SlideShare uma empresa Scribd logo
1 de 5
Baixar para ler offline
2. WORKING EXPERIENCE (KISWIRE CORD SDN. BHD)
2.1. MANPOWER MANAGEMENT - ELECTRICAL DEPARTMENT ORGANIZATION CHART
2.2. BREAKDOWN AND PREVENTIVE MAINTENANCE ACTIVITIES
2.2.1 DISTRIBUTE AND ALLOCATE MANPOWER DAILY BY PROCESS
2.2.2 PROVIDE TECHNICAL TRAINING AND SUPPORT
2.2.3 TO LEAD MAINTENANCE TEAM IN-CASE MAJOR BREAKDOWN
2.2.4 TO PLAN SCHEDULE AND LAYOUT FOR DAILY / WEEKLY PREVENTIVE MAINTANANCE ACTIVTIES
2.2.5 TO COORDINATE WITH CONTRACTOR FOR EXTERNAL SUPPORT
2.2.6 TO PREPARE WEEKLY MAINTENANCE BREAKDOWN REPORT
2.3. SPARE PART AND INVENTORY MANAGEMENT
2.3.1 TO SETUP SPARE PART AND INVENTORY MANAGEMENT SYSTEM BASE ON KISWIRE PRODUCTION SYSTEM
2.3.2 TO PURCHASE AND COORDINATE SPARE PART ARRIVAL (DEPENDS ON URGENCIES)
2.4 NEW MACHINE AND FACILITIES INSTALLATION
2.4.1. DOCUMENT PREPARATION (SCHEDULE, ELECTRICAL LAYOUT DESIGN AND REQUIREMENT, etc)
2.4.2. MATERIAL CALCULATION AND PREPARATION (SUB MAIN CABLING, SEC. CABLING, CONTROL,etc)
2.4.3. COORDINATE CONTRACTOR THROUGHOUT INSTALLATION PROCESS
2.4.4. COMMISSIONING AND TESTING
2.4.5. PROJECT COSTING CALCULATION
1. Total Installation : 11 lines
REMARKS
(PICKLING /
IN-LINE
PATENTING /
PLATING)
PROCESS ATTACHMENT
BeadwirePatenting Line
SC & BW Plating Line SC & BW PicklingLine
SAIFUL
TEAM HEAD
Sn. ENGINEER ENGINEER ENGINEER
FOREMAN
LEADERS
Sn TECH
Jnr TECH
GENERAL
TOTAL
MANPOWER:
20
ENGINEER ENGINEER
THAUFAN
SR. ENGINEER
a) Furnace SC/BW Line
b) Diffusion SC
c) PB Bath
d)P/Off - T/up machine
e) PP Bath -
Bondrite,Borax,CU,Zn
(SCHEDULE,MACHINE LAY-OUT,AIR & WATER PIPING, etc)
(PIPE AND MACHINE PART)
MECHANICAL DEPARTMENT ORGANIZATION CHART
1. Total Installation : 42 units
2. Overall Machine : 64 units
1. Total Installation : >1000 units
1. Total Installation : > 500 units
1. Total Installation : 6 system
1. Total Installation : 2 system
1. Total Installation : 10 system
COMPRESSOR
COOLING SYSTEM
REMARKS
WET DRAWING MC
SC MC
THERMOPACK
TREATMENT PLANT
WASTE WATER
ATTACHMENT
DRY DRAWING MC
PROCESS
-SETTING AND COMMISIONING
2. START-UP DELAY SOP
2.6. FACTORY EXPANSION PROJECT
1. EXPANSION YEAR 2008
1. EXPANSION YEAR 2008
1. EXPANSION YEAR 2008
1. EXPANSION YEAR 2009
1. EXPANSION YEAR 2010
2. NEW APPLICATION 33KV
DESCRIPTION ATTACHMENT REMARKS
KSSB
STEELCORD TBR D
STEELCORD INLINE E
SSW BLK F
MD CONTROL
FACTORY ATTACHMENT REMARKS
BEADWIRE
KCSB Load (A) vs time (hour)
KCSB Load Start-up
2500
3000
A(Amp)
t(hour)
1500 pm
2800
2600
OVERHAUL
MACHINE
TWISTER (405UNIT)
FINE DRAWING MACHINE
(411UNIT)
5
1. EXPANSION YEAR 2012
1. EXPANSION YEAR 2014
1. EXPANSION YEAR 2015
3. TRAINING
3.1. ON JOB TRAINING - KISWIRE GUNCHEON, KOREA
3.2. FUJI INVERTER TRAINING
3.3. TOYOTA PRODUCTION SYSTEM TRANING, JAPAN
3.4 ISO/TS 16949 PROCESS BASE INTERNAL AUDITING
3.5 INTERGRATED MANAGEMENT SYSTEM (QMS+EMS) INTERNAL AUDIT TRAINING
3.6 UNDERSTANDING AND IMPLEMENTING AN ENERGY MANAGEMENT SYSTEM BASED ON ISO50001:2011
3.7 ENERGY MANAGER TRAINING BY MAESCO
3.8 MICROSOFT EXCELL BASIC AND INTERMEDIATE TRAINING
REMARKS
132KV INCOMER
FACTORY ATTACHMENT
BEADWIRE 2
STEELCORD TBR F
HONGDUK SC POHANG, KOREA 2014 ( 9 MTH)
KYUNG HEE UNIVERSITI, SEOUL, KOREA - KOREAN LANGUAGE - 2014
2009
4. IDEA AND IMPLEMENTATION
DESCRIPTION ATTACHMENT REMARKS
2011 MY IDEA CONTEST - REDUCE
OF TRAVESER BREAKDOWN AND
INCREASE PRODUCTIVITY
2011 KISWIRE GLOBAL My IDEA
CONTEST IN KOREA - 2ND PLACE
( IMPLEMENT TO ALL BUNCHER
MACHINE - 130MC)
AIR WIPER - CHANGING MATERIAL
DUE TO WIRE QUALITY AND TO SAVE
COST PART CHANGING
2ND PLACE - IMPLEMENT TO ALL
LINE USED SC AND BW
FINE DRAWING SAVE COST IDEA
2ND PLACE - SAVE COST FOR
BEARING PRECISION
BUNCHER MACHINE IMPROVEMENT
OF PITCH GEAR DUE TO HIGH
BREAKDOWN
2015 IDEA IMPLEMENT
ANDON SYSTEM
TPS TRAINING AT JAPAN -
IMPLEMENT TO ALL FACTORY
PACEMAKER
TPS TRAINING AT JAPAN -
IMPLEMENT TO ALL FACTORY
ROTATING SINK BAR FOR BW PB PREVENT WIRE QUALITYROTATING SINK BAR FOR BW PB
BATH
PREVENT WIRE QUALITY
PROBLEM

Mais conteúdo relacionado

Destaque

Stacks, Queues, Binary Search Trees - Lecture 1 - Advanced Data Structures
Stacks, Queues, Binary Search Trees -  Lecture 1 - Advanced Data StructuresStacks, Queues, Binary Search Trees -  Lecture 1 - Advanced Data Structures
Stacks, Queues, Binary Search Trees - Lecture 1 - Advanced Data StructuresAmrinder Arora
 
צביעה של גרפים מקריים
צביעה של גרפים מקרייםצביעה של גרפים מקריים
צביעה של גרפים מקרייםDalya Gartzman
 
GENDER DAN DUNIA KERJA- DJOKO AW
GENDER DAN DUNIA KERJA- DJOKO AWGENDER DAN DUNIA KERJA- DJOKO AW
GENDER DAN DUNIA KERJA- DJOKO AWDjoko Adi Walujo
 
Mike Hoogenakker 50th Birthday
Mike Hoogenakker 50th BirthdayMike Hoogenakker 50th Birthday
Mike Hoogenakker 50th Birthdaydutchhook
 
Dugway Dispatch - December 2011 Edition
Dugway Dispatch - December 2011 EditionDugway Dispatch - December 2011 Edition
Dugway Dispatch - December 2011 EditionDugway_Proving_Ground
 
кто я
кто якто я
кто яJIexa01
 
Women in Business November 2012 newsletter
Women in Business November 2012 newsletterWomen in Business November 2012 newsletter
Women in Business November 2012 newsletterJacoba Poppleton
 
From Muppets to Mastery - SXSW 2013
From Muppets to Mastery - SXSW 2013From Muppets to Mastery - SXSW 2013
From Muppets to Mastery - SXSW 2013Russ U
 

Destaque (11)

Slideshare
SlideshareSlideshare
Slideshare
 
Stacks, Queues, Binary Search Trees - Lecture 1 - Advanced Data Structures
Stacks, Queues, Binary Search Trees -  Lecture 1 - Advanced Data StructuresStacks, Queues, Binary Search Trees -  Lecture 1 - Advanced Data Structures
Stacks, Queues, Binary Search Trees - Lecture 1 - Advanced Data Structures
 
צביעה של גרפים מקריים
צביעה של גרפים מקרייםצביעה של גרפים מקריים
צביעה של גרפים מקריים
 
Gusevkontaktn
GusevkontaktnGusevkontaktn
Gusevkontaktn
 
GENDER DAN DUNIA KERJA- DJOKO AW
GENDER DAN DUNIA KERJA- DJOKO AWGENDER DAN DUNIA KERJA- DJOKO AW
GENDER DAN DUNIA KERJA- DJOKO AW
 
Mike Hoogenakker 50th Birthday
Mike Hoogenakker 50th BirthdayMike Hoogenakker 50th Birthday
Mike Hoogenakker 50th Birthday
 
Dugway Dispatch - December 2011 Edition
Dugway Dispatch - December 2011 EditionDugway Dispatch - December 2011 Edition
Dugway Dispatch - December 2011 Edition
 
кто я
кто якто я
кто я
 
Sistema de gestion
Sistema de gestionSistema de gestion
Sistema de gestion
 
Women in Business November 2012 newsletter
Women in Business November 2012 newsletterWomen in Business November 2012 newsletter
Women in Business November 2012 newsletter
 
From Muppets to Mastery - SXSW 2013
From Muppets to Mastery - SXSW 2013From Muppets to Mastery - SXSW 2013
From Muppets to Mastery - SXSW 2013
 

Semelhante a Working Experience

Design of Pre-Engineered Building (PEB) Structure
Design of Pre-Engineered Building (PEB) StructureDesign of Pre-Engineered Building (PEB) Structure
Design of Pre-Engineered Building (PEB) StructureIRJET Journal
 
MEHUL.H.VORA Project final.
MEHUL.H.VORA Project final.MEHUL.H.VORA Project final.
MEHUL.H.VORA Project final.Mehul Vora
 
Design out maintenance on frequent failure of motor ball bearings-2-3
Design out maintenance on frequent failure of motor ball bearings-2-3Design out maintenance on frequent failure of motor ball bearings-2-3
Design out maintenance on frequent failure of motor ball bearings-2-3IAEME Publication
 
Colombo Dockyard PLC Industrial Training Report
Colombo Dockyard PLC Industrial Training ReportColombo Dockyard PLC Industrial Training Report
Colombo Dockyard PLC Industrial Training ReportWickramarathne GT
 
Standard design bop_sep10
Standard design bop_sep10Standard design bop_sep10
Standard design bop_sep10PRABIR DATTA
 
Magnetic Levitating Hover Board to Work as a Forklift
Magnetic Levitating Hover Board to Work as a ForkliftMagnetic Levitating Hover Board to Work as a Forklift
Magnetic Levitating Hover Board to Work as a Forkliftijtsrd
 
Report On Summer Training
Report On Summer Training Report On Summer Training
Report On Summer Training SATYAM PEEYUSH
 
IRJET- Productivity Improvement of Assembly Workstation in a Small Scale ...
IRJET-  	  Productivity Improvement of Assembly Workstation in a Small Scale ...IRJET-  	  Productivity Improvement of Assembly Workstation in a Small Scale ...
IRJET- Productivity Improvement of Assembly Workstation in a Small Scale ...IRJET Journal
 
Stope Optimization in Metal Mines
Stope Optimization in Metal MinesStope Optimization in Metal Mines
Stope Optimization in Metal MinesAnurag Jha
 
DESIGNING FRAMED STRUCTURE IN ETABS AND STAAD PRO
DESIGNING FRAMED STRUCTURE IN ETABS AND STAAD PRODESIGNING FRAMED STRUCTURE IN ETABS AND STAAD PRO
DESIGNING FRAMED STRUCTURE IN ETABS AND STAAD PROIRJET Journal
 
G. Naveen Kumar-Instrumentation Design Engineer
G. Naveen Kumar-Instrumentation Design EngineerG. Naveen Kumar-Instrumentation Design Engineer
G. Naveen Kumar-Instrumentation Design EngineerNaveen Kumar
 
Vasanth_Electrical Engineer_CV_new
Vasanth_Electrical Engineer_CV_newVasanth_Electrical Engineer_CV_new
Vasanth_Electrical Engineer_CV_newvasanth morais
 
BHEL summer internship report
BHEL summer internship reportBHEL summer internship report
BHEL summer internship reportShivam Teotia
 
IRJET- Analysis & Design of Reinforced Concrete Building (G+4) using ETABS
IRJET- Analysis & Design of Reinforced Concrete Building (G+4) using ETABSIRJET- Analysis & Design of Reinforced Concrete Building (G+4) using ETABS
IRJET- Analysis & Design of Reinforced Concrete Building (G+4) using ETABSIRJET Journal
 
Khubaib Khan_CV Instrument
Khubaib Khan_CV InstrumentKhubaib Khan_CV Instrument
Khubaib Khan_CV InstrumentKhubaib Khan
 

Semelhante a Working Experience (20)

Design of Pre-Engineered Building (PEB) Structure
Design of Pre-Engineered Building (PEB) StructureDesign of Pre-Engineered Building (PEB) Structure
Design of Pre-Engineered Building (PEB) Structure
 
MEHUL.H.VORA Project final.
MEHUL.H.VORA Project final.MEHUL.H.VORA Project final.
MEHUL.H.VORA Project final.
 
Design out maintenance on frequent failure of motor ball bearings-2-3
Design out maintenance on frequent failure of motor ball bearings-2-3Design out maintenance on frequent failure of motor ball bearings-2-3
Design out maintenance on frequent failure of motor ball bearings-2-3
 
renew the project
renew the projectrenew the project
renew the project
 
Ch25 new
Ch25 newCh25 new
Ch25 new
 
Colombo Dockyard PLC Industrial Training Report
Colombo Dockyard PLC Industrial Training ReportColombo Dockyard PLC Industrial Training Report
Colombo Dockyard PLC Industrial Training Report
 
Khlau Rev0 150701
Khlau Rev0 150701Khlau Rev0 150701
Khlau Rev0 150701
 
Standard design bop_sep10
Standard design bop_sep10Standard design bop_sep10
Standard design bop_sep10
 
Magnetic Levitating Hover Board to Work as a Forklift
Magnetic Levitating Hover Board to Work as a ForkliftMagnetic Levitating Hover Board to Work as a Forklift
Magnetic Levitating Hover Board to Work as a Forklift
 
Report On Summer Training
Report On Summer Training Report On Summer Training
Report On Summer Training
 
IRJET- Productivity Improvement of Assembly Workstation in a Small Scale ...
IRJET-  	  Productivity Improvement of Assembly Workstation in a Small Scale ...IRJET-  	  Productivity Improvement of Assembly Workstation in a Small Scale ...
IRJET- Productivity Improvement of Assembly Workstation in a Small Scale ...
 
Stope Optimization in Metal Mines
Stope Optimization in Metal MinesStope Optimization in Metal Mines
Stope Optimization in Metal Mines
 
Grid code 2014
Grid code 2014Grid code 2014
Grid code 2014
 
DESIGNING FRAMED STRUCTURE IN ETABS AND STAAD PRO
DESIGNING FRAMED STRUCTURE IN ETABS AND STAAD PRODESIGNING FRAMED STRUCTURE IN ETABS AND STAAD PRO
DESIGNING FRAMED STRUCTURE IN ETABS AND STAAD PRO
 
G. Naveen Kumar-Instrumentation Design Engineer
G. Naveen Kumar-Instrumentation Design EngineerG. Naveen Kumar-Instrumentation Design Engineer
G. Naveen Kumar-Instrumentation Design Engineer
 
Vasanth_Electrical Engineer_CV_new
Vasanth_Electrical Engineer_CV_newVasanth_Electrical Engineer_CV_new
Vasanth_Electrical Engineer_CV_new
 
BHEL summer internship report
BHEL summer internship reportBHEL summer internship report
BHEL summer internship report
 
IRJET- Analysis & Design of Reinforced Concrete Building (G+4) using ETABS
IRJET- Analysis & Design of Reinforced Concrete Building (G+4) using ETABSIRJET- Analysis & Design of Reinforced Concrete Building (G+4) using ETABS
IRJET- Analysis & Design of Reinforced Concrete Building (G+4) using ETABS
 
Technical Portfolio_2010 to 2017
Technical Portfolio_2010 to 2017Technical Portfolio_2010 to 2017
Technical Portfolio_2010 to 2017
 
Khubaib Khan_CV Instrument
Khubaib Khan_CV InstrumentKhubaib Khan_CV Instrument
Khubaib Khan_CV Instrument
 

Working Experience

  • 1. 2. WORKING EXPERIENCE (KISWIRE CORD SDN. BHD) 2.1. MANPOWER MANAGEMENT - ELECTRICAL DEPARTMENT ORGANIZATION CHART 2.2. BREAKDOWN AND PREVENTIVE MAINTENANCE ACTIVITIES 2.2.1 DISTRIBUTE AND ALLOCATE MANPOWER DAILY BY PROCESS 2.2.2 PROVIDE TECHNICAL TRAINING AND SUPPORT 2.2.3 TO LEAD MAINTENANCE TEAM IN-CASE MAJOR BREAKDOWN 2.2.4 TO PLAN SCHEDULE AND LAYOUT FOR DAILY / WEEKLY PREVENTIVE MAINTANANCE ACTIVTIES 2.2.5 TO COORDINATE WITH CONTRACTOR FOR EXTERNAL SUPPORT 2.2.6 TO PREPARE WEEKLY MAINTENANCE BREAKDOWN REPORT 2.3. SPARE PART AND INVENTORY MANAGEMENT 2.3.1 TO SETUP SPARE PART AND INVENTORY MANAGEMENT SYSTEM BASE ON KISWIRE PRODUCTION SYSTEM 2.3.2 TO PURCHASE AND COORDINATE SPARE PART ARRIVAL (DEPENDS ON URGENCIES) 2.4 NEW MACHINE AND FACILITIES INSTALLATION 2.4.1. DOCUMENT PREPARATION (SCHEDULE, ELECTRICAL LAYOUT DESIGN AND REQUIREMENT, etc) 2.4.2. MATERIAL CALCULATION AND PREPARATION (SUB MAIN CABLING, SEC. CABLING, CONTROL,etc) 2.4.3. COORDINATE CONTRACTOR THROUGHOUT INSTALLATION PROCESS 2.4.4. COMMISSIONING AND TESTING 2.4.5. PROJECT COSTING CALCULATION 1. Total Installation : 11 lines REMARKS (PICKLING / IN-LINE PATENTING / PLATING) PROCESS ATTACHMENT BeadwirePatenting Line SC & BW Plating Line SC & BW PicklingLine SAIFUL TEAM HEAD Sn. ENGINEER ENGINEER ENGINEER FOREMAN LEADERS Sn TECH Jnr TECH GENERAL TOTAL MANPOWER: 20 ENGINEER ENGINEER THAUFAN SR. ENGINEER a) Furnace SC/BW Line b) Diffusion SC c) PB Bath d)P/Off - T/up machine e) PP Bath - Bondrite,Borax,CU,Zn (SCHEDULE,MACHINE LAY-OUT,AIR & WATER PIPING, etc) (PIPE AND MACHINE PART) MECHANICAL DEPARTMENT ORGANIZATION CHART
  • 2. 1. Total Installation : 42 units 2. Overall Machine : 64 units 1. Total Installation : >1000 units 1. Total Installation : > 500 units 1. Total Installation : 6 system 1. Total Installation : 2 system 1. Total Installation : 10 system COMPRESSOR COOLING SYSTEM REMARKS WET DRAWING MC SC MC THERMOPACK TREATMENT PLANT WASTE WATER ATTACHMENT DRY DRAWING MC PROCESS -SETTING AND COMMISIONING
  • 3. 2. START-UP DELAY SOP 2.6. FACTORY EXPANSION PROJECT 1. EXPANSION YEAR 2008 1. EXPANSION YEAR 2008 1. EXPANSION YEAR 2008 1. EXPANSION YEAR 2009 1. EXPANSION YEAR 2010 2. NEW APPLICATION 33KV DESCRIPTION ATTACHMENT REMARKS KSSB STEELCORD TBR D STEELCORD INLINE E SSW BLK F MD CONTROL FACTORY ATTACHMENT REMARKS BEADWIRE KCSB Load (A) vs time (hour) KCSB Load Start-up 2500 3000 A(Amp) t(hour) 1500 pm 2800 2600 OVERHAUL MACHINE TWISTER (405UNIT) FINE DRAWING MACHINE (411UNIT) 5
  • 4. 1. EXPANSION YEAR 2012 1. EXPANSION YEAR 2014 1. EXPANSION YEAR 2015 3. TRAINING 3.1. ON JOB TRAINING - KISWIRE GUNCHEON, KOREA 3.2. FUJI INVERTER TRAINING 3.3. TOYOTA PRODUCTION SYSTEM TRANING, JAPAN 3.4 ISO/TS 16949 PROCESS BASE INTERNAL AUDITING 3.5 INTERGRATED MANAGEMENT SYSTEM (QMS+EMS) INTERNAL AUDIT TRAINING 3.6 UNDERSTANDING AND IMPLEMENTING AN ENERGY MANAGEMENT SYSTEM BASED ON ISO50001:2011 3.7 ENERGY MANAGER TRAINING BY MAESCO 3.8 MICROSOFT EXCELL BASIC AND INTERMEDIATE TRAINING REMARKS 132KV INCOMER FACTORY ATTACHMENT BEADWIRE 2 STEELCORD TBR F HONGDUK SC POHANG, KOREA 2014 ( 9 MTH) KYUNG HEE UNIVERSITI, SEOUL, KOREA - KOREAN LANGUAGE - 2014 2009
  • 5. 4. IDEA AND IMPLEMENTATION DESCRIPTION ATTACHMENT REMARKS 2011 MY IDEA CONTEST - REDUCE OF TRAVESER BREAKDOWN AND INCREASE PRODUCTIVITY 2011 KISWIRE GLOBAL My IDEA CONTEST IN KOREA - 2ND PLACE ( IMPLEMENT TO ALL BUNCHER MACHINE - 130MC) AIR WIPER - CHANGING MATERIAL DUE TO WIRE QUALITY AND TO SAVE COST PART CHANGING 2ND PLACE - IMPLEMENT TO ALL LINE USED SC AND BW FINE DRAWING SAVE COST IDEA 2ND PLACE - SAVE COST FOR BEARING PRECISION BUNCHER MACHINE IMPROVEMENT OF PITCH GEAR DUE TO HIGH BREAKDOWN 2015 IDEA IMPLEMENT ANDON SYSTEM TPS TRAINING AT JAPAN - IMPLEMENT TO ALL FACTORY PACEMAKER TPS TRAINING AT JAPAN - IMPLEMENT TO ALL FACTORY ROTATING SINK BAR FOR BW PB PREVENT WIRE QUALITYROTATING SINK BAR FOR BW PB BATH PREVENT WIRE QUALITY PROBLEM