Utilization of Electrical Power [18EE742]
Beyond Syllabus
Topic: BMRCL
By:
Dr. J P Sridhar
Associate Professor
EEE Department
SJB Institute of Technology
Date: 31/10/2022
EAST – WEST CORRIDOR 18.10 KMS
NORTH-SOUTH CORRIDOR 14.90 KMS
TOTAL 33.00 KMS
ELEVATED 25.65 KMS
AT GRADE (At Ground Level) 00.65 KMS
UNDERGROUND 6.70 KMS
GAUGE Standard Gauge
TRACTION 750V dc Third Rail
SPEED Max 80Kmph ; Avg. 32Kmph
NO. OF STATIONS 32 (24 elevated, 8 UG)
TRAVEL TIME 33 / 28 Mins. (end to end)
HEAD WAY 4 Mins at start ;later 3 Mins
Namma Metro
2011 2021
Designed phpdt 31000 41000
TRAIN HEADWAY
4 Min 3 Min E-W
4 Min N-S
TRAIN COMPOSITION
6 CARS E-W
3 CARS N-S
6 CARS
COACHES 180 270
NO OF PASSENGERS
2011 10.20 LAKHS/DAY
2021 16.10 LAKHS/DAY
Projected to carry 15% of traffic
Capacity of 3 Car consist 1000 PAX
Capacity of 6 Car consist 2068 PAX
Train Operation
Coaches
Max permissible speed 80 kmph
Commercial speed 32 kmph
Coach body SS - L 20.80 m W - 2.88 m
H 3.80 m
Carrying capacity 50 seats -306 standees
(8 persons/sq.m)
Axle load 15 tonnes.
Coaches (contd)
Traction motors 4 Nos. of 180 KW / MC
Acceleration max 1.0 m /sec/sec
Deceleration max 1.1 m/sec/sec (normal)
1.3 m/sec/sec(emergency)
Additional features HVAC/ATP/ATO/PIDS/PA etc.,
Safety
1. For Operations :
• Automatic Train Protection (ATP)
• Automatic Train Operation (ATO)
• Continuous Automatic Train Control (CATC)& Cab Signaling
2. For Commuters :
• Door Closures – Plug swing type.
• Coaches with fire retarding materials, low smoke & toxicity
• Side walk way in tunnels and elevated structures for emergency evacuation
• PA system between driver and commuters in coaches
• Operations Control Centre communication with Driver
Norms and Standards for Metro Planning
Geometric Design
Min Horizontal curve Radius
- Broad gauge 200- 300 m
- Standard gauge
Elevated 90- 120 m
Under ground 200 m
Min.Vertical curve radius 1500 m
Distance between track centres
(double line) - Elevated 4.20 m
- Underground13.05 m
Clearance below Viaduct 5.50 m (min)
Norms and Standards for Metro Planning (contd)
Horizontal Curves
Between stations Desirable - 600m or more
At Station platforms Minimum - 1000 m
Depot/workshop Minimum - 120 m
Min straight between Preferable > 25 m otherwise NIL
two reverse curves
Applied cant (Ca) Maximum - 125 mm
Cant deficiency (cd) Maximum - 100mm
Cant gradient Maximum - 1in 360
Generally - 1in 720
Rate of change of ca/cd - 50 mm per second
Norms and Standards for Metro Station Planning
Planning considerations
Entrance Passageways should be kept short and direct with
min number of bends
Non-conflicting movements for incoming and out going
passengers
Forward movement wherever possible.
Ticket Counters (adequate numbers) to be provided
Columns and obstructions to be minimised
Requisite number and size of escalators and stair cases to be
provided
Minimum walking distance for pedestrians
Norms and Standards for Metro Station Planning
(contd)
Adequate width of platform based on the peak 3
minute Station load to be provided
Concourse : Paid/ Unpaid areas based on Station load
Adequate Number of ticket counters and
Ticket Issuing Machines (TIM) to be provided
Facilities for PWDs viz. Lifts. Ramps, Braille path to be
provided
Toilets for passengers
Norms and Standards for Metro Station Planning
(contd)
Platforms
Width - Depends on the Station
load.
- Min 3m for side platform
- Min 12m for island platform
Levels
a) Floor finish - 100 mm
b) Finished floor
to structural ceiling - 3600 to 4000 mm
Norms and Standards for Metro Station Planning
(contd)
Stairs and Ramps in Public areas
Height of riser (R) Minimum 150mm
Preferred 156 mm
Maximum 170 mm
Length of tread (T) Minimum 280 mm
Preferred 300 mm
Maximum 340 mm
Tread riser
combination
(2R+T)
Minimum
Maximum
600mm
640 mm
Norms and Standards for Metro Station Planning
Stairs and Ramps in Public areas (contd)
Number of risers
per flight
Maximum 15
Width of Staircase Based on
capacity
requirement
63
persons/min/
meter width
Unidirectional Absolute
Minimum
width
2000 mm
Bidirectional Absolute
minimum
width
2800 mm
Norms and Standards for Metro Station Planning
(contd)
Escalators in Public areas
Length of
intermediate landings
Minimum 2000mm
Vertical clearance
(Finished step level to
soffit of the structure)
Minimum 2700mm
Height of balustrade 1165 mm
Space after landing to
any structure
Minimum 6000 mm
Norms and Standards for Metro Station Planning
Escalators in Public areas (contd)
Angle of Inclination Max 30 degrees
Step speed 0.75 m/sec
Step width 1000 mm
Step depth (tread) 400 mm
Step rise (on incline) 210 mm (Max)
Number of flat steps for
landing at top/bottom
Four (Min)
Norms and Standard for Metro Station Planning
Escalators in Public areas (contd)
Clear Hoist way width on
passenger side
2700 mm
Vertical head room from step
nosing line to soffit of the
structure
2750 mm
Parapet wall height
surrounding
concourse/platform/
escalators at upper landing
1200 mm
Norms and Standard for Metro Station Planning
(contd)
Ticket gates
Dimension
- Length
- Width
- Height
2000 mm
270 mm
1000 mm
Modules Spacing
i.e. Gate + Space
750 mm (Min)
765 (Max)
Numbers Based on the
capacity of the
passengers they
serve.
Emergency Evacuation at stations (contd)
(a) Total evacuation time for all
passengers from plat form
Not more than 5.5
minutes
(b) Total number of passengers to
be evacuated in (crush load)
during emergency Train load
plus waiting passengers on
platform for two missed
headways.
(2068+No of passengers
waiting on the plat form)
(c) Escalators (Moving)
Emergency (stationary)
135 passengers/min/m
56 passengers/min
(d) Stair case 56 passengers/min/m
(e) Walking speed Hor : 37.8 m/min
Ver : 14.63 m/min
Standards for Fire Safety (contd)
Code followed NFPA 130 for Fixed Guide Way System.
• Emergency Evacuation time - max 5.5 mins from platform,
- max 7.5 mins from platform to streets.
• No. of exits (min) from concourse to streets - Two.
• Max. walking distance on platform to nearest stairs-30 meters.
• Fireman's stairs a must.
• Building set backs as per NBC.
• Fire retarding materials compulsory in coaches and other locations.
- Should have low fire load.
- Should have low heat release rate.
- Should have low smoke and toxicity.
• In Tunnels, use cables-Fire Retardant Low Smoke Zen Halogen type (FRLSOH).
• Emergency Trip System (ETS) at station ends.
ETS cable fire rated for one hour at 5000 C
Civil Works
Loadings
• Dead load
• Super imposed dead load
• Live load
• Footpath live load
• Wind Forces.
• Seismic forces (Seismic zone II)
• Impact forces
• Traction & Braking forces
• Long welded rail forces
• Construction loads while launching
Track Standards
Rails : 60 Kg per m UIC Head hardened.
Track : Ballastless slab with
1. Vossoloh-336 fastening system (as per DPR).
2. Long welded Track.
3. At grade lines PSC sleepers at 1540/Km
with ERC- Mark III clips and GR sole plates.
Depots : 60 kg 90 UTS indigenous rails.
Prestressed Concrete sleepers @ 1540/Km with ERC-
Mark III clips and GR sole plates.
Turn Outs : 1:7 in depots on Fan shaped PSC sleepers.
1:9 in main line-thick web switch-cast Manganese
Steel crossings with welded legs.
Ballast : 300 mm thick cushion in main lines
250 mm thick cushion in depots.
Design Life of Structures
•Civil infrastructure-Viaducts 120 yrs
- Tunnels 120 yrs
- Buildings 50 yrs
- Track 40 yrs
•Rolling Stock (Coaches) 35 yrs
•Electrical Installations 15 to 20 yrs
•Signaling & Telecom installations 15 to 20 yrs
Construction Cost
Sl. No. Particulars
Completed
Construction Cost*
Rs. Crores
1. Land 600
2. Civil Engineering Works 2593
3. Electrical Works & VAC 603
4. Signalling, Telecommunication & AFC Works 478
5. Depots 186
6. Rolling Stock 1054
7. Construction Cost 5514
8. General Charges & Contingency 398
9. Total Construction Cost 5912
10. IDC, etc., 483
11. Total 6395
Basic Cost April 2005
* Annual escalation @ 5% per annum considered at DPR prices. Project
to be commissioned in phases. Full Commissioning in 5 years from
starting construction (in Jan 2007)
Salient financial points
• Financial Internal Rate of Return (FIRR) –8.29%
• Economical Internal Rate of Return (EIRR) –22.3%
• Operating profit from the second year of operation
• Losses (incl. debt servicing, depreciation appropriation, etc.) in
the first Six years expected to be wiped out by the 12th year of
operation
Rs. Crs.
Sl.
No.
Particulars GOI TOTAL
1 EQUITY 959.25
(15%)
1918.50
(30%)
2 SUBORDINATE
DEBT
639.50
(10%)
1598.75
(25%)
3 Sub Total (1+2) 1598.75
(25%)
3527.25
(55%)
4 Senior term
Debt
2877.75
(45%)
5 Grand Total
(3+4)
6395.00
(100%)
Funding
Senior Term debt
♣JBIC funding Rs. 1795 Crs. (44 billion yen)
♣Domestic loans / ADB loan Rs. 1083 Crs.
JBIC funding for
♣Construction of underground portion – stations,
tunnels incl. ventilation and Air-conditioning
♣Installing Signalling & Telecommunication
system over the whole network.
♣Installing Automatic fare collection system
♣General Consultancy Services
Distance in kms. Fare
(Rs.)
0 to ≤ 2 6.00
2 to ≤ 6 9.00
6 to ≤ 12 11.00
12 to ≤ 18 14.00
> 18 16.00
FARE STRUCTURE (2012-13)
(at April -2005 projected cost)
Schedule
Byappanahalli-Cricket Stadium DEC 2010/
FEB 2011
Yeshwanthpur -Swastik JUN 2011
U/G Section JUN 2012
City Station– Mysore Rd AUG 2012
City Market– R.V Road SEP 2012
UNIQUE LAND PACKAGE
Rehabilitation Allowances
Residential / Commercial Properties
RESIDENTIAL
Shifting Allowance Avg. Rs. 15000/- one time payment
Inconvenience Allowance Avg. Rs. 30000/- one time payment
Transitional Allowance Rs. 75000/- one time payment
Rental Income Lost Rs. 10/- per sq. ft. lost
Right to salvage material Full
TDR As applicable
COMMERCIAL
Shifting Allowance Avg. Rs. 15000/- one time payment
Loss of Business Avg. Rs. 75000/- one time payment
Business Re-establishment Avg. Rs. 240/- per sq. ft. for area lost
Rental Income lost Rs. 20/- per sq. ft. lost
Right to salvage material Full
TDR As applicable
Integration with KSRTC, BMTC, IPTs, Railways, Airport.
Public parking to be provided at major Metro stations.
Bus bays at other stations.
Feeder bus services to be provided to all the Metro
stations.
Common ticketing for Metro & feeder buses.
Seamless Travel (contd)
YESHWANTHPUR
MAHALAKSHMI
LAYOUT
MYSORE ROAD
TERMINAL
DEEPANJALI
NAGAR
VIJAYANAGAR
HOSAHALLI
TOLL GATE
MAGADI
ROAD
CITY RLY
STATION
MAJESTIC
CENTRAL
COLLEGE
VIDHANA
SOUDHA
CRICKET
STADIUM
M G ROAD
TRINITY
CIRCLE
ULSOOR
CMH ROAD
OLD MADRAS
ROAD
B HALLI
TERMINAL
RAJAJINAGAR
KUVEMPU ROAD
MALLESWARAM
SWASTIK
CHICKPET
CITY MARKET
K R ROAD
LALBAGH
SOUTH END
CIRCLE
JAYNAGAR
R V ROAD
TERMINAL
Huge Parking Lots
PEENYA
DEPOT
JALAHALLI CROSS
ORR
PEENYA
VILLAGE
Elevated
Under Ground
At Grade
DASARAHALLI
HESARGHATTA
ROAD TERMINAL
SOAP FACTORY
Railway, KSRTC,
BMTC
KSRTC, BMTC
BMTC, MONO AT
BANASHANKARI
BMTC,
KSRTC,MONO
RAILWAYS,KSRTC,
BMTC
Seamless Travel INTEGRATION
Fare System
•Integrated ticket for Metro, Mono & Bus.
•Fare integration into a single card system.
•Smart Cards for regular users.
•Individual tickets for single time user.
METRO SUCCESS MANTRA
Easy access to station concourses from
road level-escalators
Frequency of services
Punctuality of running of trains
Affordable Fares
Immediate evacuation at metro stations
Bus bays at entrance of stations
METRO SUCCESS MANTRA (contd)
Pick and Drop facilities at stations
Seamless Streamlined Side- walks to reach metro
stations from neighbourhood
Well paved side-walks with ramps at road crossings
for 0.5 to 1km around stations on all sides.
Essential shops, stores at stations and on way to
stations so that at the end of the day, people can go
home purchasing essential needs for the next day
Grid of Metro lines