SlideShare uma empresa Scribd logo
1 de 57
Module 6
Project Schedule Management
Agus Suhanto
Module Overview
• Lesson 1: Key Concepts & Terms
• Lesson 2: Plan Schedule Management
• Lesson 3: Define Activities
• Lesson 4: Sequence Activities
• Lesson 5: Estimate Activity Duration
• Lesson 6: Develop Schedule
• Lesson 7: Control Schedule
Lesson 1: Key Concepts & Terms
• Project Schedule Management
• Key Terms
• Trends & Emerging Practices
• Tailoring Considerations
• Considerations for Adaptive Environment
Project Schedule Management
Project schedule management is the processes
required to manage the timely completion of the
project.
Key Terms
• Schedule baseline: the version of the schedule model
used to manage the project; it is what the project team’s
performance is measured against.
• Schedule compression: a technique to shorten an already
developed schedule.
• Crashing: schedule compression technique by adding resources.
• Fast tracking: schedule compression technique in which activities
normally done in sequence are performed in parallel for at least a
portion of their duration.
• Activity list: list of activities to be managed in the project
schedule.
• Network diagram: a diagram of project activities that
shows the sequential relationships of activities using
arrows and nodes.
Key Terms (continued)
• Contingency (schedule) reserve: the estimated duration
within the schedule baseline, which is allocated for
identified risks that are accepted.
• Management reserve: specified amount of the project
duration (not included in baseline) withheld for
management control purposes and are reserved for
unforeseen work that is within the scope of the project.
• Critical path: the longest duration path through a network
diagram, and it determines the shortest time it could take
to complete the project.
• Milestone: significant events within the project schedule;
not work activities and have no duration.
Key Terms (continued)
• Near critical path: closest in duration to the critical path.
• Total float: the amount of time an activity can be delayed
without delaying the project end date or an intermediary
milestone.
• Free float: the amount of time an activity can be delayed
without delaying the early start date of its successor(s).
• Project float: the amount of time a project can be delayed
without delaying the externally imposed project
completion date required by the customer.
Key Terms (continued)
• Lead: the amount of time a successor activity can be
advanced with respect to a predecessor activity.
• Lag: the amount of time a successor activity will be
delayed with respect to a predecessor activity.
• Student syndrome (procrastination): people start to apply
themselves only at the last possible moment before
deadline.
• Parkinson’s Law: work expands to fill the time available
for its completion.
Trends & Emerging Practices
• Iterative scheduling with backlog
• On-demand scheduling
Tailoring Considerations
• Life cycle approach
• Resource availability
• Project dimensions
• Technology support
Considerations for Adaptive Environments
• Adaptive approaches use short cycles to
undertake work, review the results, and adapt as
necessary.
• To address the full delivery life cycle for larger,
enterprise-wide systems, a range of techniques
utilizing the predictive, adaptive, or hybrid
approach may need to be adopted.
• The role of project manager does not change.
Lesson 2: Plan Schedule Management
• Plan Schedule Management Overview
• Plan Schedule Management Data Flow
• Plan Schedule Management Input
• Plan Schedule Management Tools & Technique
• Plan Schedule Management Output
Plan Schedule Management Overview
Plan schedule management is the process of
establishing the policies, procedures, and
documentation for planning, developing,
managing, executing, and controlling the project
schedule.
Plan Schedule Management Data Flow
Plan Schedule Management Input
• Project charter
• Project management plan
• Scope management plan
• Development approach
• Enterprise Environmental factors
• Organizational process assets
Plan Schedule Management Tools & Techniques
• Expert judgment
• Data analysis
• Alternative analysis
• Meetings
Plan Schedule Management Output
• Project management plan
• Schedule management plan
• Project schedule model development
• Release and iteration length
• Level of accuracy
• Units of measure
• Organizational procedures links
• Project schedule model maintenance
• Control thresholds
• Rules of performance measurement
• Rules for establishing percent complete
• EVM techniques to be employed
• Schedule performance measurements
• Reporting formats
Lesson 3: Define Activities
• Define Activities Overview
• Define Activities Data Flow
• Define Activities Input
• Define Activities Tools & Techniques
• Define Activities Output
Define Activities Overview
• Define activities is the process of identifying and
documenting the specific actions to be performed to
produce the project deliverables.
• It decomposes work packages into schedule activities
that provide a basis for estimating, scheduling,
executing, monitoring, and controlling the project
work.
Define Activities Data Flow
Define Activities Input
• Project management plan
• Scope management plan
• Scope baseline
• Enterprise environmental factors
• Organizational process assets
Define Activities Tools & Techniques
• Decomposition
• Rolling wave planning
• Meetings
Define Activities Output
• Project documents
• Activity list
• Activity attributes
• Milestone list
• Change requests
• Project management plan updates
• Schedule baseline
• Cost baseline
Lesson 4: Sequence Activities
• Sequence Activities Overview
• Sequence Activities Data Flow
• Sequence Activities Input
• Sequence Activities Tools & Techniques
• Sequence Activities Output
Sequence Activities Overview
• Sequence activities is the process of identifying
and documenting relationships among the project
activities.
• It defines the logical sequence of work to obtain
the greatest efficiency given all project constraints.
Sequence Activities Data Flow
Sequence Activities Input
• Project management plan
• Schedule management plan
• Scope baseline
• Project documents
• Activity attributes
• Activity list
• Assumption log
• Milestone list
• Enterprise environmental factors
• Organizational process assets
Sequence Activities Tools & Techniques
• Precedence diagramming method
• Finish-to-start (FS)
• Finish-to-finish (FF)
• Start-to-start (SS)
• Start-to-finish (SF)
• Dependency determination & integration
• Mandatory internal
• Mandatory external
• Discretionary internal
• Discretionary external
• Lead & Lag
Precedence Diagramming Method
Lead and Lag
Schedule Network Diagram
Sequence Activities Output
• Project schedule network diagram
• Project documents updates
• Activity attributes
• Activity list
• Assumption log
• Milestone list
Lesson 5: Estimate Activity Duration
• Estimate Activity Duration Overview
• Estimate Activity Duration Data Flow
• Estimate Activity Duration Input
• Estimate Activity Duration Tools & Techniques
• Estimate Activity Duration Output
Estimate Activity Duration Overview
Estimate activity duration is the process of
estimating the number of work periods needed to
complete individual activities with estimated
resources.
Estimate Activity Duration Data Flow
Estimating Duration Factors
• Law of diminishing return
• Number of resources
• Advances in technology
• Motivation of staff
Estimate Activity Duration Input
• Project management plan
• Schedule management plan
• Scope baseline
• Project documents
• Activity attributes
• Activity list
• Assumption log
• Lessons learned register
• Milestone list
• Project team assignments
• Resource breakdown structure
• Resource calendars
• Resource requirements
• Risk register
• Enterprise environmental
factor
• Organizational process
access
Estimate Activity Duration Tools & Techniques
• Expert judgment
• Analogous estimating
• Parametric estimating
• Regression analysis
(scatter diagram)
• Learning curve
• Heuristics
• Three-point estimating
• Bottom-up estimating
• Data analysis
• Alternative analysis
• Reserve analysis
• Decision making
• Voting
• Meeting
Three-point Estimating Formula
• Triangular distribution:
𝑡𝐸 =
𝑡𝑂 + 𝑡𝑀 + 𝑡𝑃
3
• Beta distribution:
𝑡𝐸 =
𝑡𝑂 + 4 𝑡𝑀 + 𝑡𝑃
6
Estimate Activity Duration Output
• Duration estimates
• Basis of estimates
• Project documents updates
• Activity attributes
• Assumption log
• Lesson learned register
Lesson 6: Develop Schedule
• Develop Schedule Overview
• Develop Schedule Data Flow
• Develop Schedule Input
• Develop Schedule Tools & Techniques
• Develop Schedule Output
Develop Schedule Overview
• Develop schedule is the process of analyzing,
activity sequences, durations, resource
requirements, and schedule constraints to create a
schedule model for project execution and
monitoring & controlling.
• Key benefit: it generates a schedule model with
planned dates for completing project activities.
Develop Schedule Data Flow
Develop Schedule Input
• Project management plan
• Schedule management plan
• Scope baseline
• Project documents
• Activity attributes
• Activity list
• Assumption log
• Basis of estimates
• Duration estimates
• Lessons learned register
• Milestone list
• Project schedule network
diagram
• Project team assignments
• Resource calendars
• Resource requirements
• Risk register
• Agreements
• Enterprise environmental
factors
• Organizational process
assets
Develop Schedule Tools & Techniques
• Schedule network
analysis
• Critical path method
• Resource optimization
• Resource leveling
• Resource smoothing
• Data analysis
• What-if scenario
• Simulation
• Leads and lags
• Schedule compression
• Crashing
• Fast tracking
• Project management
information system
• Agile release planning
Critical Path & Float
Finding Float
• Perform forward pass to define early start (ES) and
early finish (EF) of each activity
• Perform backward pass to define late start (LS)
and late finish (LF) of each activity
• Float = EF – ES or
• Float = LF – LS
• Critical path has 0 float.
Develop Schedule Output
• Project management plan
• Schedule baseline
• Project documents
• Project schedule
• Bar chart
• Milestone chart
• Project schedule network
diagrams
• Schedule data
• Project calendars
• Change requests
• Project management plan
updates
• Schedule management plan
• Cost baseline
• Project documents updates
• Activity attributes
• Assumption log
• Duration estimates
• Lessons learned register
• Resource requirements
• Risk register
Lesson 7: Control Schedule
• Control Schedule Overview
• Control Schedule Data Flow
• Control Schedule Input
• Control Schedule Tools & Techniques
• Control Schedule Output
Control Schedule Overview
• Control schedule is the process to update the
project schedule and managing changes to the
schedule baseline.
• The key benefit of this process is that the schedule
baseline is maintained throughout the project.
Control Schedule Data Flow
Control Schedule Input
• Project management plan
• Schedule management plan
• Schedule baseline
• Scope baseline
• Performance measurement
baseline
• Project documents
• Lessons learned register
• Project calendars
• Project schedules
• Resource calendars
• Schedule data
• Work performance data
• Organizational process
assets
Control Schedule Tools & Techniques
• Data analysis
• Earned value analysis
• Iteration burndown chart
• Performance reviews
• Trend analysis
• Variance analysis
• What-if scenario analysis
• Critical path method
• Project management information system
• Resource optimization
• Leads & lags
• Schedule compression
Control Schedule Output
• Work performance
information
• Project documents
• Schedule forecasts
• Change requests
• Project management plan
updates
• Schedule management plan
• Schedule baseline
• Cost baseline
• Performance measurement
baseline
• Project documents updates
• Assumption log
• Basis of estimates
• Lessons learned register
• Project schedules
• Resource calendars
• Risk register
• Schedule data
Quiz
Module Reviews
References
• [PMBOK6] – The PMBOK 6th edition from pmi.org
• [RITA9] – Rita Mulcahy’s PMP Exam Prep 9th
edition from RMC Publications™

Mais conteúdo relacionado

Mais procurados

Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniquesShivangi Saini
 
Project Management
Project ManagementProject Management
Project ManagementMark Roman
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycleSAJID ALI RUK
 
PMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management ProcessesPMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management ProcessesMohamed Loey
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management - dyaksa hanindito
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasMazen Zbib
 
Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationAnand Bobade
 
Project cost management PMBOK 5th Edition
Project cost management PMBOK 5th EditionProject cost management PMBOK 5th Edition
Project cost management PMBOK 5th Editionpankajsh10
 
Introduce Project Management
Introduce Project ManagementIntroduce Project Management
Introduce Project Managementguest90bddb
 
Projrct Monitoring & Controling
Projrct   Monitoring  & ControlingProjrct   Monitoring  & Controling
Projrct Monitoring & ControlingDarshana Viduranga
 
Project Management and Process
Project Management and ProcessProject Management and Process
Project Management and ProcessMuhammad Rehman
 
Project Time Management
Project Time ManagementProject Time Management
Project Time ManagementSerdar Temiz
 
Project management tools and techniques
Project management tools and techniquesProject management tools and techniques
Project management tools and techniquesTata Dinyuy
 
Project execution and implementation
Project execution and implementationProject execution and implementation
Project execution and implementationDr. Saima Baig
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management FundamentalsNishant Munjal
 

Mais procurados (20)

Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Project Management
Project ManagementProject Management
Project Management
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycle
 
PMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management ProcessesPMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management Processes
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management -
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areas
 
Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity Duration
 
Project cost management PMBOK 5th Edition
Project cost management PMBOK 5th EditionProject cost management PMBOK 5th Edition
Project cost management PMBOK 5th Edition
 
Introduce Project Management
Introduce Project ManagementIntroduce Project Management
Introduce Project Management
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Projrct Monitoring & Controling
Projrct   Monitoring  & ControlingProjrct   Monitoring  & Controling
Projrct Monitoring & Controling
 
Project Management and Process
Project Management and ProcessProject Management and Process
Project Management and Process
 
Project Management Tools
Project Management ToolsProject Management Tools
Project Management Tools
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
MS Project 2010 Training
MS Project 2010 TrainingMS Project 2010 Training
MS Project 2010 Training
 
Project management tools and techniques
Project management tools and techniquesProject management tools and techniques
Project management tools and techniques
 
Project management
Project managementProject management
Project management
 
Project execution and implementation
Project execution and implementationProject execution and implementation
Project execution and implementation
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
 

Semelhante a Project Schedule Management - PMBOK6

06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagementDhamo daran
 
Presintation on Project constraint
Presintation on Project constraint Presintation on Project constraint
Presintation on Project constraint university(kust)
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfHuyNguyen657394
 
Day 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxDay 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxMohanadRabea1
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project ManagementRasan Samarasinghe
 
Software project management tools
Software project management toolsSoftware project management tools
Software project management toolsDarshak Mehta
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5Hisham Ali,PMP
 
2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptxProfDrAnbalaganChinn
 
Time management pressent
Time management pressentTime management pressent
Time management pressentiklil fairuz
 
Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Agus Suhanto
 
Project management master class karin rheeder
Project management master class   karin rheederProject management master class   karin rheeder
Project management master class karin rheederKarin Rheeder
 
Project time management
Project time managementProject time management
Project time managementImran Jamil
 

Semelhante a Project Schedule Management - PMBOK6 (20)

Time management
Time managementTime management
Time management
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagement
 
Presintation on Project constraint
Presintation on Project constraint Presintation on Project constraint
Presintation on Project constraint
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdf
 
Day 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxDay 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptx
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
6.3 Sequence Activities
6.3 Sequence Activities6.3 Sequence Activities
6.3 Sequence Activities
 
Software project management tools
Software project management toolsSoftware project management tools
Software project management tools
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
 
2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx
 
Time management pressent
Time management pressentTime management pressent
Time management pressent
 
5. PMP Training - Time management
5. PMP Training - Time management5. PMP Training - Time management
5. PMP Training - Time management
 
Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6
 
06 project time management m
06 project time management m06 project time management m
06 project time management m
 
Project Management
Project ManagementProject Management
Project Management
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
pm--basic.pptx
pm--basic.pptxpm--basic.pptx
pm--basic.pptx
 
Project management master class karin rheeder
Project management master class   karin rheederProject management master class   karin rheeder
Project management master class karin rheeder
 
Project time management
Project time managementProject time management
Project time management
 

Último

Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insightWayne Abrahams
 
Shaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingShaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingGiuseppe De Simone
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramCIToolkit
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证jdkhjh
 
The Final Activity in Project Management
The Final Activity in Project ManagementThe Final Activity in Project Management
The Final Activity in Project ManagementCIToolkit
 
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsFrom Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsCIToolkit
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)jennyeacort
 
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsDigital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsHannah Smith
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchRashtriya Kisan Manch
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsCIToolkit
 
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentFrom Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentCIToolkit
 
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...CIToolkit
 
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Giuseppe De Simone
 
How-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionHow-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionCIToolkit
 

Último (16)

Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insight
 
Shaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingShaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful Thinking
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
 
The Final Activity in Project Management
The Final Activity in Project ManagementThe Final Activity in Project Management
The Final Activity in Project Management
 
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsFrom Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
 
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsDigital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield Metrics
 
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentFrom Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
 
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
 
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
 
How-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionHow-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem Resolution
 

Project Schedule Management - PMBOK6

  • 1. Module 6 Project Schedule Management Agus Suhanto
  • 2. Module Overview • Lesson 1: Key Concepts & Terms • Lesson 2: Plan Schedule Management • Lesson 3: Define Activities • Lesson 4: Sequence Activities • Lesson 5: Estimate Activity Duration • Lesson 6: Develop Schedule • Lesson 7: Control Schedule
  • 3. Lesson 1: Key Concepts & Terms • Project Schedule Management • Key Terms • Trends & Emerging Practices • Tailoring Considerations • Considerations for Adaptive Environment
  • 4. Project Schedule Management Project schedule management is the processes required to manage the timely completion of the project.
  • 5. Key Terms • Schedule baseline: the version of the schedule model used to manage the project; it is what the project team’s performance is measured against. • Schedule compression: a technique to shorten an already developed schedule. • Crashing: schedule compression technique by adding resources. • Fast tracking: schedule compression technique in which activities normally done in sequence are performed in parallel for at least a portion of their duration. • Activity list: list of activities to be managed in the project schedule. • Network diagram: a diagram of project activities that shows the sequential relationships of activities using arrows and nodes.
  • 6. Key Terms (continued) • Contingency (schedule) reserve: the estimated duration within the schedule baseline, which is allocated for identified risks that are accepted. • Management reserve: specified amount of the project duration (not included in baseline) withheld for management control purposes and are reserved for unforeseen work that is within the scope of the project. • Critical path: the longest duration path through a network diagram, and it determines the shortest time it could take to complete the project. • Milestone: significant events within the project schedule; not work activities and have no duration.
  • 7. Key Terms (continued) • Near critical path: closest in duration to the critical path. • Total float: the amount of time an activity can be delayed without delaying the project end date or an intermediary milestone. • Free float: the amount of time an activity can be delayed without delaying the early start date of its successor(s). • Project float: the amount of time a project can be delayed without delaying the externally imposed project completion date required by the customer.
  • 8. Key Terms (continued) • Lead: the amount of time a successor activity can be advanced with respect to a predecessor activity. • Lag: the amount of time a successor activity will be delayed with respect to a predecessor activity. • Student syndrome (procrastination): people start to apply themselves only at the last possible moment before deadline. • Parkinson’s Law: work expands to fill the time available for its completion.
  • 9. Trends & Emerging Practices • Iterative scheduling with backlog • On-demand scheduling
  • 10. Tailoring Considerations • Life cycle approach • Resource availability • Project dimensions • Technology support
  • 11. Considerations for Adaptive Environments • Adaptive approaches use short cycles to undertake work, review the results, and adapt as necessary. • To address the full delivery life cycle for larger, enterprise-wide systems, a range of techniques utilizing the predictive, adaptive, or hybrid approach may need to be adopted. • The role of project manager does not change.
  • 12. Lesson 2: Plan Schedule Management • Plan Schedule Management Overview • Plan Schedule Management Data Flow • Plan Schedule Management Input • Plan Schedule Management Tools & Technique • Plan Schedule Management Output
  • 13. Plan Schedule Management Overview Plan schedule management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
  • 15. Plan Schedule Management Input • Project charter • Project management plan • Scope management plan • Development approach • Enterprise Environmental factors • Organizational process assets
  • 16. Plan Schedule Management Tools & Techniques • Expert judgment • Data analysis • Alternative analysis • Meetings
  • 17. Plan Schedule Management Output • Project management plan • Schedule management plan • Project schedule model development • Release and iteration length • Level of accuracy • Units of measure • Organizational procedures links • Project schedule model maintenance • Control thresholds • Rules of performance measurement • Rules for establishing percent complete • EVM techniques to be employed • Schedule performance measurements • Reporting formats
  • 18. Lesson 3: Define Activities • Define Activities Overview • Define Activities Data Flow • Define Activities Input • Define Activities Tools & Techniques • Define Activities Output
  • 19. Define Activities Overview • Define activities is the process of identifying and documenting the specific actions to be performed to produce the project deliverables. • It decomposes work packages into schedule activities that provide a basis for estimating, scheduling, executing, monitoring, and controlling the project work.
  • 21. Define Activities Input • Project management plan • Scope management plan • Scope baseline • Enterprise environmental factors • Organizational process assets
  • 22. Define Activities Tools & Techniques • Decomposition • Rolling wave planning • Meetings
  • 23. Define Activities Output • Project documents • Activity list • Activity attributes • Milestone list • Change requests • Project management plan updates • Schedule baseline • Cost baseline
  • 24. Lesson 4: Sequence Activities • Sequence Activities Overview • Sequence Activities Data Flow • Sequence Activities Input • Sequence Activities Tools & Techniques • Sequence Activities Output
  • 25. Sequence Activities Overview • Sequence activities is the process of identifying and documenting relationships among the project activities. • It defines the logical sequence of work to obtain the greatest efficiency given all project constraints.
  • 27. Sequence Activities Input • Project management plan • Schedule management plan • Scope baseline • Project documents • Activity attributes • Activity list • Assumption log • Milestone list • Enterprise environmental factors • Organizational process assets
  • 28. Sequence Activities Tools & Techniques • Precedence diagramming method • Finish-to-start (FS) • Finish-to-finish (FF) • Start-to-start (SS) • Start-to-finish (SF) • Dependency determination & integration • Mandatory internal • Mandatory external • Discretionary internal • Discretionary external • Lead & Lag
  • 32. Sequence Activities Output • Project schedule network diagram • Project documents updates • Activity attributes • Activity list • Assumption log • Milestone list
  • 33. Lesson 5: Estimate Activity Duration • Estimate Activity Duration Overview • Estimate Activity Duration Data Flow • Estimate Activity Duration Input • Estimate Activity Duration Tools & Techniques • Estimate Activity Duration Output
  • 34. Estimate Activity Duration Overview Estimate activity duration is the process of estimating the number of work periods needed to complete individual activities with estimated resources.
  • 36. Estimating Duration Factors • Law of diminishing return • Number of resources • Advances in technology • Motivation of staff
  • 37. Estimate Activity Duration Input • Project management plan • Schedule management plan • Scope baseline • Project documents • Activity attributes • Activity list • Assumption log • Lessons learned register • Milestone list • Project team assignments • Resource breakdown structure • Resource calendars • Resource requirements • Risk register • Enterprise environmental factor • Organizational process access
  • 38. Estimate Activity Duration Tools & Techniques • Expert judgment • Analogous estimating • Parametric estimating • Regression analysis (scatter diagram) • Learning curve • Heuristics • Three-point estimating • Bottom-up estimating • Data analysis • Alternative analysis • Reserve analysis • Decision making • Voting • Meeting
  • 39. Three-point Estimating Formula • Triangular distribution: 𝑡𝐸 = 𝑡𝑂 + 𝑡𝑀 + 𝑡𝑃 3 • Beta distribution: 𝑡𝐸 = 𝑡𝑂 + 4 𝑡𝑀 + 𝑡𝑃 6
  • 40. Estimate Activity Duration Output • Duration estimates • Basis of estimates • Project documents updates • Activity attributes • Assumption log • Lesson learned register
  • 41. Lesson 6: Develop Schedule • Develop Schedule Overview • Develop Schedule Data Flow • Develop Schedule Input • Develop Schedule Tools & Techniques • Develop Schedule Output
  • 42. Develop Schedule Overview • Develop schedule is the process of analyzing, activity sequences, durations, resource requirements, and schedule constraints to create a schedule model for project execution and monitoring & controlling. • Key benefit: it generates a schedule model with planned dates for completing project activities.
  • 44. Develop Schedule Input • Project management plan • Schedule management plan • Scope baseline • Project documents • Activity attributes • Activity list • Assumption log • Basis of estimates • Duration estimates • Lessons learned register • Milestone list • Project schedule network diagram • Project team assignments • Resource calendars • Resource requirements • Risk register • Agreements • Enterprise environmental factors • Organizational process assets
  • 45. Develop Schedule Tools & Techniques • Schedule network analysis • Critical path method • Resource optimization • Resource leveling • Resource smoothing • Data analysis • What-if scenario • Simulation • Leads and lags • Schedule compression • Crashing • Fast tracking • Project management information system • Agile release planning
  • 47. Finding Float • Perform forward pass to define early start (ES) and early finish (EF) of each activity • Perform backward pass to define late start (LS) and late finish (LF) of each activity • Float = EF – ES or • Float = LF – LS • Critical path has 0 float.
  • 48. Develop Schedule Output • Project management plan • Schedule baseline • Project documents • Project schedule • Bar chart • Milestone chart • Project schedule network diagrams • Schedule data • Project calendars • Change requests • Project management plan updates • Schedule management plan • Cost baseline • Project documents updates • Activity attributes • Assumption log • Duration estimates • Lessons learned register • Resource requirements • Risk register
  • 49. Lesson 7: Control Schedule • Control Schedule Overview • Control Schedule Data Flow • Control Schedule Input • Control Schedule Tools & Techniques • Control Schedule Output
  • 50. Control Schedule Overview • Control schedule is the process to update the project schedule and managing changes to the schedule baseline. • The key benefit of this process is that the schedule baseline is maintained throughout the project.
  • 52. Control Schedule Input • Project management plan • Schedule management plan • Schedule baseline • Scope baseline • Performance measurement baseline • Project documents • Lessons learned register • Project calendars • Project schedules • Resource calendars • Schedule data • Work performance data • Organizational process assets
  • 53. Control Schedule Tools & Techniques • Data analysis • Earned value analysis • Iteration burndown chart • Performance reviews • Trend analysis • Variance analysis • What-if scenario analysis • Critical path method • Project management information system • Resource optimization • Leads & lags • Schedule compression
  • 54. Control Schedule Output • Work performance information • Project documents • Schedule forecasts • Change requests • Project management plan updates • Schedule management plan • Schedule baseline • Cost baseline • Performance measurement baseline • Project documents updates • Assumption log • Basis of estimates • Lessons learned register • Project schedules • Resource calendars • Risk register • Schedule data
  • 55. Quiz
  • 57. References • [PMBOK6] – The PMBOK 6th edition from pmi.org • [RITA9] – Rita Mulcahy’s PMP Exam Prep 9th edition from RMC Publications™

Notas do Editor

  1. Presentation: 80 minutes Lab: 90 minutes After completing this module, students will be able to: Describe the architectural features of Microsoft SharePoint 2016. Identify new, deprecated, and removed features in SharePoint 2016. Describe the editions for SharePoint 2016 on-premises and Microsoft SharePoint Online. Required materials To teach this module, you need the Microsoft PowerPoint file 20339-2A_01.pptx. Preparation tasks To prepare for this module: Read all of the materials for this module. Practice performing the demonstrations and labs. Work through the Module Review and Takeaways section, and determine how you will use the information to reinforce student learning and promote knowledge transfer to on-the-job performance. As you prepare for this class, it is imperative that you complete the labs yourself. This gives you an understanding of how the labs work and the concepts that each covers, so that you can provide meaningful hints to students who might have issues. Furthermore, it will help guide your lecture to ensure that you discuss the concepts that the labs cover. Ask the students to start 20339-2A-NYC-DC1-A at this point, as per step 1 of the Lab.