_lessons learned_2013_nov_13
 
Commercial Crew Program status-update-1-9-13
Commercial Crew Program status-update-1-9-13Commercial Crew Program status-update-1-9-13
Commercial Crew Program status-update-1-9-13
 
CCCProgram_TIMM-COMSTAC_ 5-16-07.ppt
CCCProgram_TIMM-COMSTAC_ 5-16-07.pptCCCProgram_TIMM-COMSTAC_ 5-16-07.ppt
CCCProgram_TIMM-COMSTAC_ 5-16-07.ppt
 
NASA_CCO_status-2013 update
NASA_CCO_status-2013 updateNASA_CCO_status-2013 update
NASA_CCO_status-2013 update
 
Ianson
IansonIanson
Ianson
 
Investor space ops-presentation_2_dec2017
Investor  space ops-presentation_2_dec2017Investor  space ops-presentation_2_dec2017
Investor space ops-presentation_2_dec2017
 
Briefing - The Atlast V Aft Bulkhead Carrier Update - Past Missions, Upcoming...
Briefing - The Atlast V Aft Bulkhead Carrier Update - Past Missions, Upcoming...Briefing - The Atlast V Aft Bulkhead Carrier Update - Past Missions, Upcoming...
Briefing - The Atlast V Aft Bulkhead Carrier Update - Past Missions, Upcoming...
 
Goddard 2015: Pamela Melroy, DARPA
Goddard 2015: Pamela Melroy, DARPAGoddard 2015: Pamela Melroy, DARPA
Goddard 2015: Pamela Melroy, DARPA
 
DLA End of Fall Semester Report
DLA End of Fall Semester ReportDLA End of Fall Semester Report
DLA End of Fall Semester Report
 
Ssc10 iv-2
Ssc10 iv-2Ssc10 iv-2
Ssc10 iv-2
 
4 Super Lightweight Tank - Risk Management
4 Super Lightweight Tank - Risk Management4 Super Lightweight Tank - Risk Management
4 Super Lightweight Tank - Risk Management
 
Cook.richard
Cook.richardCook.richard
Cook.richard
 
Patrick.guske.update
Patrick.guske.updatePatrick.guske.update
Patrick.guske.update
 
Patrick.guske.update
Patrick.guske.updatePatrick.guske.update
Patrick.guske.update
 
Project management @ bec doms
Project management @ bec domsProject management @ bec doms
Project management @ bec doms
 
Project Plan - Risk Management & Integration
Project Plan - Risk Management & IntegrationProject Plan - Risk Management & Integration
Project Plan - Risk Management & Integration
 
IG-12-022
IG-12-022IG-12-022
IG-12-022
 
Project management@ ppt doms
Project management@ ppt doms Project management@ ppt doms
Project management@ ppt doms
 
PMI Global 2007 - Urucu/Manaus
PMI Global 2007 - Urucu/ManausPMI Global 2007 - Urucu/Manaus
PMI Global 2007 - Urucu/Manaus
 
SpaceX Rocket Data
SpaceX Rocket DataSpaceX Rocket Data
SpaceX Rocket Data
 

Mais de Dmitry Tseitlin

Ton Tlegram Open Network
Ton Tlegram Open NetworkTon Tlegram Open Network
Ton Tlegram Open NetworkDmitry Tseitlin
 
State of innovation Thomson Reuters 2016
State of innovation Thomson Reuters 2016 State of innovation Thomson Reuters 2016
State of innovation Thomson Reuters 2016 Dmitry Tseitlin
 
Clarity from above PWC 2016
Clarity from above PWC 2016Clarity from above PWC 2016
Clarity from above PWC 2016Dmitry Tseitlin
 
Отчет Фонд Сколково 25 апреля 2011
Отчет Фонд Сколково 25 апреля 2011Отчет Фонд Сколково 25 апреля 2011
Отчет Фонд Сколково 25 апреля 2011Dmitry Tseitlin
 
Technology roadmap highlights_report 2015
Technology roadmap highlights_report 2015Technology roadmap highlights_report 2015
Technology roadmap highlights_report 2015Dmitry Tseitlin
 
IGS Low cost access to space April 2016
IGS Low cost access to space April 2016IGS Low cost access to space April 2016
IGS Low cost access to space April 2016Dmitry Tseitlin
 
Satellite technologies in UK agriculture 2015
Satellite technologies in UK agriculture 2015Satellite technologies in UK agriculture 2015
Satellite technologies in UK agriculture 2015Dmitry Tseitlin
 
A Roadmap to Interstellar Flight Philip Lubin Physics Dept, UC Santa Barbara ...
A Roadmap to Interstellar Flight Philip Lubin Physics Dept, UC Santa Barbara ...A Roadmap to Interstellar Flight Philip Lubin Physics Dept, UC Santa Barbara ...
A Roadmap to Interstellar Flight Philip Lubin Physics Dept, UC Santa Barbara ...Dmitry Tseitlin
 
Постановление Правительства "О реализации национальной технологической иниц...
Постановление Правительства "О реализации национальной технологической иниц...Постановление Правительства "О реализации национальной технологической иниц...
Постановление Правительства "О реализации национальной технологической иниц...Dmitry Tseitlin
 
ESA - 2013 space transportation
ESA - 2013 space transportation ESA - 2013 space transportation
ESA - 2013 space transportation Dmitry Tseitlin
 
Результаты РФФИ 2015
Результаты РФФИ 2015 Результаты РФФИ 2015
Результаты РФФИ 2015 Dmitry Tseitlin
 
Cоздание сверхтяжелых РН для исследования и освоения Луны и Марса - прошлое, ...
Cоздание сверхтяжелых РН для исследования и освоения Луны и Марса - прошлое, ...Cоздание сверхтяжелых РН для исследования и освоения Луны и Марса - прошлое, ...
Cоздание сверхтяжелых РН для исследования и освоения Луны и Марса - прошлое, ...Dmitry Tseitlin
 
Ракета космического назначения «Зенит 3SL» для программы «Морской Старт» В.М...
Ракета космического назначения «Зенит 3SL» для программы «Морской Старт» В.М...Ракета космического назначения «Зенит 3SL» для программы «Морской Старт» В.М...
Ракета космического назначения «Зенит 3SL» для программы «Морской Старт» В.М...Dmitry Tseitlin
 
Space Works Nano Microsatellite Market forecast 2016
Space Works Nano Microsatellite Market forecast 2016Space Works Nano Microsatellite Market forecast 2016
Space Works Nano Microsatellite Market forecast 2016Dmitry Tseitlin
 
WIPO Global Innovation Index 2015
WIPO Global Innovation Index 2015WIPO Global Innovation Index 2015
WIPO Global Innovation Index 2015Dmitry Tseitlin
 
Agritech Funder Investing report 2015
Agritech Funder Investing report 2015Agritech Funder Investing report 2015
Agritech Funder Investing report 2015Dmitry Tseitlin
 
High technology entrepreneurs and the patent system. 2008 Berkeley
High technology entrepreneurs and the patent system. 2008 BerkeleyHigh technology entrepreneurs and the patent system. 2008 Berkeley
High technology entrepreneurs and the patent system. 2008 BerkeleyDmitry Tseitlin
 
Start-up Space Tauri Group 2016 -
Start-up Space Tauri Group 2016 -Start-up Space Tauri Group 2016 -
Start-up Space Tauri Group 2016 -Dmitry Tseitlin
 
SolarCity Analysts Day_2015
SolarCity Analysts Day_2015SolarCity Analysts Day_2015
SolarCity Analysts Day_2015Dmitry Tseitlin
 

Mais de Dmitry Tseitlin (20)

Ton Tlegram Open Network
Ton Tlegram Open NetworkTon Tlegram Open Network
Ton Tlegram Open Network
 
Marinet en 2017
Marinet en 2017Marinet en 2017
Marinet en 2017
 
State of innovation Thomson Reuters 2016
State of innovation Thomson Reuters 2016 State of innovation Thomson Reuters 2016
State of innovation Thomson Reuters 2016
 
Clarity from above PWC 2016
Clarity from above PWC 2016Clarity from above PWC 2016
Clarity from above PWC 2016
 
Отчет Фонд Сколково 25 апреля 2011
Отчет Фонд Сколково 25 апреля 2011Отчет Фонд Сколково 25 апреля 2011
Отчет Фонд Сколково 25 апреля 2011
 
Technology roadmap highlights_report 2015
Technology roadmap highlights_report 2015Technology roadmap highlights_report 2015
Technology roadmap highlights_report 2015
 
IGS Low cost access to space April 2016
IGS Low cost access to space April 2016IGS Low cost access to space April 2016
IGS Low cost access to space April 2016
 
Satellite technologies in UK agriculture 2015
Satellite technologies in UK agriculture 2015Satellite technologies in UK agriculture 2015
Satellite technologies in UK agriculture 2015
 
A Roadmap to Interstellar Flight Philip Lubin Physics Dept, UC Santa Barbara ...
A Roadmap to Interstellar Flight Philip Lubin Physics Dept, UC Santa Barbara ...A Roadmap to Interstellar Flight Philip Lubin Physics Dept, UC Santa Barbara ...
A Roadmap to Interstellar Flight Philip Lubin Physics Dept, UC Santa Barbara ...
 
Постановление Правительства "О реализации национальной технологической иниц...
Постановление Правительства "О реализации национальной технологической иниц...Постановление Правительства "О реализации национальной технологической иниц...
Постановление Правительства "О реализации национальной технологической иниц...
 
ESA - 2013 space transportation
ESA - 2013 space transportation ESA - 2013 space transportation
ESA - 2013 space transportation
 
Результаты РФФИ 2015
Результаты РФФИ 2015 Результаты РФФИ 2015
Результаты РФФИ 2015
 
Cоздание сверхтяжелых РН для исследования и освоения Луны и Марса - прошлое, ...
Cоздание сверхтяжелых РН для исследования и освоения Луны и Марса - прошлое, ...Cоздание сверхтяжелых РН для исследования и освоения Луны и Марса - прошлое, ...
Cоздание сверхтяжелых РН для исследования и освоения Луны и Марса - прошлое, ...
 
Ракета космического назначения «Зенит 3SL» для программы «Морской Старт» В.М...
Ракета космического назначения «Зенит 3SL» для программы «Морской Старт» В.М...Ракета космического назначения «Зенит 3SL» для программы «Морской Старт» В.М...
Ракета космического назначения «Зенит 3SL» для программы «Морской Старт» В.М...
 
Space Works Nano Microsatellite Market forecast 2016
Space Works Nano Microsatellite Market forecast 2016Space Works Nano Microsatellite Market forecast 2016
Space Works Nano Microsatellite Market forecast 2016
 
WIPO Global Innovation Index 2015
WIPO Global Innovation Index 2015WIPO Global Innovation Index 2015
WIPO Global Innovation Index 2015
 
Agritech Funder Investing report 2015
Agritech Funder Investing report 2015Agritech Funder Investing report 2015
Agritech Funder Investing report 2015
 
High technology entrepreneurs and the patent system. 2008 Berkeley
High technology entrepreneurs and the patent system. 2008 BerkeleyHigh technology entrepreneurs and the patent system. 2008 Berkeley
High technology entrepreneurs and the patent system. 2008 Berkeley
 
Start-up Space Tauri Group 2016 -
Start-up Space Tauri Group 2016 -Start-up Space Tauri Group 2016 -
Start-up Space Tauri Group 2016 -
 
SolarCity Analysts Day_2015
SolarCity Analysts Day_2015SolarCity Analysts Day_2015
SolarCity Analysts Day_2015
 

Cots lessons learned_2013_nov13

  • 1. National Aeronautics and Space Administration Commercial Orbital Transportation Services (COTS) Program Lessons Learned HEOMD Knowledge Sharing Forum November 13, 2013 NASA HQ Alan Lindenmoyer Program Manager Mike Horkachuck Gwynne Shotwell COTS Project Executive for SpaceX President, SpaceX Bruce Manners Frank Culbertson COTS Project Executive for Orbital Executive VP and General Manager, Orbital
  • 2. 2 Agenda • COTS Summary – SpaceX – Orbital • Key Lessons Learned – From Program – From SpaceX – From Orbital
  • 3. 3 SpaceX COTS Summary • COTS Space Act Agreement awarded August 2006 and amended in December 2010 with additional risk reduction milestones • All 40 milestones completed in August 2012 for payments totaling $396M – Demo Mission 1: December 8, 2010 – Demo Mission 2/3: May 22-31, 2012 • Key Facts: – New Falcon 9 U.S. launch vehicle – New autonomous Dragon cargo spacecraft capable of carrying cargo to and from the ISS and LEO – New commercial launch facility at CCAFS, FL Cape Canaveral Launch Site ISS Capture of Dragon Falcon 9
  • 4. 4 SpaceX C2+ Launch May 22, 2012SpaceX COTS Demonstration Launches C1 Launch December 8, 2010 C2+ Launch May 22, 2012
  • 5. 5 SpaceX COTS Demo Mission C2+ Cargo Return Dragon splashdown in Pacific May 31,2012 Returned ISS cargoDragon in McGregor, TX On recovery ship
  • 6. 6 $M $M 2006 2007 2008 2009 2010 2011 2012 Milestones Total Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 278.0 1 Project Mgmt Plan 23.1 23.1 2 Demo 1 SRR 5.0 28.1 3 Demo 1 PDR 18.1 46.2 4 Financing Round 1 10.0 56.2 5 Demo 2 SRR 31.1 87.4 6 Demo 1 CDR 8.1 95.5 7 Demo 3 SRR 22.3 117.8 8 Demo 2 PDR 21.1 139.0 9 Draco Init. Hot fire 6.0 145.0 10 Financing Round 2 10.0 155.0 11 Demo 3 PDR 22.0 177.0 12 Multi-Engine Test 22.0 199.0 13 Demo 2/3 CDR 25.0 224.0 14 Financing Round 3 10.0 234.0 15 Demo 1 RR 5.0 239.0 16 CUCU Flight Unit 9.0 248.0 17 Demo 1 Mission 5.0 253.0 18 Demo 2 RR 5.0 258.0 19 Demo 2 Mission 5.0 263.0 20 Cargo Int. Demo 5.0 268.0 21 Demo 3 RR 5.0 273.0 22 Demo 3 Mission 5.0 278.0 SpaceX COTS Milestones 08-27-12 Feb May Jul 23 Feb 8 Nov 29 Aug 22 Sep 15 Mar 1 Mar 15 Aug 4 Mar Jun 8 Feb 8 Dec 18 Jan Mar 21 Mar 21 Dec 19 Oct 29 Jun 27Apr Sep Mar JunSep Dec 15 Jun Nov JanDec 18 Dec Sep Jul Dec Sep Jun 7 Current Plan Actual Completion Date Initial SAA Plan Jan Mar 9 Jun 7 Aug 22
  • 7. 7 $M $M 2007 2008 2009 2010 2011 2012 Milestones Total Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 118.0 23 Modal Test Plan 5.0 5.0 24 Modal Test 5.0 10.0 25 LIDAR Test (open loop) 5.0 15.0 26 Solar Array Deploy Test 5.0 20.0 27 LIDAR Test Plan (closed loop) 5.0 25.0 28 Thermal Vacuum Test Plan 5.0 30.0 29 Infrastructure Plan 10.0 40.0 30 Thermal Vacuum Test 20.0 60.0 31 Test site Infrastructure Implementation 5.0 65.0 32 Dragon Trunk Acoustic Test 10.0 75.0 33 LIDAR Test 6 DOF (closed loop) 5.0 80.0 34 Design Rev. Enhanced Powered Cargo Accom. 5.0 85.0 35 Design Rev. Pressurized Cargo Vol Increase 5.0 90.0 36 Dragon EMI/EMC Test (HITL) 10.0 100.0 37 Dragon Cargo Racks & Hatch Simulator 3.0 103.0 38 Ground Demo Enhanced Powered Cargo 5.0 108.0 39 Launch site Infrastructure Implementation 5.0 113.0 40 Production Infrastructure Implementation 5.0 118.0 SAA Total 396.0 396.0 SpaceX Augmented COTS Milestones 10-27-11 Dec 16 Dec 16 Dec 16 Dec 16 Mar 31 Mar Mar Current Plan Actual Completion Date Initial SAA Plan Apr 6 May 10 Jul Jun 23 Jun 23 Jul Aug Sep 14 Oct 26 Aug 24 Aug 24 Aug 26 Sep 20 Sep Oct 26 Sep Oct 26 Sep Oct 26
  • 8. 8 Orbital COTS Summary • Space Act Agreement awarded February 2008 and amended in December 2010 with additional risk reduction milestones • All 29 milestones completed in November 2013 for payments totaling $288M – Maiden Test Flight: April 21, 2013 – ISS Demo Mission: Sep. 18-23, 2013 • Key Facts: – New Antares U.S. launch vehicle – New autonomous Cygnus cargo spacecraft capable of carrying cargo to the ISS and disposing cargo from the ISS – New commercial launch facility at Wallops Island, VA Antares MARS/Wallops Launch Site Cygnus Approaching ISS
  • 9. 9 Orbital COTS Demonstration Launches A-ONE Launch April 21, 2013 Orb-D1 Launch September 21, 2013
  • 10. 10 Orbital D-1 ISS Demonstration Mission D-1 Orb-1 D-1 Cygnus
  • 11. 11 $M $M 2008 2009 2010 2011 2012 2013 Milestones Total Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 170.0 1 Program Plan Review 10.0 10.0 2 Demo Mission SRR 20.0 30.0 3 UCM PDR 10.0 40.0 4 DELETED 5 COTS Int/Ops Facility 10.0 50.0 6 PCM PDR 10.0 60.0 7 DELETED 8 IP&CL Submission 10.0 70.0 9 ISS Phase 1 SRP 10.0 80.0 10 COTS System PDR 20.0 100.0 11 PCM CDR 10.0 110.0 12 Cygnus Avionics Test 10.0 120.0 13 ISS Phase 2 SRP 10.0 130.0 14 COTS System CDR 10.0 140.0 15 SM Core Assembly Complete 7.5 147.5 16 SM Test Readiness Review 7.5 155.0 17 SM Initial CPT 5.0 160.0 18 LV Stage I Assy. Complete 2.5 162.5 19 Cargo Int. Demo 2.5 165.0 20 Mission Readiness Review 2.5 167.5 21 System Demo Flight 2.5 170.0 Orbital COTS Milestones 08-05-13 Current Plan Actual Completion Date Initial SAA Plan Aug Nov 6 Apr May 22 Mar 27 Sep Aug 14 Jul 17 Feb 18 Oct 9 Sep 22 Jun Nov Oct Jul Mar 31 Aug 13 Jul 31 Jun Mar Mar 23Sep Aug 30 Nov 17 DecOct Sep Sep Dec Oct Dec 6 Oct Dec JunMay AprJan Nov 6 Jul 27 Dec 14 Jul 11
  • 12. 12 $M $M 2008 2009 2010 2011 2012 2013 Milestones Total Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 118.0 22 Test Flight Mission Review 20.0 20.0 23 Test Flight Mission Analys. 10.0 30.0 24 Cygnus Mass Sim. (CMS) Design Review 10.0 40.0 25 Install Add’l PITL Simulators 5.0 45.0 26 PROX FEU Test Unit 5.0 50.0 27 Maiden Flt Stg 1 Core Del. 24.0 74.0 28 Maiden Flt Uppr Stage Del. 20.0 94.0 29 Maiden Flt CMS Delivered 10.0 104.0 30 Maiden Flt Stage 1 Assy. 10.0 114.0 31 Maiden Test Flight 4.0 118.0 SAA Total 288.0 280.5 Orbital Augmented COTS Milestones 05-16-13 Current Plan Actual Completion Date Initial SAA Plan Dec 15 Feb 23 Mar 03 Apr May Apr 28 Jun 21 Jun 20 Jul Oct May 6 Jun 17 May 9 Sep 17
  • 13. 13 Key Lessons Learned from Program • Government seed money was highly leveraged – Commercial partners funded over 50% of COTS development costs • Fixed price milestone payments maximized incentive to control cost and minimize schedule delays • Minimum firm requirements along with commensurate Government oversight were key to fostering innovation and reducing life cycle development costs – Goals (vs. requirements) were established to open trade space and optimize design – Firm requirements were identified only where necessary to assure the safety of the ISS and crew – ISS interface requirements evolved over time and were coordinated in a collaborative manner with the commercial partners • A portfolio of multiple partners with different capabilities assured a balanced approach to technical and business risks – Increased the chances of at least one successful partner – Market forces kept development and operational costs in check • Commercial friendly intellectual property/data rights and limited termination liability encouraged investment of private capital
  • 14. 14 Lessons Learned from Program (Cont.) • NASA commitment to purchase operational services greatly improves the ability for companies to raise funds • NASA does not have the statutory authority to provide Government Furnished Equipment (GFE) under a SAA – Even though originally contemplated in the SAA and in the best interest of the Government, COTS had to revert to loan agreements and cumbersome GSA excess procedures to transfer equipment to facilitate berthing with the ISS • Augmentation of funding late in the program enabled additional risk reduction testing not initially affordable – Directly contributed to the successful first attempt berthing of SpaceX Dragon to ISS – Would be difficult to predict how much, if any, to hold in reserve during program formulation and initialization to protect for such milestone adjustments • COTS model for public-private partnerships worked!
  • 15. 15 Key Lessons Learned from SpaceX • Design, Test and Repeat (engineering units prior to qualification) – This philosophy can be better than just detailed analysis and only one test –learn much more – Need to have a team that can react and make changes quickly • Use of COTS electronics parts is feasible (instead of all S-level parts) thru use of some radiation screening/tests and better architecture decisions (redundancy and reboot capability) – Saves significant cost and schedule over traditional avionics – Previous Cost "GE Price" modeling experience was ”No matter how many runs done with varying complexity, similarity vs new design, etc– the cost and schedule of the Avionics and software drove the project cost.” Much more expensive than even massive structure or thermal systems.  Note: if total length of a project can be reduced 6-12 months by using readily available parts and processes, you really save the monthly burn rate of the whole project for that many months. – Just gets projects done faster, so NASA could be more responsive and can do more things • Design with cost in mind – SpaceX paid much more attention to the cost of parts and component in the initial design phases than NASA contractors traditionally do; to the point of building many things in house, because it was perceived to be too expensive to buy vendor part. They always questioned why it can’t be done less expensively and pushed back on costly requirements. – In-house production has the added benefit of allowing better schedule control than from sub-tier suppliers and allows a streamlined change/update process.
  • 16. 16 Key Lessons Learned from SpaceX (Cont.) • NASA observed SpaceX’s use of “WIKI tools” for multiple critical business and engineering processes saves time—trying to move to a paperless environment. – Microsoft SharePoint and Confluence primarily for team processes and general info that they want teams to have instead of some team meetings – Provided models instead of large documents in some cases (FEM models and summary vs structural analysis report) – TRAC tickets are being used for issues, changes and risks by many teams.  Provides a "virtual" meeting to ask questions and throw out ideas. Tracks all the comments for others to look at. Eventually, bringing them to closure and having all the managers and responsible engineers sign off on it.  Saves time (schedule) by letting people look at ticket when they can fit it in their schedule and not have to wait for a meeting to be called when everyone can attend.  a Virtual board/review if you will. – NASA use suggested for simple issues, changes and risk (identify them as such), but move quickly to a meeting if not coming to timely closure or unclear questions arise.
  • 17. 17 Key Lessons Learned from Orbital • Design Review Process – Independent Review Teams – Use of independent review team (IRT) of “experienced” experts to serve as design review team can be very effective – IRT typically not bound by cost or schedule and can serve as a common sense sounding board for design and programmatic decisions – Membership of team should remain consistent throughout program (to the extent practical) – Review team findings should go to level of management above program manager for disposition/review • Use of “standard building block” designs – NASA standard practices typically utilize custom or first use designs, whereas commercial leverages existing “product line” designs – Lowers technical risk due to vast experience with designs/components – Could also potentially lower cost & schedule due to potentially eliminating the need for additional qualification testing (where applicable) – Does not come without risk however… • Leveraging common goals with all constituents (i.e. States, local governments, DOD,…) – NASA frequently “goes it alone” on programs and supplies all funding – Commercial industry realizes the benefits of competition and synergistic desires  Example – State of Virginia had interests in developing spaceport (i.e. MARS) and supplied significant funding  Example – Industry partners, in some cases, provided funding for unique hardware in exchange for IP rights
  • 18. 18 Key Lessons Learned from Orbital • NASA can embrace cultural shift of working with “Commercial” partners, but it is a continuing challenge – NASA has immense technical capability – NASA needs to understand partner challenges, both technical and programmatic – NASA needs to avoid “grading” systems designs and offer solutions that consider partner challenges – If we show value, industry will “open up” • Communication & trust is essential – Partners, not customers or “suppliers” – Regular tag-ups – Talk often and early… – Relationship should be built to last and therefore needs to be protected and nurtured • Breaking interfaces/systems which were not designed for multi-party use is difficult and needs careful thought & consideration
  • 19. 19