PMP Formulas
Earned Value
CV = EV - AC
CPI = EV / AC
SV = EV - PV
SPI = EV / PV
EAC ‘no variances’ = BAC / CPI
EAC ‘fundamentally flawed’ = AC + ETC
EAC ‘atypical’ = AC + BAC - EV
EAC ‘typical’ = AC + ((BAC - EV) / CPI)
ETC = EAC - AC
ETC ‘atypical’ = BAC - EV
ETC ‘typical’ = (BAC - EV) / CPI
ETC ‘flawed’ = new estimate
Percent Complete = EV / BAC * 100
VAC = BAC - EAC
EV = % complete * BAC
% COMPLETE = EV / BAC x 100
% SPENT = AC / BAC x 100
CV% = CV / EV x 100
SV% = SV / PV x 100
PERT
PERT 3-point = (Pessimistic+(4*Most Likely)+Optimistic)/6
PERT α = (Pessimistic - Optimistic) / 6
PERT Activity Variance = ((Pessimistic - Optimistic) / 6)^2
PERT Variance all activities = _sum((Pessimistic - Optimistic) / 6)^2
Classes of Estimates
Order of Magnitude estimate = -25% to +75%
Preliminary estimate = -15% to + 50%
Budget estimate = -10% to +25%
Definitive estimate = -5% to +10%
Final estimate = 0%
www.pmlead.net
Project Selection
PV = FV / (1+r)^n
FV = PV * (1+r)^n
NPV = Select biggest number.
ROI = Select biggest number.
IRR = Select biggest number.
Payback Period = Add up the projected cash inflow minus expenses until you reach the initial
investment.
BCR = Benefit / Cost
CBR = Cost / Benefit
Opportunity Cost = The value of the project not chosen.
Exp. Value = Probability % x Consequence $
Communications
Communication Channels = n * (n-1) / 2
Probability
EMV = Probability * Impact in currency
Procurement
PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target Cost
Depreciation
Straight-line Depreciation:
Depr. Expense = Asset Cost / Useful Life
Depr. Rate = 100% / Useful Life
Double Declining Balance Method:
Depr. Rate = 2 * (100% / Useful Life)
Depr. Expense = Depreciation Rate * Book Value at Beginning of Year
Book Value = Book Value at beginning of year - Depreciation Expense
Sum-of-Years' Digits Method:
Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc.
Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th)
www.pmlead.net
SIGMA
1 sigma = 68.26%
2 sigma = 95.46%
3 sigma = 99.73%
6 sigma = 99.99%
Important Values
Control Limits = 3 sigma from mean
Control Specifications = Defined by customer; less than the control limits
Float on the critical path = 0 days
Pareto Diagram = 80/20
Time a PM spends communicating = 90%
Crashing a project = Crash least expensive tasks on critical path.
JIT inventory = 0% (or very close to 0%.)
Network Diagram
Forward Pass
ES = EF of the predecessor node
EF = ES + Dur
Backward Pass
LF = LS of the Successor
LS = LF – Dur
Slack = LF – EF = LS – ES
Free Float = ES(Successor) - EF(Predecessor)
You need to understand the formulas not only memorize them
Refer to the PMBoK 4th
Edition for more details
PMI®, PMP®, CAPM® and PMBOK® Guide are trademarks of the Project Management Institute, Inc.
PMI® has not endorsed and did not participate in the development of this product.
ES Dur EF
Node
LS Float LF
ES Du EF
Prepared by:
Amr Miqdadi,PMP,MCSE
amiqdadi@pmlead.net

More Related Content

Viewers also liked

Trabajo en grupo fifo, lifo y cross docking
Trabajo en grupo fifo, lifo y cross   dockingTrabajo en grupo fifo, lifo y cross   docking
Trabajo en grupo fifo, lifo y cross dockingdaniel
 
Matriz de responsabilidade
Matriz de responsabilidadeMatriz de responsabilidade
Matriz de responsabilidadeuserbeta
 
Metodologia prince2
Metodologia prince2Metodologia prince2
Metodologia prince2fwlondon
 
IPPM - The Integrated Process and Project Management Organization
IPPM - The Integrated Process and Project Management OrganizationIPPM - The Integrated Process and Project Management Organization
IPPM - The Integrated Process and Project Management OrganizationStefan Hagen
 
Gestión de servicios IT, fundamentos de ITIL
Gestión de servicios IT, fundamentos de ITILGestión de servicios IT, fundamentos de ITIL
Gestión de servicios IT, fundamentos de ITILRamiro Cid
 
PMP, Project Management Professional
PMP, Project Management ProfessionalPMP, Project Management Professional
PMP, Project Management ProfessionalOliver Centeno
 
Gestión del proyecto TROPOS utilizando metodología PRINCE2
Gestión del proyecto TROPOS utilizando metodología PRINCE2Gestión del proyecto TROPOS utilizando metodología PRINCE2
Gestión del proyecto TROPOS utilizando metodología PRINCE2itproiectus
 
Roles Y Responsabilidades Lecciones Aprendidas V1.3
Roles Y Responsabilidades  Lecciones Aprendidas V1.3Roles Y Responsabilidades  Lecciones Aprendidas V1.3
Roles Y Responsabilidades Lecciones Aprendidas V1.3cserran2
 
PMBOK Cuarta Edición. Cambios a la Guía.
PMBOK Cuarta Edición. Cambios a la Guía.PMBOK Cuarta Edición. Cambios a la Guía.
PMBOK Cuarta Edición. Cambios a la Guía.Armando Peralta Díaz
 
Gestión de Servicios - Curso ITIL: Fundamentos
Gestión de Servicios - Curso ITIL: FundamentosGestión de Servicios - Curso ITIL: Fundamentos
Gestión de Servicios - Curso ITIL: FundamentosONGEI PERÚ
 
¿Cómo asignar los roles de los procesos de ITIL?
¿Cómo asignar los roles de los procesos de ITIL?¿Cómo asignar los roles de los procesos de ITIL?
¿Cómo asignar los roles de los procesos de ITIL?EXIN
 
Metodologías SCRUM + PMBOK
Metodologías SCRUM + PMBOKMetodologías SCRUM + PMBOK
Metodologías SCRUM + PMBOKitproiectus
 

Viewers also liked (20)

Trabajo en grupo fifo, lifo y cross docking
Trabajo en grupo fifo, lifo y cross   dockingTrabajo en grupo fifo, lifo y cross   docking
Trabajo en grupo fifo, lifo y cross docking
 
PRINCE2 para emprendedores
PRINCE2 para emprendedoresPRINCE2 para emprendedores
PRINCE2 para emprendedores
 
PMBoK y Prince2, ¿Iguales, diferentes o complementarios?
PMBoK y Prince2, ¿Iguales, diferentes o complementarios?PMBoK y Prince2, ¿Iguales, diferentes o complementarios?
PMBoK y Prince2, ¿Iguales, diferentes o complementarios?
 
Matriz de responsabilidade
Matriz de responsabilidadeMatriz de responsabilidade
Matriz de responsabilidade
 
Metodologia prince2
Metodologia prince2Metodologia prince2
Metodologia prince2
 
IPPM - The Integrated Process and Project Management Organization
IPPM - The Integrated Process and Project Management OrganizationIPPM - The Integrated Process and Project Management Organization
IPPM - The Integrated Process and Project Management Organization
 
Metodologías ágiles
Metodologías ágilesMetodologías ágiles
Metodologías ágiles
 
Gestión de servicios IT, fundamentos de ITIL
Gestión de servicios IT, fundamentos de ITILGestión de servicios IT, fundamentos de ITIL
Gestión de servicios IT, fundamentos de ITIL
 
PMP, Project Management Professional
PMP, Project Management ProfessionalPMP, Project Management Professional
PMP, Project Management Professional
 
Sistema fifo
Sistema fifoSistema fifo
Sistema fifo
 
Gestión del proyecto TROPOS utilizando metodología PRINCE2
Gestión del proyecto TROPOS utilizando metodología PRINCE2Gestión del proyecto TROPOS utilizando metodología PRINCE2
Gestión del proyecto TROPOS utilizando metodología PRINCE2
 
PRINCE2, un buen inicio para un Project Manager
PRINCE2, un buen inicio para un Project ManagerPRINCE2, un buen inicio para un Project Manager
PRINCE2, un buen inicio para un Project Manager
 
Roles Y Responsabilidades Lecciones Aprendidas V1.3
Roles Y Responsabilidades  Lecciones Aprendidas V1.3Roles Y Responsabilidades  Lecciones Aprendidas V1.3
Roles Y Responsabilidades Lecciones Aprendidas V1.3
 
PMBOK Cuarta Edición. Cambios a la Guía.
PMBOK Cuarta Edición. Cambios a la Guía.PMBOK Cuarta Edición. Cambios a la Guía.
PMBOK Cuarta Edición. Cambios a la Guía.
 
Examen pmp costos
Examen pmp costosExamen pmp costos
Examen pmp costos
 
Gestión de Servicios - Curso ITIL: Fundamentos
Gestión de Servicios - Curso ITIL: FundamentosGestión de Servicios - Curso ITIL: Fundamentos
Gestión de Servicios - Curso ITIL: Fundamentos
 
Integrando ITIL v3 y PMBoK v4
Integrando ITIL v3 y PMBoK v4Integrando ITIL v3 y PMBoK v4
Integrando ITIL v3 y PMBoK v4
 
Que es Scrum?
Que es Scrum?Que es Scrum?
Que es Scrum?
 
¿Cómo asignar los roles de los procesos de ITIL?
¿Cómo asignar los roles de los procesos de ITIL?¿Cómo asignar los roles de los procesos de ITIL?
¿Cómo asignar los roles de los procesos de ITIL?
 
Metodologías SCRUM + PMBOK
Metodologías SCRUM + PMBOKMetodologías SCRUM + PMBOK
Metodologías SCRUM + PMBOK
 

Similar to Pmp formulas

Formula pocket guide
Formula pocket guideFormula pocket guide
Formula pocket guideVicky Maly
 
PMP Exam Formulas
PMP Exam FormulasPMP Exam Formulas
PMP Exam FormulasAmr Miqdadi
 
Important formules for ugc net commerce,management (most important) downl...
Important  formules  for  ugc net commerce,management (most important)  downl...Important  formules  for  ugc net commerce,management (most important)  downl...
Important formules for ugc net commerce,management (most important) downl...DIwakar Rajput
 
Lucian Smith - Modular Modeling: Standards and Tools (IMAG)
Lucian Smith - Modular Modeling: Standards and Tools (IMAG)Lucian Smith - Modular Modeling: Standards and Tools (IMAG)
Lucian Smith - Modular Modeling: Standards and Tools (IMAG)Lucian Smith
 
Rethinking the Way We do Templates in C++
Rethinking the Way We do Templates in C++Rethinking the Way We do Templates in C++
Rethinking the Way We do Templates in C++Mateusz Pusz
 
Cash Flow - Unit III Engineering Economics - MG6863
Cash Flow - Unit III Engineering Economics - MG6863Cash Flow - Unit III Engineering Economics - MG6863
Cash Flow - Unit III Engineering Economics - MG6863Balamurugan Subburaj
 
Lecture#5 Operators in C++
Lecture#5 Operators in C++Lecture#5 Operators in C++
Lecture#5 Operators in C++NUST Stuff
 
Basic math operations using dataweave
Basic math operations using dataweaveBasic math operations using dataweave
Basic math operations using dataweaveRamakrishna kapa
 
PAC 2020 Santorin - Andreas Grabner
PAC 2020 Santorin - Andreas Grabner PAC 2020 Santorin - Andreas Grabner
PAC 2020 Santorin - Andreas Grabner Neotys
 

Similar to Pmp formulas (20)

Pmp formulas
Pmp formulasPmp formulas
Pmp formulas
 
Pmp formula pocket guide
Pmp formula pocket guidePmp formula pocket guide
Pmp formula pocket guide
 
Pmp Formula Pocket_Guide
Pmp Formula Pocket_GuidePmp Formula Pocket_Guide
Pmp Formula Pocket_Guide
 
Formula pocket guide
Formula pocket guideFormula pocket guide
Formula pocket guide
 
Pmp formula pocket guide
Pmp formula pocket guidePmp formula pocket guide
Pmp formula pocket guide
 
PMP Exam Formulas
PMP Exam FormulasPMP Exam Formulas
PMP Exam Formulas
 
Break even point(BEP)
Break even point(BEP)Break even point(BEP)
Break even point(BEP)
 
PMBOK 6th ed Formulas.pdf
PMBOK 6th ed Formulas.pdfPMBOK 6th ed Formulas.pdf
PMBOK 6th ed Formulas.pdf
 
cheat sheet.ppt
cheat sheet.pptcheat sheet.ppt
cheat sheet.ppt
 
Important formules for ugc net commerce,management (most important) downl...
Important  formules  for  ugc net commerce,management (most important)  downl...Important  formules  for  ugc net commerce,management (most important)  downl...
Important formules for ugc net commerce,management (most important) downl...
 
Python as a calculator
Python as a calculatorPython as a calculator
Python as a calculator
 
Lucian Smith - Modular Modeling: Standards and Tools (IMAG)
Lucian Smith - Modular Modeling: Standards and Tools (IMAG)Lucian Smith - Modular Modeling: Standards and Tools (IMAG)
Lucian Smith - Modular Modeling: Standards and Tools (IMAG)
 
Rethinking the Way We do Templates in C++
Rethinking the Way We do Templates in C++Rethinking the Way We do Templates in C++
Rethinking the Way We do Templates in C++
 
Cash Flow - Unit III Engineering Economics - MG6863
Cash Flow - Unit III Engineering Economics - MG6863Cash Flow - Unit III Engineering Economics - MG6863
Cash Flow - Unit III Engineering Economics - MG6863
 
Lecture#5 Operators in C++
Lecture#5 Operators in C++Lecture#5 Operators in C++
Lecture#5 Operators in C++
 
Pmp formulas v5
Pmp formulas v5Pmp formulas v5
Pmp formulas v5
 
Cpl
CplCpl
Cpl
 
PMP Exam Formulas To Know
PMP Exam Formulas To KnowPMP Exam Formulas To Know
PMP Exam Formulas To Know
 
Basic math operations using dataweave
Basic math operations using dataweaveBasic math operations using dataweave
Basic math operations using dataweave
 
PAC 2020 Santorin - Andreas Grabner
PAC 2020 Santorin - Andreas Grabner PAC 2020 Santorin - Andreas Grabner
PAC 2020 Santorin - Andreas Grabner
 

Pmp formulas

  • 1. www.pmlead.net PMP Formulas Earned Value CV = EV - AC CPI = EV / AC SV = EV - PV SPI = EV / PV EAC ‘no variances’ = BAC / CPI EAC ‘fundamentally flawed’ = AC + ETC EAC ‘atypical’ = AC + BAC - EV EAC ‘typical’ = AC + ((BAC - EV) / CPI) ETC = EAC - AC ETC ‘atypical’ = BAC - EV ETC ‘typical’ = (BAC - EV) / CPI ETC ‘flawed’ = new estimate Percent Complete = EV / BAC * 100 VAC = BAC - EAC EV = % complete * BAC % COMPLETE = EV / BAC x 100 % SPENT = AC / BAC x 100 CV% = CV / EV x 100 SV% = SV / PV x 100 PERT PERT 3-point = (Pessimistic+(4*Most Likely)+Optimistic)/6 PERT α = (Pessimistic - Optimistic) / 6 PERT Activity Variance = ((Pessimistic - Optimistic) / 6)^2 PERT Variance all activities = _sum((Pessimistic - Optimistic) / 6)^2 Classes of Estimates Order of Magnitude estimate = -25% to +75% Preliminary estimate = -15% to + 50% Budget estimate = -10% to +25% Definitive estimate = -5% to +10% Final estimate = 0%
  • 2. www.pmlead.net Project Selection PV = FV / (1+r)^n FV = PV * (1+r)^n NPV = Select biggest number. ROI = Select biggest number. IRR = Select biggest number. Payback Period = Add up the projected cash inflow minus expenses until you reach the initial investment. BCR = Benefit / Cost CBR = Cost / Benefit Opportunity Cost = The value of the project not chosen. Exp. Value = Probability % x Consequence $ Communications Communication Channels = n * (n-1) / 2 Probability EMV = Probability * Impact in currency Procurement PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target Cost Depreciation Straight-line Depreciation: Depr. Expense = Asset Cost / Useful Life Depr. Rate = 100% / Useful Life Double Declining Balance Method: Depr. Rate = 2 * (100% / Useful Life) Depr. Expense = Depreciation Rate * Book Value at Beginning of Year Book Value = Book Value at beginning of year - Depreciation Expense Sum-of-Years' Digits Method: Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc. Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th)
  • 3. www.pmlead.net SIGMA 1 sigma = 68.26% 2 sigma = 95.46% 3 sigma = 99.73% 6 sigma = 99.99% Important Values Control Limits = 3 sigma from mean Control Specifications = Defined by customer; less than the control limits Float on the critical path = 0 days Pareto Diagram = 80/20 Time a PM spends communicating = 90% Crashing a project = Crash least expensive tasks on critical path. JIT inventory = 0% (or very close to 0%.) Network Diagram Forward Pass ES = EF of the predecessor node EF = ES + Dur Backward Pass LF = LS of the Successor LS = LF – Dur Slack = LF – EF = LS – ES Free Float = ES(Successor) - EF(Predecessor) You need to understand the formulas not only memorize them Refer to the PMBoK 4th Edition for more details PMI®, PMP®, CAPM® and PMBOK® Guide are trademarks of the Project Management Institute, Inc. PMI® has not endorsed and did not participate in the development of this product. ES Dur EF Node LS Float LF ES Du EF Prepared by: Amr Miqdadi,PMP,MCSE amiqdadi@pmlead.net