Project Overview
Dr. Abha Mishra
SRI-LMB
1.  Objective and purpose and
geographic location
2.  Expected results
3.  Organizational structure
4.  Major activities and time
frame
5.  work plan
6.  Coordination and governance
CONTENT
1.1 Objective and Purpose
•  Project title: Sustaining and Enhancing the
Momentum for Innovation and Learning around
the System of Rice Intensification (SRI) in the
Lower Mekong River Basin
•  Overall objective: To contribute to enhance
resilience of rainfed farmers of LMB region
confronting climate change
•  Purpose: Increased crop yield, productivity and
profitability on sustainable basis at smallholders
farmers’ field in rainfed areas of LMB region
1.2 Geographic location
Rainfed
areas of
Lower
Mekong
River Basin
2. Expected results
1.  Multi-institutional-multi-stakeholders networking developed
and strengthened from local to regional level ;
2.  Science based, pro poor profitable crop management
practices developed, demonstrated and disseminated on larger
scale in 4 LMB countries;
3.  Co-generated knowledge and learning disseminated and pro-
poor policy briefs with emphasis on women and landless developed
and shared with policy makers; and
4.  National research-extension capacity strengthened and
training capacity of farmer trainers, national trainers and local,
involved in smallholder farmer extension programme, improved
3. Organizational structure
National	
  innovation	
  
platform	
  
	
  
National	
  innovation	
  
platform	
  	
  
	
  
National	
  
Innovation	
  
platform	
  
National	
  innovation	
  
platform	
  
	
  
P
1
LIP	
  
CFPAR	
  
FPAR	
  
NIP	
  
Regional innovation
platform
Regional
innovation
platform
Regional
innovation
platform
RI
P	
  
N-S
partnership
S-S
partnership
P
2
P
3
P
1
P
3
P
2
P
1
P
2
P
1
P
2
International
collaboration
Organizational structure at country level
Government/ministries
Local
NGO
Academic
institution
PMU Office
Province 2
Dist.
2
Dist.
1
Dist.
3
Province 1
Dist.
2
Dist
. 1
Dist
. 3
Province 3
Dist.
2
Dist
. 1
Dist.
3
4. Major activities and time frame
Activities planned for the first year
Ø Establishment of project coordination unit
(Regional)
Ø  Establishment of project management unit
(National)
Ø Setting up of project website and intranet
facility
Ø  Regional inception and planning workshop
Ø  National inception and planning
workshops (4)
0-6 months
Activities plan for the first year (contd.)
Ø Participatory rural appraisal and baseline
survey
Ø  Establishment of project management
unit at local level (provincial level)
Ø  Setting up of Monitoring & Evaluation
and Impact study
Ø Planning and designing of CFPAR
6-12
months
Budget for year 1 = 459,225.00 Euros
6. Work plan
Project
cycle
Planning
and
preparation
Implement,
monitor and
report
Review,
revise and
report
PCU
LMU
PMU
ACISAI/AIT
Country Offices
of FAO IPM and
AIT in
collaboration
with Ag.
ministries
Province
offices of
Ag.
ministries
þ
Office set up and organization of
inception and regional workshops
2.1.1 Conduct Regional ToT on FPAR
Who participates: PMU Coordinators, LMU Coordinators and National
Training Assistant
Who organize and where: AIT
When: 6-9 months
2.2 Conduct Participatory Rural Appraisal (PRA)
Who: PRA expert (Sub-contractor)
Where: Provinces identified for FPAR activity
When: 7-9 months
þ
2.1 Conduct CFPAR
2.1.3 Select village and farmers, conduct baseline survey and
design CFPAR and develop curricula
Who: PMU and LMU offices (Lead: PMU Coordinators and LMU Coordinators,
Assist: National training Expert)
Where: Provinces selected for FPAR
When: 8-11 months
2.1.4 Conduct Mini ToT, field experiments, field day and
review CFPAR (Season long training)
Who: LMU and PMU member (Farmers, trainers, LMU coordinators, PMU
coordinators) with support from AIT and FAO IPM
Where: FPAR Province (one ToT/province)
When: 12-18 months
2.1 Conduct CFPAR contd.
2.2.1 1st annual national workshops/policy dialogue initiation
Who: PMU in each country
Where: Camboida, Laos, Vietnam and Thailand
When: 18-24 months
2.2.1 1st annual regional workshop
Who: AIT
Where: Laos
When: 18-24 months
2.2 Conduct workshop
3.1.1. Implement field experiments; organize mid-season
evaluation workshop and disseminate results through
farmers’ Field Day
Who: Trained Farmers
Where: Identified villages
When: 25-48 months
3.1 Conduct FPAR
3.2 Review FPAR
LMU workshop (province)
PMU workshop (Country)
PCU workshop (AIT)
4th	
  post	
  FFS	
  site	
  (2	
  FT)
3rd	
  post	
  FFS	
  site	
  (2	
  FT)
2nd	
  post	
  FFS	
  site	
  (2	
  FT)
1st	
  post	
  FFS	
  site	
  (2	
  FT)
4th	
  post	
  FFS	
  site	
  (2	
  FT)
3rd	
  post	
  FFS	
  site	
  (2	
  FT)
2nd	
  post	
  FFS	
  site	
  (2	
  FT)
1st	
  post	
  FFS	
  site	
  (2	
  FT)
4th	
  post	
  FFS	
  site	
  (2	
  FT)
3rd	
  post	
  FFS	
  site	
  (2	
  FT)
2nd	
  post	
  FFS	
  site	
  (2	
  FT)
1st	
  post	
  FFS	
  site	
  (2	
  FT)
FPAR	
  sites
FPAR	
  sites
FPAR	
  sites
Field experiments-cum-training using Farmers’ Field School
Approach
4.1 Understand the pattern of change among different
groups of farmers
Who: IDS, AIT, National academic institution
Where: LMU, PMU and PCU
When: 6 – 48 months
4.2 Conduct research for strengthen the role of women and
landless, and develop pro-poor options for policy dialogue
Who: Oxfam America
Where: LMU and PMU
When: 6-48 months
4.3 Monitoring and Review
Who: AIT
When: 6-48 months
At farmers’ level - Farmer’s diary
At researcher level – Journal publications, reports.
For policy dialogue – Policy brief (for national and for regional audience)
Time-frame: year 3 to year 5.
6.1 Develop extension materials in collaboration with ministries
based on the result of FPAR
Who: AIT
Time frame: Semester 5 – semester 10
6.2 Radio programmes to spread the result of more interesting
FPAR, banners, press release, brochure, newsletter and other
promotional items
6.3 Documentary production
6.4 Share learning with international audience through
conference/ seminar
Coordination at country level in Cambodia, Laos and Vietnam
Country offices of FAO Regional IPM Programme
(PMU office)
OthersCSO Academic
Institution
Governance – National Steering Committee
7. Coordination and governance
Coordination at regional level
PMU
Vietnam
PMU
Laos
PMU
Cambodia
PMU
Thailand
National coordination
Governance: Regional steering committee
ACISIA BOD
Ait eu-sri-project overview

More Related Content

Similar to Ait eu-sri-project overview

SRI-LMB Newsletter Vol 2. Issue 1, Year 2014
SRI-LMB Newsletter Vol 2. Issue 1, Year 2014SRI-LMB Newsletter Vol 2. Issue 1, Year 2014
SRI-LMB Newsletter Vol 2. Issue 1, Year 2014
Sri Lmb
 
Cambodia Group, AIT SRI
Cambodia Group, AIT SRICambodia Group, AIT SRI
Cambodia Group, AIT SRI
Sri Lmb
 
Cambodia Group, AIT SRI
Cambodia Group, AIT SRICambodia Group, AIT SRI
Cambodia Group, AIT SRI
Sri Lmb
 
CCARDESA progress Report - Prof T. Simalenga - GA 2014
CCARDESA progress Report - Prof T. Simalenga - GA 2014CCARDESA progress Report - Prof T. Simalenga - GA 2014
CCARDESA progress Report - Prof T. Simalenga - GA 2014
CCARDESA
 
Baseline study report 22nd August 2016
Baseline study report 22nd August 2016Baseline study report 22nd August 2016
Baseline study report 22nd August 2016
Roshan Chitrakar
 
Cn mo11 2_alt_status_and_planning_final_hessel
Cn mo11 2_alt_status_and_planning_final_hesselCn mo11 2_alt_status_and_planning_final_hessel
Cn mo11 2_alt_status_and_planning_final_hessel
Erik van den Elsen
 

Similar to Ait eu-sri-project overview (20)

SRI-LMB Newsletter Vol 2. Issue 1, Year 2014
SRI-LMB Newsletter Vol 2. Issue 1, Year 2014SRI-LMB Newsletter Vol 2. Issue 1, Year 2014
SRI-LMB Newsletter Vol 2. Issue 1, Year 2014
 
Cambodia Group, AIT SRI
Cambodia Group, AIT SRICambodia Group, AIT SRI
Cambodia Group, AIT SRI
 
Cambodia Group, AIT SRI
Cambodia Group, AIT SRICambodia Group, AIT SRI
Cambodia Group, AIT SRI
 
Pillar 2: Execution of the Implementation Plan | Lucrezia Caon, GSP Secretariat
Pillar 2: Execution of the Implementation Plan | Lucrezia Caon, GSP SecretariatPillar 2: Execution of the Implementation Plan | Lucrezia Caon, GSP Secretariat
Pillar 2: Execution of the Implementation Plan | Lucrezia Caon, GSP Secretariat
 
International Potato Center - Food Security Through Asian Roots and Tubers (F...
International Potato Center - Food Security Through Asian Roots and Tubers (F...International Potato Center - Food Security Through Asian Roots and Tubers (F...
International Potato Center - Food Security Through Asian Roots and Tubers (F...
 
Funded projects and new project proposal
Funded projects and new project proposalFunded projects and new project proposal
Funded projects and new project proposal
 
Key FPAR Learning and Draft Work Plans, Cambodia
Key FPAR Learning and Draft Work Plans, CambodiaKey FPAR Learning and Draft Work Plans, Cambodia
Key FPAR Learning and Draft Work Plans, Cambodia
 
African Soil Partnership
African Soil PartnershipAfrican Soil Partnership
African Soil Partnership
 
CCARDESA progress Report - Prof T. Simalenga - GA 2014
CCARDESA progress Report - Prof T. Simalenga - GA 2014CCARDESA progress Report - Prof T. Simalenga - GA 2014
CCARDESA progress Report - Prof T. Simalenga - GA 2014
 
Introduction to GLOSOLAN and SEALNET, the REgional SOil LAboratory Network (R...
Introduction to GLOSOLAN and SEALNET, the REgional SOil LAboratory Network (R...Introduction to GLOSOLAN and SEALNET, the REgional SOil LAboratory Network (R...
Introduction to GLOSOLAN and SEALNET, the REgional SOil LAboratory Network (R...
 
Introduction to GLOSOLAN and SEALNET, the Regional Soil Laboratory Network fo...
Introduction to GLOSOLAN and SEALNET, the Regional Soil Laboratory Network fo...Introduction to GLOSOLAN and SEALNET, the Regional Soil Laboratory Network fo...
Introduction to GLOSOLAN and SEALNET, the Regional Soil Laboratory Network fo...
 
CORD Recoup Communication Activities 2005 09
CORD Recoup Communication Activities 2005 09CORD Recoup Communication Activities 2005 09
CORD Recoup Communication Activities 2005 09
 
We are the_solution
We are the_solutionWe are the_solution
We are the_solution
 
Limpopo Experience in Water and Food-Towards Research-Policy linkages & Outco...
Limpopo Experience in Water and Food-Towards Research-Policy linkages & Outco...Limpopo Experience in Water and Food-Towards Research-Policy linkages & Outco...
Limpopo Experience in Water and Food-Towards Research-Policy linkages & Outco...
 
Pillar 2 of GSP: Encourage investment, technical cooperation, policy, educati...
Pillar 2 of GSP: Encourage investment, technical cooperation, policy, educati...Pillar 2 of GSP: Encourage investment, technical cooperation, policy, educati...
Pillar 2 of GSP: Encourage investment, technical cooperation, policy, educati...
 
Baseline study report 22nd August 2016
Baseline study report 22nd August 2016Baseline study report 22nd August 2016
Baseline study report 22nd August 2016
 
Cn mo11 2_alt_status_and_planning_final_hessel
Cn mo11 2_alt_status_and_planning_final_hesselCn mo11 2_alt_status_and_planning_final_hessel
Cn mo11 2_alt_status_and_planning_final_hessel
 
Regional scenario development and analysis: linking qualitative and quantitat...
Regional scenario development and analysis: linking qualitative and quantitat...Regional scenario development and analysis: linking qualitative and quantitat...
Regional scenario development and analysis: linking qualitative and quantitat...
 
MLN community of practice
MLN community of practiceMLN community of practice
MLN community of practice
 
Scoping visit rwanda final
Scoping visit rwanda   finalScoping visit rwanda   final
Scoping visit rwanda final
 

More from Sri Lmb

More from Sri Lmb (20)

Enamu Haque - CA Presentation for Thailand
Enamu Haque - CA Presentation for ThailandEnamu Haque - CA Presentation for Thailand
Enamu Haque - CA Presentation for Thailand
 
Hillario Padilla - SRI Plastic Mulch
Hillario Padilla - SRI Plastic Mulch Hillario Padilla - SRI Plastic Mulch
Hillario Padilla - SRI Plastic Mulch
 
Abha Mishra - MEL Study in LMB Countries
Abha Mishra - MEL Study in LMB CountriesAbha Mishra - MEL Study in LMB Countries
Abha Mishra - MEL Study in LMB Countries
 
Lucy Fisher-SRI Networks Around the World Where to Next?
Lucy Fisher-SRI Networks Around the World Where to Next?Lucy Fisher-SRI Networks Around the World Where to Next?
Lucy Fisher-SRI Networks Around the World Where to Next?
 
Hemantha Kumar Pamarthy MEL study in Laos
Hemantha Kumar Pamarthy MEL study in LaosHemantha Kumar Pamarthy MEL study in Laos
Hemantha Kumar Pamarthy MEL study in Laos
 
Bancy - SRI in Kenya and towards SRI-Africa learning network
Bancy - SRI in Kenya and towards SRI-Africa learning networkBancy - SRI in Kenya and towards SRI-Africa learning network
Bancy - SRI in Kenya and towards SRI-Africa learning network
 
Jan Willem Ketelaar - Save and Grow - Green rice Landscapes
Jan Willem Ketelaar - Save and Grow - Green rice LandscapesJan Willem Ketelaar - Save and Grow - Green rice Landscapes
Jan Willem Ketelaar - Save and Grow - Green rice Landscapes
 
P K Viswanathan - Reflection on Key Points from Day 1 and some pointers for D...
P K Viswanathan - Reflection on Key Points from Day 1 and some pointers for D...P K Viswanathan - Reflection on Key Points from Day 1 and some pointers for D...
P K Viswanathan - Reflection on Key Points from Day 1 and some pointers for D...
 
B C Barah- Upscaling Strategy for Agro-Ecological Innovations for Food Security
B C Barah- Upscaling Strategy for Agro-Ecological Innovations for Food SecurityB C Barah- Upscaling Strategy for Agro-Ecological Innovations for Food Security
B C Barah- Upscaling Strategy for Agro-Ecological Innovations for Food Security
 
A M Muazzam Husain- SRI in Bangaldesh
A M Muazzam Husain- SRI in BangaldeshA M Muazzam Husain- SRI in Bangaldesh
A M Muazzam Husain- SRI in Bangaldesh
 
Project Achievements – Key learning and Recommendations
Project Achievements – Key learning and Recommendations Project Achievements – Key learning and Recommendations
Project Achievements – Key learning and Recommendations
 
No-till crop establishment of transplanted and direct seeded rice in Conserva...
No-till crop establishment of transplanted and direct seeded rice in Conserva...No-till crop establishment of transplanted and direct seeded rice in Conserva...
No-till crop establishment of transplanted and direct seeded rice in Conserva...
 
SRI-LMB in Uttaradit Province
SRI-LMB in Uttaradit ProvinceSRI-LMB in Uttaradit Province
SRI-LMB in Uttaradit Province
 
Key Findings of the Evaluation of the SRI-LMB Project
Key Findings of the Evaluation of the SRI-LMB ProjectKey Findings of the Evaluation of the SRI-LMB Project
Key Findings of the Evaluation of the SRI-LMB Project
 
Project achievement and the “way forward” by Wijay
Project achievement and the “way forward” by WijayProject achievement and the “way forward” by Wijay
Project achievement and the “way forward” by Wijay
 
SRI-LMB in Laos by Viengxay Photakoun and Kongsy Xayavong from DTEAP, MAF Laos
SRI-LMB in Laos by Viengxay Photakoun and Kongsy Xayavong from DTEAP, MAF LaosSRI-LMB in Laos by Viengxay Photakoun and Kongsy Xayavong from DTEAP, MAF Laos
SRI-LMB in Laos by Viengxay Photakoun and Kongsy Xayavong from DTEAP, MAF Laos
 
Upscaling Strategy for Agro-Ecological  Innovations for Food Security
Upscaling Strategy for Agro-Ecological  Innovations for Food Security Upscaling Strategy for Agro-Ecological  Innovations for Food Security
Upscaling Strategy for Agro-Ecological  Innovations for Food Security
 
SRI in Surin province Thailand
SRI in Surin province ThailandSRI in Surin province Thailand
SRI in Surin province Thailand
 
Final report on SRI LMB from Vietnam
Final report on SRI LMB from Vietnam Final report on SRI LMB from Vietnam
Final report on SRI LMB from Vietnam
 
Final Workshop by Kong Kea, Project Management Unit, Cambodia
Final Workshop by Kong Kea, Project Management Unit, CambodiaFinal Workshop by Kong Kea, Project Management Unit, Cambodia
Final Workshop by Kong Kea, Project Management Unit, Cambodia
 

Recently uploaded

Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
Nauman Safdar
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
daisycvs
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
ZurliaSoop
 

Recently uploaded (20)

Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Buy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail AccountsBuy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail Accounts
 
WheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond InsightsWheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond Insights
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation Final
 
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
 
Pre Engineered Building Manufacturers Hyderabad.pptx
Pre Engineered  Building Manufacturers Hyderabad.pptxPre Engineered  Building Manufacturers Hyderabad.pptx
Pre Engineered Building Manufacturers Hyderabad.pptx
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
 
HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Durg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTS
Durg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTSDurg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTS
Durg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTS
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
 
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service AvailableNashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
 
New 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateNew 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck Template
 

Ait eu-sri-project overview

  • 2. SRI-LMB 1.  Objective and purpose and geographic location 2.  Expected results 3.  Organizational structure 4.  Major activities and time frame 5.  work plan 6.  Coordination and governance CONTENT
  • 3. 1.1 Objective and Purpose •  Project title: Sustaining and Enhancing the Momentum for Innovation and Learning around the System of Rice Intensification (SRI) in the Lower Mekong River Basin •  Overall objective: To contribute to enhance resilience of rainfed farmers of LMB region confronting climate change •  Purpose: Increased crop yield, productivity and profitability on sustainable basis at smallholders farmers’ field in rainfed areas of LMB region
  • 4. 1.2 Geographic location Rainfed areas of Lower Mekong River Basin
  • 5. 2. Expected results 1.  Multi-institutional-multi-stakeholders networking developed and strengthened from local to regional level ; 2.  Science based, pro poor profitable crop management practices developed, demonstrated and disseminated on larger scale in 4 LMB countries; 3.  Co-generated knowledge and learning disseminated and pro- poor policy briefs with emphasis on women and landless developed and shared with policy makers; and 4.  National research-extension capacity strengthened and training capacity of farmer trainers, national trainers and local, involved in smallholder farmer extension programme, improved
  • 6. 3. Organizational structure National  innovation   platform     National  innovation   platform       National   Innovation   platform   National  innovation   platform     P 1 LIP   CFPAR   FPAR   NIP   Regional innovation platform Regional innovation platform Regional innovation platform RI P   N-S partnership S-S partnership P 2 P 3 P 1 P 3 P 2 P 1 P 2 P 1 P 2 International collaboration
  • 7. Organizational structure at country level Government/ministries Local NGO Academic institution PMU Office Province 2 Dist. 2 Dist. 1 Dist. 3 Province 1 Dist. 2 Dist . 1 Dist . 3 Province 3 Dist. 2 Dist . 1 Dist. 3
  • 8. 4. Major activities and time frame
  • 9. Activities planned for the first year Ø Establishment of project coordination unit (Regional) Ø  Establishment of project management unit (National) Ø Setting up of project website and intranet facility Ø  Regional inception and planning workshop Ø  National inception and planning workshops (4) 0-6 months
  • 10. Activities plan for the first year (contd.) Ø Participatory rural appraisal and baseline survey Ø  Establishment of project management unit at local level (provincial level) Ø  Setting up of Monitoring & Evaluation and Impact study Ø Planning and designing of CFPAR 6-12 months Budget for year 1 = 459,225.00 Euros
  • 12. PCU LMU PMU ACISAI/AIT Country Offices of FAO IPM and AIT in collaboration with Ag. ministries Province offices of Ag. ministries þ Office set up and organization of inception and regional workshops
  • 13. 2.1.1 Conduct Regional ToT on FPAR Who participates: PMU Coordinators, LMU Coordinators and National Training Assistant Who organize and where: AIT When: 6-9 months 2.2 Conduct Participatory Rural Appraisal (PRA) Who: PRA expert (Sub-contractor) Where: Provinces identified for FPAR activity When: 7-9 months þ 2.1 Conduct CFPAR
  • 14. 2.1.3 Select village and farmers, conduct baseline survey and design CFPAR and develop curricula Who: PMU and LMU offices (Lead: PMU Coordinators and LMU Coordinators, Assist: National training Expert) Where: Provinces selected for FPAR When: 8-11 months 2.1.4 Conduct Mini ToT, field experiments, field day and review CFPAR (Season long training) Who: LMU and PMU member (Farmers, trainers, LMU coordinators, PMU coordinators) with support from AIT and FAO IPM Where: FPAR Province (one ToT/province) When: 12-18 months 2.1 Conduct CFPAR contd.
  • 15. 2.2.1 1st annual national workshops/policy dialogue initiation Who: PMU in each country Where: Camboida, Laos, Vietnam and Thailand When: 18-24 months 2.2.1 1st annual regional workshop Who: AIT Where: Laos When: 18-24 months 2.2 Conduct workshop
  • 16. 3.1.1. Implement field experiments; organize mid-season evaluation workshop and disseminate results through farmers’ Field Day Who: Trained Farmers Where: Identified villages When: 25-48 months 3.1 Conduct FPAR 3.2 Review FPAR LMU workshop (province) PMU workshop (Country) PCU workshop (AIT)
  • 17. 4th  post  FFS  site  (2  FT) 3rd  post  FFS  site  (2  FT) 2nd  post  FFS  site  (2  FT) 1st  post  FFS  site  (2  FT) 4th  post  FFS  site  (2  FT) 3rd  post  FFS  site  (2  FT) 2nd  post  FFS  site  (2  FT) 1st  post  FFS  site  (2  FT) 4th  post  FFS  site  (2  FT) 3rd  post  FFS  site  (2  FT) 2nd  post  FFS  site  (2  FT) 1st  post  FFS  site  (2  FT) FPAR  sites FPAR  sites FPAR  sites Field experiments-cum-training using Farmers’ Field School Approach
  • 18. 4.1 Understand the pattern of change among different groups of farmers Who: IDS, AIT, National academic institution Where: LMU, PMU and PCU When: 6 – 48 months 4.2 Conduct research for strengthen the role of women and landless, and develop pro-poor options for policy dialogue Who: Oxfam America Where: LMU and PMU When: 6-48 months 4.3 Monitoring and Review Who: AIT When: 6-48 months
  • 19. At farmers’ level - Farmer’s diary At researcher level – Journal publications, reports. For policy dialogue – Policy brief (for national and for regional audience) Time-frame: year 3 to year 5.
  • 20. 6.1 Develop extension materials in collaboration with ministries based on the result of FPAR Who: AIT Time frame: Semester 5 – semester 10 6.2 Radio programmes to spread the result of more interesting FPAR, banners, press release, brochure, newsletter and other promotional items 6.3 Documentary production 6.4 Share learning with international audience through conference/ seminar
  • 21. Coordination at country level in Cambodia, Laos and Vietnam Country offices of FAO Regional IPM Programme (PMU office) OthersCSO Academic Institution Governance – National Steering Committee 7. Coordination and governance
  • 22. Coordination at regional level PMU Vietnam PMU Laos PMU Cambodia PMU Thailand National coordination Governance: Regional steering committee ACISIA BOD