SlideShare a Scribd company logo
1 of 18
Case Study (1)
- Sharon
Construction
Corporation
April 16, 2013
Case situation
• Project- 200,000 seat stadium
• Start from Feb. 15, expected finish time: 1 year
• Overhead cost of $500 per week for any delay after 52 weeks
• Penalty of $15,000 per week of delay beyond next Feb. 15
• Uncertainties: Strike and Weather in December (42th weeks).
1.) Possible labor strike in Dec.:
No Strike, P=50%;
Strike:+8 weeks , P=35%; +12 weeks , P=15%
2.) Possible heating need: 33% with extra heating cost $500
per week, 67% with no heating need.
Five proposals
• 1. Expedite the pouring of seat gallery supports with extra cost
$20,000 and cut 6 weeks
• 2. The same as proposal 1, but in addition, expediting filling of
the field with extra cost $10,000 and cut 5 weeks
• 3. Expedite the roofing with extra cost $9,000 and cut 6 weeks
• 4. Do nothing until Dec. 1. If it is cold, delay the pouring or
heating; If a strike occurs, expedite all activities after strike
over with extra cost $3000 per activity per week.
• 5. Do nothing until Dec. 1.
A
clean site
B
Subsurface
drainage
C
Field &
Truck
filling
D
Turf
installation
E
Excavation
F
Pouring
concrete
footing
G
Pouring
seat
gallery
support
H
Pre cast
galleries
I
Pouring
concrete seats
J
Installing
steel
structure
K
Roof
erection
L
Building
dressing
room
M
Seat
painting
FINISH
N
Light
installation
O
Scoreboard &
facilities
Precedence Network
8
80
8
8
8
16
4
12
16
14
30
12
4
16
16
30
12
12
28
16
4
8
20 20 28
28
42
41
13
41 45
4
28
4
32
45 48
3
28
28
5
4
33
48
32
Critical Path: A E F G H I M
A
clean site
B
Subsurface
drainage
C
Field &
Truck
filling
D
Turf
installation
E
Excavation
F
Pouring
concrete
footing
G
Pouring
seat
gallery
support
H
Pre cast
galleries
I
Pouring
concrete seats
J
Installing
steel
structure
K
Roof
erection
L
Building
dressing
room
M
Seat
painting
FINISH
N
Light
installation
O
Scoreboard &
facilities
8
80
8
8
8
16
4
12
16
14
30
12
4
16
16
30
12
6
22
16
4
8
20 20 28
22
42+X
35
13
35 39
4
28
4
32
39 42+X
3
28
28
5
4
33
42+X
32
Proposal 1 Possible strike occurs in 42th week
Possible strike occurs in 42th week
Actual Cost
P(Strike) No heating
(P=67%)
Heating
(P=33%)
No strike, P=50% $20,000 $20,000
Strike +8w, P=35% $20,000 $20,000
Strike +12w, P=15% $51,000 $51,000
$20,000[Expediting cost]+(42+12-52) x
($15,000[Penalty]+$500[Overhead]) =$51,000
A
clean site
B
Subsurface
drainage
C
Field &
Truck
filling
D
Turf
installation
E
Excavation
F
Pouring
concrete
footing
G
Pouring
seat
gallery
support
H
Pre cast
galleries
I
Pouring
concrete seats
J
Installing
steel
structure
K
Roof
erection
L
Building
dressing
room
M
Seat
painting
FINISH
N
Light
installation
O
Scoreboard &
facilities
8
80
8
8
8
16
4
12
16
9
25
12
4
16
16
25
12
6
22
16
4
8
20 20 28
22
37
35
13
35 39
4
28
4
32
39 42+X
3
28
28
5
4
33
42+X
32
Proposal 2
Possible strike occurs in 42th week
Actual Cost
$30,000[Expediting cost] +(42+12-52)x
($15,000[Penalty]+$500[Overhead cost]) = $61,000
P(Strike) No heating
(P=67%)
Heating
(P=33%)
No strike, P=50% $30,000 $30,000
Strike +8w, P=35% $30,000 $30,000
Strike +12w, P=15% $61,000 $61,000
Scenario of Proposal 3
scenario
No Strike
Good weather
no heating
needed, done within 48
weeks
Bad weather, delay 4
weeks, no heating
needed, done within 52
weeks.
Bad weather, heating
needed, done within 48
weeks
Strike
+8 weeks strike, no
heating needed, done
within 56 weeks
+12 weeks strike, no
heating needed, done
within 60 weeks
A
clean site
B
Subsurface
drainage
C
Field &
Truck
filling
D
Turf
installation
E
Excavation
F
Pouring
concrete
footing
G
Pouring
seat
gallery
support
H
Pre cast
galleries
I
Pouring
concrete seats
J
Installing
steel
structure
K
Roof
erection
L
Building
dressing
room
M
Seat
painting
FINISH
N
Light
installation
O
Scoreboard &
facilities
8
80
8
8
8
16
4
12
16
14
30
12
4
16
16
30
12
12
28
16
4
2
20 20 22
28
42+X
41
13
41 45+X
4
22
4
36
45+X 48+X
3
22
22
5
4
27
48+X
26
Proposal 3 Possible strike and cold weather occur in 42th week
Possible strike and cold weather occur in 42th week
Actual Cost
P(Strike) No heating
(P=67%)
Heating
(P=33%)
No strike, P=50% $9,000 $11,000
Strike +8w, P=35% $71,000 $71,000
Strike +12w, P=15% $133,000 $133,000
$9,000[Expediting cost] +(48+12-52) x
($500[Overhead cost] + $15,000[Penalty]) =$133,000
Scenario of Proposal 4
scenario
No Strike
Good weather,
no heating
needed, done within 48
weeks
Bad weather, delay 4
weeks, no heating
needed, done within 52
weeks
Bad weather, heating
needed, done within
48 weeks
Strike
+8 weeks strike, Crash 4
weeks, no heating
needed, done within 52
weeks
+12 weeks strike, Crash
4 weeks , no heating
needed, done within 56
weeks
A
clean site
B
Subsurface
drainage
C
Field &
Truck
filling
D
Turf
installation
E
Excavation
F
Pouring
concrete
footing
G
Pouring
seat
gallery
support
H
Pre cast
galleries
I
Pouring
concrete seats
J
Installing
steel
structure
K
Roof
erection
L
Building
dressing
room
M
Seat
painting
FINISH
N
Light
installation
O
Scoreboard &
facilities
8
80
8
8
8
16
4
12
16
14
30
12
4
16
16
30
12
12
28
16
4
8
20 20 28
28
42+8
41
13
41 49+2
4-2=2
28
4
32
51 51+1
3-2=1
28
28
5
4
33
52
32
Proposal 4 Possible strike and cold weather occur in 42th week
Possible strike and cold weather occur in 42th week
Actual Cost
P(Strike) No heating
(P=67%)
Heating
(P=33%)
No strike, P=50% $0 $2,000
Strike +8w, P=35% $12,000 $12,000
Strike +12w, P=15% $74,000 $74,000
42+12
53+2
55 55+1
56
$3,000[crash cost]x4 +(56-52) x ($500[Overhead
cost] + $15,000[Penalty]) = $74,000
$3,000[ Expediting cost] x 4 weeks= $12,000
Scenario of Proposal 5
scenario
No Strike
Good weather,
no heating
needed, done within 48
weeks
Bad weather, delay 4
weeks, no heating
needed, done within 52
weeks
Bad weather, heating
needed, done within 48
weeks
Strike
+8 weeks strike,
no heating
needed, done within 56
weeks
+12 weeks strike,
no heating
needed, done within 60
weeks
A
clean site
B
Subsurface
drainage
C
Field &
Truck
filling
D
Turf
installation
E
Excavation
F
Pouring
concrete
footing
G
Pouring
seat
gallery
support
H
Pre cast
galleries
I
Pouring
concrete seats
J
Installing
steel
structure
K
Roof
erection
L
Building
dressing
room
M
Seat
painting
FINISH
N
Light
installation
O
Scoreboard &
facilities
8
80
8
8
8
16
4
12
16
14
30
12
4
16
16
30
12
12
28
16
4
8
20 20 28
28
42+X
41
13
41+X 45+X
4
28
4
32
45+X 48+X
3
28
28
5
4
33
48+X
32
Proposal 5 Possible strike and cold weather occur in 42th week
Possible strike and cold weather occur in 42th week
Actual Cost
P(Strike) No heating
(P=67%)
Heating
(P=33%)
No strike, P=50% $0 $2,000
Strike +8w, P=35% $62,000 $62,000
Strike +12w, P=15% $124,000 $124,000
(48+8-52)x ($500[Overhead
cost]+$15,000[Penalty])= $62,000
Cost Analysis
No heating Scenario (67%)
Heating needed Scenario (33%)
Probability Strike Proposal
1
Proposal
2
Proposal
3
Proposal
4
Proposal
5
No Strike- 50% $20,000 $30,000 $9,000 $0 $0
+8 weeks- 35% $20,000 $30,000 $71,000 $12,000 $62,000
+12 weeks- 15% $51,000 $61,000 $133,000 $74,000 $124,000
EMV $24,650 $34,650 $49,300 $15,300 $40,300
Probability Strike Proposal
1
Proposal
2
Proposal
3
Proposal
4
Proposal
5
No Strike- 50% $20,000 $30,000 $11,000 $2000 $2000
+8 weeks- 35% $20,000 $30,000 $71,000 $12,000 $62,000
+12 weeks- 15% $51,000 $61,000 $133,000 $74,000 $124,000
EMV $24,650 $34,650 $49,330 $15, 630 $40, 630
Recommendation
basedonCostAnalysis-EMVmethod
• Choose proposal 4
• Proposal 1 would be the second choice
Reason
• Proposal 4 has the lowest EMV, and it can end up with no
extra cost.
• Proposal 1 would be the second choice because it has
second lowest EMV and is better than 2, 3 and 5 if a
strike happens.
• If the CEO is adverse to risk, then select proposal 1
which has smaller loss range (from $20,000 to $ 51,000)
Time Analysis
Probability Strike Proposal
1
Proposal
2
Proposal
3
Proposal
4
Proposal
5
No Strike- 50% 42 42 48 48 48
+8 weeks- 35% 50 50 56 52 56
+12 weeks- 15% 54 54 60 56 60
Make span 46.6 46.6 52.6 50.6 52.6
Recommendation
basedonTimeAnalysis
• Take proposal 1
• Proposal 4 would be the second choice
Reason
• Proposal 1 & 2 has the shortest average duration, but
proposal 2 costs more.
• Proposal 4 would be the second choice because it has
second shortest average duration and is better than
proposal 1 if the cost-time ratio is considered.
• If the CEO cares time the most, then select proposal 1.
Other factors
• Behavioral – Employee morale and enthusiasm if a strike
occurs. Is this company brand oriented?
• Organizational – Will a strike and falling behind schedule lead
to layoffs or low morale? Does the sub-contractor have the
capacity to work in an expedited scenario?
• Political- Will local or state government become involved in a
labor dispute
• Financial- how urgently does the firm need cash flow? Will
early completion lead to financial benefits?
• Cultural – If labor force is mostly of the same
background, they may be more culturally or less culturally
likely to strike.
Decision making as the
president
• I will choose proposal 4.
• The first reason is obvious that it has the lowest EMV. I am a
risk seeker so I do not think the broader loss rang would be a
big problem.
• Although proposal 4 has longer duration than proposal 1
based on Time Analysis. Besides, there is no extra bonus if we
get it done earlier. For financial reason, I will choose proposal
4 for sure.

More Related Content

What's hot

Pan europa foods - Project Management
Pan europa foods - Project ManagementPan europa foods - Project Management
Pan europa foods - Project ManagementRobbi Palacios
 
4. the project in the organizational structure
4. the project in the organizational structure4. the project in the organizational structure
4. the project in the organizational structureJeanette C. Patindol
 
Project Status Report With Budget Estimation And Milestones Printable Report ...
Project Status Report With Budget Estimation And Milestones Printable Report ...Project Status Report With Budget Estimation And Milestones Printable Report ...
Project Status Report With Budget Estimation And Milestones Printable Report ...SlideTeam
 
WORKFLOW
WORKFLOW WORKFLOW
WORKFLOW TW Carl
 
Front End Engineering Design (FEED) Project Control Training
Front End Engineering Design (FEED) Project Control TrainingFront End Engineering Design (FEED) Project Control Training
Front End Engineering Design (FEED) Project Control TrainingDEVELOP
 
Pak elektron case
Pak elektron casePak elektron case
Pak elektron caseliberty00
 
Case study for project management-Triple constraints
Case study for project management-Triple constraintsCase study for project management-Triple constraints
Case study for project management-Triple constraintsminal0493
 
PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2Anand Bobade
 
The Project Management Process - Week 1
The Project Management Process -  Week 1The Project Management Process -  Week 1
The Project Management Process - Week 1Craig Brown
 
CSCMP 2014: Bayer: Putting the S Back in S&OP
CSCMP 2014: Bayer: Putting the S Back in S&OPCSCMP 2014: Bayer: Putting the S Back in S&OP
CSCMP 2014: Bayer: Putting the S Back in S&OPAlyssaVallie
 
Film Prioritization
Film PrioritizationFilm Prioritization
Film Prioritizationinga.sheikh
 
Channel Tunnel Report
Channel Tunnel ReportChannel Tunnel Report
Channel Tunnel ReportVidur Pandit
 
Ice fili done
Ice fili doneIce fili done
Ice fili donemanhawy
 
PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1Anand Bobade
 
Chunnel Project_Development Phase
Chunnel Project_Development PhaseChunnel Project_Development Phase
Chunnel Project_Development PhaseKhyati Tewari
 

What's hot (20)

Pan europa foods - Project Management
Pan europa foods - Project ManagementPan europa foods - Project Management
Pan europa foods - Project Management
 
4. the project in the organizational structure
4. the project in the organizational structure4. the project in the organizational structure
4. the project in the organizational structure
 
MidlandCase
MidlandCaseMidlandCase
MidlandCase
 
Project management-Report
Project management-ReportProject management-Report
Project management-Report
 
PMP Exam Preparation - 200 Questions
PMP Exam Preparation - 200 QuestionsPMP Exam Preparation - 200 Questions
PMP Exam Preparation - 200 Questions
 
Project Status Report With Budget Estimation And Milestones Printable Report ...
Project Status Report With Budget Estimation And Milestones Printable Report ...Project Status Report With Budget Estimation And Milestones Printable Report ...
Project Status Report With Budget Estimation And Milestones Printable Report ...
 
WORKFLOW
WORKFLOW WORKFLOW
WORKFLOW
 
Front End Engineering Design (FEED) Project Control Training
Front End Engineering Design (FEED) Project Control TrainingFront End Engineering Design (FEED) Project Control Training
Front End Engineering Design (FEED) Project Control Training
 
Pak elektron case
Pak elektron casePak elektron case
Pak elektron case
 
Case study for project management-Triple constraints
Case study for project management-Triple constraintsCase study for project management-Triple constraints
Case study for project management-Triple constraints
 
PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2
 
The Project Management Process - Week 1
The Project Management Process -  Week 1The Project Management Process -  Week 1
The Project Management Process - Week 1
 
CSCMP 2014: Bayer: Putting the S Back in S&OP
CSCMP 2014: Bayer: Putting the S Back in S&OPCSCMP 2014: Bayer: Putting the S Back in S&OP
CSCMP 2014: Bayer: Putting the S Back in S&OP
 
The chunnel project
The chunnel projectThe chunnel project
The chunnel project
 
Film Prioritization
Film PrioritizationFilm Prioritization
Film Prioritization
 
Case Dragonfly
Case DragonflyCase Dragonfly
Case Dragonfly
 
Channel Tunnel Report
Channel Tunnel ReportChannel Tunnel Report
Channel Tunnel Report
 
Ice fili done
Ice fili doneIce fili done
Ice fili done
 
PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1
 
Chunnel Project_Development Phase
Chunnel Project_Development PhaseChunnel Project_Development Phase
Chunnel Project_Development Phase
 

Similar to Sharon Construction Case Study

Stadium Project
Stadium ProjectStadium Project
Stadium Projectlakvij
 
Deep Retrofit: The Contractor's Perspective
Deep Retrofit: The Contractor's PerspectiveDeep Retrofit: The Contractor's Perspective
Deep Retrofit: The Contractor's PerspectiveSustainableEnergyAut
 
Real Estate Construction Proposal PowerPoint Presentation Slides
Real Estate Construction Proposal PowerPoint Presentation SlidesReal Estate Construction Proposal PowerPoint Presentation Slides
Real Estate Construction Proposal PowerPoint Presentation SlidesSlideTeam
 
Building and Grounds Presentation to BOF
Building and Grounds Presentation to BOFBuilding and Grounds Presentation to BOF
Building and Grounds Presentation to BOFLynn McMullin
 

Similar to Sharon Construction Case Study (7)

Shaft Construction
Shaft ConstructionShaft Construction
Shaft Construction
 
P25
P25P25
P25
 
Shaft Construction
Shaft ConstructionShaft Construction
Shaft Construction
 
Stadium Project
Stadium ProjectStadium Project
Stadium Project
 
Deep Retrofit: The Contractor's Perspective
Deep Retrofit: The Contractor's PerspectiveDeep Retrofit: The Contractor's Perspective
Deep Retrofit: The Contractor's Perspective
 
Real Estate Construction Proposal PowerPoint Presentation Slides
Real Estate Construction Proposal PowerPoint Presentation SlidesReal Estate Construction Proposal PowerPoint Presentation Slides
Real Estate Construction Proposal PowerPoint Presentation Slides
 
Building and Grounds Presentation to BOF
Building and Grounds Presentation to BOFBuilding and Grounds Presentation to BOF
Building and Grounds Presentation to BOF
 

Recently uploaded

Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...ZurliaSoop
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxVishalSingh1417
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfSherif Taha
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfPoh-Sun Goh
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxVishalSingh1417
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxDenish Jangid
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and ModificationsMJDuyan
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...christianmathematics
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...Nguyen Thanh Tu Collection
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin ClassesCeline George
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxRamakrishna Reddy Bijjam
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.MaryamAhmad92
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...Poonam Aher Patil
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSCeline George
 

Recently uploaded (20)

Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
Asian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptxAsian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptx
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 

Sharon Construction Case Study

  • 1. Case Study (1) - Sharon Construction Corporation April 16, 2013
  • 2. Case situation • Project- 200,000 seat stadium • Start from Feb. 15, expected finish time: 1 year • Overhead cost of $500 per week for any delay after 52 weeks • Penalty of $15,000 per week of delay beyond next Feb. 15 • Uncertainties: Strike and Weather in December (42th weeks). 1.) Possible labor strike in Dec.: No Strike, P=50%; Strike:+8 weeks , P=35%; +12 weeks , P=15% 2.) Possible heating need: 33% with extra heating cost $500 per week, 67% with no heating need.
  • 3. Five proposals • 1. Expedite the pouring of seat gallery supports with extra cost $20,000 and cut 6 weeks • 2. The same as proposal 1, but in addition, expediting filling of the field with extra cost $10,000 and cut 5 weeks • 3. Expedite the roofing with extra cost $9,000 and cut 6 weeks • 4. Do nothing until Dec. 1. If it is cold, delay the pouring or heating; If a strike occurs, expedite all activities after strike over with extra cost $3000 per activity per week. • 5. Do nothing until Dec. 1.
  • 4. A clean site B Subsurface drainage C Field & Truck filling D Turf installation E Excavation F Pouring concrete footing G Pouring seat gallery support H Pre cast galleries I Pouring concrete seats J Installing steel structure K Roof erection L Building dressing room M Seat painting FINISH N Light installation O Scoreboard & facilities Precedence Network 8 80 8 8 8 16 4 12 16 14 30 12 4 16 16 30 12 12 28 16 4 8 20 20 28 28 42 41 13 41 45 4 28 4 32 45 48 3 28 28 5 4 33 48 32 Critical Path: A E F G H I M
  • 5. A clean site B Subsurface drainage C Field & Truck filling D Turf installation E Excavation F Pouring concrete footing G Pouring seat gallery support H Pre cast galleries I Pouring concrete seats J Installing steel structure K Roof erection L Building dressing room M Seat painting FINISH N Light installation O Scoreboard & facilities 8 80 8 8 8 16 4 12 16 14 30 12 4 16 16 30 12 6 22 16 4 8 20 20 28 22 42+X 35 13 35 39 4 28 4 32 39 42+X 3 28 28 5 4 33 42+X 32 Proposal 1 Possible strike occurs in 42th week Possible strike occurs in 42th week Actual Cost P(Strike) No heating (P=67%) Heating (P=33%) No strike, P=50% $20,000 $20,000 Strike +8w, P=35% $20,000 $20,000 Strike +12w, P=15% $51,000 $51,000 $20,000[Expediting cost]+(42+12-52) x ($15,000[Penalty]+$500[Overhead]) =$51,000
  • 6. A clean site B Subsurface drainage C Field & Truck filling D Turf installation E Excavation F Pouring concrete footing G Pouring seat gallery support H Pre cast galleries I Pouring concrete seats J Installing steel structure K Roof erection L Building dressing room M Seat painting FINISH N Light installation O Scoreboard & facilities 8 80 8 8 8 16 4 12 16 9 25 12 4 16 16 25 12 6 22 16 4 8 20 20 28 22 37 35 13 35 39 4 28 4 32 39 42+X 3 28 28 5 4 33 42+X 32 Proposal 2 Possible strike occurs in 42th week Actual Cost $30,000[Expediting cost] +(42+12-52)x ($15,000[Penalty]+$500[Overhead cost]) = $61,000 P(Strike) No heating (P=67%) Heating (P=33%) No strike, P=50% $30,000 $30,000 Strike +8w, P=35% $30,000 $30,000 Strike +12w, P=15% $61,000 $61,000
  • 7. Scenario of Proposal 3 scenario No Strike Good weather no heating needed, done within 48 weeks Bad weather, delay 4 weeks, no heating needed, done within 52 weeks. Bad weather, heating needed, done within 48 weeks Strike +8 weeks strike, no heating needed, done within 56 weeks +12 weeks strike, no heating needed, done within 60 weeks
  • 8. A clean site B Subsurface drainage C Field & Truck filling D Turf installation E Excavation F Pouring concrete footing G Pouring seat gallery support H Pre cast galleries I Pouring concrete seats J Installing steel structure K Roof erection L Building dressing room M Seat painting FINISH N Light installation O Scoreboard & facilities 8 80 8 8 8 16 4 12 16 14 30 12 4 16 16 30 12 12 28 16 4 2 20 20 22 28 42+X 41 13 41 45+X 4 22 4 36 45+X 48+X 3 22 22 5 4 27 48+X 26 Proposal 3 Possible strike and cold weather occur in 42th week Possible strike and cold weather occur in 42th week Actual Cost P(Strike) No heating (P=67%) Heating (P=33%) No strike, P=50% $9,000 $11,000 Strike +8w, P=35% $71,000 $71,000 Strike +12w, P=15% $133,000 $133,000 $9,000[Expediting cost] +(48+12-52) x ($500[Overhead cost] + $15,000[Penalty]) =$133,000
  • 9. Scenario of Proposal 4 scenario No Strike Good weather, no heating needed, done within 48 weeks Bad weather, delay 4 weeks, no heating needed, done within 52 weeks Bad weather, heating needed, done within 48 weeks Strike +8 weeks strike, Crash 4 weeks, no heating needed, done within 52 weeks +12 weeks strike, Crash 4 weeks , no heating needed, done within 56 weeks
  • 10. A clean site B Subsurface drainage C Field & Truck filling D Turf installation E Excavation F Pouring concrete footing G Pouring seat gallery support H Pre cast galleries I Pouring concrete seats J Installing steel structure K Roof erection L Building dressing room M Seat painting FINISH N Light installation O Scoreboard & facilities 8 80 8 8 8 16 4 12 16 14 30 12 4 16 16 30 12 12 28 16 4 8 20 20 28 28 42+8 41 13 41 49+2 4-2=2 28 4 32 51 51+1 3-2=1 28 28 5 4 33 52 32 Proposal 4 Possible strike and cold weather occur in 42th week Possible strike and cold weather occur in 42th week Actual Cost P(Strike) No heating (P=67%) Heating (P=33%) No strike, P=50% $0 $2,000 Strike +8w, P=35% $12,000 $12,000 Strike +12w, P=15% $74,000 $74,000 42+12 53+2 55 55+1 56 $3,000[crash cost]x4 +(56-52) x ($500[Overhead cost] + $15,000[Penalty]) = $74,000 $3,000[ Expediting cost] x 4 weeks= $12,000
  • 11. Scenario of Proposal 5 scenario No Strike Good weather, no heating needed, done within 48 weeks Bad weather, delay 4 weeks, no heating needed, done within 52 weeks Bad weather, heating needed, done within 48 weeks Strike +8 weeks strike, no heating needed, done within 56 weeks +12 weeks strike, no heating needed, done within 60 weeks
  • 12. A clean site B Subsurface drainage C Field & Truck filling D Turf installation E Excavation F Pouring concrete footing G Pouring seat gallery support H Pre cast galleries I Pouring concrete seats J Installing steel structure K Roof erection L Building dressing room M Seat painting FINISH N Light installation O Scoreboard & facilities 8 80 8 8 8 16 4 12 16 14 30 12 4 16 16 30 12 12 28 16 4 8 20 20 28 28 42+X 41 13 41+X 45+X 4 28 4 32 45+X 48+X 3 28 28 5 4 33 48+X 32 Proposal 5 Possible strike and cold weather occur in 42th week Possible strike and cold weather occur in 42th week Actual Cost P(Strike) No heating (P=67%) Heating (P=33%) No strike, P=50% $0 $2,000 Strike +8w, P=35% $62,000 $62,000 Strike +12w, P=15% $124,000 $124,000 (48+8-52)x ($500[Overhead cost]+$15,000[Penalty])= $62,000
  • 13. Cost Analysis No heating Scenario (67%) Heating needed Scenario (33%) Probability Strike Proposal 1 Proposal 2 Proposal 3 Proposal 4 Proposal 5 No Strike- 50% $20,000 $30,000 $9,000 $0 $0 +8 weeks- 35% $20,000 $30,000 $71,000 $12,000 $62,000 +12 weeks- 15% $51,000 $61,000 $133,000 $74,000 $124,000 EMV $24,650 $34,650 $49,300 $15,300 $40,300 Probability Strike Proposal 1 Proposal 2 Proposal 3 Proposal 4 Proposal 5 No Strike- 50% $20,000 $30,000 $11,000 $2000 $2000 +8 weeks- 35% $20,000 $30,000 $71,000 $12,000 $62,000 +12 weeks- 15% $51,000 $61,000 $133,000 $74,000 $124,000 EMV $24,650 $34,650 $49,330 $15, 630 $40, 630
  • 14. Recommendation basedonCostAnalysis-EMVmethod • Choose proposal 4 • Proposal 1 would be the second choice Reason • Proposal 4 has the lowest EMV, and it can end up with no extra cost. • Proposal 1 would be the second choice because it has second lowest EMV and is better than 2, 3 and 5 if a strike happens. • If the CEO is adverse to risk, then select proposal 1 which has smaller loss range (from $20,000 to $ 51,000)
  • 15. Time Analysis Probability Strike Proposal 1 Proposal 2 Proposal 3 Proposal 4 Proposal 5 No Strike- 50% 42 42 48 48 48 +8 weeks- 35% 50 50 56 52 56 +12 weeks- 15% 54 54 60 56 60 Make span 46.6 46.6 52.6 50.6 52.6
  • 16. Recommendation basedonTimeAnalysis • Take proposal 1 • Proposal 4 would be the second choice Reason • Proposal 1 & 2 has the shortest average duration, but proposal 2 costs more. • Proposal 4 would be the second choice because it has second shortest average duration and is better than proposal 1 if the cost-time ratio is considered. • If the CEO cares time the most, then select proposal 1.
  • 17. Other factors • Behavioral – Employee morale and enthusiasm if a strike occurs. Is this company brand oriented? • Organizational – Will a strike and falling behind schedule lead to layoffs or low morale? Does the sub-contractor have the capacity to work in an expedited scenario? • Political- Will local or state government become involved in a labor dispute • Financial- how urgently does the firm need cash flow? Will early completion lead to financial benefits? • Cultural – If labor force is mostly of the same background, they may be more culturally or less culturally likely to strike.
  • 18. Decision making as the president • I will choose proposal 4. • The first reason is obvious that it has the lowest EMV. I am a risk seeker so I do not think the broader loss rang would be a big problem. • Although proposal 4 has longer duration than proposal 1 based on Time Analysis. Besides, there is no extra bonus if we get it done earlier. For financial reason, I will choose proposal 4 for sure.

Editor's Notes

  1. Expedite the pouring by paying extra $20,000 with 6 weeks deduction. Weather will not affect the activity I (pouring concrete)
  2. It is pretty much the same as the proposal 1 except adding the “field & truck filling cost” with extra $10,000.
  3. If there is no strike, let the cold weather happed without heating and delay 4 weeks, because there is no incentive to get it done earlier. It causes 4 weeks delay, so totally duration of the project is 52 which is still within 1 year.
  4. Cut six weeks of the roof erection with additional cost of $9,000. Pouring concrete would be affect by bad weather, so the extra heating cast $500/ week MIGHT happen.Lets take proposal 3 for example. If there is no strike, just delay 4 weeks and wait for the bad weather over. The total duration is still beyond 52 weeks. If there is a strike, no matter 8 weeks or 12 weeks, this strike period overlap with the bad weather forecast. Therefore, there is no need to use heating when pouring concrete.
  5. If there is no strike, let the cold weather happed without heating. It causes 4 weeks delay, so totally duration of the project is 52 which is still within 1 year.
  6. Wait for the strike over and then expedite the remaining works by cutting no less than 1/3 of its duration with extra cost $3,000/week. Cold weather and strike occur at the same timeIf there is a strike, then heating is no longer needed at all.
  7. Wait for the strike over and then expedite the remaining works by cutting no less than 1/3 of its duration with extra cost $3,000/week. Cold weather and strike occur at the same timeIf there is a strike, then heating is no longer needed at all.
  8. Based on each scenario, we generate EMV (expected money value) for each case. For proposal 1, we got EMV=$24,650 by add up fixed cost and possible extra cost. $20,000 which is the fixed cost of expediting the pouring process and ($51,000-20,000)*0.15.
  9. So based on the cost analysis EMV method, we recommend to choose Proposal 4 because it has the lowest EMV in both no heating and heating needed scenario. On the other hand, Proposal 1 would be The second choice. Not only because it has the second lowest EMV, but also smaller loss range compared to Proposal 4.
  10. And we do the Time Analysis to satisfy the question 2 ” what other basis might be used to make a decision besides expected costs?” So we do the calculation of each possible duration.As I said before, for proposal 3,4 5, there is no incentive to get the project done earlier than 52 weeks, so there are two option open (either do heating or not ) when no strike scenario.
  11. Based on the Time analysis, we recommend to choose proposal 1, for the shortest expected duration. Although Proposal 1& 2 have the same duration, proposal 1 is cheaper. On the other hand, proposal 4 would be the second choice if the cost-time ratio is considered.
  12. What other factors might enter into the decision such as behavioral, organizational, and political? Behavioral-Is my company brand oriented? For example, we have a good reputation of always being on time, we want to keep this reputation. So we might under more time pressure and then pick up the shortest duration even it costs more. Sometimes, there are many like 3~5 project doing simotaneously. They might financially sacrifice this time pressure project to finished it earlier as possible and bring more capacity to do other project and earn more money to make it up. Also for the CEO attitude like he is a risk seeker or adverse? Organizational-Do the subcontractors, or material, machine suppliers have to capacity to work in an expedited scenario? Political- will governer get involved to labor dispute? Or maybe the government want to lower down the unemplyee rate, so they change policy, like we can hire non un worker.Financial- there is no information about the financial structure in this case study, such as how does the owner pay us, monthly or at the end of the project, how would our cash flow be?. Do we have enough liquidity to expedite the project? Do we have bonus if the project is done earlier?