Room and Pillar working – utilising continuous mining systems
FIRST WORKINGS
•First workings are conducted for two main reasons:
•To develop the pillars, bords and/or panels to
enable their subsequent extraction, and
•To develop multiple main entries for access to the
coal reserves. These entries are supported in the
long term by the pillars consequently formed.
FIRST WORKINGS
The number of development headings driven in any area of
workings can vary between two and eight.
This is dependent primarily on the purpose of development,
and the second method of working together with the following
factors:
• Mine capacity,
• Pillar and /or pillar and panel system relating to depth of
working, productivity and panel extraction system,
• Number of continuous miner units operating,
• Coal clearance system,
• Men and material transport, and
• Ventilation.
FIRST WORKINGS
Typical Development Layout
The standard layout consists of a five road development, with the main
conveyor and feeder breaker positioned in the central roadway. This
provides working areas to carry out all the main development functions:
One heading for the
CM to be cutting
One heading ready
for cutting
One heading for
ventilation
rearrangement and
survey work
One heading for
cleaning by LHD
One heading for
supporting by
Quadbolter
OPEN ENDED LIFTING – METHOD A
OPEN ENDED LIFTING – METHOD B
SPLIT AND FENDER
This is the most common method of pillar mining.
The pillars are usually square or rectangular with dimensions
dependent on the depth of working. Typically a pillar dimension of 45
x 45 meter is used at depth of around 450 m.
Basically the pillars developed by the first working are split into sub-
pillars and the fenders are then lifted (mined).
The width of the lift is governed by the length of the continuous miner,
roof conditions and support rules of the individual mine.
Generally the split is supported by roof bolts or other means of
supporting, depending on the timing of the mining.
Roof bolting and W-straps were supplemented with timber props and
bars.
SPLIT AND FENDER
The lifting operation took place usually towards the goaf side with
the pillar, with the basic philosophy of working adjacent to a
competent rib.
However, in mines with competent roof conditions, lifting from both
sides of the split was possible, and with the approval of mine
inspectorate.
When extracting on both left and right, pillars up to four meters in
width were left in the fenders to provide temporary support.
However, the current system of splitting with mobile breaker line
supports, lifting from both sides of the split is standard practice.
A small stook (support Buttress) of coal seam ( min width 2.0m) is
normally left to control caving, particularly on the goaf side.
Typical De-pillaring layout
PRICE LIST OF DIFFERENT MACHINERIES IN THE CM PANEL
Sl.
No.
Equipment Quanti
ty
Country of
Origin
Unit Price
US $
Total Price
US $
1 Continuous
Miner 12CM15-
10D
1 no. USA 2,791,265.00 2,791,265.00
2 Shuttle Car
10SC32B
2 no. RSA 934,617.00 1,869,234.00
3 Feeder Breaker
BF14B-3-7C
1 no. USA 743,312.00 743,312.00
4 Quad Bolter 1 no. Australia 1,183,225.00 1,183,225.00
5 Electrical
Equipment
1 no. UK 971,115.00 971,115.00
TOTAL PACKAGE VALUE – US DOLLARS 7,558,151.00
(US Dollars Seven million Five hundred Fifty Eight thousand one hundred Fifty One only)
SHUTTLE CAR 10SC32
ROLE OF SHUTTLE CAR IN THE
OVERALL PROCESS.
 The function of shuttle car is to transport the coal that is sheared by
continuous miner from the face to the place where feeder breaker is
installed.
 Capacity of a 10SC32 shuttle is 10.19 tons and the fill factor is about
0.85.
Joy Shuttle Car Model 10SC32B Specifications
General
•Type : JOY 10SC32
•Operating voltage: 1050 V
•Voltage Rating: ±10%
•Total Rated Power: 202.6kW
2 × 85 kW Traction Motors
1 × 18.6 kW Conveyor Motor
1 × 14 kW Pump Motor
•Weight 20,500kg (approximately) empty
•Cubic Capacity : 10.19cu meters
•Dimensions (l × w × h): 8.99m × 3.05m × 1.31m
•Ground clearance: 290mm (Nominal)
•Ground Bearing Pressure: 520 kPa empty; 830 kPa loaded
•Gradient (in line of advance): Below 6 degrees. If greater than 6 degrees, a
new gear with reduction of 66.56: 1 could be used.
•Cross gradient: not greater than 5 degrees
•Total Service Life: 1.5 million tones
SPLIT AND FENDER
SPLIT AND FENDER
SPLIT AND FENDER
SPLIT AND LIFT USING BREAKER LINE SUPPORTS
SPLIT AND LIFT USING BREAKER LINE SUPPORTS
BREAKER LINE SUPPORT (BLS)
Advantages.
 Greater positive setting loads and roof support on goaf
edge .
 Cost saving in timber usage to defray their capital cost.
 Able to be reset to the new breaker line position as
extraction takes place faster than timber breaker lines can
be set.
 Increases potential continuous miner cutting time and
productivity.
 Through remote control they remove the active goaf edge
area personnel who would be required otherwise to set the
breaker-line props thus further improving safety.
MOBILE BREAKER LINE SUPPORT
Breaker lines installed for 3 rows before extraction commences6
Extraction sequence
Breaker lines installed during pillar split
Remote Reading Telltale (3
2 x 2.4m SG bolts (breaker
Pillar stress cells (5m + 10m
Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10
BARRIERPILLAR
Proposed Monitoring Scheme CM1 Panel
1
Auto warning telltale installed during pillar split
Breaker lines installed for 3 rows before extraction commences6
Extraction sequence
Breaker lines installed during pillar split
Remote Reading Telltale (3m + 10m)
2 x 2.4m SG bolts (breaker line)
Pillar stress cells (5m + 10m)
Auto warning telltale (single height 10m – trigger 5mm)
Remote Rib Exto. (3m + 10m)
BARRIERPILLAR
Proposed Monitoring Scheme CM1 Panel
1
Auto warning telltale installed during pillar split
2
Breaker lines installed for 3 rows before extraction commences6
Breaker lines installed during pillar split
Remote Reading Telltale (3
2 x 2.4m SG bolts (breaker
Pillar stress cells (5m + 10m
Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10
BARRIERPILLAR
Proposed Monitoring Scheme CM1 Panel
1
Auto warning telltale installed during pillar split
2
3
4
Breaker lines installed for 3 rows before extraction commences6
Extraction sequence
Breaker lines installed during pillar split
Remote Reading Telltale (3
2 x 2.4m SG bolts (breaker
Pillar stress cells (5m + 10m
Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10
BARRIERPILLAR
Proposed Monitoring Scheme CM1 Panel
1
Auto warning telltale installed during pillar split
2
3
4
Breaker lines installed for 3 rows before extraction commences6
Extraction sequence
Breaker lines installed during pillar split
Remote Reading Telltale (3
2 x 2.4m SG bolts (breaker line)
Pillar stress cells (5m + 10m
Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10
BARRIERPILLAR
Proposed Monitoring Scheme CM1 Panel
1
Auto warning telltale installed during pillar split
2
3
5
6
4
Breaker lines installed for 3 rows before extraction commences6
Extraction sequence
Breaker lines installed during pillar split
Remote Reading Telltale (3
2 x 2.4m SG bolts (breaker
Pillar stress cells (5m + 10m
Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10
BARRIERPILLAR
Proposed Monitoring Scheme CM1 Panel
1
Auto warning telltale installed during pillar split
2
3
5
6
7
8
4
Breaker lines installed for 3 rows before extraction commences6
Extraction sequence
Breaker lines installed during pillar split
Remote Reading Telltale (3
2 x 2.4m SG bolts (breaker
Pillar stress cells (5m + 10m
Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10
BARRIERPILLAR
Proposed Monitoring Scheme CM1 Panel
1
Auto warning telltale installed during pillar split
2
3
5
6
7
8
9
10
4
Breaker lines installed for 3 rows before extraction commences6
Extraction sequence
Breaker lines installed during pillar split
Remote Reading Telltale (3
2 x 2.4m SG bolts (breaker
Pillar stress cells (5m + 10m
Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10
BARRIERPILLAR
Proposed Monitoring Scheme CM1 Panel
1
Auto warning telltale installed during pillar split
2
3
5
6
7
8
9
10
11
12
13
4
Breaker lines installed for 3 rows before extraction commences6
Extraction sequence
Breaker lines installed during pillar split
Remote Reading Telltale (3
2 x 2.4m SG bolts (breaker
Pillar stress cells (5m + 10m
Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10
BARRIERPILLAR
Proposed Monitoring Scheme CM1 Panel
1
Auto warning telltale installed during pillar split
2
3
5
6
7
8
9
10
11
12
13 14
154
Breaker lines installed for 3 rows before extraction commences6
Extraction sequence
Breaker lines installed during pillar split
Remote Reading Telltale (3
2 x 2.4m SG bolts (breaker
Pillar stress cells (5m + 10m
Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10
BARRIERPILLAR
Proposed Monitoring Scheme CM1 Panel
1
Auto warning telltale installed during pillar split
2
3
5
6
7
8
9
10
11
12
13 14
16154
Breaker lines installed for 3 rows before extraction commences6
Extraction sequence
Breaker lines installed during pillar split
Remote Reading Telltale (3
2 x 2.4m SG bolts (breaker
Pillar stress cells (5m + 10m
Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10
BARRIERPILLAR
Proposed Monitoring Scheme CM1 Panel
1
Auto warning telltale installed during pillar split
2
3
5
6
7
8
9
10
11
12
13 14
16154
Breaker lines installed for 3 rows before extraction commences6
Extraction sequence
Breaker lines installed during pillar split
Remote Reading Telltale (3
2 x 2.4m SG bolts (breaker
Pillar stress cells (5m + 10m
Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10
BARRIERPILLAR
Proposed Monitoring Scheme CM1 Panel
1
Auto warning telltale installed during pillar split
2
3
5
6
7
8
9
10
11
12
13 14
17
18
16154
Breaker lines installed for 3 rows before extraction commences6
Extraction sequence
Breaker lines installed during pillar split
Remote Reading Telltale (3
2 x 2.4m SG bolts (breaker
Pillar stress cells (5m + 10m
Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10
BARRIERPILLAR
Proposed Monitoring Scheme CM1 Panel
1
Auto warning telltale installed during pillar split
2
3
5
6
7
8
9
10
11
12
13 14
17
18
19
20
16154
Breaker lines installed for 3 rows before extraction commences6
Extraction sequence
Breaker lines installed during pillar split
Remote Reading Telltale (3
2 x 2.4m SG bolts (breaker
Pillar stress cells (5m + 10m
Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10
BARRIERPILLAR
Proposed Monitoring Scheme CM1 Panel
1
Auto warning telltale installed during pillar split
2
3
5
6
7
8
9
10
11
12
13 14
17
18
19
20
21
22
16154
Breaker lines installed for 3 rows before extraction commences6
Extraction sequence
Breaker lines installed during pillar split
Remote Reading Telltale (3
2 x 2.4m SG bolts (breaker
Pillar stress cells (5m + 10m
Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10
BARRIERPILLAR
Proposed Monitoring Scheme CM1 Panel
1
Auto warning telltale installed during pillar split
2
3
5
6
7
8
9
10
11
12
13 14
17
18
19
20
21
22
23
24
16154
Breaker lines installed for 3 rows before extraction commences6
Extraction sequence
Breaker lines installed during pillar split
Remote Reading Telltale (3
2 x 2.4m SG bolts (breaker
Pillar stress cells (5m + 10m
Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10
BARRIERPILLAR
Proposed Monitoring Scheme CM1 Panel
1
Auto warning telltale installed during pillar split
2
3
5
6
7
8
9
10
11
12
13 14
17
18
19
20
21
22
23
24
25
27
26
28
16154
Breaker lines installed for 3 rows before extraction commences6
Extraction sequence
Breaker lines installed during pillar split
Remote Reading Telltale (3
2 x 2.4m SG bolts (breaker
Pillar stress cells (5m + 10m
Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10
BARRIERPILLAR
Proposed Monitoring Scheme CM1 Panel
1
Auto warning telltale installed during pillar split
2
3
5
6
7
8
9
10
11
12
13 14
17
18
19
20
21
22
23
24
25
27
26
28
29
30
31
32
16154
Breaker lines installed for 3 rows before extraction commences6 Extraction sequence
Breaker lines installed during pillar split
Remote Reading Telltale (3m + 10m)
2 x 2.4m SG bolts (breaker line)
Pillar stress cells (5m + 10m)
Auto warning telltale (single height 10m – trigger 5mm)
Remote Rib Exto. (3m + 10m)
BARRIERPILLAR
Proposed Monitoring Scheme CM1 Panel
1
Auto warning telltale installed during pillar split
2
3
5
6
7
8
9
10
11
12
13 14
17
18
19
20
21
22
23
24
25
27
26
28
30
29
32
31
33
34
35
36
OLD BEN METHOD – PANEL AND PILLAR EXTRACTION
•Developing multiple headings, usually three, to the
limits of the area to be extracted.
•These panels, along with newly formed pillars (in the
virgin coal) were extracted in retreat.
•Here, the secondary development consisted of three
roads, leaving reserves for pillar extraction on either
side.
•The total panel width was greater than 200 m.
•Tertiary development, consisting of three roads, was
done towards the end of the panel to increase overall
extraction.
•From this development, short fenders were then
developed and extracted.
OLD BEN METHOD – PANEL AND PILLAR EXTRACTION
OLD BEN METHOD – PANEL AND PILLAR EXTRACTION
WONGAWILLI METHOD
 The Wongawilli system was developed at Wongawilli
Colliery in the southern coalfield of New South Wales in
the early 1960s.
 Generally with the Wongawilli system, a panel is created by
a secondary development consisting of three to five roads
and leaving a continuous pillar of coal between the
development and the previously caved area.
 The pillar is normally between 50 m and 150 m wide and is
extracted by developing and extracting 7 m wide ribs in a
modified split and lift system.
 The pillars formed by the development are extracted as the
rib extraction retreats. As a result of the length of the rib
pillars, this method resembles a shortwall face.
WONGAWILLI METHOD
 This method was developed to provide a single
working place to extract coal in a stress-relieved area
and to utilize the coal seam as support during
extraction.
 An overall extraction of 90 per cent was achieved by
this system.
WONGAWILLI METHOD
 The main disadvantages of the Wongawilli system
area:
 ➤ Excessive floor lift when splitting successive
headings in a large panel
 ➤ Difficulties when removing stooks on the return
run out of each heading
 ➤ Difficulties with ventilating rib pillar panels when
the roof caves completely, thus filling voids in the goaf
area and choking the ventilation flow.
 1. Provision of a single working place
2. Extraction of coal in stress relieved areas
3. Maximise extraction of the seam,
4. Simple system readily understood by all employees.
 The method provides;
a) A straight goaf line
b) Simple ventilation system, with air being coursed
via the goaf, and
c) Working within de-stressed areas.
WONGAWILLI METHOD
WONGAWILLI METHOD
RIB PILLAR EXTRACTION METHOD
RIB PILLAR EXTRACTION METHOD
RIB PILLAR EXTRACTION METHOD – SYSTEMATIC CUTTING AND
SUPPORT SEQUENCE
RIB PILLAR EXTRACTION METHOD – SYSTEMATIC CUTTING AND
SUPPORT SEQUENCE
RIB PILLAR EXTRACTION METHOD
 Panel Layout and Cutting Sequence
 The area allocated to rib-pillar mining is divided into
workable sections, and the primary development
normally consists of four roadways from the main
development to the limit of the remnant. The two
outer roads are utilized as return airways, and the two
inner road travelling and conveyor-belt roads. The
inner roads also serve as intake airways
 The secondary development consists of three roads,
two being intake airways and one a return airway.
 Cross conveyor installations are used to ensure that
the tramming distance for shuttle cars is minimized.

More Related Content

What's hot

Develpoment and extraction of coal pillar by continuous
Develpoment and extraction of coal pillar by continuousDevelpoment and extraction of coal pillar by continuous
Develpoment and extraction of coal pillar by continuous
Shubham Agrawal
 

What's hot (20)

Longwall machinery
Longwall  machineryLongwall  machinery
Longwall machinery
 
Continuous miner
Continuous minerContinuous miner
Continuous miner
 
Road Header and Bolter Miner
Road Header and Bolter MinerRoad Header and Bolter Miner
Road Header and Bolter Miner
 
High Wall Mining
High Wall MiningHigh Wall Mining
High Wall Mining
 
Longwall mining (Multisling mining - Horizontal slicing) NIT ROURKELA
Longwall mining (Multisling mining - Horizontal slicing) NIT ROURKELALongwall mining (Multisling mining - Horizontal slicing) NIT ROURKELA
Longwall mining (Multisling mining - Horizontal slicing) NIT ROURKELA
 
Highwall mining – a new approach in india
Highwall mining – a new approach in indiaHighwall mining – a new approach in india
Highwall mining – a new approach in india
 
Bord and pillar working with LHD/SDL
Bord and pillar working with LHD/SDLBord and pillar working with LHD/SDL
Bord and pillar working with LHD/SDL
 
Conventional support system
Conventional support systemConventional support system
Conventional support system
 
Roof supports in coal mines
Roof supports in coal minesRoof supports in coal mines
Roof supports in coal mines
 
Transportation in underground mines
Transportation  in underground mines Transportation  in underground mines
Transportation in underground mines
 
In pit crusher conveyour system
In pit crusher conveyour systemIn pit crusher conveyour system
In pit crusher conveyour system
 
DESIGN OF SUPPORT SYSTEM IN BORD AND PILLAR MINE
DESIGN OF SUPPORT SYSTEM IN BORD AND PILLAR MINEDESIGN OF SUPPORT SYSTEM IN BORD AND PILLAR MINE
DESIGN OF SUPPORT SYSTEM IN BORD AND PILLAR MINE
 
Thin seam mining
Thin seam miningThin seam mining
Thin seam mining
 
Surface miner
Surface minerSurface miner
Surface miner
 
CONTINUOUS MINERS
CONTINUOUS MINERSCONTINUOUS MINERS
CONTINUOUS MINERS
 
Lpdt
LpdtLpdt
Lpdt
 
Develpoment and extraction of coal pillar by continuous
Develpoment and extraction of coal pillar by continuousDevelpoment and extraction of coal pillar by continuous
Develpoment and extraction of coal pillar by continuous
 
Haulage system in Mines
Haulage system in MinesHaulage system in Mines
Haulage system in Mines
 
Board & Pillar
Board & PillarBoard & Pillar
Board & Pillar
 
LHD Load haul dump ppt
LHD Load haul dump pptLHD Load haul dump ppt
LHD Load haul dump ppt
 

Similar to Development and depillaring with continuous miner

Coiled Tubing Introduction and Basics.pdf
Coiled Tubing Introduction and Basics.pdfCoiled Tubing Introduction and Basics.pdf
Coiled Tubing Introduction and Basics.pdf
salem123gmaal
 
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
coderweb
 

Similar to Development and depillaring with continuous miner (20)

sarpi coal mine project
sarpi coal mine projectsarpi coal mine project
sarpi coal mine project
 
Coiled Tubing Introduction and Basics.pdf
Coiled Tubing Introduction and Basics.pdfCoiled Tubing Introduction and Basics.pdf
Coiled Tubing Introduction and Basics.pdf
 
Coal Handling Plant
Coal Handling PlantCoal Handling Plant
Coal Handling Plant
 
Track
TrackTrack
Track
 
coal mining training report
coal mining training report coal mining training report
coal mining training report
 
Tưới di chuyển với súng tưới bán kính lớn Nelson Big gun
Tưới di chuyển với súng tưới bán kính lớn Nelson Big gunTưới di chuyển với súng tưới bán kính lớn Nelson Big gun
Tưới di chuyển với súng tưới bán kính lớn Nelson Big gun
 
Ursviken 2015 pole sytems and crane arms
Ursviken 2015 pole sytems and crane armsUrsviken 2015 pole sytems and crane arms
Ursviken 2015 pole sytems and crane arms
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machine
 
Orto Alresa series_Digtor_22_C_ENG.pdf
Orto Alresa series_Digtor_22_C_ENG.pdfOrto Alresa series_Digtor_22_C_ENG.pdf
Orto Alresa series_Digtor_22_C_ENG.pdf
 
ICDE2006, Singapore
ICDE2006, SingaporeICDE2006, Singapore
ICDE2006, Singapore
 
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
 
Training
TrainingTraining
Training
 
Tirap report
Tirap report Tirap report
Tirap report
 
cpi mill testing.ppt
cpi mill testing.pptcpi mill testing.ppt
cpi mill testing.ppt
 
MASS VIBRATION POKERS 2011.ppt
MASS VIBRATION POKERS 2011.pptMASS VIBRATION POKERS 2011.ppt
MASS VIBRATION POKERS 2011.ppt
 
SOOSAN CRAWLER DRILL
SOOSAN CRAWLER DRILLSOOSAN CRAWLER DRILL
SOOSAN CRAWLER DRILL
 
Pricast Mill Scan Dsp Lnvt
Pricast Mill Scan Dsp LnvtPricast Mill Scan Dsp Lnvt
Pricast Mill Scan Dsp Lnvt
 
Редукторы серии U Power Jacks
Редукторы серии U Power JacksРедукторы серии U Power Jacks
Редукторы серии U Power Jacks
 
Trishuli hydro power plant 3 day educational visit
Trishuli hydro power plant 3 day educational visitTrishuli hydro power plant 3 day educational visit
Trishuli hydro power plant 3 day educational visit
 
trisuli hydropower nepal
trisuli hydropower nepaltrisuli hydropower nepal
trisuli hydropower nepal
 

More from Safdar Ali

More from Safdar Ali (20)

Safety in mines
Safety in minesSafety in mines
Safety in mines
 
Tunneling
TunnelingTunneling
Tunneling
 
Explosives and accesories
Explosives and accesoriesExplosives and accesories
Explosives and accesories
 
Role of management information systems in a mine.
Role of management information systems in a mine.Role of management information systems in a mine.
Role of management information systems in a mine.
 
Basting
BastingBasting
Basting
 
Pre requisites of marine operations
Pre requisites of marine operationsPre requisites of marine operations
Pre requisites of marine operations
 
Nuclear devices for mining
Nuclear devices for miningNuclear devices for mining
Nuclear devices for mining
 
Mining of manganese nodules from sea floor
Mining of manganese nodules from sea floorMining of manganese nodules from sea floor
Mining of manganese nodules from sea floor
 
Mine water risk in open pit slope stability
Mine water risk in open pit slope stabilityMine water risk in open pit slope stability
Mine water risk in open pit slope stability
 
Innovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngInnovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellng
 
Lighting terminlologyand their units
Lighting terminlologyand their unitsLighting terminlologyand their units
Lighting terminlologyand their units
 
Evaluation of slope stability for waste rock dumps in a mine
Evaluation of slope stability for waste rock dumps in a mineEvaluation of slope stability for waste rock dumps in a mine
Evaluation of slope stability for waste rock dumps in a mine
 
Final grouting freezing
Final grouting freezingFinal grouting freezing
Final grouting freezing
 
Digitization and 3d modelling of a mine plan
Digitization and 3d modelling of a mine planDigitization and 3d modelling of a mine plan
Digitization and 3d modelling of a mine plan
 
Variety of mine plans and sections & second schedule
Variety of mine plans and sections & second scheduleVariety of mine plans and sections & second schedule
Variety of mine plans and sections & second schedule
 
Statutory provisions for the preaparation of mine plans and sections
Statutory provisions for the preaparation of mine plans and sectionsStatutory provisions for the preaparation of mine plans and sections
Statutory provisions for the preaparation of mine plans and sections
 
Gps & its applications in opencast mine surveying
Gps & its applications in opencast mine surveyingGps & its applications in opencast mine surveying
Gps & its applications in opencast mine surveying
 
Laser and its mining applications
Laser and its mining applicationsLaser and its mining applications
Laser and its mining applications
 
Gyrotheodolite
GyrotheodoliteGyrotheodolite
Gyrotheodolite
 
Gps2
Gps2Gps2
Gps2
 

Recently uploaded

The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 

Recently uploaded (20)

Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the Classroom
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptx
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Interdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxInterdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptx
 

Development and depillaring with continuous miner

  • 1. www.MINEPORTAL.in ONLINE TEST SERIES FOR GATE MINING COAL/METAL FIRST/SECOND CLASS COAL INDIA MT MINING EXAM OVERMAN/SIRDAR EXAM OTHER PSU MANAGEMENT TRAINEE EXAM FREE STUDY MATERIAL/VIDEO LECTURES ONLINE ORDER MINING BOOKS CALL/WHATSAPP-8804777500 www.fb.com/mineportal.in
  • 2.
  • 3. Diagram of a mine with longwall and continuous mining system
  • 4. Room and Pillar working – utilising continuous mining systems
  • 5. FIRST WORKINGS •First workings are conducted for two main reasons: •To develop the pillars, bords and/or panels to enable their subsequent extraction, and •To develop multiple main entries for access to the coal reserves. These entries are supported in the long term by the pillars consequently formed.
  • 6. FIRST WORKINGS The number of development headings driven in any area of workings can vary between two and eight. This is dependent primarily on the purpose of development, and the second method of working together with the following factors: • Mine capacity, • Pillar and /or pillar and panel system relating to depth of working, productivity and panel extraction system, • Number of continuous miner units operating, • Coal clearance system, • Men and material transport, and • Ventilation.
  • 8. Typical Development Layout The standard layout consists of a five road development, with the main conveyor and feeder breaker positioned in the central roadway. This provides working areas to carry out all the main development functions: One heading for the CM to be cutting One heading ready for cutting One heading for ventilation rearrangement and survey work One heading for cleaning by LHD One heading for supporting by Quadbolter
  • 9. OPEN ENDED LIFTING – METHOD A
  • 10. OPEN ENDED LIFTING – METHOD B
  • 11. SPLIT AND FENDER This is the most common method of pillar mining. The pillars are usually square or rectangular with dimensions dependent on the depth of working. Typically a pillar dimension of 45 x 45 meter is used at depth of around 450 m. Basically the pillars developed by the first working are split into sub- pillars and the fenders are then lifted (mined). The width of the lift is governed by the length of the continuous miner, roof conditions and support rules of the individual mine. Generally the split is supported by roof bolts or other means of supporting, depending on the timing of the mining. Roof bolting and W-straps were supplemented with timber props and bars.
  • 12. SPLIT AND FENDER The lifting operation took place usually towards the goaf side with the pillar, with the basic philosophy of working adjacent to a competent rib. However, in mines with competent roof conditions, lifting from both sides of the split was possible, and with the approval of mine inspectorate. When extracting on both left and right, pillars up to four meters in width were left in the fenders to provide temporary support. However, the current system of splitting with mobile breaker line supports, lifting from both sides of the split is standard practice. A small stook (support Buttress) of coal seam ( min width 2.0m) is normally left to control caving, particularly on the goaf side.
  • 14. PRICE LIST OF DIFFERENT MACHINERIES IN THE CM PANEL Sl. No. Equipment Quanti ty Country of Origin Unit Price US $ Total Price US $ 1 Continuous Miner 12CM15- 10D 1 no. USA 2,791,265.00 2,791,265.00 2 Shuttle Car 10SC32B 2 no. RSA 934,617.00 1,869,234.00 3 Feeder Breaker BF14B-3-7C 1 no. USA 743,312.00 743,312.00 4 Quad Bolter 1 no. Australia 1,183,225.00 1,183,225.00 5 Electrical Equipment 1 no. UK 971,115.00 971,115.00 TOTAL PACKAGE VALUE – US DOLLARS 7,558,151.00 (US Dollars Seven million Five hundred Fifty Eight thousand one hundred Fifty One only)
  • 16. ROLE OF SHUTTLE CAR IN THE OVERALL PROCESS.  The function of shuttle car is to transport the coal that is sheared by continuous miner from the face to the place where feeder breaker is installed.  Capacity of a 10SC32 shuttle is 10.19 tons and the fill factor is about 0.85.
  • 17. Joy Shuttle Car Model 10SC32B Specifications General •Type : JOY 10SC32 •Operating voltage: 1050 V •Voltage Rating: ±10% •Total Rated Power: 202.6kW 2 × 85 kW Traction Motors 1 × 18.6 kW Conveyor Motor 1 × 14 kW Pump Motor •Weight 20,500kg (approximately) empty •Cubic Capacity : 10.19cu meters •Dimensions (l × w × h): 8.99m × 3.05m × 1.31m •Ground clearance: 290mm (Nominal) •Ground Bearing Pressure: 520 kPa empty; 830 kPa loaded •Gradient (in line of advance): Below 6 degrees. If greater than 6 degrees, a new gear with reduction of 66.56: 1 could be used. •Cross gradient: not greater than 5 degrees •Total Service Life: 1.5 million tones
  • 21. SPLIT AND LIFT USING BREAKER LINE SUPPORTS
  • 22. SPLIT AND LIFT USING BREAKER LINE SUPPORTS
  • 23. BREAKER LINE SUPPORT (BLS) Advantages.  Greater positive setting loads and roof support on goaf edge .  Cost saving in timber usage to defray their capital cost.  Able to be reset to the new breaker line position as extraction takes place faster than timber breaker lines can be set.  Increases potential continuous miner cutting time and productivity.  Through remote control they remove the active goaf edge area personnel who would be required otherwise to set the breaker-line props thus further improving safety.
  • 25. Breaker lines installed for 3 rows before extraction commences6 Extraction sequence Breaker lines installed during pillar split Remote Reading Telltale (3 2 x 2.4m SG bolts (breaker Pillar stress cells (5m + 10m Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10 BARRIERPILLAR Proposed Monitoring Scheme CM1 Panel 1 Auto warning telltale installed during pillar split
  • 26. Breaker lines installed for 3 rows before extraction commences6 Extraction sequence Breaker lines installed during pillar split Remote Reading Telltale (3m + 10m) 2 x 2.4m SG bolts (breaker line) Pillar stress cells (5m + 10m) Auto warning telltale (single height 10m – trigger 5mm) Remote Rib Exto. (3m + 10m) BARRIERPILLAR Proposed Monitoring Scheme CM1 Panel 1 Auto warning telltale installed during pillar split 2
  • 27. Breaker lines installed for 3 rows before extraction commences6 Breaker lines installed during pillar split Remote Reading Telltale (3 2 x 2.4m SG bolts (breaker Pillar stress cells (5m + 10m Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10 BARRIERPILLAR Proposed Monitoring Scheme CM1 Panel 1 Auto warning telltale installed during pillar split 2 3
  • 28. 4 Breaker lines installed for 3 rows before extraction commences6 Extraction sequence Breaker lines installed during pillar split Remote Reading Telltale (3 2 x 2.4m SG bolts (breaker Pillar stress cells (5m + 10m Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10 BARRIERPILLAR Proposed Monitoring Scheme CM1 Panel 1 Auto warning telltale installed during pillar split 2 3
  • 29. 4 Breaker lines installed for 3 rows before extraction commences6 Extraction sequence Breaker lines installed during pillar split Remote Reading Telltale (3 2 x 2.4m SG bolts (breaker line) Pillar stress cells (5m + 10m Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10 BARRIERPILLAR Proposed Monitoring Scheme CM1 Panel 1 Auto warning telltale installed during pillar split 2 3 5 6
  • 30. 4 Breaker lines installed for 3 rows before extraction commences6 Extraction sequence Breaker lines installed during pillar split Remote Reading Telltale (3 2 x 2.4m SG bolts (breaker Pillar stress cells (5m + 10m Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10 BARRIERPILLAR Proposed Monitoring Scheme CM1 Panel 1 Auto warning telltale installed during pillar split 2 3 5 6 7 8
  • 31. 4 Breaker lines installed for 3 rows before extraction commences6 Extraction sequence Breaker lines installed during pillar split Remote Reading Telltale (3 2 x 2.4m SG bolts (breaker Pillar stress cells (5m + 10m Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10 BARRIERPILLAR Proposed Monitoring Scheme CM1 Panel 1 Auto warning telltale installed during pillar split 2 3 5 6 7 8 9 10
  • 32. 4 Breaker lines installed for 3 rows before extraction commences6 Extraction sequence Breaker lines installed during pillar split Remote Reading Telltale (3 2 x 2.4m SG bolts (breaker Pillar stress cells (5m + 10m Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10 BARRIERPILLAR Proposed Monitoring Scheme CM1 Panel 1 Auto warning telltale installed during pillar split 2 3 5 6 7 8 9 10 11 12 13
  • 33. 4 Breaker lines installed for 3 rows before extraction commences6 Extraction sequence Breaker lines installed during pillar split Remote Reading Telltale (3 2 x 2.4m SG bolts (breaker Pillar stress cells (5m + 10m Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10 BARRIERPILLAR Proposed Monitoring Scheme CM1 Panel 1 Auto warning telltale installed during pillar split 2 3 5 6 7 8 9 10 11 12 13 14
  • 34. 154 Breaker lines installed for 3 rows before extraction commences6 Extraction sequence Breaker lines installed during pillar split Remote Reading Telltale (3 2 x 2.4m SG bolts (breaker Pillar stress cells (5m + 10m Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10 BARRIERPILLAR Proposed Monitoring Scheme CM1 Panel 1 Auto warning telltale installed during pillar split 2 3 5 6 7 8 9 10 11 12 13 14
  • 35. 16154 Breaker lines installed for 3 rows before extraction commences6 Extraction sequence Breaker lines installed during pillar split Remote Reading Telltale (3 2 x 2.4m SG bolts (breaker Pillar stress cells (5m + 10m Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10 BARRIERPILLAR Proposed Monitoring Scheme CM1 Panel 1 Auto warning telltale installed during pillar split 2 3 5 6 7 8 9 10 11 12 13 14
  • 36. 16154 Breaker lines installed for 3 rows before extraction commences6 Extraction sequence Breaker lines installed during pillar split Remote Reading Telltale (3 2 x 2.4m SG bolts (breaker Pillar stress cells (5m + 10m Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10 BARRIERPILLAR Proposed Monitoring Scheme CM1 Panel 1 Auto warning telltale installed during pillar split 2 3 5 6 7 8 9 10 11 12 13 14 17 18
  • 37. 16154 Breaker lines installed for 3 rows before extraction commences6 Extraction sequence Breaker lines installed during pillar split Remote Reading Telltale (3 2 x 2.4m SG bolts (breaker Pillar stress cells (5m + 10m Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10 BARRIERPILLAR Proposed Monitoring Scheme CM1 Panel 1 Auto warning telltale installed during pillar split 2 3 5 6 7 8 9 10 11 12 13 14 17 18 19 20
  • 38. 16154 Breaker lines installed for 3 rows before extraction commences6 Extraction sequence Breaker lines installed during pillar split Remote Reading Telltale (3 2 x 2.4m SG bolts (breaker Pillar stress cells (5m + 10m Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10 BARRIERPILLAR Proposed Monitoring Scheme CM1 Panel 1 Auto warning telltale installed during pillar split 2 3 5 6 7 8 9 10 11 12 13 14 17 18 19 20 21 22
  • 39. 16154 Breaker lines installed for 3 rows before extraction commences6 Extraction sequence Breaker lines installed during pillar split Remote Reading Telltale (3 2 x 2.4m SG bolts (breaker Pillar stress cells (5m + 10m Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10 BARRIERPILLAR Proposed Monitoring Scheme CM1 Panel 1 Auto warning telltale installed during pillar split 2 3 5 6 7 8 9 10 11 12 13 14 17 18 19 20 21 22 23 24
  • 40. 16154 Breaker lines installed for 3 rows before extraction commences6 Extraction sequence Breaker lines installed during pillar split Remote Reading Telltale (3 2 x 2.4m SG bolts (breaker Pillar stress cells (5m + 10m Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10 BARRIERPILLAR Proposed Monitoring Scheme CM1 Panel 1 Auto warning telltale installed during pillar split 2 3 5 6 7 8 9 10 11 12 13 14 17 18 19 20 21 22 23 24 25 27 26 28
  • 41. 16154 Breaker lines installed for 3 rows before extraction commences6 Extraction sequence Breaker lines installed during pillar split Remote Reading Telltale (3 2 x 2.4m SG bolts (breaker Pillar stress cells (5m + 10m Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10 BARRIERPILLAR Proposed Monitoring Scheme CM1 Panel 1 Auto warning telltale installed during pillar split 2 3 5 6 7 8 9 10 11 12 13 14 17 18 19 20 21 22 23 24 25 27 26 28 29 30 31 32
  • 42. 16154 Breaker lines installed for 3 rows before extraction commences6 Extraction sequence Breaker lines installed during pillar split Remote Reading Telltale (3m + 10m) 2 x 2.4m SG bolts (breaker line) Pillar stress cells (5m + 10m) Auto warning telltale (single height 10m – trigger 5mm) Remote Rib Exto. (3m + 10m) BARRIERPILLAR Proposed Monitoring Scheme CM1 Panel 1 Auto warning telltale installed during pillar split 2 3 5 6 7 8 9 10 11 12 13 14 17 18 19 20 21 22 23 24 25 27 26 28 30 29 32 31 33 34 35 36
  • 43. OLD BEN METHOD – PANEL AND PILLAR EXTRACTION •Developing multiple headings, usually three, to the limits of the area to be extracted. •These panels, along with newly formed pillars (in the virgin coal) were extracted in retreat. •Here, the secondary development consisted of three roads, leaving reserves for pillar extraction on either side. •The total panel width was greater than 200 m. •Tertiary development, consisting of three roads, was done towards the end of the panel to increase overall extraction. •From this development, short fenders were then developed and extracted.
  • 44. OLD BEN METHOD – PANEL AND PILLAR EXTRACTION
  • 45. OLD BEN METHOD – PANEL AND PILLAR EXTRACTION
  • 46. WONGAWILLI METHOD  The Wongawilli system was developed at Wongawilli Colliery in the southern coalfield of New South Wales in the early 1960s.  Generally with the Wongawilli system, a panel is created by a secondary development consisting of three to five roads and leaving a continuous pillar of coal between the development and the previously caved area.  The pillar is normally between 50 m and 150 m wide and is extracted by developing and extracting 7 m wide ribs in a modified split and lift system.  The pillars formed by the development are extracted as the rib extraction retreats. As a result of the length of the rib pillars, this method resembles a shortwall face.
  • 47. WONGAWILLI METHOD  This method was developed to provide a single working place to extract coal in a stress-relieved area and to utilize the coal seam as support during extraction.  An overall extraction of 90 per cent was achieved by this system.
  • 48. WONGAWILLI METHOD  The main disadvantages of the Wongawilli system area:  ➤ Excessive floor lift when splitting successive headings in a large panel  ➤ Difficulties when removing stooks on the return run out of each heading  ➤ Difficulties with ventilating rib pillar panels when the roof caves completely, thus filling voids in the goaf area and choking the ventilation flow.
  • 49.  1. Provision of a single working place 2. Extraction of coal in stress relieved areas 3. Maximise extraction of the seam, 4. Simple system readily understood by all employees.  The method provides; a) A straight goaf line b) Simple ventilation system, with air being coursed via the goaf, and c) Working within de-stressed areas. WONGAWILLI METHOD
  • 53. RIB PILLAR EXTRACTION METHOD – SYSTEMATIC CUTTING AND SUPPORT SEQUENCE
  • 54. RIB PILLAR EXTRACTION METHOD – SYSTEMATIC CUTTING AND SUPPORT SEQUENCE
  • 55. RIB PILLAR EXTRACTION METHOD  Panel Layout and Cutting Sequence  The area allocated to rib-pillar mining is divided into workable sections, and the primary development normally consists of four roadways from the main development to the limit of the remnant. The two outer roads are utilized as return airways, and the two inner road travelling and conveyor-belt roads. The inner roads also serve as intake airways  The secondary development consists of three roads, two being intake airways and one a return airway.  Cross conveyor installations are used to ensure that the tramming distance for shuttle cars is minimized.