SlideShare a Scribd company logo
1 of 41
SIX MONTHS INDUSTRIAL TRAINING
UNDERTAKEN

AT
33/11 KV SUBSTATION
IN
JUBILANT LIFE SCIENCES LIMITED
Bhagwanpur ,Rookee,Haridwar
WHAT IS A SUBSTATION ?

A substation is a part of an electrical generation,
transmission, and distribution system. Substations
transform voltage from high to low, or the reverse,
or perform any of several other important
functions. Electric power may flow through several
substations between generating plant and
consumer, and its voltage may change in several
steps.
SINGLE LINE DIAGRAM
Single Line Diagrams do not show the exact
electrical connections of the circuits. As the
name suggests, SLDs use a single line to represent
all three phases. They show the relative electrical
interconnections of generators, transformers,
transmission and distribution lines, loads, circuit
breakers, etc., used in assembling the power
system. The amount of information included in
an SLD depends on the purpose for which the
diagram is used.
CONCEPT OF BUS
1. The concept of bus is Same as the
concept of a node in an electrical circuit.
2. There is one bus for each phase.
3. Shown in SLDs as lines connecting
equipment to the buses.
4. Made of aluminum or copper bars or
pipes and can be several meters long.
5. The impedance of buses is very low,
practically zero, so electrically the whole
bus is at the same potential.
EQUIPMENTS AT THE
SUBSTATION
1.MAJOR
EQUIPMENT:

POWER TRANSFORMERS

2.MEASURING
INSTRUMENTS:
A) CURRENT TRANSFORMER
B) POTENTIAL TRANSFORMER

3.PROTECTING DEVICES:
A)
B)
C)
D)

ISOLATOR
CIRCUIT BREAKER
RELAY
LIGHTNING ARRESTOR
OTHER ELEMENTS:
A)
B)
C)
D)
E)

CONDUCTORS AND CABLES
CAPACITOR BANK
CONTROL BATTRIES
BUS BARS
WAVE TRAP
POWER TRANSFORMER
The substation has the two 220/66 KV step down power transformers (100
MVA) installed made by BHEL and ABB and two 66/11 KV step down power
transformer (20 MVA) made by ECE and TA.

WHAT IS A POWER TRANSFORMER ?
Transformer is a vital link in a power system which has made possible the
power generated at low voltages (6600 to 22000 volts) to be stepped up to
extra high voltages for transmission over long distances and then
transformed to low voltages for utilization at proper load centers.
With this tool in hands it has become possible to harness the energy
resources at far off places from the load centers and connect the same
through long extra high voltage transmission lines working on high
efficiencies. At that, it may be said to be the simplest equipment with no
motive parts. Nevertheless it has its own problems associated with
insulation, dimensions and weights because of demands for ever rising
voltages and capacities.
PARTS OF THE TRANSFORMER
1. Transformer Tank
2.High Voltage Bushing
3. Low Voltage Bushing
4.Cooling Fins/Radiator
5. Cooling Fans
6. Conservator Tank
7. System Ground Terminal
8. Drain Valve
9.Dehydrating breather
10. Oil
Temperature/Pressure
gauges
11. Bushing Current
Transformers
12. Control Panel
13. Surge Arresters
2. ISOLAOTRS

It is just like a switch is
used to make sure that
an electrical circuit can
be completely deenergized for service or
maintenance.
Difference b/w Isolator
and circuit Breaker
The
major
difference
between an isolator and a
circuit breaker is that an
isolator is an off-load device
intended to be opened only
after current has been
interrupted by some other
control device.
CIRCUIT BREAKER
1.The basic functions of circuit breaker is protection, which is
interruption of short-circuit and overload fault currents.
2. High-voltage breakers are nearly always solenoid-operated, with
current sensing protective relays operated through current
transformers.
High-voltage breakers are broadly classified by the medium used to
extinguish the arc.
1.Bulk oil
2.Minimum oil
3.Air blast
4.Vacuum
5.SF6

Sulfur hexafluoride (SF6) high-voltage circuit-breakers
A sulfur hexafluoride circuit breaker uses contacts surrounded by sulfur
hexafluoride gas to quench the arc. They are most often used for
transmission-level voltages and may be incorporated into compact gasinsulated switchgear.
RELAY
A protective relay is an
electromechanical apparatus, often
with more than one coil, designed to
calculate operating conditions on an
electrical circuit and trip circuit
breakers when a fault is detected.
DISTANCE RELAY
The most common form of protection
on high voltage transmission systems is
distance relay protection. Power lines
have set impedance per km. and using
this value and comparing voltage and
current the distance to a fault can be
determined.
LIGHTNING ARRESTOR
1. A lightning arrester is a device used on electrical power systems to
protect the insulation and conductors of the system from the damaging
effects of lightning.
2. When a lightning surge travels along the power line to the arrester,
the current from the surge is diverted through the arrestor, in most
cases to earth.
CURRENT TRANSFORMER AND POTENTIAL
TRANSFORMER

1. Current transformers, together with potential transformers (PT) are
known as instrument transformers.
2. When current in a circuit is too high to
directly apply to measuring instruments,
a current transformer produces a reduced
current accurately proportional to the
current in the circuit, which can be
conveniently connected to measuring and
recording instruments.
Potential
Transformer or Voltage
Transformer are used in electrical power
system for stepping down the system
voltage to a safe value which can be fed
to low ratings meters and relays.
Commercially available relays and
meters used for protection and
metering, are designed for low voltage.
CAPACITOR BANK
A capacitor bank is a grouping of several
identical capacitors interconnected in
parallel or in series with one another.
These groups of capacitors are typically
used
to
correct
or
counteract
undesirable
characteristics,
such
as power factor lag or phase shifts
inherent in alternating current (AC)
electrical power supplies.

CONTROL BATTERIES
Generally we gave dc supply to the
all protective equipment like
relays ,indicators , and for all
controlling devices through
batteries in substation .
the
Transformer

"the heart of the alternating current system"
- William Stanley
Jr.
POWER
TRANSFORMERS
PARTS OF THE TRANSFORMER
1. Transformer Tank
2.High Voltage Bushing
3. Low Voltage Bushing
4.Cooling Fins/Radiator
5. Cooling Fans
6. Conservator Tank
7. System Ground Terminal
8. Drain Valve
9.Dehydrating breather
10. Oil
Temperature/Pressure
gauges
11. Bushing Current
Transformers
12. Control Panel
13. Surge Arresters
ļƒ˜Main components of a
transformer are:
ā€¢Magnetic core
ā€¢Primary and secondary windings
ā€¢Insulation of windings
ā€¢Expansion tank or conservator
ā€¢Tank , oil , cooling arrangement ,
temperature gauge, oil gauge
ā€¢Buchholz relay
ā€¢Silica gel breather
(1) MAGNETIC CORE
ā€¢Magnetic core consists of an iron core. The core is laminated and made of
silicon steel.
ā€¢Thickness varies from 0.35mm to 0.5mm.
ā€¢Laminations are insulated from each other by coating then with a thin coat
of varnish.
ā€¢Various types of stampings and laminations employed in the construction
of transformers.
There are two types of transformer cores ,they are
(a) Shell type (b)Core type
Shell type ā€“ Two windings are carried by central limb. Core is made up of E
and I stampings and has three limbs. Has two parallel paths for magnetic
flux.
Core type- Has two limbs for two windings and is made up of two L-type
stampings. Has only one magnetic path.
(2) Winding
ā€¢There are two windings in a transformer.
ā€¢They are primary and secondary windings.
ā€¢Made up of copper.
(3) Insulation
ā€¢Paper is still used as basic conductor insulation.
ā€¢For power transformers enamelled copper with paper insulation is also used.
(4) Insulating oil
ā€¢The coil used in transformer protects the paper from dirt and moisture and
removes the heat
produced in the core and coils,
ā€¢It also acts as insulating medium.
Oil must possess following properties:
ā€¢High dielectric strength
ā€¢Free from inorganic acid , alkali and corrosive sulphur.
ā€¢Low viscosity to provide good heat transfer.
ā€¢ Good resistance to emulsion so that the oil may throw down any moisture entering
the tank
instead of holding it.
(5)EXPANSION TANK or Conservator
ā€¢A small auxiliary oil tank mounted above
the
transformer and connected to main tank by a
pipe.
ā€¢Its function is to keep transformer tank full
of oil.
(6)TEMPERATURE GAUGE
ā€¢Is to indicate hot oil or hottest spot temperature.
ā€¢It is self contained weather proof unit made of
alarm contacts.
(7) OIL GAUGE
ā€¢Every transformer is fitted with an oil gauge to indicate
the oil level
present inside the tank.
ā€¢It is provided with an alarm contact which gives an
alarm when the
oil level drops beyond permissible height due to oil leak
or due to any
other reason.

(8) BUCHHOLZ RELAY
ā€¢First warning that fault is present is given by
presence of bubbles in oil.
ā€¢It gives an alarm in case of minor fault and to
disconnect transformer
From the supply mains in case of severe faults.
(9) Breather
ā€¢It is a chamber which prevents entry of moisture
inside the transformer tank.
ā€¢It is filled with drying agent such as calcium chloride or silica gel.
ā€¢This absorbs moisture and allows dry air to enter transformer tank. It
is replaced regularly.
CLASSIFICATION OF TRANSFORMERS
ļƒ˜Transformers are classified on basis of
1.Duty they perform
2.Construction
3.Voltage output
4.Application
5.Cooling
6.Input supply
ļƒ˜Duty they perform
I.Power transformer ā€“ from transmission and distribution
II.Current transformer- instrument transformers
III.Potential transformer- instrument transformers
ļƒ˜Construction
I.Core type transformer
II.Shell type transformer
III.Berry type transformer
ļƒ˜Voltage output
I.Step down transformer(Higher to Lower)
II.Step up transformer(Lower to Higher)
III.Auto transformer(Variable from ā€˜0ā€™ to rated value)
ļƒ˜Application
I.Welding transformer
II.Furnace transformer
ļƒ˜Cooling
I.Duct type transformer
II.Oil immersed transformer
self cooled
Forced air cooled
Water cooled
Forced oil cooled
ļƒ˜Input supply
I.Single phase transformer
II.Three phase transformer
star- star
Star-delta
Delta-delta

Delta-Star
Open- Delta
Scott connection
EMF EQUATION OF TRANSFORMER
Wkt, T=1/f
Average emf (e)= dĪ¦/dt
dĪ¦ = Ī¦m
dt = 1/4f
Average rate of change of flux= Ī¦m / (1/4f) = 4f Ī¦m volts
Average emf induced per turn = Average rate of change of flux= 4f Ī¦m
volts
Form factor = RMS value/ Average value = 1.11
RMS value= Form factor x Average value
=1.11 x Average value
RMS value of emf induced/turn = 1.11 x 4f Ī¦m = 4.44 f Ī¦m volts
Primary and Secondary winding having N1 and N2 turns.
RMS value of emf induced Primary winding, E1 = 4.44 f Ī¦m N1 volts
RMS value of emf induced Secondary winding, E1 = 4.44 f Ī¦m N2 volts
TRANSFORMER RATIO
For an ideal transformer, E1 = V1 and E2 = V2
There is no voltage drop in the windings.
V1 I1 = V2 I2
V2 / V1 = E2 / E1 = I1 / I2 = N2 / N1 = K
V2 / V1 = K -> Voltage ratio
E2 / E1 = K -> Transformation ratio
N2 / N1 = K -> Turns ratio
I1 / I2 = K -> Current ratio
(i)If K > 1 , then the transformer is called step-up transformer.
(ii) If K < 1 , then the transformer is called step-down transformer.
RATING OF TRANSFORMER
ā€¢The rating of transformer is expressed by Volt- Ampere (VA)
ā€¢Cu loss depends on Current (A)
ā€¢Iron loss depends on Voltage (V)
ā€¢Total loss depends upon Volt- Ampere (VA)
ā€¢It is independent of Load power factor cos Ī¦.
Ideal transformer
Ideal transformer has following properties :
ā€¢No winding resistance i.e., purely inductive
ā€¢No magnetic leakage flux
ā€¢No cu loss
ā€¢No core loss
ā€¢Ideal transformer secondary is open. Ac supply is connected to primary
winding. Current flows through primary winding. This current is called
MAGNETISING CURRENT (IĪ¼).
ā€¢Value of Magnetising current is small. The Magnetising current produces an
alternating flux (Ī¦).
ā€¢IĪ¼ and Ī¦ are in-phase. This changing flux links primary with secondary
winding.
ā€¢Due to alternating flux a self-induced emf (E1) is produced in primary
winding which is equal to and in opposition with V1. It is known as counter
emf or back emf of primary winding.
ā€¢Induced emf E2 is produced in secondary winding because of alternating flux
linking with secondary winding. This emf is known as mutually induced emf.
PRACTICAL TRANSFORMER ON NOLOAD
If the primary winding is connected to alternating voltage and
secondary winding is left open then transformer is said to be on NOLOAD. Since secondary is open this current is called no-load primary
current (Io).
No load input power, P0= V1 I0 cos Ī¦0
Active or working or iron loss or wattful component (Iw) which is inphase with ā€˜V1ā€™ and supplies iron loss and small amount of primary cu
loss.
Iw = I0 cos Ī¦0
Where, cos Ī¦0 is no load power factor.
Reactive or magnetizing or wattles component IĪ¼
which is in quadrature with V1 and its function is to sustain flux in core.
IĪ¼= I0 Sin Ī¦0
TRANSFORMER ON LOAD
When the secondary winding is connected to load then the transformer
is said to be on load.
Phase angle between V2 and I2 depends on type of load.
Resistive = I2 in-phase with V2
Load Inductive = I2 will lag V2
capacitive= I2 will lead V2
When transformer is loaded,
ļƒ˜Flux is constant at no-load as well as at loaded condition, therefore
transformer is called as constant flux apparatus.
ļƒ˜Total primary current will be vector sum of I0 and I2ā€™
ļƒ˜Transformer winding resistance
In practical transformer the winding have some resistances. Primary winding has
primary resistance(R2).

Transformer winding leakage reactance
Primary leakage flux(Ī¦L1) ā€“ All the flux generated by the
primary winding does not link with secondary winding. Some part of flux passes
through air rather than around the core. This flux is in-phase with I1.
Secondary leakage flux(Ī¦L2) ā€“ Leakage flux is set up in
secondary winding. This flux induces eL2 in secondary winding. This flux Ī¦L2 does
not link with primary is also in-phase with I2.
ļƒ˜OPEN CIRCUIT / NO-LOAD TEST ON TRANSFORMER
PURPOSE OF THIS TEST IS TO DETERMINE
ā€¢Core loss or Iron loss Or Magnetic loss (Pi)
ā€¢No load current (I0)
ā€¢Shunt branch parameters R0 and X0
ļƒ˜One of the winding is kept open.
ā€¢Rated voltage at rated frequency is applied to other(LV) winding.
ā€¢A voltmeter, wattmeter, and an ammeter are connected in LV side of the
transformer.
ļƒ¼Ammeter > Reads No-Load Current, I0
ļƒ¼Voltmeter > Reads Applied Voltage, V0
ļƒ¼Wattmeter> Reads No-Load Input Power, W0 or P0
DETERMINATION OF EQUIVALENT CIRCUIT CONSTANTS
THROUGH NO- LOAD TEST
No load power factor, CosĪ¦0 = W0 / V0 I0
Core loss component, Iw = I0 CosĪ¦0
Magnetising component, Im = I0 SinĪ¦0
Core Loss, Pi = No load power (W0)
Core loss resistance, R0 = V0 / Iw = V0 / I0 CosĪ¦0
Magnetising reactance, X0= V0 / Im = V0 / I0 SinĪ¦0
ļƒ˜SHORT CIRCUIT / IMPEDANCE TEST ON
TRANSFORMER
PURPOSE OF THIS TEST IS TO DETERMINE
ā€¢Z01 or Z02 ā€“ Total impedance referred to either primary or secondary side
ā€¢R01 or R02- Total resistance referred to either primary or secondary side
ā€¢X01 or X02- Total reactance referred to either primary or secondary side
ā€¢Full load cu loss I22 R02
ļ¶In this test one of the winding is short circuited by thick conductor.
ļ¶Current rating of HV side is low compared with LV side.
ļ¶Power input gives total cu loss at rated load.
ļ¶Unity power factor wattmeter is used for measuring power in SC test.
DETERMINATION OF EQUIVALENT CIRCUIT CONSTANTS THROUGH
LOAD TEST

ļƒ˜SC power factor, CosĪ¦sc = Wsc / Vsc Isc
ļƒ˜Resistance of transformer referred to primary side , R01 =
Wsc / (Isc)2
ļƒ˜Impedance of transformer referred to primary side, Z01 =
Z01 Cos Ī¦sc= Vsc / Isc
Presentation training

More Related Content

What's hot

Madan mohan malaviya
Madan mohan malaviyaMadan mohan malaviya
Madan mohan malaviyaAnuj Bansal
Ā 
Electrical Grid Substation
Electrical Grid SubstationElectrical Grid Substation
Electrical Grid SubstationAng Sovann
Ā 
Installation Operation & Maintenance of 33kV & 11kV Switchgear
Installation   Operation & Maintenance of 33kV & 11kV SwitchgearInstallation   Operation & Maintenance of 33kV & 11kV Switchgear
Installation Operation & Maintenance of 33kV & 11kV SwitchgearSheikh Nazmul Islam
Ā 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear johny renoald
Ā 
132kv substation inplant training seminar
132kv substation inplant training seminar132kv substation inplant training seminar
132kv substation inplant training seminarShrikant Bhansali
Ā 
Unit 06 - Substation and maintenance
Unit 06 - Substation and maintenanceUnit 06 - Substation and maintenance
Unit 06 - Substation and maintenancePremanandDesai
Ā 
Switchgear Equipment in a Substation
Switchgear Equipment in a SubstationSwitchgear Equipment in a Substation
Switchgear Equipment in a SubstationMd. Atiqur Rahman
Ā 
Ppt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipurPpt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipurkishankky
Ā 
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATIONPPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATIONSwatantra SwAt
Ā 
Tan delta test for power transformers
Tan delta test for power transformersTan delta test for power transformers
Tan delta test for power transformersjibinjoy1988
Ā 
Protection of transmission lines (distance)
Protection of transmission lines (distance)Protection of transmission lines (distance)
Protection of transmission lines (distance)Rohini Haridas
Ā 
Switchgear Installation Precomissioning Inspection.PPT
Switchgear Installation  Precomissioning Inspection.PPTSwitchgear Installation  Precomissioning Inspection.PPT
Switchgear Installation Precomissioning Inspection.PPTAbdullah Al Dushaishi
Ā 
Substation Maintenance
Substation MaintenanceSubstation Maintenance
Substation Maintenancekarikalan123
Ā 
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)J. FR
Ā 
SF6 CIRCUIT BREAKER
SF6 CIRCUIT BREAKERSF6 CIRCUIT BREAKER
SF6 CIRCUIT BREAKERsssspp
Ā 
Capacitive voltage transformer (1)
Capacitive voltage transformer (1)Capacitive voltage transformer (1)
Capacitive voltage transformer (1)kaushal boghani
Ā 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformerSMRITI KESHARWANI
Ā 
400kv-Substation-Training-report-Unnao-India.ppt
400kv-Substation-Training-report-Unnao-India.ppt400kv-Substation-Training-report-Unnao-India.ppt
400kv-Substation-Training-report-Unnao-India.pptMarcWorld
Ā 

What's hot (20)

Madan mohan malaviya
Madan mohan malaviyaMadan mohan malaviya
Madan mohan malaviya
Ā 
Electrical Grid Substation
Electrical Grid SubstationElectrical Grid Substation
Electrical Grid Substation
Ā 
Protection and Switchgear
Protection and SwitchgearProtection and Switchgear
Protection and Switchgear
Ā 
Installation Operation & Maintenance of 33kV & 11kV Switchgear
Installation   Operation & Maintenance of 33kV & 11kV SwitchgearInstallation   Operation & Maintenance of 33kV & 11kV Switchgear
Installation Operation & Maintenance of 33kV & 11kV Switchgear
Ā 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
Ā 
132kV GSS ppt
132kV GSS ppt132kV GSS ppt
132kV GSS ppt
Ā 
132kv substation inplant training seminar
132kv substation inplant training seminar132kv substation inplant training seminar
132kv substation inplant training seminar
Ā 
Unit 06 - Substation and maintenance
Unit 06 - Substation and maintenanceUnit 06 - Substation and maintenance
Unit 06 - Substation and maintenance
Ā 
Switchgear Equipment in a Substation
Switchgear Equipment in a SubstationSwitchgear Equipment in a Substation
Switchgear Equipment in a Substation
Ā 
Ppt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipurPpt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipur
Ā 
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATIONPPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
Ā 
Tan delta test for power transformers
Tan delta test for power transformersTan delta test for power transformers
Tan delta test for power transformers
Ā 
Protection of transmission lines (distance)
Protection of transmission lines (distance)Protection of transmission lines (distance)
Protection of transmission lines (distance)
Ā 
Switchgear Installation Precomissioning Inspection.PPT
Switchgear Installation  Precomissioning Inspection.PPTSwitchgear Installation  Precomissioning Inspection.PPT
Switchgear Installation Precomissioning Inspection.PPT
Ā 
Substation Maintenance
Substation MaintenanceSubstation Maintenance
Substation Maintenance
Ā 
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
Ā 
SF6 CIRCUIT BREAKER
SF6 CIRCUIT BREAKERSF6 CIRCUIT BREAKER
SF6 CIRCUIT BREAKER
Ā 
Capacitive voltage transformer (1)
Capacitive voltage transformer (1)Capacitive voltage transformer (1)
Capacitive voltage transformer (1)
Ā 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
Ā 
400kv-Substation-Training-report-Unnao-India.ppt
400kv-Substation-Training-report-Unnao-India.ppt400kv-Substation-Training-report-Unnao-India.ppt
400kv-Substation-Training-report-Unnao-India.ppt
Ā 

Viewers also liked

Training from 220kv GSS Sanganer, which is located on Muhana Road, Jaipur
Training from 220kv GSS Sanganer, which is located on Muhana Road, JaipurTraining from 220kv GSS Sanganer, which is located on Muhana Road, Jaipur
Training from 220kv GSS Sanganer, which is located on Muhana Road, JaipurR-One Power
Ā 
33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)Prateek Agarwal
Ā 
Typical layout of a Sub-Station
Typical layout of a Sub-StationTypical layout of a Sub-Station
Typical layout of a Sub-StationTowfiqur Rahman
Ā 
Power factor correction
Power factor correctionPower factor correction
Power factor correctionAbdur rehman
Ā 
Power Quality Systems and Power Factor Correction Presentation
Power Quality Systems and Power Factor Correction PresentationPower Quality Systems and Power Factor Correction Presentation
Power Quality Systems and Power Factor Correction PresentationMircea Gingu
Ā 
Kamal final presentation eee reb- comilla
Kamal final presentation eee  reb- comillaKamal final presentation eee  reb- comilla
Kamal final presentation eee reb- comillasiam hossain
Ā 
Mit ppt 132/33kv ppt
Mit ppt 132/33kv pptMit ppt 132/33kv ppt
Mit ppt 132/33kv pptMithilesh Kumar
Ā 
The transformer
The transformerThe transformer
The transformerSrajan Raj
Ā 
132KV SUBSTATION UPPTCL
132KV SUBSTATION UPPTCL132KV SUBSTATION UPPTCL
132KV SUBSTATION UPPTCLAman Rajput
Ā 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentationRajashekar Gurrala
Ā 
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, AllahabadSummer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, AllahabadSudhir Cement Industries Pvt. Ltd. Meerut
Ā 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentationKamal Mittal
Ā 
132kv Substation
132kv Substation132kv Substation
132kv Substationguestecdd58
Ā 
PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substationIshank Ranjan
Ā 
Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV Girish Gupta
Ā 
Substation overview
Substation overviewSubstation overview
Substation overviewBHAGWAN PRASAD
Ā 

Viewers also liked (16)

Training from 220kv GSS Sanganer, which is located on Muhana Road, Jaipur
Training from 220kv GSS Sanganer, which is located on Muhana Road, JaipurTraining from 220kv GSS Sanganer, which is located on Muhana Road, Jaipur
Training from 220kv GSS Sanganer, which is located on Muhana Road, Jaipur
Ā 
33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)
Ā 
Typical layout of a Sub-Station
Typical layout of a Sub-StationTypical layout of a Sub-Station
Typical layout of a Sub-Station
Ā 
Power factor correction
Power factor correctionPower factor correction
Power factor correction
Ā 
Power Quality Systems and Power Factor Correction Presentation
Power Quality Systems and Power Factor Correction PresentationPower Quality Systems and Power Factor Correction Presentation
Power Quality Systems and Power Factor Correction Presentation
Ā 
Kamal final presentation eee reb- comilla
Kamal final presentation eee  reb- comillaKamal final presentation eee  reb- comilla
Kamal final presentation eee reb- comilla
Ā 
Mit ppt 132/33kv ppt
Mit ppt 132/33kv pptMit ppt 132/33kv ppt
Mit ppt 132/33kv ppt
Ā 
The transformer
The transformerThe transformer
The transformer
Ā 
132KV SUBSTATION UPPTCL
132KV SUBSTATION UPPTCL132KV SUBSTATION UPPTCL
132KV SUBSTATION UPPTCL
Ā 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentation
Ā 
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, AllahabadSummer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Ā 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentation
Ā 
132kv Substation
132kv Substation132kv Substation
132kv Substation
Ā 
PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substation
Ā 
Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV
Ā 
Substation overview
Substation overviewSubstation overview
Substation overview
Ā 

Similar to Presentation training

Ppt on 132 kv gss by ashok khoja
Ppt on  132 kv gss  by ashok khojaPpt on  132 kv gss  by ashok khoja
Ppt on 132 kv gss by ashok khojaASHOK KHOJA
Ā 
rough.pptx
rough.pptxrough.pptx
rough.pptxvirat217995
Ā 
vishal-170827171239 (1).pdf
vishal-170827171239 (1).pdfvishal-170827171239 (1).pdf
vishal-170827171239 (1).pdfSunnyYadav735981
Ā 
the substation components study
the substation components study the substation components study
the substation components study Krishnaveni Reddy
Ā 
132 KV Substation Gajraula.pptx
132 KV Substation Gajraula.pptx132 KV Substation Gajraula.pptx
132 KV Substation Gajraula.pptxAsif682330
Ā 
Anurag Attri.pptx
Anurag Attri.pptxAnurag Attri.pptx
Anurag Attri.pptxAsif682330
Ā 
Gss ppt by kanhaiya
Gss ppt  by kanhaiyaGss ppt  by kanhaiya
Gss ppt by kanhaiyaimkanhaiyalal
Ā 
ntpc ppt
ntpc pptntpc ppt
ntpc pptJatan Soni
Ā 
132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training report132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training reportMuntazir Mehdi
Ā 
132 gss ppt
132 gss ppt132 gss ppt
132 gss ppthunk143
Ā 
LV switchgear FINAL.pptx
LV switchgear FINAL.pptxLV switchgear FINAL.pptx
LV switchgear FINAL.pptxRanjanKumar17478
Ā 
Design of substation
Design of substationDesign of substation
Design of substationSayanSarkar55
Ā 
220kvgss-180808104033 (1).pdf
220kvgss-180808104033 (1).pdf220kvgss-180808104033 (1).pdf
220kvgss-180808104033 (1).pdfSinghJi18
Ā 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at JassureShuvam Pathania
Ā 
220kv gss pindwara(sirohi)
220kv gss pindwara(sirohi)220kv gss pindwara(sirohi)
220kv gss pindwara(sirohi)Pankaj Rawal
Ā 

Similar to Presentation training (20)

Ppt on 132 kv gss by ashok khoja
Ppt on  132 kv gss  by ashok khojaPpt on  132 kv gss  by ashok khoja
Ppt on 132 kv gss by ashok khoja
Ā 
Ashish.pptx
Ashish.pptxAshish.pptx
Ashish.pptx
Ā 
rough.pptx
rough.pptxrough.pptx
rough.pptx
Ā 
vishal-170827171239 (1).pdf
vishal-170827171239 (1).pdfvishal-170827171239 (1).pdf
vishal-170827171239 (1).pdf
Ā 
the substation components study
the substation components study the substation components study
the substation components study
Ā 
132 KV Substation Gajraula.pptx
132 KV Substation Gajraula.pptx132 KV Substation Gajraula.pptx
132 KV Substation Gajraula.pptx
Ā 
Anurag Attri.pptx
Anurag Attri.pptxAnurag Attri.pptx
Anurag Attri.pptx
Ā 
Gss ppt by kanhaiya
Gss ppt  by kanhaiyaGss ppt  by kanhaiya
Gss ppt by kanhaiya
Ā 
ntpc ppt
ntpc pptntpc ppt
ntpc ppt
Ā 
132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training report132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training report
Ā 
Ashwani kumar
Ashwani kumarAshwani kumar
Ashwani kumar
Ā 
132 gss ppt
132 gss ppt132 gss ppt
132 gss ppt
Ā 
LV switchgear FINAL.pptx
LV switchgear FINAL.pptxLV switchgear FINAL.pptx
LV switchgear FINAL.pptx
Ā 
PDFen (1).pdf
PDFen (1).pdfPDFen (1).pdf
PDFen (1).pdf
Ā 
Design of substation
Design of substationDesign of substation
Design of substation
Ā 
220 kv gss
220 kv gss220 kv gss
220 kv gss
Ā 
Chic export company_catalogue
Chic export company_catalogueChic export company_catalogue
Chic export company_catalogue
Ā 
220kvgss-180808104033 (1).pdf
220kvgss-180808104033 (1).pdf220kvgss-180808104033 (1).pdf
220kvgss-180808104033 (1).pdf
Ā 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at Jassure
Ā 
220kv gss pindwara(sirohi)
220kv gss pindwara(sirohi)220kv gss pindwara(sirohi)
220kv gss pindwara(sirohi)
Ā 

Recently uploaded

Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
Ā 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
Ā 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
Ā 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
Ā 
VIP Call Girls In Saharaganj ( Lucknow ) šŸ” 8923113531 šŸ” Cash Payment (COD) šŸ‘’
VIP Call Girls In Saharaganj ( Lucknow  ) šŸ” 8923113531 šŸ”  Cash Payment (COD) šŸ‘’VIP Call Girls In Saharaganj ( Lucknow  ) šŸ” 8923113531 šŸ”  Cash Payment (COD) šŸ‘’
VIP Call Girls In Saharaganj ( Lucknow ) šŸ” 8923113531 šŸ” Cash Payment (COD) šŸ‘’anilsa9823
Ā 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
Ā 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
Ā 
Call Girls Jp Nagar Just Call šŸ‘— 7737669865 šŸ‘— Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call šŸ‘— 7737669865 šŸ‘— Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call šŸ‘— 7737669865 šŸ‘— Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call šŸ‘— 7737669865 šŸ‘— Top Class Call Girl Service Bang...amitlee9823
Ā 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
Ā 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
Ā 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
Ā 
Russian Call Girls In Gurgaon ā¤ļø8448577510 āŠ¹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ā¤ļø8448577510 āŠ¹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ā¤ļø8448577510 āŠ¹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ā¤ļø8448577510 āŠ¹Best Escorts Service In 24/7 Delh...lizamodels9
Ā 
Call Girls Hebbal Just Call šŸ‘— 7737669865 šŸ‘— Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call šŸ‘— 7737669865 šŸ‘— Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call šŸ‘— 7737669865 šŸ‘— Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call šŸ‘— 7737669865 šŸ‘— Top Class Call Girl Service Bangaloreamitlee9823
Ā 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsMichael W. Hawkins
Ā 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
Ā 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
Ā 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
Ā 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
Ā 

Recently uploaded (20)

Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
Ā 
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pillsMifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Ā 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
Ā 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ā 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
Ā 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
Ā 
VIP Call Girls In Saharaganj ( Lucknow ) šŸ” 8923113531 šŸ” Cash Payment (COD) šŸ‘’
VIP Call Girls In Saharaganj ( Lucknow  ) šŸ” 8923113531 šŸ”  Cash Payment (COD) šŸ‘’VIP Call Girls In Saharaganj ( Lucknow  ) šŸ” 8923113531 šŸ”  Cash Payment (COD) šŸ‘’
VIP Call Girls In Saharaganj ( Lucknow ) šŸ” 8923113531 šŸ” Cash Payment (COD) šŸ‘’
Ā 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Ā 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
Ā 
Call Girls Jp Nagar Just Call šŸ‘— 7737669865 šŸ‘— Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call šŸ‘— 7737669865 šŸ‘— Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call šŸ‘— 7737669865 šŸ‘— Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call šŸ‘— 7737669865 šŸ‘— Top Class Call Girl Service Bang...
Ā 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
Ā 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
Ā 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
Ā 
Russian Call Girls In Gurgaon ā¤ļø8448577510 āŠ¹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ā¤ļø8448577510 āŠ¹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ā¤ļø8448577510 āŠ¹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ā¤ļø8448577510 āŠ¹Best Escorts Service In 24/7 Delh...
Ā 
Call Girls Hebbal Just Call šŸ‘— 7737669865 šŸ‘— Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call šŸ‘— 7737669865 šŸ‘— Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call šŸ‘— 7737669865 šŸ‘— Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call šŸ‘— 7737669865 šŸ‘— Top Class Call Girl Service Bangalore
Ā 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael Hawkins
Ā 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
Ā 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
Ā 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
Ā 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
Ā 

Presentation training

  • 1. SIX MONTHS INDUSTRIAL TRAINING UNDERTAKEN AT 33/11 KV SUBSTATION IN JUBILANT LIFE SCIENCES LIMITED Bhagwanpur ,Rookee,Haridwar
  • 2. WHAT IS A SUBSTATION ? A substation is a part of an electrical generation, transmission, and distribution system. Substations transform voltage from high to low, or the reverse, or perform any of several other important functions. Electric power may flow through several substations between generating plant and consumer, and its voltage may change in several steps.
  • 3. SINGLE LINE DIAGRAM Single Line Diagrams do not show the exact electrical connections of the circuits. As the name suggests, SLDs use a single line to represent all three phases. They show the relative electrical interconnections of generators, transformers, transmission and distribution lines, loads, circuit breakers, etc., used in assembling the power system. The amount of information included in an SLD depends on the purpose for which the diagram is used.
  • 4.
  • 5. CONCEPT OF BUS 1. The concept of bus is Same as the concept of a node in an electrical circuit. 2. There is one bus for each phase. 3. Shown in SLDs as lines connecting equipment to the buses. 4. Made of aluminum or copper bars or pipes and can be several meters long. 5. The impedance of buses is very low, practically zero, so electrically the whole bus is at the same potential.
  • 6. EQUIPMENTS AT THE SUBSTATION 1.MAJOR EQUIPMENT: POWER TRANSFORMERS 2.MEASURING INSTRUMENTS: A) CURRENT TRANSFORMER B) POTENTIAL TRANSFORMER 3.PROTECTING DEVICES: A) B) C) D) ISOLATOR CIRCUIT BREAKER RELAY LIGHTNING ARRESTOR
  • 7. OTHER ELEMENTS: A) B) C) D) E) CONDUCTORS AND CABLES CAPACITOR BANK CONTROL BATTRIES BUS BARS WAVE TRAP
  • 8. POWER TRANSFORMER The substation has the two 220/66 KV step down power transformers (100 MVA) installed made by BHEL and ABB and two 66/11 KV step down power transformer (20 MVA) made by ECE and TA. WHAT IS A POWER TRANSFORMER ? Transformer is a vital link in a power system which has made possible the power generated at low voltages (6600 to 22000 volts) to be stepped up to extra high voltages for transmission over long distances and then transformed to low voltages for utilization at proper load centers. With this tool in hands it has become possible to harness the energy resources at far off places from the load centers and connect the same through long extra high voltage transmission lines working on high efficiencies. At that, it may be said to be the simplest equipment with no motive parts. Nevertheless it has its own problems associated with insulation, dimensions and weights because of demands for ever rising voltages and capacities.
  • 9. PARTS OF THE TRANSFORMER 1. Transformer Tank 2.High Voltage Bushing 3. Low Voltage Bushing 4.Cooling Fins/Radiator 5. Cooling Fans 6. Conservator Tank 7. System Ground Terminal 8. Drain Valve 9.Dehydrating breather 10. Oil Temperature/Pressure gauges 11. Bushing Current Transformers 12. Control Panel 13. Surge Arresters
  • 10. 2. ISOLAOTRS It is just like a switch is used to make sure that an electrical circuit can be completely deenergized for service or maintenance. Difference b/w Isolator and circuit Breaker The major difference between an isolator and a circuit breaker is that an isolator is an off-load device intended to be opened only after current has been interrupted by some other control device.
  • 11. CIRCUIT BREAKER 1.The basic functions of circuit breaker is protection, which is interruption of short-circuit and overload fault currents. 2. High-voltage breakers are nearly always solenoid-operated, with current sensing protective relays operated through current transformers. High-voltage breakers are broadly classified by the medium used to extinguish the arc. 1.Bulk oil 2.Minimum oil 3.Air blast 4.Vacuum 5.SF6 Sulfur hexafluoride (SF6) high-voltage circuit-breakers A sulfur hexafluoride circuit breaker uses contacts surrounded by sulfur hexafluoride gas to quench the arc. They are most often used for transmission-level voltages and may be incorporated into compact gasinsulated switchgear.
  • 12. RELAY A protective relay is an electromechanical apparatus, often with more than one coil, designed to calculate operating conditions on an electrical circuit and trip circuit breakers when a fault is detected. DISTANCE RELAY The most common form of protection on high voltage transmission systems is distance relay protection. Power lines have set impedance per km. and using this value and comparing voltage and current the distance to a fault can be determined.
  • 13. LIGHTNING ARRESTOR 1. A lightning arrester is a device used on electrical power systems to protect the insulation and conductors of the system from the damaging effects of lightning. 2. When a lightning surge travels along the power line to the arrester, the current from the surge is diverted through the arrestor, in most cases to earth.
  • 14. CURRENT TRANSFORMER AND POTENTIAL TRANSFORMER 1. Current transformers, together with potential transformers (PT) are known as instrument transformers. 2. When current in a circuit is too high to directly apply to measuring instruments, a current transformer produces a reduced current accurately proportional to the current in the circuit, which can be conveniently connected to measuring and recording instruments. Potential Transformer or Voltage Transformer are used in electrical power system for stepping down the system voltage to a safe value which can be fed to low ratings meters and relays. Commercially available relays and meters used for protection and metering, are designed for low voltage.
  • 15. CAPACITOR BANK A capacitor bank is a grouping of several identical capacitors interconnected in parallel or in series with one another. These groups of capacitors are typically used to correct or counteract undesirable characteristics, such as power factor lag or phase shifts inherent in alternating current (AC) electrical power supplies. CONTROL BATTERIES Generally we gave dc supply to the all protective equipment like relays ,indicators , and for all controlling devices through batteries in substation .
  • 16.
  • 17. the Transformer "the heart of the alternating current system" - William Stanley Jr.
  • 18.
  • 20. PARTS OF THE TRANSFORMER 1. Transformer Tank 2.High Voltage Bushing 3. Low Voltage Bushing 4.Cooling Fins/Radiator 5. Cooling Fans 6. Conservator Tank 7. System Ground Terminal 8. Drain Valve 9.Dehydrating breather 10. Oil Temperature/Pressure gauges 11. Bushing Current Transformers 12. Control Panel 13. Surge Arresters
  • 21. ļƒ˜Main components of a transformer are: ā€¢Magnetic core ā€¢Primary and secondary windings ā€¢Insulation of windings ā€¢Expansion tank or conservator ā€¢Tank , oil , cooling arrangement , temperature gauge, oil gauge ā€¢Buchholz relay ā€¢Silica gel breather
  • 22. (1) MAGNETIC CORE ā€¢Magnetic core consists of an iron core. The core is laminated and made of silicon steel. ā€¢Thickness varies from 0.35mm to 0.5mm. ā€¢Laminations are insulated from each other by coating then with a thin coat of varnish. ā€¢Various types of stampings and laminations employed in the construction of transformers. There are two types of transformer cores ,they are (a) Shell type (b)Core type Shell type ā€“ Two windings are carried by central limb. Core is made up of E and I stampings and has three limbs. Has two parallel paths for magnetic flux. Core type- Has two limbs for two windings and is made up of two L-type stampings. Has only one magnetic path.
  • 23. (2) Winding ā€¢There are two windings in a transformer. ā€¢They are primary and secondary windings. ā€¢Made up of copper. (3) Insulation ā€¢Paper is still used as basic conductor insulation. ā€¢For power transformers enamelled copper with paper insulation is also used. (4) Insulating oil ā€¢The coil used in transformer protects the paper from dirt and moisture and removes the heat produced in the core and coils, ā€¢It also acts as insulating medium. Oil must possess following properties: ā€¢High dielectric strength ā€¢Free from inorganic acid , alkali and corrosive sulphur. ā€¢Low viscosity to provide good heat transfer. ā€¢ Good resistance to emulsion so that the oil may throw down any moisture entering the tank instead of holding it.
  • 24. (5)EXPANSION TANK or Conservator ā€¢A small auxiliary oil tank mounted above the transformer and connected to main tank by a pipe. ā€¢Its function is to keep transformer tank full of oil. (6)TEMPERATURE GAUGE ā€¢Is to indicate hot oil or hottest spot temperature. ā€¢It is self contained weather proof unit made of alarm contacts.
  • 25. (7) OIL GAUGE ā€¢Every transformer is fitted with an oil gauge to indicate the oil level present inside the tank. ā€¢It is provided with an alarm contact which gives an alarm when the oil level drops beyond permissible height due to oil leak or due to any other reason. (8) BUCHHOLZ RELAY ā€¢First warning that fault is present is given by presence of bubbles in oil. ā€¢It gives an alarm in case of minor fault and to disconnect transformer From the supply mains in case of severe faults.
  • 26. (9) Breather ā€¢It is a chamber which prevents entry of moisture inside the transformer tank. ā€¢It is filled with drying agent such as calcium chloride or silica gel. ā€¢This absorbs moisture and allows dry air to enter transformer tank. It is replaced regularly.
  • 27. CLASSIFICATION OF TRANSFORMERS ļƒ˜Transformers are classified on basis of 1.Duty they perform 2.Construction 3.Voltage output 4.Application 5.Cooling 6.Input supply ļƒ˜Duty they perform I.Power transformer ā€“ from transmission and distribution II.Current transformer- instrument transformers III.Potential transformer- instrument transformers ļƒ˜Construction I.Core type transformer II.Shell type transformer III.Berry type transformer ļƒ˜Voltage output I.Step down transformer(Higher to Lower) II.Step up transformer(Lower to Higher) III.Auto transformer(Variable from ā€˜0ā€™ to rated value)
  • 28. ļƒ˜Application I.Welding transformer II.Furnace transformer ļƒ˜Cooling I.Duct type transformer II.Oil immersed transformer self cooled Forced air cooled Water cooled Forced oil cooled ļƒ˜Input supply I.Single phase transformer II.Three phase transformer star- star Star-delta Delta-delta Delta-Star Open- Delta Scott connection
  • 29. EMF EQUATION OF TRANSFORMER Wkt, T=1/f Average emf (e)= dĪ¦/dt dĪ¦ = Ī¦m dt = 1/4f Average rate of change of flux= Ī¦m / (1/4f) = 4f Ī¦m volts Average emf induced per turn = Average rate of change of flux= 4f Ī¦m volts Form factor = RMS value/ Average value = 1.11 RMS value= Form factor x Average value =1.11 x Average value RMS value of emf induced/turn = 1.11 x 4f Ī¦m = 4.44 f Ī¦m volts Primary and Secondary winding having N1 and N2 turns. RMS value of emf induced Primary winding, E1 = 4.44 f Ī¦m N1 volts RMS value of emf induced Secondary winding, E1 = 4.44 f Ī¦m N2 volts
  • 30. TRANSFORMER RATIO For an ideal transformer, E1 = V1 and E2 = V2 There is no voltage drop in the windings. V1 I1 = V2 I2 V2 / V1 = E2 / E1 = I1 / I2 = N2 / N1 = K V2 / V1 = K -> Voltage ratio E2 / E1 = K -> Transformation ratio N2 / N1 = K -> Turns ratio I1 / I2 = K -> Current ratio (i)If K > 1 , then the transformer is called step-up transformer. (ii) If K < 1 , then the transformer is called step-down transformer.
  • 31. RATING OF TRANSFORMER ā€¢The rating of transformer is expressed by Volt- Ampere (VA) ā€¢Cu loss depends on Current (A) ā€¢Iron loss depends on Voltage (V) ā€¢Total loss depends upon Volt- Ampere (VA) ā€¢It is independent of Load power factor cos Ī¦.
  • 32. Ideal transformer Ideal transformer has following properties : ā€¢No winding resistance i.e., purely inductive ā€¢No magnetic leakage flux ā€¢No cu loss ā€¢No core loss ā€¢Ideal transformer secondary is open. Ac supply is connected to primary winding. Current flows through primary winding. This current is called MAGNETISING CURRENT (IĪ¼). ā€¢Value of Magnetising current is small. The Magnetising current produces an alternating flux (Ī¦). ā€¢IĪ¼ and Ī¦ are in-phase. This changing flux links primary with secondary winding. ā€¢Due to alternating flux a self-induced emf (E1) is produced in primary winding which is equal to and in opposition with V1. It is known as counter emf or back emf of primary winding. ā€¢Induced emf E2 is produced in secondary winding because of alternating flux linking with secondary winding. This emf is known as mutually induced emf.
  • 33. PRACTICAL TRANSFORMER ON NOLOAD If the primary winding is connected to alternating voltage and secondary winding is left open then transformer is said to be on NOLOAD. Since secondary is open this current is called no-load primary current (Io). No load input power, P0= V1 I0 cos Ī¦0 Active or working or iron loss or wattful component (Iw) which is inphase with ā€˜V1ā€™ and supplies iron loss and small amount of primary cu loss. Iw = I0 cos Ī¦0 Where, cos Ī¦0 is no load power factor. Reactive or magnetizing or wattles component IĪ¼ which is in quadrature with V1 and its function is to sustain flux in core. IĪ¼= I0 Sin Ī¦0
  • 34. TRANSFORMER ON LOAD When the secondary winding is connected to load then the transformer is said to be on load. Phase angle between V2 and I2 depends on type of load. Resistive = I2 in-phase with V2 Load Inductive = I2 will lag V2 capacitive= I2 will lead V2 When transformer is loaded, ļƒ˜Flux is constant at no-load as well as at loaded condition, therefore transformer is called as constant flux apparatus. ļƒ˜Total primary current will be vector sum of I0 and I2ā€™
  • 35. ļƒ˜Transformer winding resistance In practical transformer the winding have some resistances. Primary winding has primary resistance(R2). Transformer winding leakage reactance Primary leakage flux(Ī¦L1) ā€“ All the flux generated by the primary winding does not link with secondary winding. Some part of flux passes through air rather than around the core. This flux is in-phase with I1. Secondary leakage flux(Ī¦L2) ā€“ Leakage flux is set up in secondary winding. This flux induces eL2 in secondary winding. This flux Ī¦L2 does not link with primary is also in-phase with I2.
  • 36.
  • 37. ļƒ˜OPEN CIRCUIT / NO-LOAD TEST ON TRANSFORMER PURPOSE OF THIS TEST IS TO DETERMINE ā€¢Core loss or Iron loss Or Magnetic loss (Pi) ā€¢No load current (I0) ā€¢Shunt branch parameters R0 and X0 ļƒ˜One of the winding is kept open. ā€¢Rated voltage at rated frequency is applied to other(LV) winding. ā€¢A voltmeter, wattmeter, and an ammeter are connected in LV side of the transformer. ļƒ¼Ammeter > Reads No-Load Current, I0 ļƒ¼Voltmeter > Reads Applied Voltage, V0 ļƒ¼Wattmeter> Reads No-Load Input Power, W0 or P0
  • 38. DETERMINATION OF EQUIVALENT CIRCUIT CONSTANTS THROUGH NO- LOAD TEST No load power factor, CosĪ¦0 = W0 / V0 I0 Core loss component, Iw = I0 CosĪ¦0 Magnetising component, Im = I0 SinĪ¦0 Core Loss, Pi = No load power (W0) Core loss resistance, R0 = V0 / Iw = V0 / I0 CosĪ¦0 Magnetising reactance, X0= V0 / Im = V0 / I0 SinĪ¦0
  • 39. ļƒ˜SHORT CIRCUIT / IMPEDANCE TEST ON TRANSFORMER PURPOSE OF THIS TEST IS TO DETERMINE ā€¢Z01 or Z02 ā€“ Total impedance referred to either primary or secondary side ā€¢R01 or R02- Total resistance referred to either primary or secondary side ā€¢X01 or X02- Total reactance referred to either primary or secondary side ā€¢Full load cu loss I22 R02 ļ¶In this test one of the winding is short circuited by thick conductor. ļ¶Current rating of HV side is low compared with LV side. ļ¶Power input gives total cu loss at rated load. ļ¶Unity power factor wattmeter is used for measuring power in SC test.
  • 40. DETERMINATION OF EQUIVALENT CIRCUIT CONSTANTS THROUGH LOAD TEST ļƒ˜SC power factor, CosĪ¦sc = Wsc / Vsc Isc ļƒ˜Resistance of transformer referred to primary side , R01 = Wsc / (Isc)2 ļƒ˜Impedance of transformer referred to primary side, Z01 = Z01 Cos Ī¦sc= Vsc / Isc