Program governance Structure

S
Saurabh SardesaiE-Business Strategy Consultant
PROGRAM GOVERNANCE STRUCTURE 
SETUP & MANAGEMENT 
By Saurabh Sardesai 
www.starvaluemodel.com 
June 2014
Objectives 
 Establish a Program/Project governance structure within the 
organization and ensure stakeholder participation 
 Define the program roles, decision making hierarchy, 
program execution strategies and best practices 
 Describe the protocol for proper flow of relevant information 
to all stakeholders 
 Establish a project/program review, issue management & 
change mgmt mechanism 
 Mechanism to identify program compliance and 
communications to all stakeholders 
 Evaluate various models of program governance and 
investigate their suitability for adaption 
 Translate business strategy into actual program execution via 
a proper governance framework
Governance defined 
 Governance, for a program or a project, is a 
combination of individuals filling executive and 
management roles, program oversight functions 
organized into structures, and policies that define 
management principles and decision making. 
 This combination is focused upon providing direction 
and oversight, which guide the achievement of the 
needed business outcome from the execution of the 
program effort, and providing data and feedback, 
which measure the ongoing contribution by the 
program to needed results within the overall 
business strategy and direction.
Need/Background 
 The organization was facing a huge problem of 
managing diverse projects across geographies without 
having a formal program structure in place 
 Senior management was finding it increasingly difficult 
to have an oversight on project execution in absence of 
proper governance structure and formal feedback 
channels 
 There was a clear disconnect between project execution 
and business mission or strategy 
 There was no overarching body like a Steering 
committee to provide oversight to projects 
 A need was felt to aggregate all multiple projects data in 
a central place and use the information to better 
manage the defined outcomes
Stakeholders 
 Board of Directors and C level executives 
 Project sponsors and funding partners 
 Internal and external clients of the organization 
 Business units within the organization 
 Vendor partners of the organization 
 Project managers and delivery managers/heads 
 Development teams, architects and testers 
 Support staff, line managers and consultants 
 Product control and management teams 
 Other relevant project stakeholders
Plan of action 
 Initiate consultations with relevant stakeholders to get 
their opinion & feedback 
 Establish a Program Steering Committee as the 
overarching body for program/project execution 
 Establish a Program Management Office (PMO) 
 Establish a Program Organization model and Project 
Organization model 
 Define and set up roles for Program Director, Program 
Managers, PMO managers and PMO support staff 
 Implement mechanisms to provide guidance and direction 
regarding policies, governance principles, and decision or 
authority specifications. 
 Establish a communications network and protocol for 
effective program and project communication to internal 
and external stakeholders of the organization
Steering committee models 
 Consensus Model: Executive-level sponsors who must reach 
consensus on issues, changes, and adjustments in order to proceed 
 Consultative Model: Executives and senior managers who are 
stakeholders for some aspect of the defined outcomes. Their role is 
to understand issues and needed changes, provide advice and 
assessment of potential impact, and make needed adjustments 
within their own responsibility area 
 Advisory Model: Representatives for the major business segments 
who are responsible for outcomes, or portions of outcomes, within 
the business strategy and direction. Their role is to monitor program 
progress, understand issues raised and adjustments made, assess 
potential impact within their own business segments, and carry back 
information about committee decisions to their respective business 
segments 
 For our initiative we recommend the Advisory model as the 
organization is large and has many interdependent businesses that 
routinely interact with each other
Recommended model – Program 
Management Office (PMO) 
 The Program Management Office (PMO) 
provides support along administrative, financial, 
process, and staff dimensions associated with 
successful program execution. 
 The PMO also provides review and tracking of 
financial expenditures, generation of required 
reports and financial documents, and ensures 
compliance with policies and practices. 
 The PMO provides & administers policies, 
procedures, & practices that provide an 
operational framework for program members
Sample Program model
Sample PMO structure
Sample Project structure 
within a PMO
Benefits of recommended model 
 Increases the long term potential of the program 
and individual projects 
 Continuous linkage to enterprise business 
strategy and direction 
 Clear and well-understood decision-making 
authority 
 Effective oversight of & insight into program 
progress and direction 
 Executive control over program evolution and 
outcomes 
 Central storage and management of all project 
data
Measuring Program success 
 Delivering the program to the client on time and 
within the dates specified in the agreement, taking 
into account any amendments or approved change 
requests 
 Achieving the financial objectives set forth in the 
business case, taking into account any amendments 
or change controls 
 Meeting all expectations related to quality and 
fulfilment of program requirements 
 Adhering to an established program methodology 
measured by a joint governance board 
 Achieving overall client satisfaction and repeat 
business
PMO – Tools of engagement 
 Overview and statement of purpose 
 Communication plan 
 Integrated program schedule 
 Program quality plan 
 Program risk management plan 
 Program issue management plan 
 Program change management 
 Program monitoring and control 
management
Elements of good program 
governance 
 A compelling business case, stating the objects of the 
project and specifying the in-scope and out-of-scope 
aspects 
 A mechanism to assess the compliance of the completed 
project to its original objectives 
 Identifying all stakeholders with an interest in the project 
 A defined method of communication to each stakeholder 
 A set of business-level requirements as agreed by all 
stakeholders 
 An agreed specification for the project deliverables 
 The appointment of a project manager 
 Clear assignment of project roles and responsibilities
Elements of good program 
governance….contd. 
 A current, published project plan that spans all project 
stages from project initiation through development to the 
transition to operations. 
 A system of accurate upward status- and progress-reporting 
including time records. 
 A central document repository for the project 
 A centrally-held glossary of project terms 
 A process for the management and resolution of issues that 
arise during the project 
 A process for the recording and communication 
of risks identified during the project 
 A standard for quality review of the key governance 
documents and of the project deliverables
Program Communications Plan 
 Sets up approved methods of communication 
 Establishes standard communication procedure 
 Frequency and type of updates provided to the 
program/project stakeholders 
 Provides consistency in information flow 
 Removes misinterpretations and doubts 
 What information to be sent to whom & when 
 Ensures Executive program engagement 
 Helps keep everyone on the same page
Communication Plan elements 
 Documented communication paths for information sharing, 
including tools (VOIP, email, video/Web conferencing, etc.) 
will be used throughout the program & for projects 
 Program and project contact lists based 
 Roles and responsibilities matrix for all stakeholders 
 A program organization chart to identify high-level 
organization, reporting, escalation and accountability for the 
program. 
 Approval and escalation procedures for decision making 
 Recurring Communication Matrix to ensure timely and 
effective communication 
 Program event management plan that ensures the right 
event occurrence reporting about issues, risks, milestones etc
Integrated Program Schedule 
 Key program tasks 
 Key program and/or project milestones 
 Duration of the program and projects in it 
 Dependencies related to the program 
 Assigned responsibilities within the program 
 Key deliverables of the program & schedule 
 Program tracking and control mechanism 
 Actual v/s Expected program metrics 
 Measurement and analysis of any deviations
Program Quality Plan 
 The quality plan defines the expectations of 
quality that will be delivered by the program. 
 The plan addresses the overall approach that will 
be adopted by the program and associated 
projects to ensure that quality is delivered 
according to stakeholder expectations. 
 The quality plan also defines quantitative 
measures that are used to validate quality prior 
to moving through a quality gate and eventually 
prior to implementation.
Program Risk Management Plan 
 The risk management plan is used to define the tolerance 
for risk throughout the program life cycle as well as the 
methods for identifying, recording and addressing risk 
throughout the program. 
 The early and frequent identification of risk in a program is 
essential to meeting cost, schedule and quality 
expectations. 
 Steering committee and program manager to meet on a 
monthly basis, or as defined in the communication plan, to 
review the identified risks, examine each associated action 
plan and define updates that need to be initiated. 
 Additionally, the team communicates any newly identified 
risks that may impact the program as they surface.
Sample program risk 
distribution chart 
14% 
20% 
6% 
33% 
2% 
12% 
13% 
Dependencies 
Requirements 
Knowledge 
Availability 
Commitment 
Project size 
Complexity
Program Mgr v/s Project Mgr 
Program manager Project manager 
Integrates efforts, continuously assesses and refines approaches 
and plans, ensures good communication. 
Plans, organizes, directs, and 
controls the project effort. 
Directs managers to achieve defined outcomes aligned with 
business strategy. 
Manages for on-time delivery of 
specific products. 
Acts as the implementation arm of the program sponsor(s) and / 
or steering committee. 
Manages work within the project 
plan framework. 
Manages managers. Manages technical staff. 
As Table above shows, the program manager and project manager roles 
are quite different from one another. Whereas project managers 
typically focus on delivering a specific component, program managers 
typically focus on one or more outcomes that are business strategy 
components.
Links to Business Strategy 
 Throughout program planning and execution, 
managers must ensure that the program sustains a 
connection to the business strategy. 
 This strategy is dynamic, not static. Both internal 
and external events affect the enterprise's initiatives, 
 So programs need mechanisms that will maintain a 
link between the initiative and the business strategy, 
and provide for effective data exchange and 
necessary adjustments. 
 We can divide such mechanisms into two categories: 
those active during program mobilization and 
planning, and those active during execution.
Program Mobilization – 
Strategic Review 
 IT goals and strategy 
 Program capital and expenses budget 
 Program benefits definition 
 Program outline 
 Candidate projects identification 
 Program mobilization plan 
 Consulting and staffing agreements 
 A business strategy review 
 Program planning strategy
Program execution reviews 
 As the program proceeds, the program plan and 
schedule should provide for periodic strategy 
reviews by the program sponsor(s) and / or 
steering committee. 
 The schedule for these reviews can be aligned 
with the program's phase structure, which cuts 
across all of the constituent projects. 
 As a phase-end approaches, reviewers can 
compare the program's current state and results 
against the then-current business strategy, and 
propose needed adjustments.
Decisions and Authority 
 An important aspect of program governance 
is assigning specific decision-making 
authority to each executive and management 
role. 
 Program managers can hold special group 
work sessions for this purpose and then 
create and distribute a matrix for major 
decision areas and roles. 
 Decision hierarchy structure should be clearly 
communicated to all program stakeholders
Sample authority matrix
Program Issue Management 
Plan 
 Throughout any program, risks are bound to become 
issues needing resolution in accordance with the 
strategy defined in the risk management plan. 
 In the likely scenario that an issue arises that has not 
yet been identified as a risk, the issue management 
plan provides strategies and guiding principles for 
resolving the issue. 
 Recognizing that this theoretical situation is not the 
typical situation in the execution of programs and 
projects, the same escalation principles identified 
through the program organization chart apply in the 
escalation of issues.
Program Change Management 
 Whether due to missed requirements, project 
issues or increased scope, a program is bound to 
encounter change during the life cycle. 
 The program change management plan defines 
the authority that the program has to approve 
change from an associated project, how said 
project requests change the agreed-to plan 
 How the program should receive approval on 
change requests that are beyond its authority is 
also defined in this plan
Program monitoring & control 
 Event log (includes identified risks, issues, 
changes, decisions and action items) 
 Project performance information such as key 
metrics on realized rate, resource utilization, 
ROI, duration, deliverables etc 
 Weekly status reports to stakeholders 
 Recommendations for intervention and 
corrective actions from senior management 
 Lessons learnt activities from closed initiatives 
 Managing change control requests 
 Effectively manage deviations from baseline
Conclusion 
 Establishing a governance framework is a 
significant activity requiring participation 
from all the relevant stakeholders 
 The key to a program’s success is optimal 
utilization of the governance framework, 
policies and best practices 
 Continuous feedback and communication are 
the essential ingredients of a Program 
 Program Management is a ‘people’ thing’ and 
must be projected that way
Thank you
1 de 33

Recomendados

Creating a colaborative program governance por
Creating a colaborative program governanceCreating a colaborative program governance
Creating a colaborative program governanceAlan Bueno, PMP, Prince2, ITIL
801 visualizações26 slides
The Effective Program Management Office (PgMO) (c) 2010 por
The Effective Program Management Office (PgMO) (c) 2010The Effective Program Management Office (PgMO) (c) 2010
The Effective Program Management Office (PgMO) (c) 2010Karen Y. Lucas PMP, PgMP, CISA, CISSP
3.9K visualizações12 slides
PMO and Project Portfolio Management por
PMO and Project Portfolio ManagementPMO and Project Portfolio Management
PMO and Project Portfolio ManagementDiana Rusnakova
475 visualizações14 slides
What is Program Management - An Overview por
What is Program Management - An OverviewWhat is Program Management - An Overview
What is Program Management - An OverviewYolanda Williams
11.8K visualizações12 slides
Setting up a pmo por
Setting up a pmoSetting up a pmo
Setting up a pmocrmackenzie
15.7K visualizações11 slides
Program Management Deployment Concept Consulting por
Program Management Deployment Concept ConsultingProgram Management Deployment Concept Consulting
Program Management Deployment Concept ConsultingEagle-Eye Management Consultancy (UK) Limited
1.7K visualizações26 slides

Mais conteúdo relacionado

Mais procurados

PMBOK 7th Edition What is Changing? por
PMBOK 7th Edition What is Changing?PMBOK 7th Edition What is Changing?
PMBOK 7th Edition What is Changing?Abdelrahman Elsheikh PMOC,PMP,CBAP,RMP,ACP,SP,MCITP,ITIL
4.5K visualizações54 slides
Program Management por
Program ManagementProgram Management
Program ManagementRajnish Anand
1.1K visualizações26 slides
PMO Presentation por
PMO PresentationPMO Presentation
PMO Presentationwilliamfranklin
1.8K visualizações21 slides
Program management skills por
Program management skillsProgram management skills
Program management skillsTathagat Varma
34.4K visualizações19 slides
Overview of Program Management por
Overview of Program ManagementOverview of Program Management
Overview of Program ManagementFlevy.com Best Practices
2.4K visualizações20 slides
PMO - Strategic Model & Concepts Overview por
PMO - Strategic Model & Concepts OverviewPMO - Strategic Model & Concepts Overview
PMO - Strategic Model & Concepts OverviewPMOfficers PMOAcademy
4K visualizações19 slides

Mais procurados(20)

Program Management por Rajnish Anand
Program ManagementProgram Management
Program Management
Rajnish Anand1.1K visualizações
PMO Presentation por williamfranklin
PMO PresentationPMO Presentation
PMO Presentation
williamfranklin1.8K visualizações
Program management skills por Tathagat Varma
Program management skillsProgram management skills
Program management skills
Tathagat Varma34.4K visualizações
PMO - Strategic Model & Concepts Overview por PMOfficers PMOAcademy
PMO - Strategic Model & Concepts OverviewPMO - Strategic Model & Concepts Overview
PMO - Strategic Model & Concepts Overview
PMOfficers PMOAcademy4K visualizações
Project Management Concepts (from PMBOK 5th Ed) por Jeremy Jay Lim
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)
Jeremy Jay Lim198.9K visualizações
Project management por Al Amin Neaz Ahmed
Project managementProject management
Project management
Al Amin Neaz Ahmed931 visualizações
Pmo por ammody
PmoPmo
Pmo
ammody1.9K visualizações
PMO Kick-Off Presentation por Ebru Seiwert
PMO Kick-Off PresentationPMO Kick-Off Presentation
PMO Kick-Off Presentation
Ebru Seiwert818 visualizações
Project management por Simran Kaur
Project managementProject management
Project management
Simran Kaur1.3K visualizações
Program Management por Anand Subramaniam
Program ManagementProgram Management
Program Management
Anand Subramaniam78.4K visualizações
The PMO journey por Tery Everett
The PMO journeyThe PMO journey
The PMO journey
Tery Everett1K visualizações
PMP Lecture 1: Introduction to Project Management por Benha University
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project Management
Benha University4.9K visualizações
Project, Program & Portfolio Management por Anand Subramaniam
Project, Program & Portfolio ManagementProject, Program & Portfolio Management
Project, Program & Portfolio Management
Anand Subramaniam40.7K visualizações
Lecture 05:Advanced Project Management PM Processes and Framework por Fida Karim 🇵🇰
Lecture 05:Advanced Project Management   PM Processes and FrameworkLecture 05:Advanced Project Management   PM Processes and Framework
Lecture 05:Advanced Project Management PM Processes and Framework
Fida Karim 🇵🇰3.3K visualizações
Project management por Jay Raval
Project managementProject management
Project management
Jay Raval1.4K visualizações
What is a PMO por RamPrasad Kurakula
What is a PMOWhat is a PMO
What is a PMO
RamPrasad Kurakula2.4K visualizações
Introduction to Project Management (workshop) - v.1 por Mena M. Eissa
Introduction to Project Management (workshop) - v.1Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1
Mena M. Eissa15.1K visualizações

Destaque

Enterprise Agile Transformation Case Study por
Enterprise Agile Transformation Case StudyEnterprise Agile Transformation Case Study
Enterprise Agile Transformation Case Studysystred
2.2K visualizações24 slides
Saurabh Reengineering Your Business por
Saurabh   Reengineering Your BusinessSaurabh   Reengineering Your Business
Saurabh Reengineering Your BusinessSaurabh Sardesai
311 visualizações4 slides
Value in entireness saurabh sardesai por
Value in entireness saurabh sardesaiValue in entireness saurabh sardesai
Value in entireness saurabh sardesaiSaurabh Sardesai
531 visualizações7 slides
Decision Making in an Organization por
Decision Making in an OrganizationDecision Making in an Organization
Decision Making in an Organizationed gbargaye
41.4K visualizações33 slides
Saurabh Harmony Business Analysis por
Saurabh Harmony Business AnalysisSaurabh Harmony Business Analysis
Saurabh Harmony Business AnalysisSaurabh Sardesai
267 visualizações19 slides
IT Project Governance Overview por
IT Project Governance OverviewIT Project Governance Overview
IT Project Governance OverviewSteve Gerick
4.5K visualizações13 slides

Destaque(20)

Enterprise Agile Transformation Case Study por systred
Enterprise Agile Transformation Case StudyEnterprise Agile Transformation Case Study
Enterprise Agile Transformation Case Study
systred2.2K visualizações
Saurabh Reengineering Your Business por Saurabh Sardesai
Saurabh   Reengineering Your BusinessSaurabh   Reengineering Your Business
Saurabh Reengineering Your Business
Saurabh Sardesai311 visualizações
Value in entireness saurabh sardesai por Saurabh Sardesai
Value in entireness saurabh sardesaiValue in entireness saurabh sardesai
Value in entireness saurabh sardesai
Saurabh Sardesai531 visualizações
Decision Making in an Organization por ed gbargaye
Decision Making in an OrganizationDecision Making in an Organization
Decision Making in an Organization
ed gbargaye41.4K visualizações
Saurabh Harmony Business Analysis por Saurabh Sardesai
Saurabh Harmony Business AnalysisSaurabh Harmony Business Analysis
Saurabh Harmony Business Analysis
Saurabh Sardesai267 visualizações
IT Project Governance Overview por Steve Gerick
IT Project Governance OverviewIT Project Governance Overview
IT Project Governance Overview
Steve Gerick4.5K visualizações
Principles of program governance por Glen Alleman
Principles of program governancePrinciples of program governance
Principles of program governance
Glen Alleman19.5K visualizações
Effective GOVERNANCE in Project Portfolio Management por Michal Augustini
Effective GOVERNANCE in Project Portfolio ManagementEffective GOVERNANCE in Project Portfolio Management
Effective GOVERNANCE in Project Portfolio Management
Michal Augustini5.1K visualizações
Difference between management & administration por Prof. Chhaya Sachin Patel
Difference between management & administrationDifference between management & administration
Difference between management & administration
Prof. Chhaya Sachin Patel14.2K visualizações
Administration Vs. Management por Irene Deona
Administration Vs. ManagementAdministration Vs. Management
Administration Vs. Management
Irene Deona96.2K visualizações
Project Governance and Failure por Michael Krigsman
Project Governance and FailureProject Governance and Failure
Project Governance and Failure
Michael Krigsman4.9K visualizações

Similar a Program governance Structure

Advanced program management constituency management por
Advanced program management   constituency managementAdvanced program management   constituency management
Advanced program management constituency managementMarcus Vannini
3.8K visualizações23 slides
Model of Programs.pptx por
Model of Programs.pptxModel of Programs.pptx
Model of Programs.pptxlalithamani sampath
3 visualizações11 slides
Program management - Fundamentals por
Program management   - FundamentalsProgram management   - Fundamentals
Program management - FundamentalsJulen Mohanty
67.4K visualizações59 slides
Program management for goup1 por
Program management for goup1Program management for goup1
Program management for goup1Mohammed Al_busailiy
1.5K visualizações17 slides
DAS PM RESPONSIBILITIES por
DAS PM RESPONSIBILITIESDAS PM RESPONSIBILITIES
DAS PM RESPONSIBILITIESJoseph Hoffman
109 visualizações2 slides
PMO Proposal For Global Sales Operations por
PMO Proposal For Global Sales OperationsPMO Proposal For Global Sales Operations
PMO Proposal For Global Sales Operationstonyhinojosa
2.9K visualizações30 slides

Similar a Program governance Structure(20)

Advanced program management constituency management por Marcus Vannini
Advanced program management   constituency managementAdvanced program management   constituency management
Advanced program management constituency management
Marcus Vannini3.8K visualizações
Program management - Fundamentals por Julen Mohanty
Program management   - FundamentalsProgram management   - Fundamentals
Program management - Fundamentals
Julen Mohanty67.4K visualizações
Program management for goup1 por Mohammed Al_busailiy
Program management for goup1Program management for goup1
Program management for goup1
Mohammed Al_busailiy1.5K visualizações
DAS PM RESPONSIBILITIES por Joseph Hoffman
DAS PM RESPONSIBILITIESDAS PM RESPONSIBILITIES
DAS PM RESPONSIBILITIES
Joseph Hoffman109 visualizações
PMO Proposal For Global Sales Operations por tonyhinojosa
PMO Proposal For Global Sales OperationsPMO Proposal For Global Sales Operations
PMO Proposal For Global Sales Operations
tonyhinojosa2.9K visualizações
Change Management for Technology Projects 4 por dmdk12
Change Management for Technology Projects 4Change Management for Technology Projects 4
Change Management for Technology Projects 4
dmdk12785 visualizações
MPPC.ppt por KuberBhusal1
MPPC.pptMPPC.ppt
MPPC.ppt
KuberBhusal127 visualizações
It Project Management por TJ Rains
It Project ManagementIt Project Management
It Project Management
TJ Rains1.6K visualizações
Program management scope management por Julen Mohanty
Program management   scope managementProgram management   scope management
Program management scope management
Julen Mohanty8.1K visualizações
Almm monitoring and evaluation tools draft[1]acm por Alberto Mico
Almm monitoring and evaluation tools draft[1]acmAlmm monitoring and evaluation tools draft[1]acm
Almm monitoring and evaluation tools draft[1]acm
Alberto Mico925 visualizações
Governance por Glen Alleman
GovernanceGovernance
Governance
Glen Alleman5.3K visualizações
Project Management vs. Program Management: Strategies for Transition Success por Ruffin Veal and Associates, Inc.
Project Management vs. Program Management: Strategies for Transition SuccessProject Management vs. Program Management: Strategies for Transition Success
Project Management vs. Program Management: Strategies for Transition Success
Ruffin Veal and Associates, Inc.12.4K visualizações
PMO (Project Management Office) por Dilawar Abbas
PMO (Project Management Office)PMO (Project Management Office)
PMO (Project Management Office)
Dilawar Abbas7.4K visualizações
Leon Tisdale Show por Leon Tisdale
Leon Tisdale ShowLeon Tisdale Show
Leon Tisdale Show
Leon Tisdale274 visualizações
PMO 3.0 - Next Gen Lean Model - Doug Floyd por dvfloyd
PMO 3.0 - Next Gen Lean Model - Doug FloydPMO 3.0 - Next Gen Lean Model - Doug Floyd
PMO 3.0 - Next Gen Lean Model - Doug Floyd
dvfloyd1.4K visualizações
Project Management V1 por Rebecca Keating
Project Management V1Project Management V1
Project Management V1
Rebecca Keating1.6K visualizações
Project Management Framework por Wadhwani Foundation
Project Management FrameworkProject Management Framework
Project Management Framework
Wadhwani Foundation9.5K visualizações
Project monitoring and control & planning for monitoring por Sandeep Kumar
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoring
Sandeep Kumar8.7K visualizações

Último

Lucky Cement Presentation.pdf por
Lucky Cement Presentation.pdfLucky Cement Presentation.pdf
Lucky Cement Presentation.pdfbakhtawaraq
10 visualizações17 slides
Merger.pdf por
Merger.pdfMerger.pdf
Merger.pdfCristina Martin-Palomino Casanova
5 visualizações7 slides
Narcissism vs Leadership (1).pdf por
Narcissism vs Leadership (1).pdfNarcissism vs Leadership (1).pdf
Narcissism vs Leadership (1).pdfkullmd
9 visualizações5 slides
The Wheel of Life - Coaching Wheel por
The Wheel of Life - Coaching WheelThe Wheel of Life - Coaching Wheel
The Wheel of Life - Coaching WheelAlex Clapson
22 visualizações1 slide
Action Project Presentation.pptx por
Action Project Presentation.pptxAction Project Presentation.pptx
Action Project Presentation.pptxKhondoker Rukaiya Siddiqa
18 visualizações5 slides
What Is Psychological Safety? por
What Is Psychological Safety?What Is Psychological Safety?
What Is Psychological Safety?Alex Clapson
26 visualizações5 slides

Último(14)

Lucky Cement Presentation.pdf por bakhtawaraq
Lucky Cement Presentation.pdfLucky Cement Presentation.pdf
Lucky Cement Presentation.pdf
bakhtawaraq10 visualizações
Narcissism vs Leadership (1).pdf por kullmd
Narcissism vs Leadership (1).pdfNarcissism vs Leadership (1).pdf
Narcissism vs Leadership (1).pdf
kullmd9 visualizações
The Wheel of Life - Coaching Wheel por Alex Clapson
The Wheel of Life - Coaching WheelThe Wheel of Life - Coaching Wheel
The Wheel of Life - Coaching Wheel
Alex Clapson22 visualizações
What Is Psychological Safety? por Alex Clapson
What Is Psychological Safety?What Is Psychological Safety?
What Is Psychological Safety?
Alex Clapson26 visualizações
v20231127 WHOPE BEMA Day One Sendai Framework Volunteer Workshop Session Zoom... por Andrew Networks
v20231127 WHOPE BEMA Day One Sendai Framework Volunteer Workshop Session Zoom...v20231127 WHOPE BEMA Day One Sendai Framework Volunteer Workshop Session Zoom...
v20231127 WHOPE BEMA Day One Sendai Framework Volunteer Workshop Session Zoom...
Andrew Networks50 visualizações
Intuitively Moving Institutions Towards Global Regulatory Resilience por Ajaz Hussain
Intuitively Moving Institutions Towards Global Regulatory Resilience Intuitively Moving Institutions Towards Global Regulatory Resilience
Intuitively Moving Institutions Towards Global Regulatory Resilience
Ajaz Hussain78 visualizações
TITAN SUBMARINE por supiriyakithuva
TITAN SUBMARINETITAN SUBMARINE
TITAN SUBMARINE
supiriyakithuva21 visualizações
TAX ANALYSIS (CASE OF RWANDA).pptx por SadamuFrancois
TAX ANALYSIS (CASE  OF RWANDA).pptxTAX ANALYSIS (CASE  OF RWANDA).pptx
TAX ANALYSIS (CASE OF RWANDA).pptx
SadamuFrancois11 visualizações
balixa.io Plan.pdf por tycoonone91
balixa.io Plan.pdfbalixa.io Plan.pdf
balixa.io Plan.pdf
tycoonone9130 visualizações
Cracking the Optimism vs Pessimism Code.pptx por Workforce Group
Cracking the Optimism vs Pessimism Code.pptxCracking the Optimism vs Pessimism Code.pptx
Cracking the Optimism vs Pessimism Code.pptx
Workforce Group32 visualizações

Program governance Structure

  • 1. PROGRAM GOVERNANCE STRUCTURE SETUP & MANAGEMENT By Saurabh Sardesai www.starvaluemodel.com June 2014
  • 2. Objectives  Establish a Program/Project governance structure within the organization and ensure stakeholder participation  Define the program roles, decision making hierarchy, program execution strategies and best practices  Describe the protocol for proper flow of relevant information to all stakeholders  Establish a project/program review, issue management & change mgmt mechanism  Mechanism to identify program compliance and communications to all stakeholders  Evaluate various models of program governance and investigate their suitability for adaption  Translate business strategy into actual program execution via a proper governance framework
  • 3. Governance defined  Governance, for a program or a project, is a combination of individuals filling executive and management roles, program oversight functions organized into structures, and policies that define management principles and decision making.  This combination is focused upon providing direction and oversight, which guide the achievement of the needed business outcome from the execution of the program effort, and providing data and feedback, which measure the ongoing contribution by the program to needed results within the overall business strategy and direction.
  • 4. Need/Background  The organization was facing a huge problem of managing diverse projects across geographies without having a formal program structure in place  Senior management was finding it increasingly difficult to have an oversight on project execution in absence of proper governance structure and formal feedback channels  There was a clear disconnect between project execution and business mission or strategy  There was no overarching body like a Steering committee to provide oversight to projects  A need was felt to aggregate all multiple projects data in a central place and use the information to better manage the defined outcomes
  • 5. Stakeholders  Board of Directors and C level executives  Project sponsors and funding partners  Internal and external clients of the organization  Business units within the organization  Vendor partners of the organization  Project managers and delivery managers/heads  Development teams, architects and testers  Support staff, line managers and consultants  Product control and management teams  Other relevant project stakeholders
  • 6. Plan of action  Initiate consultations with relevant stakeholders to get their opinion & feedback  Establish a Program Steering Committee as the overarching body for program/project execution  Establish a Program Management Office (PMO)  Establish a Program Organization model and Project Organization model  Define and set up roles for Program Director, Program Managers, PMO managers and PMO support staff  Implement mechanisms to provide guidance and direction regarding policies, governance principles, and decision or authority specifications.  Establish a communications network and protocol for effective program and project communication to internal and external stakeholders of the organization
  • 7. Steering committee models  Consensus Model: Executive-level sponsors who must reach consensus on issues, changes, and adjustments in order to proceed  Consultative Model: Executives and senior managers who are stakeholders for some aspect of the defined outcomes. Their role is to understand issues and needed changes, provide advice and assessment of potential impact, and make needed adjustments within their own responsibility area  Advisory Model: Representatives for the major business segments who are responsible for outcomes, or portions of outcomes, within the business strategy and direction. Their role is to monitor program progress, understand issues raised and adjustments made, assess potential impact within their own business segments, and carry back information about committee decisions to their respective business segments  For our initiative we recommend the Advisory model as the organization is large and has many interdependent businesses that routinely interact with each other
  • 8. Recommended model – Program Management Office (PMO)  The Program Management Office (PMO) provides support along administrative, financial, process, and staff dimensions associated with successful program execution.  The PMO also provides review and tracking of financial expenditures, generation of required reports and financial documents, and ensures compliance with policies and practices.  The PMO provides & administers policies, procedures, & practices that provide an operational framework for program members
  • 11. Sample Project structure within a PMO
  • 12. Benefits of recommended model  Increases the long term potential of the program and individual projects  Continuous linkage to enterprise business strategy and direction  Clear and well-understood decision-making authority  Effective oversight of & insight into program progress and direction  Executive control over program evolution and outcomes  Central storage and management of all project data
  • 13. Measuring Program success  Delivering the program to the client on time and within the dates specified in the agreement, taking into account any amendments or approved change requests  Achieving the financial objectives set forth in the business case, taking into account any amendments or change controls  Meeting all expectations related to quality and fulfilment of program requirements  Adhering to an established program methodology measured by a joint governance board  Achieving overall client satisfaction and repeat business
  • 14. PMO – Tools of engagement  Overview and statement of purpose  Communication plan  Integrated program schedule  Program quality plan  Program risk management plan  Program issue management plan  Program change management  Program monitoring and control management
  • 15. Elements of good program governance  A compelling business case, stating the objects of the project and specifying the in-scope and out-of-scope aspects  A mechanism to assess the compliance of the completed project to its original objectives  Identifying all stakeholders with an interest in the project  A defined method of communication to each stakeholder  A set of business-level requirements as agreed by all stakeholders  An agreed specification for the project deliverables  The appointment of a project manager  Clear assignment of project roles and responsibilities
  • 16. Elements of good program governance….contd.  A current, published project plan that spans all project stages from project initiation through development to the transition to operations.  A system of accurate upward status- and progress-reporting including time records.  A central document repository for the project  A centrally-held glossary of project terms  A process for the management and resolution of issues that arise during the project  A process for the recording and communication of risks identified during the project  A standard for quality review of the key governance documents and of the project deliverables
  • 17. Program Communications Plan  Sets up approved methods of communication  Establishes standard communication procedure  Frequency and type of updates provided to the program/project stakeholders  Provides consistency in information flow  Removes misinterpretations and doubts  What information to be sent to whom & when  Ensures Executive program engagement  Helps keep everyone on the same page
  • 18. Communication Plan elements  Documented communication paths for information sharing, including tools (VOIP, email, video/Web conferencing, etc.) will be used throughout the program & for projects  Program and project contact lists based  Roles and responsibilities matrix for all stakeholders  A program organization chart to identify high-level organization, reporting, escalation and accountability for the program.  Approval and escalation procedures for decision making  Recurring Communication Matrix to ensure timely and effective communication  Program event management plan that ensures the right event occurrence reporting about issues, risks, milestones etc
  • 19. Integrated Program Schedule  Key program tasks  Key program and/or project milestones  Duration of the program and projects in it  Dependencies related to the program  Assigned responsibilities within the program  Key deliverables of the program & schedule  Program tracking and control mechanism  Actual v/s Expected program metrics  Measurement and analysis of any deviations
  • 20. Program Quality Plan  The quality plan defines the expectations of quality that will be delivered by the program.  The plan addresses the overall approach that will be adopted by the program and associated projects to ensure that quality is delivered according to stakeholder expectations.  The quality plan also defines quantitative measures that are used to validate quality prior to moving through a quality gate and eventually prior to implementation.
  • 21. Program Risk Management Plan  The risk management plan is used to define the tolerance for risk throughout the program life cycle as well as the methods for identifying, recording and addressing risk throughout the program.  The early and frequent identification of risk in a program is essential to meeting cost, schedule and quality expectations.  Steering committee and program manager to meet on a monthly basis, or as defined in the communication plan, to review the identified risks, examine each associated action plan and define updates that need to be initiated.  Additionally, the team communicates any newly identified risks that may impact the program as they surface.
  • 22. Sample program risk distribution chart 14% 20% 6% 33% 2% 12% 13% Dependencies Requirements Knowledge Availability Commitment Project size Complexity
  • 23. Program Mgr v/s Project Mgr Program manager Project manager Integrates efforts, continuously assesses and refines approaches and plans, ensures good communication. Plans, organizes, directs, and controls the project effort. Directs managers to achieve defined outcomes aligned with business strategy. Manages for on-time delivery of specific products. Acts as the implementation arm of the program sponsor(s) and / or steering committee. Manages work within the project plan framework. Manages managers. Manages technical staff. As Table above shows, the program manager and project manager roles are quite different from one another. Whereas project managers typically focus on delivering a specific component, program managers typically focus on one or more outcomes that are business strategy components.
  • 24. Links to Business Strategy  Throughout program planning and execution, managers must ensure that the program sustains a connection to the business strategy.  This strategy is dynamic, not static. Both internal and external events affect the enterprise's initiatives,  So programs need mechanisms that will maintain a link between the initiative and the business strategy, and provide for effective data exchange and necessary adjustments.  We can divide such mechanisms into two categories: those active during program mobilization and planning, and those active during execution.
  • 25. Program Mobilization – Strategic Review  IT goals and strategy  Program capital and expenses budget  Program benefits definition  Program outline  Candidate projects identification  Program mobilization plan  Consulting and staffing agreements  A business strategy review  Program planning strategy
  • 26. Program execution reviews  As the program proceeds, the program plan and schedule should provide for periodic strategy reviews by the program sponsor(s) and / or steering committee.  The schedule for these reviews can be aligned with the program's phase structure, which cuts across all of the constituent projects.  As a phase-end approaches, reviewers can compare the program's current state and results against the then-current business strategy, and propose needed adjustments.
  • 27. Decisions and Authority  An important aspect of program governance is assigning specific decision-making authority to each executive and management role.  Program managers can hold special group work sessions for this purpose and then create and distribute a matrix for major decision areas and roles.  Decision hierarchy structure should be clearly communicated to all program stakeholders
  • 29. Program Issue Management Plan  Throughout any program, risks are bound to become issues needing resolution in accordance with the strategy defined in the risk management plan.  In the likely scenario that an issue arises that has not yet been identified as a risk, the issue management plan provides strategies and guiding principles for resolving the issue.  Recognizing that this theoretical situation is not the typical situation in the execution of programs and projects, the same escalation principles identified through the program organization chart apply in the escalation of issues.
  • 30. Program Change Management  Whether due to missed requirements, project issues or increased scope, a program is bound to encounter change during the life cycle.  The program change management plan defines the authority that the program has to approve change from an associated project, how said project requests change the agreed-to plan  How the program should receive approval on change requests that are beyond its authority is also defined in this plan
  • 31. Program monitoring & control  Event log (includes identified risks, issues, changes, decisions and action items)  Project performance information such as key metrics on realized rate, resource utilization, ROI, duration, deliverables etc  Weekly status reports to stakeholders  Recommendations for intervention and corrective actions from senior management  Lessons learnt activities from closed initiatives  Managing change control requests  Effectively manage deviations from baseline
  • 32. Conclusion  Establishing a governance framework is a significant activity requiring participation from all the relevant stakeholders  The key to a program’s success is optimal utilization of the governance framework, policies and best practices  Continuous feedback and communication are the essential ingredients of a Program  Program Management is a ‘people’ thing’ and must be projected that way