SlideShare uma empresa Scribd logo
1 de 4
Baixar para ler offline
INTRODUCTION
Part of the Port of Melbourne Channel
DeepeningProject was to dredge the Yarra River,
the last section of the Channel before arriving at
Swanson Dock where the container terminals are
located.
The Yarra River is crossed by steel service
pipelines for gas (30” / 0.75 m) and oil (24”/
0.60 m) and a concrete sewage tunnel of 3-m
diameter. These services pipelines are essential to
the city of Melbourne and had to remain ‘live’, i.e.
operational during the deepening works. By
deepening the river, however, the existing cover
on these services pipelines would no longer
adequately protect against possible anchor drop
and drag and scour of the riverbed caused by the
return current and propeller wash of passing ships.
CHALLENGES
A new means of protection for the services
pipelineswas necessary. The initial Port of
Melbourne Corporation (PoMC) protection plan
was to relocate the pipelines to a deeper level.
Unfortunately, building a new concrete sewage
tunnel and installing 2 pipelines in the river’s
complicated soil conditions would make the the
construction of new crossings especially difficult
and at inordinate expense.
As a Partner in the PoMC Alliance Team, Boskalis
proposed a novel protection system using plate
and rock placement that was far more attractive
and financially viable. But this too presented
challenges. Given that the allowable construction
height(protection layer thickness) above the
services pipelines was very limited, the usual
practise of pipeline protection by depositing a
layer of loose rock was not possible; a tailor-made
design had to be created.
A
Project
SHEET
Channel Deepening Project, Melbourne, Australia
Services pipeline protection works
A 	Location map
B 	 Steel plate to cover the sewer
C 	 Aerial view of the Services crossing the Yarra River.
	 The upper 3 had to be protected. The other 2 were
	demolished.
features
Client Port of Melbourne Corporation
Location Melbourne, Victoria, Australia
Period Preparation:
including the tender, EES and SEES:
August 2003 – January 2008
Execution:
February 2008 – November 2009
Contractor Boskalis Australia Pty. Ltd.
CB C
Theinformationcontainedinthisdatasheetisforguidancepurposesonlyandmaybesubjecttochanges.©Boskalis.Allrightsreserved.01—2012
INNOVATIVE SOLUTIONS
A design team was formed by PoMC which
included local consultants, a university and
laboratories. Boskalis provided input on possible
options and constructability.
During the design process intensive consultations
and risk assessments were held with services
owners. To protect the sewer, Boskalis placed
80-mm steel plates with a cover layer of 150-mm
styrocrete,encased in a steel box, in order to
absorb the energy of a dropping anchor. In
addition, steel wing plates placed at both sides of
the 80-mm protective plates protected the sewer
from dragging anchors. Placement of these
protective plates required that a perfect bedding
of the existing 0.5 m of natural clay be left in
place on top of the sewer. To protect the gas and
oil pipelines, Boskalis placed a cover of a
0.7-m-thick concrete penetrated rock layer of
150-mm diameter rock. Side slopes consisted of
concrete penetrated rock slopes with a minimum
thickness of 1.0 m of 300 mm rock.
To lift a dragging anchor to a level so that it could
not grip under the constructions, anchor berms of
400-mmrock were made on the sides of all these
protective constructions. Despite the very limited
construction height above the services pipelines
and water depths of 16 m and more, extreme
precision was maintained	 during all
construction stages for both the dredgingworks
and the placement of the protective rock and steel
plates.
Channel Deepening Project, Melbourne, Australia
Services pipeline protection works
MODIFIED EQUIPMENT
Boskalis modified its main pieces of equipment, the backhoe dredger (BHD)
Storken and the grab dredger Goomai, and developed special tools to
achieve the required accuracy as well as to ensure a high level of safety.The
BHD Storken was modified to be an electronically controlled operation with a
special redundant version of the Boskalis Crane Monitoring System (CMS)
equipped with multiple positioning and sensor systems. This system allowed
the operator to see the grab and the services pipelines with their defined
safety zone in real time. The Storken dredged with the Boskalis Horizontal
D	Cross section services protection. Steel plates are
	 being placed
E 	Multibeam picture of the excavation with the HPG
	 above and around the sewer
D
E
01—2012Theinformationcontainedinthisdatasheetisforguidancepurposesonlyandmaybesubjecttochanges.©Boskalis.Allrightsreserved.
Profiling Grab (HPG)and the system gave audible
alarms or could take over control when the grab
came within the safety zones. She was also
equipped with arobust set of additional controls to
safeguard the integrity of the pipelines, such as
remotely operated spud locking pins which
ensured that the spuds could not drop without the
deliberate action of the operator. The spuds were
equipped with spud-cans (or‘ big feet’) to reduce
the depth that the spuds could penetrate into the
riverbed. Furthermore, an automated concrete
placement system was installed on the Storken for
the application of a controlled volume of concrete
per m2
in order to construct the concrete
penetrated protective rocklayers.
The grab dredger Goomai was modified to
operate as a lifting crane for handling the support
frame known as the Yarra Tree. The Yarra Tree
was purpose-built to accurately place the
protection plates over the sewer pipeline. The
Yarra Tree is a stable, non-propelled structure, 23
metres in height that was securely installed in the
riverbed during operations by the Goomai. It had
a moveable system that allowed it to maneuver the
protective plates onto the top of the sewer with
accuracy to the centimeter. In addition, the Yarra
Tree was equipped with a disk cutter device for
centimeter-accuracy dredging as a backup system
for the HPG.
TESTING
Considering that new techniques were to be
applied and that the works were to be executed
above live pipelines, extensive physical tests were
F	 Grab dredger Goomai lifting the Yarra Tree to place the 	
	 steel plates above the sewer
G	Disc cutter test
H	Grouting beam attached to the BHD Storken
F
G
H
Channel Deepening Project, Melbourne, Australia
Services pipeline protection works
01—2012Theinformationcontainedinthisdatasheetisforguidancepurposesonlyandmaybesubjecttochanges.©Boskalis.Allrightsreserved.
Royal Boskalis Westminster N.V.
PO Box 43
3350 AA Papendrecht
The Netherlands
T +31 78 69 69 000
F +31 78 69 69 555
royal@boskalis.com
www.boskalis.com
executed to ensure the feasibility of the proposed systems:
‚‚ Physical scale tests (1:25) in which anchors were dragged on concrete 	
penetrated rock protections above pipelines
‚‚ Full scale tests with concrete rock penetrated slopes
‚‚ Full scale tests with disk cutter in stiff clay
‚‚ Full scale tests of placement of protective plates.
SAFE AND PRECISE
The design and successful installation of this novel anchor protection system for
pipelines and underwater constructions with minimal construction height was
made possible through the cooperation between client, designer and
contractor.
Boskalis modified and built equipment that was able to install the protection
system safely and in compliance with challenging accuracy requirements.
Ultimately this precision dredging ensured that the Port of Melbourne Channel
deepening project was successfully completed with full protection of all
services pipelines that exist underneath the Yarra River.
I	 Position control of the Yarra Tree.
J	 Rock slope under construction for test.
K 	Rock slope prepared for concrete penetration test.
L 	Result of concrete penetration test
I
J
K
L
Channel Deepening Project, Melbourne, Australia
Services pipeline protection works

Mais conteúdo relacionado

Mais procurados

Installation challenges
Installation challengesInstallation challenges
Installation challengesAndrea Intieri
 
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....Vladimir Popovic
 
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)Vladimir Popovic
 
ottobre 2016 - articolo Saipem bollettino SPE
ottobre 2016 - articolo  Saipem bollettino SPEottobre 2016 - articolo  Saipem bollettino SPE
ottobre 2016 - articolo Saipem bollettino SPEAndrea Intieri
 
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LININGSEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LININGDEEPAK MALLICK
 
Mod subaqueous flowtite
Mod subaqueous flowtiteMod subaqueous flowtite
Mod subaqueous flowtitelcs13262
 
Reston/Hunter Mill Stormwater Facility Repair and Rehabilitation
Reston/Hunter Mill Stormwater Facility Repair and RehabilitationReston/Hunter Mill Stormwater Facility Repair and Rehabilitation
Reston/Hunter Mill Stormwater Facility Repair and RehabilitationFairfax County
 
AME POWER PLANT REFERENCES
AME POWER PLANT REFERENCESAME POWER PLANT REFERENCES
AME POWER PLANT REFERENCESCarlo Avanzini
 
NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012Mike Vernon
 
Coal Combustible Presentation 7 30_2015
Coal Combustible Presentation 7 30_2015Coal Combustible Presentation 7 30_2015
Coal Combustible Presentation 7 30_2015Terry Aylward
 
Sidewinder UK Services Overview
Sidewinder UK Services OverviewSidewinder UK Services Overview
Sidewinder UK Services OverviewSidewinder UK
 
Marange Resources Water Supply System Design-Odzi to Concession Pipeline
Marange Resources Water Supply System Design-Odzi to Concession PipelineMarange Resources Water Supply System Design-Odzi to Concession Pipeline
Marange Resources Water Supply System Design-Odzi to Concession PipelineAugustine Marume
 

Mais procurados (20)

Installation challenges
Installation challengesInstallation challenges
Installation challenges
 
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
 
Alan sutton
Alan suttonAlan sutton
Alan sutton
 
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
Lanchkhuti City / Oragvis Gele RC Tank (1,900m3)
 
ottobre 2016 - articolo Saipem bollettino SPE
ottobre 2016 - articolo  Saipem bollettino SPEottobre 2016 - articolo  Saipem bollettino SPE
ottobre 2016 - articolo Saipem bollettino SPE
 
Richard Martinez #1 PDF
Richard Martinez #1 PDFRichard Martinez #1 PDF
Richard Martinez #1 PDF
 
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LININGSEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
 
Barker.R.CV.
Barker.R.CV.Barker.R.CV.
Barker.R.CV.
 
Mod subaqueous flowtite
Mod subaqueous flowtiteMod subaqueous flowtite
Mod subaqueous flowtite
 
Mining Operations Optimize Dewatering Processes
Mining Operations Optimize Dewatering ProcessesMining Operations Optimize Dewatering Processes
Mining Operations Optimize Dewatering Processes
 
Reston/Hunter Mill Stormwater Facility Repair and Rehabilitation
Reston/Hunter Mill Stormwater Facility Repair and RehabilitationReston/Hunter Mill Stormwater Facility Repair and Rehabilitation
Reston/Hunter Mill Stormwater Facility Repair and Rehabilitation
 
Rd cs steele_county
Rd cs steele_countyRd cs steele_county
Rd cs steele_county
 
Aoil profile 2016
Aoil  profile  2016 Aoil  profile  2016
Aoil profile 2016
 
AME OUTLINES
AME OUTLINESAME OUTLINES
AME OUTLINES
 
AME POWER PLANT REFERENCES
AME POWER PLANT REFERENCESAME POWER PLANT REFERENCES
AME POWER PLANT REFERENCES
 
NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012
 
Coal Combustible Presentation 7 30_2015
Coal Combustible Presentation 7 30_2015Coal Combustible Presentation 7 30_2015
Coal Combustible Presentation 7 30_2015
 
Sidewinder UK Services Overview
Sidewinder UK Services OverviewSidewinder UK Services Overview
Sidewinder UK Services Overview
 
Jonathan Wharton CV
Jonathan Wharton CVJonathan Wharton CV
Jonathan Wharton CV
 
Marange Resources Water Supply System Design-Odzi to Concession Pipeline
Marange Resources Water Supply System Design-Odzi to Concession PipelineMarange Resources Water Supply System Design-Odzi to Concession Pipeline
Marange Resources Water Supply System Design-Odzi to Concession Pipeline
 

Destaque

ADD AGENCY IPS TEMP_HEATHROW_FINAL
ADD AGENCY IPS TEMP_HEATHROW_FINALADD AGENCY IPS TEMP_HEATHROW_FINAL
ADD AGENCY IPS TEMP_HEATHROW_FINALSteve Turner
 
Grafico semanal del dax perfomance index para el 08 02 2013
Grafico semanal del dax perfomance index para el 08 02 2013Grafico semanal del dax perfomance index para el 08 02 2013
Grafico semanal del dax perfomance index para el 08 02 2013Experiencia Trading
 
Lab course outline
Lab course outlineLab course outline
Lab course outlineshahnita79
 
Leathers pants by leathersshop
Leathers pants by leathersshopLeathers pants by leathersshop
Leathers pants by leathersshopLeather Jackets
 
Creative Ethnography for Design
Creative Ethnography for DesignCreative Ethnography for Design
Creative Ethnography for DesignJames Wilson
 
Research Methods II: Urban Ethnography on The Wire
Research Methods II: Urban Ethnography on The WireResearch Methods II: Urban Ethnography on The Wire
Research Methods II: Urban Ethnography on The WireDr Igor Calzada, MBA, FeRSA
 
LConey-Journal_of_Physical_Security-Article_The-Ability-to-Defend-Against-the...
LConey-Journal_of_Physical_Security-Article_The-Ability-to-Defend-Against-the...LConey-Journal_of_Physical_Security-Article_The-Ability-to-Defend-Against-the...
LConey-Journal_of_Physical_Security-Article_The-Ability-to-Defend-Against-the...Lillie Coney
 

Destaque (11)

ADD AGENCY IPS TEMP_HEATHROW_FINAL
ADD AGENCY IPS TEMP_HEATHROW_FINALADD AGENCY IPS TEMP_HEATHROW_FINAL
ADD AGENCY IPS TEMP_HEATHROW_FINAL
 
Grafico semanal del dax perfomance index para el 08 02 2013
Grafico semanal del dax perfomance index para el 08 02 2013Grafico semanal del dax perfomance index para el 08 02 2013
Grafico semanal del dax perfomance index para el 08 02 2013
 
Lab course outline
Lab course outlineLab course outline
Lab course outline
 
Chuan Ho Catalog
Chuan Ho CatalogChuan Ho Catalog
Chuan Ho Catalog
 
cv
 cv cv
cv
 
Leathers pants by leathersshop
Leathers pants by leathersshopLeathers pants by leathersshop
Leathers pants by leathersshop
 
Denovo Company Intro 4.27.16-4
Denovo Company Intro 4.27.16-4Denovo Company Intro 4.27.16-4
Denovo Company Intro 4.27.16-4
 
Creative Ethnography for Design
Creative Ethnography for DesignCreative Ethnography for Design
Creative Ethnography for Design
 
Research Methods II: Urban Ethnography on The Wire
Research Methods II: Urban Ethnography on The WireResearch Methods II: Urban Ethnography on The Wire
Research Methods II: Urban Ethnography on The Wire
 
Attendance
AttendanceAttendance
Attendance
 
LConey-Journal_of_Physical_Security-Article_The-Ability-to-Defend-Against-the...
LConey-Journal_of_Physical_Security-Article_The-Ability-to-Defend-Against-the...LConey-Journal_of_Physical_Security-Article_The-Ability-to-Defend-Against-the...
LConey-Journal_of_Physical_Security-Article_The-Ability-to-Defend-Against-the...
 

Semelhante a Port of Melbourne Channel Deepening Project Services Pipeline Protection Works

Pipex Pumping Stations, Chambers & Catchpits
Pipex Pumping Stations, Chambers & CatchpitsPipex Pumping Stations, Chambers & Catchpits
Pipex Pumping Stations, Chambers & Catchpitseddiebradbrook
 
Cc channel lining aberdeen western peripheral route - transport scotland (1)
Cc channel lining   aberdeen western peripheral route - transport scotland (1)Cc channel lining   aberdeen western peripheral route - transport scotland (1)
Cc channel lining aberdeen western peripheral route - transport scotland (1)Oscar044
 
Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15John Grover
 
Sealing cables over land and sea - Panel Building & Systems Integration Magaz...
Sealing cables over land and sea - Panel Building & Systems Integration Magaz...Sealing cables over land and sea - Panel Building & Systems Integration Magaz...
Sealing cables over land and sea - Panel Building & Systems Integration Magaz...Roxtec UK & Ireland
 
May 2016 M37 RH Milner AS PUBLISHED
May 2016 M37 RH Milner AS PUBLISHEDMay 2016 M37 RH Milner AS PUBLISHED
May 2016 M37 RH Milner AS PUBLISHEDDean Bassett
 
Fib2010 article263 concrete durability_rev_a
Fib2010 article263 concrete durability_rev_aFib2010 article263 concrete durability_rev_a
Fib2010 article263 concrete durability_rev_agefyra-rion
 
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
060626_Temple_Mills_Bridge_Reconstruction_Javad_AkhtarJavad Akhtar
 
Three Valleys Chertsey WTW 2005
Three Valleys Chertsey WTW 2005Three Valleys Chertsey WTW 2005
Three Valleys Chertsey WTW 2005Niall Pembroke
 
Melbourne Channel Deepening
Melbourne Channel DeepeningMelbourne Channel Deepening
Melbourne Channel DeepeningSikko Krol
 
Armoured pipelines
Armoured pipelinesArmoured pipelines
Armoured pipelinesdocscipark
 
CC Mining Applications
CC Mining ApplicationsCC Mining Applications
CC Mining ApplicationsChristiane Cyr
 
SSCS Track Record
SSCS Track RecordSSCS Track Record
SSCS Track RecordAdam Tucker
 
Whitescape Civil Engineering Case Study
Whitescape Civil Engineering Case StudyWhitescape Civil Engineering Case Study
Whitescape Civil Engineering Case StudyAndrew White
 
Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Mike Bisland
 
Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull
 
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...John Grover
 
2376 robor ductile_iron_brochure5
2376 robor ductile_iron_brochure52376 robor ductile_iron_brochure5
2376 robor ductile_iron_brochure5Joshua Ting
 
Ch rockfall protection_works_along_konkan_railway_route_maharashtra_and_goa
Ch rockfall protection_works_along_konkan_railway_route_maharashtra_and_goaCh rockfall protection_works_along_konkan_railway_route_maharashtra_and_goa
Ch rockfall protection_works_along_konkan_railway_route_maharashtra_and_goamaccaferriindia
 

Semelhante a Port of Melbourne Channel Deepening Project Services Pipeline Protection Works (20)

Pipex Pumping Stations, Chambers & Catchpits
Pipex Pumping Stations, Chambers & CatchpitsPipex Pumping Stations, Chambers & Catchpits
Pipex Pumping Stations, Chambers & Catchpits
 
Cc channel lining aberdeen western peripheral route - transport scotland (1)
Cc channel lining   aberdeen western peripheral route - transport scotland (1)Cc channel lining   aberdeen western peripheral route - transport scotland (1)
Cc channel lining aberdeen western peripheral route - transport scotland (1)
 
Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15
 
Ns brochure
Ns  brochureNs  brochure
Ns brochure
 
Sealing cables over land and sea - Panel Building & Systems Integration Magaz...
Sealing cables over land and sea - Panel Building & Systems Integration Magaz...Sealing cables over land and sea - Panel Building & Systems Integration Magaz...
Sealing cables over land and sea - Panel Building & Systems Integration Magaz...
 
Submarine outfalls & intakes ppt
Submarine outfalls & intakes pptSubmarine outfalls & intakes ppt
Submarine outfalls & intakes ppt
 
May 2016 M37 RH Milner AS PUBLISHED
May 2016 M37 RH Milner AS PUBLISHEDMay 2016 M37 RH Milner AS PUBLISHED
May 2016 M37 RH Milner AS PUBLISHED
 
Fib2010 article263 concrete durability_rev_a
Fib2010 article263 concrete durability_rev_aFib2010 article263 concrete durability_rev_a
Fib2010 article263 concrete durability_rev_a
 
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
 
Three Valleys Chertsey WTW 2005
Three Valleys Chertsey WTW 2005Three Valleys Chertsey WTW 2005
Three Valleys Chertsey WTW 2005
 
Melbourne Channel Deepening
Melbourne Channel DeepeningMelbourne Channel Deepening
Melbourne Channel Deepening
 
Armoured pipelines
Armoured pipelinesArmoured pipelines
Armoured pipelines
 
CC Mining Applications
CC Mining ApplicationsCC Mining Applications
CC Mining Applications
 
SSCS Track Record
SSCS Track RecordSSCS Track Record
SSCS Track Record
 
Whitescape Civil Engineering Case Study
Whitescape Civil Engineering Case StudyWhitescape Civil Engineering Case Study
Whitescape Civil Engineering Case Study
 
Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011
 
Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012
 
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...
 
2376 robor ductile_iron_brochure5
2376 robor ductile_iron_brochure52376 robor ductile_iron_brochure5
2376 robor ductile_iron_brochure5
 
Ch rockfall protection_works_along_konkan_railway_route_maharashtra_and_goa
Ch rockfall protection_works_along_konkan_railway_route_maharashtra_and_goaCh rockfall protection_works_along_konkan_railway_route_maharashtra_and_goa
Ch rockfall protection_works_along_konkan_railway_route_maharashtra_and_goa
 

Port of Melbourne Channel Deepening Project Services Pipeline Protection Works

  • 1. INTRODUCTION Part of the Port of Melbourne Channel DeepeningProject was to dredge the Yarra River, the last section of the Channel before arriving at Swanson Dock where the container terminals are located. The Yarra River is crossed by steel service pipelines for gas (30” / 0.75 m) and oil (24”/ 0.60 m) and a concrete sewage tunnel of 3-m diameter. These services pipelines are essential to the city of Melbourne and had to remain ‘live’, i.e. operational during the deepening works. By deepening the river, however, the existing cover on these services pipelines would no longer adequately protect against possible anchor drop and drag and scour of the riverbed caused by the return current and propeller wash of passing ships. CHALLENGES A new means of protection for the services pipelineswas necessary. The initial Port of Melbourne Corporation (PoMC) protection plan was to relocate the pipelines to a deeper level. Unfortunately, building a new concrete sewage tunnel and installing 2 pipelines in the river’s complicated soil conditions would make the the construction of new crossings especially difficult and at inordinate expense. As a Partner in the PoMC Alliance Team, Boskalis proposed a novel protection system using plate and rock placement that was far more attractive and financially viable. But this too presented challenges. Given that the allowable construction height(protection layer thickness) above the services pipelines was very limited, the usual practise of pipeline protection by depositing a layer of loose rock was not possible; a tailor-made design had to be created. A Project SHEET Channel Deepening Project, Melbourne, Australia Services pipeline protection works A Location map B Steel plate to cover the sewer C Aerial view of the Services crossing the Yarra River. The upper 3 had to be protected. The other 2 were demolished. features Client Port of Melbourne Corporation Location Melbourne, Victoria, Australia Period Preparation: including the tender, EES and SEES: August 2003 – January 2008 Execution: February 2008 – November 2009 Contractor Boskalis Australia Pty. Ltd. CB C
  • 2. Theinformationcontainedinthisdatasheetisforguidancepurposesonlyandmaybesubjecttochanges.©Boskalis.Allrightsreserved.01—2012 INNOVATIVE SOLUTIONS A design team was formed by PoMC which included local consultants, a university and laboratories. Boskalis provided input on possible options and constructability. During the design process intensive consultations and risk assessments were held with services owners. To protect the sewer, Boskalis placed 80-mm steel plates with a cover layer of 150-mm styrocrete,encased in a steel box, in order to absorb the energy of a dropping anchor. In addition, steel wing plates placed at both sides of the 80-mm protective plates protected the sewer from dragging anchors. Placement of these protective plates required that a perfect bedding of the existing 0.5 m of natural clay be left in place on top of the sewer. To protect the gas and oil pipelines, Boskalis placed a cover of a 0.7-m-thick concrete penetrated rock layer of 150-mm diameter rock. Side slopes consisted of concrete penetrated rock slopes with a minimum thickness of 1.0 m of 300 mm rock. To lift a dragging anchor to a level so that it could not grip under the constructions, anchor berms of 400-mmrock were made on the sides of all these protective constructions. Despite the very limited construction height above the services pipelines and water depths of 16 m and more, extreme precision was maintained during all construction stages for both the dredgingworks and the placement of the protective rock and steel plates. Channel Deepening Project, Melbourne, Australia Services pipeline protection works MODIFIED EQUIPMENT Boskalis modified its main pieces of equipment, the backhoe dredger (BHD) Storken and the grab dredger Goomai, and developed special tools to achieve the required accuracy as well as to ensure a high level of safety.The BHD Storken was modified to be an electronically controlled operation with a special redundant version of the Boskalis Crane Monitoring System (CMS) equipped with multiple positioning and sensor systems. This system allowed the operator to see the grab and the services pipelines with their defined safety zone in real time. The Storken dredged with the Boskalis Horizontal D Cross section services protection. Steel plates are being placed E Multibeam picture of the excavation with the HPG above and around the sewer D E
  • 3. 01—2012Theinformationcontainedinthisdatasheetisforguidancepurposesonlyandmaybesubjecttochanges.©Boskalis.Allrightsreserved. Profiling Grab (HPG)and the system gave audible alarms or could take over control when the grab came within the safety zones. She was also equipped with arobust set of additional controls to safeguard the integrity of the pipelines, such as remotely operated spud locking pins which ensured that the spuds could not drop without the deliberate action of the operator. The spuds were equipped with spud-cans (or‘ big feet’) to reduce the depth that the spuds could penetrate into the riverbed. Furthermore, an automated concrete placement system was installed on the Storken for the application of a controlled volume of concrete per m2 in order to construct the concrete penetrated protective rocklayers. The grab dredger Goomai was modified to operate as a lifting crane for handling the support frame known as the Yarra Tree. The Yarra Tree was purpose-built to accurately place the protection plates over the sewer pipeline. The Yarra Tree is a stable, non-propelled structure, 23 metres in height that was securely installed in the riverbed during operations by the Goomai. It had a moveable system that allowed it to maneuver the protective plates onto the top of the sewer with accuracy to the centimeter. In addition, the Yarra Tree was equipped with a disk cutter device for centimeter-accuracy dredging as a backup system for the HPG. TESTING Considering that new techniques were to be applied and that the works were to be executed above live pipelines, extensive physical tests were F Grab dredger Goomai lifting the Yarra Tree to place the steel plates above the sewer G Disc cutter test H Grouting beam attached to the BHD Storken F G H Channel Deepening Project, Melbourne, Australia Services pipeline protection works
  • 4. 01—2012Theinformationcontainedinthisdatasheetisforguidancepurposesonlyandmaybesubjecttochanges.©Boskalis.Allrightsreserved. Royal Boskalis Westminster N.V. PO Box 43 3350 AA Papendrecht The Netherlands T +31 78 69 69 000 F +31 78 69 69 555 royal@boskalis.com www.boskalis.com executed to ensure the feasibility of the proposed systems: ‚‚ Physical scale tests (1:25) in which anchors were dragged on concrete penetrated rock protections above pipelines ‚‚ Full scale tests with concrete rock penetrated slopes ‚‚ Full scale tests with disk cutter in stiff clay ‚‚ Full scale tests of placement of protective plates. SAFE AND PRECISE The design and successful installation of this novel anchor protection system for pipelines and underwater constructions with minimal construction height was made possible through the cooperation between client, designer and contractor. Boskalis modified and built equipment that was able to install the protection system safely and in compliance with challenging accuracy requirements. Ultimately this precision dredging ensured that the Port of Melbourne Channel deepening project was successfully completed with full protection of all services pipelines that exist underneath the Yarra River. I Position control of the Yarra Tree. J Rock slope under construction for test. K Rock slope prepared for concrete penetration test. L Result of concrete penetration test I J K L Channel Deepening Project, Melbourne, Australia Services pipeline protection works