SlideShare a Scribd company logo
1 of 2
Red Line Consulting
Concurrence driven Project Management
Ever wonder why those nice MS Project
digital Gantt charts don’t result in
projects that are on time and on budget?
The simple reason is the schedule
becomes disconnected from the team
members performing the tasks. The
answer is Concurrence driven project
management.
There are two basic types of scheduling.
Most people are very familiar with the MS
Project version of the Gantt chart (or time
line) that is created by a scheduler with
input from key leaders. This tool is very
useful for assessing when a project is no
longer on schedule. There is another
approach based on concurrence of all
parties.
One of the common reasons schedule
driven planning fails is the key
information holders are not leaders but
SMEs who are “overly technical” and
“difficult to engage” are not brought into
the planning. A key to successful projects
is being able to extract that critical “truth”
about the project path without having a 2-
hour discussion on the temporal effect of
obtuse widgets on acute widgets.
What is concurrence based PM?
Concurrence is focused on the agreement
of key stakeholders at all levels including
SME’s and their supporting team
members. There are two basic types 1)
risk mitigation (Office Andon) and 2)
schedule development.
The Office Andon system is a
democratizing and anonymous risk
mitigation system. Any person can flag a
task as yellow or red with or without
commenting. The managers then
investigate to resolve the concern to
ensure tasks are completed. Risks can
come from many areas including OTD,
FTY, budget, NPS, quality, and the
customer relationship. Complex
organizations and informal hierarchy
often work against information flow;
anonymity is a strategic tool in
information gathering.
Schedule development is based on
stakeholders agreeing to deliverables and
dates. Concurrence requires verified
interaction. One system gave each
stakeholder a password-encoded field to
accept, decline, or propose alternative
dates. A date was not verified until all
stakeholders had signed off. The issue of
dates being moved by the scheduler
without stakeholder concurrence was
addressed by turning all stakeholder
agreements to pending if the agreed date
changed. Concurrence based scheduling
was responsible for bringing the ITEP
engine test program back into compliance
with an agreed schedule within 5 days.
2015
Dr. T Scott
ConcurrencePM
Early risk identification
Forward Looking
Realistic completion
Collaborative
Accept, Reject, propose
dates
Non-RecurringCosts
Indicate failureto mutually
agree ondeliverables
RED LINE CONSULTING
3625 Michigan Ave
Cincinnati, OH 45208
PHONE
720-663-7303
WEB
www.redline.consulting
www.officeandon.com
Addresses need for
adequate controls
Why is it different?
Concurrence changes the discussion from backward
looking (why did this happen) to forward looking
(stopping the problem before it happens). The Gantt
system focus on when tasks should be completed and
flags when a date is missed while the concurrence system
works to uncover when tasks will realistically be
completed enabling leadership to make the adjustments
necessary to maintain the schedule before key dates are
missed. Furthermore, the people doing the work are now
personally invested in the deliverable dates (they
personally signed for them). Creating ownership helps to
develop a culture of responsibility and accountability.
What problem does it solve?
Well thought out schedules often become disconnected
from programs and projects as work progresses. Some
reasons for this include schedulers focusing on
management meetings; SME’s being too detailed in
discussions; and management fearing customers finding
out work is not progressing according to the original plan.
Often there are more incentives to show a disconnected
schedule than address issues and risks to the schedule.
Concurrence based scheduling forces stakeholders to buy-
in and creates visibility of schedule clashes and resource
limitations at the task level. It also contains the tools to
re-align tasks to ensure the critical path can be met.
Why should I use it?
The best reason to try something different is if what you
are doing now is not working very well. In aerospace non-
recurring cost is out of control and schedules are slipping
years. Some examples are BR725, 787, C-series, MRJ, and
LEAP. Here are some numbers the Spirit Aerosystems
PROSPECTUSSUPPLEMENT (To prospectus dated April 7,
2011) page S-6:
Included in 2011 cost of sales are forward-loss charges of
$81.8 million on the G280 wing program, net $29.0 million
on the Sikorsky CH-53K program, $18.3 million on the
B747-8 program and $3.0 million on the A350 XWB non-
recurring wing program. […] Also included in 2010 cost of
sales is a $2.8 million forward-loss on the G280 wing
program. Included in the 2009 cost of sales are forward-
loss charges of $93.0 million on the G280 wing program
and $10.9 million on the Cessna Citation Columbus
program. 1
Subsequently, investors sued Spirit:
[Spirit] Lacked adequate internal and financial controls,
especially relating to cost overruns for the Company’s 787
program, G650 Wing program, BR725 program, the G280
Wing program, and other programs. 2
Something is obviously missing from the meticulously
constructed schedules for these programs. In the case of
BR725, the Marlin Breer, the Spirit Technical Fellow for
icing, told the leadership the project would take 3 people
3 years but the budget and plan compressed the schedule;
reality caught up to the program in this and many other
areas.
Marlin’s case provides insight into the underlying issue,
the schedulers become disconnected from the teams
executing the work because they are taking to middle and
senior managers who are focused on the schedule. A
concurrence-based model continually aligns the project
timeline to the team capabilities. A digital system of
concurrence enables acceptance of dates or proposal of
alternative dates.
References:
1)http://www.sec.gov/Archives/edgar/data/1364885/0
00104746914001906/a2218754z424b7.htm
2)http://www.faruqilaw.com/cases/show/id/1081
WEB
www.redline.consulting
www.officeandon.com
PHONE
720-663-7303
RED LINE CONSULTING
3625 Michigan Ave
Cincinnati, OH 45208
Airplane development without cost overruns

More Related Content

What's hot

Managing Interdependencies in Complex Organizations
Managing Interdependencies in Complex OrganizationsManaging Interdependencies in Complex Organizations
Managing Interdependencies in Complex OrganizationsNicolay Worren
 
Project Success/Failure
Project Success/FailureProject Success/Failure
Project Success/FailurePeter Salmon
 
Project Governance and Failure
Project Governance and FailureProject Governance and Failure
Project Governance and FailureMichael Krigsman
 
Top Ten Reasons Why Projects Fail
Top Ten Reasons Why Projects FailTop Ten Reasons Why Projects Fail
Top Ten Reasons Why Projects Failjpstewar
 
Pan europa foods - Project Management
Pan europa foods - Project ManagementPan europa foods - Project Management
Pan europa foods - Project ManagementRobbi Palacios
 
Project Management case analysis
Project Management case analysisProject Management case analysis
Project Management case analysisWakas Khalid
 
Research Report: Strategies for Project Recovery
Research Report: Strategies for Project RecoveryResearch Report: Strategies for Project Recovery
Research Report: Strategies for Project RecoveryPM Solutions
 
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceWhy Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceAcumen
 
APM Presents - Why project governance and its key principles and challenges
APM Presents - Why project governance and its key principles and challengesAPM Presents - Why project governance and its key principles and challenges
APM Presents - Why project governance and its key principles and challengesAssociation for Project Management
 
How to implement team communication strategies remotely
How to implement team communication strategies remotelyHow to implement team communication strategies remotely
How to implement team communication strategies remotelyOrangescrum
 
Identifying and Recovering Troubled Projects
Identifying and Recovering Troubled ProjectsIdentifying and Recovering Troubled Projects
Identifying and Recovering Troubled ProjectsRicardo Viana Vargas
 
Lead A Project To Success
Lead A Project To SuccessLead A Project To Success
Lead A Project To SuccessChelse Benham
 
SymEx 2015 - Troubled Project Recovery, The Story of Firefighter & Hero
SymEx 2015 - Troubled Project Recovery, The Story of Firefighter & HeroSymEx 2015 - Troubled Project Recovery, The Story of Firefighter & Hero
SymEx 2015 - Troubled Project Recovery, The Story of Firefighter & HeroPMI Indonesia Chapter
 
Why projects fail avoiding the classic pitfalls
Why projects fail avoiding the classic pitfallsWhy projects fail avoiding the classic pitfalls
Why projects fail avoiding the classic pitfallsTa Ngoc
 
The editors bookshelf
The editors bookshelfThe editors bookshelf
The editors bookshelfGlen Alleman
 
12.0 risk management agile+evm (v10.2)
12.0 risk management agile+evm (v10.2)12.0 risk management agile+evm (v10.2)
12.0 risk management agile+evm (v10.2)Glen Alleman
 
Projects Management in Reality: Lessons from Government Projects
Projects Management in Reality: Lessons from Government ProjectsProjects Management in Reality: Lessons from Government Projects
Projects Management in Reality: Lessons from Government ProjectsArab Federation for Digital Economy
 
10 Project Management Mistakes
10 Project Management Mistakes10 Project Management Mistakes
10 Project Management MistakesOrangescrum
 
Project Execution in Changing Times - Focus on the Essentials
Project Execution in Changing Times - Focus on the EssentialsProject Execution in Changing Times - Focus on the Essentials
Project Execution in Changing Times - Focus on the EssentialsEndeavor Management
 

What's hot (19)

Managing Interdependencies in Complex Organizations
Managing Interdependencies in Complex OrganizationsManaging Interdependencies in Complex Organizations
Managing Interdependencies in Complex Organizations
 
Project Success/Failure
Project Success/FailureProject Success/Failure
Project Success/Failure
 
Project Governance and Failure
Project Governance and FailureProject Governance and Failure
Project Governance and Failure
 
Top Ten Reasons Why Projects Fail
Top Ten Reasons Why Projects FailTop Ten Reasons Why Projects Fail
Top Ten Reasons Why Projects Fail
 
Pan europa foods - Project Management
Pan europa foods - Project ManagementPan europa foods - Project Management
Pan europa foods - Project Management
 
Project Management case analysis
Project Management case analysisProject Management case analysis
Project Management case analysis
 
Research Report: Strategies for Project Recovery
Research Report: Strategies for Project RecoveryResearch Report: Strategies for Project Recovery
Research Report: Strategies for Project Recovery
 
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceWhy Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
 
APM Presents - Why project governance and its key principles and challenges
APM Presents - Why project governance and its key principles and challengesAPM Presents - Why project governance and its key principles and challenges
APM Presents - Why project governance and its key principles and challenges
 
How to implement team communication strategies remotely
How to implement team communication strategies remotelyHow to implement team communication strategies remotely
How to implement team communication strategies remotely
 
Identifying and Recovering Troubled Projects
Identifying and Recovering Troubled ProjectsIdentifying and Recovering Troubled Projects
Identifying and Recovering Troubled Projects
 
Lead A Project To Success
Lead A Project To SuccessLead A Project To Success
Lead A Project To Success
 
SymEx 2015 - Troubled Project Recovery, The Story of Firefighter & Hero
SymEx 2015 - Troubled Project Recovery, The Story of Firefighter & HeroSymEx 2015 - Troubled Project Recovery, The Story of Firefighter & Hero
SymEx 2015 - Troubled Project Recovery, The Story of Firefighter & Hero
 
Why projects fail avoiding the classic pitfalls
Why projects fail avoiding the classic pitfallsWhy projects fail avoiding the classic pitfalls
Why projects fail avoiding the classic pitfalls
 
The editors bookshelf
The editors bookshelfThe editors bookshelf
The editors bookshelf
 
12.0 risk management agile+evm (v10.2)
12.0 risk management agile+evm (v10.2)12.0 risk management agile+evm (v10.2)
12.0 risk management agile+evm (v10.2)
 
Projects Management in Reality: Lessons from Government Projects
Projects Management in Reality: Lessons from Government ProjectsProjects Management in Reality: Lessons from Government Projects
Projects Management in Reality: Lessons from Government Projects
 
10 Project Management Mistakes
10 Project Management Mistakes10 Project Management Mistakes
10 Project Management Mistakes
 
Project Execution in Changing Times - Focus on the Essentials
Project Execution in Changing Times - Focus on the EssentialsProject Execution in Changing Times - Focus on the Essentials
Project Execution in Changing Times - Focus on the Essentials
 

Viewers also liked

Gas turbine power plants
Gas turbine power plantsGas turbine power plants
Gas turbine power plantsNishkam Dhiman
 
Energy Summit San Carlos Apache Nation December 12 13
Energy Summit   San Carlos Apache Nation December 12 13Energy Summit   San Carlos Apache Nation December 12 13
Energy Summit San Carlos Apache Nation December 12 13droby
 
Compressor Station Heat Recovery & Zsi Technology
Compressor Station Heat Recovery & Zsi TechnologyCompressor Station Heat Recovery & Zsi Technology
Compressor Station Heat Recovery & Zsi Technologydcousino
 
Zero Stage Introduction
Zero Stage IntroductionZero Stage Introduction
Zero Stage Introductiondcousino
 
Materials used in gas turbine
Materials used in gas turbine Materials used in gas turbine
Materials used in gas turbine shekuit
 
Fadec full authority digital engine control-final
Fadec  full authority digital engine control-finalFadec  full authority digital engine control-final
Fadec full authority digital engine control-finalAbhishek Alankar
 
Gaz türbinli motorların tarihçesi ve sınıflandırılması
Gaz türbinli motorların tarihçesi ve sınıflandırılmasıGaz türbinli motorların tarihçesi ve sınıflandırılması
Gaz türbinli motorların tarihçesi ve sınıflandırılmasıMete Cantekin
 
Innovative IC Engine Concept
Innovative IC Engine ConceptInnovative IC Engine Concept
Innovative IC Engine ConceptJayesh Mehta
 
Linked Learning: An Engaging Approach for All
Linked Learning: An Engaging Approach for AllLinked Learning: An Engaging Approach for All
Linked Learning: An Engaging Approach for AllDr. Marguerite Williams
 
Chapter 71 gas turbine
Chapter 71  gas turbineChapter 71  gas turbine
Chapter 71 gas turbinedigisof
 
variable geometry turbocharger
variable geometry turbochargervariable geometry turbocharger
variable geometry turbochargerRishabh Mishra
 
Operation and Modeling of Turbogenerators - Hsing-pang Liu - June 2010
Operation and Modeling of Turbogenerators - Hsing-pang Liu - June 2010Operation and Modeling of Turbogenerators - Hsing-pang Liu - June 2010
Operation and Modeling of Turbogenerators - Hsing-pang Liu - June 2010cahouser
 
Gas Turbine and Jet propulsion
Gas Turbine and Jet propulsionGas Turbine and Jet propulsion
Gas Turbine and Jet propulsionSLA1987
 
Fadec- full authority digital engine control-latest
Fadec- full authority digital engine control-latestFadec- full authority digital engine control-latest
Fadec- full authority digital engine control-latestAbhishek Alankar
 
Presentation:COMBUSTION CHAMBER
Presentation:COMBUSTION CHAMBERPresentation:COMBUSTION CHAMBER
Presentation:COMBUSTION CHAMBERabsalar
 

Viewers also liked (20)

Gas turbine power plants
Gas turbine power plantsGas turbine power plants
Gas turbine power plants
 
Energy Summit San Carlos Apache Nation December 12 13
Energy Summit   San Carlos Apache Nation December 12 13Energy Summit   San Carlos Apache Nation December 12 13
Energy Summit San Carlos Apache Nation December 12 13
 
Compressor Station Heat Recovery & Zsi Technology
Compressor Station Heat Recovery & Zsi TechnologyCompressor Station Heat Recovery & Zsi Technology
Compressor Station Heat Recovery & Zsi Technology
 
Zero Stage Introduction
Zero Stage IntroductionZero Stage Introduction
Zero Stage Introduction
 
Turbine section module 15.6
Turbine section module 15.6Turbine section module 15.6
Turbine section module 15.6
 
Warranty
WarrantyWarranty
Warranty
 
Materials used in gas turbine
Materials used in gas turbine Materials used in gas turbine
Materials used in gas turbine
 
Gas turbine
Gas turbineGas turbine
Gas turbine
 
Fadec full authority digital engine control-final
Fadec  full authority digital engine control-finalFadec  full authority digital engine control-final
Fadec full authority digital engine control-final
 
Gaz türbinli motorların tarihçesi ve sınıflandırılması
Gaz türbinli motorların tarihçesi ve sınıflandırılmasıGaz türbinli motorların tarihçesi ve sınıflandırılması
Gaz türbinli motorların tarihçesi ve sınıflandırılması
 
Water Swirled Into Gas Turbine Technology - Combined Cycle + 14% over curren...
Water Swirled Into Gas Turbine Technology -  Combined Cycle + 14% over curren...Water Swirled Into Gas Turbine Technology -  Combined Cycle + 14% over curren...
Water Swirled Into Gas Turbine Technology - Combined Cycle + 14% over curren...
 
Innovative IC Engine Concept
Innovative IC Engine ConceptInnovative IC Engine Concept
Innovative IC Engine Concept
 
Linked Learning: An Engaging Approach for All
Linked Learning: An Engaging Approach for AllLinked Learning: An Engaging Approach for All
Linked Learning: An Engaging Approach for All
 
Chapter 71 gas turbine
Chapter 71  gas turbineChapter 71  gas turbine
Chapter 71 gas turbine
 
variable geometry turbocharger
variable geometry turbochargervariable geometry turbocharger
variable geometry turbocharger
 
Operation and Modeling of Turbogenerators - Hsing-pang Liu - June 2010
Operation and Modeling of Turbogenerators - Hsing-pang Liu - June 2010Operation and Modeling of Turbogenerators - Hsing-pang Liu - June 2010
Operation and Modeling of Turbogenerators - Hsing-pang Liu - June 2010
 
Gas Turbine and Jet propulsion
Gas Turbine and Jet propulsionGas Turbine and Jet propulsion
Gas Turbine and Jet propulsion
 
Fadec- full authority digital engine control-latest
Fadec- full authority digital engine control-latestFadec- full authority digital engine control-latest
Fadec- full authority digital engine control-latest
 
Turbo chargers
Turbo chargersTurbo chargers
Turbo chargers
 
Presentation:COMBUSTION CHAMBER
Presentation:COMBUSTION CHAMBERPresentation:COMBUSTION CHAMBER
Presentation:COMBUSTION CHAMBER
 

Similar to Concurrence.PM.v2

How To Develop A Project Management Plan
How To Develop A Project Management PlanHow To Develop A Project Management Plan
How To Develop A Project Management PlanOrangescrum
 
Analysing attrition in outsourced
Analysing attrition in outsourcedAnalysing attrition in outsourced
Analysing attrition in outsourcedcsandit
 
Analysing Attrition in Outsourced Software Project
Analysing Attrition in Outsourced Software ProjectAnalysing Attrition in Outsourced Software Project
Analysing Attrition in Outsourced Software Projectcsandit
 
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IRJET Journal
 
Common causes of cost overruns in construction projects
Common causes of cost overruns in construction projectsCommon causes of cost overruns in construction projects
Common causes of cost overruns in construction projectsSANJEEV Wazir
 
Maximizing Project Value with Construction Management Platforms..pdf
Maximizing Project Value with Construction Management Platforms..pdfMaximizing Project Value with Construction Management Platforms..pdf
Maximizing Project Value with Construction Management Platforms..pdfiFieldsmart Technologies
 
Building Better_Maximizing Efficiency with Construction Management Software S...
Building Better_Maximizing Efficiency with Construction Management Software S...Building Better_Maximizing Efficiency with Construction Management Software S...
Building Better_Maximizing Efficiency with Construction Management Software S...iFieldsmart Technologies
 
Estimate budget and project crashing.pptx
Estimate budget and project crashing.pptxEstimate budget and project crashing.pptx
Estimate budget and project crashing.pptxMIANMNADEEM
 
Mortgage LOS Implementation: A Roadmap for Sustainability
Mortgage LOS Implementation: A Roadmap for SustainabilityMortgage LOS Implementation: A Roadmap for Sustainability
Mortgage LOS Implementation: A Roadmap for SustainabilityCognizant
 
Is It Time For A Mid-Project Checkup?
Is It Time For A Mid-Project Checkup?Is It Time For A Mid-Project Checkup?
Is It Time For A Mid-Project Checkup?David Coleman
 
Top 7 reasons why preemptive construction management is crucial for construct...
Top 7 reasons why preemptive construction management is crucial for construct...Top 7 reasons why preemptive construction management is crucial for construct...
Top 7 reasons why preemptive construction management is crucial for construct...iFieldsmart Technologies
 
Capital_projects_life_cycle_managemant_Oil_and_Gas
Capital_projects_life_cycle_managemant_Oil_and_GasCapital_projects_life_cycle_managemant_Oil_and_Gas
Capital_projects_life_cycle_managemant_Oil_and_GasMircea Tomescu
 
5 project management project planning
5 project management  project planning5 project management  project planning
5 project management project planningYasirHamour
 
Major Project Management Challenges and The Way Forward.pptx
Major Project Management Challenges and The Way Forward.pptxMajor Project Management Challenges and The Way Forward.pptx
Major Project Management Challenges and The Way Forward.pptxMd. Masudur Rahman, PMP
 
Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15
Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15
Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15Project Control | PROJ CTRL
 
Top 7 reasons why preemptive construction management is crucial for construct...
Top 7 reasons why preemptive construction management is crucial for construct...Top 7 reasons why preemptive construction management is crucial for construct...
Top 7 reasons why preemptive construction management is crucial for construct...iFieldsmart Technologies
 
Project management practices the criteria for success or failure
Project management practices the criteria for success or failureProject management practices the criteria for success or failure
Project management practices the criteria for success or failureTa Ngoc
 

Similar to Concurrence.PM.v2 (20)

How To Develop A Project Management Plan
How To Develop A Project Management PlanHow To Develop A Project Management Plan
How To Develop A Project Management Plan
 
Analysing attrition in outsourced
Analysing attrition in outsourcedAnalysing attrition in outsourced
Analysing attrition in outsourced
 
Analysing Attrition in Outsourced Software Project
Analysing Attrition in Outsourced Software ProjectAnalysing Attrition in Outsourced Software Project
Analysing Attrition in Outsourced Software Project
 
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
 
Common causes of cost overruns in construction projects
Common causes of cost overruns in construction projectsCommon causes of cost overruns in construction projects
Common causes of cost overruns in construction projects
 
Maximizing Project Value with Construction Management Platforms..pdf
Maximizing Project Value with Construction Management Platforms..pdfMaximizing Project Value with Construction Management Platforms..pdf
Maximizing Project Value with Construction Management Platforms..pdf
 
Building Better_Maximizing Efficiency with Construction Management Software S...
Building Better_Maximizing Efficiency with Construction Management Software S...Building Better_Maximizing Efficiency with Construction Management Software S...
Building Better_Maximizing Efficiency with Construction Management Software S...
 
Project Planning
Project Planning Project Planning
Project Planning
 
Estimate budget and project crashing.pptx
Estimate budget and project crashing.pptxEstimate budget and project crashing.pptx
Estimate budget and project crashing.pptx
 
Essay On Planning
Essay On PlanningEssay On Planning
Essay On Planning
 
Mortgage LOS Implementation: A Roadmap for Sustainability
Mortgage LOS Implementation: A Roadmap for SustainabilityMortgage LOS Implementation: A Roadmap for Sustainability
Mortgage LOS Implementation: A Roadmap for Sustainability
 
How to Steer Clear Of Budget Overruns in Software.pdf
How to Steer Clear Of Budget Overruns in Software.pdfHow to Steer Clear Of Budget Overruns in Software.pdf
How to Steer Clear Of Budget Overruns in Software.pdf
 
Is It Time For A Mid-Project Checkup?
Is It Time For A Mid-Project Checkup?Is It Time For A Mid-Project Checkup?
Is It Time For A Mid-Project Checkup?
 
Top 7 reasons why preemptive construction management is crucial for construct...
Top 7 reasons why preemptive construction management is crucial for construct...Top 7 reasons why preemptive construction management is crucial for construct...
Top 7 reasons why preemptive construction management is crucial for construct...
 
Capital_projects_life_cycle_managemant_Oil_and_Gas
Capital_projects_life_cycle_managemant_Oil_and_GasCapital_projects_life_cycle_managemant_Oil_and_Gas
Capital_projects_life_cycle_managemant_Oil_and_Gas
 
5 project management project planning
5 project management  project planning5 project management  project planning
5 project management project planning
 
Major Project Management Challenges and The Way Forward.pptx
Major Project Management Challenges and The Way Forward.pptxMajor Project Management Challenges and The Way Forward.pptx
Major Project Management Challenges and The Way Forward.pptx
 
Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15
Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15
Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15
 
Top 7 reasons why preemptive construction management is crucial for construct...
Top 7 reasons why preemptive construction management is crucial for construct...Top 7 reasons why preemptive construction management is crucial for construct...
Top 7 reasons why preemptive construction management is crucial for construct...
 
Project management practices the criteria for success or failure
Project management practices the criteria for success or failureProject management practices the criteria for success or failure
Project management practices the criteria for success or failure
 

Concurrence.PM.v2

  • 1. Red Line Consulting Concurrence driven Project Management Ever wonder why those nice MS Project digital Gantt charts don’t result in projects that are on time and on budget? The simple reason is the schedule becomes disconnected from the team members performing the tasks. The answer is Concurrence driven project management. There are two basic types of scheduling. Most people are very familiar with the MS Project version of the Gantt chart (or time line) that is created by a scheduler with input from key leaders. This tool is very useful for assessing when a project is no longer on schedule. There is another approach based on concurrence of all parties. One of the common reasons schedule driven planning fails is the key information holders are not leaders but SMEs who are “overly technical” and “difficult to engage” are not brought into the planning. A key to successful projects is being able to extract that critical “truth” about the project path without having a 2- hour discussion on the temporal effect of obtuse widgets on acute widgets. What is concurrence based PM? Concurrence is focused on the agreement of key stakeholders at all levels including SME’s and their supporting team members. There are two basic types 1) risk mitigation (Office Andon) and 2) schedule development. The Office Andon system is a democratizing and anonymous risk mitigation system. Any person can flag a task as yellow or red with or without commenting. The managers then investigate to resolve the concern to ensure tasks are completed. Risks can come from many areas including OTD, FTY, budget, NPS, quality, and the customer relationship. Complex organizations and informal hierarchy often work against information flow; anonymity is a strategic tool in information gathering. Schedule development is based on stakeholders agreeing to deliverables and dates. Concurrence requires verified interaction. One system gave each stakeholder a password-encoded field to accept, decline, or propose alternative dates. A date was not verified until all stakeholders had signed off. The issue of dates being moved by the scheduler without stakeholder concurrence was addressed by turning all stakeholder agreements to pending if the agreed date changed. Concurrence based scheduling was responsible for bringing the ITEP engine test program back into compliance with an agreed schedule within 5 days. 2015 Dr. T Scott ConcurrencePM Early risk identification Forward Looking Realistic completion Collaborative Accept, Reject, propose dates Non-RecurringCosts Indicate failureto mutually agree ondeliverables RED LINE CONSULTING 3625 Michigan Ave Cincinnati, OH 45208 PHONE 720-663-7303 WEB www.redline.consulting www.officeandon.com Addresses need for adequate controls
  • 2. Why is it different? Concurrence changes the discussion from backward looking (why did this happen) to forward looking (stopping the problem before it happens). The Gantt system focus on when tasks should be completed and flags when a date is missed while the concurrence system works to uncover when tasks will realistically be completed enabling leadership to make the adjustments necessary to maintain the schedule before key dates are missed. Furthermore, the people doing the work are now personally invested in the deliverable dates (they personally signed for them). Creating ownership helps to develop a culture of responsibility and accountability. What problem does it solve? Well thought out schedules often become disconnected from programs and projects as work progresses. Some reasons for this include schedulers focusing on management meetings; SME’s being too detailed in discussions; and management fearing customers finding out work is not progressing according to the original plan. Often there are more incentives to show a disconnected schedule than address issues and risks to the schedule. Concurrence based scheduling forces stakeholders to buy- in and creates visibility of schedule clashes and resource limitations at the task level. It also contains the tools to re-align tasks to ensure the critical path can be met. Why should I use it? The best reason to try something different is if what you are doing now is not working very well. In aerospace non- recurring cost is out of control and schedules are slipping years. Some examples are BR725, 787, C-series, MRJ, and LEAP. Here are some numbers the Spirit Aerosystems PROSPECTUSSUPPLEMENT (To prospectus dated April 7, 2011) page S-6: Included in 2011 cost of sales are forward-loss charges of $81.8 million on the G280 wing program, net $29.0 million on the Sikorsky CH-53K program, $18.3 million on the B747-8 program and $3.0 million on the A350 XWB non- recurring wing program. […] Also included in 2010 cost of sales is a $2.8 million forward-loss on the G280 wing program. Included in the 2009 cost of sales are forward- loss charges of $93.0 million on the G280 wing program and $10.9 million on the Cessna Citation Columbus program. 1 Subsequently, investors sued Spirit: [Spirit] Lacked adequate internal and financial controls, especially relating to cost overruns for the Company’s 787 program, G650 Wing program, BR725 program, the G280 Wing program, and other programs. 2 Something is obviously missing from the meticulously constructed schedules for these programs. In the case of BR725, the Marlin Breer, the Spirit Technical Fellow for icing, told the leadership the project would take 3 people 3 years but the budget and plan compressed the schedule; reality caught up to the program in this and many other areas. Marlin’s case provides insight into the underlying issue, the schedulers become disconnected from the teams executing the work because they are taking to middle and senior managers who are focused on the schedule. A concurrence-based model continually aligns the project timeline to the team capabilities. A digital system of concurrence enables acceptance of dates or proposal of alternative dates. References: 1)http://www.sec.gov/Archives/edgar/data/1364885/0 00104746914001906/a2218754z424b7.htm 2)http://www.faruqilaw.com/cases/show/id/1081 WEB www.redline.consulting www.officeandon.com PHONE 720-663-7303 RED LINE CONSULTING 3625 Michigan Ave Cincinnati, OH 45208 Airplane development without cost overruns