SlideShare a Scribd company logo
1 of 15
Download to read offline
10/16/2010




                               Material Requirements                                                                         Outline
  14                          Planning (MRP) and ERP                                      Global Company Profile: Wheeled
                                                                                          Coach
                                                                                          Dependent Demand
                                                                                          Dependent Inventory Model
       PowerPoint presentation to accompany                                               Requirements
       Heizer and Render
       Operations Management, 10e                                                                   Master Production Schedule
       Principles of Operations Management, 8e
                                                                                                    Bills of Material
       PowerPoint slides by Jeff Heyl
                                                                                                    Accurate Inventory Records
                                                                                                    Purchase Orders Outstanding
                                                                                                    Lead Times for Components
© 2011 Pearson Education, Inc. publishing as Prentice Hall    14 - 1   © 2011 Pearson Education, Inc. publishing as Prentice Hall        14 - 2




                          Outline – Continued                                                    Outline – Continued

                   MRP Structure                                                         Extensions of MRP
                                                                                                     Material Requirements Planning II
                   MRP Management                                                                    (MRP II)
                              MRP Dynamics                                                           Closed-Loop
                                                                                                     Closed Loop MRP
                              MRP and JIT                                                            Capacity Planning
                   Lot-Sizing Techniques                                                 MRP In Services
                                                                                                     Distribution Resource Planning
                                                                                                     (DRP)

© 2011 Pearson Education, Inc. publishing as Prentice Hall    14 - 3   © 2011 Pearson Education, Inc. publishing as Prentice Hall        14 - 4




                          Outline – Continued                                                    Learning Objectives
                                                                              When you complete this chapter you
                  Enterprise Resource Planning (ERP)
                                                                              should be able to:
                            Advantages and Disadvantages of
                            ERP Systems
                                                                                          1. Develop a product structure
                            ERP in the Service Sector
                                                                                          2. Build a gross requirements plan
                                                                                          3. Build a net requirements plan
                                                                                          4. Determine lot sizes for lot-for-lot,
                                                                                             EOQ, and PPB


© 2011 Pearson Education, Inc. publishing as Prentice Hall    14 - 5   © 2011 Pearson Education, Inc. publishing as Prentice Hall        14 - 6




                                                                                                                                                  1
10/16/2010




                          Learning Objectives                                                                  Wheeled Coach
       When you complete this chapter you
       should be able to:                                                                          Largest manufacturer of
                                                                                                   ambulances in the world
                        5. Describe MRP II                                                                          p
                                                                                                   International competitor
                        6. Describe closed-loop MRP                                                12 major ambulance designs
                        7. Describe ERP                                                                       18,000 different inventory items
                                                                                                              6,000 manufactured parts
                                                                                                              12,000 purchased parts

© 2011 Pearson Education, Inc. publishing as Prentice Hall       14 - 7    © 2011 Pearson Education, Inc. publishing as Prentice Hall            14 - 8




                                    Wheeled Coach                                                     Dependent Demand

                 Four Key Tasks
                                                                                       For any product for which a schedule
                           Material plan must meet both the                               can be established, dependent
                           requirements of the master schedule
                             q                                                          demand techniques should be used
                           and the capabilities of the
                           production facility
                           Plan must be executed as designed
                           Minimize inventory investment
                           Maintain excellent record integrity

© 2011 Pearson Education, Inc. publishing as Prentice Hall       14 - 9    © 2011 Pearson Education, Inc. publishing as Prentice Hall            14 - 10




                           Dependent Demand                                                           Dependent Demand
                                                                                             The demand for one item is related
          Benefits of MRP
                                                                                             to the demand for another item
          1. Better response to customer
                                                                                             Given a quantity for the end item,
             orders
                                                                                             the demand for all parts and
          2. Faster response to market changes                                               components can be calculated
          3. Improved utilization of facilities                                              In general, used whenever a
             and labor                                                                       schedule can be established for an
          4. Reduced inventory levels                                                        item
                                                                                             MRP is the common technique
© 2011 Pearson Education, Inc. publishing as Prentice Hall       14 - 11   © 2011 Pearson Education, Inc. publishing as Prentice Hall            14 - 12




                                                                                                                                                           2
10/16/2010




                           Dependent Demand                                                                                     Master Production Schedule
                                                                                                                                          (MPS)
          Effective use of dependent demand                                                                                         Specifies what is to be made and when
          inventory models requires the                                                                                             Must be in accordance with the aggregate
          following                                                                                                                 production plan
                       1. Master
                       1 M t production schedule
                                 d ti     h d l                                                                                     Inputs from financial plans customer
                                                                                                                                                          plans,
                                                                                                                                    demand, engineering, supplier performance
                       2. Specifications or bill of material
                                                                                                                                    As the process moves from planning to
                       3. Inventory availability                                                                                    execution, each step must be tested for
                       4. Purchase orders outstanding                                                                               feasibility
                       5. Lead times                                                                                                The MPS is the result of the production
                                                                                                                                    planning process
© 2011 Pearson Education, Inc. publishing as Prentice Hall                                                    14 - 13   © 2011 Pearson Education, Inc. publishing as Prentice Hall                                                       14 - 14




        Master Production Schedule                                                                                                            The Planning Process
                  (MPS)
                                                                                                                                           Production                            Marketing                Finance
                                                                                                                                            Capacity                              Customer                 Cash flow
                MPS is established in terms of specific                                                                                     Inventory                             demand

                products
                                                                                                                                           Procurement                                                    Human resources
                Schedule must be followed for a                                                                                             Supplier
                                                                                                                                            performance
                                                                                                                                                                                                           Manpower
                                                                                                                                                                                                           planning
                reasonable length of time
                The MPS is quite often fixed or frozen in                                                                                  Management
                                                                                                                                                                                     Aggregate
                                                                                                                                                                                                          Engineering
                                                                                                                                            Return on                                                      Design
                the near term part of the plan                                                                                              investment
                                                                                                                                            Capital
                                                                                                                                                                                     production
                                                                                                                                                                                        plan
                                                                                                                                                                                                           completion


                The MPS is a rolling schedule                                                                                                                                                                   Change
                                                                                                                                                                                                               production
                The MPS is a statement of what is to be                                                                                                                          Master production
                                                                                                                                                                                     schedule
                                                                                                                                                                                                                 plan?

                produced, not a forecast of demand
                                                                                                                                                                                                                       Figure 14.1
© 2011 Pearson Education, Inc. publishing as Prentice Hall                                                    14 - 15   © 2011 Pearson Education, Inc. publishing as Prentice Hall                                                       14 - 16




                      The Planning Process                                                                                                                 Aggregate
                                                         Master production
                                                                                                                                                         Production Plan
                                                             schedule                          Change
                                                                                                master
                                Change                                                        production                    Months                                                           January                 February
                             requirements?                    Material                        schedule?
                                                         requirements plan
                                                                                                                            Aggregate Production Plan                                         1,500                   1,200
                                                                                                                            (Shows the total
                                 Change                                                                                     quantity of amplifiers)
                                capacity?                    Capacity
                                                                p   y
                                                         requirements plan                                                  Weeks                                                      1     2       3   4     5       6     7       8
                                                                                                                            Master Production Schedule
                                                  No                            Is capacity   Is execution                  (Shows the specific type and
                                                                Realistic?      plan being    meeting the                   quantity of amplifier to be
                                                                                   met?           plan?
                                                                Yes                                                         produced
                                                             Execute capacity                                               240-watt amplifier                                       100           100         100          100
                                                                  plans
                                                                                                                            150-watt amplifier                                               500         500         450          450
                                                                                                                            75-watt amplifier                                                      300                      100
                                                                Execute
                                                              material plans

                                                                                                                                                                                                                           Figure 14.2
                                                                                                Figure 14.1
© 2011 Pearson Education, Inc. publishing as Prentice Hall                                                    14 - 17   © 2011 Pearson Education, Inc. publishing as Prentice Hall                                                       14 - 18




                                                                                                                                                                                                                                                   3
10/16/2010




        Master Production Schedule                                                                                                              Focus for Different
                  (MPS)                                                                                                                         Process Strategies
                                                                                                                                                                  Make to Order       Assemble to Order      Stock to Forecast
                                                                                                                                                                                         or Forecast
        Can be expressed in any of the                                                                                                                          (Process Focus)          (Repetitive)        (Product Focus)
                                                                                                                           Number of
        following terms:                                                                                                    inputs

                                                                                                                                                                  Schedule orders
           1.
           1 A customer order in a job shop (make-
                                                                                                                         Typical focus of the
              to-order) company                                                                                          master production                                             Schedule modules
                                                                                                                              schedule
           2. Modules in a repetitive (assemble-to-
              order or forecast) company                                                                                   Number of
                                                                                                                           end items                                                                          Schedule finished
                                                                                                                                                                                                                  product
           3. An end item in a continuous (stock-to-
                                                                                                                                                  Examples:        Print shop             Motorcycles        Steel, Beer, Bread
              forecast) company                                                                                                                                  Machine shop              Autos, TVs           Lightbulbs
                                                                                                                                                             Fine-dining restaurant   Fast-food restaurant          Paper
                                                                                                                     Figure 14.3
© 2011 Pearson Education, Inc. publishing as Prentice Hall                                                14 - 19   © 2011 Pearson Education, Inc. publishing as Prentice Hall                                                    14 - 20




                                     MPS Examples                                                                                                       Bills of Material
       For Nancy’s Specialty Foods                                                                                                    List of components, ingredients,
                                                                                                                                      and materials needed to make
                                Gross Requirements for Crabmeat Quiche                                                                product
    Day                   6          7      8         9      10   11    12    13      14 and so on
    Amount               50               100        47      60        110    75                                                      Provides product structure
                                                                                                                                      P   id      d t t     t
                                 Gross Requirements for Spinach Quiche                                                                           Items above given level are called
    Day                  7   8   9                   10      11   12    13    14      15   16 and so on                                          parents
    Amount             100 200 150                                60    75           100
                                                                                                                                                 Items below given level are called
                                                                                             Table 14.1
                                                                                                                                                 children

© 2011 Pearson Education, Inc. publishing as Prentice Hall                                                14 - 21   © 2011 Pearson Education, Inc. publishing as Prentice Hall                                                    14 - 22




                                         BOM Example                                                                                                       BOM Example
Level                   Product structure for “Awesome” (A)                                                         Level                   Product structure for “Awesome” (A)
   0                                                    A                                                              0                                                    A

                                                                                                                                     Part B: 2 x number of As =            (2)(50) =Std. 12” Speaker kit w/
                                                                                                                                                                                                     100
   1             B(2) Std. 12” Speaker kit                                    C(3) Std. 12” Speaker kit w/
                                                                                   amp-booster                         1             B(2) Std. 12” 3 x number of As =
                                                                                                                                     Part C: Speaker kit                       C(3)
                                                                                                                                                                           (3)(50) =amp-booster 150
                                                                                                                                     Part D: 2 x number of Bs
                                                                                                                                                     + 2 x number of Fs = (2)(100) + (2)(300) = 800
   2                         E(2)                                      E(2)            F(2) Std. 12” Speaker           2                     E
                                                                                                                                     Part E:(2) 2 x number of Bs        E(2)           F(2) Std. 12” Speaker
                                                                                           booster assembly                                                                                 booster assembly
                                                                                                                                                     + 2 x number of Cs = (2)(100) + (2)(150) = 500
                                            Packing box and                                                                          Part F: 2 x Packing box and =
                                                                                                                                                       number of Cs        (2)(150) =                300
   3      D(2)                           installation kit of wire,            G(1)         D(2)                        3      D(2)                                             G(1)        D(2)
                                           bolts, and screws                                                                         Part G: 1installation kit ofFs =
                                                                                                                                                       number of wire,
                                                                                                                                                     xbolts, and screws    (1)(300) =                300


                                                                         Amp-booster                                                                                                       Amp-booster

              12” Speaker                                                                     12” Speaker                         12” Speaker                                                                    12” Speaker

© 2011 Pearson Education, Inc. publishing as Prentice Hall                                                14 - 23   © 2011 Pearson Education, Inc. publishing as Prentice Hall                                                    14 - 24




                                                                                                                                                                                                                                            4
10/16/2010




                                    Bills of Material                                                               Bills of Material
                                                                                                    Planning Bills
                  Modular Bills
                                                                                                             Also called “pseudo” or super bills
                             Modules are not final products but
                             components that can be assembled                                                Created to assign an artificial
                             into
                             i t multiple end items
                                   lti l    d it                                                             parent to the BOM
                             Can significantly simplify planning                                             Used to group subassemblies to
                             and scheduling                                                                  reduce the number of items planned
                                                                                                             and scheduled
                                                                                                             Used to create standard “kits” for
                                                                                                             production

© 2011 Pearson Education, Inc. publishing as Prentice Hall            14 - 25   © 2011 Pearson Education, Inc. publishing as Prentice Hall                                                               14 - 26




                                    Bills of Material                                                            Accurate Records
                 Phantom Bills                                                                      Accurate inventory records are
                           Describe subassemblies that exist                                        absolutely required for MRP (or
                           only temporarily                                                         any dependent demand system) to
                           Are part of another assembly and                                         operate correctly
                                                                                                     p              y
                           never go into inventory                                                  Generally MRP systems require
                 Low-Level Coding                                                                   more than 99% accuracy
                           Item is coded at the lowest level at                                     Outstanding purchase orders must
                           which it occurs                                                          accurately reflect quantities and
                           BOMs are processed one level at a time                                   scheduled receipts
© 2011 Pearson Education, Inc. publishing as Prentice Hall            14 - 27   © 2011 Pearson Education, Inc. publishing as Prentice Hall                                                               14 - 28




                                                                                                       Time-
                                                                                                       Time-Phased Product
                                            Lead Times                                                       Structure
                                                                                                                                                           Must have D and E
                                                                                                   Start production of D                                   completed here so
                     The time required to purchase,                                                                                                         production can
                                                                                                                                                              begin on B
                     produce, or assemble an item                                                                                            1 week
                                                                                                                                                               2 weeks to
                                                                                                                                                           D    produce
                               For production – the sum of the                                                                                                                      B
                                                                                                                                    2 weeks
                               order, wait, move, setup, store,
                               order wait move setup store                                                                                                 E
                               and run times                                                                                                                                             A
                                                                                                                                                 2 weeks                            1 week
                               For purchased items – the time                                          2 weeks
                                                                                                                                                                       E
                                                                                                                                                                       1 week
                               between the recognition of a need                                                               G                                                    C
                                                                                                                                             3 weeks
                               and the availability of the item for                                                                                                    F
                                                                                                                 1 week
                               production                                                                                      D
                                                                                               |             |             |             |             |           |            |            |
                                                                                              1             2             3            4       5                  6             7            8   Figure 14.4
                                                                                                                                     Time in weeks
© 2011 Pearson Education, Inc. publishing as Prentice Hall            14 - 29   © 2011 Pearson Education, Inc. publishing as Prentice Hall                                                               14 - 30




                                                                                                                                                                                                                   5
10/16/2010




                                      MRP Structure                                                                                                         Determining Gross
                      Data Files                                                     Output Reports
                                                                                                                                                              Requirements
                                                                                           MRP by
                         BOM                                 Master                      period report
                                                       production schedule                                                                     Starts with a production schedule for the
                                                                                            MRP by
                                                                                           date report
                                                                                                                                               end item – 50 units of Item A in week 8
                     Lead times
                                                                                                                                               Using the lead time for the item,
                                                                                                                                                    g                          ,
                   (Item master file)                                                    Planned order
                                                                                             report                                            determine the week in which the order
                   Inventory data
                                                                                                                                               should be released – a 1 week lead time
                                                                                         Purchase advice
                                                                 Material
                                                              requirement
                                                                                                                                               means the order for 50 units should be
                                                                planning
                                                               programs
                                                                                                                                               released in week 7
                                                             (computer and          Exception reports
                 Purchasing data                                software)
                                                                                    Order early or late
                                                                                     or not needed
                                                                                                                                               This step is often called “lead time
                                                                                    Order quantity too                                         offset” or “time phasing”
                                                                                    small or too large
  Figure 14.5
© 2011 Pearson Education, Inc. publishing as Prentice Hall                                                            14 - 31   © 2011 Pearson Education, Inc. publishing as Prentice Hall   14 - 32




                            Determining Gross                                                                                                               Determining Gross
                              Requirements                                                                                                                    Requirements
               From the BOM, every Item A requires 2                                                                                           The process continues through the entire
               Item Bs – 100 Item Bs are required in                                                                                           BOM one level at a time – often called
               week 7 to satisfy the order release for                                                                                         “explosion”
               Item A
                                                                                                                                               By processing the BOM by level, items
               The lead time for the Item B is 2 weeks –                                                                                       with multiple parents are only processed
               release an order for 100 units of Item B in                                                                                     once, saving time and resources and
               week 5                                                                                                                          reducing confusion
               The timing and quantity for component                                                                                           Low-level coding ensures that each item
               requirements are determined by the order                                                                                        appears at only one level in the BOM
               release of the parent(s)
© 2011 Pearson Education, Inc. publishing as Prentice Hall                                                            14 - 33   © 2011 Pearson Education, Inc. publishing as Prentice Hall   14 - 34




              Gross Requirements Plan                                                                                                               Net Requirements Plan
                                                                         Week
                                                  1          2     3     4   5       6        7          8 Lead Time
  A.      Required date                                                                             50
          Order release date                                                                 50             1 week
  B.      Required date                                                                    100
          Order release date                                                 100                            2 weeks
  C.      Required date                                                                    150
          Order release date                                                       150                      1 week
  E.      Required date                                                      200   300
          Order release date                                     200   300                                  2 weeks
  F.      Required date                                                            300
          Order release date                                     300                                        3 weeks
  D.      Required date                                          600         200
          Order release date                            600            200                                  1 week
  G.      Required date                                          300
          Order release date                   300                                                          2 weeks

                                                                                                         Table 14.3
© 2011 Pearson Education, Inc. publishing as Prentice Hall                                                            14 - 35   © 2011 Pearson Education, Inc. publishing as Prentice Hall   14 - 36




                                                                                                                                                                                                       6
10/16/2010




                    Net Requirements Plan                                                                                                                           Determining Net
                                                                                                                                                                     Requirements
                                                                                                                                                 Starts with a production schedule for the
                                                                                                                                                 end item – 50 units of Item A in week 8
                                                                                                                                                 Because there are 10 Item As on hand,
                                                                                                                                                 only 40 are actually required – (net
                                                                                                                                                 requirement) = (gross requirement - on-
                                                                                                                                                 hand inventory)
                                                                                                                                                 The planned order receipt for Item A in
                                                                                                                                                 week 8 is 40 units – 40 = 50 - 10


© 2011 Pearson Education, Inc. publishing as Prentice Hall                                                              14 - 37   © 2011 Pearson Education, Inc. publishing as Prentice Hall                        14 - 38




                                   Determining Net                                                                                                                  Determining Net
                                    Requirements                                                                                                                     Requirements
               Following the lead time offset procedure,                                                                                         A planned order receipt of 65 units in
               the planned order release for Item A is                                                                                           week 7 generates a planned order release
               now 40 units in week 7                                                                                                            of 65 units in week 5
               The gross requirement for Item B is now                                                                                           The on-hand inventory record for Item B
                                                                                                                                                      on hand
               80 units in week 7                                                                                                                is updated to reflect the use of the 15
               There are 15 units of Item B on hand, so                                                                                          items in inventory and shows no on-hand
               the net requirement is 65 units in week 7                                                                                         inventory in week 8
               A planned order receipt of 65 units in                                                                                            This is referred to as the Gross-to-Net
               week 7 generates a planned order release                                                                                          calculation and is the third basic function
               of 65 units in week 5                                                                                                             of the MRP process
© 2011 Pearson Education, Inc. publishing as Prentice Hall                                                              14 - 39   © 2011 Pearson Education, Inc. publishing as Prentice Hall                        14 - 40




                         Gross Requirements                                                                                                           Net Requirements Plan
                              Schedule
        Figure 14.6
                                            A                                     S                                                       The logic of net requirements
                                 B                        C              B                    C
                                                                                                   Master schedule                             Gross
                                                                                                                                                           Allocations
                                                                                                                                            requirements +
                                  Lead time = 4 for A                    Lead time = 6 for S            for B
                                 Master schedule for A                  Master schedule for S       sold directly

        Periods              5     6    7    8       9 10 11            8    9 10 11 12 13            1   2   3
                                  40        50                15             40     20        30      10 10                                            Total requirements

                                                                                                                                                                              On   Scheduled              Net
                                                                                                                                                                    –        hand + receipts       = requirements

                Periods                          1    2       3    4    5     6    7      8
                                                                                                   Therefore, these
          Gross requirements: B              10      40+10
                                                     =50
                                                              40   50   20        15+30
                                                                                  =45
                                                                                                   are the gross                                                             Available inventory
                                                                                                   requirements for B

© 2011 Pearson Education, Inc. publishing as Prentice Hall                                                              14 - 41   © 2011 Pearson Education, Inc. publishing as Prentice Hall                        14 - 42




                                                                                                                                                                                                                              7
10/16/2010




                         MRP Planning Sheet                                                                               Safety Stock
                                                                                                BOMs, inventory records, purchase and
                                                                                                production quantities may not be perfect
                                                                                                Consideration of safety stock may be
                                                                                                p
                                                                                                prudent
                                                                                                Should be minimized and ultimately
                                                                                                eliminated
                                                                                                Typically built into projected on-hand
                                                                                                inventory
                                                             Figure 14.7




© 2011 Pearson Education, Inc. publishing as Prentice Hall            14 - 43   © 2011 Pearson Education, Inc. publishing as Prentice Hall   14 - 44




                              MRP Management                                                                              MRP and JIT
             MRP is a dynamic system
                                                                                                   MRP is a planning system that
             Facilitates replanning when changes occur
                                                                                                   does not do detailed scheduling
                        Regenerating
                        Net change
                                                                                                   MRP requires fixed lead times
                                                                                                   which might actually vary with
             System nervousness can result from too
             many changes
                                                                                                   batch size
             Time fences put limits on replanning                                                  JIT excels at rapidly moving small
                                                                                                   batches of material through the
             Pegging links each item to its parent
             allowing effective analysis of changes                                                system

© 2011 Pearson Education, Inc. publishing as Prentice Hall            14 - 45   © 2011 Pearson Education, Inc. publishing as Prentice Hall   14 - 46




           Finite Capacity Scheduling                                                             Small Bucket Approach
                                                                                          1. MRP “buckets” are reduced to daily or hourly
                    MRP systems do not consider
                    capacity during normal planning                                       2. Planned receipts are used internally to
                                                                                             sequence production
                    cycles
                                                                                          3. Inventory is moved through the plant on a JIT
                    Finite capacity scheduling (FCS)                                         basis
                    recognizes actual capacity limits                                     4. Completed products are moved to finished
                                                                                             goods inventory which reduces required
                    By merging MRP and FCS, a finite                                         quantities for subsequent planned orders
                    schedule is created with feasible                                     5. Back flushing based on the BOM is used to
                    capacities which facilitates rapid                                       deduct inventory that was used in production
                    material movement
© 2011 Pearson Education, Inc. publishing as Prentice Hall            14 - 47   © 2011 Pearson Education, Inc. publishing as Prentice Hall   14 - 48




                                                                                                                                                       8
10/16/2010




                                      Balanced Flow                                                                                                      Supermarket
                  Used in repetitive operations                                                                                   Items used by many products are
                  MRP plans are                                                                                                   held in a common area often called
                  executed using                                                                                                  a supermarket
                  JIT techniques                                                                                                  Items are withdrawn as needed
                  based on “pull”
                  principles                                                                                                      Inventory is maintained using JIT
                                                                                                                                  systems and procedures
                  Flows are carefully
                  balanced with                                                                                                   Common items are not planned by
                  small lot sizes                                                                                                 the MRP system

© 2011 Pearson Education, Inc. publishing as Prentice Hall                                           14 - 49   © 2011 Pearson Education, Inc. publishing as Prentice Hall                                           14 - 50




                     Lot-
                     Lot-Sizing Techniques                                                                                          Lot-
                                                                                                                                    Lot-Sizing Techniques
               Lot-for-lot techniques order just what
                                                                                                                              Part Period Balancing (PPB) looks at
               is required for production based on
                                                                                                                              future orders to determine most
               net requirements
                                                                                                                              economic lot size
                          May not always be feasible
                                                                                                                              The Wagner-Whitin algorithm is a
                          If setup costs are high, lot-for-lot can                                                            complex dynamic programming
                          be expensive
                                                                                                                              technique
               Economic order quantity (EOQ)                                                                                            Assumes a finite time horizon
                          EOQ expects a known constant                                                                                  Effective, but computationally
                          demand and MRP systems often deal                                                                             burdensome
                          with unknown and variable demand
© 2011 Pearson Education, Inc. publishing as Prentice Hall                                           14 - 51   © 2011 Pearson Education, Inc. publishing as Prentice Hall                                           14 - 52




                          Lot-for-
                          Lot-for-Lot Example                                                                                            Lot-for-
                                                                                                                                         Lot-for-Lot Example
                                                                                                                     No on-hand inventory is carried through the system
                                              1        2     3    4    5    6    7    8    9    10
                                                                                                                     Total holding cost = $0 3 4 5 6 7 8 9 10
                                                                                                                                      1   2
       Gross                                                                                                          Gross
       requirements
                                             35       30     40   0    10   40   30   0    30   55                   There are seven 35 30 for this 10 40 this plan
                                                                                                                      requirements    setups 40 0 item in 30 0 30                                              55

       Scheduled                                                                                                     Total ordering cost = 7 x $100 = $700
                                                                                                                      Scheduled
       receipts                                                                                                       receipts
       Projected on                                                                                                   Projected on
                                     35      35        0     0    0    0    0    0    0    0    0                                                   35      35        0     0    0    0    0    0    0    0    0
       hand                                                                                                           hand
       Net                                                                                                            Net
                                              0       30     40   0    10   40   30   0    30   55                                                           0       30     40   0    10   40   30   0    30   55
       requirements                                                                                                   requirements
       Planned order                                                                                                  Planned order
                                                      30     40        10   40   30        30   55                                                                   30     40        10   40   30        30   55
       receipts                                                                                                       receipts
       Planned order                                                                                                  Planned order
                                             30       40          10   40   30        30   55                                                               30       40          10   40   30        30   55
       releases                                                                                                       releases


       Holding cost = $1/week; Setup cost = $100; Lead time = 1 week                                                  Holding cost = $1/week; Setup cost = $100; Lead time = 1 week

© 2011 Pearson Education, Inc. publishing as Prentice Hall                                           14 - 53   © 2011 Pearson Education, Inc. publishing as Prentice Hall                                           14 - 54




                                                                                                                                                                                                                              9
10/16/2010




                    EOQ Lot Size Example                                                                                             EOQ Lot Size Example
                                                                                                                      Annual demand = 1,404
                                                                                                                      Total cost = setup cost + holding cost
                                              1        2     3    4     5     6    7    8    9    10
                                                                                                                      Total cost = (1,404/73) x $1004 + (73/2) x ($1 x852 weeks)
                                                                                                                                         1  2    3       5   6    7       9  10
       Gross
       requirements
                                             35       30     40   0    10    40    30   0    30   55                  Total cost = $3,798 30 40 0 10 40 30 0 30 55
                                                                                                                       Gross
                                                                                                                       requirements
                                                                                                                                        35
                                                                                                                      Cost for 10 weeks = $3,798 x (10 weeks/52 weeks) =
       Scheduled                                                                                                       Scheduled
       receipts                                                                                                          $730
                                                                                                                       receipts
       Projected on                                                                                                     Projected on
                                     35      35        0     43   3    3     66    26   69   69   39                                                  35      35        0         0    0     0    0     0    0   0     0
       hand                                                                                                             hand
       Net                                                                                                              Net
                                              0       30     0    0     7     0    4    0    0    16                                                           0       30         0    0     7    0     4    0   0     16
       requirements                                                                                                     requirements
       Planned order                                                                                                    Planned order
                                                      73               73          73             73                                                                   73                   73          73             73
       receipts                                                                                                         receipts
       Planned order                                                                                                    Planned order
                                             73                   73         73              73                                                               73                       73         73             73
       releases                                                                                                         releases


       Holding cost = $1/week; Setup cost = $100; Lead time = 1 week                                                     Holding cost = $1/week; Setup cost = $100; Lead time = 1 week
         Average weekly gross requirements = 27; EOQ = 73 units                                                            Average weekly gross requirements = 27; EOQ = 73 units
© 2011 Pearson Education, Inc. publishing as Prentice Hall                                             14 - 55   © 2011 Pearson Education, Inc. publishing as Prentice Hall                                                 14 - 56




                                        PPB Example                                                                       Periods                        PPB Example
                                                                                                                                                Trial Lot Size
                                                                                                                                              (cumulative net                                                  Costs
                                                                                                                         Combined              requirements)                      Part Periods          Setup Holding Total
                                                                                                                         2                              30                0
                                              1        2     3    4     5     6    7    8    9    10
                                                                                                                         2, 3                           70 1            2
                                                                                                                                                                          40 = 40 x41 5
                                                                                                                                                                              3               6         7    8   9     10
       Gross                                                                                                            2, 3, 4
                                                                                                                        Gross                           70                40
                                             35       30     40   0    10    40    30   0    30   55                                                       35          30    40    0    10   40         30   0   30    55
       requirements                                                                                                     requirements
                                                                                                                        2, 3, 4, 5                      80                70 = 40 x 1 + 10 x 3           100 + 70 = 170
       Scheduled                                                                                                        Scheduled 6
                                                                                                                        2, 3, 4, 5,                    120                230 = 40 x 1 + 10 x 3
       receipts                                                                                                         receipts                                                + 40 x 4
       Projected on                                                                                                     Projected on e periods
                                                                                                                             Co b
                                                                                                                             Combine pe ods                         2 - 5 as t s results in t e Part Period
                                                                                                                                                                             this esu ts the a t e od
                                     35                                                                                                 35
       hand                                                                                                             hand                                        closest to the EPP
       Net                                                                                                              6
                                                                                                                        Net                             40                    0
       requirements                                                                                                     requirements
                                                                                                                        6, 7                            70                    30 = 30 x 1
       Planned order                                                                                                    6, 7, 8
                                                                                                                        Planned order                   70                    30 = 30 x 1 + 0 x 2
       receipts                                                                                                         receipts 9
                                                                                                                        6, 7, 8,                       100                    120 = 30 x 1 + 30 x 3      100 + 120 = 220
       Planned order                                                                                                    Planned order
                                                                                                                             Combine                periods 6 - 9 as this results in the Part Period
       releases                                                                                                         releases
                                                                                                                                                            closest to the EPP
                                                                                                                         10                              55                   0                          100 +   0    = 100
       Holding cost = $1/week; Setup cost = $100; Lead time = 1 week                                                                         Holding cost = $1/week; Setup cost = 300 + 190 = 490
                                                                                                                                                            Total cost            $100;
                             EPP = 100 units                                                                                                              EPP = 100 units
© 2011 Pearson Education, Inc. publishing as Prentice Hall                                             14 - 57   © 2011 Pearson Education, Inc. publishing as Prentice Hall                                                 14 - 58




                                        PPB Example                                                                                       Lot-
                                                                                                                                          Lot-Sizing Summary
                                              1        2     3    4     5     6    7    8    9    10
                                                                                                                         For these three examples
       Gross
                                             35       30     40   0    10    40    30   0    30   55
       requirements
       Scheduled
       receipts                                                                                                                                          Lot-for-lot                             $700
       Projected on
       hand
                                     35      35        0     50   10   10    0     60   30   30   0                                                      EOQ                                     $730
       Net
       requirements
                                              0       30     0    0     0    40    0    0    0    55                                                     PPB                                     $490
       Planned order
                                                      80                     100                  55
       receipts
       Planned order
                                             80                        100                   55
       releases


       Holding cost = $1/week; Setup cost = $100; Lead time = 1 week
                             EPP = 100 units
© 2011 Pearson Education, Inc. publishing as Prentice Hall                                             14 - 59   © 2011 Pearson Education, Inc. publishing as Prentice Hall                                                 14 - 60




                                                                                                                                                                                                                                      10
10/16/2010




                         Lot-
                         Lot-Sizing Summary                                                                                                             Lot-
                                                                                                                                                        Lot-Sizing Summary
               In theory, lot sizes should be recomputed                                                                                       Lot sizes can be modified to allow for
               whenever there is a lot size or order                                                                                           scrap, process constraints, and
               quantity change                                                                                                                 purchase lots
               In practice, this results in system                                                                                             Use lot-sizing with care as it can cause
               nervousness and instability                                                                                                     considerable distortion of requirements
               Lot-for-lot should                                                                                                              at lower levels of the BOM
               be used when                                                                                                                    When setup costs are significant and
               low-cost JIT can                                                                                                                demand is reasonably smooth, PPB,
               be achieved                                                                                                                     Wagner-Whitin, or EOQ should give
                                                                                                                                               reasonable results

© 2011 Pearson Education, Inc. publishing as Prentice Hall                                                           14 - 61   © 2011 Pearson Education, Inc. publishing as Prentice Hall                                                  14 - 62




                            Extensions of MRP                                                                                                      Material Requirements
                                                                                                                                                         Planning II
                 MRP II                                                                                                                       Requirement data can be enriched by
                 Closed-Loop MRP                                                                                                              other resources
                         MRP system provides input to the capacity                                                                            Generally called MRP II or Material
                         plan, MPS, and production planning process                                                                           Resource Planning
                 Capacity Planning                                                                                                            Outputs include
                         MRP system generates a load report which                                                                                       Scrap
                         details capacity requirements
                                                                                                                                                        Packaging waste
                         This is used to drive the capacity planning
                         process                                                                                                                        Carbon emissions
                         Changes pass back through the MRP system                                                                             Data used by purchasing, production
                         for rescheduling                                                                                                     scheduling, capacity planning, inventory
© 2011 Pearson Education, Inc. publishing as Prentice Hall                                                           14 - 63   © 2011 Pearson Education, Inc. publishing as Prentice Hall                                                  14 - 64




         Material Resource Planning
                                                                                                                                            Closed-
                                                                                                                                            Closed-Loop MRP System
                                                                                    Weeks
                                                             LT    5            6           7             8
          Computer                                           1                                            100                                                               Aggregate Production Plan

          Labor Hrs: .2 each                                                                                  20
                                                                                                                                  OK?
          Machine Hrs: .2 each                                                                                20                  NO               Priority Management                           Capacity Management
          Scrap: 1 ounce fiberglass each                                                                  6.25     lbs
          Payables: $0 each                                                                                   $0                               Develop Master Production                     Evaluate Resource Availability
                                                                                                                                                       Schedule                                       (Rough Cut)
          PC Board (1 each)                                  2                               100                                  OK?
                                                                                                                                  NO           OK? YES                                                                             Planning
          Labor Hrs: .15 each                                                                   15
          Machine Hrs: .1 each                                                                  10                                                   Prepare Materials                       Determine Capacity Availability
                                                                                                                                                     Requirements Pan
          Scrap: .5 ounces copper each                                                      3.125    lb
                                                                                                                                               OK? YES
          Payables: raw material at $5 each                                                 $500                                                                                                                                   Execution
          Processor (5 each)                                 4      500                                                                          Detailed Production                         Implement Input/Output Control        (in repetitive
                                                                                                                                                   Activity Control                                                                systems JIT
          Labor Hrs: .2 each                                        100                                                                     (Shop Scheduling/Dispatching)                                                          techniques
          Machine Hrs: .2 each                                      100                                                                                                                                                            are used)
          Scrap: .01 ounces of acid waste each                    0.3125   lb
          Payables: processors at $10 each                        $5,000
                                                                                                                                                                                                                               Figure 14.8
                                                                                                 Table 14.4
© 2011 Pearson Education, Inc. publishing as Prentice Hall                                                           14 - 65   © 2011 Pearson Education, Inc. publishing as Prentice Hall                                                  14 - 66




                                                                                                                                                                                                                                                     11
Heizer om10 ch14-mrp
Heizer om10 ch14-mrp
Heizer om10 ch14-mrp
Heizer om10 ch14-mrp

More Related Content

What's hot (20)

Heizer om10 ch04
Heizer om10 ch04Heizer om10 ch04
Heizer om10 ch04
 
Heizer om10 ch05-designh good and services
Heizer om10 ch05-designh good and servicesHeizer om10 ch05-designh good and services
Heizer om10 ch05-designh good and services
 
Heizer om10 ch07_s-capacity
Heizer om10 ch07_s-capacityHeizer om10 ch07_s-capacity
Heizer om10 ch07_s-capacity
 
Heizer om10 ch01
Heizer om10 ch01Heizer om10 ch01
Heizer om10 ch01
 
Heizer om10 ch11_s-outsourching
Heizer om10 ch11_s-outsourchingHeizer om10 ch11_s-outsourching
Heizer om10 ch11_s-outsourching
 
Heizer om10 ch10-work design
Heizer om10 ch10-work designHeizer om10 ch10-work design
Heizer om10 ch10-work design
 
Heizer om10 ch11-supply chain
Heizer om10 ch11-supply chainHeizer om10 ch11-supply chain
Heizer om10 ch11-supply chain
 
Heizer om10 ch08-location
Heizer om10 ch08-locationHeizer om10 ch08-location
Heizer om10 ch08-location
 
Heizer om10 ch17-maintenance and reliability
Heizer om10 ch17-maintenance and reliabilityHeizer om10 ch17-maintenance and reliability
Heizer om10 ch17-maintenance and reliability
 
Heizer om10 ch06-managing quality
Heizer om10 ch06-managing qualityHeizer om10 ch06-managing quality
Heizer om10 ch06-managing quality
 
Heizer 16
Heizer 16Heizer 16
Heizer 16
 
Heizer 10
Heizer 10Heizer 10
Heizer 10
 
Heizer 13
Heizer 13Heizer 13
Heizer 13
 
Heizer 17
Heizer 17Heizer 17
Heizer 17
 
Heizer supp 11
Heizer supp 11Heizer supp 11
Heizer supp 11
 
Heizer 01
Heizer 01Heizer 01
Heizer 01
 
Heizer 04
Heizer 04Heizer 04
Heizer 04
 
Heizer mod b
Heizer mod bHeizer mod b
Heizer mod b
 
Heizer 09
Heizer 09Heizer 09
Heizer 09
 
Heizer mod e
Heizer mod eHeizer mod e
Heizer mod e
 

Viewers also liked

241232978 solution-manual-om-ch-12
241232978 solution-manual-om-ch-12241232978 solution-manual-om-ch-12
241232978 solution-manual-om-ch-12Hashem Yahya Almahdi
 
Video Case 6 2
Video Case 6 2Video Case 6 2
Video Case 6 2Joanmaines
 
241232978 solution-manual-om-ch-12
241232978 solution-manual-om-ch-12241232978 solution-manual-om-ch-12
241232978 solution-manual-om-ch-12Hashem Yahya Almahdi
 
172385052 solution-manual-operation-management-ch-17-pdf
172385052 solution-manual-operation-management-ch-17-pdf172385052 solution-manual-operation-management-ch-17-pdf
172385052 solution-manual-operation-management-ch-17-pdfHashem Yahya Almahdi
 
241233316 solution-manual-of-chapter-8-om
241233316 solution-manual-of-chapter-8-om241233316 solution-manual-of-chapter-8-om
241233316 solution-manual-of-chapter-8-omHashem Yahya Almahdi
 
Material requirement planning presentation
Material requirement planning presentationMaterial requirement planning presentation
Material requirement planning presentationjhanakshah
 

Viewers also liked (7)

241232978 solution-manual-om-ch-12
241232978 solution-manual-om-ch-12241232978 solution-manual-om-ch-12
241232978 solution-manual-om-ch-12
 
Video Case 6 2
Video Case 6 2Video Case 6 2
Video Case 6 2
 
Heizer 14
Heizer 14Heizer 14
Heizer 14
 
241232978 solution-manual-om-ch-12
241232978 solution-manual-om-ch-12241232978 solution-manual-om-ch-12
241232978 solution-manual-om-ch-12
 
172385052 solution-manual-operation-management-ch-17-pdf
172385052 solution-manual-operation-management-ch-17-pdf172385052 solution-manual-operation-management-ch-17-pdf
172385052 solution-manual-operation-management-ch-17-pdf
 
241233316 solution-manual-of-chapter-8-om
241233316 solution-manual-of-chapter-8-om241233316 solution-manual-of-chapter-8-om
241233316 solution-manual-of-chapter-8-om
 
Material requirement planning presentation
Material requirement planning presentationMaterial requirement planning presentation
Material requirement planning presentation
 

Similar to Heizer om10 ch14-mrp

Microsoft EPM and Team Foundation Server [TFS]
Microsoft EPM and Team Foundation Server [TFS] Microsoft EPM and Team Foundation Server [TFS]
Microsoft EPM and Team Foundation Server [TFS] Jaiveer Singh
 
Work done at MARG in FY 2011-12
Work done at MARG in FY 2011-12Work done at MARG in FY 2011-12
Work done at MARG in FY 2011-12Amol Vidwans
 
SAP BI Solution
SAP BI SolutionSAP BI Solution
SAP BI Solutionjshah786
 
Seismi Case Study | Oracle Mining Event | Santiago de Chile | 15 March 2012
Seismi Case Study | Oracle Mining Event | Santiago de Chile | 15 March 2012Seismi Case Study | Oracle Mining Event | Santiago de Chile | 15 March 2012
Seismi Case Study | Oracle Mining Event | Santiago de Chile | 15 March 2012Seismi Limited
 
UKOUG 2012 Metadata Management for Oracle Hyperion EPM
UKOUG 2012 Metadata Management for Oracle Hyperion EPMUKOUG 2012 Metadata Management for Oracle Hyperion EPM
UKOUG 2012 Metadata Management for Oracle Hyperion EPMOrchestra Networks
 
Analysis Of Plans
Analysis Of PlansAnalysis Of Plans
Analysis Of Planspipmonck
 
Ruszkowski.james
Ruszkowski.jamesRuszkowski.james
Ruszkowski.jamesNASAPMC
 
Joint UNDP-UNESCAP Initiative: CapacityDevelopment of Local Governments in ...
Joint UNDP-UNESCAP Initiative:  CapacityDevelopment of Local Governments  in ...Joint UNDP-UNESCAP Initiative:  CapacityDevelopment of Local Governments  in ...
Joint UNDP-UNESCAP Initiative: CapacityDevelopment of Local Governments in ...Oswar Mungkasa
 
Mrpii manufacturing resource planning eresource
Mrpii manufacturing resource planning eresourceMrpii manufacturing resource planning eresource
Mrpii manufacturing resource planning eresourceEresource Erp
 
Laia.Oliver Cv
Laia.Oliver CvLaia.Oliver Cv
Laia.Oliver Cvlaiaoliver
 
Erpsapbusproc
ErpsapbusprocErpsapbusproc
Erpsapbusprocfmtzu21
 
La visione di Oracle per la Management Excellence e overview di Oracle Hyperi...
La visione di Oracle per la Management Excellence e overview di Oracle Hyperi...La visione di Oracle per la Management Excellence e overview di Oracle Hyperi...
La visione di Oracle per la Management Excellence e overview di Oracle Hyperi...antonella Buonagurio
 
Bill Stankiewicz Copy Scope 2010 Wilkinson Sword Company
Bill Stankiewicz Copy Scope 2010 Wilkinson Sword CompanyBill Stankiewicz Copy Scope 2010 Wilkinson Sword Company
Bill Stankiewicz Copy Scope 2010 Wilkinson Sword CompanyBillStankiewicz
 
1516-2016 Transition
1516-2016 Transition1516-2016 Transition
1516-2016 TransitionSabrina Chang
 
Sirris Digitale Fabriek IV - Informatiebrug tussen productieaansturing en het...
Sirris Digitale Fabriek IV - Informatiebrug tussen productieaansturing en het...Sirris Digitale Fabriek IV - Informatiebrug tussen productieaansturing en het...
Sirris Digitale Fabriek IV - Informatiebrug tussen productieaansturing en het...Sirris
 
Heizer om10 ch01 [operation and productivity]
Heizer om10 ch01 [operation and productivity]Heizer om10 ch01 [operation and productivity]
Heizer om10 ch01 [operation and productivity]ahmadsyafiqfaris
 

Similar to Heizer om10 ch14-mrp (20)

Microsoft EPM and Team Foundation Server [TFS]
Microsoft EPM and Team Foundation Server [TFS] Microsoft EPM and Team Foundation Server [TFS]
Microsoft EPM and Team Foundation Server [TFS]
 
Work done at MARG in FY 2011-12
Work done at MARG in FY 2011-12Work done at MARG in FY 2011-12
Work done at MARG in FY 2011-12
 
SAP BI Solution
SAP BI SolutionSAP BI Solution
SAP BI Solution
 
Seismi Case Study | Oracle Mining Event | Santiago de Chile | 15 March 2012
Seismi Case Study | Oracle Mining Event | Santiago de Chile | 15 March 2012Seismi Case Study | Oracle Mining Event | Santiago de Chile | 15 March 2012
Seismi Case Study | Oracle Mining Event | Santiago de Chile | 15 March 2012
 
UKOUG 2012 Metadata Management for Oracle Hyperion EPM
UKOUG 2012 Metadata Management for Oracle Hyperion EPMUKOUG 2012 Metadata Management for Oracle Hyperion EPM
UKOUG 2012 Metadata Management for Oracle Hyperion EPM
 
Analysis Of Plans
Analysis Of PlansAnalysis Of Plans
Analysis Of Plans
 
Ruszkowski.james
Ruszkowski.jamesRuszkowski.james
Ruszkowski.james
 
Joint UNDP-UNESCAP Initiative: CapacityDevelopment of Local Governments in ...
Joint UNDP-UNESCAP Initiative:  CapacityDevelopment of Local Governments  in ...Joint UNDP-UNESCAP Initiative:  CapacityDevelopment of Local Governments  in ...
Joint UNDP-UNESCAP Initiative: CapacityDevelopment of Local Governments in ...
 
Mrpii manufacturing resource planning eresource
Mrpii manufacturing resource planning eresourceMrpii manufacturing resource planning eresource
Mrpii manufacturing resource planning eresource
 
Laia.Oliver Cv
Laia.Oliver CvLaia.Oliver Cv
Laia.Oliver Cv
 
Erpsapbusproc
ErpsapbusprocErpsapbusproc
Erpsapbusproc
 
La visione di Oracle per la Management Excellence e overview di Oracle Hyperi...
La visione di Oracle per la Management Excellence e overview di Oracle Hyperi...La visione di Oracle per la Management Excellence e overview di Oracle Hyperi...
La visione di Oracle per la Management Excellence e overview di Oracle Hyperi...
 
Bill Stankiewicz Copy Scope 2010 Wilkinson Sword Company
Bill Stankiewicz Copy Scope 2010 Wilkinson Sword CompanyBill Stankiewicz Copy Scope 2010 Wilkinson Sword Company
Bill Stankiewicz Copy Scope 2010 Wilkinson Sword Company
 
1516-2016 Transition
1516-2016 Transition1516-2016 Transition
1516-2016 Transition
 
Bookgasco 06draft2
Bookgasco 06draft2Bookgasco 06draft2
Bookgasco 06draft2
 
Sirris Digitale Fabriek IV - Informatiebrug tussen productieaansturing en het...
Sirris Digitale Fabriek IV - Informatiebrug tussen productieaansturing en het...Sirris Digitale Fabriek IV - Informatiebrug tussen productieaansturing en het...
Sirris Digitale Fabriek IV - Informatiebrug tussen productieaansturing en het...
 
Heizer om10 ch01 [operation and productivity]
Heizer om10 ch01 [operation and productivity]Heizer om10 ch01 [operation and productivity]
Heizer om10 ch01 [operation and productivity]
 
Erp
ErpErp
Erp
 
Juha 1999 2013 -
Juha 1999 2013 -Juha 1999 2013 -
Juha 1999 2013 -
 
2008-2014 Math
2008-2014 Math 2008-2014 Math
2008-2014 Math
 

Heizer om10 ch14-mrp

  • 1. 10/16/2010 Material Requirements Outline 14 Planning (MRP) and ERP Global Company Profile: Wheeled Coach Dependent Demand Dependent Inventory Model PowerPoint presentation to accompany Requirements Heizer and Render Operations Management, 10e Master Production Schedule Principles of Operations Management, 8e Bills of Material PowerPoint slides by Jeff Heyl Accurate Inventory Records Purchase Orders Outstanding Lead Times for Components © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 1 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 2 Outline – Continued Outline – Continued MRP Structure Extensions of MRP Material Requirements Planning II MRP Management (MRP II) MRP Dynamics Closed-Loop Closed Loop MRP MRP and JIT Capacity Planning Lot-Sizing Techniques MRP In Services Distribution Resource Planning (DRP) © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 3 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 4 Outline – Continued Learning Objectives When you complete this chapter you Enterprise Resource Planning (ERP) should be able to: Advantages and Disadvantages of ERP Systems 1. Develop a product structure ERP in the Service Sector 2. Build a gross requirements plan 3. Build a net requirements plan 4. Determine lot sizes for lot-for-lot, EOQ, and PPB © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 5 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 6 1
  • 2. 10/16/2010 Learning Objectives Wheeled Coach When you complete this chapter you should be able to: Largest manufacturer of ambulances in the world 5. Describe MRP II p International competitor 6. Describe closed-loop MRP 12 major ambulance designs 7. Describe ERP 18,000 different inventory items 6,000 manufactured parts 12,000 purchased parts © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 7 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 8 Wheeled Coach Dependent Demand Four Key Tasks For any product for which a schedule Material plan must meet both the can be established, dependent requirements of the master schedule q demand techniques should be used and the capabilities of the production facility Plan must be executed as designed Minimize inventory investment Maintain excellent record integrity © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 9 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 10 Dependent Demand Dependent Demand The demand for one item is related Benefits of MRP to the demand for another item 1. Better response to customer Given a quantity for the end item, orders the demand for all parts and 2. Faster response to market changes components can be calculated 3. Improved utilization of facilities In general, used whenever a and labor schedule can be established for an 4. Reduced inventory levels item MRP is the common technique © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 11 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 12 2
  • 3. 10/16/2010 Dependent Demand Master Production Schedule (MPS) Effective use of dependent demand Specifies what is to be made and when inventory models requires the Must be in accordance with the aggregate following production plan 1. Master 1 M t production schedule d ti h d l Inputs from financial plans customer plans, demand, engineering, supplier performance 2. Specifications or bill of material As the process moves from planning to 3. Inventory availability execution, each step must be tested for 4. Purchase orders outstanding feasibility 5. Lead times The MPS is the result of the production planning process © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 13 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 14 Master Production Schedule The Planning Process (MPS) Production Marketing Finance Capacity Customer Cash flow MPS is established in terms of specific Inventory demand products Procurement Human resources Schedule must be followed for a Supplier performance Manpower planning reasonable length of time The MPS is quite often fixed or frozen in Management Aggregate Engineering Return on Design the near term part of the plan investment Capital production plan completion The MPS is a rolling schedule Change production The MPS is a statement of what is to be Master production schedule plan? produced, not a forecast of demand Figure 14.1 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 15 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 16 The Planning Process Aggregate Master production Production Plan schedule Change master Change production Months January February requirements? Material schedule? requirements plan Aggregate Production Plan 1,500 1,200 (Shows the total Change quantity of amplifiers) capacity? Capacity p y requirements plan Weeks 1 2 3 4 5 6 7 8 Master Production Schedule No Is capacity Is execution (Shows the specific type and Realistic? plan being meeting the quantity of amplifier to be met? plan? Yes produced Execute capacity 240-watt amplifier 100 100 100 100 plans 150-watt amplifier 500 500 450 450 75-watt amplifier 300 100 Execute material plans Figure 14.2 Figure 14.1 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 17 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 18 3
  • 4. 10/16/2010 Master Production Schedule Focus for Different (MPS) Process Strategies Make to Order Assemble to Order Stock to Forecast or Forecast Can be expressed in any of the (Process Focus) (Repetitive) (Product Focus) Number of following terms: inputs Schedule orders 1. 1 A customer order in a job shop (make- Typical focus of the to-order) company master production Schedule modules schedule 2. Modules in a repetitive (assemble-to- order or forecast) company Number of end items Schedule finished product 3. An end item in a continuous (stock-to- Examples: Print shop Motorcycles Steel, Beer, Bread forecast) company Machine shop Autos, TVs Lightbulbs Fine-dining restaurant Fast-food restaurant Paper Figure 14.3 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 19 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 20 MPS Examples Bills of Material For Nancy’s Specialty Foods List of components, ingredients, and materials needed to make Gross Requirements for Crabmeat Quiche product Day 6 7 8 9 10 11 12 13 14 and so on Amount 50 100 47 60 110 75 Provides product structure P id d t t t Gross Requirements for Spinach Quiche Items above given level are called Day 7 8 9 10 11 12 13 14 15 16 and so on parents Amount 100 200 150 60 75 100 Items below given level are called Table 14.1 children © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 21 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 22 BOM Example BOM Example Level Product structure for “Awesome” (A) Level Product structure for “Awesome” (A) 0 A 0 A Part B: 2 x number of As = (2)(50) =Std. 12” Speaker kit w/ 100 1 B(2) Std. 12” Speaker kit C(3) Std. 12” Speaker kit w/ amp-booster 1 B(2) Std. 12” 3 x number of As = Part C: Speaker kit C(3) (3)(50) =amp-booster 150 Part D: 2 x number of Bs + 2 x number of Fs = (2)(100) + (2)(300) = 800 2 E(2) E(2) F(2) Std. 12” Speaker 2 E Part E:(2) 2 x number of Bs E(2) F(2) Std. 12” Speaker booster assembly booster assembly + 2 x number of Cs = (2)(100) + (2)(150) = 500 Packing box and Part F: 2 x Packing box and = number of Cs (2)(150) = 300 3 D(2) installation kit of wire, G(1) D(2) 3 D(2) G(1) D(2) bolts, and screws Part G: 1installation kit ofFs = number of wire, xbolts, and screws (1)(300) = 300 Amp-booster Amp-booster 12” Speaker 12” Speaker 12” Speaker 12” Speaker © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 23 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 24 4
  • 5. 10/16/2010 Bills of Material Bills of Material Planning Bills Modular Bills Also called “pseudo” or super bills Modules are not final products but components that can be assembled Created to assign an artificial into i t multiple end items lti l d it parent to the BOM Can significantly simplify planning Used to group subassemblies to and scheduling reduce the number of items planned and scheduled Used to create standard “kits” for production © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 25 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 26 Bills of Material Accurate Records Phantom Bills Accurate inventory records are Describe subassemblies that exist absolutely required for MRP (or only temporarily any dependent demand system) to Are part of another assembly and operate correctly p y never go into inventory Generally MRP systems require Low-Level Coding more than 99% accuracy Item is coded at the lowest level at Outstanding purchase orders must which it occurs accurately reflect quantities and BOMs are processed one level at a time scheduled receipts © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 27 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 28 Time- Time-Phased Product Lead Times Structure Must have D and E Start production of D completed here so The time required to purchase, production can begin on B produce, or assemble an item 1 week 2 weeks to D produce For production – the sum of the B 2 weeks order, wait, move, setup, store, order wait move setup store E and run times A 2 weeks 1 week For purchased items – the time 2 weeks E 1 week between the recognition of a need G C 3 weeks and the availability of the item for F 1 week production D | | | | | | | | 1 2 3 4 5 6 7 8 Figure 14.4 Time in weeks © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 29 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 30 5
  • 6. 10/16/2010 MRP Structure Determining Gross Data Files Output Reports Requirements MRP by BOM Master period report production schedule Starts with a production schedule for the MRP by date report end item – 50 units of Item A in week 8 Lead times Using the lead time for the item, g , (Item master file) Planned order report determine the week in which the order Inventory data should be released – a 1 week lead time Purchase advice Material requirement means the order for 50 units should be planning programs released in week 7 (computer and Exception reports Purchasing data software) Order early or late or not needed This step is often called “lead time Order quantity too offset” or “time phasing” small or too large Figure 14.5 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 31 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 32 Determining Gross Determining Gross Requirements Requirements From the BOM, every Item A requires 2 The process continues through the entire Item Bs – 100 Item Bs are required in BOM one level at a time – often called week 7 to satisfy the order release for “explosion” Item A By processing the BOM by level, items The lead time for the Item B is 2 weeks – with multiple parents are only processed release an order for 100 units of Item B in once, saving time and resources and week 5 reducing confusion The timing and quantity for component Low-level coding ensures that each item requirements are determined by the order appears at only one level in the BOM release of the parent(s) © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 33 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 34 Gross Requirements Plan Net Requirements Plan Week 1 2 3 4 5 6 7 8 Lead Time A. Required date 50 Order release date 50 1 week B. Required date 100 Order release date 100 2 weeks C. Required date 150 Order release date 150 1 week E. Required date 200 300 Order release date 200 300 2 weeks F. Required date 300 Order release date 300 3 weeks D. Required date 600 200 Order release date 600 200 1 week G. Required date 300 Order release date 300 2 weeks Table 14.3 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 35 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 36 6
  • 7. 10/16/2010 Net Requirements Plan Determining Net Requirements Starts with a production schedule for the end item – 50 units of Item A in week 8 Because there are 10 Item As on hand, only 40 are actually required – (net requirement) = (gross requirement - on- hand inventory) The planned order receipt for Item A in week 8 is 40 units – 40 = 50 - 10 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 37 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 38 Determining Net Determining Net Requirements Requirements Following the lead time offset procedure, A planned order receipt of 65 units in the planned order release for Item A is week 7 generates a planned order release now 40 units in week 7 of 65 units in week 5 The gross requirement for Item B is now The on-hand inventory record for Item B on hand 80 units in week 7 is updated to reflect the use of the 15 There are 15 units of Item B on hand, so items in inventory and shows no on-hand the net requirement is 65 units in week 7 inventory in week 8 A planned order receipt of 65 units in This is referred to as the Gross-to-Net week 7 generates a planned order release calculation and is the third basic function of 65 units in week 5 of the MRP process © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 39 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 40 Gross Requirements Net Requirements Plan Schedule Figure 14.6 A S The logic of net requirements B C B C Master schedule Gross Allocations requirements + Lead time = 4 for A Lead time = 6 for S for B Master schedule for A Master schedule for S sold directly Periods 5 6 7 8 9 10 11 8 9 10 11 12 13 1 2 3 40 50 15 40 20 30 10 10 Total requirements On Scheduled Net – hand + receipts = requirements Periods 1 2 3 4 5 6 7 8 Therefore, these Gross requirements: B 10 40+10 =50 40 50 20 15+30 =45 are the gross Available inventory requirements for B © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 41 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 42 7
  • 8. 10/16/2010 MRP Planning Sheet Safety Stock BOMs, inventory records, purchase and production quantities may not be perfect Consideration of safety stock may be p prudent Should be minimized and ultimately eliminated Typically built into projected on-hand inventory Figure 14.7 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 43 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 44 MRP Management MRP and JIT MRP is a dynamic system MRP is a planning system that Facilitates replanning when changes occur does not do detailed scheduling Regenerating Net change MRP requires fixed lead times which might actually vary with System nervousness can result from too many changes batch size Time fences put limits on replanning JIT excels at rapidly moving small batches of material through the Pegging links each item to its parent allowing effective analysis of changes system © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 45 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 46 Finite Capacity Scheduling Small Bucket Approach 1. MRP “buckets” are reduced to daily or hourly MRP systems do not consider capacity during normal planning 2. Planned receipts are used internally to sequence production cycles 3. Inventory is moved through the plant on a JIT Finite capacity scheduling (FCS) basis recognizes actual capacity limits 4. Completed products are moved to finished goods inventory which reduces required By merging MRP and FCS, a finite quantities for subsequent planned orders schedule is created with feasible 5. Back flushing based on the BOM is used to capacities which facilitates rapid deduct inventory that was used in production material movement © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 47 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 48 8
  • 9. 10/16/2010 Balanced Flow Supermarket Used in repetitive operations Items used by many products are MRP plans are held in a common area often called executed using a supermarket JIT techniques Items are withdrawn as needed based on “pull” principles Inventory is maintained using JIT systems and procedures Flows are carefully balanced with Common items are not planned by small lot sizes the MRP system © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 49 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 50 Lot- Lot-Sizing Techniques Lot- Lot-Sizing Techniques Lot-for-lot techniques order just what Part Period Balancing (PPB) looks at is required for production based on future orders to determine most net requirements economic lot size May not always be feasible The Wagner-Whitin algorithm is a If setup costs are high, lot-for-lot can complex dynamic programming be expensive technique Economic order quantity (EOQ) Assumes a finite time horizon EOQ expects a known constant Effective, but computationally demand and MRP systems often deal burdensome with unknown and variable demand © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 51 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 52 Lot-for- Lot-for-Lot Example Lot-for- Lot-for-Lot Example No on-hand inventory is carried through the system 1 2 3 4 5 6 7 8 9 10 Total holding cost = $0 3 4 5 6 7 8 9 10 1 2 Gross Gross requirements 35 30 40 0 10 40 30 0 30 55 There are seven 35 30 for this 10 40 this plan requirements setups 40 0 item in 30 0 30 55 Scheduled Total ordering cost = 7 x $100 = $700 Scheduled receipts receipts Projected on Projected on 35 35 0 0 0 0 0 0 0 0 0 35 35 0 0 0 0 0 0 0 0 0 hand hand Net Net 0 30 40 0 10 40 30 0 30 55 0 30 40 0 10 40 30 0 30 55 requirements requirements Planned order Planned order 30 40 10 40 30 30 55 30 40 10 40 30 30 55 receipts receipts Planned order Planned order 30 40 10 40 30 30 55 30 40 10 40 30 30 55 releases releases Holding cost = $1/week; Setup cost = $100; Lead time = 1 week Holding cost = $1/week; Setup cost = $100; Lead time = 1 week © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 53 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 54 9
  • 10. 10/16/2010 EOQ Lot Size Example EOQ Lot Size Example Annual demand = 1,404 Total cost = setup cost + holding cost 1 2 3 4 5 6 7 8 9 10 Total cost = (1,404/73) x $1004 + (73/2) x ($1 x852 weeks) 1 2 3 5 6 7 9 10 Gross requirements 35 30 40 0 10 40 30 0 30 55 Total cost = $3,798 30 40 0 10 40 30 0 30 55 Gross requirements 35 Cost for 10 weeks = $3,798 x (10 weeks/52 weeks) = Scheduled Scheduled receipts $730 receipts Projected on Projected on 35 35 0 43 3 3 66 26 69 69 39 35 35 0 0 0 0 0 0 0 0 0 hand hand Net Net 0 30 0 0 7 0 4 0 0 16 0 30 0 0 7 0 4 0 0 16 requirements requirements Planned order Planned order 73 73 73 73 73 73 73 73 receipts receipts Planned order Planned order 73 73 73 73 73 73 73 73 releases releases Holding cost = $1/week; Setup cost = $100; Lead time = 1 week Holding cost = $1/week; Setup cost = $100; Lead time = 1 week Average weekly gross requirements = 27; EOQ = 73 units Average weekly gross requirements = 27; EOQ = 73 units © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 55 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 56 PPB Example Periods PPB Example Trial Lot Size (cumulative net Costs Combined requirements) Part Periods Setup Holding Total 2 30 0 1 2 3 4 5 6 7 8 9 10 2, 3 70 1 2 40 = 40 x41 5 3 6 7 8 9 10 Gross 2, 3, 4 Gross 70 40 35 30 40 0 10 40 30 0 30 55 35 30 40 0 10 40 30 0 30 55 requirements requirements 2, 3, 4, 5 80 70 = 40 x 1 + 10 x 3 100 + 70 = 170 Scheduled Scheduled 6 2, 3, 4, 5, 120 230 = 40 x 1 + 10 x 3 receipts receipts + 40 x 4 Projected on Projected on e periods Co b Combine pe ods 2 - 5 as t s results in t e Part Period this esu ts the a t e od 35 35 hand hand closest to the EPP Net 6 Net 40 0 requirements requirements 6, 7 70 30 = 30 x 1 Planned order 6, 7, 8 Planned order 70 30 = 30 x 1 + 0 x 2 receipts receipts 9 6, 7, 8, 100 120 = 30 x 1 + 30 x 3 100 + 120 = 220 Planned order Planned order Combine periods 6 - 9 as this results in the Part Period releases releases closest to the EPP 10 55 0 100 + 0 = 100 Holding cost = $1/week; Setup cost = $100; Lead time = 1 week Holding cost = $1/week; Setup cost = 300 + 190 = 490 Total cost $100; EPP = 100 units EPP = 100 units © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 57 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 58 PPB Example Lot- Lot-Sizing Summary 1 2 3 4 5 6 7 8 9 10 For these three examples Gross 35 30 40 0 10 40 30 0 30 55 requirements Scheduled receipts Lot-for-lot $700 Projected on hand 35 35 0 50 10 10 0 60 30 30 0 EOQ $730 Net requirements 0 30 0 0 0 40 0 0 0 55 PPB $490 Planned order 80 100 55 receipts Planned order 80 100 55 releases Holding cost = $1/week; Setup cost = $100; Lead time = 1 week EPP = 100 units © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 59 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 60 10
  • 11. 10/16/2010 Lot- Lot-Sizing Summary Lot- Lot-Sizing Summary In theory, lot sizes should be recomputed Lot sizes can be modified to allow for whenever there is a lot size or order scrap, process constraints, and quantity change purchase lots In practice, this results in system Use lot-sizing with care as it can cause nervousness and instability considerable distortion of requirements Lot-for-lot should at lower levels of the BOM be used when When setup costs are significant and low-cost JIT can demand is reasonably smooth, PPB, be achieved Wagner-Whitin, or EOQ should give reasonable results © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 61 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 62 Extensions of MRP Material Requirements Planning II MRP II Requirement data can be enriched by Closed-Loop MRP other resources MRP system provides input to the capacity Generally called MRP II or Material plan, MPS, and production planning process Resource Planning Capacity Planning Outputs include MRP system generates a load report which Scrap details capacity requirements Packaging waste This is used to drive the capacity planning process Carbon emissions Changes pass back through the MRP system Data used by purchasing, production for rescheduling scheduling, capacity planning, inventory © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 63 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 64 Material Resource Planning Closed- Closed-Loop MRP System Weeks LT 5 6 7 8 Computer 1 100 Aggregate Production Plan Labor Hrs: .2 each 20 OK? Machine Hrs: .2 each 20 NO Priority Management Capacity Management Scrap: 1 ounce fiberglass each 6.25 lbs Payables: $0 each $0 Develop Master Production Evaluate Resource Availability Schedule (Rough Cut) PC Board (1 each) 2 100 OK? NO OK? YES Planning Labor Hrs: .15 each 15 Machine Hrs: .1 each 10 Prepare Materials Determine Capacity Availability Requirements Pan Scrap: .5 ounces copper each 3.125 lb OK? YES Payables: raw material at $5 each $500 Execution Processor (5 each) 4 500 Detailed Production Implement Input/Output Control (in repetitive Activity Control systems JIT Labor Hrs: .2 each 100 (Shop Scheduling/Dispatching) techniques Machine Hrs: .2 each 100 are used) Scrap: .01 ounces of acid waste each 0.3125 lb Payables: processors at $10 each $5,000 Figure 14.8 Table 14.4 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 65 © 2011 Pearson Education, Inc. publishing as Prentice Hall 14 - 66 11